general aspect of energy management and energy audit

259
1 Bureau of Energy Efficiency 1. ENERGY SCENARIO Syllabus Energy Scenario: Commercial and Non-Commercial Energy, Primary Energy Resources, Commercial Energy Production, Final Energy Consumption, Energy Needs of Growing Economy, Long Term Energy Scenario, Energy Pricing, Energy Sector Reforms, Energy and Environment: Air Pollution, Climate Change, Energy Security, Energy Conservation and its Importance, Energy Strategy for the Future, Energy Conservation Act-2001 and its Features. 1.1 Introduction Energy is one of the major inputs for the economic development of any country. In the case of the developing countries, the energy sector assumes a critical importance in view of the ever- increasing energy needs requiring huge investments to meet them. Energy can be classified into several types based on the following criteria: Primary and Secondary energy Commercial and Non commercial energy Renewable and Non-Renewable energy 1.2 Primary and Secondary Energy Primary energy sources are those that are either found or stored in nature. Common pri- mary energy sources are coal, oil, natural gas, and biomass (such as wood). Other primary energy sources available include nuclear energy from radioactive substances, thermal energy stored in earth's interi- or, and potential energy due to earth's gravity. The major pri- mary and secondary energy sources are shown in Figure 1.1 Primary energy sources are mostly converted in industrial utilities into secondary energy sources; for example coal, oil or gas converted into steam Figure 1.1 Major Primary and Secondary Sources

Upload: pradeepdesaiuch

Post on 18-Jan-2016

134 views

Category:

Documents


1 download

DESCRIPTION

Energy

TRANSCRIPT

Page 1: General Aspect of Energy Management and Energy Audit

1Bureau of Energy Efficiency

1. ENERGY SCENARIO

SyllabusEnergy Scenario: Commercial and Non-Commercial Energy, Primary Energy Resources,Commercial Energy Production, Final Energy Consumption, Energy Needs of GrowingEconomy, Long Term Energy Scenario, Energy Pricing, Energy Sector Reforms, Energyand Environment: Air Pollution, Climate Change, Energy Security, Energy Conservationand its Importance, Energy Strategy for the Future, Energy Conservation Act-2001 and itsFeatures.

1.1 Introduction

Energy is one of the major inputs for the economic development of any country. In the case ofthe developing countries, the energy sector assumes a critical importance in view of the ever-increasing energy needs requiring huge investments to meet them.

Energy can be classified into several types based on the following criteria:

• Primary and Secondary energy• Commercial and Non commercial energy• Renewable and Non-Renewable energy

1.2 Primary and Secondary Energy

Primary energy sources arethose that are either found orstored in nature. Common pri-mary energy sources are coal,oil, natural gas, and biomass(such as wood). Other primaryenergy sources availableinclude nuclear energy fromradioactive substances, thermalenergy stored in earth's interi-or, and potential energy due toearth's gravity. The major pri-mary and secondary energysources are shown in Figure 1.1

Primary energy sources aremostly converted in industrialutilities into secondary energysources; for example coal, oilor gas converted into steam Figure 1.1 Major Primary and Secondary Sources

Page 2: General Aspect of Energy Management and Energy Audit

1. Energy Scenario

2Bureau of Energy Efficiency

and electricity. Primary energy can also be used directly. Some energy sources have non-ener-gy uses, for example coal or natural gas can be used as a feedstock in fertiliser plants.

1.3 Commercial Energy and Non Commercial Energy

Commercial Energy

The energy sources that are available in the market for a definite price are known as commer-cial energy. By far the most important forms of commercial energy are electricity, coal andrefined petroleum products. Commercial energy forms the basis of industrial, agricultural,transport and commercial development in the modern world. In the industrialized countries,commercialized fuels are predominant source not only for economic production, but also formany household tasks of general population.

Examples: Electricity, lignite, coal, oil, natural gas etc.

Non-Commercial Energy

The energy sources that are not available in the commercial market for a price are classified asnon-commercial energy. Non-commercial energy sources include fuels such as firewood, cattledung and agricultural wastes, which are traditionally gathered, and not bought at a price usedespecially in rural households. These are also called traditional fuels. Non-commercial energyis often ignored in energy accounting.

Example: Firewood, agro waste in rural areas; solar energy for water heating, electricitygeneration, for drying grain, fish and fruits; animal power for transport, threshing, lifting waterfor irrigation, crushing sugarcane; wind energy for lifting water and electricity generation.

1.4 Renewable and Non-Renewable Energy

Renewable energy is energy obtained from sources that are essentially inexhaustible. Examplesof renewable resources include wind power, solar power, geothermal energy, tidal power andhydroelectric power (See Figure 1.2). The most important feature of renewable energy is that itcan be harnessed without the release of harmful pollutants.

Non-renewable energy is the conventional fossil fuels such as coal, oil and gas, which arelikely to deplete with time.

Figure 1.2 Renewable and Non-Renewable Energy

Page 3: General Aspect of Energy Management and Energy Audit

1. Energy Scenario

3Bureau of Energy Efficiency

1.5 Global Primary Energy Reserves*

Coal

The proven global coal reserve was estimated to be 9,84,453 milliontonnes by end of 2003. The USA had the largest share of the globalreserve (25.4%) followed by Russia (15.9%), China (11.6%). Indiawas 4th in the list with 8.6%.

Oil

The global proven oil reserve was estimated to be 1147 billion barrels by the end of 2003. SaudiArabia had the largest share of the reserve with almost 23%. (One barrel of oil is approximately 160 litres)

Gas

The global proven gas reserve was estimated to be 176 trillion cubic metresby the end of 2003. The Russian Federation had the largest share of thereserve with almost 27%.(*Source: BP Statistical Review of World Energy, June 2004)

World oil and gas reserves are estimated at just 45 years and 65years respectively. Coal is likely to last a little over 200 years

Global Primary Energy Consumption

The global primary energy consumption at the end of 2003 was equivalent to 9741 milliontonnes of oil equivalent (Mtoe). The Figure 1.3 shows in what proportions the sources men-tioned above contributed to this global figure.

Figure 1.3 Global Primary Energy Consumption

Page 4: General Aspect of Energy Management and Energy Audit

1. Energy Scenario

4Bureau of Energy Efficiency

The primary energy consumption for few of the developed and developing countries are shownin Table 1.1. It may be seen that India's absolute primary energy consumption is only 1/29th ofthe world, 1/7th of USA, 1/1.6th time of Japan but 1.1, 1.3, 1.5 times that of Canada, Franceand U.K respectively.

TABLE 1.1 PRIMARY ENERGY CONSUMPTION BY FUEL, 2003

In Million tonnes oil equivalent

Oil Natural Coal Nuclear Hydro TotalCountry Gas Energy electric

USA 914.3 566.8 573.9 181.9 60.9 2297.8

Canada 96.4 78.7 31.0 16.8 68.6 291.4

France 94.2 39.4 12.4 99.8 14.8 260.6

Russian Federation 124.7 365.2 111.3 34.0 35.6 670.8

United Kingdom 76.8 85.7 39.1 20.1 1.3 223.2

China 275.2 29.5 799.7 9.8 64.0 1178.3

India 113.3 27.1 185.3 4.1 15.6 345.3

Japan 248.7 68.9 112.2 52.2 22.8 504.8

Malaysia 23.9 25.6 3.2 - 1.7 54.4

Pakistan 17.0 19.0 2.7 0.4 5.6 44.8

Singapore 34.1 4.8 - - - 38.9

TOTAL WORLD 3636.6 2331.9 2578.4 598.8 595.4 9741.1

Energy Distribution Between Developed and Developing Countries

Although 80 percent of the world's popula-tion lies in the developing countries (a four-fold population increase in the past 25 years),their energy consumption amounts to only 40percent of the world total energy consump-tion. The high standards of living in thedeveloped countries are attributable to high-energy consumption levels. Also, the rapidpopulation growth in the developing coun-tries has kept the per capita energy consump-tion low compared with that of highly indus-trialized developed countries. The world average energy consumption per person is equivalentto 2.2 tonnes of coal. In industrialized countries, people use four to five times more than theworld average, and nine times more than the average for the developing countries. An Americanuses 32 times more commercial energy than an Indian.

Figure 1.4: Energy Distribution Between D evelopedand Developing Countries

Page 5: General Aspect of Energy Management and Energy Audit

1. Energy Scenario

5Bureau of Energy Efficiency

1.6 Indian Energy Scenario

Coal dominates the energy mix in India, contributing to 55% of the total primary energy pro-duction. Over the years, there has been a marked increase in the share of natural gas in prima-ry energy production from 10% in 1994 to 13% in 1999. There has been a decline in the shareof oil in primary energy production from 20% to 17% during the same period.

Energy Supply

Coal Supply

India has huge coal reserves, at least 84,396 million tonnes of proven recoverable reserves (atthe end of 2003). This amounts to almost 8.6% of the world reserves and it may last for about230 years at the current Reserve to Production (R/P) ratio. In contrast, the world's proven coalreserves are expected to last only for 192 years at the current R/P ratio.Reserves/Production (R/P) ratio- If the reserves remaining at the end of the year are dividedby the production in that year, the result is the length of time that the remaining reserves wouldlast if production were to continue at that level.

India is the fourth largest producer of coal and lignite in the world. Coal production is con-centrated in these states (Andhra Pradesh, Uttar Pradesh, Bihar, Madhya Pradesh, Maharashtra,Orissa, Jharkhand, West Bengal).

Oil Supply

Oil accounts for about 36 % of India'stotal energy consumption. India todayis one of the top ten oil-guzzlingnations in the world and will soonovertake Korea as the third largestconsumer of oil in Asia after Chinaand Japan. The country's annual crudeoil production is peaked at about 32million tonne as against the currentpeak demand of about 110 milliontonne. In the current scenario, India'soil consumption by end of 2007 isexpected to reach 136 milliontonne(MT), of which domestic production will be only 34 MT. India will have to pay an oil billof roughly $50 billion, assuming a weighted average price of $50 per barrel of crude. In 2003-04, against total export of $64 billion, oil imports accounted for $21 billion. India imports 70%of its crude needs mainly from gulf nations. The majority of India's roughly 5.4 billion barrelsin oil reserves are located in the Bombay High, upper Assam, Cambay, Krishna-Godavari. Interms of sector wise petroleum product consumption, transport accounts for 42% followed bydomestic and industry with 24% and 24% respectively. India spent more than Rs.1,10,000 croreon oil imports at the end of 2004.

Page 6: General Aspect of Energy Management and Energy Audit

1. Energy Scenario

6Bureau of Energy Efficiency

Natural Gas Supply

Natural gas accounts for about 8.9 per cent of energy consumption in the country. The currentdemand for natural gas is about 96 million cubic metres per day (mcmd) as against availabilityof 67 mcmd. By 2007, the demand is expected to be around 200 mcmd. Natural gas reservesare estimated at 660 billion cubic meters.

Electrical Energy Supply

The all India installed capacity of electric power generating sta-tions under utilities was 1,12,581 MW as on 31st May 2004,consisting of 28,860 MW- hydro, 77,931 MW - thermal and2,720 MW- nuclear and 1,869 MW- wind (Ministry of Power).The gross generation of power in the year 2002-2003 stood at531 billion units (kWh).

Nuclear Power Supply

Nuclear Power contributes to about 2.4 per cent of electricitygenerated in India. India has ten nuclear power reactors at five nuclear power stations produc-ing electricity. More nuclear reactors have also been approved for construction.

Hydro Power Supply

India is endowed with a vast and viable hydro potential for power generation of which only15% has been harnessed so far. The share of hydropower in the country's total generated unitshas steadily decreased and it presently stands at 25% as on 31st May 2004. It is assessed thatexploitable potential at 60% load factor is 84,000 MW.

Final Energy Consumption

Final energy consumption is the actual energy demand at the user end. This is the differencebetween primary energy consumption and the losses that takes place in transport, transmission& distribution and refinement. The actual final energy consumption (past and projected) isgiven in Table 1.2.

TABLE 1.2 DEMAND FOR COMMERCIAL ENERGY FOR FINAL

CONSUMPTION (BAU SCENARIO)

Source Units 1994-95 2001-02 2006-07 2011-12

Electricity Billion Units 289.36 480.08 712.67 1067.88

Coal Million Tonnes 76.67 109.01 134.99 173.47

Lignite Million Tonnes 4.85 11.69 16.02 19.70

Natural Gas Million Cubic Meters 9880 15730 18291 20853

Oil Products Million Tonnes 63.55 99.89 139.95 196.47

Source: Planning Commission BAU:_Business As Usual

Page 7: General Aspect of Energy Management and Energy Audit

1. Energy Scenario

7Bureau of Energy Efficiency

Sector Wise Energy Consumption in India

The major commercial energy consuming sectors in thecountry are classified as shown in the Figure 1.5. As seenfrom the figure, industry remains the biggest consumer ofcommercial energy and its share in the overall consumptionis 49%. (Reference year: 1999/2000)

1.7 Energy Needs of Growing Economy

Economic growth is desirable for developing countries, andenergy is essential for economic growth. However, the relationship between economic growthand increased energy demand is not always a straightforward linear one. For example, underpresent conditions, 6% increase in India's Gross Domestic Product (GDP) would impose anincreased demand of 9 % on its energy sector.

In this context, the ratio of energy demand to GDP is a useful indicator. A high ratio reflectsenergy dependence and a strong influence of energy on GDP growth. The developed countries,by focusing on energy efficiency and lower energy-intensive routes, maintain their energy toGDP ratios at values of less than 1. The ratios for developing countries are much higher.

India's Energy Needs

The plan outlay vis-à-vis share of energy is given in Figure 1.6. As seen from the Figure, 18.0%of the total five-year plan outlay is spent on the energy sector.

Per Capita Energy Consumption

The per capita energy consumption (see Figure 1.7) is too low for India as compared to devel-oped countries. It is just 4% of USA and 20% of the world average. The per capita consump-tion is likely to grow in India with growth in economy thus increasing the energy demand.

Figure 1.5 Sector Wise EnergyConsumption (1999-2000)

Figure 1.6 Expenditure Towards Energy Sector

PLANWISE OUTLAY

Page 8: General Aspect of Energy Management and Energy Audit

1. Energy Scenario

8Bureau of Energy Efficiency

Energy Intensity

Energy intensity is energy consumption per unit of GDP. Energy intensity indicates the devel-opment stage of the country. India's energy intensity is 3.7 times of Japan, 1.55 times of USA,1.47 times of Asia and 1.5 times of World average.

1.8 Long Term Energy Scenario for India

Coal

Coal is the predominant energy source for power production in India, generating approximate-ly 70% of total domestic electricity. Energy demand in India is expected to increase over thenext 10-15 years; although new oil and gas plants are planned, coal is expected to remain thedominant fuel for power generation. Despite significant increases in total installed capacity dur-ing the last decade, the gap between electricity supply and demand continues to increase. Theresulting shortfall has had a negative impact on industrial output and economic growth.However, to meet expected future demand, indigenous coal production will have to be greatlyexpanded. Production currently stands at around 290 Million tonnes per year, but coal demandis expected to more than double by 2010. Indian coal is typically of poor quality and as suchrequires to be beneficiated to improve the quality; Coal imports will also need to increase dra-matically to satisfy industrial and power generation requirements.

Oil

India's demand for petroleum products is likely to rise from 97.7 million tonnes in 2001-02 toaround 139.95 million tonnes in 2006-07, according to projections of the Tenth Five-Year Plan.The plan document puts compound annual growth rate (CAGR) at 3.6 % during the plan peri-od. Domestic crude oil production is likely to rise marginally from 32.03 million tonnes in2001-02 to 33.97 million tonnes by the end of the 10th plan period (2006-07). India's self suf-ficiency in oil has consistently declined from 60% in the 50s to 30% currently. Same is expect-

Figure 1.7 Per Capita Energy Consumption

Page 9: General Aspect of Energy Management and Energy Audit

1. Energy Scenario

9Bureau of Energy Efficiency

ed to go down to 8% by 2020. As shown inthe figure 1.8, around 92% of India's totaloil demand by 2020 has to be met byimports.

Natural Gas

India's natural gas production is likely torise from 86.56 million cmpd in 2002-03to 103.08 million cmpd in 2006-07. It ismainly based on the strength of a morethan doubling of production by privateoperators to 38.25 mm cmpd.

Electricity

India currently has apeak demand shortageof around 14% and anenergy deficit of 8.4%.Keeping this in viewand to maintain a GDP(gross domestic prod-uct) growth of 8% to10%, the Governmentof India has very pru-dently set a target of215,804 MW powergeneration capacity byMarch 2012 from thelevel of 100,010 MW ason March 2001, that is a capacity addition of 115,794 MW in the next 11 years (Table 1.3). In the area of nuclear power the objective is to achieve 20,000 MW of nuclear generation capac-ity by the year 2020.

Figure 1.8 India's Oil Balance

Figure 1.9 Proven Oil Reserve/Consumption (in Million Tonnes)India Vs World (At End 2002)

700

142700

97.7 3522.5

0

20000

40000

60000

80000

100000

120000

140000

160000

India 700 97.7

World 142700 3522.5

Proved Reserve Consumption

TABLE 1.3 INDIA'S PERSPECTIVE PLAN FOR POWER FOR ZERO DEFICIT

POWER BY 2011/12 (SOURCE TENTH AND ELEVENTH FIVE-YEAR

PLAN PROJECTIONS)

Thermal Gas / LNG / Nuclear Hydro Total(MW)(Coal) (MW) Diesel (MW) (MW) (MW)

Installed capacity as on Gas: 10,153March 2001 61,157 Diesel: 864 2720 25,116 100,010

Additional capacity 53,333 20,408 9380 32,673 115,794(2001-2012)

Total capacity as on 114,490 31,425 12,100 57,789 215,804March 2012 (53.0%) (14.6%) (5.6%) (26.8%)

Page 10: General Aspect of Energy Management and Energy Audit

1. Energy Scenario

10Bureau of Energy Efficiency

1.9 Energy Pricing in India

Price of energy does not reflect true cost to society. The basic assumption underlying efficien-cy of market place does not hold in our economy, since energy prices are undervalued and ener-gy wastages are not taken seriously. Pricing practices in India like many other developing coun-tries are influenced by political, social and economic compulsions at the state and central level.More often than not, this has been the foundation for energy sector policies in India. The Indianenergy sector offers many examples of cross subsidies e.g., diesel, LPG and kerosene beingsubsidised by petrol, petroleum products for industrial usage and industrial, and commercialconsumers of electricity subsidising the agricultural and domestic consumers.

Coal

Grade wise basic price of coal at the pithead excluding statutory levies for run-of-mine (ROM)coal are fixed by Coal India Ltd from time to time. The pithead price of coal in India comparesfavourably with price of imported coal. In spite of this, industries still import coal due its high-er calorific value and low ash content.

Oil

As part of the energy sector reforms, the government has attempted to bring prices for many ofthe petroleum products (naphtha, furnace oil, LSHS, LDO and bitumen) in line with interna-tional prices. The most important achievement has been the linking of diesel prices to interna-tional prices and a reduction in subsidy. However, LPG and kerosene, consumed mainly bydomestic sectors, continue to be heavily subsidised. Subsidies and cross-subsidies have result-ed in serious distortions in prices, as they do not reflect economic costs in many cases.

Natural Gas

The government has been the sole authority for fixing the price of natural gas in the country. Ithas also been taking decisions on the allocation of gas to various competing consumers. The gasprices varies from Rs 5 to Rs.15 per cubic metre.

Electricity

Electricity tariffs in India are structured in a relatively simple manner. While high tension con-sumers are charged based on both demand (kVA) and energy (kWh), the low-tension (LT) con-sumer pays only for the energy consumed (kWh) as per tariff system in most of the electricityboards. The price per kWh varies significantly across States as well as customer segments with-in a State. Tariffs in India have been modified to consider the time of usage and voltage levelof supply. In addition to the base tariffs, some State Electricity Boards have additional recov-ery from customers in form of fuel surcharges, electricity duties and taxes. For example, for anindustrial consumer the demand charges may vary from Rs. 150 to Rs. 300 per kVA, whereasthe energy charges may vary anywhere between Rs. 2 to Rs. 5 per kWh. As for the tariff adjust-ment mechanism, even when some States have regulatory commissions for tariff review, thedecisions to effect changes are still political and there is no automatic adjustment mechanism,which can ensure recovery of costs for the electricity boards.

Page 11: General Aspect of Energy Management and Energy Audit

1. Energy Scenario

11Bureau of Energy Efficiency

1.10 Energy Sector Reforms

Since the initiation of economic reforms in India in 1991, there has been a growing acceptanceof the need for deepening these reforms in several sectors of the economy, which were essen-tially in the hands of the government for several decades. It is now been realized that if sub-stance has to be provided to macroeconomic policy reform, then it must be based on reformsthat concern the functioning of several critical sectors of the economy, among which the infra-structure sectors in general and the energy sector in particular, are paramount.

Coal

The government has recognized the need for new coal policy initiatives and for rationalizationof the legal and regulatory framework that would govern the future development of this indus-try. One of the key reforms is that the government has allowed importing of coal to meet ourrequirements. Private sector has been allowed to extract coal for captive use only. Furtherreforms are contemplated for which the Coal Mines Nationalization Act needs to be amendedfor which the Bill is awaiting approval of the Parliament.

The ultimate objective of some of the ongoing measures and others under consideration isto see that a competitive environment is created for the functioning of various entities in thisindustry. This would not only bring about gains in efficiency but also effect cost reduction,which would consequently ensure supply of coal on a larger scale at lower prices. Competitionwould also have the desirable effect of bringing in new technology, for which there is an urgentand overdue need since the coal industry has suffered a prolonged period of stagnation in tech-nological innovation.

Oil and Natural Gas

Since 1993, private investors have been allowed to import and market liquefied petroleum gas(LPG) and kerosene freely; private investment is also been allowed in lubricants, which are notsubject to price controls. Prices for naphtha and some other fuels have been liberalized. In 1997the government introduced the New Exploration Licensing Policy (NELP) in an effort to pro-mote investment in the exploration and production of domestic oil and gas. In addition, therefining sector has been opened to private and foreign investors in order to reduce imports ofrefined products and to encourage investment in downstream pipelines. Attractive terms arebeing offered to investors for the construction of liquefied natural gas (LNG) import facilities.

Electricity

Following the enactment of the Electricity Regulatory Commission Legislation, the CentralElectricity Regulatory Commission (CERC) was set up, with the main objective of regulatingthe Central power generation utilities. State level regulatory bodies have also been set up to settariffs and promote competition. Private investments in power generation were also allowed.The State SEBs were asked to switch over to separate Generation, Transmission andDistribution corporations. There are plans to link all SEB grids and form a unified nationalpower grid.

Electricity Act, 2003

The government has enacted Electricity Act, 2003 which seeks to bring about a qualitativetransformation of the electricity sector. The Act seeks to create liberal framework of develop-

Page 12: General Aspect of Energy Management and Energy Audit

1. Energy Scenario

12Bureau of Energy Efficiency

ment for the power sector by distancing Government from regulation. It replaces the three exist-ing legislations, namely, Indian Electricity Act, 1910, the Electricity (Supply) Act, 1948 andthe Electricity Regulatory Commissions Act, 1998. The objectives of the Act are "to consoli-date the laws relating to generation, transmission, distribution, trading and use of electricity andgenerally for taking measures conducive to development of electricity industry, promotingcompetition therein, protecting interest of consumers and supply of electricity to all areas, ratio-nalization of electricity tariff, ensuring transparent policies regarding subsidies, promotion ofefficient and environmentally benign policies, constitution of Central Electricity Authority,Regulatory Commissions and establishment of Appellate Tribunal and for matters connectedtherewith or incidental thereto."

The salient features of the Electricity Act, 2003 are:

i) The Central Government to prepare a National Electricity Policy in consultation with StateGovernments. (Section 3)ii) Thrust to complete the rural electrification and provide for management of rural distributionby Panchayats, Cooperative Societies, non-Government organisations, franchisees etc.(Sections 4, 5 & 6)iii) Provision for licence free generation and distribution in the rural areas. (Section 14)iv) Generation being delicensed and captive generation being freely permitted. Hydro projectswould, however, need clearance from the Central Electricity Authority. (Sections 7, 8 & 9)v) Transmission Utility at the Central as well as State level, to be a Government company - withresponsibility for planned and coordinated development of transmission network. (Sections 38& 39)vi) Provision for private licensees in transmission and entry in distribution through an indepen-dent network, (Section 14)vii) Open access in transmission from the outset. (Sections 38-40)viii) Open access in distribution to be introduced in phases with surcharge for current level ofcross subsidy to be gradually phased out along with cross subsidies and obligation to supply.SERCs to frame regulations within one year regarding phasing of open access. (Section 42)ix) Distribution licensees would be free to undertake generation and generating companieswould be free to take up distribution businesses. (Sections 7, 12)x) The State Electricity Regulatory Commission is a mandatory requirement. (Section 82)xi) Provision for payment of subsidy through budget. (Section 65)xii) Trading, a distinct activity is being recognised with the safeguard of the RegulatoryCommissions being authorised to fix ceilings on trading margins, if necessary. (Sections 12, 79& 86)xiii) Provision for reorganisation or continuance of SEBs. (Sections 131 & 172)xiv) Metering of all electricity supplied made mandatory. (Section 55)xv) An Appellate Tribunal to hear appeals against the decision of the CERC andSERCs. (Section 111)xvi) Provisions relating to theft of electricity made more stringent. (Section 135-150)xvii) Provisions safeguarding consumer interests. (Sections 57-59, 166) Ombudsman scheme(Section 42) for consumers grievance redressal.

Page 13: General Aspect of Energy Management and Energy Audit

1. Energy Scenario

13Bureau of Energy Efficiency

1.11 Energy and Environment

The usage of energy resources in industryleads to environmental damages by pollutingthe atmosphere. Few of examples of air pollu-tion are sulphur dioxide (SO2), nitrous oxide(NOX) and carbon monoxide (CO) emissionsfrom boilers and furnaces, chloro-fluro car-bons (CFC) emissions from refrigerants use,etc. In chemical and fertilizers industries,toxic gases are released. Cement plants andpower plants spew out particulate matter.Typical inputs, outputs, and emissions for atypical industrial process are shown in Figure1.10.

Air Pollution

A variety of air pollutants have known or suspected harmful effects on human health and theenvironment. These air pollutants are basically the products of combustion from fossil fuel use.Air pollutants from these sources may not only create problems near to these sources but alsocan cause problems far away. Air pollutants can travel long distances, chemically react in theatmosphere to produce secondary pollutants such as acid rain or ozone.

Evolutionary Trends in Pollution Problems

In both developed and rapidly industrialising countries, the major historic air pollutionproblem has typically been high levels of smoke and SO2 arising from the combustion of sul-phur-containing fossil fuels such as coal for domestic and industrial purposes.

Smogs resulting from the combined effects of black smoke, sulphate / acid aerosol and foghave been seen in European cities until few decades ago and still occur in many cities in devel-oping world. In developed countries, this problem has significantly reduced over recent decadesas a result of changing fuel-use patterns; the increasing use of cleaner fuels such as natural gas,and the implementation of effective smoke and emission control policies.

In both developed and developing countries, the major threat to clean air is now posed bytraffic emissions. Petrol- and diesel-engined motor vehicles emit a wide variety of pollutants,principally carbon monoxide (CO), oxides of nitrogen (NOx), volatile organic compounds(VOCs) and particulates, which have an increasing impact on urban air quality.

In addition, photochemical reactions resulting from the action of sunlight on NO2 and VOCsfrom vehicles leads to the formation of ozone, a secondary long-range pollutant, which impactsin rural areas often far from the original emission site. Acid rain is another long-range pollutantinfluenced by vehicle NOx emissions.

Industrial and domestic pollutant sources, together with their impact on air quality, tend tobe steady-state or improving over time. However, traffic pollution problems are worseningworld-wide. The problem may be particularly severe in developing countries with dramaticallyincreasing vehicle population, infrastructural limitations, poor engine/emission control tech-nologies and limited provision for maintenance or vehicle regulation.

Figure 1.10 Inputs & Outputs of Process

Page 14: General Aspect of Energy Management and Energy Audit

The principle pollutants produced by industrial, domestic and traffic sources are sulphurdioxide, nitrogen oxides, particulate matter, carbon monoxide, ozone, hydrocarbons, benzene,1,3-butadiene, toxic organic micropollutants, lead and heavy metals.

Brief introduction to the principal pollutants are as follows:

Sulphur dioxide is a corrosive acid gas, which combines with watervapour in the atmosphere to produce acid rain. Both wet and dry deposi-tion have been implicated in the damage and destruction of vegetationand in the degradation of soils, building materials and watercourses. SO2

in ambient air is also associated with asthma and chronic bronchitis. Theprincipal source of this gas is power stations and industries burning fos-sil fuels, which contain sulphur.

Nitrogen oxides are formed during high temperature combustionprocesses from the oxidation of nitrogen in the air or fuel. The principalsource of nitrogen oxides - nitric oxide (NO) and nitrogen dioxide (NO2),collectively known as NOx - is road traffic. NO and NO2 concentrationsare greatest in urban areas where traffic is heaviest. Other importantsources are power stations and industrial processes.

Nitrogen oxides are released into the atmosphere mainly in the formof NO, which is then readily oxidised to NO2 by reaction with ozone.

Elevated levels of NOx occur in urban environments under stable meteorological conditions,when the air mass is unable to disperse.

Nitrogen dioxide has a variety of environmental and health impacts. It irritates the respira-tory system and may worsen asthma and increase susceptibility to infections. In the presence ofsunlight, it reacts with hydrocarbons to produce photochemical pollutants such as ozone.

Nitrogen oxides combine with water vapour to form nitric acid. This nitric acid is in turnremoved from the atmosphere by direct deposition to the ground, or transfer to aqueous droplets(e.g. cloud or rainwater), thereby contributing to acid deposition.

Acidification from SO2 and NOx

Acidification of water bodies and soils, and the consequent impact on agriculture, forestry andfisheries are the result of the re-deposition of acidifying compounds resulting principally fromthe oxidation of primary SO2 and NO2 emissions from fossil fuel combustion. Deposition maybe by either wet or dry processes, and acid deposition studies often need to examine both ofthese acidification routes.

Airborne particulate matter varies widely in its physical and chem-ical composition, source and particle size. PM10 particles (the fraction ofparticulates in air of very small size (<10 µm)) are of major current con-cern, as they are small enough to penetrate deep into the lungs and sopotentially pose significant health risks. In addition, they may carry sur-face-absorbed carcinogenic compounds into the lungs. Larger particles,meanwhile, are not readily inhaled, and are removed relatively efficient-ly from the air by settling.

A major source of fine primary particles are combustion processes, in particular diesel com-

1. Energy Scenario

14Bureau of Energy Efficiency

Page 15: General Aspect of Energy Management and Energy Audit

bustion, where transport of hot exhaust vapour into a cooler exhaust pipe can lead to sponta-neous nucleation of "carbon" particles before emission. Secondary particles are typicallyformed when low volatility products are generated in the atmosphere, for example the oxida-tion of sulphur dioxide to sulphuric acid. The atmospheric lifetime of particulate matter isstrongly related to particle size, but may be as long as 10 days for particles of about 1mm indiameter.

Concern about the potential health impacts of PM10 has increased very rapidly over recentyears. Increasingly, attention has been turning towards monitoring of the smaller particle frac-tion PM2.5 capable of penetrating deepest into the lungs, or to even smaller size fractions or totalparticle numbers.

Carbon monoxide (CO) is a toxic gas, which is emitted into theatmosphere as a result of combustion processes, and from oxidation ofhydrocarbons and other organic compounds. In urban areas, CO is pro-duced almost entirely (90%) from road traffic emissions. CO at levelsfound in ambient air may reduce the oxygen-carrying capacity of theblood. It survives in the atmosphere for a period of approximately 1month and finally gets oxidised to carbon dioxide (CO2).

Ground-level ozone (O3), unlike other primary pollutants mentionedabove, is not emitted directly into the atmosphere, but is a secondary pol-lutant produced by reaction between nitrogen dioxide (NO2), hydrocar-bons and sunlight. Ozone can irritate the eyes and air passages causingbreathing difficulties and may increase susceptibility to infection. It is ahighly reactive chemical, capable of attacking surfaces, fabrics and rub-ber materials. Ozone is also toxic to some crops, vegetation and trees.

Whereas nitrogen dioxide (NO2) participates in the formation ofozone, nitrogen oxide (NO) destroys ozone to form oxygen (O2) and nitrogen dioxide (NO2).For this reason, ozone levels are not as high in urban areas (where high levels of NO are emit-ted from vehicles) as in rural areas. As the nitrogen oxides and hydrocarbons are transported outof urban areas, the ozone-destroying NO is oxidised to NO2, which participates in ozone for-mation.

Hydrocarbons

There are two main groups of hydrocarbons of concern: volatile organic compounds (VOCs)and polycyclic aromatic hydrocarbons (PAHs). VOCs are released in vehicle exhaust gaseseither as unburned fuels or as combustion products, and are also emitted by the evaporation ofsolvents and motor fuels. Benzene and 1,3-butadiene are of particular concern, as they are

known carcinogens. Other VOCs are important because of the role theyplay in the photochemical formation of ozone in the atmosphere.

Benzene is an aromatic VOC, which is a minor constituent of petrol(about 2% by volume). The main sources of benzene in the atmosphereare the distribution and combustion of petrol. Of these, combustion bypetrol vehicles is the single biggest source (70% of total emissions)

1. Energy Scenario

15Bureau of Energy Efficiency

Page 16: General Aspect of Energy Management and Energy Audit

1. Energy Scenario

16Bureau of Energy Efficiency

whilst the refining, distribution and evaporation of petrol from vehicles accounts for approxi-mately a further 10% of total emissions. Benzene is emitted in vehicle exhaust not only asunburnt fuel but also as a product of the decomposition of other aromatic compounds. Benzeneis a known human carcinogen.

1,3-butadiene, like benzene, is a VOC emitted into the atmosphereprincipally from fuel combustion of petrol and diesel vehicles. Unlike ben-zene, however, it is not a constituent of the fuel but is produced by the com-bustion of olefins. 1,3-butadiene is also an important chemical in certainindustrial processes, particularly the manufacture of synthetic rubber. It ishandled in bulk at a small number of industrial locations. Other than in the

vicinity of such locations, the dominant source of 1,3-butadiene in the atmosphere are the motorvehicles. 1,3 Butadiene is also a known, potent, human carcinogen.

TOMPs (Toxic Organic Micropollutants) are produced by the incompletecombustion of fuels. They comprise a complex range of chemicals some ofwhich, although they are emitted in very small quantities, are highly toxicor and carcinogenic. Compounds in this category include: · PAHs (PolyAromatic Hydrocarbons)· PCBs (PolyChlorinated Biphenyls)· Dioxins· Furans

Heavy Metals and Lead

Particulate metals in air result from activities such as fossil fuel com-bustion (including vehicles), metal processing industries and waste inciner-ation. There are currently no emission standards for metals other than lead.Lead is a cumulative poison to the central nervous system, particularlydetrimental to the mental development of children.

Lead is the most widely used non-ferrous metal and has a large numberof industrial applications. Its single largest industrial use worldwide is in the manufacture ofbatteries and it is also used in paints, glazes, alloys, radiation shielding, tank lining and piping.

As tetraethyl lead, it has been used for many years as an additive in petrol; with the increas-ing use of unleaded petrol, however, emissions and concentrations in air have reduced steadilyin recent years.

Climatic Change

Human activities, particularly the combustion of fossil fuels, have made the blanket of green-house gases (water vapour, carbon dioxide, methane, ozone etc.) around the earth thicker. Theresulting increase in global temperature is altering the complex web of systems that allow lifeto thrive on earth such as rainfall, wind patterns, ocean currents and distribution of plant andanimal species.

Greenhouse Effect and the Carbon Cycle

Life on earth is made possible by energy from the sun, which arrives mainly in the form of vis-

Page 17: General Aspect of Energy Management and Energy Audit

1. Energy Scenario

17Bureau of Energy Efficiency

ible light. About 30 percent of the sunlight is scattered back into space by outer atmosphere andthe balance 70 percent reaches the earth's surface, which reflects it in form of infrared radiation.The escape of slow moving infrared radiation is delayed by the green house gases. A thickerblanket of greenhouse gases traps more infrared radiation and increase the earth's temperature(Refer Figure 1.11).

Greenhouse gases makeup only 1 percent of the atmosphere, but they act as a blanketaround the earth, or like a glass roof of a greenhouse and keep the earth 30 degrees warmer thanit would be otherwise - without greenhouse gases, earth would be too cold to live. Human activ-ities that are responsible for making the greenhouse layer thicker are emissions of carbon diox-ide from the combustion of coal, oil and natural gas; by additional methane and nitrous oxidefrom farming activities and changes in land use; and by several man made gases that have along life in the atmosphere. The increase in greenhouse gases is happening at an alarming rate. If greenhouse gases emis-sions continue to grow at current rates, it is almost certain that the atmospheric levels of carbondioxide will increase twice or thrice from pre-industrial levels during the 21st century.

Even a small increase in earth's temperature will be accompanied by changes in climate-such as cloud cover, precipitation, wind patterns and duration of seasons. In an already highlycrowded and stressed earth, millions of people depend on weather patterns, such as monsoonrains, to continue as they have in the past. Even minimum changes will be disruptive and diffi-cult.

Carbon dioxide is responsible for 60 percent of the "enhanced greenhouse effect". Humansare burning coal, oil and natural gas at a rate that is much faster than the rate at which these fos-sil fuels were created. This is releasing the carbon stored in the fuels into the atmosphere andupsetting the carbon cycle (a precise balanced system by which carbon is exchanged between

Figure 1.11 The Greenhouse Effect

Page 18: General Aspect of Energy Management and Energy Audit

1. Energy Scenario

18Bureau of Energy Efficiency

the air, the oceans and land vegetation taking place over millions of years). Currently, carbondioxide levels in the atmospheric are rising by over 10 percent every 20 years.

Current Evidence of Climatic Change

Cyclones, storm, hurricanes are occurring more frequently and floods and draughts are moreintense than before. This increase in extreme weather events cannot be explained away as ran-dom events.

This trend toward more powerful storms and hotter, longer dry periods is predicted by com-puter models. Warmer temperatures mean greater evaporation, and a warmer atmosphere is ableto hold more moisture and hence there is more water aloft that can fall as precipitation.Similarly, dry regions are prone to lose still more moisture if the weather is hotter and hencethis leads to more severe droughts and desertification.

Future Effects

Even the minimum predicted shifts in climate for the 21st century are likely to be significantand disruptive. Predictions of future climatic changes are wide-ranging. The global tempera-ture may climb from 1.4 to 5.8 degrees C; the sea level may rise from 9 to 88 cm. Thus, increas-es in sea level this century are expected to range from significant to catastrophic. This uncer-tainty reflects the complexity, interrelatedness, and sensitivity of the natural systems that makeup the climate.

Severe Storms and Flooding

The minimum warming forecast for the next 100 years is more than twice the 0.6 degree Cincrease that has occurred since 1900 and that earlier increase is already having marked conse-quences. Extreme weather events, as predicted by computer models, are striking more often andcan be expected to intensify and become still more frequent. A future of more severe storms andfloods along the world's increasingly crowded coastlines is likely.

Food Shortages

Although regional and local effects may differ widely, a general reduction is expected in poten-tial crop yields in most tropical and sub-tropical regions. Mid-continental areas such as theUnited States' "grain belt" and vast areas of Asia are likely to become dry. Sub-Saharan Africawhere dryland agriculture relies solely on rain, the yields would decrease dramatically evenwith minimum increase in temperature. Such changes could cause disruptions in food supply ina world is already afflicted with food shortages and famines.

Dwindling Freshwater supply

Salt-water intrusion from rising sea levels will reduce the quality and quantity of freshwatersupplies. This is a major concern, since billions of people on earth already lack access to fresh-water. Higher ocean levels already are contaminating underground water sources in many partsof the world.

Loss of Biodiversity

Most of the world's endangered species (some 25 per cent of mammals and 12 per cent of birds)may become extinct over the next few decades as warmer conditions alter the forests, wetlands,

Page 19: General Aspect of Energy Management and Energy Audit

and rangelands they depend on, and human development blocks them from migrating else-where.

Increased Diseases

Higher temperatures are expected to expand the range of some dangerous "vector-borne" dis-eases, such as malaria, which already kills 1 million people annually, most of them children.

A World Under Stress

Ongoing environmentally damaging activities such as overgrazing, deforestation, and denudedagricultural soils means that nature will be more vulnerable than previously to changes in cli-mate.

Similarly, the world's vast human population, much of it poor, is vulnerable to climatestress. Millions live in dangerous places such as floodplains or in slums around the big cities ofthe developing world. Often there is nowhere else for population to move. In the distant past,man and his ancestors migrated in response to changes in habitat. There will be much less roomfor migration in future.

Global warming almost certainly will be unfair. The industrialized countries of NorthAmerica and Western Europe, and other countries such as Japan, are responsible for the vastamount of past and current greenhouse-gas emissions. These emissions are incurred for the highstandards of living enjoyed by the people in those countries.

Yet those to suffer most from climate change will be in the developing world. They havefewer resources for coping with storms, with floods, with droughts, with disease outbreaks, andwith disruptions to food and water supplies. They are eager for economic development them-selves, but may find that this already difficult process has become more difficult because of cli-mate change. The poorer nations of the world have done almost nothing to cause global warm-ing yet is most exposed to its effects.

Acid Rain

Acid rain is caused by release of SOX and NOX from combustion of fossil fuels, which then mix

1. Energy Scenario

19Bureau of Energy Efficiency

Figure 1.12

Page 20: General Aspect of Energy Management and Energy Audit

1. Energy Scenario

20Bureau of Energy Efficiency

with water vapour in atmosphere to form sulphuric and nitric acids respectively (Refer Figure1.12). The effects of acid rain are as follows:• Acidification of lakes, streams, and soils• Direct and indirect effects (release of metals, For example: Aluminum which washes away

plant nutrients)• Killing of wildlife (trees, crops, aquatic plants, and animals)• Decay of building materials and paints, statues, and sculptures • Health problems (respiratory, burning- skin and eyes)

1.12 Energy Security

The basic aim of energy security for a nation is to reduce its dependency on the imported ener-gy sources for its economic growth.

India will continue to experience an energy supply shortfall throughout the forecast period.This gap has widened since 1985, when the country became a net importer of coal. India hasbeen unable to raise its oil production substantially in the 1990s. Rising oil demand of close to10 percent per year has led to sizable oil import bills. In addition, the government subsidisesrefined oil product prices, thus compounding the overall monetary loss to the government.

Imports of oil and coal have been increasing at rates of 7% and 16% per annum respective-ly during the period 1991-99. The dependence on energy imports is projected to increase in thefuture. Estimates indicate that oil imports will meet 75% of total oil consumption requirementsand coal imports will meet 22% of total coal consumption requirements in 2006. The importsof gas and LNG (liquefied natural gas) are likely to increase in the coming years. This energyimport dependence implies vulnerability to external price shocks and supply fluctuations, whichthreaten the energy security of the country.

Increasing dependence on oil imports means reliance on imports from the Middle East, aregion susceptible to disturbances and consequent disruptions of oil supplies. This calls fordiversification of sources of oil imports. The need to deal with oil price fluctuations also neces-sitates measures to be taken to reduce the oil dependence of the economy, possibly through fis-cal measures to reduce demand, and by developing alternatives to oil, such as natural gas andrenewable energy.

Some of the strategies that can be used to meet future challenges to their energy security are• Building stockpiles • Diversification of energy supply sources• Increased capacity of fuel switching• Demand restraint, • Development of renewable energy sources. • Energy efficiency • Sustainable development

Although all these options are feasible, their implementation will take time. Also, for coun-tries like India, reliance on stockpiles would tend to be slow because of resource constraints.Besides, the market is not sophisticated enough or the monitoring agencies experienced enoughto predict the supply situation in time to take necessary action. Insufficient storage capacity isanother cause for worry and needs to be augmented, if India has to increase its energy stock-

Page 21: General Aspect of Energy Management and Energy Audit

1. Energy Scenario

21Bureau of Energy Efficiency

pile. However, out of all these options, the simplest and the most easily attainable is reducing

demand through persistent energy conservation efforts.

1.13 Energy Conservation and its Importance

Coal and other fossil fuels, which have taken threemillion years to form, are likely to deplete soon. In thelast two hundred years, we have consumed 60% of allresources. For sustainable development, we need toadopt energy efficiency measures.Today, 85% of primary energy comes from non-renewable, and fossil sources (coal, oil, etc.). Thesereserves are continually diminishing with increasingconsumption and will not exist for future generations(see Figure 1.13).

What is Energy Conservation?

Energy Conservation and Energy Efficiency are separate,but related concepts. Energy conservation is achievedwhen growth of energy consumption is reduced, measuredin physical terms. Energy Conservation can, therefore, bethe result of several processes or developments, such asproductivity increase or technological progress. On theother hand Energy efficiency is achieved when energyintensity in a specific product, process or area of produc-tion or consumption is reduced without affecting output,consumption or comfort levels. Promotion of energy effi-ciency will contribute to energy conservation and is there-fore an integral part of energy conservation promotionalpolicies.

Energy efficiency is often viewed as a resource option like coal, oil or natural gas. It pro-vides additional economic value by preserving the resource base and reducing pollution. Forexample, replacing traditional light bulbs with Compact Fluorescent Lamps (CFLs) means youwill use only 1/4th of the energy to light a room. Pollution levels also reduce by the sameamount (refer Figure 1.14).

Nature sets some basic limits on how efficiently energy can be used, but in most cases ourproducts and manufacturing processes are still a long way from operating at this theoreticallimit. Very simply, energy efficiency means using less energy to perform the same function.Although, energy efficiency has been in practice ever since the first oil crisis in 1973, it hastoday assumed even more importance because of being the most cost-effective and reliablemeans of mitigating the global climatic change. Recognition of that potential has led to highexpectations for the control of future CO2 emissions through even more energy efficiencyimprovements than have occurred in the past. The industrial sector accounts for some 41 percent of global primary energy demand and approximately the same share of CO2 emissions. The

Figure 1.13

Figure 1.14

Page 22: General Aspect of Energy Management and Energy Audit

1. Energy Scenario

22Bureau of Energy Efficiency

benefits of Energy conservation for various players are given in Figure 1.15.

1.14 Energy Strategy for the Future

The energy strategy for the future could be classified into immediate, medium-term and long-term strategy. The various components of these strategies are listed below:

Immediate-term strategy:

• Rationalizing the tariff structure of various energy products.• Optimum utilization of existing assets• Efficiency in production systems and reduction in distribution losses, including those in

traditional energy sources.• Promoting R&D, transfer and use of technologies and practices for environmentally sound

energy systems, including new and renewable energy sources.

Medium-term strategy:

• Demand management through greater conservation of energy, optimum fuel mix, structur-al changes in the economy, an appropriate model mix in the transport sector, i.e. greaterdependence on rail than on road for the movement of goods and passengers and a shiftaway from private modes to public modes for passenger transport; changes in design of dif-ferent products to reduce the material intensity of those products, recycling, etc.

• There is need to shift to less energy-intensive modes of transport. This would include mea-sures to improve the transport infrastructure viz. roads, better design of vehicles, use ofcompressed natural gas (CNG) and synthetic fuel, etc. Similarly, better urban planningwould also reduce the demand for energy use in the transport sector.

• There is need to move away from non-renewable to renewable energy sources viz. solar,wind, biomass energy, etc.

Figure 1.15

Page 23: General Aspect of Energy Management and Energy Audit

1. Energy Scenario

23Bureau of Energy Efficiency

Long-term strategy:

Efficient generation of energy resources• Efficient production of coal, oil and natural gas • Reduction of natural gas flaring

Improving energy infrastructure• Building new refineries• Creation of urban gas transmission and distribution network• Maximizing efficiency of rail transport of coal production.• Building new coal and gas fired power stations.

Enhancing energy efficiency• Improving energy efficiency in accordance with national, socio-economic, and environ-

mental priorities • Promoting of energy efficiency and emission standards • Labeling programmes for products and adoption of energy efficient technologies in large

industries

Deregulation and privatization of energy sector• Reducing cross subsidies on oil products and electricity tariffs• Decontrolling coal prices and making natural gas prices competitive• Privatization of oil, coal and power sectors for improved efficiency.

Investment legislation to attract foreign investments.• Streamlining approval process for attracting private sector participation in power gener-

ation, transmission and distribution .

1.15 The Energy Conservation Act, 2001 and its Features

Policy Framework - Energy Conservation Act - 2001

With the background of high energy saving potential and its benefits, bridging the gap betweendemand and supply, reducing environmental emissions through energy saving, and to effec-tively overcome the barrier, the Government of India has enacted the Energy Conservation Act- 2001. The Act provides the much-needed legal framework and institutional arrangement forembarking on an energy efficiency drive.

Under the provisions of the Act, Bureau of Energy Efficiency has been established witheffect from 1st March 2002 by merging erstwhile Energy Management Centre of Ministry ofPower. The Bureau would be responsible for implementation of policy programmes and coor-dination of implementation of energy conservation activities.

Important features of the Energy Conservation Act are:

Standards and Labeling

Standards and Labeling (S & L) has been identified as a key activity for energy efficiencyimprovement. The S & L program, when in place would ensure that only energy efficient equip-ment and appliance would be made available to the consumers.

Page 24: General Aspect of Energy Management and Energy Audit

1. Energy Scenario

24Bureau of Energy Efficiency

The main provision of EC act on Standards and Labeling are:

• Evolve minimum energy consumption and performance standards for notified equip-ment and appliances.

• Prohibit manufacture, sale and import of such equipment, which does not conform to thestandards.

• Introduce a mandatory labeling scheme for notified equipment appliances to enable con-sumers to make informed choices

• Disseminate information on the benefits to consumers

Designated Consumers

The main provisions of the EC Act on designated consumers are:• The government would notify energy intensive industries and other establishments as

designated consumers;• Schedule to the Act provides list of designated consumers which covered basically ener-

gy intensive industries, Railways, Port Trust, Transport Sector, Power Stations,Transmission & Distribution Companies and Commercial buildings or establishments;

• The designated consumer to get an energy audit conducted by an accredited energy audi-tor;

• Energy managers with prescribed qualification are required to be appointed or designat-ed by the designated consumers;

• Designated consumers would comply with norms and standards of energy consumptionas prescribed by the central government.

Certification of Energy Managers and Accreditation of Energy Auditing Firms

The main activities in this regard as envisaged in the Act are:A cadre of professionally qualified energy managers and auditors with expertise in policy

analysis, project management, financing and implementation of energy efficiency projectswould be developed through Certification and Accreditation programme. BEE to design train-ing modules, and conduct a National level examination for certification of energy managers andenergy auditors.

Energy Conservation Building Codes:

The main provisions of the EC Act on Energy Conservation Building Codes are:• The BEE would prepare guidelines for Energy Conservation Building Codes (ECBC);• These would be notified to suit local climate conditions or other compelling factors by

the respective states for commercial buildings erected after the rules relating to energyconservation building codes have been notified. In addition, these buildings should havea connected load of 500 kW or contract demand of 600 kVA and above and are intend-ed to be used for commercial purposes;

• Energy audit of specific designated commercial building consumers would also be pre-scribed.

Central Energy Conservation Fund:

The EC Act provisions in this case are:

Page 25: General Aspect of Energy Management and Energy Audit

1. Energy Scenario

25Bureau of Energy Efficiency

• The fund would be set up at the centre to develop the delivery mechanism for large-scaleadoption of energy efficiency services such as performance contracting and promotionof energy service companies. The fund is expected to give a thrust to R & D and demon-stration in order to boost market penetration of efficient equipment and appliances. Itwould support the creation of facilities for testing and development and to promote con-sumer awareness.

Bureau of Energy Efficiency (BEE):

• The mission of Bureau of Energy Efficiency is to institutionalize energy efficiency ser-vices, enable delivery mechanisms in the country and provide leadership to energy effi-ciency in all sectors of economy. The primary objective would be to reduce energy inten-sity in the Indian Economy.

• The general superintendence, directions and management of the affairs of the Bureau isvested in the Governing Council with 26 members. The Council is headed by UnionMinister of Power and consists of members represented by Secretaries of various lineMinistries, the CEOs of technical agencies under the Ministries, members representingequipment and appliance manufacturers, industry, architects, consumers and five powerregions representing the states. The Director General of the Bureau shall be the ex-offi-cio member-secretary of the Council.

• The BEE will be initially supported by the Central Government by way of grants throughbudget, it will, however, in a period of 5-7 years become self-sufficient. It would beauthorized to collect appropriate fee in discharge of its functions assigned to it. The BEEwill also use the Central Energy Conservation Fund and other funds raised from varioussources for innovative financing of energy efficiency projects in order to promote ener-gy efficient investment.

Role of Bureau of Energy Efficiency

• The role of BEE would be to prepare standards and labels of appliances and equipment,develop a list of designated consumers, specify certification and accreditation procedure,prepare building codes, maintain Central EC fund and undertake promotional activitiesin co-ordination with center and state level agencies. The role would include develop-ment of Energy service companies (ESCOs), transforming the market for energy effi-ciency and create awareness through measures including clearing house.

Role of Central and State Governments:

The following role of Central and State Government is envisaged in the Act

• Central - to notify rules and regulations under various provisions of the Act, provide ini-tial financial assistance to BEE and EC fund, Coordinate with various StateGovernments for notification, enforcement, penalties and adjudication.

• State - to amend energy conservation building codes to suit the regional and local cli-matic condition, to designate state level agency to coordinate, regulate and enforce pro-visions of the Act and constitute a State Energy Conservation Fund for promotion ofenergy efficiency.

Page 26: General Aspect of Energy Management and Energy Audit

1. Energy Scenario

26Bureau of Energy Efficiency

Enforcement through Self-Regulation:

E.C. Act would require inspection of only two items. The following procedure of self-regula-tion is proposed to be adopted for verifying areas that require inspection of only two items thatrequire inspection.

• The certification of energy consumption norms and standards of production process bythe Accredited Energy Auditors is a way to enforce effective energy efficiency inDesignated Consumers.

• For energy performance and standards, manufacturer's declared values would bechecked in Accredited Laboratories by drawing sample from market. Any manufactureror consumer or consumer association can challenge the values of the other manufactur-er and bring to the notice of BEE. BEE can recognize for challenge testing in disputedcases as a measure for self-regulation.

Penalties and Adjudication:

• Penalty for each offence under the Act would be in monetary terms i.e. Rs.10,000 foreach offence and Rs.1,000 for each day for continued non Compliance.

• The initial phase of 5 years would be promotional and creating infrastructure for implementation of Act. No penalties would be effective during this phase.

• The power to adjudicate has been vested with state Electricity Regulatory Commissionwhich shall appoint any one of its member to be an adjudicating officer for holding anenquiry in connection with the penalty imposed.

Features Extracted from The Energy Conservation Act, 2001.

