gpe - autenticação · b dummy if you fail this notation in the exam you will have “0” in the...

33
GPE engineering project management Project Management in an Engineering Context

Upload: dinhmien

Post on 14-Mar-2019

213 views

Category:

Documents


0 download

TRANSCRIPT

GPE engineering project management

Project Management in an Engineering

Context

SOW CHARTER SCOPE DEFINITION

PM

WBS

circulation, negotiation, translation

WP à activities ----- estimation Time Cost

GANTT PERT AOA AON

Network  diagrams  in  context  

-­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐  planning,  resource  alloca7on,  cost  alloca7on,  control  -­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐-­‐  

WBS

Mainly  PMBOK  chapter  6  

Network  diagrams    

WBS  

PERT, what does it state

for? They are like WBS?

PERT  –  Program  Evalua/on  &  Review  Technique

WBS GANTT

PERT

Network  Analysis    (PERT  –  Program  Evalua/on  &  Review  Technique;    CPM  –  Cri/cal  Path  Method)    

Network  modula7on  approach  used   in  planning,   scheduling   and   controlling  projects.   Beyond   the   analysis  they   facilitate,   they   represent   a   common  ground   to  discuss  op7ons   so   they   are  excellent   communica7on  tools.  They  facilitate  thema7c  brain-­‐storming  analysis    

Network  diagrams  are  en7ty/rela7onship  models  (interrela7ons  among  instances  of  resources)  usually  used  in  project  planning,  namely  on  scheduling  and  7me  management    

Using  these  models    we  need  to  take  into  account:    

•   interrela7on  of  ac7vi7es  (sequencing  rela7ons)  and    •   rela7ons  among  ac7vi7es  and  resources  (alloca7on)      

 There  are  more  complex  models,  using  sta7s7cs  but  we  will  eventually  address  them  later  

Cri7cal  Path  Method  (CPM)  (determinis7c)    A  schedule  network  analysis   technique  used   to  determine   the  amount  of   scheduling  flexibility   (the  amount  of  float)  on  various  logical  network  paths  in  the  project  schedule  network,  and  to  determine  the  minimum  total  project  dura7on.  Early  dates  are  calculated  by  means  of  a  forward  pass,  using  a  specified  start  date.  Late  dates  are  calculated  by  means  of  a  backward  pass,  star7ng  from  a  specified  comple7on  date,  which  some7mes  is  the  project  early  finish  date  calculated  during  the  forward  pass  calcula7on.        Program  Evalua7on  and  Review  Technique  (PERT)  (probabilis7c)    A  technique  used  to  improve  the  accuracy  of  the  cost  or  dura7on  es7mates  of  project  components  when   there   is   uncertainty.   PERT  uses  weighted   averages  of   op7mis7c,   pessimis7c,   and  most   likely  es7mates   (the   well-­‐known   three-­‐point   es7mates)   of   the   components'   cost   or   dura7on.   Different  weigh7ng  schemes  represent  different  probability  distribu7ons  of  the  possible  cost  or  dura7on  of  a  component.  For  instance,  the  typical  formula  is  [(op/mis/c  +  4  /mes  the  most  likely  +  pessimis/c)  divided  by  6],  approximates  a  beta  distribu7on.    

CPM/PERT  •  Cri7cal  Path  Method  (CPM)  

–  DuPont  &  Remington-­‐Rand  (1956)  

–  Determinis7c  task  7mes  

–  Ac7vity-­‐on-­‐node  network  construc7on  

•  Project  Evalua7on  and  Review  Technique  (PERT)  

–  US  Navy,  Booz,  Allen  &  Hamilton  –  Mul7ple  task  7me  es7mates  (probabilis7c)  

