glasgow cal seminar
TRANSCRIPT
Managing construction risk using
the Observational Method
Dr Jason Le Masurier
Department of Civil Engineering
Contents
Geotechnical engineering risk The Observational Method Research project Case studies Systems to support the OM process Putting it into practice
Geotechnical Engineering
Boreholes
Temporary steel props
Attempts to eliminate uncertaintycan be wasteful…
…on the other hand
Predefined design Design Construct
Redesign
‘Fire fighting’
OK for predictable / low uncertainty cases
Otherwise:
Approaches to geotechnical design
1
Traditional construction procurement encourages the predefined design approach Linear and fragmented procurement route Lowest price bidding Desire to eliminate uncertainty / risk
There is an alternative…
The Observational Method
2 The Observational Method
Information and knowledge of
the ground
Design for most probable
Design contingencies for most
unfavourable
Observe -monitor
performance
Construct next stage
Design - review & improve further or use contingencies
Select
performance
indicators and
set triggers
Information and knowledgeof the ground
Perception
Action Reflection
Human nature
Perceived need
Implement design
Design solution
Construction Best Practice ??
Perceived need
Implement design
Design solution
‘Traditional’ construction practice
There are benefits in being ‘ Loopy ’
Monitor / observe
Construct Design (review)
Observational Method
See what happens
Think about it
Driving a car
Do something /nothing
Risk and opportunity
Final cost based on predefined design
Estimated cost
Cum
ulat
ive
Des
ign
cost
Cum
ulat
ive
Con
stru
ctio
n co
st
OM – minimum cost option
--- Predefined
OM design
Changing perceptions of cost as a project develops
after Muir Wood, 2000
Research project – University of Bristol‘Geotechnical innovation through observation’
Research funded by the Partners in Innovation initiative and supported by 12 industrial partner organisations.
The key objectives were: to enhance robustness of the Observational Method in
practice through systems thinking and process modelling;
to demonstrate the Observational Method as a special case of a generic approach to uncertainty management;
apply the process modelling methodology to a live construction project.
Action research
Case study research
Grounded theory
Grounded theory
Brainstorming workshop
Working in industry
Interviewing project team members
Interviewing domain experts
Research methodology
Technology Transfer Secondment
Case studies
New Hong Kong Airport Platform M6 Motorway, Scotland Limehouse Link, London Heathrow Express Tunnels, London
Chek Lap Kok Airport Platform – managing settlement uncertainty
Chek Lap Kok Airport Platform – installation levels procedure
M6 Motorway Construction, Scotland
M6 Motorway Construction – soil nailing
Grouting facility to mitigate settlement risk
Limehouse Link, London – eliminating temporary support on a 1.7km cut and cover tunnel
Heathrow Express Tunnels – NATM construction
Heathrow Express Tunnels – the morning after
Monitor / observe
Construct Design (review)
Enquiry findings
‘Organisations and groups of organisations have multiple defences to prevent incidents. In the construction industry these defences can be influenced by the contractual relationships…This has the advantage of providing some redundancy and diversity in the defences against failure but it can also provide the opportunity for misunderstandings and simultaneous failures where there is uncertainty about the respective roles and responsibilities of the parties.