CHAPTER -I

Definitions

In this Act, unless the context otherwise requires: -(a) "accredited energy auditor" means an auditor possessing qualifications specified under

clause (p) of sub-section (2) of section 13;(b) " Appellate Tribunal" means Appellate Tribunal for Energy Conservation established under

section 30;(c) "building" means any structure or erection or part of a structure or erection, after the rules

relating to energy conservation building codes have been notified under clause (a) of sec-tion 15 of clause (l) of sub-section (2) of section 56, which is having a connected load of500kW or contract demand of 600 kVA and above and is intended to be used for commer-cial purposes;

(d) "Bureau" means the Bureau of Energy Efficiency established under subsection (l) of sec-tion 3;

(e) "Chairperson" means the Chairperson of the Governing council;(f) "designated agency" means any agency designated under clause (d) of section 15;(g) "designated consumer" means any consumer specified under clause (e) of section 14;(h) "energy" means any form of energy derived from fossil fuels, nuclear substances or mate-

Page 27: General Aspect of Energy Management and Energy Audit

1. Energy Scenario

27Bureau of Energy Efficiency

rials, hydro-electricity and includes electrical energy or electricity generated from renew-able sources of energy or bio-mass connected to the grid;

(i) "energy audit" means the verification, monitoring and analysis of use of energy includingsubmission of technical report containing recommendations for improving energy effi-ciency with cost benefit analysis and an action plan to reduce energy consumption;

(j) "energy conservation building codes" means the norms and standards of energy consump-tion expressed in terms of per square meter of the area wherein energy is used and includesthe location of the building;

(k) "energy consumption standards" means the norms for process and energy consumptionstandards specified under clause (a) of section 14;

(l) "Energy Management Centre" means the Energy Management Centre set up under theResolution of the Government of India in the erstwhile Ministry of Energy, Department ofPower No. 7(2)/87-EP (Vol. IV), dated the 5th July, 1989 and registered under the SocietiesRegistration Act, 1860; (21 of 1860)

(m) "energy manager" means any individual possessing the qualifications prescribed underclause (m) of section 14;

(n) " Governing Council" means the Governing Council referred to in section 4;(o) "member" means the member of the Governing Council and includes the Chairperson;(p) "notification" means a notification in the Gazette of India or, as the case may be, the

Official Gazette of a State;(q) "prescribed" means prescribed by rules made under this Act;(r) "regulations" means regulations made by the Bureau under this Act;(s) "schedule" means the Schedule of this Act;(t) "State Commission" means the State Electricity Regulatory Commission established under

sub-section (l) of section 17 of the Electricity Regulatory Commissions Act, 1998; (14 of1998)

(u) words and expression used and not defined in this Act but defined in the Indian ElectricityAct, 1910 or the Electricity (Supply) Act, 1948 or the Electricity Regulatory CommissionsAct, 1998 shall have meanings respectively assigned to them in those Acts. (9 of 1940, 54of 1948,14 of 1998)

CHAPTER IV,

SECTION 13

Powers and Functions of Bureau

(1) The Bureau shall, effectively co-ordinate with designated consumers, designated agenciesand other agencies, recognise and utilise the existing resources and infrastructure, in per-forming the functions assigned to it by or under this Act

(2) The Bureau may perform such functions and exercise such powers as may be assigned toit by or under this Act and in particular, such functions and powers include the function andpower to -

(a) recommend to the Central Government the norms for processes and energy consumptionstandards required to be notified under clause (a) of section 14 ;

(b) recommend to the Central Government the particulars required to be displayed on labelon equipment or on appliances and manner of their display under clause (d) of section14;

Page 28: General Aspect of Energy Management and Energy Audit

1. Energy Scenario

28Bureau of Energy Efficiency

(c) recommend to the Central Government for notifying any user or class of users of ener-gy as a designated consumer under clause (e) of section 14;

(d) take suitable steps to prescribe guidelines for energy conservation building codes underclause (p) of section 14;

(e) take all measures necessary to create awareness and disseminate information for effi-cient use of energy and its conservation;

(f) arrange and organize training of personnel and specialists in the techniques for efficientuse of energy and its conservation;

(g) strengthen consultancy services in the field of energy conservation;(h) promote research and development in the field of energy conservation;(i) develop testing and certification procedure and promote testing facilities for certification

and testing for energy consumption of equipment and appliances;(j) formulate and facilitate implementation of pilot projects and demonstration projects for

promotion of efficient use of energy and its conservation;(k) promote use of energy efficient processes, equipment, devices and systems;(l) promote innovative financing of energy efficiency projects;(m)give financial assistance to institutions for promoting efficient use of energy and its con-

servation;(n) levy fee, as may be determined by regulations, for services provided for promoting effi-

cient use of energy and its conservation;(o) maintain a list of accredited energy auditors as may be specified by regulations;(p) specify, by regulations, qualifications for the accredited energy auditors;(q) specify, by regulations, the manner and intervals of time in which the energy audit shall

be conducted ;(r) specify, by regulations, certification procedures for energy managers to be designated or

appointed by designated consumers;(s) prepare educational curriculum on efficient use of energy and its conservation for edu-

cational institutions, boards, universities or autonomous bodies and coordinate withthem for inclusion of such curriculum in their syllabus;

(t) implement international co-operation programmes relating to efficient use of energy andits conservation as may be assigned to it by the Central Government;

(u) perform such other functions as may be prescribed.

CHAPTER V, SECTION 14

Power of Central Government to Facilitate and Enforce Efficient use of Energy and itsConservation

The Central Government may, by notification, in consultation with the Bureau, - (a) specify the norms for processes and energy consumption standards for any equipment,

appliances which consumes, generates, transmits or supplies energy;(b) specify equipment or appliance or class of equipments or appliances, as the case may be,

for the purposes of this Act;(c) prohibit manufacture or sale or purchase or import of equipment or appliance specified

under clause (b) unless such equipment or appliances conforms to energy consumptionstandards;

Page 29: General Aspect of Energy Management and Energy Audit

1. Energy Scenario

29Bureau of Energy Efficiency

Provided that no notification prohibiting manufacture or sale or purchase or import orequipment or appliance shall be issued within two years from the date of notification issuedunder clause (a) of this section;

(d) direct display of such particulars on label on equipment or on appliance specified underclause (b) and in such manner as may be specified by regulations;

(e) specify, having regarding to the intensity or quantity of energy consumed and the amountof investment required for switching over to energy efficient equipments and capacity orindustry to invest in it and availability of the energy efficient machinery and equipmentrequired by the industry, any user or class of users of energy as a designated consumer forthe purposes of this Act;

(f) alter the list of Energy Intensive Industries specified in the Schedule;(g) establish and prescribe such energy consumption norms and standards for designated con-

sumers as it may consider necessary: Provided that the Central Government may pre-scribe different norms and standards for different designated consumers having regardto such factors as may be prescribed;

(h) direct, having regard to quantity of energy consumed or the norms and standards of ener-gy consumption specified under clause (a) the energy intensive industries specified in theSchedule to get energy audit conducted by an accredited energy auditor in such manner andintervals of time as may be specified by regulations;

(i) direct, if considered necessary for efficient use of energy and its conservation, any desig-nated consumer to get energy audit conducted by an accredited energy auditor;

(j) specify the matters to be included for the purposes of inspection under sub-section (2) ofsection 17;

(k) direct any designated consumer to furnish to the designated agency, in such form and man-ner and within such period, as may be prescribed, the information with regard to the ener-gy consumed and action taken on the recommendation of the accredited energy auditor;

(l) direct any designated consumer to designate or appoint energy manger in charge of activ-ities for efficient use of energy and its conservation and submit a report, in the form andmanner as may be prescribed, on the status of energy consumption at the end of the everyfinancial year to designated agency;

(m) prescribe minimum qualification for energy managers to be designated or appointed underclause (l);

(n) direct every designated consumer to comply with energy consumption norms and stan-dards;

(o) direct any designated consumer, who does not fulfil the energy consumption norms andstandards prescribed under clause (g), to prepare a scheme for efficient use of energy andits conservation and implement such scheme keeping in view of the economic viability ofthe investment in such form and manner as may be prescribed;

(p) prescribe energy conservation building codes for efficient use of energy and its conserva-tion in the building or building complex;

(q) amend the energy conservation building codes to suit the regional and local climatic con-ditions;

(r) direct every owner or occupier of the building or building complex, being a designatedconsumer to comply with the provisions of energy conservation building codes for efficientuse of energy and its conservation;

Page 30: General Aspect of Energy Management and Energy Audit

1. Energy Scenario

30Bureau of Energy Efficiency

(s) direct, any designated consumer referred to in clause (r), if considered necessary, for effi-cient use of energy and its conservation in his building to get energy audit conducted inrespect of such building by an accredited energy auditor in such manner and intervals oftime as may be specified by regulations;

(t) take all measures necessary to create awareness and disseminate information for efficientuse of energy and its conservation;

(u) arrange and organise training of personnel and specialists in the techniques for efficient useof energy and its conservation;

(v) take steps to encourage preferential treatment for use of energy efficient equipment orappliances: Provided that the powers under clauses (p) and (s) shall be exercised in con-sultation with the concerned State.

CHAPTER VI, SECTION 15

Power Of State Government To Facilitate And Enforce Efficient Use Of Energy And ItsConservation

The State Government may, by notification, in consultation with the Bureau - (a) amend the energy conservation building codes to suit the regional and local climatic con-

ditions and may, by rules made by it, specify and notify energy conservation building codeswith respect to use of energy in the buildings;

(b) direct every owner or occupier of a building or building complex being a designated con-sumer to comply with the provisions of the energy conservation building codes;

(c) direct, if considered necessary for efficient use of energy and its conservation, any desig-nated consumer referred to in clause (b) to get energy audit conducted by an accreditedenergy auditor in such manner and at such intervals of time as may be specified by regu-lations;

(d) designate any agency as designated agency to coordinate, regulate and enforce provisionsof this Act within the State;

(e) take all measures necessary to create awareness and disseminate information for efficientuse of energy and its conservation;

(f) arrange and organise training of personnel and specialists in the techniques for efficient useof energy and its conservation;

(g) take steps to encourage preferential treatment for use of energy efficient equipment orappliances;

(h) direct, any designated consumer to furnish to the designated agency, in such form and man-ner and within such period as may be specified by rules made by it, information with regardto the energy consumed by such consumer;

(i) specify the matters to be included for the purposes of inspection under sub-section (2) ofsection 17;

(1) The State Government shall constitute a Fund to be called the State Energy ConservationFund for the purposes of promotion of efficient use of energy and its conservation withinthe State.

(2) To the Fund shall be credited all grants and loans that may be made by the StateGovernment or, Central Government or any other organization or individual for the pur-poses of this Act.

Page 31: General Aspect of Energy Management and Energy Audit

(3) The Fund shall be applied for meeting the expenses incurred for implementing the provi-sions of this Act.

(4) The Fund created under sub-section (l) shall be administered by such persons or anyauthority and in such manner as may be specified in the rules made by the StateGovernment.

(1) The designated agency may appoint, after the expiry of five years from the date of com-mencement of this Act, as many inspecting officers as may be necessary for the purpose ofensuring compliance with energy consumption standard specified under clause (a) of sec-tion 14 or ensure display of particulars on label on equipment or appliances specified underclause (b) of section 14 or for the purpose of performing such other functions as may beassigned to them.

(2) Subject to any rules made under this Act, an inspecting officer shall have power to - (a) inspect any operation carried on or in connection with the equipment or appliance speci-

fied under clause (b) of section 14 or in respect of which energy standards under clause (a)of section 14 have been specified;

(b) enter any place of designated consumer at which the energy is used for any activity andmay require any proprietor, employee, director, manager or secretary or any other personwho may be attending in any manner to or helping in, carrying on any activity with the helpof energy -

(i) to afford him necessary facility to inspect - (A) any equipment or appliance as he may require and which may be available at such place;(B) any production process to ascertain the energy consumption norms and standards; (ii) to make an inventory of stock of any equipment or appliance checked or verified by him; (iii) to record the statement of any person which may be useful for, or relevant to, for efficient

use of energy and its conservation under this Act.(3) An inspecting officer may enter any place of designated consumer - (a) where any activity with the help of energy is carried on; and (b) where any equipment or appliance notified under clause (b) of section 14 has been kept,

during the hours at which such places is open for production or conduct of business con-nected therewith.

(4) An inspecting officer acting under this section shall, on no account, remove or cause to beremoved from the place wherein he has entered, any equipment or appliance or books ofaccounts or other documents.

The Central Government or the State Government may, in the exercise of its powers and per-formance of its functions under this Act and for efficient use of energy and its conservation,issue such directions in writing as it deems fit for the purposes of this Act to any person, offi-cer, authority or any designated consumer and such person, officer or authority or any desig-nated consumer shall be bound to comply with such directions.

Explanation - For the avoidance of doubts, it is hereby declared that the power to issuedirections under this section includes the power to direct -

(a) regulation of norms for process and energy consumption standards in any industry or build-ing or building complex; or

(b) regulation of the energy consumption standards for equipment and appliances.

1. Energy Scenario

31Bureau of Energy Efficiency

Page 32: General Aspect of Energy Management and Energy Audit

1. Energy Scenario

32Bureau of Energy Efficiency

CHAPTER VIII, SECTION 26

Penalties and Adjudication

(1) If any person fails to comply with the provision of clause (c) or the clause (d) or clause (h)or clause (i) or clause (k) or clause (l) or clause (n) or clause (r) or clause (s) of section14 or clause (b) or clause (c) or clause (h) of section 15, he shall be liable to a penaltywhich shall not exceed ten thousand rupees for each such failures and, in the case of con-tinuing failures, with an additional penalty which may extend to one thousand rupees forevery day during which such failures continues:Provided that no person shall be liable to pay penalty within five years from the date of

commencement of this Act.(2) Any amount payable under this section, if not paid, may be recovered as if it were an arrear

of land revenue.(1) For the purpose of adjudging section 26, the State Commission shall appoint any of its

members to be an adjudicating officer for holding an inquiry in such manner as may be pre-scribed by the Central Government, after giving any person concerned a reasonable oppor-tunity of being heard for the purpose of imposing any penalty.(2) While holding aninquiry the adjudicating officer shall have power to summon and enforce the attendance ofany person acquainted with the facts and circumstances of the case of give evidence or pro-duce any document which in the opinion of the adjudicating officer, may be useful for orrelevant to the subject-matter of the inquiry, and if, on such inquiry, he is satisfied that theperson has failed to comply with the provisions of any of the clauses of the sections spec-ified in section 26, he may impose such penalty as he thinks fit in accordance with the pro-visions of any of those clauses of that section:Provided that where a State Commission has not been established in a State, theGovernment of that State shall appoint any of its officer not below the rank equivalent toa Secretary dealing with legal affairs in that State to be an adjudicating officer for the pur-poses of this section and such officer shall cease to be an adjudicating officer immediate-ly on the appointment of an adjudicating officer by the State Commission on its establish-ment in that State: Provided further that where an adjudicating officer appointed by a StateGovernment ceased to be an adjudicating officer, he shall transfer to the adjudicating offi-cer appointed by the State Commission all matters being adjudicated by him and thereafterthe adjudicating officer appointed by the State Commission shall adjudicate the penaltieson such matters.

While adjudicating the quantum of penalty under section 26, the adjudicating officer shall havedue regard to the following factors, namely:-(a) the amount of disproportionate gain or unfair advantage, wherever quantifiable, made as a

result of the default;(b) the repetitive nature of the default.No civil court shall have jurisdiction to entertain any suit

or proceeding in respect of any matter which an adjudicating officer appointed under thisAct or the Appellate Tribunal is empowered by or under this Act to determine and noinjunction shall be granted by any court or other authority in respect of any action taken orto be taken in pursuance of any power conferred by or under this Act.

Page 33: General Aspect of Energy Management and Energy Audit

1. Energy Scenario

33Bureau of Energy Efficiency

CHAPTER IX, SECTION 30

Appellate Tribunal for Energy Conservation

The Central Government shall, by notification, establish an Appellate Tribunal to be known asthe Appellate Tribunal for Energy Conservation to hear appeals against the orders of the adju-dicating officer or the Central Government or the State Government or any other authorityunder this Act

CHAPTER X,

Miscellaneous

SECTION 61

The provisions of this Act shall not apply to the Ministry or Department of the CentralGovernment dealing with Defence, Atomic Energy or such other similar Ministries orDepartments undertakings or Boards or institutions under the control of such Ministries orDepartments as may be notified by the Central Government.

THE SCHEDULE

[See section 2 (s)]

List of Energy Intensive Industries and other establishments specified asdesignated consumers

1. Aluminium;2. Fertilizers;3. Iron and Steel;4. Cement;5. Pulp and paper;6. Chlor Akali;7. Sugar;8. Textile;9. Chemicals;10. Railways;11. Port Trust;12. Transport Sector (industries and services);13. Petrochemicals, Gas Crackers, Naphtha Crackers and Petroleum Refineries;14. Thermal Power Stations, hydel power stations, electricity transmission companies

and distribution companies;15. Commercial buildings or establishments;

Full version of this act may be obtained from www.bee-india.nic.in

Page 34: General Aspect of Energy Management and Energy Audit

1. Energy Scenario

34Bureau of Energy Efficiency

QUESTIONS

1. Define the following terms with three examples for each -

a) Primary and Secondary Energy.b) Commercial and Non-commercial Energy.c) Renewable and Non-renewable Energy

2. In terms of coal reserve India's position in the world is

(a) 10th (b) 17th (c) 4th (d) 26th

3. The world oil reserves is expected to last another

(a) 300 years (b) 45 years (c) 600 years (d) forever

4. Of the total primary energy consumption in India coal accounts for

(a) 35% (b) 46% (c) 55% (d) 75%

5. List atleast five States where coal deposits are concentrated in India.

6. How much % of our Country's oil consumption is imported and how much does it cost (approximately) per year?

7. Name any three places of oil reserves located in India.

8. What is the hydro power generation potential available in India, and how much is exploited so far?

9. What are the % shares of commercial energy consumption in industrial and agricultural sectors?

10. How is economic growth linked to energy consumption?

11. What do you think of strategies required for long-term management of energy in India?

12. Discuss the subsidies and cross subsidies in oil sector in India.

13. Write in few words about the various reforms in the energy sector.

14. Though Plant Respiration and Decomposition release more than ten times CO2

released by human activities, explain why CO2 is regarded as a potential threat to the planet.

15. The contribution of CO2 to the green house gases is

(a) 23% (b) 95% (c) 54% (d) 0%

16. What are the implications of Global warming?

17. Describe the Greenhouse effect.

18. The excess of which gas in the atmosphere is the main cause for greenhouse effect?

19. Name three greenhouse gases. Which one of them produces the maximum greenhouse effect?

Page 35: General Aspect of Energy Management and Energy Audit

1. Energy Scenario

35Bureau of Energy Efficiency

20. What are the major pollutants in burning fossil fuels?

21. Differentiate between energy conservation and energy efficiency.

22. What are the benefits for industry through implementing energy efficiencyprogramme?

23. Why energy conservation is important in the prevailing energy scenario?

24. The energy conservation act requires that all designated energy consumers should get energy audits conducted by(a) Energy manager (b) accredited energy auditor (c) managing director (d) chartered accountant

25. Name five designated consumers under the energy conservation act.

26. Name any three main provisions of the EC act, 2001 as applicable to the designatedconsumers.

27. List the incorrect statement and correct the same.The Energy Conservation Act, 2001 requires that a) designated consumer to furnish to the designated agency, in such form and manner and within such period as may be prescribed the information with regard to the energy purchased and action taken on the recommendation of energy auditor.b)direct, if consider necessary, for efficient use of energy and its conservation, to get energy audit conducted by a certified energy auditor.

REFERENCES

1. Encyclopedia of Energy - McGraw Hill Publication2. Handbook of Energy Engineering , The Fairmont Press Inc - Albert Thumann 3. Energy Handbook, Von Nostrand Reinhold Company - Robert L. Loftness4. Cleaner Production - Energy Efficiency Manual for GERIAP, UNEP, Bangkok prepared by

National Productivity Council5. Statistics have been drawn from BP Statistical Review of World Energy, June 2003,

International Energy Outlook, March 2002, Energy Information administration, Office ofintegrated analysis and forecasting, US department of energy, Washington

6. Indian Planning commission statistics7. The Energy and Resources Institute (TERI)

www.bp.com/centres/energywww.eia.doe.govwww.epa.org

Page 36: General Aspect of Energy Management and Energy Audit
Page 37: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

Chapter: 1.1 Energy Scenario

Part-I: Objective type questions and answers

1. The energy sources, that are either found or stored in nature are

a) Secondary Energy Sources b) Primary Energy Sources

c) both (a) and (b) d) none of the above

2. Which of the following is commercial energy source?

a) Electricity b) Coal c) Oil d) All the above

3. Inexhaustible energy sources are known as

a) commercial Energy b) renewable Energy

c) primary energy d) secondary energy

4. Which country has the largest share of the global coal reserves?

a) Russia b) China c) USA d) India

5. The % of gas reserves for Russian Federation, when compared to world reserve is considered at

a) 10 % of World reserve b) 20 % of World reserve

c) 30 % of World reserve d) 40 % of World reserve

6. World oil reserves are estimated to last over

a) 45 years b) 60 years c) 200 years d) 75 years

7. World gas reserves are estimated to last over

a) 45 years b) 65 years c) 200 years d) 75 years

8. The global primary energy consumption (2002) was equivalent to

a) 21,842 Mtoe b) 15,360 Mtoe c) 9405 Mtoe d) 12,396 Mtoe

9. The primary energy consumption of India is

a) 1/29 of the world b) 1/16 of the world c) 1/7 of the world d) 1/20 of the world

10. The world average per person energy consumption is equivalent to _____tonnes of coal

a) 3 b) 2.2 c) 4.5 d) 1.0

11. Which fuel dominates the energy mix in Indian energy scenario?–

a) Oil b) Natural gas c) Coal d) Nuclear

12. The fourth largest producer of coal and lignite in the world is ______ (EM/EA)

a) USA b) Russia c) India d) China

13. Indian per capita energy consumption is ____ of the world average.

a) 4% b) 20% c) 1% d) 10%

1.1 energy scenario - revised(table format) 1

Page 38: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

14. Energy consumption per unit of GDP is called as:

a) Energy Ratio b) Energy intensityc) Per capita consumption d) None

15. India’s energy intensity is ___ times of world average.

a) 1.5 b) 2.5 c) 3.6 d) 10

16. India’s current percentage peak demand shortage for electricity is: (EM/EA)

a) 1% b) 3% c) 10% d) 14%

17. Name the Act, which is proposed to bring the qualitative transformation of the electricity sector:

a) Regulatory Commission Act 1998 b) Indian Electricity Act 1910

c) Supply Act 1948 d) Electricity Act 2003

18. Which of the following is highest contributor to the air pollution?

a) Carbon Monoxide b) Hydro Carbons

c) Sulphur Oxides d) Particulates

19. Projected temperature increase in degree centigrade 2100 due to climate change is:

a) 2 b) 4 c) 6 d) 8 Increase

20. Acid rain is caused by the release of the following components from combustion of fuels.

a) SOx and NOx b) SOx and CO2c) CO2 and NOx d) H2O

Part – II: Short type questions and answers

1. Classify the types of the energy available on the earth?

Energy can be classified into several types based on the following criteria as:

• Primary and Secondary energy

• Commercial and Non commercial energy

• Renewable and Non-Renewable energy

2. Briefly mention about primary sources of energy?

Primary energy sources are those that are either found or stored in nature. Common primary energy sources are coal, oil, natural gas and biomass. Other primary energy sources found on earth include nuclear energy from radioactive substances, thermal energy stored in earth’s interior and potential energy due to earth’s gravity.

3. What is renewable energy and list at least three renewable energy sources?

Renewable energy is the energy obtained from sources that are essentially inexhaustible but has limited potential for exploitation. Examples of renewable resources include wind power, solar power, geothermal energy, tidal power and hydro electric.

4. Name the five states in India, where coal production is concentrated.

Coal production is concentrated in Andhra Pradesh, Bihar, Madhya Pradesh, Maharashtra, Orissa, Jharkhand and West Bengal

1.1 energy scenario - revised(table format) 2

Page 39: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

5. Define Reserve to ‘Production Ratio’?

Ans. It is the ratio of fuel reserves remaining at the end of the year to the production in that year.

6. How do you define ‘Final Energy Consumption’?

Final energy consumption is the actual energy demand at the user end. This is the difference between primary energy consumption and the losses that takes place in transport, transmission, distribution and refinement.

7. Why developed countries have been able to maintain low ratio of energy to GDP?

This is because they have been able to focus on two important issues like, energy efficiency and lower energy intensity routes.

8. What is Energy intensity and what it indicates?

Energy intensity is energy consumed per unit of GDP and it indicates the development stage of that country.

9. Mention the parameters on which the high tension and low tension consumers are charged by electricity boards.

Generally, high tension consumers are charged based on both demand (kVA) and energy (kWh) while the low tension consumers are charged based on only energy consumed (kWh).

10. What is main objective of Electricity Act, 2003?

The main objective of Electricity Act, 2003 is to create liberal framework of development for the power sector by distancing Government from regulation.

11. List down the major sources of pollutants in Air?

The major sources of pollutants in Air are fuel combustion in transport, industry, forest fires, and solid waste disposal.

12. What is greenhouse gas effect?

The heating up of earth’s atmosphere due to trapping of long wavelength infrared rays by the carbon di- oxide layer in the atmosphere is called green house effect.

13. What are the key greenhouse gases driving global warming?

Carbon-dioxide, CFC, methane, Ozone, Nitrous oxide etc.

14. What are the two major anthropogenic causes for the generation of Carbon dioxide in the atmosphere?

1. Combustion of fossil fuels 2. Changes in land use

15. List down at least three effects of acid rain?

The effects of acid rains are as follows:

Acidification of lakes, streams and soils.

Direct and indirect affects (release of metals, for e.g. aluminium which washes away plant nutrients

Killing of wild life.

Decay of building materials, paints, statues and sculptures.

Health problems (respiratory, burning skin and eyes)

1.1 energy scenario - revised(table format) 3

Page 40: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

16. What is the basis for aim of Energy Security for any country?

The basic aim of energy security for a nation is to reduce its dependency on the imported energy sources for its economic growth.

17. Differentiate between Energy Conservation and Energy Efficiency?

Energy conservation is achieved when growth of energy consumption is reduced, measured in physical terms. Whereas the energy efficiency is achieved when energy intensity in a specific product, process or area of production is reduced without affecting output, consumption or comfort levels.

18. How a nation benefits from Energy Efficiency programs?

Through energy efficiency, energy imports will be reduced, which helps in conserving limited resources and lead to improved energy security.

19. How Bureau of Energy Efficiency (BEE) facilitates energy efficiency programs in India?

BEE facilitates Energy efficiency programs in India by preparing standards and labels of appliances, developing a list of designated consumers, specifying certification and accreditation procedures, preparing building codes, maintaining central EC fund and undertaking promotional activities in coordination with centre and state level agencies.

20. List down at least five designated consumers specified by the BEE?

Aluminium, Fertilizers, Iron and Steel, Cement, Pulp and Paper etc.,

Part-III: Long type questions and answers

1. List the strategies for better energy security of the nation?

Some of the strategies that can be used to meet future challenges to Nation’s energy security are:

• Building stockpiles

• Diversification of energy supply sources

• Increased capacity of fuel switching

• Demand restraint

• Development of renewable energy sources

• Energy efficiency

• Sustainable development

2. Mention some of the long-term energy strategies available for the better energy secured nation?

Efficient generation of energy resources

• Efficient production of coal, oil and natural gas

• Reduction of natural gas flaring

Improving energy infrastructure

• Building new refineries

• Creation of urban gas transmission and distribution network

1.1 energy scenario - revised(table format) 4

Page 41: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

• Maximizing efficiency of rail transport of coal production.

• Building a new coal & gas fired power stations.

• Maximizing efficiency of rail transport of coal production.

• Building new coal and gas fired power stations.

Enhancing energy efficiency

• Improving energy efficiency in accordance with national, socio-economic, and environmental priorities

• Promoting of energy efficiency and emission standards

• Labeling programmes for products and adoption of energy efficient technologies in large industries

Deregulation and privatization of energy sector

• Reducing cross subsidies on oil products and electricity tariffs

• Decontrolling coal prices and making natural gas prices competitive

• Privatization of oil, coal and power sectors for improved efficiency.

Investment legislation to attract foreign investments.

• Streamlining approval process for attracting private sector participation in power generation, transmission and distribution

3. How do an Industry, nation and globe would benefit from energy efficiency programs?

Energy efficiency benefits for industry, nation and globe are as follows:

Industry:

• Reduced energy bills • Increased competitiveness • Increased productivity • Improved quality • Increased profits

Nation:

• Reduced energy imports • Avoided costs can be used for poverty reduction • Conservation of limited resources • Improved energy security

Globe:

• Reduced GHG and other emissions • Maintains a suitable environment

4. How energy pricing is done in India?

Coal: Grade wise basic price of coal at the pithead excluding statutory levies for run-of-mine (ROM) coal are fixed by Coal India Ltd from time to time. The pithead price of coal in India compares favourably with price of imported coal. In spite of this, industries still import coal due to its higher calorific value and low ash content.

Oil: As part of the energy sector reforms, the government has attempted to bring prices for many of the petroleum products (naphtha, furnace oil, LSHS, LDO and bitumen) in line with international prices. The most important achievement has been the linking of diesel prices to international prices and a reduction in subsidy. However, LPG and kerosene, consumed mainly by domestic sectors, continue to be heavily subsidised. Subsidies and cross-subsidies have resulted in serious distortions in prices,

1.1 energy scenario - revised(table format) 5

Page 42: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

as they do not reflect economic costs at all in many cases.

Natural Gas: The government has been the sole authority for fixing the price of natural gas in the country. It has also been taking decisions on the allocation of gas to various competing consumers.

Electricity: Electricity tariffs in India are structured in a relatively simple manner. While high tension consumers are charged based on both demand (kVA) and energy (kWh), the low-tension (LT) consumer pays only for the energy consumed (kWh) as per tariff system in most of the electricity boards. In addition to the base tariffs, some of the State Electricity Boards have additional recovery from customers in form of fuel surcharges, electricity duties and taxes.

5. Briefly describe the economic reforms in Coal, oil and natural gas and electricity sectors.

Since the initiation of economic reforms in India in 1991, there has been a growing acceptance of the need for deepening these reforms in several sectors of the economy, which were essentially in the hands of the government for several decades. It is now been realized that if substance has to be provided to macroeconomic policy reform, then it must be based on reforms that concern the functioning of several critical sectors of the economy, among which the infrastructure sectors in general and the energy sector in particular, are paramount.

Coal

The government has recognized the need for new coal policy initiatives and for rationalization of the legal and regulatory framework that would govern the future development of this industry. One of the key reforms is that the government has allowed importing of coal to meet our requirements. Private sector is now allowed to participate in the extraction and marketing of coal.

The ultimate objective of some of the ongoing measures and others under consideration is to see that a competitive environment is created for the functioning of various entities in this industry. This would not only bring about gains in efficiency but also effect cost reduction, which would consequently ensure supply of coal on a larger scale at lower prices. Competition would also have the desirable effect of bringing in new technology, for which there is an urgent and overdue need since the coal industry has suffered a prolonged period of stagnation in technological innovation.

Oil and Natural Gas

Since 1993, private investors have been allowed to import and market liquefied petroleum gas (LPG) and kerosene freely; private investment is also been allowed in lubricants, which are not subject to price controls. Prices for naphtha and some other fuels have been liberalized. In 1997 the government introduced the New Exploration Licensing Policy (NELP) in an effort to promote investment in the exploration and production of domestic oil and gas. In addition, the refining sector has been opened to private and foreign investors in order to reduce imports of refined products and to encourage investment in downstream pipelines. Attractive terms are being offered to investors for the construction of liquefied natural gas (LNG) import facilities.

Electricity

Following the enactment of the Electricity Regulatory Commission Legislation, the Central Electricity Regulatory Commission (CERC) was set up, with the main objective of regulating the Central power generation utilities. State level regulatory bodies have also been set up to set tariffs and promote competition. Private investments in power generation were also allowed. The State SEBs were asked to switch over to separate Generation, Transmission and Distribution corporations. While, India currently does not have a unified national power grid, the country plans to link the SEB grids eventually, and has set up a state company, Powergrid, to oversee the unification.

1.1 energy scenario - revised(table format) 6

Page 43: General Aspect of Energy Management and Energy Audit

36Bureau of Energy Efficiency

2. BASICS OF ENERGY AND ITS VARIOUS FORMS

SyllabusBasics of Energy and its various forms: Electricity basics - DC & AC currents,Electricity tariff, Load management and Maximum demand control, Power factor. Thermal basics -Fuels, Thermal energy contents of fuel, Temperature & Pressure, Heatcapacity, Sensible and Latent heat, Evaporation, Condensation, Steam, Moist air andHumidity & Heat transfer, Units and conversion.

2.1 Definition

Energy is the ability to do work and work is the transfer of energy from one form to another. Inpractical terms, energy is what we use to manipulate the world around us, whether by excitingour muscles, by using electricity, or by using mechanical devices such as automobiles. Energycomes in different forms - heat (thermal), light (radiant), mechanical, electrical, chemical, andnuclear energy.

2.2 Various Forms of Energy

There are two types of energy - stored (potential) energy and working (kinetic) energy. Forexample, the food we eat contains chemical energy, and our body stores this energy until werelease it when we work or play.

2.2.1 Potential Energy

Potential energy is stored energy and the energy of position (gravitational). It exists in variousforms.

Chemical EnergyChemical energy is the energy stored in the bonds of atoms and molecules. Biomass, petrole-um, natural gas, propane and coal are examples of stored chemical energy.

Nuclear EnergyNuclear energy is the energy stored in the nucleus of an atom - the energy that holds the nucle-us together. The nucleus of a uranium atom is an example of nuclear energy.

Stored Mechanical EnergyStored mechanical energy is energy stored in objects by the application of a force. Compressedsprings and stretched rubber bands are examples of stored mechanical energy.

Page 44: General Aspect of Energy Management and Energy Audit

2. Basics of Energy and its Various Forms

37Bureau of Energy Efficiency

Gravitational EnergyGravitational energy is the energy of place or position. Water in a reservoir behind a hydropow-er dam is an example of gravitational energy. When the water is released to spin the turbines, itbecomes motion energy.

2.2.2 Kinetic Energy

Kinetic energy is energy in motion- the motion of waves, electrons, atoms, molecules and sub-stances. It exists in various forms.

Radiant EnergyRadiant energy is electromagnetic energy that travels in transverse waves. Radiant energyincludes visible light, x-rays, gamma rays and radio waves. Solar energy is an example of radi-ant energy.

Thermal EnergyThermal energy (or heat) is the internal energy in substances- the vibration and movement ofatoms and molecules within substances. Geothermal energy is an example of thermal energy.

MotionThe movement of objects or substances from one place to another is motion. Wind andhydropower are examples of motion.

SoundSound is the movement of energy through substances in longitudinal (compression/rarefaction)waves.

Electrical EnergyElectrical energy is the movement of electrons. Lightning and electricity are examples of elec-trical energy.

2.2.3 Energy Conversion

Energy is defined as "the ability to do work." In this sense, examples of work include movingsomething, lifting something, warming something, or lighting something. The following is anexample of the transformation of different types of energy into heat and power.

It is difficult to imagine spending an entire day without using energy. We use energy to light ourcities and homes, to power machinery in factories, cook our food, play music, and operate ourTV.

More the number of conversion stages, lesserthe overall energy efficiency

Oil burns to generate heat --> Heat boils water -->

Water turns to steam -->Steam pressure turns a turbine -->

Turbine turns an electric generator -->Generator produces electricity -->

Electricity powers light bulbs -->Light bulbs give off light and heat

Page 45: General Aspect of Energy Management and Energy Audit

2. Basics of Energy and its Various Forms

38Bureau of Energy Efficiency

2.2.4 Grades of Energy

High-Grade Energy

Electrical and chemical energy are high-grade energy, because the energy is concentrated in asmall space. Even a small amount of electrical and chemical energy can do a great amount ofwork. The molecules or particles that store these forms of energy are highly ordered and com-pact and thus considered as high grade energy. High-grade energy like electricity is better usedfor high grade applications like melting of metals rather than simply heating of water.

Low-Grade Energy

Heat is low-grade energy. Heat can still be used to do work (example of a heater boiling water),but it rapidly dissipates. The molecules, in which this kind of energy is stored (air and watermolecules), are more randomly distributed than the molecules of carbon in a coal. This disor-dered state of the molecules and the dissipated energy are classified as low-grade energy.

2.3 Electrical Energy Basics

Electric current is divided into two types: Directional Current (DC) and Alternating Current(AC).

Directional (Direct) Current

A non-varying, unidirectional electric current (Example: Current produced by batteries)

Characteristics: • Direction of the flow of positive and negative charges does not change with time• Direction of current (direction of flow for positive charges) is constant with time• Potential difference (voltage) between two points of the circuit does not change polarity

with time

Alternating Current

A current which reverses in regularly recurring intervals of time and which has alternately pos-itive and negative values, and occurring a specified number of times per second. (Example:Household electricity produced by generators, Electricity supplied by utilities.)

Characteristics: · Direction of the current reverses periodically with time· Voltage (tension) between two points of the circuit changes polarity with time.· In 50 cycle AC, current reverses direction 100 times a second (two times during onecycle)

Ampere (A)

Current is the rate of flow of charge. The ampere is the basic unit of electric current. It is thatcurrent which produces a specified force between two parallel wires, which are 1 metre apartin a vacuum.

Voltage (V)

The volt is the International System of Units (SI) measure of electric potential or electromo-

Page 46: General Aspect of Energy Management and Energy Audit

2. Basics of Energy and its Various Forms

39Bureau of Energy Efficiency

kVAr (Reactive Power)

kVAr is the reactive power. Reactive power is the portion of apparent power that does no work.This type of power must be supplied to all types of magnetic equipment, such as motors, trans-formers etc. Larger the magnetizing requirement, larger the kVAr.

Kilowatt (kW) (Active Power)

kW is the active power or the work-producing part of apparent power.

tive force. A potential of one volt appears across a resistance of one ohm when a current of oneampere flows through that resistance.

1000 V = 1 kiloVolts (kV)

Resistance

VoltageResistance =

_______

Current

The unit of resistance is ohm (Ω)

Ohm' Law

Ohm's law states that the current through a conductor is directly proportional to the potentialdifference across it, provided the temperature and other external conditions remain constant.

Frequency

The supply frequency tells us the cycles at which alternating current changes. The unit of fre-quency is hertz (Hz :cycles per second).

Kilovolt Ampere (kVA)

It is the product of kilovolts and amperes. This measures the electrical load on a circuit or sys-tem. It is also called the apparent power.

1000

AmperesxVoltage(kVA)powerApparent,circuit electrical phase single aFor =

1000)(,sin

factorPowerxAmperesxVoltagekWPowerphasegleFor =

1000

732.1)(,

factorPowerxAmperesxVoltagexkWPowerphaseThreeFor =

1000

AmperesxVoltagex3(kVA)powerApparent,circuit electrical phase threeaFor =

Page 47: General Aspect of Energy Management and Energy Audit

2. Basics of Energy and its Various Forms

40Bureau of Energy Efficiency

Power Factor

Power Factor (PF) is the ratio between the active power (kW) and apparent power (kVA).

When current lags the voltage like in inductive loads, it is called lagging power factor and whencurrent leads the voltage like in capacitive loads, it is called leading power factor.

Inductive loads such as induction motors, transformers, discharge lamp, etc. absorb com-paratively more lagging reactive power (kVAr) and hence, their power factor is poor. Lower thepower factor; electrical network is loaded with more current. It would be advisable to havehighest power factor (close to 1) so that network carries only active power which does realwork. PF improvement is done by installing capacitors near the load centers, which improvepower factor from the point of installation back to the generating station.

Kilowatt-hour (kWh)

Kilowatt-hour is the energy consumed by 1000 Watts in one hour. If 1kW (1000 watts) of a elec-trical equipment is operated for 1 hour, it would consume 1 kWh of energy (1 unit of electrici-ty).

For a company, it is the amount of electrical units in kWh recorded in the plant over a monthfor billing purpose. The company is charged / billed based on kWh consumption.

Electricity Tariff

Calculation of electric bill for a company

Electrical utility or power supplying companies charge industrial customers not only based onthe amount of energy used (kWh) but also on the peak demand (kVA) for each month.

Contract Demand

Contract demand is the amount of electric power that a customer demands from utility in a spec-ified interval. Unit used is kVA or kW. It is the amount of electric power that the consumeragreed upon with the utility. This would mean that utility has to plan for the specified capacity.

Maximum demand

Maximum demand is the highest average kVA recorded during any one-demand interval with-in the month. The demand interval is normally 30 minutes, but may vary from utility to utilityfrom 15 minutes to 60 minutes. The demand is measured using a tri-vector meter / digital ener-gy meter.

Page 48: General Aspect of Energy Management and Energy Audit

2. Basics of Energy and its Various Forms

41Bureau of Energy Efficiency

Prediction of Load

While considering the methods of load prediction, some of the terms used in connection withpower supply must be appreciated.Connected Load - is the nameplate rating (in kW or kVA) of the apparatus installed on a con-sumer's premises.Demand Factor - is the ratio of maximum demand to the connected load.Load Factor - The ratio of average load to maximum load.

The load factor can also be defined as the ratio of the energy consumed during a given periodto the energy, which would have been used if the maximum load had been maintained through-out that period. For example, load factor for a day (24 hours) will be given by:

PF Measurement

A power analyzer can measure PF directly, or alternately kWh, kVAh or kVArh readings arerecorded from the billing meter installed at the incoming point of supply. The relation kWh /kVAh gives the power factor.

Time of Day (TOD) Tariff

Many electrical utilitieslike to have flatdemand curve toachieve high plant effi-ciency. They encourageuser to draw morepower during off-peakhours (say during nighttime) and less powerduring peak hours. Asper their plan, theyoffer TOD Tariff,which may be incen-tives or disincentives.Energy meter willrecord peak and non-peak consumption sep-arately by timer con-trol. TOD tariff givesopportunity for the user to reduce their billing, as off peak hour tariff charged are quite low incomparison to peak hour tariff.

LoadMaximum

Load Average Factor Load =

HoursxrecordedloadMaximum

hoursduringconsumedEnergyFactorLoad

24

24=

Page 49: General Aspect of Energy Management and Energy Audit

2. Basics of Energy and its Various Forms

42Bureau of Energy Efficiency

Three phase AC power measurement

Most of the motive drives such as pumps, compressors, machines etc. operate with 3 phase ACInduction motor. Power consumption can be determined by using the relation.

Power = √3 x V x I x CosΦPortable power analysers /instruments are available for measuring all electrical parameters.

Example:

A 3-phase AC induction motor (20 kW capacity) is used for pumping operation. Electricalparameter such as current, volt and power factor were measured with power analyzer. Findenergy consumption of motor in one hour? (line volts. = 440 V, line current = 25 amps and PF= 0.90).

Energy consumption = √ 3 x 0.440 (kV) x 25(A) x 0.90(PF) x 1(hour) = 17.15 kWh

Motor loading calculation

The nameplate details of motor, kW or HP indicate the output parameters of the motor at fullload. The voltage, amps and PF refer to the rated input parameters at full load.

Example:

A three phase,10 kW motor has the name plate details as 415 V, 18.2 amps and 0.9 PF. Actualinput measurement shows 415 V, 12 amps and 0.7 PF which was measured with power analyz-er during motor running.

Rated output at full load = 10 kWRated input at full load = 1.732 x 0.415 x 18.2 x 0.9 = 11.8 kWThe rated efficiency of motor at full load = (10 x 100) / 11.8 = 85%

Measured (Actual) input power = 1.732x 0.415 x 12x 0.7 = 6.0 kW

Which applications use single-phase power in an industry?

Single-phase power is mostly used for lighting, fractional HP motors and electric heater appli-cations.

Example :

A 400 Watt mercury vapor lamp was switched on for 10 hours per day. The supply volt is 230V. Find the power consumption per day? (Volt = 230 V, Current = 2 amps, PF = 0.8)

Electricity consumption (kWh) = V x I x Cos x No of Hours = 0.230 x 2 x 0.8 x 10 = 3.7 kWh or Units

%2.511008.11

0.6100% === xx

kWRated

kWMeasuredloadingMotor

Page 50: General Aspect of Energy Management and Energy Audit

Example :

An electric heater of 230 V, 5 kW rating is used for hot water generation in an industry. Findelectricity consumption per hour (a) at the rated voltage (b) at 200 V

(a) Electricity consumption (kWh) at rated voltage = 5 kW x 1 hour = 5 kWh. (b) Electricity consumption at 200 V (kWh) = (200 / 230)2 x 5 kW x 1 hour = 3.78 kWh.

2.4 Thermal Energy Basics

Temperature and PressureTemperature and pressure are measures of the physical state of a substance. They are closelyrelated to the energy contained in the substance. As a result, measurements of temperature andpressure provide a means of determining energy content.

Temperature

It is the degree of hotness or coldness measured on a definite scale. Heat is a form of energy;temperature is a measure of its thermal effects. In other words, temperature is a means of deter-mining sensible heat content of the substanceIn the Celsius scale the freezing point of water is 0°C and the boiling point of water is 100°Cat atmospheric pressure.

To change temperature given in Fahrenheit (°F) to Celsius (°C)Start with (°F); subtract 32; multiply by 5; divide by 9; the answer is (°C)

To change temperature given in Celsius (°C) to Fahrenheit (°F)Start with (°C); multiply by 9; divide by 5; add on 32; the answer is (°F)

Pressure

It is the force per unit area applied to outside of a body. When we heat a gas in a confined space,we create more force; a pressure increase. For example, heating the air inside a balloon willcause the balloon to stretch as the pressure increases.

Pressure, therefore, is also indicative of stored energy. Steam at high pressures containsmuch more energy than at low pressures.

Heat

Heat is a form of energy, a distinct and measurable property of all matter. The quantity of heatdepends on the quantity and type of substance involved.

Unit of Heat

Calorie is the unit for measuring the quantity of heat. It is the quantity of heat, which can raisethe temperature of 1 g of water by 1°C.

Calorie is too small a unit for many purposes. Therefore, a bigger unit Kilocalorie (1 Kilocalorie

2. Basics of Energy and its Various Forms

43Bureau of Energy Efficiency

°C = (°F - 32) x 5/9

Page 51: General Aspect of Energy Management and Energy Audit

2. Basics of Energy and its Various Forms

44Bureau of Energy Efficiency

= 1000 calories) is used to measure heat. 1 kilocalorie can raise the temperature of 1000g (i.e.1kg) of water by 1°C.

However, nowadays generally joule as the unit of heat energy is used. It is the internation-ally accepted unit. Its relationship with calorie is as follows:

1 Calorie = 4.187 J

Specific Heat

If the same amount of heat energy is supplied to equal quantities of water and milk, their tem-perature goes up by different amounts. This property is called the specific heat of a substanceand is defined as the quantity of heat required to raise the temperature of 1kg of a substancethrough 1°C.

The specific heat of water is very high as compared to other common substances; it takes alot of heat to raise the temperature of water. Also, when water is cooled, it gives out a largequantity of heat.

Sensible heat

It is that heat which when added or subtracted results in a change of temperature.

Quantity of Heat

The quantity of heat, Q, supplied to a substance to increase its temperature by t°C depends on

– mass of the substance (m)– increase in temperature (∆t)– specific heat of the substance (Cp)

TABLE 2.1 SPECIFIC HEAT OF SOME COMMON

SUBSTANCES

Substance Specific Heat (Joules / kg °C)

Lead 130

Mercury 140

Brass 380

Copper 390

Iron 470

Glass 670

Aluminium 910

Rubber 1890

Ice 2100

Alcohol 2400

Water 4200

Page 52: General Aspect of Energy Management and Energy Audit

The quantity of heat is given by:

Q = mass x specific heat x increase in temperature Q = m x Cp x ∆t

Phase Change

The change of state from the solid state to a liquid state is called fusion. The fixed temperatureat which a solid changes into a liquid is called its melting point.

The change of a state from a liquid state to a gas is called vaporization.

Latent heat of fusion

The latent heat of fusion of a substance is the quantity of heat required to convert 1kg solid toliquid state without change of temperature. It is represented by the symbol L. Its unit is Jouleper kilogram (J/Kg)

Thus, L (ice) = 336000 J/kg,

Latent Heat of Vaporization

The latent heat of vaporization of a substance is the quantity of heat required to change 1kg ofthe substance from liquid to vapour state without change of temperature. It is also denoted bythe symbol L and its unit is also J/kg. The latent heat of vaporization of water is 22,60,000 J/kg.

When 1 kg of steam at 100°C condenses to form water at 100°C, it gives out 2260 kJ (540kCals) of heat. Steam gives out more heat than an equal amount of boiling water because of itslatent heat.

Latent heat

It is the change in heat content of a substance, when its physical state is changed without achange in temperature.

Super Heat

The heating of vapour, particularly saturated steam to a temperature much higher than the boil-ing point at the existing pressure. This is done in power plants to improve efficiency and toavoid condensation in the turbine.

Humidity

The moisture content of air is referred to as humidity and may be expressed in two ways: spe-cific humidity and relative humidity.

Specific Humidity

It is the actual weight of water vapour mixed in a kg of dry air.

Humidity Factor

Humidity factor = kg of water per kg of dry air (kg/kg).

2. Basics of Energy and its Various Forms

45Bureau of Energy Efficiency

Page 53: General Aspect of Energy Management and Energy Audit

Relative Humidity (RH)

It is the measure of degree of saturation of the air at any dry-bulb (DB) temperature. Relativehumidity given as a percentage is the actual water content of the air divided by the moisturecontent of fully saturated air at the existing temperature.

Dew Point

It is the temperature at which condensation of water vapour from the air begins as the temper-ature of the air-water vapour mixture falls.

Dry bulb Temperature

It is an indication of the sensible heat content of air-water vapour mixtures.

Wet bulb Temperature

It is a measure of total heat content or enthalpy. It is the temperature approached by the dry bulband the dew point as saturation occurs.

Dew Point Temperature

It is a measure of the latent heat content of air-water vapour mixtures and since latent heat is afunction of moisture content, the dew point temperature is determined by the moisture content.

Fuel Density

Density is the ratio of the mass of the fuel to the volume of the fuel at a stated temperature.

Specific gravity of fuel

The density of fuel, relative to water, is called specific gravity. The specific gravity of water isdefined as 1. As it is a ratio there are no units. Higher the specific gravity, higher will be theheating values.

Viscosity

The viscosity of a fluid is a measure of its internal resistance to flow. All liquid fuels decreasein viscosity with increasing temperature

Calorific Value

Energy content in an organic matter (Calorific Value) can be measured by burning it and mea-suring the heat released. This is done by placing a sample of known mass in a bomb calorime-ter, a device that is completely sealed and insulated to prevent heat loss. A thermometer isplaced inside (but it can be read from the outside) and the increase in temperature after the sam-ple is burnt completely is measured. From this data, energy content in the organic matter can befound out.

The heating value of fuel is the measure of the heat released during the complete combus-tion of unit weight of fuel. It is expressed as Gross Calorific Value (GCV) or Net Calorific Value(NCV). The difference between GCV and NCV is the heat of vaporization of the moisture andatomic hydrogen (conversion to water vapour) in the fuel. Typical GCV and NCV for heavy fueloil are 10,500 kcal/kg and 9,800 kcal/kg.

2. Basics of Energy and its Various Forms

46Bureau of Energy Efficiency

Page 54: General Aspect of Energy Management and Energy Audit

Heat Transfer

Heat will always be transferred from higher temperature to lower temperature independent ofthe mode. The energy transferred is measured in Joules (kcal or Btu). The rate of energy trans-fer, more commonly called heat transfer, is measured in Joules/second (kcal/hr or Btu/hr).Heat is transferred by three primary modes: o Conduction (Energy transfer in a solid) o Convection (Energy transfer in a fluid)o Radiation (Does not need a material to travel through)

Conduction

The conduction of heat takes place, when two bodies are in contact with one another. If onebody is at a higher temperature than the other, the motion of the molecules in the hotter bodywill vibrate the molecules at the point of contact in the cooler body and consequently result inincrease in temperature.

The amount of heat transferred by conduction depends upon the temperature difference, theproperties of the material involved, the thickness of the material, the surface contact area, andthe duration of the transfer.

Good conductors of heat are typically substances that are dense as they have moleculesclose together. This allows the molecular agitation process to permeate the substance easily. So,metals are good conductors of heat, while gaseous substance, having low densities or widelyspaced molecules, are poor conductors of heat. Poor conductors of heat are usually called insu-lators.

The measure of the ability of a substance to insulate is its thermal resistance. This is com-monly referred to as the R-value (RSI in metric). The R-value is generally the inverse of thethermal conductivity, the ability to conduct heat.

Typical units of measure for conductive heat transfer are:

Per unit area (for a given thickness)Metric (SI) : Watt per square meter (W/m2 )

OverallMetric (SI) : Watt (W) or kilowatts (kW)

Convection

The transfer of heat by convection involves the movement of a fluid such as a gas or liquid fromthe hot to the cold portion. There are two types of convection: natural and forced.

In case of natural convection, the fluid in contact with or adjacent to a high temperaturebody is heated by conduction. As it is heated, it expands, becomes less dense and consequent-ly rises. This begins a fluid motion process in which a circulating current of fluid moves pastthe heated body, continuously transferring heat away from it.

In the case of forced convection, the movement of the fluid is forced by a fan, pump or otherexternal means. A centralized hot air heating system is a good example of forced convection.

Convection depends on the thermal properties of the fluid as well as surface conditions atthe body and other factors that affect the ability of the fluid to flow. With a low conductivityfluid such as air, a rough surface can trap air against the surface reducing the conductive heat

2. Basics of Energy and its Various Forms

47Bureau of Energy Efficiency

Page 55: General Aspect of Energy Management and Energy Audit

transfer and consequently reducing the convective currents.Units of measure for rate of convective heat transfer are:

Metric (SI) : Watt (W) or kilowatts (kW)

Thermal Radiation

Thermal radiation is a process in which energy is transferred by electromagnetic waves similarto light waves. These waves may be both visible (light) and invisible. A very common exampleof thermal radiation is a heating element on a heater. When the heater element is first switchedon, the radiation is invisible, but you can feel the warmth it radiates. As the element heats, itwill glow orange and some of the radiation is now visible. The hotter the element, the brighterit glows and the more radiant energy it emits.

The key processes in the interaction of a substance with thermal radiation are:Absorption the process by which radiation enters a body and

becomes heatTransmission the process by which radiation passes through a bodyReflection the process by which radiation is neither absorbed or transmitted

through the body; rather it bounces off

Objects receive thermal radiation when they are struck by electromagnetic waves, therebyagitating the molecules and atoms. More agitation means more energy and a higher tempera-ture. Energy is transferred to one body from another without contact or transporting mediumsuch as air or water. In fact, thermal radiation heat transfer is the only form of heat transfer pos-sible in a vacuum.

