    Project Server Governance Model

    Enterprise Service Project Server

    Functional Unit

    Document Code

    DescriptionGovernance Model for Project Server

    Edition & Date 26-Nov-15

    Originator /Prepared By Bilal Farooq

    Document Change Owner Bilal Farooq

    Reviewed ByHassan Farouk

    Document Owner Bilal Farooq

    Approved By Muhammad Umer Shahbaz

    First Edition 26-Nov-2015

    First Draft 02-Dec-2015

    Document Location

    Distribution List

    The master copy of this document is stored on an electronic database (Intelex) and is “write-protected ”; itcan only be changed by the relevant identified personal. Copies cannot be printed. However any hard orsoft copy of this document is considered to be an uncontrolled copy used for reference only.

  • 8/16/2019 Governance Model for Project Server

    2/15

    Project Server Governance Model

    Technology Division, Telenor Pakistan Page 2

    Table of Contents

    Table of Contents

    Document Revision History .......................................................................................................................... 3

    Definitions ...................................................................................................................................................... 4

    Purpose ......................................................................................................................................................... 4

    Scope ............................................................................................................................................................. 4

    Inputs, Outputs and Linked Processes .......................................................................................................... 4

    Tools ............................................................................................................................................................... 4

    Roles and Responsibilities ............................................................................................................................ 5

    Document Owner / Process Owner............................................................................................................ 5

    Document Change Owner .......................................................................................................................... 5

    Decision Making ............................................................................................................................................ 6

    New Operational Request .......................................................................................................................... 6

    Boarding New Stakeholders Operational Request ..................................................................................... 6

    Enabling of Project Server Features ........................................................................................................... 6

    Granting Access Rights ............................................................................................................................... 6

    Operating Procedures ................................................................................................................................... 7

    Follow Asia Harmony Process .................................................................................................................... 7

    Project Server Health Status Reports ......................................................................................................... 7

    New Operational Requests ......................................................................................................................... 7

    RACI Matrix ................................................................................................................................................ 7

    Appendix ....................................................................................................................................................... 8

    Appendix A ................................................................................................................................................. 8

    Appendix B ...............................................................................................................................................10

    Appendix C................................................................................................................................................12

    This document is the property of Technology Division-Telenor Pakistan (Pvt.) Ltd. It may not be divulged toorganizations, divisions or persons outside the Technology Division /Telenor Pakistan without prior consent ofthe relevant line management authority of Technology Division.

  • 8/16/2019 Governance Model for Project Server

    3/15

    Project Server Governance Model

    Technology Division, Telenor Pakistan Page 3

    1. Document Revision History

    Sr.

    No

    Version Change Description Updated By Review By Review

    Date 1 1.0 First Draft Bilal Farooq Hassan Farouk 2-Dec-2015

    2 1.1

    3 1.2

    Important Note:

    Only the Document Change Owner is authorized to update the Document Revision History.

    Any change in the document will be done by consensus (mutual agreement) of stakeholders.

  • 8/16/2019 Governance Model for Project Server

    4/15

    Project Server Governance Model

    Technology Division, Telenor Pakistan Page 4

    2. Definitions

    PD: Product Development

    ES: Enterprise Services

    EAO: Enterprise Application Operations

    EPMO: Enterprise Project Management Office

    SOR: Split of responsibility

    RACI: RACI Matrix

    Document Owner/Process Owner: ES Planning

    Document Change Owner: ES Planning

    3. Purpose

    This document provides the guidelines and instructions to different teams in TelenorPakistan regarding governance of project server.

    4. Scope

    This document is applicable to for all stakeholders involved in governance ofProject Server as an Enterprise Service and users.

    5. Inputs, Outputs & linked processes

    Input: Understanding and Discussions with Stakeholders for Project ServerGovernance.

    Output: Governance Model for Project Server Linked Processes: Asia Harmony Processes

    6. Tools

    Project Server

  • 8/16/2019 Governance Model for Project Server

    5/15

    Governance Model Project Server

    Technology Division, Telenor Pakistan Page 5

    7. Roles & Responsibilities

    ES Planning

    Responsible for upgrade (H/W and S/W), Planning, Change Requests,Documentation and Capex handling

    EAO

    Responsible for operational management (Application Management,Resolution of errors, uninterrupted availability of solution and implementationof CRs as per direction of ES Planning) of Project Server, FLMs, daily HealthChecks, Escalations incase if issues persists after FLM.

