energy audit finale

49
1.0 EXECUTIVE SUMMARY Energy audit for CTF1 is established to determine how energy had been used by various systems that can be found inside CTF1. Data are collected based on three major end uses known as lighting, air conditioning and general equipments. Based on data completion, electricity/energy consumption in kilowatts for lighting system is 41.7kW, air-conditioning system is 83.79kW, and general equipment is 20.66kW. The percentages of electricity/energy consumption for these three aspects are 30.31%, 59.93% and 15.02% respectively. In order to assess the energy efficiency for CTF1, Building Energy Index (BEI) for CTF1 is computed and later compared with targeted BEI for energy efficient buildings in Malaysia. In short, calculated BEI for CTF1 is 370.5kWh/m 2 /yr whereas the targeted BEI for energy efficient building is in range of 200-250 kWh/m 2 /yr, thus it can be conclude that CTF1 has not yet considered as an energy efficient building. Since the BEI for CTF1 is considered high, a goal has to be set to reduce energy consumption in CTF1. Measures which required non-capital investment is 1

Upload: 17930

Post on 08-Apr-2015

223 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Energy Audit Finale

1.0 EXECUTIVE SUMMARY

Energy audit for CTF1 is established to determine how energy had been used

by various systems that can be found inside CTF1. Data are collected based on three

major end uses known as lighting, air conditioning and general equipments. Based on

data completion, electricity/energy consumption in kilowatts for lighting system is

41.7kW, air-conditioning system is 83.79kW, and general equipment is 20.66kW. The

percentages of electricity/energy consumption for these three aspects are 30.31%,

59.93% and 15.02% respectively.

In order to assess the energy efficiency for CTF1, Building Energy Index

(BEI) for CTF1 is computed and later compared with targeted BEI for energy

efficient buildings in Malaysia. In short, calculated BEI for CTF1 is 370.5kWh/m2/yr

whereas the targeted BEI for energy efficient building is in range of 200-250

kWh/m2/yr, thus it can be conclude that CTF1 has not yet considered as an energy

efficient building.

Since the BEI for CTF1 is considered high, a goal has to be set to reduce

energy consumption in CTF1. Measures which required non-capital investment is

recommended to become main priority to be implemented first. This is because, there

are still many aspects can be improved in order to reduce energy consumption

especially in terms management, operational and maintenance. Later on this report

several probable measures which associated energy savings are identified and

recommended for implementation.

1

Page 2: Energy Audit Finale

2.0 INTRODUCTION

This report presents results of commissioning Energy Audits for Centre of

Teaching Facilities1 (CTF1) situated at Universiti Malaysia Sarawak (UNIMAS).

This Energy Audit is a systematic study or survey to identify how energy is being

used in CTF1. It is also a useful procedure to find out the best options for energy

conservation and saving measure. It also provides an analysis of the amount of energy

consumed by major end uses during a given period in the form of electricity. Using

that information, it is also possible to list how the energy was used according to the

various outlets/room in a building. The next step in this energy audit then is to

identify the potential for energy savings accurately.

2.1 Types of Energy Audit Implemented

Energy audit of CTF1 is a combination of two different types of energy audit

available whereby the Detailed Audit is the continuation of Preliminary Audit. The

preliminary audit alternatively called a walk-through audit is the simplest and

quickest type of audit. It involves minimal interviews with site operating personnel, a

brief review of facility electric bills and other operating data, and a walk-through of

the facility to become familiar with the building operation and identify glaring areas

of energy waste or inefficiency. Typically, only major problem areas will be

uncovered during this type of audit.

The general/detailed audit expands on the preliminary audit described above

by collecting more detailed information about facility operation and performing a

more detailed evaluation of energy conservation measures identified. In-depth

information and data collection which include technical characteristics of energy

consuming equipment/systems, design conditions and parameters, building services

design report with system schematic diagrams and layout drawings showing system

characteristics are gathered from desk and field study. This type of audit will also be

2

Page 3: Energy Audit Finale

able to identify all energy conservation measures appropriate for the facility given its

operating parameters. A detailed financial analysis is performed for each measure

based on detailed implementation cost estimates; site-specific operating cost savings,

and the customer's investment criteria. Sufficient detail is provided to justify project

implementation.