All bodies emit a certain amount of radiation. The amount depends upon the body's tem-perature and nature of its surface. Some bodies only emit a small amount of radiant energy fortheir temperature, commonly called low emissivity materials (abbreviated low-E). Low-E win-dows are used to control the heat radiation in and out of buildings. Windows can be designedto reflect, absorb and transmit different parts of the sun's radiant energy.

The condition of a body's surface will determine the amount of thermal radiation that isabsorbed, reflected or re-emitted. Surfaces that are black and rough, such as black iron, willabsorb and re-emit almost all the energy that strikes them. Polished and smooth surfaces willnot absorb, but reflect, a large part of the incoming radiant energy.

Typical units of measure for rate of radiant heat transferMetric (SI) Watt per square meter (W/m2)

Evaporation

The change by which any substance is converted from a liquid state and carried off as vapour.

Example: People are cooled by evaporation of perspiration from the skin and refrigeration isaccomplished by evaporating the liquid refrigerant. Evaporation is a cooling process.

Condensation

The change by which any substance is converted from a gaseous state to liquid state.

2. Basics of Energy and its Various Forms

48Bureau of Energy Efficiency

Page 56: General Aspect of Energy Management and Energy Audit

Example: Condensation on the other hand is a heating process. As molecules of vapour con-dense and become liquid, their latent heat of vapourisation evidences itself again as sensibleheat, indicated by a rise in temperature. This heating effect of condensation is what causes theconsiderable rise in atmospheric temperature often noted as fog forms and as rain or snowbegins to fall.

Steam

Steam has been a popular mode of conveying energy, since the industrial revolution. The fol-lowing characteristics of steam make it so popular and useful to the industry:• High specific heat and latent heat • High heat transfer coefficient • Easy to control and distribute • Cheap and inert

Steam is used for generating power and also used in process industries, such as, sugar,paper, fertilizer, refineries, petrochemicals, chemical, food, synthetic fibre and textiles. In theprocess industries, the high pressure steam produced in the boiler, is first expanded in a steamturbine for generating power. The extraction or bleed from the turbine, which are generally atlow pressure, are used for the process. This method of producing power, by using the steam gen-erated for process in the boiler, is called "Cogeneration."

How to read a Steam Table?

Select the pressure and temperature of the steam at which you want to find the enthalpy. Readthe intersection of pressure and temperature for enthalpy (Heat content in the steam)

First law of Thermodynamics

It states that energy may be converted from one form to another, but it is never lost from thesystem.

Second Law of Thermodynamics

• In any conversion of energy from one form to another, some amount of energy will be dissipated as heat.

• Thus no energy conversion is 100 % efficient. • This principle is used in energy equipment efficiency calculations.

Law of Conservation of Matter

• In any physical or chemical change, matter is neither created nor destroyed, but it may bechanged from one form to another.

• For example, if a sample of coal were burnt in an enclosed chamber, carbon in coal wouldend up as CO2 in the air inside the chamber; In fact, for every carbon atom there would beone carbon dioxide molecule in the combustion products (each of which has one carbonatom). So the carbon atoms would be conserved, and so would every other atom. Thus, nomatter would be lost during this conversion of the coal into heat.

• This principle is used in energy and material balance calculations

2. Basics of Energy and its Various Forms

49Bureau of Energy Efficiency

Page 57: General Aspect of Energy Management and Energy Audit

2. Basics of Energy and its Various Forms

50Bureau of Energy Efficiency

2.5 Units and Conversions

The energy units are wide and varied. The usage of units varies with country, industry sector,systems such as FPS, CGS, MKS and SI, and also with generations of earlier period using FPSand recent generations using MKS. Even technology/equipment suppliers adopt units that aredifferent from the one being used by the user of that technology/equipment. For example somecompressor manufacturers specify output in m3/min while some specify in cubic feet/minute oreven in litres/second. All this cause confusion and hence the need for this chapter on units andconversions.

Energy Units

1 barrel of oil = 42 U.S. gallons (gal) = 0.16 cubic meters (m3)

1 MW 1,000 kW

1 kW 1,000 Watts

1 kWh 3,412 Btu

1 kWh 1.340 Hp hours

1,000 Btu 0.293 kWh

1 Therm 100,000 Btu (British Thermal Units)

1 Million Btu 293.1 Kilowatt hours

100,000 Btu 1 Therm

1 Watt 3.412 Btu per hour

1 Horsepower 746 Watts or 0.746 Kilo Watts

1 Horsepower hr. 2,545 Btu

1 kJ 0.239005 Kilocalories

1 Calorie 4.187 Joules

1 kcal/Kg 1.8 Btu's/lb.

1 Million Btu 252 Mega calories

1 Btu 252 Calories

1 Btu 1,055 Joules

1 Btu/lb. 2.3260 kJ/kg

1 Btu/lb. 0.5559 Kilocalories/kg

Power (Energy Rate) Equivalents

1 kilowatt (kW) 1 kilo joule /second (kJ/s)

1 kilowatt (kW) 3413 BTU/hour (Btu/hr.)

1 horsepower (hp) 746 watts (0.746 kW)

1 Ton of refrigeration 12000 Btu/hr.

Pressure:

Gauge pressure is defined relative to the prevailing atmospheric pressure (101.325 kPa at sealevel), or as absolute pressure:Absolute Pressure = Gauge Pressure + Prevailing Atmospheric Pressure

Page 58: General Aspect of Energy Management and Energy Audit

Units of measure of pressure:Metric (SI) : kilopascals (kPa)1 pascal (Pa) = 1 Newton/m2 (N/m2 )

1 physical atmosphere (atm) = 101325 Pa = 760 mm of mercury (mm Hg) = 14.69 lb-force/in2 (psi)

1 technical atmosphere (ata) = 1 kilogram-force/cm2 (kg/cm2)= 9.806650 × 104 Pa

Power:1 W = 1 J/s = 0.9478×10-3 Btu/s = 3.41214 Btu/hr

Fuel to kWh (Approximate conversion)

2. Basics of Energy and its Various Forms

51Bureau of Energy Efficiency

Natural gas M3 x 10.6 kWh

Ft3 x 0.3 kWh

therms x 29.3 kWh

LPG (propane) m3 x 25 kWh

Coal kg x 8.05 kWh

Coke kg x 10.0 kWh

Gas oil litres x 12.5 kWh

Light fuel oil litres x 12.9 kWh

Medium fuel oil litres x 13.1 kWh

Heavy fuel oil litres x 13.3 kWh

Prefixes for units in the International System

Prefix Symbol Power Example USA/Other

exa E 1018 quintillion

peta P 1015 pentagram (Pg) quadrillion/billiard

tera T 1012 terawatt (TW) trillion/billion

giga G 109 gigawatt (GW) billion/milliard

mega M 106 megawatt (MW) million

kilo k 103 kilogram (kg)

hecto h 102 hectoliter (hl)

deka da 101 dekagram (dag)

deci d 10-1 decimeter (dm)

centi c 10-2 centimeter (cm)

milli m 10-3 millimeter (mm)

micro µ 10-6 micrometer (µm)

nano n 10-9 nanosecond (ns)

pico p 10-12 picofarad (pf)

femto f 10-15 femtogram (fg)

atto a 10-18

Page 59: General Aspect of Energy Management and Energy Audit

2. Basics of Energy and its Various Forms

52Bureau of Energy Efficiency

To: TJ Gcal Mtoe MBtu GWh

From: Multiply by:

TJ 1 238.8 2.388 x 10-5 947.8 0.2778

Gcal 4.1868 x 10-3 1 10-7 3.968 1.163 x 10-3

Mtoe 4.1868 x 104 107 1 3.968 x 107 11630

MBtu 1.0551 x 10-3 0.252 2.52 x 10-8 1 2.931 x 10-4

GWh 3.6 860 8.6 x 10-5 3412 1

Energy

To: kg t lt st lb

From: multiply by:

kilogram (kg) 1 0.001 9.84 x 10-4 1.102 x 10-3 2.2046

tonne (t) 1000 1 0.984 1.1023 2204.6

long ton (lt) 1016 1.016 1 1.120 2240.0

short ton (st) 907.2 0.9072 0.893 1 2000.0

pound (lb) 0.454 4.54 x 10-4 4.46 x 10-4 5.0 x 10-4 1

Mass

To: gal U.S. gal U.K. bbl ft3 l m3

From: multiply by:

U.S. gallon (gal) 1 0.8327 0.02381 0.1337 3.785 0.0038

U.K. gallon (gal) 1.201 1 0.02859 0.1605 4.546 0.0045

Barrel (bbl) 42.0 34.97 1 5.615 159.0 0.159

Cubic foot (ft3) 7.48 6.229 0.1781 1 28.3 0.0283

Litre (l) 0.2642 0.220 0.0063 0.0353 1 0.001

Cubic metre (m3) 264.2 220.0 6.289 35.3147 1000.0 1

Volume

Page 60: General Aspect of Energy Management and Energy Audit

2. Basics of Energy and its Various Forms

53Bureau of Energy Efficiency

QUESTIONS

1. Discuss one energy conversion activity with various losses occurring stage wise.

2. The reactive power is represented by(a) kVA (b) kW (c) kVAr (d) PF

3. A fluorescent tube light consumes 40 W for the tube and 10 W for choke. If thelamp operates for 8 hours a day for 300 days in a year, calculate the total energy costper annum if the energy cost is Rs.3/- per kWh

4. Power factor is the ratio of (a) kW / kVA (b) kVA / kW (c) kVA / kVAr (d) kVAr / kV

5. Define the term load factor.

6. What do you understand by the term calorific value?

7. What are the three modes of heat transfer? Explain with examples?

8. Explain why steam is used commonly in industries?

9. If an electric heater consumes 4 kWh, what will be the equivalent kilocalories?

10. Why a cube of ice at 0oC is more effective in cooling a drink than the same quantityof water at 0oC?

11. 10 kg of steam at 100oC with latent heat of vapourisation 2260 kJ is cooled to 50oC.If the specific heat of water is 4200 J/kgoC, find the quantity of heat given out.

REFERENCES1. Energy Dictionary, Van Nostrand Reinhold Company, New York - V Daniel Hunt. 2. Cleaner Production – Energy Efficiency Manual for GERIAP, UNEP, Bangkok prepared

by National Productivity Council

www.eia.doe.gov/kids/btudef.htmlwww.calculator.org/properties.htmlwww.katmarsoftware.com

Page 61: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

Chapter 1.2 Basics of Energy and its various forms Part – I: Objective Type Questions and Answers

1. The type of energy possessed by the charged capacitor is

a) Kinetic energy b) Electrostatic c) Potential d) Magnetic

2. The energy stored in the bonds of atoms and molecules is called

a) Kinetic energy b) Chemical energy

c) Potential energy d) Magnetic energy

3. Active power consumption of motive drives AC 3 phase can be determined by using one of the following relations.

a) √3 x V x I b) √3 x V2 x I x cosϕ

c) √3 x V x I2 x Cosϕ d) √3 x V x I x Cosϕ

4. The grade of energy can be classified as low, high, extra ordinary. In case of electrical energy it would fall under ____ category. (EM/EA)

a) low grade b) extra ordinary grade c) high grade d) none of the above

5. The portion of apparent power that doesn’t do any work is termed as

a) Apparent power b) Active power

c) Reactive Power d) None of the above

6. Power factor (PF) is the ratio of (EM/EA)

a) Apparent power & Active power b) Active power & Reactive power

c) Active Power & Apparent power d) Apparent power & Reactive power

7. kVA is also called as

a) reactive power b) apparent power

c) active power d) captive power

8. The energy consumed by a 50 kW motor loaded at 40 kW over a period of 4 hours is

a. 50 kWh b) 160 kWh c) 40 kWh d) 2000 kWh

9. The ratio of maximum demand to the connected load is termed as

a) Load factor b) Demand factor

c) Contract demand d) none of the above

10. A single phase induction motor is drawing 10 amps at 230 volts. If the operating power factor of the motor is 0.9, then the power drawn by the motor is

a) 2.3 kW b) 3.58 kW c) 2.07 kW d) 2.70 kW

11. The quantity of heat required to raise the temperature of 1 gram of water by 1 OC is termed as

a) Specific heat b) Heat capacity c) One Calorie d) Sensible heat

12. Nameplate kW or HP rating of a motor indicates a) input kW to the motor b) output kW of the motorc) minimum input kW to the motor d) maximum input kW to the motor

1.2.Basics of Energy and its various forms 7

Page 62: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

13. The quantity of heat required to change 1 kg of the substance from liquid to vapor state without change of temperature is termed as

a) Latent heat of fusion b) Latent heat of vaporization

c) Heat capacity d) Sensible heat

14. The latent heat of condensation of 1 kg of steam at 100 °C to form water at 100 °C, it gives out the heat of

a) 580 kCal b) 540 kCal c) 620 kCal d) 2260 kCal

15. The specific heat of ____ is very high compared to other common substances listed below.

a) Lead b) Mercury c) Water d) Alcohol

16. The property of viscosity of liquid fuels:

a) decreases with decreasing temperature

b) increases with increasing temperature

c) decreases with increasing temperature

d) ) None of the above

17. The quantity of heat Q, supplied to a substance to increase its temperature depends upon the following. a) sensible heat added b) latent heat of fusion c) specific heat of the substance d) heat capacity

18. Unit of specific heat in SI system is_________. a) joule /kg °C b) kg/cm2 c) kcal/m3 d) kcal/cm2

19. The change by which any substance is converted from a gaseous state to liquid state is termed as -----

a) condensation b) Evaporation c) Fusion d) Phase change

20. The method of producing power by utilizing steam generated for process in the boiler is termed as -----

a) Extraction b) Cogeneration c) Both a & b d) Neither a nor b

Part – II: Short Type Question and Answers

1. Write a note on various forms of energy with examples.

There are two types of energy-stored (potential) energy and working (kinetic) energy. Potential energy is stored energy and the energy of position. It exists in various forms. Eg: chemical energy, nuclear energy, stored mechanical energy, gravitational energy are different types of potential energy.

Kinetic energy is energy in motion-the motion of waves, electrons, atoms, molecules and substances. It exists in various forms. Eg: radiant energy, thermal energy, motion, sound, electrical energy are various forms of kinetic energy.

2. What are the various grades of energy with an example

There are two grades of energy; namely high grade energy and low grade energy.

Electrical and chemical energy are high grade energy, because the energy is concentrated in a small space. Eg: electricity used for melting of metals.

1.2.Basics of Energy and its various forms 8

Page 63: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

Heat is low grade energy. Eg: Heat available from sun

3. What are the characteristics of Direct current and Alternating current?

Characteristics of Direct current are

Direction of the flow of positive and negative charges does not change with time

Direction of current is constant with time

Potential difference between two points of the circuit does not change sign in time

Characteristics of Alternating current are

Direction of current reverses periodically in time

Voltage between two points of the circuit changes sign periodically in time

In 50 cycle AC, current reverses direction 100 times a second

4. What is ‘Reactive power’ and ‘Active power’?

Reactive power (kVAr) is the portion of the apparent power that does no work. This type of power must be supplied to all types of magnetizing equipment, such as motors, transformers etc. larger the magnetizing requirement, larger the kVAr. Active power is the work producing part of the apparent power.

5. What is power factor and how it is evaluated in the electrical system?

Power factor is the ratio between the active power (kW) and apparent power (kVA).

)(

)(kVAwerApparentpo

kWrActivepowerPowerfacto =

2)(2)(

)(kVArkW

kWrPowerfacto+

=

6. Differentiate between ‘contract demand’ and ‘maximum demand’?

Contract demand is the amount of electric power that a customer demands from utility in a specified interval (Unit used is kVA or kW) while the maximum kW and or kVA requirement over a billing cycle is called as maximum demand.

7. Define the term ‘Load Factor’ with an example?

It is the ratio of average load to maximum load. In other words, it is the ratio of energy consumed during a given period of time to the maximum energy demand if maximum load is maintained through out that time period. For eg: the energy consumed by a plant during the day is 2000 kWh. The maximum load recorded during the day was 125 kW. The load factor for the above would be 2000/ (125 x 24) = 66.7%

8. Explain the importance of TOD (time of the day) tariff?

Many electrical utilities like to have flat demand curve to achieve high plant efficiency. They encourage user to draw more power during off-peak hours (say during night time) and less power during peak hours. As per their plan, they offer TOD Tariff, which may be incentives or disincentives. Energy meter will record peak and non-peak consumption separately by timer control. TOD tariff gives opportunity for the user to reduce their billing, as off peak hour tariff charged are quite low in comparison to peak hour tariff.

1.2.Basics of Energy and its various forms 10

Page 64: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

9. Draw the vector diagram showing the relation between kW, kVA & kVAr and angle θ between kW and kVA.

10. A 45 kW motor is drawing 30 kW of power at a given point of time. Calculate the motor loading at full load if the efficiency of the motor is 90%

Rated motor input power = 45/0.9

= 50 kW

Actual power drawn = 30 kW

% loading on the motor = 30/50

= 60%

11. A 250 W sodium vapor lamp is installed on a street. The supply voltage for a street light is 230 V and it operates for around 12 hours in a day. Considering the current of 2 amps and power factor 0.85 calculate the energy consumption per day

Energy consumption = V x I x Cos ǿ x no. of hours

= 230 x 2 x 0.85 x 12

= 4692 Watt hours or 4.692 kWh

12. A substance of mass 25 kgs @ 25OC is heated to 75 OC. if the specific heat of the substance is 0.25 kCal/kg OC, calculate the quantity of heat added in the substance?

Quantity of heat = m x Cp x ∆T

= 25 x 0.25 x (75-25)

= 312.5 kcal

13. A three phase induction 75 kW motor operates at 55 kW. The measured voltage is 415 V, current is 80 amps. Calculate the power factor of the motor?

Power consumption = 3 x V x I x Cos ǿ

(55 x 1000) = 3 x 415 x 80 x Cos ǿ

Power factor (Cos ǿ) = (55 x 1000)/( 3 x 415 x 80)

= 0.96

14. Define the terms ‘temperature’ and ‘pressure’

Temperature and pressure are measures of the physical state of a substance. They are closely related to the energy contained in the substance. As a result, measurements of temperature and pressure provide a means of determining energy content.

Temperature

It is the degree of hotness or coldness measured on a definite scale. Heat is a form of energy; temperature, a measurement of its thermal effects. In other words, temperature is a means of determining sensible heat content of the substance

Pressure

It is the force per unit area applied to outside of a body. When we heat a gas in a confined

kVA kVAr

kW

1.2.Basics of Energy and its various forms 11

Page 65: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

space, we create a pressure increase, or more push. For example: heating the air inside a balloon will cause the balloon to stretch as the pressure increases.

15. Differentiate the terms ‘specific heat’ and ‘heat capacity’?

Specific heat is defined as the quantity of heat required to raise the temperature of 1 kg of a substance through 1 OC. Heat capacity is defined as the quantity of heat required to raise the temperature of the object by 1 OC.

16. Explain the terms fusion, melting point and vaporization of a substance?

The change of state from the solid state to a liquid state is called fusion. The fixed temperature at which a solid changes into a liquid is called its melting point. The change of a state from a liquid state to a gas is called vaporization.

17. Define ‘latent heat of fusion’ and ‘latent heat of vaporization’?

Latent heat of fusion (L) of a substance is the quantity of heat required to convert 1 kg of solid to liquid state without change of temperature.

Latent heat of vaporization (L) of a substance is the quantity of heat required to change 1 kg of the substance from liquid to vapor state without change of temperature.

18. What is ‘calorific value’ and how it is evaluated by using bomb calorie meter?

Calorific value is energy content in an organic matter. It can be measured by burning it and measuring the heat released. This is done by placing a sample of known mass in a bomb calorimeter. A thermometer is placed inside and the increase in temperature after the sample is burnt completely is measured. From this data, energy content in the organic matter can be found out.

19. What is ‘thermal radiation’ ? Give an example.

Thermal radiation is a process in which energy is transferred by electro magnetic waves, similar to light waves. These waves may be both visible (light) and invisible. A very common example of thermal radiation is a heating element of a resistant heater.

20. Define ‘Law of conservation of matter’.

Law of conservation of matter states that in any physical or chemical change, matter is neither created nor destroyed, but it may be changed from one form to another.

Part – III: Long type questions and answers

1. An industry is having contract demand of 1000 kVA. The minimum billing demand is 75% of the contract demand. The connected load of the plant is 2000 kVA. The recorded demand and power factor for the month of March 2003 is 1200 kVA and 0.8. The monthly consumption is 2.0 lakh units. The average load and maximum load of the industry is 700 kW and 900 kW respectively. Calculate

1. Minimum billing demand of the industry

2. Load factor of the plant

3. Demand factor of the plant

1. Minimum billing demand = 1000 x 0.75 = 750 kVA

2. Load Factor = Average Load / Maximum Load = 700/900 = 0.78

3. Demand factor = Maximum demand / Connected load = 1200/2000 = 0.60

1.2.Basics of Energy and its various forms 12

Page 66: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

2. The contract demand of plant is 1000 kVA. The minimum billing demand is 75% of the contract demand. The basic tariff structure is as follows:

Demand charges : Rs. 180 per kVA / month

Unit charges : Rs. 3.75 for the first one lakh units / month

Rs. 3.50 above one lakh units / month

Fuel surcharge : Rs. 0.20 per unit / month

Service Tax : Rs. 0.25 per unit / month

Meter rent : Rs 500 / month

The energy consumption is 3,15,000 units and the maximum demand recorded is 600 kVA. Calculate the cost of monthly electricity consumption? Demand charges : 750 x 180 : Rs. 1,35,000

Unit charges : 100000 x 3.75 : Rs. 3,75,000

: 215000 x 3.50 : Rs. 7,52,500

Fuel surcharge : 315000 x 0.20 : Rs. 63,000

Service Tax : 315000 x 0.25 : Rs. 78,750

Meter rent : : Rs. 500

Total Cost : Rs. 14,04,750

3. What is heat transfer? Briefly explain three primary modes of heat transfer.

The rate of energy transfer is called heat transfer.

Heat is transferred by three primary modes:

o Conduction (Energy transfer in a solid)

o Convection (Energy transfer in a fluid)

o Radiation (Does not need a material to travel through)

Conduction

The conduction of heat takes places, when two bodies are in contact with one another. If one body is at a higher temperature than the other, the motion of the molecules in the hotter body will agitate the molecules at the point of contact in the cooler body and consequently result in increase in temperature.

Convection

The transfer of heat by convection involves the movement of a fluid such as a gas or liquid from the hot to the cold portion.

Thermal Radiation

Thermal radiation is a process in which energy is transferred by electromagnetic waves similar to light waves. These waves may be both visible (light) and invisible.

1.2.Basics of Energy and its various forms 13

Page 67: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

4. What are the differences of AC current and DC current? The characteristics of AC current are o Direction of the current reverses periodically in time o Voltage between two points of the circuit changes sign periodically in time o In 50 cycle AC, current reverses direction 100 times a second (two times during one

cycle) The characteristics of DC current are o Direction of the flow of positive and negative charges does not change with time o Direction of current is constant in time o Potential difference between two points of the circuit does not change sign in time

5. Describe the merits of using steam in industries.

Steam has been a popular mode of conveying energy, since the industrial revolution. The following characteristics of steam make it so popular and useful to the industry:

• Highest specific heat and latent heat

• Highest heat transfer coefficient

• Easy to control and distribute

• Cheap and inert

Steam is used for generating power and also used in process industries, such as, sugar, paper, fertilizer, refineries, petrochemicals, chemical, food, synthetic fiber and textiles. In the process industries, the high pressure steam produced in the boiler, is first expanded in a steam turbine for generating power. The extraction or bleed from the turbine, which are generally at low pressure, are used for the process. This method of producing power, by the steam generated for process in the boiler, is called "cogeneration."

1.2.Basics of Energy and its various forms 14

Page 68: General Aspect of Energy Management and Energy Audit

54Bureau of Energy Efficiency

SyllabusEnergy Management & Audit: Definition, Energy audit- need, Types of energy audit,Energy management (audit) approach-understanding energy costs, Bench marking, Energyperformance, Matching energy use to requirement, Maximizing system efficiencies,Optimizing the input energy requirements, Fuel and energy substitution, Energy auditinstruments

"The judicious and effective use of energy to maximize profits (minimizecosts) and enhance competitive positions"

(Cape Hart, Turner and Kennedy, Guide to Energy Management Fairmont press inc. 1997)

"The strategy of adjusting and optimizing energy, using systems and procedures so as toreduce energy requirements per unit of output while holding constant or reducing totalcosts of producing the output from these systems"

3.1 Definition & Objectives of Energy Management

The fundamental goal of energy management is to produce goods and provide services with theleast cost and least environmental effect.

The term energy management means many things to many people. One definition of ener-gy management is:

Another comprehensive definition is

The objective of Energy Management is to achieve and maintain optimum energy procurementand utilisation, throughout the organization and:

• To minimise energy costs / waste without affecting production & quality• To minimise environmental effects.

3.2 Energy Audit: Types And Methodology

Energy Audit is the key to a systematic approach for decision-making in the area of energy man-agement. It attempts to balance the total energy inputs with its use, and serves to identify allthe energy streams in a facility. It quantifies energy usage according to its discrete functions.Industrial energy audit is an effective tool in defining and pursuing comprehensive energy man-agement programme.

As per the Energy Conservation Act, 2001, Energy Audit is defined as "the verification, mon-

3. ENERGY MANAGEMENT AND AUDIT

Page 69: General Aspect of Energy Management and Energy Audit

3. Energy Management and Audit

55Bureau of Energy Efficiency

itoring and analysis of use of energy including submission of technical report containing rec-ommendations for improving energy efficiency with cost benefit analysis and an action plan toreduce energy consumption".

3.2.1 Need for Energy Audit

In any industry, the three top operating expenses are often found to be energy (both electricaland thermal), labour and materials. If one were to relate to the manageability of the cost orpotential cost savings in each of the above components, energy would invariably emerge as atop ranker, and thus energy management function constitutes a strategic area for cost reduction.Energy Audit will help to understand more about the ways energy and fuel are used in anyindustry, and help in identifying the areas where waste can occur and where scope for improve-ment exists.

The Energy Audit would give a positive orientation to the energy cost reduction, preventivemaintenance and quality control programmes which are vital for production and utility activi-ties. Such an audit programme will help to keep focus on variations which occur in the energycosts, availability and reliability of supply of energy, decide on appropriate energy mix, identi-fy energy conservation technologies, retrofit for energy conservation equipment etc.

In general, Energy Audit is the translation of conservation ideas into realities, by lendingtechnically feasible solutions with economic and other organizational considerations within aspecified time frame.

The primary objective of Energy Audit is to determine ways to reduce energy consumptionper unit of product output or to lower operating costs. Energy Audit provides a " bench-mark"(Reference point) for managing energy in the organization and also provides the basis for plan-ning a more effective use of energy throughout the organization.

3.2.2 Type of Energy Audit

The type of Energy Audit to be performed depends on:- Function and type of industry- Depth to which final audit is needed, and - Potential and magnitude of cost reduction desiredThus Energy Audit can be classified into the following two types.i) Preliminary Auditii) Detailed Audit

3.2.3 Preliminary Energy Audit Methodology

Preliminary energy audit is a relatively quick exercise to:• Establish energy consumption in the organization• Estimate the scope for saving• Identify the most likely (and the easiest areas for attention• Identify immediate (especially no-/low-cost) improvements/ savings• Set a 'reference point'• Identify areas for more detailed study/measurement• Preliminary energy audit uses existing, or easily obtained data

Page 70: General Aspect of Energy Management and Energy Audit

3. Energy Management and Audit

56Bureau of Energy Efficiency

3.2.4 Detailed Energy Audit Methodology

A comprehensive audit provides a detailed energy project implementation plan for a facility,since it evaluates all major energy using systems.

This type of audit offers the most accurate estimate of energy savings and cost. It considersthe interactive effects of all projects, accounts for the energy use of all major equipment, andincludes detailed energy cost saving calculations and project cost.

In a comprehensive audit, one of the key elements is the energy balance. This is based on aninventory of energy using systems, assumptions of current operating conditions and calculationsof energy use. This estimated use is then compared to utility bill charges.

Detailed energy auditing is carried out in three phases: Phase I, II and III.

Phase I - Pre Audit PhasePhase II - Audit PhasePhase III - Post Audit Phase

A Guide for Conducting Energy Audit at a Glance

Industry-to-industry, the methodology of Energy Audits needs to be flexible. A comprehensive ten-step methodology for conduct of Energy Audit at field level is pre-

sented below. Energy Manager and Energy Auditor may follow these steps to start with andadd/change as per their needs and industry types.

Page 71: General Aspect of Energy Management and Energy Audit

3. Energy Management and Audit

57Bureau of Energy Efficiency

Ten Steps Methodology for Detailed Energy Audit

Page 72: General Aspect of Energy Management and Energy Audit

3. Energy Management and Audit

58Bureau of Energy Efficiency

Page 73: General Aspect of Energy Management and Energy Audit

3. Energy Management and Audit

59Bureau of Energy Efficiency

Phase I -Pre Audit Phase Activities

A structured methodology to carry out an energy audit is necessary for efficient working. Aninitial study of the site should always be carried out, as the planning of the procedures neces-sary for an audit is most important.

Initial Site Visit and Preparation Required for Detailed Auditing

An initial site visit may take one day and gives the Energy Auditor/Engineer an opportunity tomeet the personnel concerned, to familiarize him with the site and to assess the procedures nec-essary to carry out the energy audit.

During the initial site visit the Energy Auditor/Engineer should carry out the followingactions: -• Discuss with the site's senior management the aims of the energy audit.• Discuss economic guidelines associated with the recommendations of the audit.• Analyse the major energy consumption data with the relevant personnel.• Obtain site drawings where available - building layout, steam distribution, compressed air

distribution, electricity distribution etc.• Tour the site accompanied by engineering/production

The main aims of this visit are: -

• To finalise Energy Audit team• To identify the main energy consuming areas/plant items to be surveyed during the audit.• To identify any existing instrumentation/ additional metering required.• To decide whether any meters will have to be installed prior to the audit eg. kWh, steam,

oil or gas meters.• To identify the instrumentation required for carrying out the audit.• To plan with time frame• To collect macro data on plant energy resources, major energy consuming centers• To create awareness through meetings/ programme

Phase II- Detailed Energy Audit Activities

Depending on the nature and complexity of the site, a comprehensive audit can take from sev-eral weeks to several months to complete. Detailed studies to establish, and investigate, energyand material balances for specific plant departments or items of process equipment are carriedout. Whenever possible, checks of plant operations are carried out over extended periods oftime, at nights and at weekends as well as during normal daytime working hours, to ensure thatnothing is overlooked.

The audit report will include a description of energy inputs and product outputs by majordepartment or by major processing function, and will evaluate the efficiency of each step of themanufacturing process. Means of improving these efficiencies will be listed, and at least a pre-liminary assessment of the cost of the improvements will be made to indicate the expected pay-back on any capital investment needed. The audit report should conclude with specific recom-mendations for detailed engineering studies and feasibility analyses, which must then be per-formed to justify the implementation of those conservation measures that require investments.

Page 74: General Aspect of Energy Management and Energy Audit

3. Energy Management and Audit

60Bureau of Energy Efficiency

The information to be collected during the detailed audit includes: -

1. Energy consumption by type of energy, by department, by major items of process equipment, by end-use

2. Material balance data (raw materials, intermediate and final products, recycledmaterials, use of scrap or waste products, production of by-products for re-use in otherindustries, etc.)

3. Energy cost and tariff data4. Process and material flow diagrams5. Generation and distribution of site services (eg.compressed air, steam).6. Sources of energy supply (e.g. electricity from the grid or self-generation)7. Potential for fuel substitution, process modifications, and the use of co-generation

systems (combined heat and power generation).8. Energy Management procedures and energy awareness training programs within the

establishment.Existing baseline information and reports are useful to get consumption pattern, production costand productivity levels in terms of product per raw material inputs. The audit team should col-lect the following baseline data:

- Technology, processes used and equipment details- Capacity utilisation - Amount & type of input materials used - Water consumption- Fuel Consumption- Electrical energy consumption- Steam consumption- Other inputs such as compressed air, cooling water etc - Quantity & type of wastes generated- Percentage rejection / reprocessing- Efficiencies / yield

DATA COLLECTION HINTS

It is important to plan additional data gathering carefully. Here are some basic tips to avoid wasting timeand effort:

• measurement systems should be easy to use and provide the information to the accuracy that is needed, not the accuracy that is technically possible

• measurement equipment can be inexpensive (flow rates using a bucket and stopwatch)• the quality of the data must be such that the correct conclusions are drawn (what grade of prod

uct is on, is the production normal etc)• define how frequent data collection should be to account for process variations. • measurement exercises over abnormal workload periods (such as startup and shutdowns)• design values can be taken where measurements are difficult (cooling water through heat exchang

er)DO NOT ESTIMATE WHEN YOU CAN CALCULATE

DO NOT CALCULATE WHEN YOU CAN MEASURE

Page 75: General Aspect of Energy Management and Energy Audit

3. Energy Management and Audit

61Bureau of Energy Efficiency

Draw process flow diagram and list process steps; identify waste streams and obviousenergy wastage

An overview of unit operations, important process steps, areas of material and energy use andsources of waste generation should be gathered and should be represented in a flowchart asshown in the figure below. Existing drawings, records and shop floor walk through will help inmaking this flow chart. Simultaneously the team should identify the various inputs & outputstreams at each process step.

Example: A flowchart of Penicillin-G manufacturing is given in the figure3.1 below. Notethat waste stream (Mycelium) and obvious energy wastes such as condensate drained and steamleakages have been identified in this flow chart

The audit focus area depends on several issues like consumption of input resources, energyefficiency potential, impact of process step on entire process or intensity of waste generation /energy consumption. In the above process, the unit operations such as germinator, pre-fermen-tor, fermentor, and extraction are the major conservation potential areas identified.

Figure 3.1

Page 76: General Aspect of Energy Management and Energy Audit

3. Energy Management and Audit

62Bureau of Energy Efficiency

Identification of Energy Conservation Opportunities

Fuel substitution: Identifying the appropriate fuel for efficient energy conversion

Energy generation :Identifying Efficiency opportunities in energy conversion equipment/util-ity such as captive power generation, steam generation in boilers, thermic fluid heating, optimalloading of DG sets, minimum excess air combustion with boilers/thermic fluid heating, opti-mising existing efficiencies, efficienct energy conversion equipment, biomass gasifiers,Cogeneration, high efficiency DG sets, etc.

Energy distribution: Identifying Efficiency opportunities network such as transformers,cables, switchgears and power factor improvement in electrical systems and chilled water, cool-ing water, hot water, compressed air, Etc.

Energy usage by processes: This is where the major opportunity for improvement and manyof them are hidden. Process analysis is useful tool for process integration measures.

Technical and Economic feasibility

The technical feasibility should address the following issues

• Technology availability, space, skilled manpower, reliability, service etc• The impact of energy efficiency measure on safety, quality, production or process.• The maintenance requirements and spares availability

The Economic viability often becomes the key parameter for the management acceptance. Theeconomic analysis can be conducted by using a variety of methods. Example: Pay back method,Internal Rate of Return method, Net Present Value method etc. For low investment short dura-tion measures, which have attractive economic viability, simplest of the methods, payback isusually sufficient. A sample worksheet for assessing economic feasibility is provided below:

Classification of Energy Conservation Measures

Based on energy audit and analyses of the plant, a number of potential energy saving projectsmay be identified. These may be classified into three categories:

Page 77: General Aspect of Energy Management and Energy Audit

3. Energy Management and Audit

63Bureau of Energy Efficiency

1. Low cost - high return;2. Medium cost - medium return;3. High cost - high return

Normally the low cost - high return projects receive priority. Other projects have to be analyzed,engineered and budgeted for implementation in a phased manner. Projects relating to energycascading and process changes almost always involve high costs coupled with high returns, andmay require careful scrutiny before funds can be committed. These projects are generally com-plex and may require long lead times before they can be implemented. Refer Table 3.1 for pro-ject priority guidelines.

3.3 Energy Audit Reporting Format

After successfully carried out energy audit energy manager/energy auditor should report to thetop management for effective communication and implementation. A typical energy auditreporting contents and format are given below. The following format is applicable for most ofthe industries. However the format can be suitably modified for specific requirement applicablefor a particular type of industry.

Page 78: General Aspect of Energy Management and Energy Audit

3. Energy Management and Audit

64Bureau of Energy Efficiency

Page 79: General Aspect of Energy Management and Energy Audit

3. Energy Management and Audit

65Bureau of Energy Efficiency

Page 80: General Aspect of Energy Management and Energy Audit

3. Energy Management and Audit

66Bureau of Energy Efficiency

The following Worksheets (refer Table 3.2 & Table 3.3) can be used as guidance for energyaudit assessment and reporting.

TABLE 3.2 SUMMARY OF ENERGY SAVING RECOMMENDATIONS

S.No. Energy Saving Annual Energy Annual Capital SimpleRecommendations (Fuel & Electricity) Savings Investment Payback

Savings (kWh/MT Rs.Lakhs (Rs.Lakhs) periodor kl/MT)

1

2

3

4

Total

TABLE 3.3 TYPES AND PRIORITY OF ENERGY SAVING MEASURES

Type of Energy Annual Annual Saving Options Electricity Savings Priority

/Fuel savings

KWh/MT or kl/MT (Rs Lakhs)

A No Investment(Immediate)

- OperationalImprovement- Housekeeping

B Low Investment(Short to Medium Term)

- Controls- Equipment Modification- Process change

C High Investment(Long Term)

- Energy efficient Devices- Product modification- Technology Change

Page 81: General Aspect of Energy Management and Energy Audit

3. Energy Management and Audit

67Bureau of Energy Efficiency

Page 82: General Aspect of Energy Management and Energy Audit

3.4 Understanding Energy Costs

Understanding energy cost is vital factor for awareness creation and saving calculation. Inmany industries sufficient meters may not be available to measure all the energy used. In suchcases, invoices for fuels and electricity will be useful. The annual company balance sheet is theother sources where fuel cost and power are given with production related information.

Energy invoices can be used for the following purposes:• They provide a record of energy purchased in a given year, which gives a base-line for

future reference• Energy invoices may indicate the potential for savings when related to production

requirements or to air conditioning requirements/space heating etc.• When electricity is purchased on the basis of maximum demand tariff• They can suggest where savings are most likely to be made.• In later years invoices can be used to quantify the energy and cost savings made through

energy conservation measures

Fuel Costs

A wide variety of fuels are available forthermal energy supply. Few are listedbelow:

• Fuel oil• Low Sulphur Heavy Stock (LSHS)• Light Diesel Oil (LDO)• Liquefied Petroleum Gas (LPG)• COAL• LIGNITE• WOOD ETC.

Understanding fuel cost is fairly simpleand it is purchased in Tons or Kiloliters.Availability, cost and quality are the mainthree factors that should be consideredwhile purchasing. The following factors should be taken into account during procurement offuels for energy efficiency and economics.

• Price at source, transport charge, type of transport• Quality of fuel (contaminations, moisture etc)• Energy content (calorific value)

Power Costs

Electricity price in India not only varies from State to State, but also city to city and consumerto consumer though it does the same work everywhere. Many factors are involved in decidingfinal cost of purchased electricity such as:

• Maximum demand charges, kVA(i.e. How fast the electricity is used? )

3. Energy Management and Audit

68Bureau of Energy Efficiency

Figure 3.2 Annual Energy Bill

Page 83: General Aspect of Energy Management and Energy Audit

3. Energy Management and Audit

69Bureau of Energy Efficiency

• Energy Charges, kWh(i.e., How much electricity is consumed? )

• TOD Charges, Peak/Non-peak period(i.e. When electricity is utilized ?)

• Power factor Charge, P.F(i.e., Real power use versus Apparent power use factor )

• Other incentives and penalties applied from time to time• High tension tariff and low tension tariff rate changes• Slab rate cost and its variation • Type of tariff clause and rate for various categories such as commercial, residential,

industrial, Government, agricultural, etc.• Tariff rate for developed and underdeveloped area/States • Tax holiday for new projects

Example: Purchased energy Bill

A typical summary of energy purchased in an industry based on the invoices

Unfortunately the different forms of energy are sold in different units e.g. kWh of electricity,liters of fuel oil, tonne of coal. To allow comparison of energy quantities these must be con-verted to a common unit of energy such as kWh, Giga joules, kCals etc.

Electricity (1 kWh) = 860 kCal/kWh (0.0036 GJ)Heavy fuel oil (Gross calorific value, GCV) =10000 kCal/litre ( 0.0411 GJ/litre)Coal (Gross calorific value, GCV) =4000 kCal/kg ( 28 GJ/ton)

3.5 Benchmarking and Energy Performance

Benchmarking of energy consumption internally (historical / trend analysis) and externally(across similar industries) are two powerful tools for performance assessment and logical evo-lution of avenues for improvement. Historical data well documented helps to bring out energyconsumption and cost trends month-wise / day-wise. Trend analysis of energy consumption,cost, relevant production features, specific energy consumption, help to understand effects ofcapacity utilization on energy use efficiency and costs on a broader scale.

External benchmarking relates to inter-unit comparison across a group of similar units.However, it would be important to ascertain similarities, as otherwise findings can be grossly

TABLE 3.4

Type of energy Original units Unit Cost Monthly Bill Rs.

Electricity 5,00,000 kWh Rs.4.00/kWh 20,00,000

Fuel oil 200 kL Rs.10,000/ kL 20,00,000

Coal 1000 tons Rs.2,000/ton 20,00,000

Total 60,00,000

Page 84: General Aspect of Energy Management and Energy Audit

3. Energy Management and Audit

70Bureau of Energy Efficiency

misleading. Few comparative factors, which need to be looked into while benchmarking exter-nally are:

• Scale of operation• Vintage of technology• Raw material specifications and quality• Product specifications and quality

Benchmarking energy performance permits• Quantification of fixed and variable energy consumption trends vis-à-vis production

levels• Comparison of the industry energy performance with respect to various production

levels (capacity utilization)• Identification of best practices (based on the external benchmarking data)• Scope and margin available for energy consumption and cost reduction• Basis for monitoring and target setting exercises.

The benchmark parameters can be:• Gross production related

e.g. kWh/MT clinker or cement produced (cement plant)e.g. kWh/kg yarn produced (Textile unit)e.g. kWh/MT, kCal/kg, paper produced (Paper plant)e.g. kCal/kWh Power produced (Heat rate of a power plant)e.g. Million kilocals/MT Urea or Ammonia (Fertilizer plant)e.g. kWh/MT of liquid metal output (in a foundry)

• Equipment / utility relatede.g. kW/ton of refrigeration (on Air conditioning plant)e.g. % thermal efficiency of a boiler plante.g. % cooling tower effectiveness in a cooling towere.g. kWh/NM3 of compressed air generatede.g. kWh /litre in a diesel power generation plant.

While such benchmarks are referred to, related crucial process parameters need mentioning formeaningful comparison among peers. For instance, in the above case:

• For a cement plant - type of cement, blaine number (fineness) i.e. Portland and process used (wet/dry) are to be reported alongside kWh/MT figure.

• For a textile unit - average count, type of yarn i.e. polyester/cotton, is to be reported along side kWh/square meter.

• For a paper plant - paper type, raw material (recycling extent), GSM quality is some important factors to be reported along with kWh/MT, kCal/Kg figures.

• For a power plant / cogeneration plant - plant % loading, condenser vacuum, inlet cooling water temperature, would be important factors to be mentioned alongside heat rate (kCal/kWh).

• For a fertilizer plant - capacity utilization(%) and on-stream factor are two inputs worth comparing while mentioning specific energy consumption

• For a foundry unit - melt output, furnace type, composition (mild steel, high carbon steel/cast iron etc.) raw material mix, number or power trips could be some useful oper

Page 85: General Aspect of Energy Management and Energy Audit

ating parameters to be reported while mentioning specific energy consumption data.• For an Air conditioning (A/c) plant - Chilled water temperature level and refrigeration

load (TR) are crucial for comparing kW/TR.• For a boiler plant - fuel quality, type, steam pressure, temperature, flow, are useful com

parators alongside thermal efficiency and more importantly, whether thermal efficiency is on gross calorific value basis or net calorific value basis or whether the computation is by direct method or indirect heat loss method, may mean a lot in benchmarking exercise for meaningful comparison.

• Cooling tower effectiveness - ambient air wet/dry bulb temperature, relative humidity, air and circulating water flows are required to be reported to make meaningful sense.

• Compressed air specific power consumption - is to be compared at similar inlet air temperature and pressure of generation.

• Diesel power plant performance - is to be compared at similar loading %, steady run condition etc.

Plant Energy Performance

Plant energy performance (PEP) is the measure of whether a plant is now using more or lessenergy to manufacture its products than it did in the past: a measure of how well the energymanagement programme is doing. It compares the change in energy consumption from oneyear to the other considering production output. Plant energy performance monitoring comparesplant energy use at a reference year with the subsequent years to determine the improvementthat has been made.

However, a plant production output may vary from year to year and the output has a sig-nificant bearing on plant energy use. For a meaningful comparison, it is necessary to determinethe energy that would have been required to produce this year production output, if the planthad operated in the same way as it did during the reference year. This calculated value can thenbe compared with the actual value to determine the improvement or deterioration that has takenplace since the reference year.

Production factor

Production factor is used to determine the energy that would have been required to produce thisyear's production output if the plant had operated in the same way as it did in the reference year.It is the ratio of production in the current year to that in the reference year.

Reference Year Equivalent Energy Use

The reference year's energy use that would have been used to produce the current year's pro-duction output may be called the "reference year energy use equivalent" or "reference yearequivalent" for short. The reference year equivalent is obtained by multiplying the referenceyear energy use by the production factor (obtained above)

Reference year equivalent = Reference year energy use x Production factor

The improvement or deterioration from the reference year is called "energy performance" and

3. Energy Management and Audit

71Bureau of Energy Efficiency

productionsyearReferencePr

'

' productionsyearCurrent=factoroduction

Page 86: General Aspect of Energy Management and Energy Audit

3. Energy Management and Audit

72Bureau of Energy Efficiency

is a measure of the plant's energy management progress. It is the reduction or increase in thecurrent year's energy use over the reference, and is calculated by subtracting the current year'senergy use from the reference years equivalent. The result is divided by the reference yearequivalent and multiplied by 100 to obtain a percentage.

The energy performance is the percentage of energy saved at the current rate of use comparedto the reference year rate of use. The greater the improvement, the higher the number will be.

Monthly Energy Performance

Experience however, has shown that once a plant has started measuring yearly energy perfor-mance, management wants more frequent performance information in order to monitor andcontrol energy use on an on-going basis. PEP can just as easily be used for monthly reportingas yearly reporting.

3.6 Matching Energy Usage to Requirement

Mismatch between equipment capacity and user requirement often leads to inefficiencies due topart load operations, wastages etc. Worst case design, is a designer's characteristic, while opti-mization is the energy manager's mandate and many situations present themselves towards anexercise involving graceful matching of energy equipment capacity to end-use needs. Someexamples being:

• Eliminate throttling of a pump by impeller trimming, resizing pump, installing variable speed drives

• Eliminate damper operations in fans by impeller trimming, installing variable speed drives, pulley diameter modification for belt drives, fan resizing for better efficiency.

• Moderation of chilled water temperature for process chilling needs• Recovery of energy lost in control valve pressure drops by back pressure/turbine adop

tion• Adoption of task lighting in place of less effective area lighting

3.7 Maximising System Efficiency

Once the energy usage and sources are matched properly, the next step is to operate the equip-ment efficiently through best practices in operation and maintenance as well as judicious tech-nology adoption. Some illustrations in this context are:

• Eliminate steam leakages by trap improvements• Maximise condensate recovery• Adopt combustion controls for maximizing combustion efficiency• Replace pumps, fans, air compressors, refrigeration compressors, boilers, furnaces,

heaters and other energy consuming equipment, wherever significant energy efficiency margins exist.

100xequivalentyear Reference

energy syear'Current -equivalentyear Reference eperformancenergy Plant =

Page 87: General Aspect of Energy Management and Energy Audit

3. Energy Management and Audit

73Bureau of Energy Efficiency

Optimising the Input Energy Requirements

Consequent upon fine-tuning the energy use practices, attention is accorded to considerationsfor minimizing energy input requirements. The range of measures could include:

• Shuffling of compressors to match needs.• Periodic review of insulation thickness• Identify potential for heat exchanger networking and process integration.• Optimisation of transformer operation with respect to load.

3.8 Fuel and Energy Substitution

Fuel substitution: Substituting existing fossil fuel with more efficient and less cost/less pol-luting fuel such as natural gas, biogas and locally available agro-residues.

Energy is an important input in the production. There are two ways to reduce energy depen-dency; energy conservation and substitution.

Fuel substitution has taken place in all the major sectors of the Indian economy. Keroseneand Liquefied Petroleum Gas (LPG) have substituted soft coke in residential use. Few examples of fuel substitution

• Natural gas is increasingly the fuel of choice as fuel and feedstock in the fertilizer, petrochemicals, power and sponge iron industries.

• Replacement of coal by coconut shells, rice husk etc.• Replacement of LDO by LSHS

Few examples of energy substitution

Replacement of electric heaters by steam heaters Replacement of steam based hotwater by solar systems

Case Study : Example on Fuel Substitution

A textile process industry replaced old fuel oil fired thermic fluid heater with agro fuel firedheater. The economics of the project are given below:

A: Title of Recommendation : Use of Agro Fuel (coconut chips) in place of Furnaceoil in a Boiler

B: Description of Existing System and its operation : A thermic fluid heater with furnace oil currently.

In the same plant a coconut chip fired boiler is operating continuously with good performance.

C: Description of Proposed systemand its operation : It was suggested to replace the oil fired thermic

fluid heater with coconut chip fired boiler as the company has the facilities for handling coconut chip fired system.

Page 88: General Aspect of Energy Management and Energy Audit

3. Energy Management and Audit

74Bureau of Energy Efficiency

D: Energy Saving CalculationsOld SystemType of fuel Firing : Furnace Oil fired heaterGCV : 10,200 kCal/kgAvg. Thermal Efficiency : 82%Heat Duty : 15 lakh kCal / hourOperating Hours : 25 days x 12 month x 24 hours = 7,200 hrs.Annual Fuel Cost : Rs.130 lakh (7200 x 1800 Rs./hr.)

Modified System

Type of fuel saving = Coconut chips fired HeaterGCV = 4200 kCal/kgAverage Thermal Efficiency = 72 %Heat Duty = 15 lakh kCal / hourAnnual Operating Cost = 7200 x 700 Rs./hr = 50 lakhAnnual Savings = 130 - 50 = Rs.80 lakh .Additional Auxiliary Power +Manpower Cost = Rs. 10 lakhNet Annual Saving = Rs. 70 lakh Investment for New Coconut Fired heater = Rs. 35 lakh

Simple pay back period = 6 months

3.9 Energy Audit Instruments

The requirement for an energy audit such as identification and quantification of energy neces-sitates measurements; these measurements require the use of instruments. These instrumentsmust be portable, durable, easy to operate and relatively inexpensive. The parameters generallymonitored during energy audit may include the following:

Basic Electrical Parameters in AC &DC systems - Voltage (V), Current (I), Power factor, Activepower (kW), apparent power (demand) (kVA), Reactive power (kVAr), Energy consumption(kWh), Frequency (Hz), Harmonics, etc.

Parameters of importance other than electrical such as temperature & heat flow, radiation, airand gas flow, liquid flow, revolutions per minute (RPM), air velocity, noise and vibration, dustconcentration, Total Dissolved Solids (TDS), pH, moisture content, relative humidity, flue gasanalysis - CO2, O2, CO, SOx, NOx, combustion efficiency etc.

Key instruments for energy audit are listed below.

The operating instructions for all instruments must be understood and staff should familiarizethemselves with the instruments and their operation prior to actual audit use.

Page 89: General Aspect of Energy Management and Energy Audit

3. Energy Management and Audit

75Bureau of Energy Efficiency

Electrical Measuring Instruments:

These are instruments for measuring majorelectrical parameters such as kVA, kW, PF,Hertz, kVAr, Amps and Volts. In additionsome of these instruments also measureharmonics.

These instruments are applied on-line i.e on running motors without any need to stop the motor. Instant measurements can be taken with hand-held meters, while more advanced ones facilitates cumulative readings with print outs at specified intervals.

Combustion analyzer:

This instrument has in-built chemical cellswhich measure various gases such as O2, CO,NOX and SOX.

Fuel Efficiency Monitor:

This measures oxygen and temperature of theflue gas. Calorific values of common fuelsare fed into the microprocessor which calcu-lates the combustion efficiency.

Fyrite:

A hand bellow pump draws the flue gassample into the solution inside the fyrite. Achemical reaction changes the liquid volumerevealing the amount of gas. A separate fyritecan be used for O2 and CO2 measurement.

Page 90: General Aspect of Energy Management and Energy Audit

3. Energy Management and Audit

76Bureau of Energy Efficiency

Contact thermometer:

These are thermocouples which measures forexample flue gas, hot air, hot water tempera-tures by insertion of probe into the stream.

For surface temperature, a leaf type probe isused with the same instrument.

Infrared Thermometer:

This is a non-contact type measurementwhich when directed at a heat source directlygives the temperature read out. This instru-ment is useful for measuring hot spots infurnaces, surface temperatures etc.

Pitot Tube and manometer:

Air velocity in ducts can be measured usinga pitot tube and inclined manometer for fur-ther calculation of flows.

Water flow meter:

This non-contact flow measuring deviceusing Doppler effect / Ultra sonic principle.There is a transmitter and receiver which arepositioned on opposite sides of the pipe. Themeter directly gives the flow. Water and otherfluid flows can be easily measured with thismeter.

Page 91: General Aspect of Energy Management and Energy Audit

3. Energy Management and Audit

77Bureau of Energy Efficiency

Speed Measurements:

In any audit exercise speed measurements arecritical as thay may change with frequency,belt slip and loading.

A simple tachometer is a contact type instru-ment which can be used where direct accessis possible.

More sophisticated and safer ones are noncontact instruments such as stroboscopes.

Leak Detectors:

Ultrasonic instruments are available whichcan be used to detect leaks of compressed airand other gases which are normally not pos-sible to detect with human abilities.

Lux meters:

Illumination levels are measured with a luxmeter. It consists of a photo cell which sens-es the light output, converts to electricalimpulses which are calibrated as lux.

