Gili Trawangan Relay Project Laporan & Dokumentasi
Disiapkan Oleh:
Rizal Bachtiar ST.Blueline Broadband Internet - Infrastructure Division
BLUELINEPT. Rabik Bangun Pertiwi PMAIstana Kuta Galeria Valet 2 No. 7 Kuta-BadungBali 80361Telp : 0361-769355Fax : 0361-769354Website : www.blueline.co.id
Daftar Isi
Pendahuluan...............................................................................................................Cakupan......................................................................................................................Kualitas pengerjaan project.........................................................................................Anggaran biaya yang terpakai....................................................................................Waktu pengerjaan & kendala......................................................................................Sumberdaya manusia.................................................................................................Dokumentasi...............................................................................................................
Pendahuluan
Dengan mulai adanya permintaan akan adanya sambungan koneksi ke internet di wilayah Lombok khususnya daerah Sire, pulau Gili Trawangan dan sekitarnya, maka tahun ini manajemen Blueline ingin mengambil kesempatan untuk memperluas jangkauan layanan di daerah-daerah tersebut dengan membangun satu lagi dedicated relay / basestation untuk menggantikan fungsi relay / basestation percobaan kita yang di Sire. Berdasar dari hasil survey yang telah jauh terlebih dahulu dilakukan akhirnya kita memutuskan untuk menggunakan SD. Gili Trawangan. sebagai letak paling strategis dari relay Gili Trawangan. Di kawasan sekolah ini kita menggunakan area seluas 1,5 are untuk merealisasikan pembangungan relay ini. Lahan sekolah yang kita sewa ini bernilai kontrak 60 juta rupiah untuk kurun waktu 5 tahun. Cuman dalam proses dari awal survey hingga pembangunan terdapat beberapa perubahan rencana dari rencana semula yaitu rencana pembangunan tower yang semula akan di borongkan di batalkan karena pihak pemborong membatalkan secara sepihak dengan alasan harga material sudah tidak seperti waktu perjanjian awal sehingga memaksa kita untuk menggunakan sebagian SDM dari Head Office Blueline untuk secara langsung membantu pengerjaan & sekaligus mensupervisi pengerjaannya.
Cakupan
Dalam project ini ada beberapa hal yang menjadi cakupan pekerjaan yang harus di kerjakan dan menjadi bagian dari project ini, yaitu antara lain:
➔ Perencanaan tower & pelindungnya. Dimana team infrastructure melakukan semua perencanaan pembangunan tower & pelindungnya & juga melakukan kalkulasi seluruh material & supporting material berdasar pengalaman yang telah kita miliki (menggunakan metode trial & error).
➔ Perencanaan biaya. Berdasarkan hasil perencanaan dan kalkulasi material & supporting material itu team infrastructure sub-divisi warehouse melakukan survey harga di bantu juga oleh team Lombok mengingat bahwa sebagian material pondasi kita putuskan untuk membelinya di Lombok mengingat efisiensi. Dan dari hasil survey harga itu kita gunakan data yang ada untuk melakukan perencanaan biaya.
➔ Pembelian material pondasi. Untuk hal pembelian seluruh material pondasi di lakukan oleh team Lombok (Sdr. Robert) mengingat efesiensi (jika seluruh material kita beli di Bali maka akan meningkatkan biaya pengiriman) dan juga mengingat hanya sdr. Robert yang lebih menguasai wilayah Lombok.
➔ Perencanaan pengiriman supporting material. Pengiriman supporting material seperti tower, pagar dan lain-lain di lakukan dengan sekali kirim dengan menggunakan truk dari bali pada tanggal 28 November 2010.
➔ Pencarian akomodasi. Pencarian penginapan dibantu oleh Bapak H. Muhidin yang merupakan tokoh di wilayah Gili Trawangan & juga kepala sekolah SD di mana lokasi relay kita di bangun dan dengan bantuan beliau kita mendapat harga sewa penginapan yang jauh dari harga normal karena kita dianggap sebagai tamu beliau
➔ Membantu implementasi pembangunan tower & supervisi. Dalam implementasi pembangunannya, seluruh anggota team infrastructure ikut serta dalam proses
pembangunan relay ini di bantu oleh tenaga buruh yang kita sewa untuk mempercepat proses pengerjaannya relay ini dan team kita sekaligus berperan dalam mensupervisi pengerjaan relay ini mulai dari penggalian lubang pondasi, pengecoran pondasi pemasangan pagar pelindung hingga proses menaikkan tower.
➔ Pencarian & negoisasi buruh kerja. Dalam pengerjaan project ini memang kita terpaksa menggunakan bantuan buruh (kuli bangunan) untuk mempercepat proses pembangunannya di karenakan keterbatasan jumlah team yang terlibat dan untuk efisiensi biaya. Seluruh buruh (kuli bangunan) team dapatkan dari penduduk lokal di pulau Gili Trawangan.