3.0 OBJECTIVE

The major objective of conducting an energy audit for CTF1 is to find out how

efficiently energy has been used here, and to identify opportunities for improvement.

This requires measurement of the amount of energy used by various systems and

equipment which classified under 3 major end uses which are lighting, air

conditioning and general equipments. For CTF1, only aggregated energy consumption

data, i.e. from electricity bills has been obtained which cover a large group of

equipment. As a result, the energy efficiency of individual system or equipment

would have to be assessed on the basis of estimated energy consumption.

4.0 BUILDING DESCRIPTION

Centre of Teaching Facility 1 (CTF 1) is a place for teaching and learning

centre for Engineering Faculty, Computer Science and Information Technology

Faculty, and Resource Science and Technology Faculty. Completely build around

year 2002 with an area of approximately 12300m2. The building is operating 13 hours

a day from 8 in the morning until 9 in the night, and 5 days a week of operating,

excluding the usage of weekend, and occupies almost 1000 people every day. There

are six seminar room, one lecture hall, 6 toilets, a management office, VIP room and

technician room at the CTF 1. The shape of the building is an oval shape and a

rectangular. The building consists of lower ground floor, ground floor, first floor and

second floor but only ground floor and second floor is occupied for teaching and

learning purposes of which also consisted of two toilets for each level (ground and

3

Page 4: Energy Audit Finale

second floor) and overall six toilets on the building. Each of the seminar room and

lecture theatre (combination of ground and first floor) are air conditioned, special

lighting (excluding toilet, AHU room (lower ground level), and control room, around

the building) and other electrical devices such as computer, microphone, speaker and

etc.

4

Page 5: Energy Audit Finale

5.0 METHODOLOGY

5.1 Work Phases Chart

5

InceptionClarify scope of study

for Energy Audit

Building SelectionConducting Energy Audit for a Building

Preliminary Energy Audit Data

(Walk Through Building)Major Energy ConsumptionMajor end uses Identified as

follow:

General EquipmentsLightingAir conditioning

Data CollectionThree main data available as

follow:

Desktop Data Collection

Field Data Collection Cross checking of load demand data

Completing Missing DataUncompleted data is obtain from Field Measurement

Load Data Logger

Complete Data

Data PresentationEnd-uses load apportioning

using graph/chart

RecommendationIndentified Energy

Saving Measure

Comparison Before and After Energy Savings Measure

Using BEII, LEII, ACEII

Conclusion-Cost Saving Achieved

-Payback period strategy

[Figure] 5.1 Audit Methodology

Page 6: Energy Audit Finale

i. Inception

The study is started with identifying the scope of study for the energy audit.

To understand the requirements for conducting an effective energy audit,

various information related to it are gathered. Most of the information for an

energy audit is obtains from the “Guidelines for Conducting Energy Audit in

Commercial Buildings” and also from the internet.

ii. Building Selection

The building selection for the energy audit is Central Teaching Facilities 1

(CTF 1) of Universiti Malaysia Sarawak. CTF 1 is selected since energy audit

for this building has not yet been developed. For this selection, gross total area

of CTF 1 is 12300m2.

iii. Preliminary Energy Audit

Preliminary Energy Audit is conducted mainly to get know the energy

consumption of CTF 1 based on the historical billing data. Since the electricity

supply of UNIMAS is a centralised system which distributed from the Main

Intake Station (MIS), therefore only electric bills from MIS for the whole

energy consumption of buildings inside UNIMAS is available. To acquire

energy consumption by CTF 1, estimation of cost for various systems and

equipments inside CTF1 is done.

iv. Major Energy Consumption

Most of the buildings in Malaysia consume energy from three major end uses

which identified as air conditioning, lighting and general

equipments/appliances. Similarly, for the energy audit of CTF 1, the major

energy consumption is comprised of these three major end uses.