Tachometer Stroboscope

Page 92: General Aspect of Energy Management and Energy Audit

3. Energy Management and Audit

78Bureau of Energy Efficiency

QUESTIONS

1. List down the objective of energy management..

2. What are the managerial functions involved in energy management?

3. Explain why managerial skills are as important as technical skills in energy management?

4. What are the various steps in the implementation of energy management in an organization?

5. State the importance of energy policy for industries.

6. Explain the role of training and awareness in energy management programme?

7. What is an energy audit?

8. Explain briefly the difference between preliminary and detailed energy audits?

9. What is the significance of knowing the energy costs?

10. What are the benefits of benchmarking energy consumption?

11. Explain the implications of part load operation of energy equipment with examples?

12. What do you understand by the term fuel substitution? Give examples.

13. What are the parameters that can be measured by on line power analyser?

14. Name the one instrument used to measure CO2 from boilers stack is(a) Infrared thermometer (b) Fyrite (c) Anemometer (d) Pitot tube

15. Non contact flow measurement can be carried out by(a) Orifice meter (b) Turbine flow meter (c) Ultrasonic flow meter (d) Magneticflow meter

16. Non contact speed measurements can be carried out by (a) Tachometer (b) Stroboscope (c) Oscilloscope (d) Odometer

REFERENCES

1. NPC energy audit manual and reports2. Energy management handbook, John Wiley and Sons - Wayne C. Turner3. Guide to Energy Management, Cape Hart, Turner and Kennedy4. Cleaner Production – Energy Efficiency Manual for GERIAP, UNEP, Bangkok prepared

by National Productivity Council

www.eeca.govt.nzwww.energyusernews.com/

Page 93: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

Chapter 1.3 Energy management & audit Part – I: Objective type questions and answers

1. “The judicious and effective use of energy to maximise profits and enhance competitive positions”. This can be the definition of:

a) Energy conservation b) Energy management

c) Energy policy d) Energy Audit

2. The energy management function is generally vested in – (a) Senior Management (b) One energy manager or co-ordinator (c) Distributed among number of middle manager (d) (b) & (c) together

3. The objective of energy management includes

a) Minimising energy costs b) minimising waste

c) Minimising environmental degradation d) all the above

4. The ratio of current year’s production to the reference year’s production is called as. (EA/EM)

a) demand factor b) production factor

c) utilisation factor d) load factor

5. Replacement of steam based hot water generation by solar system is an example of

a) matching energy usage to the requirement

b) maximising system efficiency

c) Energy substitution

d) Performance improvement

6. One unit of electricity is equivalent to ___ kcal heat units.

a) 800 b) 860 c) 400 d) 680

7. The benchmarking parameter for air conditioning equipment is

a) kW/Ton of Refrigeration b) kW/ kg of refrigerant handled

c) kcal/m3 of chilled water d) Differential temperature across chiller

8. The percentage of energy saved at the current rate of use, compared to the reference year rate of use, is called

a) Energy Utilization b) Energy Performance

c) Energy Efficiency d) None

9. Which instrument is used to monitor O2, CO in flue gas? (EA)

a) Combustion analyzer b) Power analyzer

c) Pyrometer d) Fyrite

1.3 Energy management & audit 15

Page 94: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

10. Lux meter is used to measure…… (EA)

a) Illumination level b) Sound intensity and illumination level

c) Harmonics d) Speed

11. For a cement plant the parameter, “kWh/MT of clinker “indicates

a) Energy Index parameter b) Utility factor

c) Production factor d) load factor

12. Energy manger should be well versed with

a) Manufacturing and processing skills b) Managerial and technical skills

c) Technical and marketing skills d) Managerial and commercial skills

13. An energy policy does not include

a) Target energy consumption reduction

b) Time period for reduction

c) Declaration of top management commitment

d) Future production projection

14. CO2 measurement of Fyrite kit is based on (EA)

a) Weight basis (dry) b) Volume basis (dry)

c) Weight basis (wet) d) Volume basis (wet)

15. Non contact speed measurements can be carried out by

a) Tachometer b) Stroboscope

c) Oscilloscope d) Speedometer

16. The tool used for performance assessment and logical evaluation of avenues for improvement in Energy management and audit is

a) Fuel substitution b) Monitoring and verification

c) Energy pricing d) Bench marking

17. Infrared thermometer is used to measure

a) Surface temperature b) Flame temperature

c) Flue gas temperature d) Hot water temperature

18. Find out the ‘odd’ among the following choices for fuel substitution for industrial sector of India.

a) LDO with LSHS b) coal with rice husk

c) natural gas for fertilizer plant d) LPG for soft coke

19. The various types of the instruments, which requires during audit need to be

a) easy to carry b) easy to operate

c) inexpensive d) all (a) to (c)

1.3 Energy management & audit 16

Page 95: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

20. Air velocity in ducts can be measured by using ___ and manometer

a) Orifice meter b) Borden gauge

c) Pitot tube d) Anemometer

Part – II: Short type questions and answers

1. List any four important factors involved in deciding final cost of purchased electricity.

The factors which are involved in deciding final cost of purchased electricity are

• Maximum demand charges, kVA

• Energy Charges, kWh

• TOD Charges, Peak/Non-peak period

• Power factor Charge, P.F

2. What are the principles of energy management?

The principles of energy management involve the following:

i) Procure all the energy needed at the lowest possible price

ii) Manage energy use at highest energy efficiency

iii) Reusing and recycling energy by cascading (waste heat recovery)

iv) Use the most appropriate technology

v) Reduce the avoidable losses

3. What is the need for managerial skills in energy management?

Managerial skills include bringing about awareness, motivating people at all levels, changing the structure & procedure, monitoring the energy consumption, norms target setting, etc. Both the organizational and people changes are required. For example, a mere awareness campaign in an industry on switching off lights, fans and air conditioners brought about a significant reduction in energy consumption.

4. What do you mean by energy audit?

Energy Audit is defined as “the verification, monitoring and analysis of use of energy including submission of technical report containing recommendations for improving energy efficiency with cost benefit analysis and an action plan to reduce energy consumption”.

5. Explain how matching energy usage to requirement can enhance energy efficiency

Mismatch between equipment capacity and user requirement often leads to inefficiencies due to part load operations, wastages etc. Worst case design, is a designer’s characteristic, while optimization is the energy manager’s mandate and many situations present themselves towards an exercise involving graceful matching of energy equipment capacity to end-use needs. Example:

• Eliminate throttling of a pump by impeller trimming, resizing pump, installing variable speed drives

1.3 Energy management & audit 17

Page 96: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

6. Give any four bench marking parameters followed in equipment/utility related in Industries.

i) kWh/ton of refrigeration (on Air conditioning plant)

ii) % thermal efficiency of a boiler plant

iii) kWh/NM3 of compressed air generated

iv) kWh /litre in a diesel power generation plant.

7. List any one energy audit instrument used for power measurement and one for flue gas measurement along with parameters to be measured?

Instrument Parameters measured

Portable power analyser used for power measurement

Measure, record the V, A. pf, Frequency, kVA, kVAr, kW, KWh, KVA, harmonics etc.

Combustion analyser used for flue gas measurement (zinconia cell board or electro mechanical cell board)

O2, CO, NOx, SOx, CO2 (calculated), temperature

Some instrument will also give excess air, efficiency, draft, etc.

8. What is the significance of an energy policy?

A written energy management policy will guide efforts to improve energy efficiency, and represents a commitment to saving energy. It will also help to ensure that the success of the program is not dependent on particular individuals in the organization. An energy management policy statement includes a declaration of commitment from senior management, as well as general aims and specific targets relating to:

Energy consumption reduction (electricity, fuel oil, gas, petrol etc.)

Energy cost reduction (by lowering consumption and negotiating lower unit rates)

Timetables

Budgetary limits

Energy cost centers

Organisation of management resources.

9. How do you classify energy conservation measures?

Based on energy audit and analyses of the plant, a number of potential energy saving projects may be identified. These may be classified into three categories:

1. Low cost – high return;

2. Medium cost – medium return;

3. High cost – high return

10. Define ‘energy management’.

The judicious and effective use of energy to maximize profits (minimize the costs) and enhance competitive positions.

1.3 Energy management & audit 18

Page 97: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

11. List steps involved in pre-audit phase.

Pre-audit phase:

Plan and organise

Walk through audit

Informal interview with plant personnel

12. What are the factors to be considered before procuring fuels for energy efficiency and economics?

The following factors should be considered before procurement of fuel for energy efficiency and economics:

o Price at source, transport charge, type of transport

o Quality of fuel

o Energy content

13. What are the few comparative factors need to be looked in to for external benchmarking used for inter-unit comparison and group of similar units?

Few comparative factors, which need to be looked into while benchmarking externally are:

• Scale of operation

• Vintage of technology

• Raw material specifications and quality

• Product specifications and quality

14. What is the objective of energy management?

The objectives of energy management is to achieve and maintain optimum energy procurement, utilisation throughout the organisation and

a) To minimise energy costs/ waste without affecting production & quality

b) To minimise environmental effects

15. What are the few important technical feasibility parameters that one should consider during analysis of energy conservation opportunities?

The technical feasibility should address the following issues:

• Technology availability, space, skilled manpower, reliability, service etc

• The impact of energy efficiency measure on safety, quality, production or process.

• The maintenance requirements and spares availability

16. Define the energy audit as per the energy conservation Act 2001?

As per the Energy Conservation Act, 2001, Energy Audit is defined as “the verification, monitoring and analysis of use of energy including submission of technical report containing recommendations for improving energy efficiency with cost benefit analysis and an action plan to reduce energy consumption”.

1.3 Energy management & audit 19

Page 98: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

17. What do you understand by ‘plant energy performance’ (PEP)?

Plant energy performance (PEP) is the measure of whether a plant is now using more or less energy to manufacture its products than it did in the past: a measure of how well the energy management programme is doing. It compares the change in energy consumption from one year to the other considering production output. Plant energy performance monitoring compares plant energy use at a reference year with the subsequent years to determine the improvement that has been made.

18. What are fuel substitution and list one example of fuel substitution?

Fuel substitution is substituting existing fossil fuel with more efficient and less cost / less polluting fuels such as natural gas, biogas, and locally available agro residues. E.g. Natural gas is increasingly the fuel of choice as fuel and feedstock in fertilizers, petrochemicals, power and sponge iron industries.

19. What are the base line data that an audit team should collect while conducting detailed energy audit?

The audit team should collect the following baseline data:

- Technology, processes used and equipment details

- Capacity utilisation

- Amount & type of input materials used

- Water consumption

- Fuel Consumption

- Electrical energy consumption

- Steam consumption

- Other inputs such as compressed air, cooling water etc

- Quantity & type of wastes generated

- Percentage rejection / reprocessing

- Efficiencies / yield

20. List at least four examples falling under “optimising the input energy requirements” while maximizing system efficiency?

• Shuffling of compressors to match needs.

• Periodic review of insulation thickness

• Identify potential for heat exchanger networking and process integration.

• Optimisation of transformer operation with respect to load.

Part – III Long type questions and answers

1. Briefly explain with examples on fuel and energy substitution

Fuel substitution: Substituting existing fossil fuel with more efficient and less cost/less polluting fuel such as natural gas, biogas and locally available agro-residues.

Energy is an important input in the production. There are two ways to reduce energy dependency; energy conservation and substitution.

Fuel substitution has taken place in all the major sectors of the Indian economy. Kerosene and Liquefied Petroleum Gas (LPG) have substituted soft coke in residential use.

Few examples of fuel substitution

1.3 Energy management & audit 20

Page 99: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

Natural gas is increasingly the fuel of choice as fuel and feedstock in the fertilizer, petrochemicals, power and sponge iron industries.

Replacement of coal by coconut shells, rice husk etc.

Replacement of LDO by LSHS

Few examples of energy substitution

Replacement of electric heaters by steam heaters

Replacement of steam based hot water by solar systems

2. Distinguish between ‘preliminary energy audit’ and ‘detailed energy audit’?

Preliminary energy audit is a relatively quick exercise to:

Establish energy consumption in the organization

Estimate the scope for saving

Identify the most likely (and the easiest areas for attention)

Identify immediate (especially no-/low-cost) improvements/ savings

Set a ‘reference point’

Identify areas for more detailed study/measurement

Preliminary energy audit uses existing, or easily obtained data

Whereas, detailed energy audit

• Provides a detailed energy project implementation plan for a facility, since it evaluates all major energy using systems.

• Offers the most accurate estimate of energy savings and cost.

• Considers the interactive effects of all projects, accounts for the energy use of all major equipment, and

• Includes detailed energy cost saving calculations and project cost.

Arrives energy balance based on an inventory of energy using systems, assumptions of current operating conditions and calculations of energy use. This estimated use is then compared to utility bill charges.

3. Give a typical energy audit reporting format.

After successfully carried out energy audit energy manager/energy auditor should report to the top management for effective communication and implementation. A typical energy audit reporting contents and format are given below. The following format is applicable for most of the industries. However the format can be suitably modified for specific requirement applicable for a particular type of industry.

Acknowledgement

Executive summary - Energy audit options at a glance and recommendations

Introduction about the plant

Production process description

1.3 Energy management & audit 21

Page 100: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

Energy and utility system description

- List of utilities

- Brief description of each utility

Detailed process flow diagram and energy and material balance

Energy efficiency in utility and process systems

Energy conservation options and recommendations

- List of options in terms of no cost / low cost, medium cost, and high investment cost, annual energy and cost savings, and pay back

- Implementation plan for energy saving measures / projects

Annexures

4. Write down the steps involved in ‘Energy management Strategy’? (EA)

1. Identify a strategic corporate approach

2. Appoint energy manager

3. Set up an energy monitoring and reporting system

4. Conduct energy audit

5. Prepare an energy management policy statement

6. Prepare and undertake a detailed project implementation plan

7. Implement a staff awareness and training program

8. Annual review

5. List steps involved in ‘detailed energy audit’. (EA)

Pre-audit phase:

Plan and organise

Walk through audit

Informal interview with plant personnel

Audit phase:

Primary data collection

Conduct survey and monitoring

Conduct detailed trials and experiments

Analysis of energy use

Identification and development of energy conservation opportunities

Cost benefit analysis

Report preparation and presentation to the plant personnel and management

Post audit phase:

Implementation and follow-ups

1.3 Energy management & audit 22

Page 101: General Aspect of Energy Management and Energy Audit

79Bureau of Energy Efficiency

4. MATERIAL AND ENERGY BALANCE

SyllabusMaterial and Energy balance: Facility as an energy system, Methods for preparingprocess flow, Material and energy balance diagrams.

Material quantities, as they pass through processing operations, can be described by materialbalances. Such balances are statements on the conservation of mass. Similarly, energy quanti-ties can be described by energy balances, which are statements on the conservation of energy.If there is no accumulation, what goes into a process must come out. This is true for batch oper-ation. It is equally true for continuous operation over any chosen time interval.

Material and energy balances are very important in an industry. Material balances are fun-damental to the control of processing, particularly in the control of yields of the products. Thefirst material balances are determined in the exploratory stages of a new process, improved dur-ing pilot plant experiments when the process is being planned and tested, checked out when theplant is commissioned and then refined and maintained as a control instrument as productioncontinues. When any changes occur in the process, the material balances need to be determinedagain.

The increasing cost of energy has caused the industries to examine means of reducing ener-gy consumption in processing. Energy balances are used in the examination of the variousstages of a process, over the whole process and even extending over the total production sys-tem from the raw material to the finished product.

Material and energy balances can be simple, at times they can be very complicated, but thebasic approach is general. Experience in working with the simpler systems such as individualunit operations will develop the facility to extend the methods to the more complicated situa-tions, which do arise. The increasing availability of computers has meant that very complexmass and energy balances can be set up and manipulated quite readily and therefore used ineveryday process management to maximise product yields and minimise costs.

4.1 Basic Principles

If the unit operation, whatever its natureis seen as a whole it may be representeddiagrammatically as a box, as shown inFigure. 4. 1. The mass and energy goinginto the box must balance with the massand energy coming out.

Figure 4.1: Mass and Energy Balance

Page 102: General Aspect of Energy Management and Energy Audit

The law of conservation of mass leads to what is called a mass or a material balance.

Mass In = Mass Out + Mass Stored

Raw Materials = Products + Wastes + Stored Materials.

ΣmR = ΣmP + ΣmW + ΣmS

(where Σ (sigma) denotes the sum of all terms).

ΣmR = ΣmR1 + ΣmR2 + ΣmR3 = Total Raw Materials

ΣmP = Σmp1 + ΣmP2 + ΣmP3 = Total Products.

ΣmW= SmW1 + S mW2 + SmW3 = Total Waste Products

ΣmS = ΣmS1 + ΣmS2 + ΣmS3 = Total Stored Products.

If there are no chemical changes occurring in the plant, the law of conservation of mass willapply also to each component, so that for component A:

mA in entering materials = mA in the exit materials + mA stored in plant.

For example, in a plant that is producing sugar, if the total quantity of sugar going into the plantis not equalled by the total of the purified sugar and the sugar in the waste liquors, then there issomething wrong. Sugar is either being burned (chemically changed) or accumulating in theplant or else it is going unnoticed down the drain somewhere. In this case:

MA = (mAP + mAW + mAU)

where mAU is the unknown loss and needs to be identified. So the material balance is now:

Raw Materials = Products + Waste Products + Stored Products + Losses

where Losses are the unidentified materials.

Just as mass is conserved, so is energy conserved in food-processing operations. The ener-gy coming into a unit operation can be balanced with the energy coming out and the energystored.

Energy In = Energy Out + Energy Stored

ΣER = ΣEP + ΣEW + ΣEL + ΣES

where

ΣER = ER1 + ER2 + ER3 + ……. = Total Energy Entering

ΣEp = EP1 + EP2 + EP3 + ……. = Total Energy Leaving with Products

ΣEW = EW1 + EW2 + EW3 + … = Total Energy Leaving with Waste Materials

ΣEL = EL1 + EL2 + EL3 + ……. = Total Energy Lost to Surroundings

ΣES = ES1 + ES2 + ES3 + ……. = Total Energy Stored

4. Material and Energy Balance

80Bureau of Energy Efficiency

Page 103: General Aspect of Energy Management and Energy Audit

Energy balances are often complicated because forms of energy can be interconverted, forexample mechanical energy to heat energy, but overall the quantities must balance.

4.2 The Sankey Diagram and its Use

The Sankey diagram is very useful toolto represent an entire input and outputenergy flow in any energy equipment orsystem such as boiler, fired heaters, fur-naces after carrying out energy balancecalculation. This diagram representsvisually various outputs and losses sothat energy managers can focus on find-ing improvements in a prioritized man-ner.

Example: The Figure 4.2 shows aSankey diagram for a reheating furnace.From the Figure 4.2, it is clear thatexhaust flue gas losses are a key area forpriority attention.

Since the furnaces operate at high temperatures, the exhaust gases leave at high tempera-tures resulting in poor efficiency. Hence a heat recovery device such as air preheater has to benecessarily part of the system. The lower the exhaust temperature, higher is the furnace effi-ciency.

4.3 Material Balances

The first step is to look at the three basic categories: materials in, materials out and materialsstored. Then the materials in each category have to be considered whether they are to be treat-ed as a whole, a gross mass balance, or whether various constituents should be treated sepa-rately and if so what constituents. To take a simple example, it might be to take dry solids asopposed to total material; this really means separating the two groups of constituents, non-waterand water. More complete dissection can separate out chemical types such as minerals, or chem-ical elements such as carbon. The choice and the detail depend on the reasons for making thebalance and on the information that is required. A major factor in industry is, of course, thevalue of the materials and so expensive raw materials are more likely to be considered thancheaper ones, and products than waste materials.

Basis and Units

Having decided which constituents need consideration, the basis for the calculations has to bedecided. This might be some mass of raw material entering the process in a batch system, orsome mass per hour in a continuous process. It could be: some mass of a particular predomi-nant constituent, for example mass balances in a bakery might be all related to 100 kg of flourentering; or some unchanging constituent, such as in combustion calculations with air where it

4. Material and Energy Balance

81Bureau of Energy Efficiency

Figure 4.2: Energy Balance for a Reheating Furnace

Page 104: General Aspect of Energy Management and Energy Audit

is helpful to relate everything to the inert nitrogen component; or carbon added in the nutrientsin a fermentation system because the essential energy relationships of the growing micro-organ-isms are related to the combined carbon in the feed; or the essentially inert non-oil constituentsof the oilseeds in an oil-extraction process. Sometimes it is unimportant what basis is chosenand in such cases a convenient quantity such as the total raw materials into one batch or passedin per hour to a continuous process are often selected. Having selected the basis, then the unitsmay be chosen such as mass, or concentrations which can be by weight or can be molar if reac-tions are important.

4.3.1 Total mass and composition

Material balances can be based on total mass, mass of dry solids, or mass of particular compo-nents, for example protein.

Example: Constituent balance

Skim milk is prepared by the removal of some of the fat from whole milk. This skim milk isfound to contain 90.5% water, 3.5% protein, 5.1% carbohydrate, 0.1% fat and 0.8% ash. If theoriginal milk contained 4.5% fat, calculate its composition assuming that fat only was removedto make the skim milk and that there are no losses in processing.

Basis: 100 kg of skim milk.

This contains, therefore, 0.1 kg of fat. Let the fat which was removed from it to make skim milkbe x kg.

Total original fat =(x + 0.1)kg Total original mass = (100 + x) kg

and as it is known that the original fat content was 4.5% so

(x + 0.1) / (100 + x) = 0.045where = x + 0.1 = 0.045(100 + x)

x = 4.6 kg

So the composition of the whole milk is then fat = 4.5%, water = 90.5/104.6 = 86.5 %, protein= 3.5/104.6 = 3.3 %, carbohydrate= 5.1/104.6 = 4.9% and ash = 0.8%

ConcentrationsConcentrations can be expressed in many ways: weight/ weight (w/w), weight/volume (w/v),molar concentration (M), mole fraction. The weight/weight concentration is the weight of thesolute divided by the total weight of the solution and this is the fractional form of the percent-age composition by weight. The weight volume concentration is the weight of solute in the totalvolume of the solution. The molar concentration is the number of molecular weights of thesolute expressed in kg in 1 m3 of the solution. The mole fraction is the ratio of the number ofmoles of the solute to the total number of moles of all species present in the solution. Noticethat in process engineering, it is usual to consider kg moles and in this chapter the term molemeans a mass of the material equal to its molecular weight in kilograms. In this chapter per-centage signifies percentage by weight (w/w) unless otherwise specified.

4. Material and Energy Balance

82Bureau of Energy Efficiency

Page 105: General Aspect of Energy Management and Energy Audit

4. Material and Energy Balance

83Bureau of Energy Efficiency

Example:Concentrations

A solution of common salt in water is prepared by adding 20 kg of salt to 100 kg of water, tomake a liquid of density 1323 kg/m3. Calculate the concentration of salt in this solution as a (a)weight fraction, (b) weight/volume fraction, (c) mole fraction, (d) molal concentration.

(a) Weight fraction:

20 / (100 + 20) = 0.167: % weight / weight = 16.7%

(b) Weight/volume:

A density of 1323kg/m3 means that lm3 of solution weighs 1323kg, but 1323kg of salt solutioncontains

(20 x 1323 kg of salt) / (100 + 20) = 220.5 kg salt / m3

1 m3 solution contains 220.5 kg salt.Weight/volume fraction = 220.5 / 1000 = 0.2205And so weight / volume = 22.1%

c) Moles of water = 100 / 18 = 5.56

Moles of salt = 20 / 58.5 = 0.34Mole fraction of salt = 0.34 / (5.56 + 0.34) = 0.058

d) The molar concentration (M) is 220.5/58.5 = 3.77 moles in m3

Note that the mole fraction can be approximated by the (moles of salt/moles of water) as thenumber of moles of water are dominant, that is the mole fraction is close to 0.34 / 5.56 = 0.061.As the solution becomes more dilute, this approximation improves and generally for dilute solu-tions the mole fraction of solute is a close approximation to the moles of solute / moles of sol-vent.

In solid / liquid mixtures of all these methods can be used but in solid mixtures the con-centrations are normally expressed as simple weight fractions.

With gases, concentrations are primarily measured in weight concentrations per unit vol-ume, or as partial pressures. These can be related through the gas laws. Using the gas law in theform:

pV = nRT

where p is the pressure, V the volume, n the number of moles, T the absolute temperature, andR the gas constant which is equal to 0.08206 m3 atm / mole K, the molar concentration of a gasis then

n / V = p/RT

and the weight concentration is then nM/V where M is the molecular weight of the gas.

The SI unit of pressure is the N/m2 called the Pascal (Pa). As this is of inconvenient size formany purposes, standard atmospheres (atm) are often used as pressure units, the conversionbeing 1 atm = 1.013 x 105 Pa, or very nearly 1 atm = 100 kPa.

Page 106: General Aspect of Energy Management and Energy Audit

Example: Air Composition

If air consists of 77% by weight of nitrogen and 23% by weight of oxygen calculate:

(a) the mean molecular weight of air,(b) the mole fraction of oxygen,(c) the concentration of oxygen in mole/m3 and kg/m3 if the total pressure is 1.5 atmospheresand the temperature is 25 °C.

(a) Taking the basis of 100 kg of air: it contains 77/28 moles of N2 and 23/32 moles of O2

Total number of moles = 2.75 + 0.72 = 3.47 moles.So mean molecular weight of air = 100 / 3.47 = 28.8Mean molecular weight of air = 28.8

b) The mole fraction of oxygen = 0.72 / (2.75 + 0.72) = 0.72 / 3.47 = 0.21Mole fraction of oxygen = 0.21

(c) In the gas equation, where n is the number of moles present: the value of R is 0.08206 m3

atm/mole K and at a temperature of 25 °C = 25 + 273 = 298 K, and where V= 1 m3

pV = nRT

and so, 1.5 x 1 = n x 0.08206 x 298n = 0.061 mole/m3

weight of air = n x mean molecular weight= 0.061 x 28.8 = 1.76 kg / m3

and of this 23% is oxygen, so weight of oxygen = 0.23 x 1.76 = 0.4 kg in 1 m3

Concentration of oxygen = 0.4kg/m3

or 0.4 / 32 = 0.013 mole / m3

When a gas is dissolved in a liquid, the mole fraction of the gas in the liquid can be determinedby first calculating the number of moles of gas using the gas laws, treating the volume as thevolume of the liquid, and then calculating the number of moles of liquid directly.

Example: Gas composition

In the carbonation of a soft drink, the total quantity of carbon dioxide required is the equivalentof 3 volumes of gas to one volume of water at 0 °C and atmospheric pressure. Calculate (a) themass fraction and (b) the mole fraction of the CO2 in the drink, ignoring all components otherthan CO2 and water.

Basis 1 m3 of water = 1000 kg

Volume of carbon dioxide added = 3 m3

From the gas equation, pV = nRT1 x 3 = n x 0.08206 x 273n = 0.134 mole.Molecular weight of carbon dioxide = 44

4. Material and Energy Balance

84Bureau of Energy Efficiency

Page 107: General Aspect of Energy Management and Energy Audit

And so weight of carbon dioxide added = 0.134 x 44 = 5.9 kg

(a) Mass fraction of carbon dioxide in drink = 5.9 / (1000 + 5.9) = 5.9 x 10-3

(b) Mole fraction of carbon dioxide in drink = 0.134 / (1000/18 + 0.134) = 2.41 x 10-3

4.3.2 Types of Process Situations

Continuous ProcessesIn continuous processes, time also enters into consideration and the balances are related to unittime. Thus in considering a continuous centrifuge separating whole milk into skim milk andcream, if the material holdup in the centrifuge is constant both in mass and in composition, thenthe quantities of the components entering and leaving in the different streams in unit time areconstant and a mass balance can be written on this basis. Such an analysis assumes that theprocess is in a steady state, that is flows and quantities held up in vessels do not change withtime.

Example: Balance across equipment in continuous centrifuging of milk

If 35,000kg of whole milk containing 4% fat is to be separated in a 6 hour period into skim milkwith 0.45% fat and cream with 45% fat, what are the flow rates of the two output streams froma continuous centrifuge which accomplishes this separation?Basis 1 hour's flow of whole milk

Mass in

Total mass = 35000/6 = 5833 kg.Fat = 5833 x 0.04 = 233 kg.And so Water plus solids-not-fat = 5600 kg.

Mass out

Let the mass of cream be x kg then its total fat content is 0.45x. The mass of skim milk is (5833- x) and its total fat content is 0.0045 (5833 - x)

Material balance on fat:

Fat in = Fat out5833 x 0.04 = 0.0045(5833 - x) + 0.45x. and so x = 465 kg.

So that the flow of cream is 465 kg / hr and skim milk (5833 - 465) = 5368 kg/hr

The time unit has to be considered carefully in continuous processes as normally such process-es operate continuously for only part of the total factory time. Usually there are three periods,start up, continuous processing (so-called steady state) and close down, and it is important todecide what material balance is being studied. Also the time interval over which any measure-ments are taken must be long enough to allow for any slight periodic or chance variation.

In some instances a reaction takes place and the material balances have to be adjustedaccordingly. Chemical changes can take place during a process, for example bacteria may bedestroyed during heat processing, sugars may combine with amino acids, fats may be hydrol-ysed and these affect details of the material balance. The total mass of the system will remain

4. Material and Energy Balance

85Bureau of Energy Efficiency

Page 108: General Aspect of Energy Management and Energy Audit

4. Material and Energy Balance

86Bureau of Energy Efficiency

the same but the constituent parts may change, for example in browning the sugars may reducebut browning compounds will increase.

Blending

Another class of situations which arise are blending problems in which various ingredients arecombined in such proportions as to give a product of some desired composition. Complicatedexamples, in which an optimum or best achievable composition must be sought, need quiteelaborate calculation methods, such as linear programming, but simple examples can be solvedby straightforward mass balances.

Drying

In setting up a material balance for a process a series of equations can be written for the vari-ous individual components and for the process as a whole. In some cases where groups of mate-rials maintain constant ratios, then the equations can include such groups rather than their indi-vidual constituents. For example in drying vegetables the carbohydrates, minerals, proteins etc.,can be grouped together as 'dry solids', and then only dry solids and water need be taken,through the material balance.

Example: Drying Yield

Potatoes are dried from 14% total solids to 93% total solids. What is the product yield from each1000 kg of raw potatoes assuming that 8% by weight of the original potatoes is lost in peeling.

Basis 1000kg potato entering

As 8% of potatoes are lost in peeling, potatoes to drying are 920 kg, solids 129 kg

Mass in (kg) Mass out (kg)Potato solids 140 kg Dried product 92Water 860 kg Potato solids 140 x (92/100)

=129 kgAssociated water 10 kgTotal product 139 kgLossesPeelings-potato

Solids 11 kgWater 69 kg

Water evaporated 781 kgTotal losses 861 kgTotal 1000 kg

Product yield = 139/1000=14%

Often it is important to be able to follow particular constituents of the raw material througha process. This is just a matter of calculating each constituent.

Page 109: General Aspect of Energy Management and Energy Audit

4. Material and Energy Balance

87Bureau of Energy Efficiency

4.4 Energy Balances

Energy takes many forms, such as heat, kinetic energy, chemical energy, potential energy butbecause of interconversions it is not always easy to isolate separate constituents of energy bal-ances. However, under some circumstances certain aspects predominate. In many heat balancesin which other forms of energy are insignificant; in some chemical situations mechanical ener-gy is insignificant and in some mechanical energy situations, as in the flow of fluids in pipes,the frictional losses appear as heat but the details of the heating need not be considered. We areseldom concerned with internal energies.

Therefore practical applications of energy balances tend to focus on particular dominantaspects and so a heat balance, for example, can be a useful description of important cost andquality aspects of process situation. When unfamiliar with the relative magnitudes of the vari-ous forms of energy entering into a particular processing situation, it is wise to put them alldown. Then after some preliminary calculations, the important ones emerge and other minorones can be lumped together or even ignored without introducing substantial errors. With expe-rience, the obviously minor ones can perhaps be left out completely though this always raisesthe possibility of error.

Energy balances can be calculated on the basis of external energy used per kilogram ofproduct, or raw material processed, or on dry solids or some key component. The energy con-sumed in food production includes direct energy which is fuel and electricity used on the farm,and in transport and in factories, and in storage, selling, etc.; and indirect energy which is usedto actually build the machines, to make the packaging, to produce the electricity and the oil andso on. Food itself is a major energy source, and energy balances can be determined for animalor human feeding; food energy input can be balanced against outputs in heat and mechanicalenergy and chemical synthesis.

In the SI system there is only one energy unit, the joule. However, kilocalories are still usedby some nutritionists and British thermal units (Btu) in some heat-balance work.

The two applications used in this chapter are heat balances, which are the basis for heattransfer, and the energy balances used in analysing fluid flow.

Heat Balances

The most common important energy form is heat energy and the conservation of this can beillustrated by considering operations such as heating and drying. In these, enthalpy (total heat)is conserved and as with the mass balances so enthalpy balances can be written round the var-ious items of equipment. or process stages, or round the whole plant, and it is assumed that noappreciable heat is converted to other forms of energy such as work.

Enthalpy (H) is always referred to some reference level or datum, so that the quantities are rel-ative to this datum. Working out energy balances is then just a matter of considering the vari-ous quantities of materials involved, their specific heats, and their changes in temperature orstate (as quite frequently latent heats arising from phase changes are encountered). Figure 4.3illustrates the heat balance.

Page 110: General Aspect of Energy Management and Energy Audit

4. Material and Energy Balance

88Bureau of Energy Efficiency

Heat is absorbed or evolved by some reactions in processing but usually the quantities are smallwhen compared with the other forms of energy entering into food processing such as sensibleheat and latent heat. Latent heat is the heat required to change, at constant temperature, thephysical state of materials from solid to liquid, liquid to gas, or solid to gas. Sensible heat is thatheat which when added or subtracted from materials changes their temperature and thus can besensed. The units of specific heat are J/kg K and sensible heat change is calculated by multi-plying the mass by the specific heat by the change in temperature, (m x c x ∆T). The units oflatent heat are J/kg and total latent heat change is calculated by multiplying the mass of thematerial, which changes its phase by the latent heat. Having determined those factors that aresignificant in the overall energy balance, the simplified heat balance can then be used with con-fidence in industrial energy studies. Such calculations can be quite simple and straightforwardbut they give a quantitative feeling for the situation and can be of great use in design of equip-ment and process.

Example: Dryer heat balance

A textile dryer is found to consume 4 m3/hr of natural gas with a calorific value of 800 kJ/mole.If the throughput of the dryer is 60 kg of wet cloth per hour, drying it from 55% moisture to10% moisture, estimate the overall thermal efficiency of the dryer taking into account the latentheat of evaporation only.

60 kg of wet cloth contains60 x 0.55 kg water = 33 kg moistureand 60 x (1-0.55) = 27 kg bone dry cloth.

As the final product contains 10% moisture, the moisture in the product is 27/9 = 3 kg

And so Moisture removed / hr = 33 - 3 = 30 kg/hrLatent heat of evaporation = 2257 kJ/KHeat necessary to supply = 30 x 2257 = 6.8 x 104 kJ/hr

Assuming the natural gas to be at standard temperature and pressure at which 1 mole occupies22.4 litres

Figure 4.3: Heat Balance

Page 111: General Aspect of Energy Management and Energy Audit

4. Material and Energy Balance

89Bureau of Energy Efficiency

Rate of flow of natural gas = 4 m3/hr = (4 x 1000)/22.4 = 179 moles/hr

Heat available from combustion = 179 x 800 = 14.3 x 104 kJ/hr

Approximate thermal efficiency of dryer = heat needed / heat used

= 6.8 x 104 / 14.3 x 104 = 48%To evaluate this efficiency more completely it would be necessary to take into account the

sensible heat of the dry cloth and the moisture, and the changes in temperature and humidity ofthe combustion air, which would be combined with the natural gas. However, as the latent heatof evaporation is the dominant term the above calculation gives a quick estimate and shows howa simple energy balance can give useful information.

Similarly energy balances can be carried out over thermal processing operations, and indeedany processing operations in which heat or other forms of energy are used.

Example: Autoclave heat balance in canning

An autoclave contains 1000 cans of pea soup. It is heated to an overall temperature of 100 °C.If the cans are to be cooled to 40 °C before leaving the autoclave, how much cooling water isrequired if it enters at 15 °C and leaves at 35 °C?

The specific heats of the pea soup and the can metal are respectively 4.1 kJ/ kg °C and0.50 kJ/ kg °C. The weight of each can is 60g and it contains 0.45 kg of pea soup. Assume thatthe heat content of the autoclave walls above 40 °C is 1.6 x 104 kJ and that there is no heat lossthrough the walls.

Let w = the weight of cooling water required; and the datum temperature be 40°C, the tem-perature of the cans leaving the autoclave.

Heat entering

Heat in cans = weight of cans x specific heat x temperature above datum= 1000 x 0.06 x 0.50 x (100-40) kJ = 1.8 x 103 kJ

Heat in can contents = weight pea soup x specific heat x temperature above datum

= 1000 x 0.45 x 4.1 x (100 - 40) = 1.1 x 105 kJ

Heat in water = weight of water x specific heat x temperature above datum

= w x 4.186 x (15-40)= -104.6 w kJ.

Heat leaving

Heat in cans = 1000 x 0.06 x 0.50 x (40-40) (cans leave at datum temperature) = 0

Heat in can contents = 1000 x 0.45 x 4.1 x (40-40) = 0

Heat in water = w x 4.186 x (35-40) = -20.9 w

Page 112: General Aspect of Energy Management and Energy Audit

HEAT-ENERGY BALANCE OF COOLING PROCESS; 40°C AS DATUM LINE

Heat Entering (kJ) Heat Leaving (kJ)

Heat in cans 1800 Heat in cans 0Heat in can contents 11000 Heat in can contents 0Heat in autoclave wall 16000 Heat in autoclave wall 0Heat in water -104.6 w Heat in water -20.9 WTotal heat entering 127.800 – 104.6 w Total heat leaving -20.9 W

Total heat entering = Total heat leaving127800 – 104.6 w = -20.9 w

w = 1527 kgAmount of cooling water required = 1527 kg.

Other Forms of Energy

Motor power is usually derived, in factories, from electrical energy but it can be produced fromsteam engines or waterpower. The electrical energy input can be measured by a suitablewattmeter, and the power used in the drive estimated. There are always losses from the motorsdue to heating, friction and windage; the motor efficiency, which can normally be obtained fromthe motor manufacturer, expresses the proportion (usually as a percentage) of the electricalinput energy, which emerges usefully at the motor shaft and so is available.

When considering movement, whether of fluids in pumping, of solids in solids handling, orof foodstuffs in mixers. the energy input is largely mechanical. The flow situations can beanalysed by recognising the conservation of total energy whether as energy of motion, or poten-tial energy such as pressure energy, or energy lost in friction. Similarly, chemical energyreleased in combustion can be calculated from the heats of combustion of the fuels and theirrates of consumption. Eventually energy emerges in the form of heat and its quantity can beestimated by summing the various sources.

EXAMPLE Refrigeration load

It is desired to freeze 10,000 loaves of bread each weighing 0.75 kg from an initial room tem-perature of 18°C to a final temperature of -18°C. The bread-freezing operation is to be carriedout in an air-blast freezing tunnel. It is found that the fan motors are rated at a total of 80 horse-power and measurements suggest that they are operating at around 90% of their rating, underwhich conditions their manufacturer's data claims a motor efficiency of 86%. If 1 ton of refrig-eration is 3.52 kW, estimate the maximum refrigeration load imposed by this freezing installa-tion assuming (a) that fans and motors are all within the freezing tunnel insulation and (b) thefans but not their motors are in the tunnel. The heat-loss rate from the tunnel to the ambient airhas been found to be 6.3 kW.

Extraction rate from freezing bread (maximum) = 104 kW

Fan rated horsepower = 80

Now 0.746 kW = 1 horsepower and the motor is operating at 90% of rating,

And so (fan + motor) power = (80 x 0.9) x 0.746 = 53.7 kW

(a) With motors + fans in tunnel

4. Material and Energy Balance

90Bureau of Energy Efficiency

Page 113: General Aspect of Energy Management and Energy Audit

Heat load from fans + motors = 53.7 kW

Heat load from ambient = 6.3 kW

Total heat load = (104 + 53.7 + 6.3) kW = 164 kW

= 46 tons of refrigeration

(b) With motors outside, the motor inefficiency = (1- 0.86) does not impose a load on the refrigeration

Total heat load = (104 + [0.86 x 53.7] + 6.3)

= 156 kW

= 44.5 tons of refrigeration

In practice, material and energy balances are often combined as the same stoichiometric infor-mation is needed for both.

Summary

1. Material and energy balances can be worked out quantitatively knowing the amounts of materials entering into a process, and the nature of the process.

2. Material and energy balances take the basic formContent of inputs = content of products + wastes/losses + changes in stored materials.

3. In continuous processes, a time balance must be established.4. Energy includes heat energy (enthalpy), potential energy (energy of pressure or position),

kinetic energy, work energy, chemical energy. It is the sum over all of these that is con-served.

5. Enthalpy balances, considering only heat are useful in many processing situations.The objective of M&E balance is to assess the input, conversion efficiency, output and

losses. A M&E balance, used in conjunction with diagnosis, is a powerful tool for establish-ing the basis for improvements and potential savings.

4.5 Method for Preparing Process Flow Chart

The identification and drawing up a unitoperation/process is prerequisite for ener-gy and material balance. The procedurefor drawing up the process flow diagramsis explained below.

Flow charts are schematic representa-tion of the production process, involvingvarious input resources, conversion stepsand output and recycle streams. Theprocess flow may be constructed stepwisei.e. by identifying the inputs / output /wastes at each stage of the process, asshown in the Figure 4.4.

4. Material and Energy Balance

91Bureau of Energy Efficiency

Figure 4.4: Process Flow Chart

Page 114: General Aspect of Energy Management and Energy Audit

4. Material and Energy Balance

92Bureau of Energy Efficiency

Inputs of the process could include raw materials, water, steam, energy (electricity, etc);

Process Steps should be sequentially drawn from raw material to finished product.Intermediates and any other byproduct should also be represented. The operating process para-meters such as temperature, pressure, % concentration, etc. should be represented. The flow rateof various streams should also be represented in appropriate units like m3/h or kg/h. In case ofbatch process the total cycle time should be included.

Wastes / by products could include solids, water, chemicals, energy etc. For each process steps(unit operation) as well as for an entire plant, energy and mass balance diagram should bedrawn.

Output of the process is the final product produced in the plant.Example: -Process flow diagram - raw material to finished product: Papermaking is a highenergy consuming process. A typical process flow with electrical & thermal energy flow for anintegrated waste paper based mill is given in Figure 4.5

4.6 Facility as an Energy System

There are various energy systems/utility services provides the required type of secondary ener-gy such as steam, compressed air, chilled water etc to the production facility in the manufac-turing plant. A typical plant energy system is shown in Figure 4.6. Although various forms of

Page 115: General Aspect of Energy Management and Energy Audit

4. Material and Energy Balance

93Bureau of Energy Efficiency

energy such as coal, oil, electricity etc enters the facility and does its work or heating, the out-going energy is usually in the form of low temperature heat.

The energy usage in the overall plant can be split up into various forms such as:• Electrical energy, which is usually purchased as HT and converted into LT supply for end

use.• Some plants generate their own electricity using DG sets or captive power plants.• Fuels such as furnace oil, coal are purchased and then converted into steam or electrici-

ty.• Boiler generates steam for heating and drying demand• Cooling tower and cooling water supply system for cooling demand• Air compressors and compressed air supply system for compressed air needsAll energy/utility system can be classified into three areas like generation, distribution and

utilisation for the system approach and energy analysis.A few examples for energy generation, distribution and utilization are shown below for boil-

er, cooling tower and compressed air energy system.

Boiler System: Boiler and its auxiliaries should be considered as a system for energy analyses.Energy manager can draw up a diagram as given in Figure 4.7 for energy and material balanceand analysis. This diagram includes many subsystems such as fuel supply system, combustionair system, boiler feed water supply system, steam supply and flue gas exhaust system.

Figure 4.6: Plant Energy System

Page 116: General Aspect of Energy Management and Energy Audit

4. Material and Energy Balance

94Bureau of Energy Efficiency

Cooling Tower & Cooling Water Supply System: Cooling water is one of the common util-ity demands in industry. A complete diagram can be drawn showing cooling tower, pumps, fans,process heat exchangers and return line as given in Figure 4.8 for energy audit and analysis. All

Figure 4.7 Boiler Plant System Energy Flow Diagram

Figure 4.8 Cooling Tower Water System

Page 117: General Aspect of Energy Management and Energy Audit

4. Material and Energy Balance

95Bureau of Energy Efficiency

the end use of cooling water with flow quantities should be indicated in the diagram.

Compressed air System

Compressed air is a versatile and safe media for energy use in the plants. A typical compressedair generation, distribution and utilization diagram is given in Figure 4.9. Energy analysis andbest practices measures should be listed in all the three areas.

4.7 How to Carryout Material and Energy (M&E) Balance?

Material and Energy balances are important, since they make it possible to identify and quanti-fy previously unknown losses and emissions. These balances are also useful for monitoring theimprovements made in an ongoing project, while evaluating cost benefits. Raw materials andenergy in any manufacturing activity are not only major cost components but also major sourcesof environmental pollution. Inefficient use of raw materials and energy in production process-es are reflected as wastes.

Guidelines for M&E Balance

• For a complex production stream, it is better to first draft the overall material and energybalance.

• While splitting up the total system, choose, simple discrete sub-systems. The process flowdiagram could be useful here.

• Choose the material and energy balance envelope such that, the number of streams enter-ing and leaving, is the smallest possible.

Figure 4.9 Instrument Air System

Page 118: General Aspect of Energy Management and Energy Audit

• Always choose recycle streams (material and energy) within the envelope.

• The measurement units may include, time factor or production linkages.

• Consider a full batch as the reference in case of batch operations.

• It is important to include start-up and cleaning operation consumptions (of material andenergy resources (M&E).

• Calculate the gas volumes at standard conditions.

• In case of shutdown losses, averaging over long periods may be necessary.

• Highlight losses and emissions (M&E) at part load operations if prevalent.

• For each stream, where applicable, indicate energy quality (pressure, temperature,enthalpy, kCal/hr, kW, Amps, Volts etc.).

• While preparing M&E balances, precision of analytical data, flow and energy measure-ments have to be accurate especially in case of short time span references.

The material and energy (M&E) balances along the above guidelines, are required to be devel-oped at the various levels.

1. Overall M&E balance: This involves the input and output streams for complete plant.

2. Section wise M&E balances: In the sequence of process flow, material and energy bal-ances are required to be made for each section/department/cost centres. This would helpto prioritize focus areas for efficiency improvement.

3. Equipment-wise M&E balances: M&E balances, for key equipment would help assessperformance of equipment, which would in turn help identify and quantify energy andmaterial avoidable losses.

Energy and Mass Balance Calculation Procedure:

The Energy and Mass balance is a calculation procedure that basically checks if directly or indi-rectly measured energy and mass flows are in agreement with the energy and mass conserva-tion principles.

This balance is of the utmost importance and is an indispensable tool for a clear under-standing of the energy and mass situation achieved in practice.

In order to use it correctly, the following procedure should be used:

• Clearly identify the problem to be studied.

• Define a boundary that encloses the entire system or sub-system to be analysed. Enteringand leaving mass and energy flows must be measured at the boundary.

• The boundary must be chosen in such a way that:

a) All relevant flows must cross it, all non-relevant flows being within the boundary.

4. Material and Energy Balance

96Bureau of Energy Efficiency

Page 119: General Aspect of Energy Management and Energy Audit

4. Material and Energy Balance

97Bureau of Energy Efficiency

b) Measurements at the boundary must be possible in an easy and accurate manner.

• Select an appropriate test period depending on the type of process and product.

• Carry out the measurements.

• Calculate the energy and mass flow.

• Verify an energy and mass balance. If the balances are outside acceptable limits, thenrepeat the measurements.

• The energy release or use in endothermic and exothermic processes should be takeninto consideration in the energy balance.

Example/ Formula

i) Energy Supplied by Combustion: Q =Fuel consumed x Gross Calorific value

ii) Energy Supplied by Electricity: Q = kWh x 860 kCals

Where, Q = thermal energy flow rate produced by electricity (kCals/hr)

iii) Continuity Equation

A1V1 = A2V2

v1 v2

Where, V1 and V2 are the velocity in m/s , 'v1' and 'v2' the specific volume in m3/kg and 'A' isthe cross sectional area of the pipe in m2.

iv) Heat addition/rejection of a fluid = mCp∆T

where, m is the mass in kg, Cp is the specific heat in kCal/kg°C, ∆T is the difference in tem-perature in k.

Example-1: Heat Balance in a Boiler

A heat balance is an attempt to balance the total energy entering a system (e.g boiler) againstthat leaving the system in different forms. The Figure 4.10 illustrates the heat balance and dif-ferent losses occurring while generating steam.

Figure 4.10

Page 120: General Aspect of Energy Management and Energy Audit

4. Material and Energy Balance

98Bureau of Energy Efficiency

Example-2: Mass Balance in a Cement Plant

The cement process involves gas, liquid and solid flows with heat and mass transfer, combus-tion of fuel, reactions of clinker compounds and undesired chemical reactions that include sul-phur, chlorine, and Alkalies.

A typical balance is shown in the figure 4.11 (Source: Based on figure from Austrian BATproposal 1996, Cembureau for Mass balance for production of 1 Kg cement)

Example-3: Mass Balance Calculation

This problem illustrates how a mass balance calculation can be used to check the results ofan air pollution monitoring study. A fabric filter (bag filter) is used to remove the dust from theinlet gas stream so that outlet gas stream meets the required emission standards in cement, fer-tilizer and other chemical industries.

During an air pollution monitoring study, the inlet gas stream to a bag filter is 1,69,920m3/hr and the dust loading is 4577 mg/m3. The outlet gas stream from the bag filter is 1,85,040m3/hr and the dust loading is 57 mg/m3. What is the maximum quantity of ash that will have to be removed per hour from the bag filterhopper based on these test results?

Figure 4.11

Figure 4.12 Conservation of Matter

Page 121: General Aspect of Energy Management and Energy Audit

4. Material and Energy Balance

99Bureau of Energy Efficiency

Solution:

Based on dust balance,

Mass (in) = Mass (out)

Inlet gas stream dust = outlet gas stream dust + Hopper Ash

1. Calculate the inlet and outlet dust quantities in kg per hour

Inlet dust quantity = 169920 (m3/hr) x 4577 (mg/m3) x 1/1000000 (kg/mg) = 777.7 kg/hr

Outlet dust quantity = 185040 (m3/hr) x 57 (mg/m3) x 1/1000000 (kg/mg) = 10.6 kg/hr

2. Calculate the quantity of ash that will have to removed from the hopper per hour

Hopper ash = Inlet gas dust quantity - Outlet gas dust quantity

= 777.7 kg/hr - 10.6 kg/hr

= 767.1 kg/hr

Example-4: Material Requirement for Process Operations

A scrubber is used to remove the fine material or dust from the inlet gas stream with a spray ofliquid (typically water) so that outlet gas stream meets the required process or emission stan-dards.

How much water must be continually added to wet scrubber shown in Figure below in orderto keep the unit running? Each of the streams is identified by a number located in a diamondsymbol. Stream 1 is the recirculation liquid flow stream back to the scrubber and it is 4.54m3/hr. The liquid being withdraw for treatment and disposal (stream 4) is 0.454 kg m3/hr.

Figure 4.13 Example of Material Balance

Page 122: General Aspect of Energy Management and Energy Audit

Assume that inlet gas stream (number 2) is completely dry and the outlet stream (number6) has 272.16 kg/hr of moisture evaporated in the scrubber. The water being added to the scrub-ber is stream number 5.

Solution:

Step 1. Conduct a material balance around the scrubber.

1. For Stream 6, convert from kg/hr to m3/hr to keep units consistent. The conversion factor below applies only to pure water.

Stream 6 = 272.16 kg/hr x m3/1000 kg

= 0.272 m3/hr

2. Set up the material balance equation and solve for Stream 3.

Input Scrubber = Output Scrubber

Stream 1 + Stream 2 = Stream 3 + Stream 6

4.54 m3/hr + 0 = y m3/hr + 0.272 m3/hr

Stream 3 = y m3/hr = 4.27 m3/hr

Step 2. Conduct a material balance around the recirculation tank. Solve for Stream 5.

Input Tank = Output Tank

Stream 3 + Stream 5 = Stream 1 + Stream 4

4.25 m3/hr + x m3/hr = 4.54 m3/hr + 0.454 m3/hr

Stream 5 = x m3/hr = 5 m3/hr - 4.27 m3/hr

= 0.73 m3/hr

If it is to calculate only the makeup water at 5,

Stream 5 = Stream 4 + Stream 6

= 0.454 + 0.272

= 0.73 m3/hr

One of the key steps in solving Example 4 was drawing a simple sketch of the system. This isabsolutely necessary so that it is possible to conduct the material balances. Drawings are a valu-able first step when solving a wide variety of problems, even ones that appears simple.

The drawing is a very useful way to summarize what we know and what we need to know.It helps visualize the solution. If the problem involves dimensional quantities (such as streamflow quantities), the dimensions should be included on the sketch. They serve as reminders ofthe need to convert the data into consistent units.

4. Material and Energy Balance

100Bureau of Energy Efficiency

Page 123: General Aspect of Energy Management and Energy Audit

4. Material and Energy Balance

101Bureau of Energy Efficiency

REFERENCES

1. Energy audit reports of National Productivity Council2. Energy Management Handbook, John Wiley and Sons - Wayne C. Turner3. Unit Operations in Food Processing, R.L. Earle, NZIFST

QUESTIONS

1. Draw a typical input output diagram for a process and indicate the various energyinputs.

2. What is the purpose of material and energy balance?

3. How Sankey diagram is useful for energy analysis ?

4. Draw a process flow chart for any product manufacture.

5. List down the various guidelines required for material and energy balance.

6. A material balance is based on (a) Mass (b) Volume (c) Concentration (d) Temperature

7. Biscuits are to be baked in a continuous oven. The inlet moisture content is 25%. Theoutlet moisture is 1%. The production is 2 tonnes /hour on a dry basis. Make a mate-rial balance and find out how much quantity of moisture is removed per hour.

8. A furnace is loaded with materials at 5 T/hr. The scale losses are 2%. Find out thematerial output?

9. In a heat exchanger, inlet and outlet temperatures of cooling water are 28 oC & 33°C. The cooling water circulation is 200 litres/hr. The process fluid enters the heatexchangers at 60 oC and leaves at 45 oC. Find out the flow rate of the process fluid? (Cp of process fluid = 0.95)

10. Steam output of boiler is measured by measuring feed water. The tank level readingfrom 8.00 a.m. to 8.00 p.m. was 600 m3. Continuous blow down was given at 1% ofthe boiler feed rate during the above period. Find out the average actual steam deliv-ered per hour?

11. The following are the cooling water requirements for a process industry: Heat exchanger 1: 300 m3 /hr. at 3 kg/cm2

Heat exchanger 2: 150 m3 /hr. at 2.5 kg/cm2

Heat exchanger 3: 200 m3 /hr. at 1 kg/cm2

Find out the total cooling water requirement per hour for the plant? (all heat exchangers are in parallel)

12. In a dryer, the condensate was measured to be 80 kg/hr. The flash steam was calcu-lated to be 12 kg/hr. Find out the actual steam consumption of the dryer?