    EPMO / PD

    Responsible for reporting of projects added in project server.

    PM

    Responsible for integrity of projects added in project server.

    Users

    Responsible for using project servers according to their access rights withoutviolating any company policy.

    7.1 Document Owner/ Process Owner

    To review the model periodically.

    To identify any changes required in the governance model.

    To help in documenting the changes and get them implemented.

    To train the staff on the changes.

    To communicate the changed version of document to stakeholders.

  • 8/16/2019 Governance Model for Project Server

    6/15

    Governance Model Project Server

    Technology Division, Telenor Pakistan Page 6

    7.2 Document Change Owner

    Implement the changes in the governance model after receiving feedbackfrom concerned Stakeholder.

    Get the governance model reviewed.

    8. Decision making

    Different types of decisions require different forms of approval. For example, proposingproject server to any department for use should be decided mutually by all stakeholders. Thissection defines how certain actions will be performed, the types of approval, and which typesof decision require which type of approval.

    8.1. New Operational Requests

    PD will raise request for any new operational request with the operations team.

    Operations will guarantee the implementation of new operational request as pertheir SLAs.

    8.2. Boarding New Stakeholder to Project Server

    PD will decide and raise a request to ES Planning enable new department oruser to start using project server.

    Whenever any stakeholder weather it is a department or user is brought onboard to start using project server, it will require approval of ES Planning.

    Operations will ensure that nominated department / user is able to use theproject server once they are given access rights to project server.

    8.3. Enabling of Project Server Features

    PD will raise request for enabling of new features of Project Server to ESPlanning.

    ES Planning will evaluate the effects of enabling the feature and will give itsrecommendations accordingly.

    Operations will guarantee the implementation of new operational request as perendorsements of ES Planning.

    8.4. Granting Access Rights

    PD will raise request for granting access rights to any individual according to theuse access rights mentioned in Appendix C. Approval of Line Manager orauthorized authority will be required for granting access rights.

    Operations will provide the access rights to the concerned stakeholder as perendorsements of ES Planning.

  • 8/16/2019 Governance Model for Project Server

    7/15

    Governance Model Project Server

    Technology Division, Telenor Pakistan Page 7

    9. Operating Procedures

    It is important that all the operating procedures follow certain processes finalized by TelenorPakistan.

    9.1.

    Follow Asia Harmony Processes.It will be ensured by all stakeholders that processes laid out for our guidance in AsiaHarmony are followed in true spirit for all operating procedures related to projectserver.

    9.2. Project Server Health Status Reports

    Operations team will periodically share the health status report of project server withES Planning for future expansions and up gradations.

    9.3. New Operational Requests

    New operational requests or change request will be raised on email with attachment ofrespective forms see. Appendix A and B. Approval from line manager or authorizedauthority of respective department will be required for every new operational request.

    9.4. RACI Matrix

    Below mentioned is the RACI Matrix which will help everyone about theresponsibilities.

    TASK(s) EPMO ES/OSSPlanning ES/OSS Ops

    Project Entry / Information ownership R

    Reporting R

    Handling Operational Issues in the Web App / Server I C R/A

    Configuration changes I C R/A

    Development on the Server / New Enhancements I R/A C

  • 8/16/2019 Governance Model for Project Server

    8/15

    Governance Model Project Server

    Technology Division, Telenor Pakistan Page 8

    Appendix A

    Change Request Form

    Prepared By Approved By Owner Approval Date Revision DOC#Hassan Faruok ES Planning 10-10-2015 1.0 NO_ES_001v02_Change Request

    Revision History

    Version Author Date Comment

  • 8/16/2019 Governance Model for Project Server

    9/15

    Governance Model Project Server

    Technology Division, Telenor Pakistan Page 9

    Change Request Details

    Change Title:

    Customer/Requested By:

    Name:

    Date:

    Required Change Description:

    Requesting the Change Request conforms that the requesting departmentwill accept all the changes in the system due to the change request

    implemented and will be responsible for the direct and indirect outcome andbehavior of the system/modules as the result of change request

    implemented.