6

Page 7: Energy Audit Finale

v. Data Collection

Data for the major end uses namely air conditioning, lighting and general

equipments is gathered from the desktop data collection, field data collection,

and cross checking of load demand data. Desktop data collection comprise of

the data obtain from schematic diagrams and layout drawings such as

Electrical, Mechanical and Architectural plan. The field data collection

involved counting and measuring the end uses at CTF 1. Measuring is done

using suitable apparatus such as clamp meter. The field measurement is also

conducted to get missing data which cannot be acquired from desktop data

collection. Cross checking of load data is then prepared to check accuracy of

the data from desktop and field data collection with the load data logger.

vi. Data presentation

Data presentation is considered as the result and analysis for the energy audit

of CTF 1. The whole completed data is concluded in a simple manner in form

of pie & bar chart and graphs. From the charts and graphs, results of data

collection are analysed in order to come out with suitable recommendation.

vii. Recommendation

Recommendation is made to identify few probable energy saving measures

that can be implemented at CTF 1 based on the result and analysis.

viii. Comparison Before and After Energy Savings Measure

Comparison is done between before and after implementing energy saving

measures using computation of Building Energy Index. From here cost

savings for the energy saving measures are determined. If the energy saving

measure required extra financial resources for purchasing new technologies,

the payback period for implementing such measure will also be determined.

7

Page 8: Energy Audit Finale

6.0 ENERGY AUDIT DATA & ANALYSIS

6.1 Building Structure Data

6.1.1 Roof Data

Roof Data- Building Material Sound proof – Special Roof- Colour Light Green- Skylight (YES/NO) No- Skylight Dimension (m x m) -- Insulation (YES/NO) Yes- Total Area (m2) 2087.5- Insulated Area (m2) 2087.5

[Table 6.1] Roof Data

6.1.2 Floor Data

[Table 6.2] Floor Data

SR- Seminar RoomLT- Lecture Theatre

8

Floor Gross Area (m2) Occupied Area (m2) Air Conditioned Area

Ground Floor – Lecture Theatre 683.50 520.53 520.53 – Toilet (LT) 76.22 76.22 - – SR1 270.00 192.00 192.00 – SR2 270.00 192.00 192.00 – SR3 288.00 192.00 192.00 – Toilet (SR) 96.00 96.00 - – Management Office

48.00 48.00 48.00

– Outside 323.00 - -Sub-Total 2054.72 1316.75 1144.53

1st Floor – SR4 270.00 192.00 192.00 – SR5 270.00 192.00 192.00 – SR6 288.00 192.00 192.00 – Toilet (SR) 96.00 96.00 - – Technician Office 48.00 48.00 48.00 – Outside 288.00 - -

Sub-Total 1260.00 720.00 624.00Total 3314.72 2036.75 1768.53

Page 9: Energy Audit Finale

6.1.3 Wall Data

[Table 6.3] Wall data

6.1.4 Room Data[Table 6.4] Room Data

9

Wall DataFacing HEP Facing FK Facing Lake(LT)

Orientation Orientation Orientation

-Material Concrete -Material Concrete -Material Concrete -Colour White -Colour White -Colour White

-Area 1531.2m2 -Area 1178.4 m2 -Area 778.8 m2

-Thickness 115mm -Thickness 115mm -Thickness 115mm -Comments -Comments -Comments

Windows Windows Windows

-Material Glass -Material Glass -Material Glass -Shading Yes -Shading Yes -Shading Yes

-Area 120m2 -Area 65m2 -Area --Shading

coefficient (2)Reflective film

-Shading coefficient (2)

Reflective film

-Shading coefficient (2)

Reflective film

-Overhang (3) No -Overhang (3) No -Overhang (3)

No

-Blinds (3) No -Blinds (3) No -Blinds (3) No-Side reveals(3) No -Side reveals(3) No -Side

reveals(3)No

-Curtains (3) No -Curtains (3) No -Curtains (3) No-Comments on

windows air infiltration

-Comments on windows air

infiltration

-Comments on windows

air infiltrationOutside Door

(Structure)Outside Door

(Structure)Outside Door

(Structure) -Open/Close(4

)Close -Open/Close(4) Close -Open/Close(

4)Close

-Comments on door air infiltration

No infiltration

-Comments on door air infiltration

No infiltration

-Comments on door air infiltration

No infiltration

Page 10: Energy Audit Finale

7.0 SYSTEM EQUIPMENTS DATA

7.1 Lighting Equipment Data

Xperlu print

10

Level Room No./DescriptionNo. of people

Temp [oC] Wall Colour Remarks

G Lecture Theatre 510 24 White/Brown Wall-Absorb Sound

SR1 150 23 White SR2 150 23 White SR3 150 23 WhiteManagement Office 5 21 White

1st SR4 150 23 White SR5 150 23 White SR6 150 23 WhiteTechnician Office 3 21 White