Page 124: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

Chapter 1.4 Material and Energy Balance Part – I: Objective type questions and answers

1. The objective of material and energy balance is to assess the:

a) input-output b) conversion efficiency

c) losses d) all the above e) none of the above

2. In the material balance of a process or unit operation process, which component will not be considered on the input side?

a) Chemicals b) Water/air c) Recycle d) By product

3. In material balance of a process, recycle product is always considered as

a) input to process b) output to process c) both (a) and (b) d) none of them

4. Losses in material and energy balance is considered as

a) inputs b) outputs c) both (a) and (b) d) none of the above

5. Sankey diagram shows in graphics ___.

a) energy input b) energy output c) energy balance d) all the above

6. In a chemical process of two reactants A (200 kg) and B (200kg) is used as reactants. If conversion is 50% and A and B reacts in equal proportion then calculate the weight of the product formed.

a) 150 kg b) 200 kg c) 250 kg d) 400 kg

7. In a furnace, the lower the exhaust temperature ____ is the furnace efficiency.

a) lower b) moderate c) higher d) none of above

8. Which of the following is the predominant loss in a furnace oil fired boiler?

a) dry flue gas losses b) heat loss due to moisture in air

c) heat loss due to radiation and convection d) heat loss due to moisture in fuel

9. In a heat treatment furnace the material is heated up to 800 °C from ambient temperature of 30 ° C considering the specific heat of material as 0.13 kCal / kg °C. What is the energy content in one kg of material after heating?

a) 150 kCal b) 250 kCal c) 350 kCal 4) 100 kCal

10. If feed of 100 tonnes per hour at 5% concentration is fed to a crystallizer, the product obtained at 25% concentration is equal to ____ tonnes per hour.

a) 20 b) 25 c) 35 d) 40

11. In an utility steam boiler, heat loss due to radiation normally is in the range of

a) 10% b) 14% c) 1% d) 8%

1.4 Material and Energy Balance 23

Page 125: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

12. Energy supplied by combustion of fuel is equal to

a) mass of fuel consumed x its calorific value b) mass of fuel consumed x its density

c) mass of fuel consumed x its specific heat d) mass of fuel consumed x its heat capacity

13. In a coal fired boiler, hourly consumption of coal is 1000 kg. The ash content in the coal is 3%. Calculate the quantity of ash formed per day. Boiler operates 24 hrs/day.

a) 50 kg b) 300 kg c) 33 kg d) 720 kg

14. Sankey diagram represents an entire input and output energy flow. State True or False?

15. Material and energy balance will identify areas to concentrate for energy conservation.

True or False

16. In a drying process moisture is reduced from 60% to 30%. Initial weight of the material is 200 kg. Calculate the final weight of the product.

a) 100 b) 120 c) 130 d) 114.3

17. Energy supplied by electricity, Q in kCal is equal to _____ .

a) kWh x 8.6 b) kWh x 86 c) kWh x 860 d) none

18. Which one is a secondary form of energy?

a) Furnace oil b) natural gas c) electricity d) coal

19. In material and energy balance, cycle time play an important role.

True or False

20. Sankey diagram is an useful tool to represent ____.

a) financial strength of the company b) management philosophy

c) input and output energy flow d) human resource strength of the company

Part – II: Short type Questions and answers:

1. The plant has four heat exchangers and cooling water is circulated through these exchangers. The details are given below.

Heat exchanger

Water flow, m3/h Temperature raise, °C

1 200 7 2 300 8 3 400 3 4 500 2

1.4 Material and Energy Balance 24

Page 126: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

Evaluate heat rejection (kCal/h) of each heat exchanger and total heat rejected to cooling water.

Heat exchanger

Water flow, m3/h Temperature raise, °C

Heat rejection, kCal/h

1 200 7 14,00,000 2 300 8 24,00,000 3 400 3 12,00,000 4 500 2 10,00,000 60,00,000

2. Define specific power consumption with an example.

The specific energy consumption is defined as the energy required to produce a unit of output.

e.g. : Compressors:

A compressor generates 100 cfm of air at 7 kg/cm2 pressure. The power drawn by the motor is 18 kW.

i.e. Specific energy consumption is = 18/100

= 0.18 kW/cfm @ 7kg/cm2

3. Why Sankey diagram is useful in energy balance calculations?

The Sankey diagram is very useful tool to represent an entire input and output energy flow in any energy equipment or system such as boiler generation, fired heaters, furnaces after carrying out energy balance calculation. This diagram represents visually various outputs and losses so that energy managers can focus on finding improvements in a prioritized manner.

4. List any three guidelines for mass and energy balance.

• For a complex production stream, it is better to first draft the overall material and energy balance.

• While splitting up the total system, choose, simple discrete sub-systems. The process flow diagram could be useful here.

• Choose the material and energy balance envelope such that, the number of streams entering and leaving, is the smallest possible.

• Always choose recycle streams (material and energy) within the envelope.

1.4 Material and Energy Balance 25

Page 127: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

5. Draw a typical Sankey diagram of reheating furnace

Ans.

6. How material and energy balance helps in energy conservation?

In material and energy balance study by assessing the input, conversion efficiency, output and losses helps in establishing the basis for improvements and potential savings. It helps in finding improvements in a prioritised manner.

7. What way material and energy balance study is useful for a Top management?

a. Material and energy balances are important, since they make it possible to identify and quantify previously unknown losses and emissions.

b. These balances are useful for monitoring the improvements made in an ongoing project, and while evaluating cost benefits by the Top management.

c. Inefficient use of raw materials and energy in production processes are reflected as wastes. This makes the top management to take quick remedial actions.

8. What is the purpose of material and energy balance?

The basic purpose of material and energy balance is

• to quantify all the material, energy and waste streams in a process or a system.

• to find out the difference between calculated/designed values and measured/actual values thereby making it possible to identify previously unknown losses and emissions.

9. Differentiate exothermic and endothermic reactions.

Exothermic reaction: A chemical reaction in which Heat is released.

Endothermic reaction: A chemical reaction in which heat is absorbed.

10. List any three energy loss components in chemical plant.

Energy loss components in chemical plants are:

1. Flue / exhaust gas losses (from boilers, reactors etc.)

2. Evaporation loss (from cooling tower, condenser)

3. Surface heat losses (boilers, process equipment etc.)

1.4 Material and Energy Balance 26

Page 128: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

11. For complete combustion of 1 kg of a typical coal 12 kg of air is required. Calorific value of coal is 4200 kCal/kg with ash content of 22%. What is the quantity (in kg) flue gas generated by burning 5 kg coal?

Flue gas generated by burning the coal in the presence of air is:

Flue gas quantity (per kg of coal) : combustion air + quantity of fuel- ash

: 12 + 1 - 0.22

: 12.78 kg

Quantity of flue gas by burning 5 kg of coal : 5 x 12.78 = 63.9 kg.

12. List any three energy loss components of induction furnace

Induction furnace energy loss components

1. Cooling coil loss

2. Auxiliary system losses

3. Radiation heat loss

13. In reheating furnace, which loss component will be recovered (or) recycled energy.

In reheating furnace, a part of the waste heat in the flue gas losses is recoverable.

14. List the items to be represented for a preparation of a process flow chart.

Items to be represented in flow charts are:

1. Input to the process

2. Process steps

3. Wastes / by products

4. Output from the process (or) final products

15. What are the various levels of mass and energy balances?

The material and energy (M&E) balances required to be developed at the various levels are:

1. Overall M&E balance: This involves the input and output streams for complete plant.

2. Section wise M&E balances: In the sequence of process flow, material and energy balances are required to be made for each section/department/cost centres. This would help to prioritize focus areas for efficiency improvement.

3. Equipment-wise M&E balances: M&E balances, for key equipment would help assess performance of equipment, which would in turn help identify and quantify energy and material avoidable losses.

1.4 Material and Energy Balance 27

Page 129: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

16. In a textile mill, an evaporator concentrates a liquor containing solids of 6% by w/w (weight by weight) to produce an output containing 30% solids w/w. Calculate the evaporation of water per 100 kg of feed to the evaporator.

Inlet solid contents : 6%

Out let solids contents : 30%

Feed : 100 kg

Solids content in kg. in feed : 100 x 0.06 = 6 kg

Out let solid content in kg. : 6 kg

i.e. Quantity of water evaporated : kgx 80630

100100 =⎟⎠⎞

⎜⎝⎛ −

17. List out any three boiler sub systems.

Plants boiler sub systems:

1. Fuel supply system

2. Combustion air system

3. Boiler feed water system

18. Why evaluation of energy and mass balance is important?.

Material and energy balances are important, since they make it possible to identify and quantify previously unknown losses and emissions. These balances are also useful for monitoring the advances made in an ongoing project and while evaluating cost benefits.

19. A sample of coal from the mine is found to contain 67.2% carbon and 22.3% ash. The refuse obtained at the end of combustion is analysed to contain 7.1% carbon and the rest is ash. Compute the % of the original carbon unburnt in the refuse.

Data: Coal – 67.2% carbon Ash- 22.3%

Refuse – 7.1% carbon Ash – 92.9%

Basis: 100 kg of coal

Ash remains the same in refuse and coal

Mass of carbon in coal : 67.2 kg

Mass of ash in coal : 22.3 kg

Mass of ash in refuse : 22.3 kg

Mass of refuse : 100/92.9 x 22.3 = 24 kg

Quantity of carbon in refuse : 7.1/100 x 24 = 1.704 kg

% of original carbon remaining unburnt in the refuse: 1.704/67.2 x 100 : 2.53%

1.4 Material and Energy Balance 28

Page 130: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

20. A furnace shell has to be cooled from 90 °C to 55 °C. The mass of the furnace shell is 2 tonnes, the specific heat of furnace shell is 0.2 kCal/kg °C. Water is available at 29 °C. The maximum allowed increase in water temperature is 5 °C. Calculate the quantity of water required to cool the furnace. Neglect heat loss.

Total heat that has to be removed from the furnace = 2000 x 0.2 x (90- 55)

= 14000 kCal

Quantity of water required = 14000/5

= 2800 kg

Part – III Long type Questions and answers:

1. Discuss the procedure followed during energy and mass balance calculation.

The energy and mass balance is a calculation procedure that basically checks if directly or indirectly measured energy and mass flows are in agreement with the energy and mass conservation principles

This balance is of the utmost importance and is an indispensable tool for a clear understanding of the energy and mass situation achieved practice.

In order to use it correctly, the following procedure should be used:

• Clearly identify the problem to be studied.

• Define a boundary that encloses the entire system or sub-system to be analysed. Entering and leaving mass and energy flows must be measured at the boundary.

• The boundary must be chosen in such a way that:

a) All relevant flows must cross it, all non-relevant flows being within the boundary.

b) Measurements at the boundary must be possible in an easy and accurate manner.

• Select an appropriate test period depending on the type of process and product.

• Carry out the measurements.

• Calculate the energy and mass flow.

• Verify an energy and mass balance. If the balances are outside acceptable limits, then repeat the measurements.

• The energy release or use in endothermic and exothermic processes should be taken into consideration in the energy balance.

2. A boiler is fed with soft water containing 120 mg/l dissolved solids. As per IS standards the maximum dissolved solids in the boiler should not exceed 3500 mg/l for boilers, operating up to 2 MPa. In order to maintain the specified level, a continuous blow down system is adopted. Find the percentage of feed water which will be blown down.

Basis 1 kg of feed water

Let blow down quantity : x kg

1.4 Material and Energy Balance 29

Page 131: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

Dissolved solids in blow down : 3500 mg/l

: X x 3500 = 120 x 1

i.e. X – 0.0343 kg

% blow down : 0.0343/1 x 100 = 3.43%

3. Production rate from a paper machine is 340 tonnes per day (TPD). Inlet and outlet dryness to paper machine is 40% and 95% respectively. Evaporated moisture temperature is 80 °C. To evaporate moisture, the steam is supplied at 3.5 kg/cm2 (a). Latent heat of steam at 3.5 kg/cm2(a) is 513 kCal/kg. Assume 24 hours/day operation.

i) Estimate the quantity of moisture to be evaporated

ii) Input steam quantity required for evaporation (per hour)

Note: Consider enthalpy of evaporated moisture as 632 kcal/kg

Production rate from a paper machine : 340 TPD

: 14.16 TPH (tonnes per hour)

Inlet dryness to paper machine : 40%

Outlet dryness from paper machine : 95%

i) Estimation of moisture to be evaporated:

Paper weight in final product : 14.16 x 0.95 = 13.45 TPH

Weight of moisture before dryer : 45.1340

40100 x⎟⎠⎞

⎜⎝⎛ −

= 20.175 TPH

Weight of moisture after dryer : 45.1395

95100 x⎟⎠⎞

⎜⎝⎛ −

= 0.707 TPH

Evaporated moisture quantity : 20.175 - 0.707 = 19.468 TPH

ii) Input steam quantity required for evaporation

Evaporated moisture temperature : 80 °C

Enthalpy of evaporated moisture : 632 kCal/kg

Heat available in moisture (sensible & latent) : 632 x 19468

: 12303776 kCal/h

For evaporation minimum equivalent heat available should be supplied from steam

Latent Heat available in supply steam (at 3.5 kg/cm2 (a)) : 513 kCal/kg

Quantity of steam required : 23984 kg

:23.98 MT/hour

1.4 Material and Energy Balance 30

Page 132: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

4. Steam balance of a brewery is given below

Steam generation Tonnes per day a) Make-up water quantity 52.00 b) Condensate return Brew house 42.48 Bottling 2.47 c) Total steam generation 96.95 Steam utilisation Brew house a. Mash Tank 10.89 b. Work kettle 27.45 c. Raw water heating 3.90 d. Process water heating 3.62 Bottling section e. Pasteurisation machines 28.99 f. Washing machines 18.68 G Miscellaneous (blow down, yeast drying, keg filling) 3.42 96.95

i) What will be the condensate return as % of steam generation?

ii) Which equipment consumes more steam?

iii) What will be the percentage of bottling section steam load?

i) Condensate returns as % of steam generation

Condensate returns quantity:

Brew house + bottling section: 42.48 + 2.47 = 44.95 kL

Total steam generation quantity: 96.95 Tonnes

% of condensate return : (44.95 /96.95) x 100 : 46.3 %

ii) Pasteurization machines consumes higher steam quantity (28.99 Tonnes)

iii) Bottling section steam load as % of steam generation

Bottling section quantity:

Pasteurisation + washing machines: 28.99 + 18.68 = 47.67 Tonnes

Total steam generation quantity: 96.95 Tonnes

% of bottling section steam load: (47.67 /96.95) x 100 : 49.1 %

1.4 Material and Energy Balance 31

Page 133: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

5. In a particular drying operation, it is necessary to hold the moisture content of feed to a calciner to 15% (W/W) to prevent lumping and sticking. This is accomplishing by mixing the feed having 30% moisture (w/w) with recycle steam of dried material having 3% moisture (w/w). The dryer operation is shown in fig below. What fraction of the dried product must be recycled.

Let F indicates quantity of feed

R indicates quantity of recycle

P indicates quantity of product

0.7F + 0.97R = 0.85 (F + R)

= 0.12 R = 0.15 F

R = 15/12 F

0.85 (F + R) = 0.97 (P + R)

0.85 (F + 1.25F) = 0.97 P + 0.97 x 1.25 F

1.91 F = 0.97 P + 1.21F

0.7 F = 0.97 P

F = 1.386 P

R = 1.386 Px 1.25

R = 1.7325 P

P + R = 1 + 1.7325 = 2.7325

R = 1007325.27325.1 x = 63.4%

Fresh feed (F)

70% solids 30% moisture

CalcinerMixer Dryer Mixed feed

85% solids 15% moisture

97% solids, 3% moisture

Recycle (R)

Product (P) 97% solids

3% moisture

Water (W)

1.4 Material and Energy Balance 32

Page 134: General Aspect of Energy Management and Energy Audit

102Bureau of Energy Efficiency

5. ENERGY ACTION PLANNING

SyllabusEnergy Action Planning: Key elements, Force field analysis, Energy policy purpose, per-spective, Contents, Formulation, Ratification, Organizing - location of energy manage-ment, Top management support, Managerial function, Roles and responsibilities of energymanager, Accountability. Motivating-motivation of employees: Information system-designing barriers, Strategies; Marketing and communicating-training and planning.

5.1 Introduction

Energy efficiency is extremelyimportant to all organisations, espe-cially those that are energy intensive. The four vital requirements for a suc-cessful energy management is shownin Figure 5.1. Any successful energymanagement programme within anorganisation needs the total supportof top management. Hence, top man-agement support is the key require-ment for success. Top managementshould give energy efficiency equalimportance in their corporate objec-tives as manpower, raw materials, production and sales. The other important requirements area well charted strategy plan, an effective monitoring system and adequate technical ability foranalysing and implementing energy saving options.

5.2 Energy Management System

Organizations seeking financial returns from superior energy management continuously striveto improve their energy performance. Their success is based on regularly assessing energy per-formance, planning and implementing action plans to improve energy efficiency. Hence a soundenergy management system is a prerequisite for identifying and implementing energy conser-vation measures, sustaining the momentum and for effecting improvements on a continuousbasis. The various steps for energy action planning are shown in Figure 5.2.

Figure 5.1 The 4 Pillars of Successful Energy Management

Page 135: General Aspect of Energy Management and Energy Audit

5. Energy Action Planning

103Bureau of Energy Efficiency

5.2.1 Top Management Commitment and Support

Top management shall make a commitment to allocate manpower and funds to achieve contin-uous improvement. To establish the energy management programme, leading organizationsappoint energy manager, form a dedicated energy team and institute an energy policy.

Appoint an Energy Manager

The tasks of energy manger are setting goals, tracking progress, and promoting the ener-gy management program. An Energy Manager helps an organization achieve its goals byestablishing energy performance as a core value.

The Energy Manager is not always an expert in energy and technical systems. SuccessfulEnergy Manager understands how energy management helps the organization achieve its finan-cial and environmental goals and objectives. Depending on the size of the organization, theEnergy Manager role can be a full-time position or an addition to other responsibilities.

Location of Energy Manager

The energy management function, whether vested in one "energy manager or coordinator" ordistributed among a number of middle managers, usually resides somewhere in the organiza-tion between senior management and those who control the end-use of energy. Exactly howand where that function is placed is a decision that needs to be made in view of the existingorganisational structure.

Figure 5.2 Steps in Energy Action Planning

Page 136: General Aspect of Energy Management and Energy Audit

5. Energy Action Planning

104Bureau of Energy Efficiency

Energy Manager: Responsibilities and Duties to be Assigned Under The EnergyConservation Act, 2001.

Responsibilities

• Prepare an annual activity plan and present to management concerning financially attrac-tive investments to reduce energy costs

• Establish an energy conservation cell within the firm with management's consent aboutthe mandate and task of the cell.

• Initiate activities to improve monitoring and process control to reduce energy costs.• Analyze equipment performance with respect to energy efficiency• Ensure proper functioning and calibration of instrumentation required to assess level of

energy consumption directly or indirectly.• Prepare information material and conduct internal workshops about the topic for other

staff.• Improve disaggregating of energy consumption data down to shop level or profit center

of a firm.• Establish a methodology how to accurately calculate the specific energy consumption of

various products/services or activity of the firm.• Develop and manage training programme for energy efficiency at operating levels.• Co-ordinate nomination of management personnel to external programs.• Create knowledge bank on sectoral, national and inter-national development on energy

efficiency technology and management system and information denomination• Develop integrated system of energy efficiency and environmental up gradation.• Co-ordinate implementation of energy audit/efficiency improvement projects through

external agencies.• Establish and/or participate in information exchange with other energy managers of the

same sector through association

Duties

• Report to BEE and State level Designated Agency once a year the information withregard to the energy consumed and action taken on the recommendation of the accredit-ed energy auditor, as per BEE Format.

• Establish an improved data recording, collection and analysis system to keep track ofenergy consumption.

• Provide support to Accredited Energy Audit Firm retained by the company for the con-duct of energy audit

• Provide information to BEE as demanded in the Act, and with respect to the tasks givenby a mandate, and the job description.

• Prepare a scheme for efficient use of energy and its conservation and implement suchscheme keeping in view of the economic stability of the investment in such form andmanner as may be provided in the regulations of the Energy Conservation Act.

Form A Dedicated Energy Team

The tasks of energy team are executing energy management activities across differentparts of the organization and ensuring integration of best practices.

Page 137: General Aspect of Energy Management and Energy Audit

5. Energy Action Planning

105Bureau of Energy Efficiency

Decisions affecting energy use are made every day by employees at all levels in an organiza-tion. Creating an energy team helps to integrate energy management activities in an organiza-tion.

In addition to planning and implementing specific improvements, the energy team measuresand tracks energy performance and communicates with management, employees and otherstakeholders.

The size of the energy team will vary depending on the size of the organization. In additionto the Energy Manager who leads the team and dedicated energy staff, the team can include arepresentative from each operational area that significantly affects energy use, such as:

• Engineering• Purchasing• Operations and Maintenance• Building/Facilities Management• Environmental Health and Safety• Contractors and Suppliers• Utilities

Energy team can encourage communications and the sharing of ideas between variousdepartments in an organization. It can serve to obtain agreements on energy conservation pro-jects, which affect more than one department. It can provide a stronger voice to the top man-agement than a single energy manager normally could. The composition of the energy team willvary from one organization to another, depending on the existing management structure, thetype and quantity of energy used and other company-specific factors. A typical example of orga-

Figure 5.3

Page 138: General Aspect of Energy Management and Energy Audit

5. Energy Action Planning

106Bureau of Energy Efficiency

Figure 5.4

nizational structure of an energy management and location of an energy manager are shown inFigure 5.3. The location of energy management function in a typical corporate sector and larg-er organization is shown in Figure 5.4.

The frequency of team meetings depend on the importance of energy costs in the overall coststructure of the company and what projects are in progress at any time. Normally a monthlymeeting is usual, so that monthly production and energy consumptions may be reviewed togeth-er by the committee. This review would include a comparison of actual performance againstpreviously set targets and budget figures, as well as against previous months. Other items forthe agenda should be a review of the status of energy conservation investments in progress orplanned.

Institute an Energy Policy

Energy policy provides the foundation for setting performance goals and integrating ener-gy management into an organization's culture and operations.

Energy Policy provides the foundation for successful energy management. It formalizes topmanagement's support and articulates the organization's commitment to energy efficiency foremployees, shareholders, the community and other stakeholders.A formal written energy policy acts both as:

• A public expression of the organization's commitment to energy conservation and envi-ronmental protection

• A working document to guide the energy management practices and provides continuity.

Page 139: General Aspect of Energy Management and Energy Audit

5. Energy Action Planning

107Bureau of Energy Efficiency

It is in the company's best interest that support for energy management is expressed in a formalwritten declaration of commitment accompanied by a set of stated objectives, an action plan forachieving them, and a clear specification of responsibilities.

Typical Format of an Energy Policy

• Declaration of top management's commitment to, and senior and middle management'sinvolvement in, energy management.

• Statement of policy.• Statement of objectives, separated into short and long-term goals.

Actions

• Have the CEO or head of the organization officially issue the policy• Involve key people in policy development to ensure cooperation• Tailor the policy to the organization's culture• Make it understandable to employees and public alike• Consider the skills and abilities of management and employees• Include detail that covers day-to-day operations• Communicate the policy to all employees, and encourage them to get involved

Sample energy policies of various organizations are given at the end of this chapter.

5.2.2 Assess Energy Performances

Understanding current and past energy use helps an organization identify opportunities toimprove energy performance and gain financial benefits. Assessing energy performance is theperiodic process of evaluating energy use for all major facilities and functions in the organiza-tion and establishing a baseline for measuring future results of energy efficiency efforts. Key aspects include data collection and management, establishing baseline, benchmarking,analysis and evaluation and conducting technical assessment and audit.

Data Collection and Management

Collect and track data -Collect energy use information and document data over time.Evaluating energy performance requires good information on how, when, and where energy isbeing used. Collecting and tracking this information is necessary for establishing baselines andmanaging energy use.

The following steps are to be considered

a) Collect data

The data must be complete and accurate because it will be used for analysis and goal setting.Consider the following when collecting energy use data:

Determine appropriate level of detail -The level and scope of data collection will vary fromorganization to organization. Some may choose to collect data from submeters on individualprocesses while others may only look at a utility bill.

Account for all energy sources - Make inventory of all energy purchased and generated on-site (electricity, gas, steam, waste fuels) in physical units (kWh, kg of steam, etc.) and on a cost

Page 140: General Aspect of Energy Management and Energy Audit

5. Energy Action Planning

108Bureau of Energy Efficiency

basis.

Document all energy uses -For the sources identified above, assemble energy bills, meter read-ings, and other use data. Energy data may reside in the accounting department, be held central-ly or at each facility, or can be acquired by contacting the appropriate utilities or energy serviceproviders. Gather at least two years of monthly data or a more frequent interval if available. Usethe most recent data available.

Collect facility and operational data -To be able to normalize and benchmark, it may be nec-essary to collect non-energy related data for all facilities and operations, such as building size,production, operating hours, etc.

b) Track Data

A system for tracking performance can range from a simple spreadsheet to detailed databasesand IT systems. In developing an appropriate tracking system for the organization, consider thefollowing: Scope -The design of the tracking system will be shaped, in large part, by the level and scopeof information that will be tracked and the frequency of data collection.

Maintenance -Tracking systems must be easy to use, update, and maintain.

Reporting and communicating -Use tracking systems to communicate energy performance toother parts of the organization and motivate change. Consider developing formats that expressenergy performance information in ways that are easily understandable across the organization.A good tracking system should make such reporting easy.

Actions

• Collect data by fuel type at an individual building or facility level• Collect data from submeters, if possible • Use data that is current and timely • Use tracking systems to develop quarterly and annual reports that profile energy perfor-

mance • Use tracking systems to allow facilities to compare their performance to their peers

c) Normalize Data

The energy use of facilities varies greatly, partly due to factors beyond the energy efficiency ofthe equipment and operations. These factors may include weather or certain operating charac-teristics. Normalizing is the process of removing the impact of various factors on energy use sothat energy performance of facilities and operations can be compared.

In order to normalize:

Determine normalization factors -Determine key factors that need to be addressed to effec-tively compare facilities. Relevant factors are frequently organization-specific.

For industrial facilities common normalization factors include:• Inputs

Page 141: General Aspect of Energy Management and Energy Audit

5. Energy Action Planning

109Bureau of Energy Efficiency

• Product type • Output • Production processes

For commercial and institutional buildings, common normalization factors include:• Climate zone • Facility size • Fuel choice • Price/cost of energy• Actual weather history • Hours of operation • Occupancy levels• Special features

Establishing Baseline

Establish baselines -Determine the starting point from which to measure progress.

Measuring energy performance at a specific time establishes a baseline and provides the start-ing point for setting goals and evaluating future efforts and overall performance. Baselinesshould be established for all levels appropriate to your organization.

The main steps involve using the data collected so far to: Establish base year -Establish a base year or an average of several historical years. Use themost complete and relevant sets of data available.

Identify metrics -Select units of measurements that effectively and appropriately express ener-gy performance for the organization. (e.g. kCal/ton, kCal/kWh, total energy cost/ton).

Publish results -Announce performance baselines to facilities, managers, and other key stake-holders in your organization.

Benchmark

Compare the energy performance of facilities to each other, peers and competitors, andover time to prioritize which facilities to focus on for improvements

Benchmarking allows us to compare the energy performance of similar facilities or anestablished level of performance. It is a useful activity in energy management because it can beused to develop relative measures of energy performance, track change over time, and identifybest energy management practices. Benchmarking can be done in variety of ways. Facility ororganizational performance may be benchmarked to:

Past performance -A comparison of current versus historical performance.

Industry average -Based on an established performance metric, such as the recognized aver-age performance of a similar group.

Best in class -Benchmarking against the best in the industry and not the average.

Best Practices -A qualitative comparison against certain, established practices considered to bethe best in the industry.

Page 142: General Aspect of Energy Management and Energy Audit

The key steps in benchmarking include: • Determine the level of benchmarking (for example -equipment, process line, facility or

organizational). • Develop metrics. • Conduct comparisons. • Track performance over time.

Analysis and Evaluation

Analyse Data -Understand your energy use patterns and trends.

Analysing data to determine energy use trends can help an organization gain a better under-standing of the factors that affect energy performance and identify steps for reducing energyconsumption.

Assessing your energy performance helps you to:

• Categorize current energy use by fuel type, operating division, facility, product line, etc. • Identify high performing facilities for recognition and reuse of best practices. • Prioritize poor performing facilities for immediate improvement. • Understand the contribution of energy expenditures to operating costs. • Develop a historical perspective and context for future actions and decisions. • Establish reference points for measuring and rewarding good performance.

There are a variety of ways by which data can be analyzed depending upon the needs of theorganization. The following analyses provide a guideline:

a) Quantitative Reviews

• Develop use profiles -Identify energy consumption peaks and valleys, and determinehow they relate to operations or key events.

• Compare performance -Compare the use and performance data of similar facilities inyour industry.

• Assess the financial impacts -Identify areas of high-cost energy use.

• Identify data gaps -Determine areas where more information is needed.

b) Qualitative Reviews

• Conduct interviews -Seek informed opinions from colleagues, lessons learned, sys-tems-specific information (e.g., HVAC, lighting, refrigeration), and in-house audits orsurveys.

• Review policies and procedures -Review organizational policies and operating proce-dures to determine their impact on energy use.

Conduct Technical Assessments & Audits

Evaluate the operating performance of facility systems and equipment to determineimprovement potential.

5. Energy Action Planning

110Bureau of Energy Efficiency

Page 143: General Aspect of Energy Management and Energy Audit

5. Energy Action Planning

111Bureau of Energy Efficiency

Knowing the organization's baseline energy use and the relative performance of entire portfo-lio is only part of the information needed. Periodic assessment of the performance of equip-ment, processes, and systems will help to identify opportunities for improvement.

Energy audits are comprehensive reviews conducted by energy auditors and/or engineersthat evaluate the actual performance of a facility's systems and equipment against its designedperformance level or against best available technology. The difference between these is thepotential for energy savings.

The main steps for conducting technical assessments and audits are:

Assemble audit team -Expertise should cover all energy-using systems, processes, and equip-ment. Include facility engineers, system specialists, and other support. Outside support may behelpful and provide an objective perspective or specific expertise.

Plan and develop an audit strategy -Identify and prioritize systems for evaluation, assignteam members to tasks, and schedule completion dates for the activities. Use benchmarkingresults to identify poor-performing facilities whose equipment and systems should be targetedfor evaluation.

Create audit report -Based on the audit results, produce a detailed summary of actual stepsthat can be taken to reduce energy use. The report should recommend actions ranging from sim-ple adjustments in operation to equipment replacement. Estimates of resource requirements forcompleting actions should also be included.

5.2.3 Set Goals

Performance goals drive energy management activities and promote continuous improvement.Setting clear and measurable goals is critical for understanding intended results, developingeffective strategies, and reaping financial gains.

Well-stated goals guide daily decision-making and are the basis for tracking and measuringprogress. Communicating and posting goals can motivate staff to support energy managementefforts throughout the organization. The Energy Manager in association with the energy teamtypically develops goals.

Setting goals helps the Energy Manager:

• Set the tone for improvement throughout the organization• Measure the success of the energy management program• Help the Energy Team to identify progress and setbacks at a facility level• Foster ownership of energy management, create a sense of purpose, and motivate staff.• Demonstrate commitment to reducing environmental impacts• Create schedules for upgrade activities and identify milestones• Tool called force field analysis can be used to clarify the goals to be achieved.

To develop effective performance goals, determine scope, estimate potential for improvementand finally establish goals.

Determine Scope

Identify organizational and time parameters for goals.

Page 144: General Aspect of Energy Management and Energy Audit

5. Energy Action Planning

112Bureau of Energy Efficiency

The scope of performance goals can include multiple levels of the organization as well as var-ious time periods for completion of specific goals.

a) Organizational level The level at which performance goals will be set depends on the nature of the organization andhow it uses energy. Common organizational levels for setting goals include:

Organization wide -Setting goals at this level provides a big picture of how the entire organi-zation wants to improve. Organization-wide goals provide a framework for communicating thesuccess of energy management both internal and external audiences.

b) Facility -At this level, goals may vary to take into account the performance of specific facil-ities based on benchmarking results or an energy audit. Facility level goals are designed to helpthe broader organization to meet its goals.

c) Process or equipment -Some organizations may find it useful to establish goals for specif-ic process lines and equipment when energy use is concentrated in specific areas.

Time Periods

Establishing appropriate and realistic target dates for goals ensures that they are meaningful andpromote change. A combination of short and long term goals can be effective.

a) Short-term goals -Annual goals provide the necessary markers for tracking and reportingprogress on a regular and on going basis.

b) Long-term goals -Long-term goals are usually organization-specific and may be shaped by: • Internal rates of return • Internal planning horizons and guidelines • Organizational strategic plans • Commitments to voluntary environmental initiatives

Estimate Potential for Improvement

Review baselines, benchmark to determine the potential and order of upgrades, and con-duct technical assessments and audits.

To set goals, it is important to have a good estimate of what level of performance is achievableand the amount of resources needed.

There are a variety ways to determine potential. The method we choose will depend on anumber of factors, such as: available resources, time, the nature of energy use at your facilities,and how the energy program is organized.

Methods used by leading energy programs include: Reviewing performance data -Assessing performance and setting baselines should help toidentify differences in energy use between similar facilities, giving a limited, point-in-time viewof your potential improvement. Performance data covering a longer period of time will be moreuseful for understanding improvement potential.

Benchmarking -Benchmarking provides a yardstick for evaluating improvement opportunitywhen enough data is available to show trends in energy use.

Page 145: General Aspect of Energy Management and Energy Audit

5. Energy Action Planning

113Bureau of Energy Efficiency

Evaluating past projects and best practices -Evaluate past projects and best practices at high-er-performing facilities to determine the feasibility of transferring these practices to other partsof the organization.

Reviewing technical assessments and audits -Identify opportunities to reduce energy useidentified during technical assessments and audits of poorer performing facilities to serve as astrong basis for quantifying the potential for improvement.

Comparing goals of similar organizations -Reviewing performance goals of other organiza-tions can help to guide and inform you of the potential for your own organization.

Linking to organization-wide strategic goals -Strategic as well as operational goals, such ascost reductions, can also help inform the goal setting process

Establish Goals

Create and express clear, measurable goals, with target dates, for the entire organization,facilities, and other units.Once the potential for improvement has been estimated, goals can be established at the appro-priate organizational levels. Energy performance goals should be formally established and rec-ognized by senior management as a mission for the whole organization.

Estimating potential for improvement should provide us with a starting point for what ispossible. However, some organizations set their final energy performance goals based on orga-nizational factors other than what is technically feasible. Such factors will affect how energyperformance goals are expressed.

Common ways for establishing goals include:Defined reduction -Goals are presented in terms of a specific quantity or percentage decreasein energy use, such as decrease of 300 tons of furnace oil or10 percent reduction of furnace oil.

Best-in-class -This goal aims for a certain level of performance compared to an establishedbenchmark.

Efficiency improvement -Goals are expressed as a function of reducing the energy intensity ofa specific performance indicator, such as 5 kWh per unit of product.

Environmental Improvement -This goal translates energy sav-ings into pollution prevention orreduction goals.

Actions

When setting goals, be sure to usethe Energy Team's wide range ofknowledge to help set aggressive,yet realistic goals.

Have management reviewyour goals to enlist their feedbackand support.

Page 146: General Aspect of Energy Management and Energy Audit

5. Energy Action Planning

114Bureau of Energy Efficiency

Figure 5.5 Force Field Analysis

Force Field Analysis

Before creating the action plan, it can be a useful exercise to clarify the goal to be achieved, andto assess what barriers must be overcome and what influences exist in the organization thatwork towards the achievement of the goal. These barriers and influences can be thought of asnegative and positive forces respectively. Force field analysis is a simple tool that can be usedto gain additional insight about the change process to be pursued. The steps involved in forcefield analysis are:

State the organizational goal and indicate the direction (say, left to right) that signifies mov-ing towards that goal: for example, the goal might be "improve energy efficiency in the assem-bly plant" or "reduce energy consumption in the facility for current occupancy levels".

Identify barriers that tend to work against the achievement of the goal: these may be internalto the organization (for example, a lack of expertise related to energy management) or external(for example, energy rate structures or government regulation).

Identify positive influences or forces that tend to work towards achievement of the goal; thesemay also be internal or external.

Estimate the relative strength of the negative and positive forces (for simplicity, we may wantto identify them as low, medium and high strength).

Prioritize those forces that can be strengthened or weakened through your action plan with thegreatest effect on achieving the goal (Tip: It is usually more effective to attempt to minimizenegative forces than to try to strengthen forces that are already positive). A typical force fieldanalysis chart is shown in Figure 5.5.

Page 147: General Aspect of Energy Management and Energy Audit

5. Energy Action Planning

115Bureau of Energy Efficiency

5.2.4 Create Action Plan

With goals in place, the organization is now ready to develop a roadmap to improve energy per-formance.

Successful organizations use a detailed action plan to ensure a systematic process to imple-ment energy performance measures. Unlike the energy policy, the action plan is regularlyupdated, most often on an annual basis, to reflect recent achievements, changes in performance,and shifting priorities.

While the scope and scale of the action plan is often dependent on the organization, the stepsbelow outline a basic starting point for creating a plan.

Define Technical Steps and Targets

Evaluate technical assessments and audit results -Identify gaps between current performanceand goals, by reviewing the results of the technical assessments and audits or progress evalua-tions.

Determine technical steps -Identify the steps necessary for upgrading and moving facilitiesfrom current performance to the desired level of performance as defined by the goals.

Create performance targets for each facility, department, and operation of the organization totrack progress towards achieving goals.

Set timelines for actions, including regular meetings among key personnel to evaluate progress,completion dates, milestones and expected outcomes.

Establish a tracking system to track and monitor the progress of action items. This systemshould track and measure energy use and project/program activities.

Determine Roles and Resources

Get agreement from management and all organizational areas affected by the action planbefore finalizing it. Work with the Energy Team to communicate the action plan to allareas of the organization.

Determine Roles

Identify internal roles -Determine who should be involved and what their responsibilities willbe. Depending on your organization and action plan, this might include departments such as:

• Facility and operations management • Financial management -capital investments, budget planning • Human resources -staffing, training, and performance standards • Maintenance • Supply management -procurement procedures, energy purchasing and equipment and

materials • Building and plant design • Engineering • New product/process development teams • Communications Marketing • Environment, Health and Safety

Page 148: General Aspect of Energy Management and Energy Audit

Identify external roles -Determine the degree to which consultants, service providers, vendors,and other product providers will be used. Some organizations may choose to outsource entireaspects of their action plan while others may only want to contract with specific vendors forlimited projects.

Establish performance metrics for contractors -If contractors will be used, determine whatstandards will be used to evaluate bids and incorporate these metrics into agreements with con-tractors.

Determine Resources

Define resources needs -For each project or program in the action plan, estimate the cost foreach item in terms of both human resources and capital/expense outlay.

Secure resources -Develop the business case for justifying and gaining funding approval foraction plan projects and resources need.

Actions

Creating an inclusive strategy that establishes roles and actions throughout the organization canhelp to integrate good energy management practices. When developing an action plan, consid-er:

• Brainstorming with various departments to identify ways they can contribute. • Holding a competition to seek ideas for energy efficiency from across the organization. • Gathering recommendations from the Energy Team and other key personnel.

5.2.5 Implement Action Plan

People can make or break an energy program. Gaining the support and cooperation of key peo-ple at different levels within the organization is an important factor for successful implementa-tion of the action plan in many organizations.

Reaching your goals frequently depends on the awareness, commitment, and capability of thepeople who will implement the projects defined in the action plan.

In addition to implementing the technical aspects of the action plan, consider the following:

• Create communication plan -Develop targeted information for key audiences about yourenergy management program.

• Raise awareness -Build support at all levels of your organization for energy managementinitiatives and goals.

• Build capacity -Through training, access to information, and transfer of successful prac-tices, procedures, and technologies, you can expand the capacity of your staff.

• Motivate -Create incentives that encourage staff to improve energy performance toachieve goals.

5. Energy Action Planning

116Bureau of Energy Efficiency

Page 149: General Aspect of Energy Management and Energy Audit

• Track and monitor -Using the tracking system developed as part of the action plan totrack and monitor progress regularly.

Create a Communication Plan

Good communication does not just happen. It requires careful planning and implementa-tion.To communicate strategically, you will need to identify key audiences, determine the informa-tion that they need, and adapt your messages appropriately for each one.

Raise Awareness

Everyone has a role in energy management. Effective programs make employees, man-agers, and other key stakeholders aware of energy performance goals and initiatives, aswell as their responsibility in carrying out the program.Communications strategies and materials for raising awareness of energy use, goals andimpacts should be tailored to the needs of the intended audience. To raise awareness, considerdoing the following:

a) Increase general energy awarenessMost people are unaware of how their everyday actions and activities at home and work affectenergy use and impact the environment. Increasing overall awareness can be an effective wayto gain greater support for energy initiatives.

Increasing general awareness of energy use can be accomplished through: New employee orientation programs -Provide basic information on organizational and indi-vidual energy use to new employees.

Poster campaigns -Develop attractive and informative posters for change rooms, bulletinboards, etc, that discusses energy use.

b) Improve facility energy awareness Individuals working in or even managing a facility may have little understanding of the energyperformance of the facility or its impact on the organization and environment. Targeted effortsdesigned to increase awareness of facility energy use can help build support for energy man-agement programs. Like general awareness efforts, facility-oriented energy awareness can takemany forms. In developing facility energy awareness programs, consider using the followingtypes of information:

Energy data statistics -Use general facility energy facts and Figures, such as overall energycosts, costs to operate equipment, environmental information related to energy use, and so on.

Energy use of equipment -Provide information on the energy performance of equipment orprocesses that employees regularly use as part of their jobs.

c) Gain management support

Frequently, managers who are not directly involved in energy management are not aware ofhow energy use effects the organization. Increasing the awareness of managers can help to buildsupport for energy management initiatives.

5. Energy Action Planning

117Bureau of Energy Efficiency

Page 150: General Aspect of Energy Management and Energy Audit

Build Capacity

Investing in training and systems to share successful practices helps ensure the success of theaction plan by building the overall organizational capacity. Many organizations have found thatinformed employees are more likely to contribute ideas, operate equipment properly, and fol-low procedures, helping to guarantee that capital investments in energy improvements will real-ize their potential.

Training

Using training to help staff understand the importance of energy performance provides theinformation necessary to make informed decisions. Training also provides an excellent oppor-tunity for gathering employee feedback and evaluations. The type and nature of training willvary by organization and your specific action plan. Common training programs include:

Operational and procedural training -Provides instruction on new operating methods or pro-cedures designed to reduce energy use. Such training is typically targeted towards specific audi-ences, such as facility managers, operations, and maintenance staff.

Administrative training -Includes reporting, monitoring, data collection, and other adminis-trative efforts that support energy management.

Specialized training -Gives specific instructions on using and maintaining equipment or toolsto ensure more efficient operation.

Knowledge and Management Information Systems

Computer-based information systems provide a robust means for sharing information on bestpractices, technologies, and operational guidance. While these systems can range from complexdatabases to a simple intranet site, they are a centralized and accessible place to store and trans-fer energy management information within an organization.

Motivate

Offering incentives for energy management is one way many organizations create interest inenergy initiatives and foster a sense of ownership among employees.

Examples of how organizations motivate staff and employees include:

Internal competition: Use tracking sheets, scorecards, etc. to compare performance of similarfacilities and foster a sense of competition.

Recognition: Highlight and reward accomplishments of individuals, departments, and facili-ties.

Financial bonus and prizes: Offer cash bonuses and other rewards if goals are met.Environmental responsibility: Use environmental messages to promote a sense of environmen-tal and social responsibility.

Financial responsibility: Use financial messages to promote a sense of fiduciary responsibili-ty.

Performance standards: Tie employee performance standards to energy goals.

5. Energy Action Planning

118Bureau of Energy Efficiency

Page 151: General Aspect of Energy Management and Energy Audit

Track & Monitor

A tracking system is the means by which an energy program's activities are monitored. The sys-tem should be centralized and available for all to use in gauging progress toward establishedtargets, milestones, and deadlines.

Maintaining a tracking system enables you to assess necessary steps, corrective actions, andidentify successes. Periodic review of the activities outlined in the action plan is critical to meetenergy performance goals.

Perform regular updates -A system is only effective if the information it contains is currentand comprehensive. Data needs to be collected and incorporated into the system at an intervalof time effective to the program. Many organizations perform weekly and monthly updates totheir tracking systems.

Conduct periodic reviews -Periodic reviews of your progress in meeting interim goals andmilestones should be conducted with the management team, the energy team, and selectedgroups of employees. The frequency of these reviews will vary depending upon the audience.Such reviews should focus on progress made, problems encountered, and potential rewards.

Identify necessary corrective actions -A tracking system is a good way to determine whethera program is performing well. It will help identify when a specific activity is not meeting itsexpected performance and is in need of review.

5.2.6 Evaluate Progress

Evaluating progress includes formal review of both energy use data and the activities carriedout as part of the action plan as compared to your performance goals.

Key aspects are measuring results and reviewing action plans.

Measure results

Compare current performance to established goals. Gather energy use data and compare resultsto goals to determine accomplishments.

Key steps in measuring results include:

Gather tracking data

• Review energy use and cost data (capital and operating expenses)• Organize reports and data from tracking and monitoring efforts• Analyze energy efficiency achievements based on your established performance metrics.

Benchmark

• Compare energy performance to baselines • Compare performance against established goals for:

• environmental performance• financial savings

Compare energy performance to peers and competitors to establish a relative understanding ofwhere your performance ranks

5. Energy Action Planning

119Bureau of Energy Efficiency

Page 152: General Aspect of Energy Management and Energy Audit

Review action plan

Understand what worked well and what didn't in order to identify best practices.

After reviewing performance data, the next steps are to understand the factors affecting theresults as well as the additional benefits of the improved energy performance.

Regular evaluation of energy performance and the effectiveness of energy management initia-tives also allow energy managers to:

• Measure the effectiveness of projects and programs implemented • Make informed decisions about future energy projects • Reward individuals and teams for accomplishments • Document additional savings opportunities as well as non-quantifiable benefits that can

be leveraged for future initiatives.

This review should look at the effectiveness of your action plan. Where activities and projectswere successful, document best practices to share throughout the organization.

Where goals were not met, many organizations determine the cause and decide what cor-rective or preventive actions should be taken.

Key steps in reviewing the action plan include:

Get feedback -Get feedback and ideas on the plan from the energy team, implementation staff,and other departments.

Assess awareness -Assess changes in employee and organizational awareness of energy issues.

Identify critical factors -Identify factors that contributed to surpassing or missing targets.

Quantify side benefits -Identify and quantify, if possible, side benefits arising from energymanagement activities such as employee comfort, productivity improvement, impact on sales,reduced operation and maintenance expenses, or better public/community relations.Action plan review involves a commitment of resources, but also has many advantages:

• Creates insight for new actions (technologies/practices/programs)• Avoids repeating failures by identifying activities that were not as effective as expected• Assesses the usefulness of the tracking system and other administrative tools to ensure

better management and evaluation• Provides staff the opportunity to contribute to and understand the process of energy

management • Provides specific success stories and financial results to communicate to stakeholders

inside and outside the organization.

5.2.7 Recognize Achievements

Providing and seeking recognition for energy management achievements is a proven stepfor sustaining momentum and support for your program.

Providing recognition to those who helped the organization achieve these results motivates staff

5. Energy Action Planning

120Bureau of Energy Efficiency

Page 153: General Aspect of Energy Management and Energy Audit

5. Energy Action Planning

121Bureau of Energy Efficiency

and employees and brings positive exposure to the energy management program. Receiving recognition from outside sources validates the importance of the energy man-

agement program to both internal and external stakeholders, and provides positive exposure forthe organization as a whole.

a) Internal Recognition

Recognizing the accomplishments of individuals and teams is key to sustaining support andmomentum for energy management initiatives. Rewarding particular efforts sets the examplefor what constitutes success and helps motivate employees through increased job satisfaction.Recognition can strengthen the morale of everyone involved in energy management.

Key steps are:

Determine recognition levels -The decision about who should receive recognition in yourorganization will likely be shaped by the purpose for providing recognition and your organiza-tional culture. Common recognition levels include:

Individual -Acknowledges the contributions and accomplishments of specific people.

Teams -Recognizes the achievements of teams, departments, and other distinct groups withinthe organization.

Facility -Rewards the accomplishments or performance of an entire facility.

Establish recognition criteria -Create criteria for recognition and communicate these criteriaand any process eligibility requirements. Recognition criteria might include thresholds ofachievement such as:

• Offered the best energy savings ideas • Achieved the greatest energy use reduction • Increased savings by quantified amount

Determine recognition type

There are a variety of ways to provide recognition and rewards. Depending on the purpose ofthe recognition program and your organizational culture, forms of recognition can range fromformal acknowledgements and certificates, to salary increases and cash bonuses, to simpleforms of appreciation such as shields or energy program shirts.

Actions

• Ask senior management to provide the recognition. • Use a formal means for providing recognition, such as an award ceremony. • Use progress evaluations to inform the recognition process.

b) External RecognitionGood work deserves to be acknowledged. Recognition from a third party can provide valida-tion for an organization's energy management program. Not only does it provide satisfaction tothose involved in earning the recognition, but it can also enhance an organization's publicimage. A solid reputation contributes to your competitive advantage by making your organiza-tion more attractive to customers, students, current and potential employees, lenders, businesspartners and other stakeholders.

Page 154: General Aspect of Energy Management and Energy Audit

5. Energy Action Planning

122Bureau of Energy Efficiency

Page 155: General Aspect of Energy Management and Energy Audit

5. Energy Action Planning

123Bureau of Energy Efficiency

Page 156: General Aspect of Energy Management and Energy Audit

5. Energy Action Planning

124Bureau of Energy Efficiency

Page 157: General Aspect of Energy Management and Energy Audit

5. Energy Action Planning

125Bureau of Energy Efficiency

Page 158: General Aspect of Energy Management and Energy Audit

5. Energy Action Planning

126Bureau of Energy Efficiency

Page 159: General Aspect of Energy Management and Energy Audit

5. Energy Action Planning

127Bureau of Energy Efficiency

Rashtriya Ispat Nigam LimitedVisakhapatnam Steel Plant

ENERGY POLICY

We, at Visakhapatnam Steel Plant, are committed to optimally utilise various forms of ener-gy in a cost effective manner to effect conservation of energy resources. To accomplish thiswe will :

• Monitor closely and control the consumption of various forms of energy through aneffective Energy Management System.

• Adopt appropriate energy conservation technologies.• Maximise the use of cheaper and easily available forms of energy.• Make energy conservation a mass movement with the involvement of all employees.• Maximise recovery of waste energy.• Reduce Specific Energy Consumption by 1% per year by 2010.

Date Dr. B.N. Singh14-06-2002 Chairman-cum-Managing Director

KESORAM RAYON(Division of Kesoram Industries Ltd.)

ENERGY POLICY

We shall strive for continuous energy economy through -

Formulation of overall energy strategy and targets. All round participation of all employees through Small Group Activities Improved capacity utilization Upgradation of process, technology and equipment Better plant layout

As a part of our energy conservation and environment protection, we are committed toreduce specific energy consumption by 1% every year till 2010.

J.D. PALODPresident

Page 160: General Aspect of Energy Management and Energy Audit

5. Energy Action Planning

128Bureau of Energy Efficiency

NRC LIMITED

ENERGY CONSERVATION POLICY

NRC Limited is committed to energy conservation for all its products & related operations.Efforts will be made to reduce energy consumption in every possible ways as under:

• Replacing old & outdated machinery, equipment by new energy efficient equipment• Benchmarking all products/services for energy consumption by comparison at

regional as well as national level• Conducting energy conservation studies including audits with a view to minimise

waste.• Creating awareness among employees &nearby population through campaigns,

publicity about need for energy conservation• We are committed to reduce our energy consumption by minimum 1% every year

till 2010.P.S. Sharma

Managing Director

Maral Overseas LimitedP.O.Maral Sarovar, A.B.Road

Khalbujurg - 451660District Khargone (M.P.)

ENERGY CONSERVATION POLICY

We are committed to conserve the energy which is a scarce resource with the requisite con-

sistency in the efficiency, effectiveness in the cost involved in the operations and ensuring

that production quality and quantity, environment, safety, health of people are maintained.

We are also committed to monitoring continuously the saving achieved and reduce itsspecific energy consumption by minimum of 1% every year.

M S. ANJANEPRESIDENT

Page 161: General Aspect of Energy Management and Energy Audit

5. Energy Action Planning

129Bureau of Energy Efficiency

QUESTIONS

1. What are the prerequisites of the successful energy management programme?

2. Why is the top management support essential for success of energy management?

3. Explain the steps involved in the force field analysis. Taking your own industry as anexample, list down the positive and negative forces?

4. Should an industry have energy policy? If yes or no, explain the reason.

5. Discuss briefly as to where the energy manager should be located in the organizationstructure?

6. What is the role of top management in energy management?

7. List down the responsibilities and duties of an energy manager in an industry?

8. Explain how accountability can be established at various levels in an energy manage-ment system?

9. List from your experience/thinking how employees can be motivated?

10. What are the requirements of good energy action planning?

11. Discuss the importance of training for effective energy management.

12. Explain the key features of energy information system. Taking your own industry asan example, list down the important data you would like to collect and monitor foreffective energy management.

13. What is the barrier to the use of energy information systems?

14. How is communication important for energy manager?

REFERENCES1. Energy Management Hand Book, Chapter 2, Milton A. Williams2. Energy Conservation in Industries, Center of Plant Engineering Services, Hyderabad.3. Productivity Vol.31 Jan-March,1991 No.4,Energy Policy Perspectives in India, Stephen

Paulus.4. Manual on Industrial Energy Audit, Energy Management Centre

Page 162: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

Chapter 1.5 Energy Action Planning Part – I: Objective type Questions and Answers

1. The force field analysis in energy action planning deals with barriers having

a) Positive forces only b) negative forces only

c) Both negative and Positive forces d) no forces

2. From the combination below, which is not a key element of a successful energy management program?

a) Technical ability b) monitoring system & a strategy plan

c) Security of plant d) top management support

3. In force field analysis of energy action-planning, one of the actions below do not fall under positive force?

1) high price of energy 2) energy efficient technology available

3) top management commitment 4) lack of awareness

4. The positive force field analysis has one of the following. Identify?

a) Force field itself b) Corporate energy philosophy

c) Energy policy itself d) None of the above

5. The support for energy management is expressed in a formal written declaration of commitment. This is called

a) Company policy b) Management policy

c) Energy policy d) Energy efficiency policy

6. Budgets for energy use within each activity centre in an organization should be treated separately like labour, raw material etc. State True or False?

