 Graphing a P6 Resource S-Curve in Excel  In my previous tutorial in this series , I described the procedure to export resource assignment data rom P6 to Excel! "ost o us have #or$ed #ith Excel charts in our %ob or during our study in college or university! &hat #e all $no# is that they are really helpul #hen you #ant to demonstrate some analytical inormation #ithout technical terms! In this tutorial, I am going to tell you ho# to develop a resource S-curve in Excel #ith P6 data! Tutorial Files Excel Spreadsheet (Excel 2007+): P6'Scurve'Example!xlsx - 1.5M  Step 1 ! Export "ri#a$era "% &esource 'ssi#ets to Excel

Upload: katie-benson

Post on 05-Oct-2015

11 views

Category:

Documents


0 download

DESCRIPTION

Graphing a P6 Resource S

TRANSCRIPT

Graphing a P6 Resource S-Curve in Excel

In myprevious tutorial in this series, I described the procedure to export resource assignment data from P6 to Excel.Most of us have worked with Excel charts in our job or during our study in college or university. What we all know is that they are really helpful when you want to demonstrate some analytical information without technical terms. In this tutorial, I am going to tell you how to develop a resource S-curve in Excel with P6 data.Tutorial Files Excel Spreadsheet (Excel 2007+):P6_Scurve_Example.xlsx- 1.5MbStep 1 Export Primavera P6 Resource Assignmentsto Excel

Following the steps from our previous tutoril, you now have all the resources and assignments in an Excel sheet. You can modify the primary sheet for better graphical features.Step 2 How to Use the Data

To draw resource curves, what we need is the two highlighted rows which are the cumulative total and the incremental total. They have the information needed for each month. So we just copy and paste these two rows and the date row to another sheet to have more space doing our job.Step 3 Copy and paste the needed data in separate sheet

Copy the data to separate worksheet. Now we have all the tools to paint a perfect picture of our project resources. All we need is to use some formula to calculate the percentage progress for each month in our table.Step 4 Calculate theProgressPercentage

To calculate interval progress and cumulative progress, just divide the value for each month (man hour needed for each month) by the total value (the summation of all man hours). You can see the formula in the Excel file attached to this tutorial.Step 5 Graphing the S-Curves

To graph any curve we should go to Insert Section of Excel and then choose a chart type in charts tab. For this tutorial purpose well select theLine chart.Step 6 Defining the S-Curves Resources

Right-click on the curves that Excel generated by default, which is not the curve that we want, and choose Select Data.

Remove all the predefined sources and then hit theAddbutton.

In this box define all the sources one by one. We should do it 3 times to define all the sources for our final S-curve. I define all the series below:Series NameSeries ValuesFormula

Monthly Man HourThe row that shows interval man hour for each month=Sheet5!$C$3:$X$3

Cumulative ProgressThe row that shows cum. % prog=Sheet5!$C$4:$X$4

The last source definition is for the dates which result in our X axis. To do that on the select source data box and under the Horizontal Axis label, hit the edit button and you will see a similar dialogue box as the above dialogue boxes:

Select all the dates as the label range for the horizontal axis and hit OK on dialogue box and then on the select Data Source box. Now you have the following chart

Now we should modify this s-curve, so we go step by step:Step 7 Select a Primary and Secondary S-CurveRight-click on the curves and select Format Data Series. In the format Data series box select the Cum Progress as the secondary curve (it means that this s-curve values are shown on the right hand axis)

Step 8 Change the data type to a 2-D Column chartRight-click on the monthly interval man hour curve (ie:the blue curve) and then select the change series chart type. In the change series chart type box, select 2-D Column chart.

Step 9 Adjust the Right-hand Vertical AxisRight-click on the right-hand vertical axis and select Format Axis in the dialogue box go to Axis options and change the second value from the top of form to1.00.

Now you have a resource S-curve which still needs some modification:

Step 10 The Final TouchesIn Excel 2007, when you select a chart, a chart tool tab will appear on the top right hand side of toolbar. In that chart you can change the color of curves, add title to curve, add table to curve. The following curve which is the final curve is the result of doing some exercises with those features:

Wrap UpWith this new P6 Resource S-curve, now your project manager can easily tell you there is something wrong with resource assignment and some leveling should be done on resources to achieve a better distributed resource S-curve.There are different ways of developing S-curves in Excel but this method works well in many project circumstances.