Page 11: Energy Audit Finale

Xperlu print

11

Page 12: Energy Audit Finale

[Figure 7.1] Lighting System and Their Power Consumption (kW)

From the graph, Open Cone Downlight has the highest power consumption

followed by Aluminium Up/Down Lighter, and then Recessed Fluorescent Fitting.

From the table, individual Open Cone Downlight also has the highest power

consumption which is 150 watts. Second and third largest for individual power

consumption are Aluminium Up/Down Lighter and Halogen Downlight with 80 watts

and 50 watts respectively. In terms of amount of lamps that being used, Recessed

Fluorescent Fitting has the highest amount being used which is148, followed by

Mounted Downlight, Aluminium Up/Down Lighter and Open Cone Downlight with

136, 114, and 111 respectively.

12

Mounted Downlig

ht

Aluminium Up/Down Li

ghter

Bare Chan

nel Flu

oresce

nt Fitti

ng Colour 8

4 Tube

Recess

ed Fl

uoresce

nt Fitti

ng

Self C

ontained

Keluar

Sign

PLC La

mp Surfa

ce M

ounted Li

ght F

itting

Surfa

ce M

ounted Li

ght F

itting

Recess

ed M

ounted Downlig

ht

Haloge

n Downlight

PLC Rec

essed

Type D

ownlight

Recess

ed Ty

pe Downlig

ht

PLC Ceil

ing Mounted

Ligh

ting

Open Cone D

ownlight

Haloge

n Downlight

Bare Chan

nel Flu

oresce

nt Fitti

ng Colour 8

4 Tube

PLC Rec

essed

Type D

ownlight

Recess

ed Ty

pe Downlig

ht

Self C

ontained

Essen

tial Lig

ht 0

2

4

6

8

10

12

14

16

18

Kilo

watt

s, kW

Page 13: Energy Audit Finale

7.2 Air conditioning Data

In the analysis of energy consumption for air conditioning system, data

collection for the system itself has been further divided into 5 subsystems which

identified as Air Handling Unit, Split Unit, Chilled Water Supply Fan Coil Unit,

Exhaust Fan Coil Unit and Chillers Water Pump system. Note that, chillers are not

included in this analysis since the chillers system is a centralised system which is

controlled from MEP.

13

Page 14: Energy Audit Finale

7.2.1 Split Unit Data

Xperlu print

14

Page 15: Energy Audit Finale

7.2.2 Air Handling Unit Data

Xperlu print

15

Page 16: Energy Audit Finale

7.2.2 Air Handling Unit Data

Xperlu print

16

Page 17: Energy Audit Finale

Ground AHU/CTF

1/G/1

Ground AHU/CTF

1/G/2

Ground AHU/CTF

1/G/3

Ground AHU/CTF

1/G/4

First AHU/CTF 1/2F/1

First AHU/CTF 1/2F/2

First AHU/CTF 1/2F/3

Sup-ply Sug-gested

10.92 10.92 10.92 11.73 11.33 11.33 11.33

Sup-ply Actual

18.5 19 17.6 19.9 19.2 20 18.4

Re-turn Sug-gested

25.75 25.75 25.75 27.15 26.05 26.05 26.05

Re-turn Actual

21.8 30.5 23.2 24.7 23.3 23.4 22.9

2.57.5

12.517.522.527.532.5

Tem

pera

ture

, oC

[Figure 7.2] AHU Suggested and Actual Temperature

From the AHU data of CTF1, actual temperature for every AHU differs from

the suggested temperature provided from the M&E drawing. From the graph above,

for suggested temperature, supply air with average temperature of 110C has

significant rise in temperature (approx. 150C) as the air returned back to AHU. On the

other hand, for the actual temperature, supply air with average temperature between

18-200C shows slight changes in temperature increase which is approximately 4-50C.