7. The term “Energy is a relatively high component of product cost”, which motivates plant to take measures for energy conservation? This is a positive force in a field analysis towards achievement of goal. State True or False?

8. In energy action planning, a formal declaration of energy policy is adopted to

a) Benefit BEE only b) Complete statutory requirement

c) Both (a) & (b) above d) achieve company’s best interests

9. “An integrated energy purchase and energy management budget should be developed as part of the energy management action plan”. This statement holds good for the company’s

a) Safety b) Accountability c) Reliability d) Stability

10. The location of energy manger in a large organisation could be

a) marketing division b) Plant maintenance unit

c) Corporate Management Services Department d) Finance division

11. Publishing a formal statement of energy policy that can be used to define company activities in energy matters is the role of -----------------

1.5 energy action planning 33

Page 163: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

a) top management b) middle management

c) energy auditor d) energy manager

12. The energy manager has to perform the function of ____.

1) Organizer 2) Planner 3) Decision Maker 4) Team leader

a) 1,2 & 3 b) 1 & 2 only

c) 1,2 & 4 d) All the four above

13. Providing information to BEE is the role of energy manager as per

a) Energy Conservation Act 2003 b) Energy Conservation Act 2004

c) Energy Conservation Act 2002 d) Energy Conservation Act 2001

14. “Publicizing the energy conservation program” includes the following

a) Signs and posters displayed in the factory or office

b) Progress charts showing targets and achievements

c) Energy conservation stickers on light switches and thermostats

d) All the above

15. In energy action planning, Monitoring and targeting is only a part of the comprehensive information systems. State True or False?

16. “A public expression of organisation's commitment to energy conservation and environmental protection” is called as

a) Company policy b) Energy policy

c) Management philosophy d) Corporate plan

17. Under Energy Conservation of Act 2001, data on energy consumed & action on recommendations of accredited energy auditor should be reported to

a) BEE and state level agency once a year

b) BEE and state level agency twice year

c) BEE only

d) State level designated agency only

18. “Training includes the complex technical issues that relate to energy efficient technologies”. This is useful as part of

a) Energy action planning b) Training division commitment

c) Management philosophy d) None of above

19. Which one of them is a positive force towards achieving goal of reduced energy consumption?

a) tax on energy consumption

b) competing corporate priorities

c) Insufficient financial resources to fund

d) Absence of corporate energy policy

20. To assess the existing situation of a plant, good energy saving strategy plan starts with…

a) energy audit b) training c) seminar d) none of the above

1.5 energy action planning 34

Page 164: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

Part – II: Short type Questions and answers

1. The successful energy management programme is possible with four vital elements. Name them?

The four vital elements for a successful energy management are:

Technical Ability, Monitoring System, Strategy Plan and Top management support

2. How force field analysis can be useful for energy action planning. ?

Force field analysis involves classifying the goal to be achieved, assessing the barriers that are to be overcome and what influences exist in organisation that work towards achievement of goal.

3. With force field analysis as a tool, give any one positive and negative force acting on achievement of goal.

One of the positive forces could be high price of energy.

One of the negative forces could be insufficient financial resources to fund measures.

4. Explain how an energy policy helps for industry?

An energy policy acts both as

• A commitment to energy conservation and environmental protection

• A working document to guide energy management practices

5. List down at least three responsibilities of an Energy Manager?

The responsibilities of an Energy Manager are:

• Prepare an annual activity plan and present to management concerning financially attractive investments to reduce energy costs

• Establish an energy conservation cell within the firm with management’s consent about the mandate and task of the cell.

• Initiate activities to improve monitoring and process control to reduce energy costs.

6. Name any four requirements for energy action planning?

The requirements for energy action planning include Personal involvement, Competition, Budgets, Energy Coordination.

(The other issues could be capital and human resources, cost centre accountability, Training, Metering, Publicity etc.)

7. Name three different ways to publicize the energy conservation program?

The different ways to publicize the energy conservation program are:

• Signs and posters displayed in the factory or office

• Progress charts showing targets and achievements

• Energy conservation stickers on light switches and thermostats

(others include-Information on bulletin boards, Articles in in-house magazines)

8. Give at least two steps involved in the tool ‘Force field analysis”

Stating organisational goal and Identifying barriers.

1.5 energy action planning 35

Page 165: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

9. Give any two technical barriers to the use of energy management information?

The technical barriers to the use of energy management information are:

• monitoring and targeting is not integrated with financial accounting

• output is not reported to either users or senior managers in a form they can readily understand and use.

10. List any two key objectives in promoting energy management?

Promoting energy management involves:

• Raising awareness of the importance of energy efficiency to cost control and environmental conservation

• Publishing achievements in energy management inside and outside the organization

11. Give two features of formal written energy Policy?

A formal written energy policy acts both as

• a public expression of organisation's commitment to energy conservation and environmental protection

• a working document to guide energy management practices and provide continuity.

12. What are the vital elements for a successful energy management programme?

The four vital elements for a successful energy management program are:

Top management support

Well charted strategy plan

An effective monitoring system, and

Adequate technical ability for analysing and implementing energy saving options

13. Briefly explain your views on “the roles of top management” taking the industry/sector you are working in four lines.

The decision of company management to control energy costs is a vital first step.

Senior management should participate in all energy committee meetings.

The top management is to publish a formal statement of its energy policy

Commitment is to appoint the responsible organisation for implementing the energy management programme.

14. Describe briefly in three or four lines the actions which you take to bring awareness on energy management program?

One of the most successful means of motivating employees is through “awareness”.

Inform them of

(1) the amount of energy they are using (2) the costs involved (3) the critical part that energy plays in the continued viability of their job (4) the many ways they can save energy in their operation (5) the relationship between production rate and energy consumption.

15. From energy conservation act-2001, list four important duties of an Energy manager.

• Report to BEE and State level Designated Agency once a year with regard to the energy consumed and action taken on the recommendation of the accredited energy auditor, as per BEE Format.

• Establish an improved data recording, collection and analysis system to keep track of

1.5 energy action planning 36

Page 166: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

energy consumption.

• Provide support to Accredited Energy Audit Firm retained by the company for the conduct of energy audit

• Provide information to BEE as demanded in the Act, and with respect to the tasks given by a mandate, and the job description

16. Briefly explain the importance of “energy information systems” in energy action planning.

Information is data that has been processed so that it is meaningful to users and helps them make decisions. When designing information systems, the objective is to reduce the amount of data that decision makers receive while increasing the quality of relevant information at their disposal. The questions to ask when one reviews the existing information system are:

Who has an interest in the information it produces?

What are they interested in knowing?

Are they getting the right information in the form that is most useful?

Information needs to be ‘accurate, timely and relevant’. But of these three requirements, the most important is relevance; information has to be appropriate to the decision to be made.

17. In your own words, explain the role of training in energy management?

Training includes the complex technical issues that relate to energy efficient technologies. It also includes the training of general staff to create:

• Awareness of energy efficiency as a corporate priority

• Understanding of the issue

• Commitment to achievement of goals

• Understanding the need for a team & its role on energy conservation

18. Briefly indicate the steps involved in using “force field analysis” for energy action planning?

The following are the steps involved in force field analysis.

i. Define organisation goal

ii. Identifying barriers

iii. Identify influence factor

iv. Identify strength and weakness

19. Explain with your experience the technical barriers to the use of energy information system?

The main barriers to the use of energy management information are:

getting accurate data on time is a key problem

Inter-division cooperation for implementation

monitoring and targeting is not integrated with financial accounting

users have no information on how to make savings

20. From Energy Conservation Act-2001, list four important duties of an Energy manager.

• Prepare an annual activity plan and project budgets to reduce energy costs

• Establish an energy conservation cell within the firm with management’s consent about the mandate and task of the cell.

1.5 energy action planning 37

Page 167: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

• Initiate activities to improve monitoring and process

• Analyze equipment performance with respect to energy efficiency

Part – III: Long type Questions and answers

1. Briefly explain about “Force field Analysis” as a tool for achieving goals of Energy action planning. Give two examples each of positive and negative forces acting towards achieving the goal in an industry.

Before creating the action plan, it can be a useful exercise to clarify the goal to be achieved, and to assess what barriers must be overcome and what influences exist in the organization that works towards the achievement of the goal. These barriers and influences can be thought of as negative and positive forces, respectively.

The simple tool, called “force field analysis” can be used to gain additional insight into the change process to be pursued. The steps involved in using it are:

State the organizational goal and indicate the direction (say, left to right) that signifies moving towards that goal:

Identify barriers that tend to work against the achievement of the goal: these may be internal to the organization

Identify positive influences or forces that tend to work towards achievement of the goal;

Estimate the relative strength of the negative and positive forces

Prioritize those forces that can be strengthened or weakened through an action plan with the greatest effect on achieving the goal.

Positive forces: High price of energy, Energy efficient technology available

Negative forces: Absence of corporate energy policy, Lack of awareness throughout company

2. Explain the need for an Energy policy?

Many organisations have not felt it necessary to adopt a formal energy policy. However, a formal written energy policy acts both as:

• A public expression of your organization’s commitment to energy conservation and environmental protection

• A working document to guide your energy management practices and provides continuity.

It is in the company's best interest that support for energy management is expressed in a formal written declaration of commitment accompanied by a set of stated objectives, an action plan for achieving them, and a clear specification of responsibilities

Format of an Energy Policy

Part 1

• Declaration of top management's commitment to, and senior and middle management's involvement in energy management.

• Statement of policy.

• Statement of objectives, separated into short and long-term goals.

Part 2

• An action plan, specifying a timetabled programme of work.

1.5 energy action planning 38

Page 168: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

• Cost resource requirements, including staffing complement, investment and training needs, necessary to achieve the programme.

• Assigned responsibility and accountability for actions outlined, specifying individuals by name and post.

• Description of any energy management committee's remit, structure, membership and reporting mechanisms.

• Named committee representative for each department and specification of internal and external lines of communication

Statement of review procedure, defining milestones and mechanisms for assessing overall progress and value for money, as well as appraising the performance of individual members of staff.

3. Explain in brief the “position of energy manager” and “Energy committee” in an organisation? In your own words, explain what do you expect as support from top management?

The energy management function, whether vested in one “energy manager or coordinator” or distributed among a number of middle managers, usually resides somewhere in the organization between senior management and those who control the end-use of energy. Exactly how and where that function is placed is a decision that needs to be made in view of the existing organisational structure.

Because energy concerns different departments within a firm, an effective energy management programme must involve a number of people. In many companies, a committee is formed to include representatives of important departments.

It can encourage communications and the sharing of ideas amongst various departments throughout the company. It can serve to obtain agreements on energy conservation projects, which affect more than one department. It can provide a stronger voice to the top management than a single manager normally could. The composition of the energy committee will vary from one company to another, depending on the existing management structure, the type and quantity of energy used and other company-specific factors.

One of the roles of the top management is to publish a formal statement of its energy policy, which can be used to define company activities in energy matters for its employees.

Further, top managements must,

• Involve in all energy committee meetings.

• Empower those given with responsibility for implementing the energy management programme.

• Ensure resources of manpower, budgets etc.

• Encourage discussion on energy in Staff/employee meetings

4. Describe about 5 items each of responsibilities and duties of Energy Manager as assigned under The Energy Conservation Act, 2001?

The responsibilities & duties assigned under The Energy Conservation Act, 2001 for Energy Manager are:

Responsibilities

• Prepare an annual activity plan and present to management concerning financially attractive investments to reduce energy costs

• Establish an energy conservation cell within the firm with management’s consent about the mandate and task of the cell.

1.5 energy action planning 39

Page 169: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

• Initiate activities to improve monitoring and process control to reduce energy costs.Analyze equipment performance with respect to energy efficiency

• Ensure proper functioning and calibration of instrumentation required to assess level of energy consumption directly or indirectly.

• Prepare information material and conduct internal workshops about the topic for other staff.

• Improve disaggregating of energy consumption data down to shop level or profit center of a firm.

• Establish a methodology how to accurately calculate the specific energy consumption of various products/services or activity of the firm.

• Develop and manage training programme for energy efficiency at operating levels.

• Co-ordinate nomination of management personnel to external programs.

• Create knowledge bank on sectoral, national and inter-national development on energy efficiency technology and management system and information denomination

• Develop integrated system of energy efficiency and environmental up gradation.

• Co-ordinate implementation of energy audit/efficiency improvement projects through external agencies.

• Establish and/or participate in information exchange with other energy managers of the same sector through association

Duties

• Report to BEE and State level Designated Agency once a year the information with regard to the energy consumed and action taken on the recommendation of the accredited energy auditor, as per BEE Format.

• Establish an improved data recording, collection and analysis system to keep track of energy consumption.

• Provide support to Accredited Energy Audit Firm retained by the company for the conduct of energy auditProvide information to BEE as demanded in the Act, and with respect to the tasks given by a mandate, and the job description.

5. List all the requirements of energy action planning?

The areas requiring attention for energy action planning.

Personal involvement

Individuals must be educated as on need for energy conservation, and then personally involved in some way in the conservation programme.

Competition

Competition can be employed to good effect as a motivating factor in energy conservation. With energy monitoring in place, similar production lines can compete with each other on energy efficiency with rewards of financial bonuses or sometimes-just simple honour. Equally the use of energy management competitions can lead to competition between different companies - for example for ‘Energy Manager of the Year’ again with some prize involved together with the honour of winning.

Budgets

Budgets for energy use within each activity centre in an organisation should be treated separately like labour or raw material budgets and accounted for in similar fashion.

Assessing managerial performance

As part of overall policy, energy management can be included in the performance

1.5 energy action planning 40

Page 170: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

assessment of a manager.

Energy coordination

In certain energy intensive industries, it might be corporate policy to assign an engineer to each manufacturing facility with primary responsibility for energy management and conservation.

Capital and human resources

Having made each division of an organisation responsible for its energy use, the senior management should ensure that the requisite personnel and capital funds are made available to undertake the energy programme.

Cost centre accountability

Each discrete activity would be accountable for its energy use separately and the individual manager answerable for the same. This entails detailed sub-metering of energy use to each such

Energy representative

Each department would assign responsibility to an individual (preferably an engineer) to act as delegate to the plant energy management committee activity.

Training

Sufficient training for the energy representative and engineers involved in energy conservation activities should be carried out

Metering

Metering is one of the management tools for energy conservation. At the individual’s level, there is a psychological impact involved with metering - Just having meters installed and monitored is in itself an inducement to reduce unnecessary energy consumption.

Publicity

One of the best ways of promoting an energy conservation programme is a publicity programme aimed at the worker on the job. Among the ways of publicizing such a programme are:

• Signs and posters displayed in the factory or office

• Progress charts showing targets and achievements

• Energy conservation stickers on light switches and thermostats

• Information on bulletin boards

• Articles in in-house magazines

In conclusion, involving people in energy conservation means changing habits. Senior managers must be willing participant in all programmes and lead by example. All employees must learn to practice energy conservation in all areas of their daily routines.

1.5 energy action planning 41

Page 171: General Aspect of Energy Management and Energy Audit

SyllabusFinancial Management: Investment-need, Appraisal and criteria, Financial analysis tech-niques-Simple pay back period, Return on investment, Net present value, Internal rate ofreturn, Cash flows, Risk and sensitivity analysis; Financing options, Energy performancecontracts and role of ESCOs.

6.1 Introduction

In the process of energy management, at some stage, investment would be required for reduc-ing the energy consumption of a process or utility. Investment would be required for modifica-tions/retrofitting and for incorporating new technology. It would be prudent to adopt a system-atic approach for merit rating of the different investment options vis-à-vis the anticipated sav-ings. It is essential to identify the benefits of the proposed measure with reference to not onlyenergy savings but also other associated benefits such as increased productivity, improved prod-uct quality etc.

The cost involved in the proposed measure should be captured in totality viz.• Direct project cost • Additional operations and maintenance cost• Training of personnel on new technology etc.Based on the above, the investment analysis can be carried out by the techniques explained

in the later section of the chapter.

6.2 Investment Need, Appraisal and Criteria

To persuade your organization to commit itself to a program of investment in energy efficien-cy, you need to demonstrate:

• The size of the energy problem it currently faces• The technical and good housekeeping measure available to reduce waste • The predicted return on any investment• The real returns achieved on particular measures over time.

The need for investments in energy conservation can arise under following circumstances• For new equipment, process improvements etc.• To provide staff training• To implement or upgrade the energy information system

Criteria

Any investment has to be seen as an addition and not as a substitute for having effective man-agement practices for controlling energy consumption throughout your organization. Spending money on technical improvements for energy management cannot compensate forinadequate attention to gaining control over energy consumption. Therefore, before you makeany investments, it is important to ensure that

130Bureau of Energy Efficiency

6. FINANCIAL MANAGEMENT

Page 172: General Aspect of Energy Management and Energy Audit

• You are getting the best performance from existing plant and equipment• Your energy charges are set at the lowest possible tariffs• You are consuming the best energy forms - fuels or electricity - as efficiently as possi-

ble• Good housekeeping practices are being regularly practiced.

When listing investment opportunities, the following criteria need to be considered:• The energy consumption per unit of production of a plant or process• The current state of repair and energy efficiency of the building design, plant and ser-

vices, including controls• The quality of the indoor environment - not just room temperatures but indoor air qual-

ity and air change rates, drafts, under and overheating including glare, etc.• The effect of any proposed measure on staff attitudes and behaviour.

Energy Proposals Vs Other Competitive Proposals

One of the most difficult problems which many energy managers face is justifying why theirorganization should invest money in increasing its energy efficiency, especially when there areother, seemingly more important priorities for the use of its capital.

• Organization typically give priority to investing in what they see as their core or profit-making activities in preference to energy efficiency

• Even when they do invest in saving energy, they tend to demand faster rates of returnthan they require from other kinds of investment.

Investment Appraisal

Energy manager has to identify how cost savings arising from energy management could beredeployed within his organization to the maximum effect. To do this, he has to work out howbenefits of increased energy efficiency can be best sold to top management as,

• Reducing operating /production costs• Increasing employee comfort and well-being• Improving cost-effectiveness and/or profits• Protecting under-funded core activities• Enhancing the quality of service or customer care delivered• Protecting the environment

6.3 Financial Analysis

In most respects, investment in energy efficiency is no different from any other area of finan-cial management. So when your organization first decides to invest in increasing its energy effi-ciency it should apply exactly the same criteria to reducing its energy consumption as it appliesto all its other investments. It should not require a faster or slower rate of return on investmentin energy efficiency than it demands elsewhere.The basic criteria for financial investment appraisal include:

• Simple Payback - a measure of how long it will be before the investment makes money,and how long the financing term needs to be

• Return on Investment (ROI) and Internal Rate of Return (IRR) - measure that allow

6. Financial Management

131Bureau of Energy Efficiency

Page 173: General Aspect of Energy Management and Energy Audit

comparison with other investment options• Net Present Value (NPV) and Cash Flow - measures that allow financial planning of

the project and provide the company with all the information needed to incorporateenergy efficiency projects into the corporate financial system.

Initially, when you can identify no or low cost investment opportunities, this principleshould not be difficult to maintain. However, if your organization decides to fund a rolling pro-gram of such investments, then over time it will become increasingly difficult for you to iden-tify opportunities, which conform to the principle. Before you'll reach this position, you needto renegotiate the basis on which investment decisions are made.

It may require particular thoroughness to ensure that all the costs and benefits arising aretaken into account. As an approximate appraisal, simple payback (the total cost of the measuredivided by the annual savings arising from it expressed as years required for the original invest-ment to be returned) is a useful tool.

As the process becomes more sophisticated, financial criteria such as Discounted CashFlow, Internal Rate of Return and Net Present Value may be used. If you do not possess suffi-cient financial expertise to calculate these yourself, you will need to ensure that you haveaccess, either within your own staff or elsewhere within the organization, to people who canemploy them on your behalf.

There are two quite separate grounds for arguing that, at least long after their payback peri-ods. Such measure does not need to be written off using fast discounting rates but can be regard-ed as adding to the long term value of the assets. For this reason, short term payback can be aninadequate yardstick for assessin long after their payback periods. Such measure does not needto be written off using fast discounting rates but can be regarded as adding to the long termvalue of the assets. For this reason, short term payback can be an inadequate yardstick forassessing longer term benefits. To assess the real gains from investing in saving energy, youshould use investment appraisal techniques, which accurately reflect the longevity of the returnson particular types of technical measures.Protecting Energy InvestmentIt is essential to keep a careful watch on your organization's maintenance policy and practicesin order to protect any investment already made in reducing your organization's energy con-sumption. There is a clear dependence relationship between energy efficiency and maintenance.This operates at two levels:

• Initially, improving energy efficiency is most cost-effectively done in existing facilitiesthrough normal maintenance procedures

• Subsequently, unless maintenance is regularly undertaken, savings from installed tech-nical measure, whether in new-build or existing facilities, may not be realized.

6.4 Financial Analysis TechniquesIn this chapter, investment analysis tools relevant to energy management projects will be

discussed.

6.4.1 Simple Pay Back Period:

Simple Payback Period (SPP) represents, as a first approximation; the time (number of years)required to recover the initial investment (First Cost), considering only the Net Annual Saving:

6. Financial Management

132Bureau of Energy Efficiency

Page 174: General Aspect of Energy Management and Energy Audit

The simple payback period is usually calculated as follows:

Examples

Simple payback period for a continuous Deodorizer that costs Rs.60 lakhs to purchase andinstall, Rs.1.5 lakhs per year on an average to operate and maintain and is expected to save Rs.20 lakhs by reducing steam consumption (as compared to batch deodorizers), may be calculat-ed as follows:According to the payback criterion, the shorter the payback period, the more desirable the pro-

ject.

Advantages

A widely used investment criterion, the payback period seems to offer the following advantages:

• It is simple, both in concept and application. Obviously a shorter payback generally indi-cates a more attractive investment. It does not use tedious calculations.

• It favours projects, which generate substantial cash inflows in earlier years, and dis-criminates against projects, which bring substantial cash inflows in later years but not inearlier years.

Limitations

• It fails to consider the time value of money. Cash inflows, in the payback calculation, aresimply added without suitable discounting. This violates the most basic principle offinancial analysis, which stipulates that cash flows occurring at different points of timecan be added or subtracted only after suitable compounding/discounting.

• It ignores cash flows beyond the payback period. This leads to discrimination againstprojects that generate substantial cash inflows in later years.

To illustrate, consider the cash flows of two projects, A and B:The payback criterion prefers A, which has a payback period of 3 years, in comparison to B,

which has a payback period of 4 years, even though B has very substantial cash inflows in years

6. Financial Management

133Bureau of Energy Efficiency

tsYearlybenefitsYearly

tFirstperiodpaybackSimple

cos

cos

−=

monthsyearsperiodpaybackSimple 335.120

60 =−

=

Page 175: General Aspect of Energy Management and Energy Audit

6. Financial Management

134Bureau of Energy Efficiency

5 and 6.• It is a measure of a project's capital recovery, not profitability.• Despite its limitations, the simple payback period has advantages in that it may be use-

ful for evaluating an investment.

Time Value of Money

A project usually entails an investment for the initial cost of installation, called the capital cost,and a series of annual costs and/or cost savings (i.e. operating, energy, maintenance, etc.)throughout the life of the project. To assess project feasibility, all these present and future cashflows must be equated to a common basis. The problem with equating cash flows which occurat different times is that the value of money changes with time. The method by which these var-ious cash flows are related is called discounting, or the present value concept.

For example, if money can be deposited in the bank at 10% interest, then a Rs.100 depositwill be worth Rs.110 in one year's time. Thus the Rs.110 in one year is a future value equiva-lent to the Rs.100 present value.

In the same manner, Rs.100 received one year from now is only worth Rs.90.91 in today'smoney (i.e. Rs.90.91 plus 10% interest equals Rs.100). Thus Rs.90.91 represents the presentvalue of Rs.100 cash flow occurring one year in the future. If the interest rate were somethingdifferent than 10%, then the equivalent present value would also change. The relationshipbetween present and future value is determined as follows:

Future Value (FV) = NPV (1 + i)n or NPV = FV / (1+i)n

Where FV = Future value of the cash flowNPV= Net Present Value of the cash flowi = Interest or discount raten = Number of years in the future

6.4.2 Return on Investment (ROI)

ROI expresses the "annual return" from the project as a percentage of capital cost. The annualreturn takes into account the cash flows over the project life and the discount rate by convert-ing the total present value of ongoing cash flows to an equivalent annual amount over the lifeof the project, which can then be compared to the capital cost. ROI does not require similar pro-ject life or capital cost for comparison.

This is a broad indicator of the annual return expected from initial capital investment,expressed as a percentage:

Annual Net Cash FlowROI = --------------------------------- x 100

Capital Cost

ROI must always be higher than cost of money (interest rate); the greater the return on invest-ment better is the investment.

Page 176: General Aspect of Energy Management and Energy Audit

6. Financial Management

135Bureau of Energy Efficiency

Limitations

• It does not take into account the time value of money.• It does not account for the variable nature of annual net cash inflows.

6.4.3 Net Present Value

The net present value (NPV) of a project is equal to the sum of the present values of all the cashflows associated with it. Symbolically,

Where NPV = Net Present ValueCFt = Cash flow occurring at the end of year 't' (t=0,1,….n)

n = life of the projectk = Discount rate

The discount rate (k) employed for evaluating the present value of the expected future cashflows should reflect the risk of the project.

Example

To illustrate the calculation of net present value, consider a project, which has the followingcash flow stream:

The cost of capital, κ, for the firm is 10 per cent. The net present value of the proposal is:

The net present value represents the net benefit over and above the compensation for time andrisk. Hence the decision rule associated with the net present value criterion is: "Accept the projectif the net present value is positive and reject the project if the net present value is negative".

Page 177: General Aspect of Energy Management and Energy Audit

Advantages

The net present value criterion has considerable merits.• It takes into account the time value of money.• It considers the cash flow stream in its project life.

6.4.4 Internal Rate of Return

This method calculates the rate of return that the investment is expected to yield. The internalrate of return (IRR) method expresses each investment alternative in terms of a rate of return (acompound interest rate). The expected rate of return is the interest rate for which total dis-counted benefits become just equal to total discounted costs (i.e net present benefits or net annu-al benefits are equal to zero, or for which the benefit / cost ratio equals one). The criterion forselection among alternatives is to choose the investment with the highest rate of return.

The rate of return is usually calculated by a process of trial and error, whereby the net cashflow is computed for various discount rates until its value is reduced to zero.

The internal rate of return (IRR) of a project is the discount rate, which makes its net pre-sent value (NPV) equal to zero. It is the discount rate in the equation:

where CFt = cash flow at the end of year "t"k = discount raten = life of the project.

CFt value will be negative if it is expenditure and positive if it is savings.

In the net present value calculation we assume that the discount rate (cost of capital) is knownand determine the net present value of the project. In the internal rate of return calculation, weset the net present value equal to zero and determine the discount rate (internal rate of return),which satisfies this condition.To illustrate the calculation of internal rate of return, consider the cash flows of a project:

The internal rate of return is the value of " κ " which satisfies the following equation:

The calculation of "k" involves a process of trial and error. We try different values of "k" tillwe find that the right-hand side of the above equation is equal to 100,000. Let us, to begin with,try k = 15 per cent. This makes the right-hand side equal to:

6. Financial Management

136Bureau of Energy Efficiency

Page 178: General Aspect of Energy Management and Energy Audit

30,000 30,000 40,000 45,000------------ + ------------- + --------------- + --------------- = 100, 802

(1.15) (1.15)2 (1.15)3 (1.15)4

This value is slightly higher than our target value, 100,000. So we increase the value of k from15 per cent to 16 per cent. (In general, a higher k lowers and a smaller k increases the right-hand side value). The right-hand side becomes:

30,000 30,000 40,000 45,000------------ + ------------- + --------------- + --------------- = 98, 641

(1.16) (1.16)2 (1.16)3 (1.16)4

Since this value is now less than 100,000, we conclude that the value of k lies between 15per cent and 16 per cent. For most of the purposes this indication suffices.

Advantages

A popular discounted cash flow method, the internal rate of return criterion has several advan-tages:

• It takes into account the time value of money.• It considers the cash flow stream in its entirety.• It makes sense to businessmen who prefer to think in terms of rate of return and find an

absolute quantity, like net present value, somewhat difficult to work with.

Limitations

• The internal rate of return figure cannot distinguish between lending and borrowing andhence a high internal rate of return need not necessarily be a desirable feature.

Example

Calculate the internal rate of return for an economizer that will cost Rs.500,000, will last 10years, and will result in fuel savings of Rs.150,000 each year.

Find the i that will equate the following:

Rs.500,000 = 150,000 x PV (A = 10 years, i = ?)

To do this, calculate the net present value (NPV) for various i values, selected by visual inspec-tion;NPV 25% = Rs.150,000 x 3.571 - Rs.500,000

= Rs.35,650

NPV 30% = Rs.150,000 x 3.092 - Rs. 500,000= -Rs. 36,200

For i = 25 per cent, net present value is positive; i = 30 per cent, net present value is negative.Thus, for some discount rate between 25 and 30 per cent, present value benefits are equated topresent value costs. To find the rate more exactly, one can interpolate between the two rates asfollows:

i = 0.25 + (0.30-0.25) x 35650 / (35650 + 36200)

= 0.275, or 27.5 percent

6. Financial Management

137Bureau of Energy Efficiency

Page 179: General Aspect of Energy Management and Energy Audit

Cash Flows

Generally there are two kinds of cash flow; the initial investment as one or more installments,and the savings arising from the investment. This over simplifies the reality of energy manage-ment investment.There are usually other cash flows related to a project. These include the following:

• Capital costs are the costs associated with the design, planning, installation and com-missioning of the project; these are usually one-time costs unaffected by inflation or dis-count rate factors, although, as in the example, installments paid over a period of timewill have time costs associated with them.

• Annual cash flows, such as annual savings accruing from a project, occur each year overthe life of the project; these include taxes, insurance, equipment leases, energy costs, ser-vicing, maintenance, operating labour, and so on. Increases in any of these costs repre-sent negative cash flows, whereas decreases in the cost represent positive cash flows.

Factors that need to be considered in calculating annual cash flows are:-• Taxes, using the marginal tax rate applied to positive (i.e. increasing taxes) or negative

(i.e. decreasing taxes) cash flows.• Asset depreciation, the depreciation of plant assets over their life; depreciation is a

"paper expense allocation" rather than a real cash flow, and therefore is not includeddirectly in the life cycle cost. However, depreciation is "real expense" in terms of taxcalculations, and therefore does have an impact on the tax calculation noted above. Forexample, if a Rs.10,00,000 asset is depreciated at 20% and the marginal tax rate is 40%,the depreciation would be Rs.200,000 and the tax cash flow would be Rs.80,000 and itis this later amount that would show up in the costing calculation.

• Intermittent cash flows occur sporadically rather than annually during the life of the pro-ject, relining a boiler once every five years would be an example.

6.5 Sensitivity and Risk Analysis

Many of the cash flows in the project are based on assumptions that have an element of uncer-tainty. The present day cash flows, such as capital cost, energy cost savings, maintenance costs,etc can usually be estimated fairly accurately. Even though these costs can be predicted withsome certainty, it should always be remembered that they are only estimates. Cash flows infuture years normally contain inflation components which are often "guess-timates" at best. Theproject life itself is an estimate that can vary significantly.

Sensitivity analysis is an assessment of risk. Because of the uncertainty in assigning valuesto the analysis, it is recommended that a sensitivity analysis be carried out - particularly on pro-jects where the feasibility is marginal. How sensitive is the project's feasibility to changes in theinput parameters? What if one or more of the factors in the analysis is not as favourable as pre-dicted? How much would it have to vary before the project becomes unviable? What is the prob-ability of this happening?

Suppose, for example, that a feasible project is based on an energy cost saving that escalatesat 10% per year, but a sensitivity analysis shows the break-even is at 9% (i.e. the projectbecomes unviable if the inflation of energy cost falls below 9%). There is a high degree of riskassociated with this project - much greater than if the break-even value was at 2%.

6. Financial Management

138Bureau of Energy Efficiency

Page 180: General Aspect of Energy Management and Energy Audit

Many of the computer spreadsheet programs have built-in "what if" functions that make sensi-tivity analysis easy. If carried out manually, the sensitivity analysis can become laborious -reworking the analysis many times with various changes in the parameters.

Sensitivity analysis is undertaken to identify those parameters that are both uncertain andfor which the project decision, taken through the NPV or IRR, is sensitive. Switching valuesshowing the change in a variable required for the project decision to change from acceptance torejection are presented for key variables and can be compared with post evaluation results forsimilar projects. For large projects and those close to the cut-off rate, a quantitative risk analy-sis incorporating different ranges for key variables and the likelihood of their occurring simul-taneously is recommended. Sensitivity and risk analysis should lead to improved project design,with actions mitigating against major sources of uncertainty being outlined

The various micro and macro factors that are considered for the sensitivity analysis are list-ed below.

Micro factors

• Operating expenses (various expenses items) • Capital structure • Costs of debt, equity • Changing of the forms of finance e.g. leasing • Changing the project duration

Macro factors

Macro economic variables are the variable that affects the operation of the industry of which thefirm operates. They cannot be changed by the firm's management.Macro economic variables, which affect projects, include among others:

• Changes in interest rates • Changes in the tax rates • Changes in the accounting standards e.g. methods of calculating depreciation • Changes in depreciation rates • Extension of various government subsidized projects e.g. rural electrification • General employment trends e.g. if the government changes the salary scales • Imposition of regulations on environmental and safety issues in the industry • Energy Price change • Technology changes

The sensitivity analysis will bring changes in various items in the analysis of financial state-ments or the projects, which in turn might lead to different conclusions regarding the imple-mentation of projects.

6.6 Financing Options

There are various options for financing in-house energy management1. From a central budget2. From a specific departmental or section budget such as engineering3. By obtaining a bank loan4. By raising money from stock market

6. Financial Management

139Bureau of Energy Efficiency

Page 181: General Aspect of Energy Management and Energy Audit

5. By awarding the project to Energy Service Company (ESCO)6. By retaining a proportion of the savings achieved.

Self-Financing Energy Management

One way to make energy management self-financing is to split savings to provide identifiablereturns to each interested party. This has the following benefits:

• Assigning a proportion of energy savings to your energy management budget means youhave a direct financial incentive to identify and quantify savings arising from your ownactivities.

• Separately identified returns will help the constituent parts of your organization under-standing whether they are each getting good value for money through their support forenergy management.

• If operated successfully, splitting the savings will improve motivation and commitmentto energy management throughout the organization since staff at all levels will see afinancial return for their effort or support.

• But the main benefit is on the independence and longevity of the energy managementfunction.

Ensuring Continuity

After implementation of energy savings, your organization ought to be able to make consider-able savings at little cost (except for the funding needed for energy management staff). Theimportant question is what should happen to these savings?

If part of these easily achieved savings is not returned to your budget as energy manager,then your access to self-generated investments funds to support future activities will be lost.And later in the program, it is likely to be much harder for you to make savings.

However, if, an energy manager, has access to a proportion of the revenue savings arisingfrom staff's activities, then these can be reinvested in:

• Further energy efficiency measures• Activities necessary to create the right climate for successful energy management which

do not, of themselves, directly generate savings • Maintaining or up-grading the management information system.

Energy Performance Contracting and Role of ESCOS

If the project is to be financed externally, one of the attractive options for many organizationsis the use of energy performance contracts delivered by energy service companies, or ESCOs.

ESCOs are usually companies that provide a complete energy project service, from assess-ment to design to construction or installation, along with engineering and project managementservices, and financing. In one way or another, the contract involves the capitalization of all ofthe services and goods purchased, and repayment out of the energy savings that result from theproject.

In performance contracting, an end-user (such as an industry, institution, or utility), seekingto improve its energy efficiency, contracts with ESCO for energy efficiency services and financ-ing.

In some contracts, the ESCOs provide a guarantee for the savings that will be realized, andabsorbs the cost if real savings fall short of this level. Typically, there will be a risk manage-

6. Financial Management

140Bureau of Energy Efficiency

Page 182: General Aspect of Energy Management and Energy Audit

ment cost involved in the contract in these situations. Insurance is sometimes attached, at a cost,to protect the ESCO in the event of a savings shortfall.

Energy efficiency projects generate incremental cost savings as opposed to incremental rev-enues from the sale of outputs. The energycost savings can be turned into incrementalcash flows to the lender or ESCO based onthe commitment of the energy user (and insome cases, a utility) to pay for the savings.

What are performance contracts?

Performance contracting represents one ofthe ways to address several of the most fre-quently mentioned barriers to investment.Performance contracting through an ESCOtransfers the technology and managementrisks away from the end-user to the ESCO.

For energy users reluctant to invest inenergy efficiency, a performance contractcan be a powerful incentive to implement aproject. Performance contracting also mini-mizes or eliminates the up-front cash outlayrequired by the end-user. Payments aremade over time as the energy savings arerealized.

6. Financial Management

141Bureau of Energy Efficiency

Figure 6.1 ESCO Role

Page 183: General Aspect of Energy Management and Energy Audit

6. Financial Management

142Bureau of Energy Efficiency

QUESTIONS

1. Why fresh investments are needed for energy conservation in industry?

2. Name at least three selling points to top management for investing in energy efficien-cy over other competitive projects.

3. Cost of an heat exchanger is Rs.1.00 lakhs .Calculate simple pay back period consid-ering annual saving potential of Rs.60,000/- and annual operating cost ofRs.15,000/- .

4. What is the main draw back of simple pay back method?

5. Calculate simple pay back period for a boiler that cost Rs.75.00 lakhs to purchaseand Rs.5 lakhs per year on an average to operate and maintain and is expected toannually save Rs.30 lakhs.

6. What are the advantages of simple pay back method?

7. A project entails an investment for initial cost of installation and series of annualcosts and/or cost savings through out the life of project.. Recommend a suitablefinancial analysis techniques and explain.

8. What do you understand by the term " present value of money"?

9. What do you understand by the term " discounting"?

10. ROI stands for (a) return on investment (b) rotating on investment (c) realization on investment (d)

reality only investment?

11. Define ROI .

12. Investment for an energy proposal is Rs.10.00 lakhs. Annual savings for the firstthree years is 150,000, 200,000 & 300,000. Considering cost of capital as 10%, whatis the net present value of the proposal?

13. What are the advantages of net present value?

14. Internal rate of return of a project is the discount rate which makes its net presentvalue equal to zero. Explain

15. What are the advantages of discounted cash flow method?

16. What is the main limitation of discounted cash flow method?

17. What is the objective of carrying out sensitivity analysis?

18. Name at least three financing options for energy management.

19. What is role of an ESCO?

20. What is performance contracting?

REFERENCES1. Financial Management, Tata Mc-Graw Hill - Prasanna Chandra.

Page 184: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

Chapter 1.6 Financial Management Part – I: Objective type questions and answers

1. Simple pay back period is equal to:

a) Ratio of First cost/net yearly savings b) Ratio of Annual gross cash flow/capital cost

c) ∑= +

n

tt

t

kCF

0 )1( d) All the above

2. Simple payback period for an energy efficient motor that costs Rs. 1.5 lakh to purchase and install and is expected to save Rs. 0.75 lakh per annum is:

a) 1.1 years b) 2 years c) 0.75 years d) 2.25 years

3. Which of the following equation used to calculate the future value of the cash flow?

a) NPV (1 – i)n b) NPV (1 + i)n

c) NPV + (1 – i)n b) NPV/ (1 + i)n

4. The NPV of equipment is Rs. 10000 and interest on discount rate is 10%. The future value of the cash flow at the end of 2 years is:

a) Rs. 10000 b) Rs. 12,100 c) Rs. 8100 d) Rs. 8264

5. The cost of replacement of inefficient compressor with an energy efficient compressor in a plant was Rs 5 lakh. The net annual cash flow is Rs 1.25 lakh. The return on investment is:

a) 15% b) 20% c) 25% d) 19.35%

6. The ratio of annual net cash flow to capital cost is ____________

a) Net present value b) Internal rate of return

c) Return on investment d) Discount factor

7. The broad indicator of the annual return expected from initial capital investment is __

a) NPV b) IRR

c) ROI d) Discount factor

8. The sum of present values of all the cash flows associated with it is called ___________

a) Return on Investment b) Internal Rate of Return

c) Net Present Value d) None of the above

9. The factor that reflects the risk of the project while evaluating the present value of the expected future cash flow is ________________

a) Life of the project b) Discount rate

c) Capital cost d) All the above

10. IRR stands for_________

a) Integration rate of return b) Interest return rate

c) Internal rate of return d) Investment return rate

1.6 Financial management - revised (table format) 42

Page 185: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

11. For all the expenditures in the plant, the value of cash flow at the end of the year will be

a) Positive b) Negative

c) Nil d) None of the above

12. The set net present value to determine internal rate of return is _______

a) 1 b) 0 c) 10 d) 2

13. The internal rate of return cannot distinguish between ____________

a) Lending b) Borrowing c) Both a & b d) None

14. Sensitivity analysis is an assessment of ________________

a) Profits b) Losses c) Risk d) all

15. The present value of a Rs. 1000 cost in year “0” projected to 10 years at an escalation rate of 5% and a 10% interest rate is:

a) Rs. 4225 b) Rs. 628 c) Rs. 1 d) Rs. 2.33

16. The present value of Rs. 1000 in 10 years time at an interest rate of 10% is:

a) Rs. 2594 b) Rs. 386 c) Rs. 349 d) Rs. 10000

17. What is ESCO?

a) Energy saving company b) Energy sourcing company

c) Energy service company d) Energy section of company

18. ROI must always be ___ than interest rate

a) Lower b) Higher c) Equal d) No relation

19. The key to the successful involvement of an ESCO in performance contracting is:

a) Monitoring b) Verification c) Both a & b d) None

20. Costs associated with the design, planing, installation and commissioning of a project are:

a) Variable costs b) Capital costs c) Salvage value d)None

Part – II: Short type questions and answers

1. List out different costs involved in the process of implementing energy management?

Different costs involved in the process of implementing energy management are:

i) Direct project cost

ii) Additional operations and maintenance cost

iii) Training of personnel

2. What circumstances need investments for energy conservation in any plant?

The need for investments in energy conservation can arise under following circumstances:

i. For new equipment, process improvements etc.

ii. To provide staff training

iii. To implement or upgrade the energy information system

1.6 Financial management - revised (table format) 43

Page 186: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

iv. And other priorities

3. What criteria need to be considered while listing down the investment opportunities for any energy conservation project?

When listing investment opportunities the following criteria need to be considered:

i) Energy consumption per unit of production of a plant or process

ii) Current state of repair and energy efficiency

iii) Quality of the indoor environment

iv) Effect of any proposed measure on staff attitudes and behaviour

4. Why organizations hesitant to invest money on energy conservation projects?

i. Organization typically gives priority to investing in what they see as their core or profit-making activities in preference to energy efficiency

ii. Even when they do invest in saving energy, they tend to demand faster rates of return than they require from other kinds of investment.

5. What are the basic criteria for financial investment appraisal?

The basic criteria for financial investment appraisal include

• Simple payback period,

• Return on investment and internal rate of return

• Net present value and cash flow

6. Why short term payback is an inadequate yardstick for assessing longer term benefits?

The benefits arising from some energy saving measures may continue long after their payback periods. Such measures do not need to be written off using fast discounting rates but can be regarded as adding to the long term value of the assets. For this reason, short term payback is an inadequate yardstick for assessing longer term benefits

7. How do you relate plant maintenance to achieve energy efficiency in a plant?

There is a clear dependence relationship between energy efficiency and maintenance. This operates at two levels:

Initially, improving energy efficiency is most cost-effectively done in existing facilities through normal maintenance procedures

Subsequently, unless maintenance is regularly undertaken, savings from installed technical measure, whether in new-build or existing facilities, may not be realized.

8. List down the advantages with ‘Simple Payback period’ technique

A widely used investment criterion, the simple payback period offers the following advantages:

• It is simple, both in concept and application. Obviously a shorter payback generally indicates a more attractive investment. It does not use tedious calculations.

• It favours projects, which generate substantial cash inflows in earlier years, and discriminates against projects, which bring substantial cash inflows in later years but not in earlier years.

9. What are the limitations with Return on Investment technique?

The limitations with ROI technique are:

It does not take into account the time value of money.

It does not account for the variable nature of annual net cash inflows.

1.6 Financial management - revised (table format) 44

Page 187: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

10. Calculate net present value for an investment towards a Compact Fluorescent Lamp (CFL). The following table gives investment and cash flow. (Assume discount rate is 10% and life of the CFL is 2 years).

Investment Rs.400/-

Savings in year Cash flow, Rs

Year # 1 1000

Year # 2 1000

Investment : Rs 400/-

Discount rate (k) : 10% (i.e. 0.1)

Life of the CFL (t) : 2 years

NPV : ∑= +

n

tt

t

kCF

0 )1(

NPV = 00

)1( kCF+

+ 11

)1( kCF+

+ 22

)1( kCF+

= 0)1.01(400

+−

+ 1)1.01(1000+

+ 2)1.01(1000+

= -400 + 909 + 826

= Rs 1335/-

11. What are the main advantages with Net Present Value criterion?

The net present value criterion has considerable merits.

i. it takes in to account the time value of money

ii. it considers the cash flow stream in its project life

12. What is the limitation with internal rate of return figure?

The internal rate of return figure cannot distinguish between lending and borrowing and hence a high internal rate of rerun need not necessarily be a desirable feature.

13. What are different kinds of cash flows in any energy management project?

Generally there are two kinds of cash flow; the initial investment as one or more instalments, and the savings arising from the investment.

14. List down the factors need to be considered in calculating annual cash flows.

Taxes, Asset depreciation and intermittent cash flows

15. Under which circumstances sensitivity analysis is required?

Sensitivity analysis is an assessment of risk. Sensitivity analysis is carried out particularly on projects where the feasibility is marginal.

1.6 Financial management - revised (table format) 45

Page 188: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

16. Calculate the present value of tax cash flow from a Rs. 10,000 investment towards 5 hp energy efficient motor with 30% declining balance depreciation rate, 50% tax rate and 10% interest rate.

Present Value = P x d x t / (i + d)= (10000 x 0.3 x 0.5)/ (0.1 + 0.3) = Rs. 3750

17. List down any three options available for financing in-house energy management?

i. From a capital budget

ii. From a specific department or section budget

iii. By obtaining bank loan

iv. By raising money from stock market

18. How to make energy management self financing?

One way to make energy management self financing is to split savings to provide identifiable returns to each interested party.

19. How an energy manager utilises if he has access to a proportion of the revenue savings arising from staff activities?

if, an energy manager has access to a proportion of the revenue savings arising from staff’s activities, then these can be reinvested in:

Further energy efficiency measures

Activities necessary to create the right climate for successful energy management which do not, of themselves, directly generate savings

Maintaining or up-grading the management information system.

20. What do you understand about ESCOs?

ESCOs are usually companies that provide a complete energy project service, from assessment to design to construction or installation, along with engineering and project management services, land financing.

Part – III: Long type questions and answers

An energy auditor recommended to replace an old air fan and incompetently designed air delivery duct system causing Rs 23 lakh a year in electricity cost by changing the system with a modern backward curved fan with adequately designed duct system for total investment costs of Rs 2.2 lakh. Expected electricity cost reduction is 5%. Considering over 15 years sustained savings, calculate ‘IRR’

Life of the modified system : 15 years

Expected annual savings : 5%

: 0.05 x 2300000

Rs. 1,15,000 / year

1.

Investment : Rs 2,20,000/-

1.6 Financial management - revised (table format) 46

Page 189: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

S = xIi

xiin

n

1)1()1(

−++

S = annual energy savings

I = Investment

N = years

I = Internal rate of return

1)1()1(

220000115000

15

15

−++

=i

xii

By trial and error method, I = 52%

Annual savings after replacement of boiler for three years is Rs. 5, 00,000, Rs. 5, 50,000, Rs. 6, 50,000. Total project cost is Rs 13.5 lakh. Considering cost of capital as 12%, what is the net present value of the proposal?

Cash flow stream of project

Investment Rs 13,50,000 Annual savings Cashflow 1 5,00,000 2 5,50,000 3 6,50,000

Cost of capital to the plant is 12%. The net present value of the proposal is:

NPV = 321 )12.1(650000

)12.1(550000

)12.1(500000

++

= 446428 + 438456 + 462657

= 13,47,541

2.

NPV = 13,50,000-13,47,541 = 2459

What is performance contracting?

The core of performance contracting is an agreement involving a comprehensive package of services provided by an ESCO, including:

An energy efficiency opportunity analysis

Project development

Engineering

Financing

Construction/Implementation

3.

Training

1.6 Financial management - revised (table format) 47

Page 190: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

Monitoring and verification

Monitoring and verification, is key to the successful involvement of an ESCO in performance contracting where energy cost savings are being guaranteed.

ESCOs are not “bankers” in the narrow sense. Their strength is in putting together a package of services that can provide guaranteed and measurable energy savings that serve as the basis for guaranteed cost savings. But, the energy savings must be measurable. The Figure 6.1 shows ESCO Role. Refer “figure No. 6.1 page No. 127 of book I need to form part of answer

Explain the limitations with ‘Simple Payback Period’ technique with an example.

The limitations are:

• It fails to consider the time value of money. Cash inflows, in the payback calculation, are simply added without suitable discounting. This violates the most basic principle of financial analysis, which stipulates that cash flows occurring at different points of time can be added or subtracted only after suitable compounding/discounting.

• It ignores cash flows beyond the payback period. This leads to discrimination against projects that generate substantial cash inflows in later years.

To illustrate, consider the cash flows of two projects, A and B:

Investment Rs. (100,000) Rs.(100,000)

Savings in Year Cash Flow of A Cash flow of B

1 50,000 20,000

2 30,000 20,000

3 20,000 20,000

4 10,000 40,000

5 10,000 50,000

6 - 60,000

The payback criterion prefers A, which has a payback period of 3 years, in comparison to B, which has a payback period of 4 years, even though B has very substantial cash inflows in years 5 and 6.

• It is a measure of a project’s capital recovery, not profitability.

4.

• Despite its limitations, the simple payback period has advantages in that it may be useful for evaluating an investment.

1.6 Financial management - revised (table format) 48

Page 191: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

Year 0 1 2 3 4 Cash flow (100,000) 30,000 30,000 40,000 45,000

30,000 30,000 40,000 45,000 100,000 = ------------ + ------------- + --------------- + --------------- (1 + κ)1 ( 1 + κ)2 ( 1 + κ )3 ( 1 + κ )4

Calculate the internal rate of return for the following cash flow of a project. Calculate the internal rate of return for the following cash flow of a project.

The internal rate of return is the value of “r” which satisfies the following equation:

The calculation of “κ” involves a process of trial and error. Try with different values of “κ” till the right-hand side of the above equation is equal to 100,000. To begin with, try κ = 15 per cent. This makes the right-hand side equal to:

30,000 30,000 40,000 45,000 ----------- + ------------- + --------------- + --------------- = 100, 802 (1.15) (1.15)2 (1.15)3 (1.15)4

This value is slightly higher than our target value, 100,000. So increase the value of κ from 15 per cent to 16 per cent. (In general, a higher κ lowers and a smaller r increases the right-hand side value). The right-hand side becomes:

30,000 30,000 40,000 45,000 ------------ + ------------- + --------------- + --------------- = 98, 641 (1.16) (1.16)2 (1.16)3 (1.16)4

5.

Since this value is now less than 100,000, it can be concluded that the value of r lies between 15 per cent and 16 per cent. For most of the purposes this indication suffices.

1.6 Financial management - revised (table format) 49

Page 192: General Aspect of Energy Management and Energy Audit

7. PROJECT MANAGEMENT

143Bureau of Energy Efficiency

SyllabusDefinition and scope of project, Technical design, Financing, Contracting, Implementationand performance monitoring. Implementation plan for top management, Planning Budget,Procurement Procedures, Construction, Measurement & Verification.

7.1 Introduction

Project management is concerned with the overall planning and co-ordination of a project fromconception to completion aimed at meeting the stated requirements and ensuring completion ontime, within cost and to required quality standards. Project management is normally reserved for focused, non-repetitive, time-limited activitieswith some degree of risk and that are beyond the usual scope of operational activities for whichthe organization is responsible.

7.2 Steps in Project Management

The various steps in a project management are:1. Project Definition and Scope2. Technical Design3. Financing4. Contracting5. Implementation 6. Performance Monitoring

7.2.1 Project Definition and Scope

What is a Project?

"A project is a one-shot, time-limited, goal-directed, major undertaking, requiring thecommitment of varied skills and resources".

A project is a temporary endeavor undertaken to create a unique product or service. A pro-ject is temporary in that there is a defined start (the decision to proceed) and a defined end (theachievement of the goals and objectives). Ongoing business or maintenance operations are notprojects. Energy conservation projects and process improvement efforts that result in betterbusiness processes or more efficient operations can be defined as projects. Projects usuallyinclude constraints and risks regarding cost, schedule or performance outcome.

Four Basic Elements of Project Management

A successful Project Manager must simultaneously manage the four basic elements of a project:

Page 193: General Aspect of Energy Management and Energy Audit

resources, time, cost, and scope. Each element must be managed effectively. All these elementsare interrelated and must be managed together if the project, and the project manager, is to bea success.

Managing Resources

A successful Project Manager must effectively manage the resources assigned to the project.This includes the labor hours of the project team. It also includes managing labor subcontractsand vendors. Managing the people resources means having the right people, with the right skillsand the proper tools, in the right quantity at the right time.

However, managing project resources frequently involves more than people management.The project manager must also manage the equipment (cranes, trucks and other heavy equip-ment) used for the project and the material (pipe, insulation, computers, manuals) assigned tothe project.

Managing Time and Schedule

Time management is a critical skill for any successful project manager. The most commoncause of bloated project budgets is lack of schedule management. Fortunately there is a lot ofsoftware on the market today to help you manage your project schedule or timeline.

Any project can be broken down into a number of tasks that have to be performed. To pre-pare the project schedule, the project manager has to figure out what the tasks are, how longthey will take, what resources they require, and in what order they should be done.

Managing Costs

Often a Project Manager is evaluated on his or her ability to complete a project within budget.The costs include estimated cost, actual cost and variability. Contingency cost takes intoaccount influence of weather, suppliers and design allowances.

How the 80/20 Rule can help a project manager?

The 80/20 Rule means that in anything a few (20 percent) are vital and many (80 percent) aretrivial. Successful Project Managers know that 20 percent of the work (the first 10 percent andthe last 10 percent) consumes 80 percent of your time and resources.

Project Management Life Cycle

The process flow of Project management processes is shown in Figure 7.1. The various ele-ments of project management life cycle area) Need identificationb) Initiationc) Planningd) Executinge) Controllingf) Closing out

7. Project Management

144Bureau of Energy Efficiency

Page 194: General Aspect of Energy Management and Energy Audit

7. Project Management

145Bureau of Energy Efficiency

a) Need Identification

The first step in the project development cycle is to identify components of the project. Projectsmay be identified both internally and externally:

• Internal identification takes place when the energy manager identifies a package of energy saving opportunities during the day-to-day energy management activities, or from facility audits.

