gibbs middle school project

1
For project informaon, and to track updates throughout the process, please visit: hp://www.arlington.k12.ma.us/administraon/faciliesenrollment/gibbsrenovaon/ & hp://www.arlingtonma.gov/gibbs. GIBBS MIDDLE SCHOOL PROJECT Contacts 7AM-5PM For general project inquiries: Bill McNally NV5’s Site Representave (617) 992-0625 For aſter hours emergencies: Arlington Police Department 24 Hour Dispatch: (781) 643-1212 Project Consultant Team NV5 - Owner’s Project Manager Finegold Alexander Architects - Architect Shawmut Design & Construcon- Construcon Manager Upcoming Fall Acvies: Mobilizaon of Masonry contractors for restoraon work on the exterior of the building. Foundaon for new Foster Street entrance and installaon of new curtainwall. Interior Steel Erecon. Installaon of new windows. Roof patching and installaon of new rootop mechanical units. Replacement of exisng stairwells. Current Construcon Acvies: Site mobilizaon is in progress. Delivery of site trailers is complete. Installaon of Temporary construcon electrical power and make safe is complete. Enabling site work is ongoing including demolion of exisng pathways and curbing. Installaon of tree protecon to remain for the duraon of construcon. Interior Abatement and Demolion is ongoing. Demolion of the exisng curtainwall at the Foster Street entrance. Removal of exisng windows, which will be replaced with cost and energy saving windows. Abatement and removal of exisng machinary from the exisng boiler Overall Construcon Schedule Summer 2017 Site Work Interior Demo/Abatement Fall 2017-Summer 2018 Interior Fit Out Summer 2018 Substanal Compleon Landscaping Furnishings Fall 2018 Occupy School

Upload: others

Post on 16-Jan-2022

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: GIBBS MIDDLE SCHOOL PROJECT

For project information, and to track updates throughout the process, please visit: http://www.arlington.k12.ma.us/administration/facilitiesenrollment/gibbsrenovation/ &

http://www.arlingtonma.gov/gibbs.

GIBBS MIDDLE SCHOOL PROJECT

Contacts 7AM-5PMFor general project inquiries: Bill McNallyNV5’s Site Representative (617) 992-0625

For after hours emergencies: Arlington Police Department 24 Hour Dispatch: (781) 643-1212

Project Consultant TeamNV5 - Owner’s Project Manager Finegold Alexander Architects - Architect Shawmut Design & Construction- Construction Manager

Upcoming Fall Activities:

• Mobilization of Masonry contractors for restoration work on the exterior of the building.

• Foundation for new Foster Street entrance and installation of new curtainwall.

• Interior Steel Erection.

• Installation of new windows.

• Roof patching and installation of new rootop mechanical units.

• Replacement of existing stairwells.

Current Construction Activities:• Site mobilization is in progress. Delivery of site trailers is complete.• Installation of Temporary construction electrical power and make safe

is complete.• Enabling site work is ongoing including demolition of existing pathways

and curbing.• Installation of tree protection to remain for the duration of

construction.• Interior Abatement and Demolition is ongoing. • Demolition of the existing curtainwall at the Foster Street entrance.

• Removal of existing windows, which will be replaced with cost and energy saving windows.

• Abatement and removal of existing machinary from the existing boiler

Overall Construction ScheduleSummer 2017 Site Work Interior Demo/Abatement

Fall 2017-Summer 2018 Interior Fit Out

Summer 2018 Substantial Completion Landscaping FurnishingsFall 2018 Occupy School