The main idea for the huge difference between suggested and actual air

temperature handle by AHU is based on the number of occupants accommodated for

every seminar room and the lecture theatre. This is because, the suggested air

temperature is supplied in order to accommodate a seminar room with 150 people and

also assuming that at all time all rooms are occupied, but in actual situation number of

people occupying the room is less than 150 and also there are certain time the rooms

are totally empty.

17

Page 18: Energy Audit Finale

Thus, in actual situation, air temperature only has slight increase when it

return back to AHU since the heat transfer from the people to the air inside the rooms

are much lesser compared with when the room meet it capacity (150 people). Similar

situation also happens in the lecture theatre. In order to deal with actual situation, staff

from MEP has increase the temperature of air into AHU so that the temperature inside

the rooms are in the ideal state and the returned air can be as closed as the suggested

return air.

18

Page 19: Energy Audit Finale

7.2.3 Chilled Water Supply Fan coil Unit

Xperlu print

19

Page 20: Energy Audit Finale

[Figure 7.3] Chilled Water Supply Fan Coil Unit

In CTF1 there are three supply chilled water fan coil unit whereby each has a

power consumption of 72 watts. Total power consumptions for these three units of

chilled water fan coil are 216 watts. Temperature of chilled water in and out for each

room is mostly governed by the number of occupants inside it. For instance in the VIP

room temperature of in and out are nearly the same since the room has no occupants

and it is always closed.

20

FUC/CTF 1/G/1 FUC/CTF 1/G/2 FUC/CTF 1/2F/10

5

10

15

20

25

30

InOut

Tem

pera

ture

, ºC

Page 21: Energy Audit Finale

7.2.4 Exhaust Fan Coil Unit

Xperlu print

21

Page 22: Energy Audit Finale

[Figure 7.4] Exhaust Fan Coil Unit

From graph above, power consumption for every fan coil unit are different

with one and another even most of them are from the same brand. This is may be

depend on the amount of the discharge air into the room and may also depend on the

size room along with number of occupants inside the room. The highest power for a

fan coil unit is 740 watts whereas the lowest is 70 watts. Most of the exhaust fan coil

units consume average power ranging between 180 watts and 340 watts. Total power

use by the exhaust fan coil unit is 5480 watts.

22

EF/C

TF 1/G

/1

EF/C

TF 1/G

/2

EF/C

TF 1/G

/3

EF/C

TF 1/G

/4

EF/C

TF 1/G

/5

EF/C

TF 1/G

/6

EF/C

TF 1/G

/7

EF/C

TF 1/G

/8

EF/C

TF 1/1

F/1

EF/C

TF 1/1

F/2

EF/C

TF 1/1

F/3

EF/C

TF 1/2

F/1

EF/C

TF 1/2

F/2

EF/C

TF 1/3

F/1

EF/C

TF 1/3

F/2

EF/C

TF 1/3

F/3

EF/C

TF 1/3

F/4

EF/C

TF 1/3

F/5

EF/C

TF 1/3

F/6

EF/C

TF 1/3

F/70.00

0.10

0.20

0.30

0.40

0.50

0.60

0.70

0.80Ki

low

atts,

kW

Page 23: Energy Audit Finale

7.2.5 Chilled Water Pump

Xperlu print

23

Page 24: Energy Audit Finale

TCHWP/CTF 1/1 TCHWP/CTF 1/2 TCHWP/CTF 1/30

2

4

6

8

10

12

Pow

er, k

W

[Figure 7.5] Chilled Water Pump

Three tertiary pumps are used to drive chilled water from the Mechanical and

Electrical Plant (MEP) into the air-conditioning system inside CTF1. Total power

consumptions by these pumps are 27500 watts.