–  Ac7vity-­‐on-­‐arrow  network    construc7on  

         PERT  elements   Events  (states),  ac7vi7es  (nature  and  7me),  preceding,  alloca7on,  context  (context  must  always  be  defined  and  clarified)    Some  examples  of  PERT  representa7on  -­‐  AOA  –  ac7vity  on  arrow,  or  ADM  -­‐  arrow  diagramming  method;  and  AON  –  ac7vity  on  node  

A,3 B,5

E,6

C,7

D,2

F,3 G,10

         PERT  elements   Events  (states),  ac7vi7es  (nature  and  7me),  preceding,  alloca7on,  context  (context  must  always  be  defined  and  clarified)    Some  examples  of  PERT  representa7on  -­‐  AOA  –  ac7vity  on  arrow,  or  ADM  -­‐  arrow  diagramming  method;  and  AON  –  ac7vity  on  node  

A,3 B,5

E,6

C,7

D,2

F,3 G,10

17  19  

Examples  of  different  nota/ons  

Parallel  ac/vi/es  signaled  as  we  exemplify  are  not  allowed  

A

B

A,B  

A

B dummy

If you fail this notation in the exam you will have “0” in the entire question

Task  B  can  only  be  started  acer  ac7vity  A  is  completed.  The  same  with  D  and  C  

A,3 B,7

C,4 D,6

10

10

A,3 B,7

C,4 D,6

Network  Analysis  example  AOA  

There  is  a  dummy  ac7vity  –  dura7on  0  (only  a  logical  dependency)  

A,3 B,7

C,4 D,6

10

10

Are  all  paths  iden7fied?  

Network  Analysis  example  AOA  

A,3 B,7

C,4 D,6

10

10

No,  there  are  three  paths,  not  two!      And  that  makes  quite  a  difference!!  

11

Network  Analysis  example  AOA  

A,3 B,7

C,4 D,6

10

10

11

Network  Analysis  example  AOA  

(A,B)

(C,B)

(C,D)

Instant time - 5 Time interval - 6

A,3 B,7

C,4 D,6

10

10

11

Activity Duration Early St Early Fi Latest St Lat. Fi. Float

A B C D

Dummy

Network  Analysis  example  AOA  

A,3 B,7

C,4 D,6

10

10

11

Activity Duration Early St Early Fi Latest St Lat. Fi. Float

A 3 0 3 1 4 1 B 7 4 11 4 11 0 C 4 0 4 0 4 0 D 6 4 10 5 11 1

Dummy 0 4 4 4 4 0

Network  Analysis  example  AOA  

Instant times

PERTS, and projects 1.  Define  the  project  and  all  its  ac7vi7es.  The  project  is  made  of  tasks  and  all  tasks  should  have  a  

single  start  and  a  single  finish  

2.  Develop  the  rela7onships  among  the  ac7vi7es.  Decide  which  ac7vi7es  must  precede,  which  must  follow  others,  and  the  ones  that  can  be  executed  in  parallel.  If  you  are  short  in  7me  try  to  put  in  parallel  as  much  ac7vi7es  as  you  can  

3.  Draw  the  network  diagram  connec7ng  all  the  ac7vi7es.  Each  ac7vity  is  unique.  Dummy  ac7vi7es  are  immaterial  in  7me  but  relevant  in  sequence,  they  impose  logical  dependences  

4.  You  can  assign  7me  and  cost  to  each  ac7vity  

5.  Compute  the  longest  7me  path  through  the  network.  This  path  is  called  the  Cri/cal  Path  

6.  Use  the  network  to  help  plan,  schedule,  monitor  and  control  the  project  and  also  as  a  communica7on  tool  

Preceded by a planning effort by the project management team. This planning effort is part of the Develop Project Manage- ment Plan process

documented  in  the  schedule  management  plan  

PERTS, and projects

PERTS, and projects

WBS GANTT PERT

 backward  pass  Early  dates  are  calculated  forwards,  using  the    forward  path.  Late  dates  are  calculated  in  reverse  direc7on,  star7ng  at  the  date  of  the  finishing  of  the  project  –  this  is  the  backward  path    