• External identification of energy savings can occur through systematic energy auditsundertaken by a reputable energy auditor or energy service company.

In screening projects, the following criteria should be used to rank-order projectopportunities.

• Cost-effectiveness of energy savings of complete package of measures (Internal rateof return, net present value, cash flow, average payback)

• Sustainability of the savings over the life of the equipment.• Ease of quantifying, monitoring, and verifying electricity and fuel savings.• Availability of technology, and ease of adaptability of the technology to Indian

conditions.• Other environmental and social cost benefits (such as reduction in local pollutants,

e.g. SOx)

b) Initiation

Initiating is the basic processes that should be performed to get the project started. This start-ing point is critical because those who will deliver the project, those who will use the project,and those who will have a stake in the project need to reach an agreement on its initiation.Involving all stakeholders in the project phases generally improves the probability of satisfyingcustomer requirements by shared ownership of the project by the stakeholders. The success ofthe project team depends upon starting with complete and accurate information, managementsupport, and the authorization necessary to manage the project.

Figure 7.1 Process Flow of a Project Management Process

Page 195: General Aspect of Energy Management and Energy Audit

7. Project Management

146Bureau of Energy Efficiency

c) Planning

The planning phase is considered the most important phase in project management. Projectplanning defines project activities that will be performed; the products that will be produced,and describes how these activities will be accomplished and managed. Project planning defineseach major task, estimates the time, resources and cost required, and provides a framework formanagement review and control. Planning involves identifying and documenting scope, tasks,schedules, cost, risk, quality, and staffing needs.

The result of the project planning, the project plan, will be an approved, comprehensive doc-ument that allows a project team to begin and complete the work necessary to achieve the pro-ject goals and objectives. The project plan will address how the project team will manage theproject elements. It will provide a high level of confidence in the organization's ability to meetthe scope, timing, cost, and quality requirements by addressing all aspects of the project.

d) Executing

Once a project moves into the execution phase, the project team and all necessary resources tocarry out the project should be in place and ready to perform project activities. The project planis completed and base lined by this time as well. The project team and the project manager'sfocus now shifts from planning the project efforts to participating, observing, and analyzing thework being done.

The execution phase is when the work activities of the project plan are executed, resultingin the completion of the project deliverables and achievement of the project objective(s). Thisphase brings together all of the project management disciplines, resulting in a product or ser-vice that will meet the project deliverable requirements and the customers need. During thisphase, elements completed in the planning phase are implemented, time is expended, andmoney is spent.

In short, it means coordinating and managing the project resources while executing the pro-ject plan, performing the planned project activities, and ensuring they are completed efficient-ly.

e) Controlling

Project Control function that involves comparing actual performance with planned performanceand taking corrective action to get the desired outcome when there are significant differences.By monitoring and measuring progress regularly, identifying variances from plan, and takingcorrective action if required, project control ensures that project objectives are met.

f) Closing out

Project closeout is performed after all defined project objectives have been met and the cus-tomer has formally accepted the project's deliverables and end product or, in some instances,when a project has been cancelled or terminated early. Although, project closeout is a routineprocess, it is an important one. By properly completing the project closeout, organizations canbenefit from lessons learned and information compiled. The project closeout phase is comprisedof contract closeout and administrative closure.

7.2.2 Technical Design

For a project to be taken up for investment, its proponent must present a sound technical feasi-

Page 196: General Aspect of Energy Management and Energy Audit

7. Project Management

147Bureau of Energy Efficiency

bility study that identifies the following components:

# The proposed new technologies, process modifications, equipment replacements andother measures included in the project.

# Product/technology/material supply chain (e.g., locally available, imported, reliability ofsupply)

# Commercial viability of the complete package of measures (internal rate of return, netpresent value, cash flow, average payback).

# Any special technical complexities (installation, maintenance, repair), associated skillsrequired.

# Preliminary designs, including schematics, for all major equipment needed, along withdesign requirements, manufacturer's name and contact details, and capital cost estimate.

# Organizational and management plan for implementation, including timetable, person-nel requirements, staff training, project engineering, and other logistical issues.

7.2.3 Financing

When considering a new project, it should be remembered that other departments in the orga-nization would be competing for capital for their projects. However, it is also important to real-ize that energy efficiency is a major consideration in all types of projects, whether they are:

• Projects designed to improve energy efficiency• Projects where energy efficiency is not the main objective, but still plays a vital role.

The funding for project is often outside the control of the project manager. However, it is impor-tant that you understand the principles behind the provision of scarce funds.

Project funds can be obtained from either internal or external sources.

Internal sources include:• Direct cash provision from company reserves• From revenue budget (if payback is less than one year)• New share capital

Funding can become an issue when energy efficiency projects have previously been given alower priority than other projects. It is worth remembering that while the prioritization of pro-jects may not be under our control, the quality of the project submission is.

External sources of funds include:• Bank loans• Leasing arrangement• Payment by savings i.e. A deal arranged with equipment supplier• Energy services contract• Private finance initiative

The availability of external funds depends on the nature of your organization. The financecharges on the money you borrow will have a bearing on the validity of your project.

Before applying for money, discuss all the options for funding the project with your financemanagers.

It is reiterated that energy savings often add substantially to the viability of othernon-energy projects.

Page 197: General Aspect of Energy Management and Energy Audit

7.2.4 Contracting

Since a substantial portion of a project is typically executed through contracts, the proper man-agement of contracts is critical to the successful implementation of the project. In this context,the following should be done.

• The competence and capability of all the contractors must be ensured. One weak link canaffect the timely performance of the contract.

• Proper discipline must be enforced among contractors and suppliers by insisting thatthey should develop realistic and detailed resource and time plans that are matching withthe project plan.

• Penalties may be imposed for failure to meet contractual obligations. Likewise, incen-tives may be offered for good performance.

• Help should be extended to contractors and suppliers when they have genuine problems.• Project authorities must retain independence to off-load contracts (partially or wholly)

to other parties where delays are anticipated.

If the project is to implemented by an outside contractor, several types of contract may be usedto undertake the installation and commissioning:

• Traditional Contract: All project specifications are provided to a contractor who pur-chases and installs equipment at cost plus a mark-up or fixed price.

• Extended Technical Guarantee/Service: The contractor offers extended guarantees onthe performance of selected equipment and / or service/maintenance agreements.

• Extended Financing Terms: The contractor provides the option of an extended lease orother financing vehicle in which the payment schedule can be based on the expected sav-ings.

• Guaranteed Saving Performance Contract: All or part of savings is guaranteed by thecontractor, and all or part of the costs of equipment and/or services is paid down out ofsavings as they are achieved.

• Shared Savings Performance Contract: The contractor provides the financing and ispaid an agreed fraction of actual savings as they are achieved. This payment is used topay down the debt costs of equipment and/or services.

7.2.5 Implementation

The main problems faced by project manager during implementation are poor monitoring ofprogress, not handling risks and poor cost management.

a) Poor monitoring of progress: Project managers some times tend to spend most of theirtime in planning activity and surprisingly very less time in following up whether theimplementation is following the plan. A proactive report generated by project plannersoftware can really help the project manager to know whether the tasks are progressingas per the plan.

b) Not handling risks: Risks have an uncanny habit of appearing at the least expectedtime. In spite of the best efforts of a project manager they are bound to happen. Risksneed immediate and focused attention. Delay in dealing with risks cause the problem toaggravate and has negative consequences for the project.

c) Poor cost management: A project manager's success is measured by the amount of costoptimization done for a project. Managers frequently do all the cost optimization duringthe planning stages but fail to follow through during the rest of the stages of the project.

7. Project Management

148Bureau of Energy Efficiency

Page 198: General Aspect of Energy Management and Energy Audit

The cost graphs in the Project planner software can help a manager to get a update onproject cost overflow. The cost variance (The difference between approved cost and theprojected cost should be always in the minds of the project managers).

Project Planning Techniques

The three basic project planning techniques are Gantt chart, CPM and PERT. All monitorprogress and costs against resource budgets.

Gantt Chart

Gantt charts are also called Bar charts. The use of Gantt charts started during the industrial rev-olution of the late 1800's. An early industrial engineer named Henry Gantt developed thesecharts to improve factory efficiency.

Gantt chart is now commonly used for scheduling the tasks and tracking the progress ofenergy management projects. Gantt charts are developed using bars to represent each task. Thelength of the bar shows how long the task is expected to take to complete. Duration is easilyshown on Gantt charts. Sequence is not well shown on Gantt Charts (Refer Figure 7.2).

If, for example, the start of Task C depends on both Activity B and Activity E, then any delayto Task E will also delay Task C. We just don't have enough information on the Gantt chart toknow this information.

CPM - Critical Path Method

DuPont developed a Critical Path Method (CPM) designed to address the challenge of shut-ting down chemical plants for maintenance and then restarting the plants once the maintenancehad been completed.

Complex project, like the above example, require a series of activities, some of which mustbe performed sequentially and others that can be performed in parallel with other activities. Thiscollection of series and parallel tasks can be modeled as a network.CPM models the activities and events of a project as a network. Activities are shown as nodeson the network and events that signify the beginning or ending of activities are shown as arcsor lines between the nodes. The Figure 7.3 shows an example of a CPM network diagram:

7. Project Management

149Bureau of Energy Efficiency

Figure 7.2 Gantt Chart

Page 199: General Aspect of Energy Management and Energy Audit

Steps in CPM Project Planning

1. Specify the individual activities.2. Determine the sequence of those activities.3. Draw a network diagram.4. Estimate the completion time for each activity.5. Identify the critical path (longest path through the network)6. Update the CPM diagram as the project progresses.

1. Specify the individual activities

All the activities in the project are listed. This list can be used as the basis for adding sequenceand duration information in later steps.

2. Determine the sequence of the activities

Some activities are dependent on the completion of other activities. A list of the immediate pre-decessors of each activity is useful for constructing the CPM network diagram.

3. Draw the Network Diagram

Once the activities and their sequences have been defined, the CPM diagram can be drawn.CPM originally was developed as an activity on node network.

4. Estimate activity completion time

The time required to complete each activity can be estimated using past experience. CPM doesnot take into account variation in the completion time.

5. Identify the Critical Path

The critical path is the longest-duration path through the network. The significance of the crit-ical path is that the activities that lie on it cannot be delayed without delaying the project.Because of its impact on the entire project, critical path analysis is an important aspect of pro-ject planning.The critical path can be identified by determining the following four parameters for each activ-ity:

• ES - earliest start time: the earliest time at which the activity can start given that itsprecedent activities must be completed first.

• EF - earliest finish time, equal to the earliest start time for the activity plus the time

7. Project Management

150Bureau of Energy Efficiency

Figure 7.3 CPM Diagram

Page 200: General Aspect of Energy Management and Energy Audit

required to complete the activity.• LF - latest finish time: the latest time at which the activity can be completed without

delaying the project.• LS - latest start time, equal to the latest finish time minus the time required to complete

the activity.The slack time for an activity is the time between its earliest and latest start time, or between itsearliest and latest finish time. Slack is the amount of time that an activity can be delayed pastits earliest start or earliest finish without delaying the project.

The critical path is the path through the project network in which none of the activities haveslack, that is, the path for which ES=LS and EF=LF for all activities in the path. A delay in thecritical path delays the project. Similarly, to accelerate the project it is necessary to reduce thetotal time required for the activities in the critical path.

6. Update CPM diagram

As the project progresses, the actual task completion times will be known and the network dia-gram can be updated to include this information. A new critical path may emerge, and structur-al changes may be made in the network if project requirements change.

CPM Benefits

• Provides a graphical view of the project.• Predicts the time required to complete the project.• Shows which activities are critical to maintaining the schedule and which are not.

CPM Limitations

While CPM is easy to understand and use, it does not consider the time variations that can havea great impact on the completion time of a complex project. CPM was developed for complexbut fairly routine projects with minimum uncertainty in the project completion times. For lessroutine projects there is more uncertainty in the completion times, and this uncertainty limits itsusefulness.

PERT

The Program Evaluation and Review Technique (PERT) is a network model that allows for ran-domness in activity completion times. PERT was developed in the late 1950's for the U.S.Navy's Polaris project having thousands of contractors. It has the potential to reduce both thetime and cost required to complete a project.

The Network Diagram

In a project, an activity is a task that must be performed and an event is a milestone marking thecompletion of one or more activities. Before an activity can begin, all of its predecessor activi-ties must be completed. Project network models represent activities and milestones by arcs andnodes.

PERT is typically represented as an activity on arc network, in which the activities are rep-resented on the lines and milestones on the nodes. The Figure 7.4 shows a simple example of aPERT diagram.

7. Project Management

151Bureau of Energy Efficiency

Page 201: General Aspect of Energy Management and Energy Audit

The milestones generally are numbered so that the ending node of an activity has a higher num-ber than the beginning node. Incrementing the numbers by 10 allows for new ones to be insert-ed without modifying the numbering of the entire diagram. The activities in the above diagramare labeled with letters along with the expected time required to complete the activity.

Steps in the PERT Planning Process

PERT planning involves the following steps:

1. Identify the specific activities and milestones.

2. Determine the proper sequence of the activities.

3. Construct a network diagram.

4. Estimate the time required for each activity.

5. Determine the critical path.

6. Update the PERT chart as the project progresses.

1. Identify activities and milestones

The activities are the tasks required to complete the project. The milestones are the events mark-ing the beginning and end of one or more activities.

2. Determine activity sequence

This step may be combined with the activity identification step since the activity sequence isknown for some tasks. Other tasks may require more analysis to determine the exact order inwhich they must be performed.

3. Construct the Network Diagram

Using the activity sequence information, a network diagram can be drawn showing the sequenceof the serial and parallel activities.

4. Estimate activity times

Weeks are a commonly used unit of time for activity completion, but any consistent unit of timecan be used.

A distinguishing feature of PERT is its ability to deal with uncertainty in activity comple-tion times. For each activity, the model usually includes three time estimates:

7. Project Management

152Bureau of Energy Efficiency

Figure 7.4 PERT Diagram

Page 202: General Aspect of Energy Management and Energy Audit

7. Project Management

153Bureau of Energy Efficiency

• Optimistic time (OT) - generally the shortest time in which the activity can be complet-ed. (This is what an inexperienced manager believes!)

• Most likely time (MT) - the completion time having the highest probability. This is dif-ferent from expected time. Seasoned managers have an amazing way of estimating veryclose to actual data from prior estimation errors.

• Pessimistic time (PT) - the longest time that an activity might require.

The expected time for each activity can be approximated using the following weighted average:

Expected time = (OT + 4 x MT+ PT) / 6

This expected time might be displayed on the network diagram.

Variance for each activity is given by:[(PT - OT) / 6]2

5. Determine the Critical Path

The critical path is determined by adding the times for the activities in each sequence and deter-mining the longest path in the project. The critical path determines the total time required forthe project.

If activities outside the critical path speed up or slow down (within limits), the total projecttime does not change. The amount of time that a non-critical path activity can be delayed with-out delaying the project is referred to as slack time.

If the critical path is not immediately obvious, it may be helpful to determine the followingfour quantities for each activity:

• ES - Earliest Start time

• EF - Earliest Finish time

• LS - Latest Start time

• LF - Latest Finish timeThese times are calculated using the expected time for the relevant activities. The ES and

EF of each activity are determined by working forward through the network and determiningthe earliest time at which an activity can start and finish considering its predecessor activities.

The latest start and finish times are the latest times that an activity can start and finish with-out delaying the project. LS and LF are found by working backward through the network. Thedifference in the latest and earliest finish of each activity is that activity's slack. The critical paththen is the path through the network in which none of the activities have slack.

The variance in the project completion time can be calculated by summing the variances inthe completion times of the activities in the critical path. Given this variance, one can calculatethe probability that the project will be completed by a certain date.

Since the critical path determines the completion date of the project, the project can beaccelerated by adding the resources required to decrease the time for the activities in the criti-cal path. Such a shortening of the project sometimes is referred to as project crashing.

Page 203: General Aspect of Energy Management and Energy Audit

6. Update as project progresses

Make adjustments in the PERT chart as the project progresses. As the project unfolds, the esti-mated times can be replaced with actual times. In cases where there are delays, additionalresources may be needed to stay on schedule and the PERT chart may be modified to reflect thenew situation.

Benefits of PERT

PERT is useful because it provides the following information:• Expected project completion time.• Probability of completion before a specified date.• The critical path activities that directly impact the completion time.• The activities that have slack time and that can lend resources to critical path activities.• Activities start and end dates.

Limitations of PERT

The following are some of PERT's limitations:• The activity time estimates are somewhat subjective and depend on judgment. In cases

where there is little experience in performing an activity, the numbers may be only aguess. In other cases, if the person or group performing the activity estimates the timethere may be bias in the estimate.

• The underestimation of the project completion time due to alternate paths becoming crit-ical is perhaps the most serious.

7.2.6 Performance Monitoring

Once the project is completed, performance review should be done periodically to compareactual performance with projected performance. Feedback on project is useful in several ways:

a) It helps us to know how realistic were the assumptions underlying the projectb) It provides a documented log of experience that is highly valuable in decision making in

future projectsc) It suggests corrective action to be taken in the light of actual performanced) It helps in uncovering judgmental biasese) It includes a desired caution among project sponsors.Performance Indicators (PIs) are an effective way of communicating a project's benefits,

usually as part of a performance measuring and reporting process. Performance Indicators areavailable for a wide range of industries and allow a measure of energy performance to beassigned to a process against which others can be judged.

Depending on the nature of the project, savings are determined using engineering calcula-tions, or through metering and monitoring, utility meter billing analysis, or computer simula-tions.

Implementation Plan for Top Management

As a result of energy audit, many energy saving opportunities would emerge. These could beclassified broadly as measures with and without investment. House keeping measures and mod-erate cost measures need no intervention from top management. However, top managementneed to be appraised of these measures.

7. Project Management

154Bureau of Energy Efficiency

Page 204: General Aspect of Energy Management and Energy Audit

In case of projects where considerable investment are required, project manager has to rankthe list of projects based on the technical feasibility and financial analysis indicated in the pre-vious chapter (Simple payback, IRR, ROI etc.) and submit the same to the top management forappraisal and approval. This will help top management in allocating resources and other facili-ties.

Planning Budget

Budget requirement varies depending upon the duration and size of the project. For projectsinvolving long duration with multiple tasks and procurements, resources have to be allocatedjudiciously as and when required. Top management should ensure that this is done to ensuresuccessful completion of project.

Procurement Procedures

Having identified the material and equipment required for the project, the next step is to iden-tify the various vendors, provide specifications, invite quotations, and carryout discussions withselect vendors. For medium to high value items, tendering process can be adopted. Tenders haveto be evaluated for technical and financial aspects. It would be desirable to have purchase man-ager as part of energy efficiency team to facilitate smooth procurement process.

Construction

During the construction phase, plant may need to be shutdown. Careful planning is required, sothat the task is carried out without affecting the production. Project manager has to be aware ofthe annual maintenance schedule, holidays, annual maintenance or any major breakdown peri-od during which anyway plant will be shutdown. Construction activity should be carefullysupervised by energy and project manager so as to ensure quality and safety.

Measurement & Verification (M&V)

Facility energy savings are determined by comparing the energy use before and after the instal-lation of energy conservation measures. The "before" case is called the baseline; the "after" caseis referred to as the post-installation or performance period. Proper determination of savingsincludes adjusting for changes that affect energy use but that are not caused by the conservationmeasures. Such adjustments may account for differences in capacity utilization, raw materialquality, product mix and other parameters, between the baseline and performance periods.In general,

Savings = (Baseline Energy Use)adjusted - Post-Installation Energy Use

For example in a paper mill a variety of products depending on thickness (Grams per Squaremeter) are made. If energy consumption is evaluated as kCals or kWh per tonne of paper thefigures could be misleading. Under these circumstances the measurement and verification sys-tem is to be designed accounting for these variations.

Case Example

Replacing an existing boiler with an energy efficient boiler.

7. Project Management

155Bureau of Energy Efficiency

Page 205: General Aspect of Energy Management and Energy Audit

A. Gantt Chart

The Figure 7.5 shows a Gantt chart for a simple energy management project, i.e. Replacing anexisting boiler with an energy efficient boiler. As already mentioned, Gantt chart is the simplest and quickest method for formal planning.Gantt charts can be very useful in planning projects with a limited number of tasks and with fewinter-relationships. This chart typically depicts activities as horizontal lines whose lengthdepends on the time needed to complete the activities. These lines can be progressively over-printed to show how much of activity has been completed.

Drawing a Gantt chart requires information on:

• The logic of the tasks;• The duration of the tasks;• The resources available to complete the tasks.

7. Project Management

156Bureau of Energy Efficiency

Figure 7.5 A Simple Gantt Chart for Boiler Replacement

Page 206: General Aspect of Energy Management and Energy Audit

B. PERT / CPM Technique:

A PERT/CPM network for Boiler Replacement (Refer Figure 7.6)

Activity on Arrow: Activity and duration of the activity are shown in arrow.

10/10: In this Numerator denotes the Earliest Event Occurrence Time and Denominatoris the Latest Event Occurrence Time.

The Critical Path for this network is:

The events on the critical path have zero slack.

Dummy activity has no duration

The total duration for the completion of the project is 110 days based on the critical path.

7. Project Management

157Bureau of Energy Efficiency

Figure 7.6

Page 207: General Aspect of Energy Management and Energy Audit

7. Project Management

158Bureau of Energy Efficiency

REFERENCES

1. Principles of Project Management, NPC publication2. Project Management, Tata M cGraw Hill – S.Choudhury3. Projects: Planning, Analysis, Selection, Implementation and Review, Tata McGraw Hill

– S.Choudhury

QUESTIONS

1. List down various steps in project management.

2. Describe briefly any of the projects you have undertaken and how was the projectmanaged?

3. What are the criteria for screening of projects?

4. What are the aspects you would look for in the technical design of the project?

5. What are the ways in which financing can be enabled for an energy efficiency invest-ment?

6. What are the aspects to be considered in the management of contract?

7. Briefly explain the different types of contracts.

8. What are the hurdles faced in the implementation of a project?

9. Make a Gantt chart for your preparation of energy manager/energy auditor examina-tion. Split into to as many components as possible.

10. In project management PERT refers to

(a) Project Energy Rating Time (b) Projected Energy Rating Terms (c) PetroleumEnergy Revolutionary Technology (d) Program Evaluation and Review Technique.

11. Explain the importance of performance monitoring.

12. Explain the need for measurement and verification.

Page 208: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

Chapter 1.7 Project Management Part – I: Objective type questions and answers

1. Project financing is one of the step of project management- State True or False

2. Proposed new technologies, process modifications, equipment replacements are the elements of

a) Financing b) contracting c) technical design d) Implementation

3. The term ‘energy services contract’ in a project comes under

a) Financing b) contracting c) monitoring d) evaluation

4. The contractor providing financing and is paid an agreed fraction of actual savings as they are achieved is called

a) Traditional contract b) Extended financing terms

c) Shared savings performance contract d) energy service contract

5. The contract in which project specifications are provided to a contractor who procures and installs equipment at cost plus a mark-up or fixed price is called

a) Extended Financing terms b) guaranteed saving performance contract

c) shared saving performance contract d) Traditional contract

6. The technique used for scheduling the tasks and tracking of the progress of energy management projects is called

a) CPM b) Gantt chart

c) CUSUM d) PERT

7. CPM predicts the time required to complete the project— State True or False

8. The time between its earliest and latest start time, or between its earliest and latest finish time of an activity is

a) delay time b) slack time c) critical path d) start time

9. The path through the project network in which none of the activities have slack is called

a) start time b) slack time c) critical path d) delay time

10. CPM provides the following benefits

a) graphical view of the project

b) inter-relationship among various tasks

c) Predicts time required to complete the project

d) all the above

1.7 Project management - revised (table format) 50

Page 209: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

11. Which of the following statements about critical path analysis (CPA) is true?

a) The critical path is the longest path through the network

b) The critical path is the shortest path through the network

c) Tasks with float will never become critical

d) The network should remain constant throughout the project

12. Project management technique which uses three time estimates-optimistic, pessimistic and most likely, which help in establishing the probability of completing a project within a specified time and take calculated risk before commencing a project is---------.

(a) PERT (b) CUSUM (c) CPM (d) none of the above

13. The network model that allows for randomness in activity completion times is called

(a) CUSUM (b) CPM (c) PERT (d) Gantt chart

14. The technique which suggests corrective action to be taken in the light of actual performance is --------

(a) CUSUM (b) PERT (c) Performance monitoring (d) none of the above

15. Performance is done after implementation. State True or false

16. An effective way of communicating a projects benefit usually as a part of a performance measuring and reporting process is termed as.

(a) Performance indicator (b) CPM (c) PERT (d) Gantt chart

17. In project management system, Critical Path Method CPM) allows for randomness activity completion time deterministic method while Programme Evaluation Review Technique (PERT) uses fixed time estimate for each activity. State True or False.

18. In Critical Path of CPM used in project planning techniques indicates _____ .

a) time require for the completion of the project

b) delays in the project

c) early start and late end of the project

d) none of the above

19. Which of the following does not belongs to project planning technique?

a) CPM b) PERT

c) Gantt chart d) IRR (internal rate of return)

20. Formal project Close Out is necessary:

a) On medium to large projects only b) On all projects

c) Only if a project has been terminated early d) As part of Post Project Appraisal

Part – II: Short type questions and answers

1. Define the term ‘project’.

A project is a one-shot, time limited, goal directed, major undertaking requiring the commitment of varied skills and resources.

1.7 Project management - revised (table format) 51

Page 210: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

2. List various steps in project management.

The various steps in project management are:

a) Project definition and scope

b) Technical design

c) Financing

d) Contracting

e) Implementation

f) Performance monitoring

3. List the external source of funds during financing stage in project management.

External sources of funds include:

Bank loans

Leasing arrangement

Payment by savings ( a deal arranged with equipment supplier)

Energy services contract

Private finance initiatives

4. List the elements to be considered during technical design of a project management.

a) Proposed new technologies, process modifications, equipment replacement and other measures included in the project.

b) Product / technology / material supply chain (sourcing of vender from domestic or international with reliability of supply)

c) Commercial viability of the complete measures (IRR, NPV, etc.)

d) Special technical complexes (installation, maintenance, repair), associated skills required.

e) Preliminary designs, including schematics along with design requirements, manufacturer name and contact details and capital cost estimates.

f) Organisational and management plan for implementation including time table, personal requirements, staff training, project engineering and other logistical issues.

5. While screening the projects, list the criteria used to rank-order project opportunities.

a) Cost effectiveness of energy savings of complete package of measures (IRR, NPC, Cash flow, payback period)

b) Sustainability of savings over life of the equipment

c) Ease of quantification, monitoring and verifying electricity and fuel savings

d) Availability of technology and ease in adoptability to Indian condition.

e) Other environmental and social benefits (such as reduction in emissions and pollutants)

1.7 Project management - revised (table format) 52

Page 211: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

6. What are the different types of contracts involved in project management system.

Traditional contract

Extended technical guarantee/service

Extended financing terms

Guaranteed savings performance contract

Shared savings performance contract

7. Briefly explain guaranteed saving performance contract.

Guaranteed Saving Performance Contract is a contract, where all or part of savings is guaranteed by the contractor, and all or part of the costs of equipment and/or services is paid down out of savings as they are achieved.

8. Briefly explain shared saving performance contract.

Shared Savings Performance Contract is the contractor, which provides the financing and is paid an agreed fraction of actual savings as they are achieved. This payment is used to pay down the debt costs of equipment and/or services.

9. List guidelines used during implementation stage of projects?

Limit long lead times

Manage out-of-pocket development by focusing efforts

Manage project carefully

10. List the main points that are most important to a successful project

a) A project must meet customer requirements

b) A project must be under budget

c) A project must be on time

11. List the steps involved in CPM project planning?

Steps in CPM Project Planning

1. Specify the individual activities.

2. Determine the sequence/interrelationships of those activities.

3. Draw a network diagram.

4. Estimate the completion time for each activity.

5. Identify the critical path (longest path through the network)

6. Update the CPM diagram as the project progresses.

12. What are the benefits of CPM.

CPM provides the following benefits:

Provides a graphical view of the project.

Depicts the interrelationships among various tasks/activities

Predicts the time required to complete the project.

Shows which activities are critical to maintaining the schedule and which are not.

1.7 Project management - revised (table format) 53

Page 212: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

13. Define briefly PERT

The Program Evaluation and Review Technique (PERT) is a network model that allows for randomness in activity completion times. PERT uses three time estimates-optimistic, pessimistic and most likely, which help in establishing the probability of completing a project within a specified time and take calculated risk before commencing a project. It has the potential to reduce both the time and cost required to complete a project.

14. What are the different steps involved in PERT planning?

PERT planning involves the following steps:

1. Identify the specific activities and milestones.

2. Determine the interdependencies and proper sequence of the activities.

3. Construct a network diagram.

4. Estimate the time(three time estimates, if probabilities are to be computed) required for each activity.

5. Determine the critical path.

6. Update the PERT chart as the project progresses.

15. What are the benefits of PERT.

PERT is useful because it provides the following information:

• Expected project completion time.

• Probability of completion before a specified date.

• The critical path activities that directly impact the completion time.

• The activities that have slack time and that can lend resources to critical path activities.

• Activity starts and end dates.

16. How performance monitoring in project management is useful? List the benefits.

Once the project is completed performance review should be done periodically to compare actual performance with projected performance. A feedback device, it is useful in several ways:

a) It throws light on how realistic were the assumptions underlying the project

b) It provides a documented log of experience that is highly valuable in future decision making

c) It suggests corrective action to be taken in the light of actual performance

d) It helps in uncovering judgmental biases

e) It includes a desired caution among project sponsors.

17. List the project planning techniques used in project management.

Gantt chart, Critical path method (CPM), Programme evaluation review techniques (PERT).

1.7 Project management - revised (table format) 54

Page 213: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

18. What is slack time in critical path in CPM?

The slack time for an activity is the time between its earliest and latest start time, or between its earliest and latest finish time. Slack is the amount of time that an activity can be delayed past its earliest start or earliest finish without delaying the project.

19. List the internal source of funds during financing stage in project management.

Internal sources of fund include:

Direct cash provision from company reserves

From the revenue budget (if pay back period is very attractive and less than a year)

New share capital

20. Explain the need for measurement and verification in a project management system

Facility energy savings are determined by comparing the energy use before and after the installation of energy conservation measures. The “before” case is called the baseline; the “after” case is referred to as the post-installation or performance period. Proper determination of savings includes adjusting for changes that affect energy use but that are not caused by the conservation measures. Such adjustments may account for differences in capacity utilization, raw material quality, product mix and other parameters, between the baseline and performance periods.

In general,

Savings = (Baseline Energy use) adjusted –Post-installation Energy use

For example in a paper mill a variety of products depending on thickness (Grams per Square meter) are made. If energy consumption is evaluated as kCals or kWh per tonne of paper the figures could be misleading. Under these circumstances the measurement and verification system is to be designed accounting for these variations

Part – III Long type questions and answers

1. Briefly explain steps in project management.

a) Project definition and scope: The first step in project development cycle is to identify components of the project. Projects may be identified both internally and externally. Next screening of the projects is used to rank older project opportunities.

b) Technical design: Once project makes its part the screening process, the hard work of developing technical specification begins. For a project to be considered a viable investment, its proponent must present a sound technical feasibility.

c) Financing: The funding for a project is often outside the control of the project manager. However, it is important that one should understand the principles behind the provision of scarce funds. Project funds can be obtained from either internal or external sources.

d) Contracting: Substantial portion of a project is typically executed through contracts, the proper management of contracts is critical to the successful implementation of a project. If the project is to be implemented by an outside contractor several types of contracts may be used to undertake the installation and commissioning.

e) Implementation: Implementation stage involves the execution of project as agreed whilst carefully monitoring the progress and managing changes. On energy efficiency projects the main issues are technology selection risk, the overall risk sharing criteria is the installation contract, structure and relationship with sub-contractors and enforcing penalties among parties.

f) Project monitoring techniques: there are variety of basic planning and monitoring

1.7 Project management - revised (table format) 55

Page 214: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

techniques. All monitor progress and costs against resource budgets. Some of them are Gantt charts, CPM (critical path method), program evaluation and review techniques.

2. What are the several types of contracts used in project management and explain in brief?

Traditional Contract: All project specifications are provided to a contractor who procures and installs equipment at cost plus a mark-up or fixed price.

Extended Technical Guarantee/Service: The contract offers extended guarantees on the performance of selected equipment, and/or offers service/maintenance agreements.

Extended Financing Terms: The contractor provides the option of an extended lease or other financing vehicle in which the payment schedule can be based on the expected savings.

Guaranteed Saving Performance Contract: All or part of savings is guaranteed by the contractor, and all or part of the costs of equipment and/or services is paid down out of savings as they are achieved.

Shared Savings Performance Contract: The contractor provides the financing and is paid an agreed fraction of actual savings as they are achieved. This payment is used to pay down the debt costs of equipment and/or services.

3. How critical path can be identified in CPM?

The critical path can be identified by determining the following four parameters for each of the activity:

• ES - earliest start time: the earliest time at which the activity can start given that its precedent activities must be completed first.

• EF - earliest finish time, equal to the earliest start time for the activity plus the time required to complete the activity.

• LF - latest finish time: the latest time at which the activity can be completed without delaying the project.

• LS - latest start time, equal to the latest finish time minus the time required to complete the activity.

The slack time for an activity is the time between its earliest and latest start time, or between its earliest and latest finish time. Slack is the amount of time that an activity can be delayed past its earliest start or earliest finish without delaying the project. The critical path is the path through the project network in which none of the activities have slack, that is, the path for which ES=LS and EF=LF for all activities in the path.

4. What is CPM and list the steps in CPM project planning?

CPM models the activities and events of a project as a network. Activities are depicted as nodes on the network and events that signify the beginning or ending of activities are depicted as arcs or lines between the nodes. The following is an example of a CPM network diagram.

1.7 Project management - revised (table format) 56

Page 215: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

Steps in CPM Project Planning

1. Specify the individual activities.

2. Determine the sequence/interrelationships of those activities.

3. Draw a network diagram.

4. Estimate the completion time for each activity.

5. Identify the critical path (longest path through the network)

6. Update the CPM diagram as the project progresses.

5. Explain and draw a typical Gantt chart

Gantt chart (named after the inventor) or bar charts are used to scheduling the tasks and tracking of the process of energy management projects. Gantt scheduling tool takes the form of a horizontal bar graph on a time schedule.

Task Duration 1 week

2 week

3 week

4 week

5 week

6 week

7 week

1. Preliminary audit and report 1 week 2. Identification of external consultants and obtaining the proposals

2 weeks

3. Selection of auditor and awarding contract

1 week

4. Detailed energy audit , field study & report preparation

4 weeks

The horizontal axis of the Gantt chart is a time scale either in absolute time or in relative time. Rows of bars in the chart show the beginning and ending dates of individual tasks in the project. In some cases bars/activities may overlap, where several activities can be performed in parallel. In such cases Gantt chart is quite useful for communicating the timings of the various tasks.

For larger projects, the tasks can be broken into sub tasks having their own Gantt charts to maintain readability and provide easy monitoring.

1.7 Project management - revised (table format) 57

Page 216: General Aspect of Energy Management and Energy Audit

8. ENERGY MONITORING AND TARGETING

159Bureau of Energy Efficiency

SyllabusEnergy Monitoring and Targeting: Defining monitoring & targeting, Elements of mon-itoring & targeting, Data and information-analysis, Techniques -energy consumption,Production, Cumulative sum of differences (CUSUM).

8.1 Definition

Energy monitoring and targeting is primarily a management technique that uses energy infor-mation as a basis to eliminate waste, reduce and control current level of energy use and improvethe existing operating procedures. It builds on the principle "you can't manage what youdon't measure". It essentially combines the principles of energy use and statistics.

While, monitoring is essentially aimed at establishing the existing pattern of energy con-sumption, targeting is the identification of energy consumption level which is desirable as amanagement goal to work towards energy conservation.

Monitoring and Targeting is a management technique in which all plant and building utili-ties such as fuel, steam, refrigeration, compressed air, water, effluent, and electricity are man-aged as controllable resources in the same way that raw materials, finished product inventory,building occupancy, personnel and capital are managed. It involves a systematic, disciplineddivision of the facility into Energy Cost Centers. The utilities used in each centre are closelymonitored, and the energy used is compared with production volume or any other suitable mea-sure of operation. Once this information is available on a regular basis, targets can be set, vari-ances can be spotted and interpreted, and remedial actions can be taken and implemented.

The Monitoring and Targeting programs have been so effective that they show typicalreductions in annual energy costs in various industrial sectors between 5 and 20%.

8.2 Elements of Monitoring & Targeting System

The essential elements of M&T system are:• Recording -Measuring and recording energy consumption• Analysing -Correlating energy consumption to a measured output, such as production

quantity• Comparing -Comparing energy consumption to an appropriate standard or benchmark• Setting Targets -Setting targets to reduce or control energy consumption• Monitoring -Comparing energy consumption to the set target on a regular basis• Reporting -Reporting the results including any variances from the targets which have

been set• Controlling -Implementing management measures to correct any variances, which may

have occurred.Particularly M&T system will involve the following:

• Checking the accuracy of energy invoices• Allocating energy costs to specific departments (Energy Accounting Centres)

Page 217: General Aspect of Energy Management and Energy Audit

• Determining energy performance/efficiency• Recording energy use, so that projects intended to improve energy efficiency can be

checked• Highlighting performance problems in equipment or systems

8.3 A Rationale for Monitoring, Targeting and Reporting

The energy used by any business varies with production processes, volumes and input.Determining the relationship of energy use to key performance indicators will allow you todetermine:

• Whether your current energy is better or worse than before• Trends in energy consumption that reflects seasonal, weekly, and other operational para-

meters• How much your future energy use is likely to vary if you change aspects of your busi-

ness• Specific areas of wasted energy• Comparison with other business with similar characteristics - This "benchmarking"

process will provide valuable indications of effectiveness of your operations as well asenergy use

• How much your business has reacted to changes in the past• How to develop performance targets for an energy management program

Information related to energy use may be obtained from following sources:

• Plant level information can be derived from financial accounting systems-utilities costcentre

• Plant department level information can be found in comparative energy consumptiondata for a group of similar facilities, service entrance meter readings etc.

• System level (for example, boiler plant) performance data can be determined from sub-metering data

• Equipment level information can be obtained from nameplate data, run-time and sched-ule information, sub-metered data on specific energy consuming equipment.

The important point to be made here is that all of these data are useful and can be processed toyield information about facility performance.

8.4 Data and Information Analysis

Electricity bills and other fuel bills should be collected periodically and analysed as below. Atypical format for monitoring plant level information is given below in the Table 8.1.

8. Energy Monitoring and Targeting

160Bureau of Energy Efficiency

Page 218: General Aspect of Energy Management and Energy Audit

8. Energy Monitoring and Targeting

161Bureau of Energy Efficiency

TABLE 8.1 ANNUAL ENERGY COST SHEET

Thermal Energy Bill Electricity Bill TotalEnergy Bill

Month Fuel 1 Fuel 2 Fuel 3 Total Day Night Maximum Total Rs.LakhRs. Lakh kWh kWh Demand Rs. Lakh

1

2

3

4

5

6

7

8

9

10

11

12

Sub-Total

%

Pie Chart on Energy Consumption

All the fuels purchased by the plant should be converted into common units such as kCal. Thefollowing Table 8.2 below is for that purpose.

Figure 8.1 % Share of Fuels Based on Energy Bill

After obtaining the respective annual energy cost, a pie chart (see Figure 8.1) can be drawn asshown below:

Page 219: General Aspect of Energy Management and Energy Audit

After conversion to a common unit, a pie chart can be drawn showing the percentage dis-tribution of energy consumption as shown in Figure 8.2.

8.5 Relating Energy Consumption and Production.

Graphing the Data

A critical feature of M&T is to understand what drives energy consumption. Is it production,hours of operation or weather? Knowing this, we can then start to analyse the data to see howgood our energy management is.

After collection of energy consumption, energy cost and production data, the next stage ofthe monitoring process is to study and analyse the data to understand what is happening in theplant. It is strongly recommended that the data be presented graphically. A better appreciationof variations is almost always obtained from a visual presentation, rather than from a table ofnumbers. Graphs generally provide an effective means of developing the energy-productionrelationships, which explain what is going on in the plant.

Use of Bar Chart

The energy data is then entered into a spreadsheet. It is hard to envisage what is happening fromplain data, so we need to present the data using bar chart. The starting point is to collect andcollate 24/12 months of energy bills. The most common bar chart application used in energy

8. Energy Monitoring and Targeting

162Bureau of Energy Efficiency

TABLE 8.2 FUEL CONVERSION DATA

Energy source Supply unit Conversion Factor to Kcal

Electricity kWh 860

HSD kg 10,500

Furnace Oil kg 10,200

LPG kg 12,000

Figure 8.2 %Share of Fuels Based on Consumption in kCals

Page 220: General Aspect of Energy Management and Energy Audit

8. Energy Monitoring and Targeting

163Bureau of Energy Efficiency

management is one showing the energy per month for this year and last year (see Figure 8.3) -however, it does not tell us the full story about what is happening. We will also need produc-tion data for the same 24/12-month period.

Having more than twelve months of production and energy data, we can plot a moving

annual total. For this chart, each point represents the sum of the previous twelve months ofdata. In this way, each point covers a full range of the seasons, holidays, etc. The Figure 8.4shows a moving annual total for energy and production data.

This technique also smoothens out errors in the timing of meter readings. If we just plotenergy we are only seeing part of the story - so we plot both energy and production on the samechart - most likely using two y-axes. Looking at these charts, both energy and productions seemto be "tracking" each other - this suggests there is no major cause for concern. But we will needto watch for a deviation of the energy line to pick up early warning of waste or to confirm

Figure 8.3 Energy Consumption :Current Year(2000) Vs. Previous year(1999)

Figure 8.4 Moving Annual Total - Energy and Production

Prod

uctio

n

Ene

rgy

Page 221: General Aspect of Energy Management and Energy Audit

8. Energy Monitoring and Targeting

164Bureau of Energy Efficiency

whether energy efficiency measures are making an impact.For any company, we also know that energy should directly relate to production. Knowing

this, we can calculate Specific Energy Consumption (SEC), which is energy consumption perunit of production. So we now plot a chart of SEC (see Figure 8.5).

At this point it is worth noting that the quality of your M&T system will only be as good as thequality of your data - both energy and production. The chart shows some variation - an all timelow in December 99 followed by a rising trend in SEC.

We also know that the level of production may have an effect on the specific consumption.If we add the production data to the SEC chart, it helps to explain some of the features. Forexample, the very low SEC occurred when there was a record level of production. This indi-cates that there might be fixed energy consumption - i.e. consumption that occurs regardless ofproduction levels. Refer Figure 8.6.

Figure 8.5: Monthly Specific Energy Consumption

Figure 8.6 SEC With Production

SEC

PRODUCTION

SEC

Page 222: General Aspect of Energy Management and Energy Audit

8. Energy Monitoring and Targeting

165Bureau of Energy Efficiency

The next step is to gain more understanding of the relationship of energy and production, andto provide us with some basis for performance measurement. To do this we plot energy againstproduction - In Microsoft Excel Worksheet, this is an XY chart option. We then add a trend lineto the data set on the chart. (In practice what we have done is carried out a single variableregression analysis!). The Figure 8.7 shown is based on the data for 1999.

We can use it to derive a "standard" for the up-coming year's consumption. This chart shows alow degree of scatter indicative of a good fit. We need not worry if our data fit is not good. Ifdata fit is poor, but we know there should be a relationship, it indicates a poor level of controland hence a potential for energy savings.

In producing the production/energy relationship chart we have also obtained a relationshiprelating production and energy consumption.

Energy consumed for the period = C + M x Production for same period

Where M is the energy consumption directly related to production (variable) and C is the"fixed" energy consumption (i.e. energy consumed for lighting, heating/cooling and generalancillary services that are not affected by production levels). Using this, we can calculate theexpected or "standard" energy consumption for any level of production within the range of thedata set.

We now have the basis for implementing a factory level M&T system. We can predict stan-dard consumption, and also set targets - for example, standard less 5%. A more sophisticatedapproach might be applying different reductions to the fixed and variable energy consumption.Although, the above approach is at factory level, the same can be extended to individualprocesses as well with sub metering.

At a simplistic level we could use the chart above and plot each new month's point to seewhere it lies. Above the line is the regime of poor energy efficiency, and below the line is theregime of an improved one.

Figure 8.7: Energy vs Production

Page 223: General Aspect of Energy Management and Energy Audit

8.6 CUSUM

Cumulative Sum (CUSUM) represents the difference between the base line (expected or stan-dard consumption) and the actual consumption points over the base line period of time.This useful technique not only provides a trend line, it also calculates savings/losses to date andshows when the performance changes.

A typical CUSUM graph follows a trend and shows the random fluctuation of energy con-sumption and should oscillate around zero (standard or expected consumption). This trend willcontinue until something happens to alter the pattern of consumption such as the effect of anenergy saving measure or, conversely, a worsening in energy efficiency (poor control, house-keeping or maintenance).

CUSUM chart (see Figure 8.8) for a generic company is shown. The CUSUM chart shows whatis really happening to the energy performance. The formula derived from the 1999 data wasused to calculate the expected or standard energy consumption.

From the chart, it can be seen that starting from year 2000, performance is better than stan-dard. Performance then declined (line going up) until April, and then it started to improve untilJuly. However, from July onwards, there is a marked, ongoing decline in performance - linegoing up.

When looking at CUSUM chart, the changes in direction of the line indicate events thathave relevance to the energy consumption pattern. Clearly, site knowledge is needed to inter-pret better what they are. For this sample company since we know that there were no plannedchanges in the energy system, the change in performance can be attributed to poor control,housekeeping or maintenance.

8. Energy Monitoring and Targeting

166Bureau of Energy Efficiency

Figure 8.8 CUSUM Chart

Page 224: General Aspect of Energy Management and Energy Audit

8. Energy Monitoring and Targeting

167Bureau of Energy Efficiency

The CUSUM Technique

Energy consumption and production data were collected for a plant over a period of 18 months.During month 9, a heat recovery system was installed. Using the plant monthly data, estimatethe savings made with the heat recovery system. The plant data is given in Table 8.3:

Steps for CUSUM analysis

1. Plot the Energy - Production graph for the first 9 months2. Draw the best fit straight line3. Derive the equation of the line

The above steps are completed in Figure 8.9, the equation derived is E = 0.4 P + 180

8.7 Case Study

TABLE 8.3 MONTH WISE PRODUCTION WITH ENERGY CONSUMPTION

Month Eact - Monthly Energy Use P - Monthly Production( toe * / month) ( tonnes / month)

1 340 380

2 340 440

3 380 460

4 380 520

5 300 320

6 400 520

7 280 240

8 424 620

9 420 600

10 400 560

11 360 440

12 320 360

13 340 420

14 372 480

15 380 540

16 280 280

17 280 260

18 380 500

* toe = tonnes of oil equivalent.

Page 225: General Aspect of Energy Management and Energy Audit

8. Energy Monitoring and Targeting

168Bureau of Energy Efficiency

TABLE 8.4 CUSUM

Month Eact P Ecalc Eact – Ecalc CUSUM(0.4 P + 180) (Cumulative Sum)

1 340 380 332 +8 +8

2 340 440 356 -16 -8

3 380 460 364 +16 +8

4 380 520 388 -8 0

5 300 320 308 -8 -8

6 400 520 388 +2 -6

7 280 240 276 +4 -2

8 424 620 428 -4 -6

9 420 600 420 0 -6

10 400 560 404 4 -10

11 360 440 356 +4 -6

12 320 360 324 -4 -10

13 340 420 348 -8 -18

14 372 480 372 0 -18

15 380 540 396 -16 -34

16 280 280 292 -12 -46

17 280 260 284 -4 -50

18 380 500 380 0 -50

Eact- Actual Energy consumption Ecalc - Calculated energy consumption

4. Calculate the expected energy consumption based on the equation5. Calculate the difference between actual and calculated energy use 6. Compute CUSUM

These steps are shown in the Table 8.4.

7. Plot the CUSUM graph8. Estimate the savings accumulated from use of the heat recovery system.

From the Figure 8.10, it can be seen that the CUSUM graph oscillates around the zero line forseveral months and then drops sharply after month 11. This suggests that the heat recovery sys-tem took almost two months to commission and reach proper operating conditions, after whichsteady savings have been achieved. Based on the graph 8.10 (see Table 8.4), savings of 44 toe(50-6) have been accumulated in the last 7 months. This represents savings of almost 2% ofenergy consumption.

442352

100 1 8# . %· =

Page 226: General Aspect of Energy Management and Energy Audit

#Eact for the last 7 months (from month 12 to month 18 in Table 8.4)

CUSUM chart for last 18 months is shown in Figure 8.10.The CUSUM technique is a simple but remarkably powerful statistical method, which high-

lights small differences in energy efficiency performances. Regular use of the procedure allowsthe Energy Manager to follow plant performance and spot any trends early.

8. Energy Monitoring and Targeting

169Bureau of Energy Efficiency

Figure 8.9 Energy Production Graph

Figure 8.10 Example CUSUM Graph

Page 227: General Aspect of Energy Management and Energy Audit

8. Energy Monitoring and Targeting

170Bureau of Energy Efficiency

QUESTIONS

1. What is the difference between monitoring and targeting?

2. Explain briefly the essential elements of a monitoring and targeting system.

3. What are the benefits of a monitoring and targeting system?

4. What do you understand by the term "benchmarking" and list few benefits?

5. Explain the difference between internal and external benchmarking.

6. Explain how a CUSUM chart is drawn with an example.

7. Narrate the type of energy monitoring and targeting systems in your industry.

REFERENCES1. Energy conservation – The Indian experience, Department of Power & NPC Publication2. Energy Audit Reports of National Productivity Council3. Cleaner Production – Energy Efficiency Manual prepared for GERIAP, UNEP,

BANGKOK by National Productivity Council

Page 228: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

Chapter 1.8 Energy Monitoring and Targeting Part – I: Objective type Questions and answers

1. Energy monitoring and targeting is built on the principle of “ _____”.

a) “production can be reduced to achieve reduced energy consumption”

b) “Consumption of energy is proportional to production rate”

c) “You cannot manage what you do not measure”

d) None of the above.

2. One of the following is not the element of energy monitoring & targeting system

a) Recording the energy consumption b) comparing the energy consumption

C) Controlling the energy consumption d) Reducing the production

3. Which of the variable does not contribute to energy consumption?

a) Production b) Hours c) Climate d) none of the above

4. Poor scattering on trend line of production Vs Energy consumption indicates ___.

a) poor level of control b) good level of control

c) both the above d) none of above.

5. Level of production may have an effect on specific energy consumption. State True or False

6. M & T involves a systematic, disciplines division of the facility in to energy cost centres. State True or False?

7. The empirical relationship used to plot production Vs Energy consumption is (Y= energy consumed for the period; C = fixed energy consumption; M = energy consumption directly related to production; X= production for same period).

a) X=Y+MC b) Y=Mx+C c) M=Cx+Y d) None of above

8. The energy used by any business varies with production process, volumes and input – State True or False.

9. 1 kg LPG = _____ kcal.

a) 12,000 kcal b) 8000 kCal c) 6000 kCal d) 4000 kCal

10. The energy used by any manufacturing process varies with

a) production volume b) type of process

c) resource input d) All the above

11. The best way of correlating production and energy data in any plant is…..

a) Text format b) Graphical representation

c) Oral communication d) None

1.8 energy monitoring and targeting -revised (table format) 58

Page 229: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

12. For any company, energy consumption mostly relates to……..

a) Profits b) Inventory c) Production d) All the above

13. What is CUSUM?

a) Cumbersome b) Cumulative Sum c) Calculated Sum d) None

14. A CUSUM graph follows a random fluctuation trend and oscillates around.

a) 100 b) 100% c) 0 d) none of the above

15. To draw a CUSUM chart following data is required

a) Monthly energy consumption& monthly production

b) Monthly specific energy consumption and turn over

c) Monthly profits and production

d) None

16. What is specific energy consumption?

a) energy consumption per month b) Energy consumed per unit of production

c) energy consumption per year d) none of the above

Data required to plot a moving annual total is ____. 17.

a) production b) energy

c) both the above d) none the above

Energy and production data is useful to calculate…… 18.

a) Specific Energy Consumption b) Specific Fuel consumption

c) Specific Cost d) None

What type of data is useful to find out the fixed energy consumption? 19.

a) SEC Vs production b) SEC Vs Energy

c) Production Vs energy d) None

What do you mean by “toe” 20.

a) Total oil equivalent b) Tons of effluent

c) Tons of oil equivalent d) none of the above

1.8 energy monitoring and targeting -revised (table format) 59

Page 230: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

Part – II: Short type Questions and answers

1. Define ‘Energy Monitoring and targeting’?

Energy monitoring and targeting is primarily a management technique that uses energy information as a basis to eliminate waste, reduce and control current level of energy use and improve the existing operating procedures. It builds on the principle “you can’t manage what you don’t measure”. It essentially combines the principles of energy use and statistics.

Monitoring is essentially aimed at preserving an established pattern. Targeting is the identification of energy consumption level, which is desirable as a management objective to work towards energy conservation

2. Briefly list Benefits that arise from an effective M&T system

Ans.

• Enhanced energy performance leading to increased profits.

• Allocation of energy costs to individual account centres.

• Improved operational and investment decision making and subsequent analysis.

• Enhanced control of operating practices which can lead to increased product quality and reduced product loss.

• Improved calculation of energy costs for projected levels of production.

• Improved identification of maintenance requirements.

3. List down the essential elements of monitoring and targeting System?

Ans.

The essential elements of an M&T system are:

• Recording • Analyzing • Comparing • Setting Targets • Monitoring • Reporting • Controlling

4. Plot electricity consumption Vs production for the months given in table below and explain trend of Specific Energy Consumption (SEC).

Month kWh Consumption

kVAh consumption

Production-MT

kVA demand

April 4,85,000 5,30,000 565 1285

May 4,30,000 4,80,000 498 1000

June 4,48,000 4,90,000 501 960

July 4,80,000 5,30,000 550 1300

1.8 energy monitoring and targeting -revised (table format) 60

Page 231: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

Ans

Energy vs. Production

420000

430000

440000

450000

460000

470000

480000

490000

480 500 520 540 560 580

Production

Eenr

gy, k

Wh

The SEC is varying in the range of 858 to 894 kWh/MT. The SEC has shown a reduction in trend with higher production during April 2004.