➔ Instalasi kelistrikan. Proses instalasi ini di lakukan menyusul setelah tower berdiri setengah. Dan proses instalasi kelistrikantermasuk di dalamnya instalasi battery, UPS dan solar panel di lakukan oleh sdr. Ketut Budha dari sub-divisi Mechanical Electrical.
Kualitas Pengerjaan Proyek
➔ Spesifikasi Galian, Beton Pondasi tower & anchorDimensi galian anchor : 1,5m x 1,5m x 2mDimensi galian grounding : 1,5m x 1,5m x 2mKomposisi campuran beton : 10 sak pasir : 5 sak koral : 1 sak semen : 1 kibik batu kaliCatatan : komposisi campuran beton di buat berdasarkan pengalaman dan bukan perhitungan secara teknis (metode trial & error)
➔ Spesifikasi Penangkal PetirDown Connector : Kawat BC35mm2 ( sesuai IEC 1024-1 tetapi masih di bawah ukuran yang di syaratkan dimana disarankan yaitu menggunakan dimensi 50mm2)Tombak / air terminal : tembaga 2 meter ( sensuai IEC 1024-1 untuk membentuk cone terbalik 60 derajat)Sistem pentanahan : Tidak terukurCatatan : sistem pentanahan tidak terukur karena memang kita tidak memiliki earth/ground meter
➔ Spesifikasi tower & pagar pengamanTower : Pipa BSA 1” dengan besi as 13mm setinggi 11 stage (33 meter)Pagar : Galvanis 3 x 3 meter
Anggaran Biaya Yang Terpakai
Financial Report
AKOMODASI
No Total 1 17 30.000 510.0002 Andre 17 30.000 510.0003 11 30.000 330.0004 14 30.000 420.0005 12 30.000 360.000
No Total 1 29/11/10 13/12/10 15
No Total 1 26/12/10 1 35.0002 26/12/10 1 65.0003 02/12/10 1 65.0004 10/12/10 1 65.0005 26/11/10 1 236.0006 01/12/10 1 310.0007 09/12/10 1 220.0008 20/12/10 1 192.0009 20/12/10 1 65.00010 20/12/10 1 50.000
No Total 1 27/11/10 1 5.0002 28/11/10 3 15.0003 29/11/10 3 15.0004 30/11/10 4 20.0005 01/12/10 4 20.0006 02/12/10 1 17.0007 03/12/10 4 & 1 37.0008 04/12/10 0 0 09 05/12/10 1 17.00010 08/12/10 1 17.00011 10/12/10 1 17.00012 11/12/10 0 0 013 12/12/10 0 0 0
Gili Trawangan Relay Infrastructure Project 2010
Uang Makan Team Gili TrawanganNama Hari Jumlah
Prapto
YudiAmikBudha
Rp 2.130.000,-
Penginapan Team Gili TrawanganMulai Tanggal Sampai Tanggal Jumlah Hari
Rp 2.000.000,-Rp. 2.000.000,-
Tiket Pesawat, Boarding & InsuranceTanggal Nama Team Jumlah
Taxi PraptoBoarding & Insurance PraptoBoarding & Insurance SayudiBoarding & Insurance BudhaTiket PraptoTiket SayudiTiket BudhaTiket BudhaBoarding & Insurance BudhaTaxi Budha
Rp 1.303.000
Air Minum Team “Narmada”Tanggal Jumlah Satuan
BotolBotolBotolBotolBotolGalon
Botl & Galon
GalonGalonGalon
Rp. 180.000,-
MATERIAL, SUPPORTING MATERIAL & TRANSPORT
Qty Item 4-Dam 150.000 600.000
Boat 200.000 800.000800.000
250.000 1.000.000
Qty Item 3- Dam 250.000 750.000 3- Dam Boat 200.000 600.000
600.000250.000 750.000
Qty Item500 Packing 1.000 500.000
Qty ItemKoral 675.000Boat 300.000
300.000375.000
Qty Item400 2.500 1.000.000
Qty Item400.000
Boat 200.000 400.000400.000500.000
Tanggal 01/12/10Harga Jumlah
Pasir kali4- Rit4- Rit Buruh4- Rit Cidomo
Rp.3.200.000,-
Tanggal 29/11/10Harga Jumlah
Batu kali
3- Rit Buruh3- Rit Cidomo
Rp.2.700.000,-
Tanggal 04/12/10Harga Jumlah
Rp.500.000,-
Tanggal 04/12/10Harga Jumlah
1,1/2 Rit1,1/2 Rit1,1/2 Rit Buruh1,1/2 Rit Cidomo
Rp.1.650.000,-
Tanggal 04/12/10Harga Jumlah
BatakoRp.1.000.000,-
Tanggal 04/12/10Harga Jumlah
2-Rit Besi Tower2-Rit2-Rit Buruh2-Rit Cidomo
Rp.1.700.000,-