In  this  example  one  backward  path  leads  us  to  “event  3”  through  ac7vity  B.  So  we  have:  •   Total  project  7me  (cri7cal  path)  =  11  •   11-­‐7  =  4.  This  means  that  the  late  start  for  ac7vity  B  is  4    

Rela7ng  to  “event  2”  we  have  to  evaluate  two  paths,  Dummy  and  D.  Through  Dummy  we  have  4  -­‐  0  =  4,  this  means  that  Dummy  late  start  is  4  and  through  D  we  have  11  -­‐  6  =  5,  so  ac7vity  D  late  start  is  5  

A,3

C,4 D,6

B,7

2

3

4 DUMMY,0

Activity

Duration

Early St

Early Fi

Latest St

Lat. Fi.

Float

A 3 0 3 1 4 1 B 7 4 11 4 11 0 C 4 0 4 0 4 0 D 6 4 10 5 11 1

Dummy

0 4 4 4 4 0

Late  start  and  backward  path  

So   you   already  have   the   rule   to   compute   early   starts   and   late   starts.   Early   starts   are  computed  in  the  forward  path  from  the  beginning  to  the  end,  adding  dura7on    and  late  starts  are  computed  in  the  backwards  path,  subtrac7ng  dura7on  from  the  end    Project  management  tools  compute  this  for  you,  you  just  have  to  manage  according  to  situated  condi7ons  (environment,  resources,  risk,  …)  

Your  project  is  to  design  and  develop  an  electric  motor.  Ac7vity  dura7ons  and  predecessors  are   iden7fied  at   the   following   table.  A)  construct  a  PERT  AOA;  B)  Which   is   the  dura7on  of  every  path?  Which  path  is  the  cri7cal  one?  C)  What  happens  if  ac/vity  E  dura/on  becomes  8?    

Ac7vity   dura7on   predecessor  

A   10   -­‐  

B   20   -­‐  

C   4   -­‐  

D   2   A  

E   10   B,C  

F   8   B,C  

G   4   B,C  

H   2   C  

I   6   G,H  

J   2   D,E  

Ac7vity   dura7on   predecessor  

A   10   -­‐  

B   20   -­‐  

C   4   -­‐  

D   2   A  

E   10   B,C  

F   8   B,C  

G   4   B,C  

H   2   C  

I   6   G,H  

J   2   D,E  

Network  Analysis  example    AOA  

Ac7vity   dura7on   predecessor  

A   10   -­‐  

B   20   -­‐  

C   4   -­‐  

D   2   A  

E   10   B,C  

F   8   B,C  

G   4   B,C  

H   2   C  

I   6   G,H  

J   2   D,E  

Network  Analysis  example    AOA  

8  paths  

CP  

Ac7vity   dura7on   predecessor  

A   10   -­‐  

B   20   -­‐  

C   4   -­‐  

D   2   A  

E   10   B,C  

F   8   B,C  

G   4   B,C  

H   2   C  

I   6   G,H  

J   2   D,E  

Network  Analysis  example    AOA  

8  paths  

CP  CP  

30

E from 10 to 8:

14

A,3 B,7

C,4 D,6

Network  Analysis  example  AOA  à  AON  

A,3 B,7

C,4 D,6 With  AON  you  don’t  have  dummies  

END BEGIN

AOA

AON

Ac7vity   dura7on   predecessor  

A   10   -­‐  

B   20   -­‐  

C   4   -­‐  

D   2   A  

E   10   B,C  

F   8   B,C  

G   4   B,C  

H   2   C  

I   6   G,H  

J   2   D,E  A,10

B,20

C,4

D,2

E,10

F,8

G,4

H,2

I,6

J,2

B

END

Network  Analysis  example  AON  

ADJ 14 BEJ 32 BF 28 BGI 30 CEJ 16 CF 12 CGI 14 CHI 12