Month kWh Consumption

Production-MT

SEC(kWh/MT)

April 4,85,000 565 858.4

May 4,30,000 498 863.5

June 4,48,000 501 894.2

July 4,80,000 55 0 872.7

5. What are the steps involved in CUSUM analysis?

1. Plot the Energy – Production graph

2. Draw the best fit straight line

3. Derive the equation of the line

4. Calculate the expected energy consumption based on the equation

5. Calculate the difference between calculated and actual energy use

6. Compute CUSUM

7. Plot the CUSUM graph

8. Estimate the savings

6. What is the significance of calculating specific energy consumption?

The energy should directly relate production and in-turn deriving specific energy consumption (also known as SEC). This can also be represented by graphical method for easy comparison of variation in SEC to gain more understanding on this issue.

1.8 energy monitoring and targeting -revised (table format) 61

Page 232: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

7. What is advantage of presenting plant data in graphical form?

Graphs generally provide an effective means of developing the energy-production relationships, which explain what is going on in the plant. The main advantage being quick understanding of the energy consumption scenario.

8. What is the benefit of using moving average total technique when plotting a monthly energy and production data?

This technique is useful for drawing the trend over a period of time. It also smoothes out errors in the timing of meter readings & also covers a full range of seasons, holidays etc.

9. Write a formula relating production and energy consumption.

Energy consumed for the period = M x production for same period + C

Where M is the energy consumption directly related to production and C is the ‘fixed’ energy consumption.

10. Why CUSUM technique is most useful?

CUSUM technique is a simple but remarkably powerful statistical method which highlights small differences in energy efficiency performances. Regular use of the procedure allows energy manger to follow his plant performance and to spot any trends at an early date.

11. Name the various sources in the plant from where information related to energy use data can be obtained?

• Plant level information can be derived from financial accounting Systems—the utilities cost centre

• Plant Department level information can be found in comparative energy consumption data for a group of similar facilities, service entrance meter readings etc.

• System level (for example, boiler plant) performance data can be determined from sub-metering data

• Equipment level information can be obtained from nameplate data, run-time and schedule information, sub-metered data on specific energy consuming equipment.

12. What do you understand by CUSUM?

CUSUM represents the difference between the base line (expected or “standard” consumption) and the actual consumption data points over the base line period of time. A CUSUM graph therefore follows a trend, which represents the random fluctuations of energy consumption and should oscillate about zero. This trend will continue until something happens to alter the pattern of consumption such as the effect of an energy saving measure or, conversely, a worsening in energy efficiency (poor control, housekeeping or maintenance).

13. Name the plant utility systems that require Monitoring and Targeting?

Plant and building utilities such as fuel, steam, refrigeration, compressed air, water, effluent, and electricity are areas which require Monitoring and Targeting.

14. What is the primary aim of “energy monitoring’ in the plant?

Monitoring is essentially aimed at establishing the existing pattern of energy consumption, targeting is the identification of energy consumption level which is desirable as a management goal to work towards energy conservation.

1.8 energy monitoring and targeting -revised (table format) 62

Page 233: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

15. How the savings can be achieved with the help of Monitoring & targeting?

The savings can be achieved in the following three ways:

o Reduction in energy usage, by eliminating energy wastages

o Changes in usage patterns by controlling maximum demand and consuming energy at different times of the day (when the cost is lower)

o Improved monitoring of energy expenditure, which ensures that you pay the correct amount based on how much energy the site uses.

16. What is the conversion factor to convert 1 kg of HSD, furnace oil and LPG into kcal?

1 kg HSD = 10500 kcal

1 kg Furnace oil = 10200 kcal

1 kg LPG = 12000 kcal

17. What are the advantages of plotting a moving annual total to relate energy consumption and production in a plant?

Having more than twelve months of production and energy data, it is possible to plot a moving annual total. For this chart, each point represents the sum of the previous twelve months of data. In this way, each point covers a full range of the seasons, holidays, etc. This technique also smoothens out errors in the timing of meter readings. It also tells the deviation of the energy line to pick up early warning of waste or to confirm whether energy efficiency measures are making an impact.

18. What are the advantages of adding production data to the specific energy consumption chart?

The level of production may have an effect on the specific consumption. If the production data is added to the SEC chart, it helps to explain some of the features. For example, the very low SEC occurred when there was a record level of production. This indicates that there might be fixed energy consumption – i.e. consumption that occurs regardless of production levels.

19. How do we better envisage the plain energy data of a plant entered in spread sheet form?

It is hard to envisage from the plain energy data entered in the spread sheet, so there is a need to present the data using bar chart. The starting point is to collect and collate 24/12 months of energy bills. The most common bar chart application used in energy management is one showing the energy per month for this year and last year. However, it does not tell the full story about what is happening. One will also need production data for the same 24/12-month period.

20. What are the advantages of benchmarking process parameters in a plant?

Benchmarking process parameters will provide valuable indications of effectiveness of plant operation as well as energy use.

1.8 energy monitoring and targeting -revised (table format) 63

Page 234: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

Part – III: Long type Questions and Answers

1. How does it help one for the determination of the relationship of energy use to key performance indicators in the plant?

Determining the relationship of energy use to key performance indicators will allow you to determine:

• Whether your current energy is better or worse than before

• Trends in energy consumption that reflects seasonal, weekly, and other operational parameters

• How much your future energy use is likely to vary if you change aspects of your business

• Specific areas of wasted energy

• Comparison with other business with similar characteristics - This “benchmarking” process will provide valuable indications of effectiveness of your operations as well as energy use

• How much your business has reacted to changes in the past

• How to develop performance targets for an energy management program

2. Use CUSUM technique and calculate energy savings for 6 months period of 2003. For calculating total energy savings, average production can be taken as 4000MT/Month. Refer data given in table below.

2003-Month

Actual –SEC, kWh/MT

Predicted SEC-kWh/MT

Jan 242 265

Feb 238 265

Mar 287 265

Apr 237 265

May 295 265

Jun 246 265

It may also be noted that energy saving measures were implemented prior to Jan-2003. It may also be noted that retrofits were not functioning during March & May 2003.

The table above gives values of Specific energy consumption monitored Vs predicted for each month. The variations are calculated and the Cumulative sum of differences is calculated from Jan-June-2003.

2003-Month

Actual -SEC,

kWh/MT

Predicted SEC-

kWh/MT Difference=

Actual-Predicted CUSUM

Jan 242 265 - 23 -23

Feb 238 265 - 27 -50

Mar 287 265 + 22 -28

Apr 237 265 - 28 -56

May 295 265 + 30 -26

Jun 246 265 - 19 -45

= 47 kWh/MT x 4000 MT x 6 months

Energy Savings for six months = 10.80 lakh kWh

1.8 energy monitoring and targeting -revised (table format) 64

Page 235: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

3. Write Ten key steps in “ Monitoring and targeting” that you will undertake as an energy manager in your plant .

As an energy manager following are the steps I prefer to undertake in my plant.

M&T is a comprehensive approach to utility management and efficiency through ongoing monitoring and target setting.

Ten Key Steps

1. Conduct Scoping Study to understand the major consumption areas.

2. Get Senior Management approval

3. Improve Metering

4. Configure Software

5. Measure Utility Consumption and Production Variables

6. Develop Targets

7. Develop Opportunities Database

8. Conduct Energy Team Meetings

9. Actions

10. Training for Culture Shift

4. What are the various ways to relate the plant’s energy consumption with production?

A critical feature of M&T is understanding the parameter that drives energy consumption, like production, hours of operation, weather, etc. Knowing this one can then start to analyze the data to see how well is energy management.

After collection of energy consumption, energy cost and production data, the next stage of the monitoring process is to study and analyze the data to understand what is happening in the plant. It is strongly recommended that the data be presented graphically. A better appreciation of variations is almost always obtained from a visual presentation, rather than from a table of numbers. Graphs generally provide an effective means of developing the energy-production relationships, which explain what is going on in the plant.

The energy data is then entered into a spreadsheet. It is hard to envisage what is happening from plain data, so you need to produce bar chart.

The starting point is to collect and collate 24/12 months of energy bills. You will also need production data for the same 24/12-month period.

Probably the most common bar chart application used in energy management is one showing the energy per month for this year and last year.– however, it does not tell us a lot about what is happening.

Having more than twelve months of data one can plot a moving annual total. For this chart, each point represents the sum of the previous twelve months of data. In this way each point has a full range of the seasons, holidays, etc. This technique also smoothes out errors in the timing of meter readings. If we just plot energy we are only seeing part of the story – so we plot both energy and production on the same chart – most likely using two y-axes. Looking

1.8 energy monitoring and targeting -revised (table format) 65

Page 236: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

at this chart both energy and production seem to be “tracking” each other – this suggests there is no major cause for concern. But one need to watch for a deviation of the energy line to pick up early warning of waste or to confirm that energy efficiency measures are making an effect.

5. Briefly explain the essential elements of monitoring and targeting System?

The essential elements of a M&T system are:

• Recording -Measuring and recording energy consumption

• Analyzing -Correlating energy consumption to a measured output, such as production quantity

• Comparing -Comparing energy consumption to an appropriate standard or benchmark

• Setting Targets -Setting targets to reduce or control energy consumption

• Monitoring -Comparing energy consumption to the set target on a regular basis

• Reporting -Reporting the results including any variances from the targets which have been set

• Controlling -Implementing management measures to correct any variances which may have occurred.

1.8 energy monitoring and targeting -revised (table format) 66

Page 237: General Aspect of Energy Management and Energy Audit

9. GLOBAL ENVIRONMENTAL CONCERNS

171Bureau of Energy Efficiency

SyllabusGlobal Environmental Concerns: United Nations Framework Convention on ClimateChange (UNFCC), Kyoto Protocol, Conference of Parties (COP), Clean DevelopmentMechanism (CDM), Prototype Carbon Fund (PCF), Sustainable Development,

9.1 Global Environmental Issues

As early as 1896, the Swedish scientist Svante Arrhenius had predicted that human activitieswould interfere with the way the sun interacts with the earth, resulting in global warming andclimate change. His prediction has become true and climate change is now disrupting globalenvironmental stability. The last few decades have seen many treaties, conventions, and proto-cols for the cause of global environmental protection.Few examples of environmental issues of global significance are:

• Ozone layer depletion• Global warming• Loss of biodiversityOne of the most important characteris-

tics of this environmental degradation is thatit affects all mankind on a global scale with-out regard to any particular country, region,or race. The whole world is a stakeholderand this raises issues on who should do whatto combat environmental degradation.

9.2 Ozone Layer Depletion

Earth's atmosphere is divided into threeregions, namely troposphere, stratosphereand mesosphere (see Figure 9.1). Thestratosphere extends from 10 to 50 kms fromthe Earth's surface. This region is concen-trated with slightly pungent smelling, lightbluish ozone gas. The ozone gas is made upof molecules each containing three atoms ofoxygen; its chemical formula is O3. Theozone layer, in the stratosphere acts as anefficient filter for harmful solar Ultraviolet B(UV-B) rays

Ozone is produced and destroyed natu-rally in the atmosphere and until recently,this resulted in a well-balanced equilibrium

Figure 9.1: Ozone Layer

Page 238: General Aspect of Energy Management and Energy Audit

(see Figure 9.2). Ozone is formedwhen oxygen molecules absorb ultra-violet radiation with wavelengths lessthan 240 nanometres and is destroyedwhen it absorbs ultraviolet radiationwith wavelengths greater than 290nanometres. In recent years, scientistshave measured a seasonal thinning ofthe ozone layer primarily at the SouthPole. This phenomenon is being calledthe ozone hole.

9.2.1 Ozone Depletion Process

Ozone is highly reactive and easily broken down by man-made chlorine and bromine com-pounds. These compounds are found to be most responsible for most of ozone layer depletion.

The ozone depletion process begins when CFCs (used in refrigerator and air conditioners)and other ozone-depleting substances (ODS) are emitted into the atmosphere. Winds efficient-ly mix and evenly distribute the ODS in the troposphere. These ODS compounds do not dis-solve in rain, are extremely stable, and have a long life span. After several years, they reach thestratosphere by diffusion.

Strong UV light breaks apart the ODS molecules. CFCs, HCFCs, carbon tetrachloride,methyl chloroform release chlorine atoms, and halons and methyl bromide release bromineatoms. It is the chlorine and bromine atom that actually destroys ozone, not the intact ODS mol-ecule. It is estimated that one chlorine atom can destroy from 10,000 to 100,000 ozone mole-cules before it is finally removed from the stratosphere.

Chemistry of Ozone Depletion

When ultraviolet light waves (UV) strike CFC* (CFCl3) molecules in the upper atmosphere, acarbon-chlorine bond breaks, producing a chlorine (Cl) atom. The chlorine atom then reactswith an ozone (O3) molecule breaking it apart and so destroying the ozone. This forms an ordi-nary oxygen molecule (O2) and a chlorine monoxide (ClO) molecule. Then a free oxygen**atom breaks up the chlorine monoxide. The chlorine is free to repeat the process of destroyingmore ozone molecules. A single CFC molecule can destroy 100,000 ozone molecules. Thechemistry of ozone depletion process is shown in Figure 9.3.

* CFC - chlorofluorocarbon: it contains chlorine, fluorine and carbon atoms.** UV radiation breaks oxygen molecules (O2) into single oxygen atoms.

9. Global Environmental Concerns

172Bureau of Energy Efficiency

Figure 9.2 Ozone Production and Destruction Process

Page 239: General Aspect of Energy Management and Energy Audit

9. Global Environmental Concerns

173Bureau of Energy Efficiency

Chemical equation isCFCl3 + UV Light ==> CFCl2 + Cl

Cl + O3 ==> ClO + O2

ClO + O ==> Cl + O2

The free chlorine atom is then free to attack another ozone molecule

Cl + O3 ==> ClO + O2

ClO + O ==> Cl + O2

and again ...

Cl + O3 ==> ClO + O2

ClO + O ==> Cl + O2

and again... for thousands of times.Scientist measure ozone layer thickness by measuring how much ultraviolet radiation reach-

es the ground, using a Dobson ozone spectrophotometer. Ozone layer thickness is measured inDobson units. The higher the number, the thicker the ozone layer. Since the 1970s, gases pro-duced for commercial purposes have been destroying the ozone layer, upsetting the naturalequilibrium that existed. It is planned that by 2005 in developed countries and by 2015 in devel-oping countries, the use of ozone depleting gases, such as CFCs, will be phased out.

9.2.2 Effects of Ozone Layer Depletion

Effects on Human and Animal Health: Increased penetration of solar UV-B radiation is like-ly to have high impact on human health with potential risks of eye diseases, skin cancer andinfectious diseases.

Effects on Terrestrial Plants: In forests and grasslands, increased radiation is likely to changespecies composition thus altering the bio-diversity in different ecosystems. It could also affectthe plant community indirectly resulting in changes in plant form, secondary metabolism, etc.

Effects on Aquatic Ecosystems: High levels of radiation exposure in tropics and subtropics

Figure 9.3 Chemistry of Ozone Depletion Process

Page 240: General Aspect of Energy Management and Energy Audit

9. Global Environmental Concerns

174Bureau of Energy Efficiency

may affect the distribution of phytoplanktons, which form the foundation of aquatic food webs.It can also cause damage to early development stages of fish, shrimp, crab, amphibians andother animals, the most severe effects being decreased reproductive capacity and impaired lar-val development.

Effects on Bio-geo-chemical Cycles: Increased solar UV radiation could affect terrestrial andaquatic bio-geo-chemical cycles thus altering both sources and sinks of greenhouse and impor-tant trace gases, e.g. carbon dioxide (CO2), carbon monoxide (CO), carbonyl sulfide (COS), etc.These changes would contribute to biosphere-atmosphere feedbacks responsible for the atmos-phere build-up of these greenhouse gases.Effects on Air Quality: Reduction of stratospheric ozone and increased penetration of UV-Bradiation result in higher photo dissociation rates of key trace gases that control the chemicalreactivity of the troposphere. This can increase both production and destruction of ozone andrelated oxidants such as hydrogen peroxide, which are known to have adverse effects on humanhealth, terrestrial plants and outdoor materials. The ozone layer, therefore, is highly beneficial to plant and animal life on earth filtering out thedangerous part of sun's radiation and allowing only the beneficial part to reach earth. Any dis-turbance or depletion of this layer would result in an increase of harmful radiation reaching theearth's surface leading to dangerous consequences.

9.2.3 Ozone Depletion Counter Measures

- International cooperation, agreement (Montreal Protocol) to phase out ozone depletingchemicals since 1974

- Tax imposed for ozone depleting substances- Ozone friendly substitutes- HCFC (less ozone depleting potential and shorter life)- Recycle of CFCs and Halons

9.3 Global Warming

Before the Industrial Revolution, human activities released very few gases into the atmosphereand all climate changes happened naturally. After the Industrial Revolution, through fossil fuelcombustion, changing agricultural practices and deforestation, the natural composition of gasesin the atmosphere is getting affected and climate and environment began to alter significantly.

Over the last 100 years, it was found out that the earth is getting warmer and warmer, unlikeprevious 8000 years when temperatures have been relatively constant. The present temperatureis 0.3 - 0.6 °C warmer than it was 100 years ago.

The key greenhouse gases (GHG) causing global warming is carbon dioxide. CFC's, eventhough they exist in very small quantities, are significant contributors to global warming.Carbon dioxide, one of the most prevalent greenhouse gases in the atmosphere, has two majoranthropogenic (human-caused) sources: the combustion of fossil fuels and changes in land use.Net releases of carbon dioxide from these two sources are believed to be contributing to therapid rise in atmospheric concentrations since Industrial Revolution. Because estimates indicatethat approximately 80 percent of all anthropogenic carbon dioxide emissions currently comefrom fossil fuel combustion, world energy use has emerged at the center of the climate changedebate.

Page 241: General Aspect of Energy Management and Energy Audit

9.3.1 Sources of Greenhouse Gases

Some greenhouse gases occur naturally in the atmos-phere, while others result from human activities.Naturally occurring greenhouse gases include watervapor, carbon dioxide, methane, nitrous oxide, andozone (refer Figure 9.4). Certain human activities, how-ever, add to the levels of most of these naturally occur-ring gases.

Carbon dioxide is released to the atmosphere whensolid waste, fossil fuels (oil, natural gas, and coal), andwood and wood products are burned.

Methane is emitted during the production and transport of coal, natural gas, and oil.Methane emissions also result from the decomposition of organic wastes in municipal solidwaste landfills, and the raising of livestock. Nitrous oxide is emitted during agricultural andindustrial activities, as well as during combustion of solid waste and fossil fuels.

Very powerful greenhouse gases that are not naturally occurring include hydrofluorocarbons(HFCs), perfluorocarbons (PFCs), and sulfur hexafluoride (SF6), which are generated in a vari-ety of industrial processes.

Often, estimates of greenhouse gas emissions are presented in units of millions of metrictons of carbon equivalents (MMTCE), which weights each gas by its Global Warming Potentialor GWP value.

9.3.2 Global Warming Potentials

Although there are a number of ways of measuring the strength of different greenhouse gasesin the atmosphere, the Global Warming Potential (GWP) is perhaps the most useful.

GWPs measure the influence greenhouse gases have on the natural greenhouse effect,including the ability of greenhouse gas molecules to absorb or trap heat and the length of time,greenhouse gas molecules remain in the atmosphere before being removed or broken down. Inthis way, the contribution that each greenhouse gas has towards global warming can beassessed.

Each greenhouse gas differs in its ability to absorb heat in the atmosphere. HFCs and PFCsare the most heat-absorbent. Methane traps over 21 times more heat per molecule than carbondioxide, and nitrous oxide absorbs 270 times more heat per molecule than carbon dioxide.Conventionally, the GWP of carbon dioxide, measured across all time horizons, is 1. The GWPsof other greenhouse gases are then measured relative to the GWP of carbon dioxide. Thus GWPof methane is 21 while GWP of nitrous oxide is 270.

Other greenhouse gases have much higher GWPs than carbon dioxide, but because theirconcentration in the atmosphere is much lower, carbon dioxide is still the most important green-house gas, contributing about 60% to the enhancement of the greenhouse effect.

9.3.3 Global Warming (Climate Change) Implications

Rise in global temperatureObservations show that global temperatures have risen by about 0.6 °C over the 20th century.There is strong evidence now that most of the observed warming over the last 50 years is causedby human activities. Climate models predict that the global temperature will rise by about 6 °C

9. Global Environmental Concerns

175Bureau of Energy Efficiency

Figure 9.4 %Share of Greenhouse Gases

Page 242: General Aspect of Energy Management and Energy Audit

by the year 2100.

Rise in sea level

In general, the faster the climate change, the greater will be the risk of damage. The mean sealevel is expected to rise 9 - 88 cm by the year 2100, causing flooding of low lying areas andother damages.

Food shortages and hunger

Water resources will be affected as precipitation and evaporation patterns change around theworld. This will affect agricultural output. Food security is likely to be threatened and someregions are likely to experience food shortages and hunger.

India could be more at risks than many other countries

Models predict an average increase in temperature in India of 2.3 to 4.8°C for the benchmarkdoubling of Carbon-dioxide scenario. Temperature would rise more in Northern India than inSouthern India. It is estimated that 7 million people would be displaced, 5700 km2 of land and4200 km of road would be lost, and wheat yields could decrease significantly.

9.4 Loss of Biodiversity

Biodiversity refers to the variety of life on earth, and its biological diversity. The number ofspecies of plants, animals, micro organisms, the enormous diversity of genes in these species,the different ecosystems on the planet, such as deserts, rainforests and coral reefs are all a partof a biologically diverse earth. Biodiversity actually boosts ecosystem productivity where eachspecies, no matter how small, all have an important role to play and that it is in this combina-tion that enables the ecosystem to possess the ability to prevent and recover from a variety ofdisasters.

It is now believed that human activity is changing biodiversity and causing massive extinc-tions. The World Resource Institute reports that there is a link between biodiversity and climatechange. Rapid global warming can affect ecosystems chances to adapt naturally. Over the past150 years, deforestation has contributed an estimated 30 percent of the atmospheric build-up ofCO2. It is also a significant driving force behind the loss of genes, species, and critical ecosys-tem services.

Link between Biodiversity and Climate change • Climate change is affecting species already threatened by multiple threats across the

globe. Habitat fragmentation due to colonization, logging, agriculture and mining etc.are all contributing to further destruction of terrestrial habitats.

• Individual species may not be able to adapt. Species most threatened by climate changehave small ranges, low population densities, restricted habitat requirements and patchydistribution.

• Ecosystems will generally shift northward or upward in altitude, but in some cases theywill run out of space - as 1°C change in temperature correspond to a 100 Km change inlatitude, hence, average shift in habitat conditions by the year 2100 will be on the orderof 140 to 580 Km.

9. Global Environmental Concerns

176Bureau of Energy Efficiency

Page 243: General Aspect of Energy Management and Energy Audit

• Coral reef mortality may increase and erosion may be accelerated. Increase level of car-bon dioxide adversely impact the coral building process (calcification).

• Sea level may rise, engulfing low-lying areas causing disappearance of many islands,and extinctions of endemic island species.

• Invasive species may be aided by climate change. Exotic species can out-compete nativewildlife for space, food, water and other resources, and may also prey on native wildlife.

• Droughts and wildfires may increase. An increased risk of wildfires due to warming anddrying out of vegetation is likely.

• Sustained climate change may change the competitive balance among species and mightlead to forests destruction

9.5 Climatic Change Problem and Response

9.5.1 The United Nations Framework Convention on Climate Change, UNFCCC

In June 1992, the "United Nations Framework Convention on Climate Change" (UNFCCC) wassigned in Rio de Janeiro by over 150 nations. The climate convention is the base for interna-tional co-operation within the climate change area. In the convention the climate problem's seri-ousness is stressed. There is a concern that human activities are enhancing the natural green-house effect, which can have serious consequences on human settlements and ecosystems.

The convention's overall objective is the stabilisation of greenhouse gas concentrations inthe atmosphere at a level that would prevent dangerous anthropogenic interference with the cli-mate system."

The principle commitment applying to parties of the convention is the adoption of policiesand measures on the mitigation of climate change, by limiting anthropogenic emissions ofgreenhouse gases and protecting and enhancing greenhouse gas sinks and reservoirs. The com-mitment includes the preparation and communication of national inventories of greenhousegases. The Climate convention does not have any quantitative targets or timetables for individ-ual nations. However, the overall objective can be interpreted as stabilization of emissions ofgreenhouse gases by year 2000 at 1990 levels.

The deciding body of the climate convention is the Conference of Parties (COP). At theCOP meetings, obligations made by the parties are examined and the objectives and imple-mentation of the climate convention are further defined and developed. The first COP was heldin Berlin, Germany in 1995 and the latest (COP 10) was held in December 2004, Buenos Aires,Argentina.

9.5.2 The Kyoto Protocol

There is a scientific consensus that human activities are causing global warming that couldresult in significant impacts such as sea level rise, changes in weather patterns and adversehealth effects. As it became apparent that major nations such as the United States and Japanwould not meet the voluntary stabilization target by 2000, Parties to the Convention decided in1995 to enter into negotiations on a protocol to establish legally binding limitations or reduc-tions in greenhouse gas emissions. It was decided by the Parties that this round of negotiationswould establish limitations only for the developed countries, including the former Communistcountries (called annex A countries).

9. Global Environmental Concerns

177Bureau of Energy Efficiency

Page 244: General Aspect of Energy Management and Energy Audit

Negotiations on the Kyoto Protocol to the United Nations Framework Convention on ClimateChange (UNFCCC) were completed December 11, 1997, committing the industrialized nationsto specify, legally binding reductions in emissions of six greenhouse gases. The 6 major green-house gases covered by the protocol are carbon dioxide (CO2), methane (CH4), nitrous oxide(N2O), hydrofluorocarbons (HFCs), perfluorocarbons (PFCs), and sulfur hexafluoride (SF6).

Emissions Reductions

The United States would be obligated under the Protocol to a cumulative reduction in its green-house gas emissions of 7% below 1990 levels for three greenhouse gases (including carbondioxide), and below 1995 levels for the three man-made gases, averaged over the commitmentperiod 2008 to 2012.

The Protocol states that developed countries are committed, individually or jointly, to ensur-ing that their aggregate anthropogenic carbon dioxide equivalent emissions of greenhouse gasesdo not exceed amounts assigned to each country with a view to reducing their overall emissionsof such gases by at least 5% below 1990 levels in the commitment period 2008 to 2012. The amounts for each country are listed as percentages of the base year, 1990 and range from92% (a reduction of 8%) for most European countries--to 110% (an increase of 10%) forIceland.

Developing Country Responsibilities

Another problematic area is that the treaty is ambiguous regarding the extent to which devel-oping nations will participate in the effort to limit global emissions. The original 1992 climatetreaty made it clear that, while the developed nations most responsible for the current buildupof greenhouse gases in the atmosphere should take the lead in combating climate change, devel-oping nations also have a role to play in protecting the global climate. Per Capita CO2 emissionsare small in developing countries and developed nations have altered the atmosphere the mostas shown in the Figure 9.5 & Figure 9.6.

9. Global Environmental Concerns

178Bureau of Energy Efficiency

Figure 9.5 Per Capita CO2 Emissions for the 15Countries With the Highest Total Industrial

Emissions, 1995

Figure 9.6 Cumulative Carbon-Dioxide Emissions,1950-95

Page 245: General Aspect of Energy Management and Energy Audit

Developing countries, including India and China, do not have to commit to reductions in thisfirst time period because their per-capita emissions are much lower than those of developedcountries, and their economies are less able to absorb the initial costs of changing to cleanerfuels. They have not contributed significantly to today's levels of pollution that has been theproduct of the developed world's Industrial Revolution. The idea is that developing countrieswill be brought more actively into the agreement as new energy technologies develops and asthey industrialize further.

Annex I and Annex II Parties Annex I parties are countries which have commitments according to the Kyoto protocol. Theentire Annex I parties are listed in the Table 9.1 below. Further Annex I parties shown in boldare also called Annex II parties. These Annex II parties have a special obligation to provide"new and additional financial sources" to developing countries (non Annex I) to help them tack-le climate change, as well as to facilitate the transfer of climate friendly technologies to bothdeveloping countries and to economies in transition. Commitments are presented as percentageof base year emission levels to be achieved during between 2008 - 2012.

9. Global Environmental Concerns

179Bureau of Energy Efficiency

Page 246: General Aspect of Energy Management and Energy Audit

Base year is 1990 for all countries except those economies in transition, who may chose analternative base year or multi-year period.

Actions required from developed and developing Nations

The Kyoto Protocol does call on all Parties (developed and developing) to take a number ofsteps to formulate national and regional programs to improve "local emission factors," activitydata, models, and national inventories of greenhouse gas emissions and sinks that remove thesegases from the atmosphere. All Parties are also committed to formulate, publish, and update cli-mate change mitigation and adaptation measures, and to cooperate in promotion and transfer ofenvironmentally sound technologies and in scientific and technical research on the climate sys-tem.

Who is bound by the Kyoto Protocol?

The Kyoto Protocol has to be signed and ratified by 55 countries (including those responsiblefor at least 55% of the developed world's 1990 carbon dioxide emissions) before it can enterinto force. Now that Russia has ratified, this been achieved and the Protocol will enter into forceon 16 February 2005.

9.5.3 India's Greenhouse Gas Emissions

India has experienced a dramatic growth in fossil fuel CO2 emissions, and the data compiled byvarious agencies shows an increase of nearly 5.9 % since 1950. At present India is rated as the6th largest contributor of CO2 emissions behind China, the 2nd largest contributor. However, ourper capita CO2 of 0.93 tons per annum is well below the world average of 3.87 tons per annum.Fossil fuel emissions in India continue to result largely from coal burning. India is highly vul-nerable to climate change as its economy is heavily reliant on climate sensitive sectors like agri-culture and forestry. The vast low-lying and densely populated coastline is susceptible to rise insea level.

The energy sector is the largest contributor of carbon dioxide emissions in India. Thenational inventory of greenhouse gases indicates that 55% of the total national emissions comefrom energy sector. These include emissions from road transport, burning of traditional bio-mass fuels, coal mining, and fugitive emissions from oil and natural gas.

Agriculture sector constitutes the next major contributor, accounting for nearly 34%. Theemissions under this sector include those from enteric fermentation in domestic animals,manure management, rice cultivation, and burning of agriculture residues. Emissions fromIndustrial sector mainly came from cement production.

Indian Response to Climatic Change

Under the UNFCCC, developing countries such as India do not have binding GHG mitigationcommitments in recognition of their small contribution to the greenhouse problem as well aslow financial and technical capacities. The Ministry of Environment and Forests is the nodalagency for climate change issues in India. It has constituted Working Groups on the UNFCCCand Kyoto Protocol. Work is currently in progress on India's initial National Communication(NATCOM) to the UNFCCC. India ratified the Kyoto Protocol in 2002

9. Global Environmental Concerns

180Bureau of Energy Efficiency

Page 247: General Aspect of Energy Management and Energy Audit

9.6 The Conference of the Parties (COP)

The Conference of the Parties is the supreme body of the Climate Change Convention. The vastmajority of the world's countries are members (185 as of July 2001). The Convention enters intoforce for a country 90 days after that country ratifies it. The COP held its first session in 1995and will continue to meet annually unless decided otherwise. However, various subsidiary bod-ies that advise and support the COP meet more frequently.

The Convention states that the COP must periodically examine the obligations of the Partiesand the institutional arrangements under the Convention. It should do this in light of theConvention's objective, the experience gained in its implementation, and the current state of sci-entific knowledge.

Exchange of Information

The COP assesses information about policies and emissions that the Parties share with eachother through their national communications. It also promotes and guides the development andperiodic refinement of comparable methodologies, which are needed for quantifying net green-house gas emissions and evaluating the effectiveness of measures to limit them. Based on theinformation available, the COP assesses the Parties efforts to meet their treaty commitments andadopts and publishes regular reports on the Convention's implementation.

Support for Developing countries

Developing countries need support so that they can submit their national communications, adaptto the adverse effects of climate change, and obtain environmentally sound technologies. TheCOP therefore oversees the provision of new and additional resources by developed countries.The third session of the Conference of the Parties adopted the Kyoto Protocol.

9.6.1 The Flexible Mechanisms

The Kyoto protocol gives the Annex I countries the option to fulfill a part of their commitmentsthrough three "flexible mechanisms". Through these mechanisms, a country can fulfill a part oftheir emissions reductions in another country or buy emission allowances from another coun-try. There are three flexible mechanisms:

i. Emissions trading ii. Joint implementation iii. Clean development mechanism

i) Emissions trading

Article 17 of the Kyoto protocol opens up for emissions trading between countries that havemade commitments to reduce greenhouse gas emissions. The countries have the option to del-egate this right of emissions trading to companies or other organisations.

In a system for emissions trading, the total amount of emissions permitted is pre-defined.The corresponding emissions allowances are then issued to the emitting installations throughauction or issued freely. Through trading, installations with low costs for reductions are stimu-lated to make reductions and sell their surplus of emissions allowances to organisations wherereductions are more expensive. Both the selling and buying company wins on this flexibilitythat trade offers with positive effects on economy, resource efficiency and climate. The envi-

9. Global Environmental Concerns

181Bureau of Energy Efficiency

Page 248: General Aspect of Energy Management and Energy Audit

ronmental advantage is that one knows, in advance, the amount of greenhouse gases that willbe emitted. The economical advantage is that the reductions are done where the reduction costsare the lowest. The system allows for a cost effective way to reach a pre-defined target and stim-ulates environmental technology development.

ii) Joint Implementation, JI

Under article 6 of the Kyoto protocol an Annex I country that has made a commitment forreducing greenhouse gases, can offer to, or obtain from another Annex I country greenhouse gasemissions reductions. These emissions reductions shall come from projects with the objectivesto reduce anthropogenic emissions from sources or increase the anthropogenic uptake in sinks.In order to be accepted as JI-projects, the projects have to be accepted by both parties inadvance. It also has to be proven that the projects will lead to emissions reductions that are high-er than what otherwise would have been obtained. JI-projects are an instrument for one indus-trial country to invest in another industrial country and in return obtain emissions reductions.These reductions can be used to help fulfill their own reduction commitments at a lower costthan if they had to do the reductions in their own country.

iii) Clean Development Mechanism (CDM)

Article 12 of the Kyoto protocol defines the Clean Development Mechanism, CDM. The pur-pose of CDM is to: a) contribute to sustainable development in developing countries; b) help Annex I-countries under the Kyoto Protocol to meet their target.

With the help of CDM, countries which have set themselves an emission reduction targetunder the Kyoto Protocol (Annex I countries) can contribute to the financing of projects indeveloping countries (non-Annex I countries) which do not have a reduction target. These pro-jects should reduce the emission of greenhouse gases while contributing to the sustainabledevelopment of the host country involved. The achieved emission reductions can be purchasedby the Annex I country in order to meet its reduction target.

In order to be accepted as CDM-projects, the projects have to be accepted by both partiesin advance. It also has to be proven that the projects will lead to emissions reductions that arehigher than what otherwise would have been obtained. The difference between JI-projects andCDM-projects is that JI-projects are done between countries that both have commitments, whilethe CDM-projects is between one country that has commitments and another country that doesnot have commitments. Emissions reductions that have been done through CDM-projects dur-ing the period 2000 to 2007, can be used for fulfilling commitments in Annex I countries forthe period 2008-2012.

How CDM works?

An investor from a developed country, can invest in, or provide finance for a project in a devel-oping country that reduces greenhouse gas emissions so that they are lower than they wouldhave been without the extra investment - i.e. compared to what would have happened withoutthe CDM under a business as usual outcome. The investor then gets credits - carbon credits -for the reductions and can use those credits to meet their Kyoto target. If the CDM works per-fectly it will not result in more or less emission reductions being achieved than were agreedunder the Kyoto Protocol, it will simply change the location in which some of the reductions

9. Global Environmental Concerns

182Bureau of Energy Efficiency

Page 249: General Aspect of Energy Management and Energy Audit

will happen. For example, a French company needs to reduce its emissions as part of its contribution to

meeting France's emission reduction target under the Kyoto Protocol. Instead of reducing emis-sions from its own activities in France, the company provides funding for the construction of anew biomass plant in India that would not have been able to go ahead without this investment.This, they argue, prevents the construction of new fossil-fueled plants in India, or displaces con-sumption of electricity from existing ones, leading to a reduction in greenhouse gas emissionsin India. The French investor gets credit for those reductions and can use them to help meet theirreduction target in France.

Requirements for Participating in CDM

Project cycle for CDM

The project cycle for CDM is shown in Figure 9.7. There are seven basic stages; the first fourstages are performed prior to the implementation of the project, while the last three stages areperformed during the lifetime of the project.

9. Global Environmental Concerns

183Bureau of Energy Efficiency

Fig 9.7 Project Cycle for CDM

Page 250: General Aspect of Energy Management and Energy Audit

While investors profit from CDM projects by obtaining reductions at costs lower than in theirown countries, the gains to the developing country host parties are in the form of finance, tech-nology, and sustainable development benefits.

Projects starting in the year 2000 are eligible to earn Certified Emission Reductions (CERs)if they lead to "real, measurable, and long-term" GHG reductions, which are additional to anythat would occur in the absence of the CDM project. This includes afforestation and reforesta-tion projects, which lead to the sequestration of carbon dioxide.

At COP-7, it was decided that the following types of projects would qualify for fast-trackapproval procedures:

- Renewable energy projects with output capacity up to 15 MW- Energy efficiency improvement projects which reduce energy consumption on the sup-

ply and/or demand side by up to 15 GWh annually- Other project activities that both reduce emissions by sources and directly emit less than

15 kilotons CO2 equivalent annually.The CDM will be supervised by an executive board, and a share of the proceeds from pro-

ject activities will be used to assist developing countries in meeting the costs of adaptation toclimate change.

Indian Initiatives on CDMGovernment of India has been willing to fulfill its responsibility under the CDM. It has devel-oped an interim criterion for approval of CDM project activities, which is now available tostakeholders. It has undertaken various capacity building activities like holding of workshops,initiation of various studies, and briefing meeting with the stakeholders. India has been active-ly participating in the CDM regime and has already approved projects for further development.

Under CDM, projects such as energy efficient hydrocarbon refrigerators, modernization ofsmall scale foundry units and renovation, modernization of thermal power stations etc. are beingtaken up.

Case ExampleIn a power plant renovation and modernization programme by replacing plant equipment whichare prone to wear and tear over a period of time, such as boilers and auxiliaries, turbine blades,HP governor valves and station auxiliaries which include material handling equipment, watertreatment, pulverisers, ash handling plant, ESP etc resulted in CO2 emission reduction from1.20 kg/kWh to 1.11 kg/kWh. The details are shown in the Table 9.2:

9. Global Environmental Concerns

184Bureau of Energy Efficiency

TABLE 9.2 EFFICIENCY IMPROVEMENT AND EMISSION REDUCTION

IN A POWER PLANT MODERNISATION PROGRAMME.

Parameters Before the programme After the programme

Gross heat rate (kcal/KWh) 2700 2500

Net efficiency (%) 28 30

Specific coal consumption 0.77 0.71

Total CO2 emissions (tones/year) 1435336 1329015

CO2 emissions (kg/ kWh) 1.20 1.11

Page 251: General Aspect of Energy Management and Energy Audit

9.7 Prototype Carbon Fund (PCF)

Recognizing that global warming will have the most impact on its borrowing client countries,the World Bank approved the establishment of the Prototype Carbon Fund (PCF). The PCF isintended to invest in projects that will produce high quality greenhouse gas emission reductionsthat could be registered with the United Nations Framework Convention on Climate Change(UNFCCC) for the purposes of the Kyoto Protocol. To increase the likelihood that the reduc-tions will be recognized by the Parties to the UNFCCC, independent experts will follow vali-dation, verification and certification procedures that respond to UNFCCC rules as they develop.

The PCF will pilot production of emission reductions within the framework of JointImplementation (JI) and the Clean Development Mechanism (CDM). The PCF will invest con-tributions made by companies and governments in projects designed to produce emission reduc-tions fully consistent with the Kyoto Protocol and the emerging framework for JI and the CDM.Contributors, or "Participants" in the PCF, will receive a pro rata share of the emission reduc-tions, verified and certified in accordance with agreements reached with the respective countries"hosting" the projects.

9.7.1 Size of Market for Emissions Reductions

• All estimates of market volume are speculative at this early stage in the market's devel-opment.

• One way of looking at the potential size of the market is to assume that about one bil-lion tonnes of carbon emissions must be reduced per year during the commitment peri-od of 2008-2012 in order for the industrialized countries to meet their obligations of a5% reduction in their 1990 levels of emissions.

Under Prototype carbon fund programme of the World Bank. Government of India hasapproved a municipal solid waste energy project for implementation in Chennai, which pro-poses to use the state of art technology for extracting energy from any solid waste irrespectiveof the energy content. Many industrial organisations in the private sector have also sought assis-tance under this fund.

9.8 Sustainable Development

9.8.1 What is Sustainable Development?

Sustainable development is often defined as 'development that meets the needs of the present,without compromising the ability of future gener-ations to meet their own needs'. Sustainable development encompasses three basicand inter-related objectives:

• Economic security and prosperity• Social development and advancement• Environmental sustainability

Sustainable development demands that we seekways of living, working and being that enable allpeople of the world to lead healthy, fulfilling, and

9. Global Environmental Concerns

185Bureau of Energy Efficiency

Figure 9.8 Sustainable Development

Page 252: General Aspect of Energy Management and Energy Audit

economically secure lives without destroying the environment and without endangering thefuture welfare of people and the planet.Sustainable development as applied to energy and environment should consider the following:

• inputs - such as fuels and energy sources, land and raw materials - are non-renewablethey should be used up only as far as they can be substituted in future

• where they are renewable they should be used up at a rate within which they can berenewed,

• outputs - in production and consumption - should not overstrain ecosystems or theassimilation capacity of the ecosphere.

9. Global Environmental Concerns

186Bureau of Energy Efficiency

Page 253: General Aspect of Energy Management and Energy Audit

9. Global Environmental Concerns

187Bureau of Energy Efficiency

QUESTIONS

1 Name and explain three effects of ozone layer depletion.

2 Explain ozone layer depletion problem?

3 Ozone is formed by combination of a) three oxygen atoms b) one oxygen atomc) four ozone atom d) five ozone atom.

4 Name at least three chemicals responsible for ozone depletion?

5 Name at least three greenhouse gases responsible for global warming?

6 Explain impacts of climatic change on earth?

7 What is the main role of UNFCCC?

8 What do you understand by term "COP" and explain its role?

9 What is Kyoto protocol, and what are its implications for developed and developingcountries?

10 Explain CDM and its objectives.

11 What are the uses of prototype carbon fund?

12 Explain the concept of sustainable development.

REFERENCES

1. Cleaner Production – Energy Efficiency Manual for GERIAP, UNEP, Bangkok preparedby National Productivity Council

2. Training material on 'Environmental concerns' prepared by National ProductivityCouncil

3. Parivesh, October 2002 – Central Pollution Control Board

www.epa.orgwww.uneptie.orgwww.cpcb.nic.inwww.wri.orgwww.safeclimate.netwww.globalwarming.org

Page 254: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

Chapter 1.9 Global Environmental Concerns Part – I Objective Type Questions

1. The spread of the ‘Stratosphere’ above the Earth’s surface is______

a) Below 15 km b) 10 to 50 km c) above 50 km d) above 100 km

2. The pungent smelling and light bluish gas in Stratosphere is due to_____

a) Carbon molecules b) Ozone molecules c) Nitrogen gas d) Oxygen

3. The ozone layer in the stratosphere acts as an efficient filter for ____

a) Solar UV- B rays b) X-rays c) Gamma rays d) UV-A rays

4. Ozone layer is found in_________

a) Ionosphere b) Troposphere c) Stratosphere d) All

5. The compounds that can easily break ozone molecules are______

a) Chlorine b) Bromine c) Both a & b d) None

6. CFC stands for___________

a) Chloro Fluro Carbons b) Carbon Fluorine Carbon

c) Compact Fluro Carbons d) None of the above

7. The main source of CFCs in household sector is___________

a) Televisions b) Refrigerators c) Washing machines d) All

8. The raise in present temperature of earth compared to 100 years ago is____

a) 2 – 6 ° C b) 0.3 – 0.6 ° C c) 10 ° C d) 0 ° C

9. Global warming is due to release of

a) SO2 b) greenhouse Gases c) inert gases d) free chlorine

10. The main constituents of Greenhouse gases (GHG) are on earth surface are

a) CO2, CH4 b) SOx c) nitrogen d) water vapor

11. The predicted raise in mean sea level due to global warming by the year 2100 ____

a) 1 m b) 1 cm c) 2 m d) 9 -88 cm

12. The agency to look after the climate changes and for action to cut GHG ____

a) UNFCCC b) WHO c) DOE d) GOI

13. What is COP?

a) Conference of Parties b) Coefficient of Pollution

c) Coalition of Parties d) Convention of People

1.9 - Global env. concerns - revised (table format) 67

Page 255: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

14. The number of major green house gases covered for their reduction by the Kyoto protocol are

a) 10 b) 2 c) 6 d) 1

15. Which country emits maximum CO2?

a) Australia b) Iceland c) Norway d) USA

16. The year in which India ratified the Kyoto protocol____

a) 1997 b) 2002 c) 2000 d) 2003

17. CDM stands for

a) Carbon Depletion Mechanism

b) Clean Development Mechanism

c) Clear Development Mechanism

d) Carbon Depletion Machinery

18. The fund intended to invest in projects that will reduce green house gas emissions is___

a) Prototype Carbon Fund b) GHG Reduction Fund

c) Pollution Control Fund d) None

19. The first project GOI approved under prototype carbon fund is_____

a) SWERF b) NICE c) Asia-Urbs d) ICT

20. The name of the world commission on Environment and development is ____

a) Brundtland Commission b) Zakaria Commission

c) Planning Commission d) None of the above

Part – II: Short type questions and answers

1. Give few examples of environment issues on global significance?

• Ozone layer depletion

• Land degradation

• Air and water pollution

• Sea-level rise

• Loss of biodiversity

2. What is Ozone layer depletion?

The ozone layer is highly reactive and easily broken down by man made chlorine and bromine compounds. These compounds are found to be most responsible for most of ozone layer depletion. This leads to decrease in thickness of the ozone layer and this phenomenon is called as Ozone layer depletion.

1.9 - Global env. concerns - revised (table format) 68

Page 256: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

3. What are the impacts of Ozone Layer depletion?

• Human health with potential risks of eye diseases, skin cancer and infectious diseases.

• Changes in species composition thus altering the bio-diversity in different ecosystems

• Damage to early development stages of fish, shrimp, crab, amphibians and other animals,

• Affect terrestrial and aquatic bio-geo-chemical cycles thus altering both sources and sinks of greenhouse and important trace gases.

4. What is the impact of Global Warming?

Greenhouse gases trap some of the out going energy and retain heat in the earth atmosphere, which results in an increase in the earth atmospheric temperature.

5. Mention three important GHG covered under the Kyoto protocol .

The six major greenhouse gases covered by the protocol are carbon dioxide (CO2), methane (CH4), nitrous oxide (N2O), hydroflurocarbons (HFCs), perflurocarbons (PFCs), and sulfur hexafluoride (SF6).

6. Who is the nodal agency for monitoring climate changes in India?

The Ministry of Environment and Forests is the nodal agency for climate change issues in India.

7. Mention few sectors that contribute to maximum emissions in India?

Energy sector: emissions from road transport, burning of traditional bio-mass fuels, coal mining, and fugitive emissions from oil and natural gas. Agriculture sector: emissions from enteric fermentation in domestic animals, manure management, rice cultivation, and burning of agriculture residues.

8. Name at least three Ozone layer Depleting Substances (ODS).

• Chloro Fluro Carbons (CFC’s)

• Hydrochloro Flurocarbons (HCFC’s)

• Hydrobromo Flurocarbons (HBFC’s)

• Halons

• Methyl Chloroform

• Carbon Tetra Chloride (CTC)

• Methyl bromide.

9. What are the three mechanisms suggested to cut GHG emissions as per Kyoto protocol?

a. Emission trading

b. Joint implementation

c. CDM

10. What is the commitment of signatories of Kyoto Protocol?

To reduce the overall emissions of GHG by at least Five percent below 1990 levels in the commitment period 2008 to 2012.

1.9 - Global env. concerns - revised (table format) 69

Page 257: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

11. What is Agenda 21 under sustainable development?

Agenda 21 set out recommendations for developed and developing nations regarding sustainable development strategies concerning clean air and water, water supply, energy, land use, housing, waste treatment, transportation, and health care.

12. Name the three zones of earth’s atmosphere?

1. Troposphere

2. Ionosphere

3. Stratosphere

13. Write about chemistry of ozone?

Ozone formed by combination of three oxygen atoms, is a very unstable molecule. The combination is brought about by high intensity ultra violet rays of the sun in the upper atmosphere.

14. Write the importance of ozone layer?

The ozone layer is highly beneficial to plant and animal life on earth filtering out the dangerous part of sun’s radiation and allowing only the beneficial part of reach earth. Any disturbance or depletion of this layer would result in an increase of harmful radiation reaching the earth’s surface leading to dangerous consequences.

15. How carbon-di-oxide is produced?

Carbon dioxide is produced when fossil fuels are used to generate energy and when forests are cut down and burned.

16. What will be the expected rise in temperature and mean sea level by the year 2100, due to climate change?

Climate models predict that the global temperature will rise by about 6 °C and mean sea level is expected to rise 9-88 cm by the year 2100.

17. What are the likely affects of Global warming on India?

Models predict an average increase in temperature in India of 2.3 to 4.8 deg. C for the benchmark doubling of carbon dioxide scenario. Temperature would raise more in northern India than in southern India, without protection approximately 7 million people would be displaced, 5700 km2

of land and 4200 km of road would be lost and wheat yields could decrease between 2.8 to 6.8%.

18. Why CoP has been formed?

All nations, who initially ratified the UNFCC, reconvened in the form of conference of Parties (CoP) at Berlin in 1995 with a goal of entering into negotiations on a protocol to establish legally binding limitations or reductions in emission.

19. Compare the per capita CO2 of India with world’s average value?

India per capita CO2 of 0.93 t per annum and is well below the world average of 3.8 t per annum.

20. Define Sustainable development defined by Brundtland commission.

The World Commission on Environment and Development (the Brundtland Commission) defined sustainable development as "development that meets the needs of the present without compromising the ability of future generations to meet their own needs."

1.9 - Global env. concerns - revised (table format) 70

Page 258: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

Part-III: Long type Questions and Answers

1. What are the implications of Global warming?

Increase in global temperature

Observations show that global temperatures have risen by about 0.6 °C over the 20th century. There is new and stronger evidence that most of the observed warming over the last 50 years is attributable to human activities. Climate models predict that the global temperature will rise by about 5.8°C by the year 2100.

Rise in sea level

In general, the faster the climate changes, the greater will be the risk of damage. The mean sea level is expected to rise 9 - 88 cm by the year 2100, causing flooding of low lying areas and other damage.

Human society will face new risks and pressures.

Food security is unlikely to be threatened at the global level, but some regions are likely to experience food shortages and hunger. Water resources will be affected as precipitation and evaporation patterns change around the world.

2. What do you understand by Conference of Parties (CoP) and explain the objectives of CoP?

The Conference of the Parties is the supreme body of the Climate Change Convention. The vast majority of the world’s states are members (185 as of July 2001). The Convention enters into force for a state 90 days after that state ratifies it. The COP held its first session in 1995 and will continue to meet annually unless decided otherwise. (The various subsidiary bodies that advise and support the COP meet more frequently.)

The Convention states that the COP must periodically examine the obligations of the Parties and the institutional arrangements under the Convention. It should do this in light of the Convention’s objective, the experience gained in its implementation, and the current state of scientific knowledge.

Exchange of Information:

The COP assesses information about policies and emissions that the Parties share with each other through their national communications. It also promotes and guides the development and periodic refinement of comparable methodologies, which are needed for quantifying net greenhouse gas emissions and evaluating the effectiveness of measures to limit them. Based on the information available, the COP assesses the Parties™ efforts to meet their treaty commitments and adopts and publishes regular reports on the Convention’s implementation.

Support for Developing countries:

Developing countries need support so that they can submit their national communications, adapt to the adverse effects of climate change, and obtain environmentally sound technologies. The COP therefore oversees the provision of new and additional resources by developed countries.

3. Explain about Prototype Carbon Fund?

Recognizing that global warming will have the most impact on its borrowing client countries, on July 20th, 1999 the Executive Directors of the World Bank approved the establishment of the Prototype Carbon Fund (PCF). The PCF is intended to invest in projects that will produce high quality greenhouse gas emission reductions that could be registered with the United Nations Framework Convention on Climate Change (UNFCCC) for the purposes of the Kyoto Protocol. To increase the likelihood that the reductions will be recognized by the Parties to the UNFCCC, independent experts will follow validation, verification and certification procedures that respond

1.9 - Global env. concerns - revised (table format) 71

Page 259: General Aspect of Energy Management and Energy Audit

Question bank for Energy Managers & Energy Auditors

to UNFCCC rules as they develop.

The PCF will pilot production of emission reductions within the framework of Joint Implementation (JI) and the Clean Development Mechanism (CDM). The PCF will invest contributions made by companies and governments in projects designed to produce emission reductions fully consistent with the Kyoto Protocol and the emerging framework for JI and the CDM. Contributors, or "Participants" in the PCF, will receive a pro rata share of the emission reductions, verified and certified in accordance with agreements reached with the respective countries "hosting" the projects.

4. Write about Indian initiatives on CDM?

Government of India has been willing to fulfill its responsibility under the CDM. It has developed an interim criterion for approval of CDM project activities, which is now available to stakeholders. It has undertaken various capacity building activities like holding of workshops, initiation of various studies, and briefing meeting with the stakeholders. India has been actively participating in the CDM regime and has already approved projects for further development.

Under CDM, projects such as energy efficient hydrocarbon refrigerators, modernization of small scale foundry units and renovation, modernization of thermal power stations etc. are being taken up.

5. Explain briefly the major provisions of Kyoto Protocol treaty. Also briefly discuss India’s greenhouse issues?

The Protocol states that “developed countries are committed, individually or jointly, to ensuring that their aggregate anthropogenic carbon dioxide equivalent emissions of greenhouse gases do not exceed amounts assigned to each country” in Annex A to the Protocol, "with a view to reducing their overall emissions of such gases by at least 5% below 1990 levels in the commitment period 2008 to 2012."

India has ratified the contentious Kyoto Protocol in August 2002. India has experienced a dramatic growth in fossil fuel CO2 emissions, and the data compiled by various agencies shows an increase of nearly 5.9 % since 1950. At present India is rated as the 6th largest contributor of CO2

emissions behind China, the 2nd largest contributor. However, our per capita CO2 of 0.93t per annum is well below the world average of 3.87t per annum. The energy sector is the largest contributor (55%) of carbon dioxide emissions in India. Agriculture sector constitutes the next major contributor, accounting for nearly 34%.

1.9 - Global env. concerns - revised (table format) 72