    Change Request Approved and Accepted

    Customer ES Planning Name: Name:Title: Title:Date: Date:

    Change Request Rejected

    Customer ES Planning Name: Name:Title: Title:Date: Date:

  • 8/16/2019 Governance Model for Project Server

    10/15

    Governance Model Project Server

    Technology Division, Telenor Pakistan Page 10

    Appendix B

    New Operational Request FormPrepared By Approved By Owner Approval Date Revision DOC#Bilal Farooq ES Planning 10-10-2015 1.0 NO_ES_001v02_New Request

    Revision History

    Version Author Date Comment

  • 8/16/2019 Governance Model for Project Server

    11/15

    Governance Model Project Server

    Technology Division, Telenor Pakistan Page 11

    New Operational Request Details

    Change Title:

    Customer/Requested By:

    Name:

    Date:

    Operational Request Description:

    Requesting the new operational Request conforms that the requestingdepartment will accept all the changes in the system due to the changerequest implemented and will be responsible for the direct and indirect

    outcome and behavior of the system/modules as the result of new requestimplemented.

    New Operational Request Approved and Accepted

    Customer ES Planning Name: Name:Title: Title:Date: Date:

    New Operational Request Rejected

    Customer ES Planning Name: Name:Title: Title:Date: Date:

  • 8/16/2019 Governance Model for Project Server

    12/15

    Governance Model Project Server

    Technology Division, Telenor Pakistan Page 12

    Appendix C

    PermissionName

    Administrators PortfolioManagers

    PortfolioViewers

    ProjectManagers

    ResourceManagers

    TeamLeads

    TeamMembers

    AccessProjectServerReportingService

    × × ×

    Build TeamOn NewProject

    × × × ×

    Can BeDelegate

    ×

    ChangeWorkflow

    ×

    Clean UpProjectServerDatabase

    ×

    Contribute toProject WebApp

    × × × ×

    Edit StatusReportRequests

    × × × × × ×

    Log On × × × × × × ×Log on toProjectServer fromProjectProfessional

    × × × ×

    ManageActive

    DirectorySettings

    ×

    ManageCheck-Ins

    × ×

    ManageCubeBuildingService

    × ×

    ManageDrivers

    × × ×

    Manage × ×

  • 8/16/2019 Governance Model for Project Server

    13/15

    Governance Model Project Server

    Technology Division, Telenor Pakistan Page 13

    EnterpriseCalendarsManageEnterpriseCustomFields

    × ×

    ManageExchangeIntegration

    ×

    ManageGantt ChartandGroupingFormats

    ×

    Manage Listsin ProjectWeb App

    × × × ×

    Manage MyDelegates

    × ×

    Manage MyResourceDelegates

    × ×

    ManageNotificationandReminders

    ×

    ManagePersonal

    Notifications

    × × × × × × ×

    ManagePortfolioAnalyses

    × × ×

    ManagePrioritizations

    × × ×

    ManageProjectServerBackup

    ×

    Manage

    ProjectServerRestore

    ×

    ManageProject WebApp Views

    × ×

    ManageQueue

    ×

    ManageResourceNotifications

    × × × × × ×

  • 8/16/2019 Governance Model for Project Server

    14/15

    Governance Model Project Server

    Technology Division, Telenor Pakistan Page 14

    ManageRules

    × ×

    ManageSecurity

    ×

    Manage

    ServerConfiguration ×

    ManageServer Events

    ×

    ManageSharePointFoundation

    ×

    Manage TimeReportingand FinancialPeriods

    ×

    Manage TimeTracking ×

    ManageUsers andGroups

    ×

    ManageWorkflowProject DetailPages

    ×

    New Project × × ×NewResource

    × × ×

    New TaskAssignment

    × × × ×

    Open ProjectTemplate

    × × × ×

    ReassignTask

    × × ×

    SaveEnterpriseGlobal

    × × ×

    Save ProjectTemplate

    × × ×

    SaveUnprotectedBaseline

    × ×

    Self-assignTeam Tasks

    × × × × ×

    Status BrokerPermission

    ×

    ViewApprovals

    × × × × × × ×

    ViewBusiness

    × × × ×

  • 8/16/2019 Governance Model for Project Server

    15/15

    Governance Model Project Server

    IntelligenceLinkView OLAPData

    × × × ×

    View Project

    Center× × × × × × ×

    View ProjectScheduleViews

    × × × × × × ×

    View ProjectTimesheetLineApprovals

    × ×

    ViewResourceAvailability

    × × × × ×

    ViewResourceCenter

    × × × × ×

    ViewResourcePlan

    × × × × ×

    ViewResourceTimesheet

    ×

    View TaskCenter

    × × × × × × ×

    View TeamBuilder × × × ×ViewTimesheets

    × × × × × × ×