• Cooperative culture • Coordinated teams • Common objectives• Communicate efficiently• Clarity over responsibilities• Creative thinking• Continuous improvement
‘C’ for success of Observational Method
Identifying next stage
construction
Monitoring
Reviewing values from monitoring
Using emergency
plan
Deciding on action
Taking extra readings
Excavating next stage
Reviewing conditions
Using contingency
plan
Agreeing
Main contractor
Sub contractor
Geotech. designer
Geotech. control Monitor
GREEN
AMBER
RED
Surveying
Designing the process
Parameter Moderately Conservative
based on design codes
Most Probable
based on experience
Reference
Made Ground / = 25 / = 38 OAP - Broadgate
Taplow Gravel / = 36 / = 40 Lehane et al
London Clay / = 23 c/ = 0 / = 24 c/ = 10kPa OAP, Cross Rail
Lambeth Clay / = 23 c/ = 0 / = 28 c/ = 25kPa OAP, Cross Rail
Water Pressure in Taplow Gravel +7.5mOD None Geotechnical Report
Minimum Equivalent Fluid Pressure applied from GL None Observations
Softening Passive soil None Observations - OAP Horseferry Road
Surcharge 20kPa 20kPa (Perm) 10kPa (Temp)
-
Overdig 0.5m None -
Undrained Shear Strength London Clay
70+7.5z*kPa
+5.5mOD - 11.0mOD 112+5.19z kPa *
-11.0mOD - 17.5mOD 200kPa
-17.5mOD - 29.2mOD 400kPa
Results - see Justification Report
Undrained Shear Strength Lambeth Clay 300kPa 400kPa Results - see Justification Report
Stiffness of Clay (Eu) 1000cu 1500cu Back-analysis
Empirical approach to design
Alternative construction sequencesOriginal design construction sequence
Observational Method design construction sequence
1 2
321
43
Secant pile wall
Existing basement
Permanent floor slabs / props
Arup (GIE) HBG McGee Arup (OMR) Soil Instruments Ltd
OMR
IMS
Project Manager
Project Manager
Project Manager
Identifying next stage of
construction
Reviewing values from monitoring
Reviewing conditions
Deciding on action
GREEN Processes
AMBER Processes
RED Processes
Reviewing values from monitoring
Reviewing values from monitoring
Section Engineer
Monitoring primary system
Surveyor
Project Manager
Construction Manager
Monitoring supplementary
Implementing contingency
plansConstruction
Manager
Byrne Bros.
Construction Manager
Monitoring supplementary
Monitoring supplementary
Monitoring primary system
Monitoring primary system
GIE
Designing the process - responsibilities
Client satisfaction
Hard Key Performance Indicators SoftTime Cost Functionality People
% complete % budgetspent
Wall deflection Settlement
Efficiency ofcommunicationCooperation of team
Material wastage
Feedback
Continuous im
provement
and learning
Client Designer Sub-contractorContractorChecking
designDesigning
works
Identifyingnext stage
Constructingnext stage
MonitoringReviewingdesign
Checkingdesign 2
Decidingactions
Level 2
Level 1
Level 3
Level 4
Shared objectives
Proj
ect p
rogr
essi
on
Monitoring
Action
Client satisfaction
Hard Key Performance Indicators SoftTime Cost Functionality People
% complete % budgetspent
Wall deflection Settlement
Efficiency ofcommunicationCooperation of team
Material wastage
FeedbackBenchmarking
Integrated processes and teams
Value Management
Partnering
Continuous im
provement
and learning
Client Designer Sub-contractorContractorChecking
designDesigning
works
Identifyingnext stage
Constructingnext stage
MonitoringReviewingdesign
Checkingdesign 2
Decidingactions
Level 2
Level 1
Level 3
Level 4
ObservationalEngineering
Shared objectives
ConclusionThe Observational Method:
has a track record in successfully managing ground uncertainties – minimising risk and maximising opportunity
thrives under collaborative project relationships requires explicit, integrated project processes and
clearly defined responsibilities is an example of a generic approach to managing
project uncertainty that can be applied holistically
Conclusion
“ If a man will begin with certainties he shall end with doubts; but if he will be content to begin with doubts, he shall end in certainties”
Advancement of Learning, Francis Bacon
Observe / monitor ‘hard’ KPIs
Construct next stage Review
PRODUCT design - improve / use contingencies
Observe / monitor ‘soft’ KPIs
DO IT Review PROCESS design - improve / use contingencies
Why do we want this project?
DO VM
... for strategic planning - WHY
DO VM...
… for PROCESS design - what, who, how, where, when
ContinuousVE
DO VE…initial design of
PRODUCT
...design the PROCESS
How will we achieve it? ...
…improved design of PRODUCT
ContinuousVM
OMloops
© Jason Le Masurier, 1999