No Qty Total 1 30/11/10 4 10.0002 01/12/10 Semen 1 63.0003 01/12/10 12 600.0004 02/12/10 Semen 2 126.0005 02/12/10 Semen 10 635.0006 02/12/10 Semen 5 350.0007 03/12/10 1 90.0008 03/12/10 1 90.0009 03/12/10 Semen 10 630.00010 04/12/10 1 30.00011 04/12/10 Semen 4 252.00012 05/12/10 1 & ½ 78.00013 03/12/10 1 11.00014 05/12/10 Semen 1 63.00015 06/01/10 Semen 1 63.00016 07/12/10 2 20.00017 11/12/10 2 8.00018 12//12/10 2 20.000
No Total 1 28/11/10 50.000 50.0002 28/11/10 50.000 50.0003 28/11/10 3.000.000 3.000.000
RP. 3.100.000,-
No Total 1 12/12/10 1 40.0002 12/12/10 1 20.0003 12/12/10 1 50.000
No Total 1 01/12/10 1 140.0002 02/12/10 1 210.0003 03/12/10 1 280.0004 04/12/10 1 350.0005 05/12/10 1 350.0006 06/12/10 1 280.0007 09/12/10 1 210.0008 10/12/10 1 210.0009 1 35.000
Pembelian Material & Supporting Material di Gili TrawanganTanggal Nama Bahan
Benag putih
Kayu
TriplekTriplek
Pulsa
Semen & PakuSiku Siku
Batteray u/cameraKuas 2”
Batteray u/cameraRp. 3.139.000,-
Biaya Transportasi Tower & Supporting Material DPS-AMITanggal Petugas jumlah
Masuk KapalKeluar KapalSewa Truk
Tanggal Jenis JumlahCidomoBuruh
Perahu butRp 120.000,-
Gaji Harian Tukang
Tanggal Nama Pekerja jumlah hariP.Wan,dolong P.wan,dolong,maidiP.wan,dolong,maidi,gamekp.wan,dolong,maidi,gamek,safiraP.wan,dolong,maidi,gamek,SafiraP.wan,dolong,maidi,gamekP.wan,dolong,maidiP.wan,dolong,maidiLemburan 2 jam
Rp. 2.065.000,-
Jadi total biaya yang di habiskan untuk membangun infrastruktur Relay Gili Trawangan ini adalah Rp. 24.787.000,-
Note: Dalam Purchase Order terdapat perbedaan total dana karena tercampur dengan tiket+boarding pass+asuransi+transport kepulangan Herdi dan keberangkatan Andre
Waktu Pengerjaan & Kendala
Waktu Pengerjaan
Dalam pengerjaannya, seluruh infrastruktur relay Gili Trawangan ini di selesaikan dalam waktu 17 hari dengan detail sebagai berikut:
Tanggal Deskripsi Aktivitas
26/11/10 ✔ Persiapan alat-alat dan material di gudang✔ Prapto berangkat bersama dengan Andre yang menggantikan
tugas Herdi ke Lombok
27/11/10 ✔ Pembelian material pondasi untuk tower bersama team Lombok
28/11/10 ✔ Ke dermaga Bangsal untuk pembelian matrial lainnya & mengurus transportasi pengiriman seluruh matrial pondasi ke Gili Trawangan
✔ Team dari Kuta berangkat dengan truk dengan membawa seluruh body tower dan supporting matrialnya dengan di kawal oleh Rachmat
✔ Ke Gili Trawangan untuk mencari penginapan untuk team✔ Prapto di tinggal di Gili Trawangan untuk mempersiapkan
supporting material lan mencari toko penjual supporting materialnya
29/11/10 ✔ Menemui toko supplier untuk memesan tambahan material✔ Mencari tukang bangunan
30/11/10 ✔ Melakukan pengecekan seluruh material & supporting material yang mulai di kirim hari itu dari Lombok
✔ Nego harga dengan tukang bangunan
01/12/10 ✔ Tukang bangunan sudah mulai kerja dan hanya dapat 2 lubang galian
✔ Pemasangan anker tengah✔ Melakukan pengecekan seluruh material & supporting material
yang masih berlanjut proses pengirimannya
02/12/10 ✔ Melanjutkan penggalian lubang anchor✔ Sayudi berangkat ke Lombok untuk membantu pengerjaan dan
memberikan supervisi terhadap kualitas pondasi dan pemasangan tower
03/12/10 ✔ Pengecoran anchor✔ Penanaman grounding/pentanahan
04/12/10 ✔ Penggalian untuk shelter relay dan pengurukan pondasi karena akan di naikkan 40 cm
✔ Pemlesteran lantai relay
05/12/10 ✔ Menaikkan atap shelter relay✔ Pengecoran anchor utama✔ Pengacian pondasi relay
06/12/10 ✔ Pemasangan semua anchor & pengecekan ulang
07/12/10 ✔ Melakukan pengecekan ulang body tower yang akan di pasang
08/12/10 ✔ Mempersiapkan kerangka pagar
09/12/10 ✔ Menaikkan body tower
10/12/10 ✔ Melanjutkan menaikkan body tower, pemasangan pagar & finishing
11/12/10 ✔ Pemasangan electrical✔ Pengecekan akhir infrastrukture relay (tower, shelter & pagar)
12/12/10 ✔ Take down solar panel dan beberapa radio bersama team Operation Lombok
✔ Team yang membangun infrastruktur tower, shelter & pagar relay kembali ke Lombok
13/12/10 ✔ Prapto, Sayudi dan Rachmat kembali ke kantor Kuta dengan membawa serta mobil operasional Lombok
✔ Pengiriman solar panel & radio ke Gili Trawangan✔ Pointing Point To Point Penida-Gili Trawangan✔ Pemasangan solat panel
14/12/10 ✔ Take down box panel + ups + battery yang ada di relay Sire dan melakukan bypass kelistrikan direct ke PLN
15/12/10 ✔ Pengiriman box panel + battery + ups ke Gili Trawangan
16/12/10 ✔ Pemasangan box panel + ups + battery di relay Gili Trawangan
17/12/10 ✔ Melanjutkan pemasangan box panel + ups + battery di relay Gili Trawangan
18/12/10 ✔ Melanjutkan pemasangan box panel + ups + battery di relay Gili Trawangan
✔ Pemasangan lampu sign tower
19/12/10 ✔ Repointing Sire Beach House ke relay Gili Trawangan✔ Training kelistrikan relay Gili Trawangan ke staf infrastructure di
Lombok
20/12/10 ✔ Repointing Sepoi-sepoi ke relay Gili Trawangan✔ Budha kembali ke Kuta
Kendala-kendala Lapangan
✔ Tukang bangunan yang di janjikan akan di usahakan oleh bapak H. Muhidin kabur tidak jelas kemana
✔ Cuaca yang tidak menentu dimana hampir setiap hari turun hujan, bahkan pada saat instalasi kelistrikan team nyaris hanya bisa bekerja kurang dari 3 jam sehari karena cuaca buruk
✔ Metode pensurveyan yang tidak standar dimana selama ini kita tidak pernah melakukan soil test seperti yang selalu dilakukan oleh para kontraktor tower profesional berpotensi membuat terjadinya salah perhitungan material seperti untuk perhitungan komposisi beton di karenakan kita tidak tahu persis struktur & sifat tanah seperti yang di kaji dalam keilmuan soil mechanic.
✔ Masalah politis dengan oknum-oknum pejabat desa membuat proses pengerjaan mengalami hambatan selama kurang lebih 2 hari
✔ Keterlambatan pengiriman material yang di sebabkan oleh program bersih pantai yang dilakukan oleh Pemda setempat .
Sumber Daya Manusia
Dalam proyek pembangunan relay Gili Trawangan ini, kita bekerja sama menggunakan bantuan sumber daya manusia dari beberapa divisi dan pihak ketiga. Yaitu:
Infrastructure Division
✔ Warehouse : (Sdr. Anand, Prapto & Legawa) untuk proses survey harga & belanja material & supporting material
✔ Installation & Maintenance : Sdr. Saifurahman untuk perencanaan pondasi & tower, Sdr. Sayudi untuk perencanaan pondasi, tower, shelter, dan supervisi lapangan, implementor, Sdr. Rachmat sebagai pengawal material & implementor, Sdr. Prapto untuk implementasi, pengechekan material, belanja di lapangan & pengatur keuangan dan Sdr. Andre sebagai implementor.
✔ Mechanical Electrical: Sdr. Dlofir untuk perencanaan kelistrikan, Sdr Ketut Budha untuk perencanaan kelistrikan & implementor
Operation Division
✔ Sdr. Robert sebagai fasilitator Blueline dengan publik & support belanja material
Accounting Department
✔ Lady (Financial Controller)✔ Eka & Enny (Inventory & Purchasing)
Pihak Ketiga
✔ Bapak Wan (tukang/kuli bangunan)✔ Bapak Dalong (tukang/kuli bangunan)✔ Bapak Maidi (tukang/kuli bangunan)✔ Bapak Gamek (tukang/kuli bangunan)✔ Bapak Safira (tukang/kuli bangunan)
Dokumentasi
Berikut terlampir beberapa foto dokumentasi proyek pembangunan relay Gili Trawangan