24

Page 25: Energy Audit Finale

7.3 General Equipments Data

Xperlu print

25

Page 26: Energy Audit Finale

Computer

Printer

Sound Sy

stem Lift

Projec

tor

Vending M

achine

Wate

r Disp

enser

0

2

4

6

8

10

12

14

16

Power, kW

General Equipment

Tota

l Pow

er, k

W

[Figure 7.6] General Equipment

26

Page 27: Energy Audit Finale

8.0 RESULT

8.1 Percentage of Energy Consumption

End Uses Description

Total Energy (kW)

Percentage (%)

Total Unit kWH

Lighting Lighting 41.70 30.31 542.10

Air Conditioning

Split Unit 2.52 1.83 32.76AHU 39.50 28.71 513.50

Fan Coil Unit 5.70 4.14 74.10Chilled Water

Pump27.50 19.98 357.50

General Equipments

General Equipments

20.66 15.02 268.58

Total 137.58 100.00 1788.54[Table 8.1] Total of Energy Consumption

Lighting 30.31%

Split Unit 1.83%

AHU 28.71%

Fan coil Unit 4.14%

Chilled Water Pumps 19.98%

General Equipments

15.02%

[Figure 8.1] Percentage of Power/Energy (Electricity) Consumption

Pie chart above shows the overall power/energy (electricity) consumption in

kilowatts for major end uses in CTF1. The Air Conditioning system taken up the

highest percentage with 54.67%, followed by lighting which has 30.31% and lastly

General Equipments with 15.02% of energy consumption. This result also shows that

the CTF1 has almost similar proportion of major end uses energy consumption in

most of unresidential buildings in Malaysia of which having proportion of 60% for air

conditioning, 30 for lighting and 10% for general equipment.

27

Page 28: Energy Audit Finale

8.2 Cost Estimation for Energy Consumption

Cost estimation for a period of a year of CTF1 is established since the

historical billing data cannot be used. This is because historical billing data comprise

the overall electricity consumption for the whole New Campus, UNIMAS whereby

the total electric consumption of CTF1 alone cannot be identified.

Description Total Energy (kW)

Total Unit kWH

TariffTotal

Charge Per Day (RM)

Total Charge Per

Month (RM)

Lighting 41.70 542.10

C2- RM16 for each

kilowatts of maximum

demand per month

667.2 15345.6

Split Unit 2.52 32.76 40.32 927.36

AHU 39.50 513.50 632 14536

Fan Coil Unit 5.70 74.10 91.2 2097.6

Chilled Water Pump

27.50 357.50 440 10120

General Equipments

20.66 268.58 330.56 7602.88

Total 137.58 1788.54 2201.28 50629.44[Table 8.2] Tariff of Electricity

Source: SESCO

28

Page 29: Energy Audit Finale

Estimated proportion of monthly charge for CTF1 from overall charge of New Campus:

[Table 8.3]

Monthly Charge for New Campus Based On 2009

RM50629.44 (5.82%)

RM818652.56 (94.18%)

CTF1Other than CTF 1

29

Month

Monthly Cost in 2009

(RM)

New Campus Average

Jan 814247.75Feb 829370.50

869282

Mac 916059.00Apr 916150.75May 848372.25Jun 794684.25July 930477.75Aug 920568.25Sept 847268.00Oct 947518.00Nov 871395.13

Dec 795272.25

Page 30: Energy Audit Finale

[Figure 8.2] Proportion of Monthly Charge for CTF1 compared to New Campus

8.3 Building Energy Index (BEI)

The degree of energy efficiency of a building is normally measured and

compared in Building Energy Index (BEI). The BEI is expressed in total energy used,

which is normally the total kWH of electricity per square metre per annum

(kWh/m2/year) of the building's net area. An energy efficient building should aim for

a lower BEI. In Malaysia, the recommended BEI of an energy efficient building is

from 200-250 kWh/m2/year.BEI for CTF1 is determined as follow:

DescriptionTotal Unit,

kWH Area of CTF1, m2Energy consumption,

kW/m2/yr PercentageLighting 542.10 12300 112.30 30.31

Split Unit 32.76 12300 6.79 1.83

AHU 513.50 12300 106.36 28.71

Fan Coil Unit 74.10 12300 15.35 4.14

Water Pump 357.50 12300 74.06 19.98

General Equipment 268.58 12300 55.64 15.02

Total 1788.54 370.50 100.00[Table 8.4] Building Energy Index of CTF1 (BEI)

BEI = 1788.54kWh÷12300m2 ÷( 1196 ×13 )yr

= 370.50kWh/m2/yr.

30

Page 31: Energy Audit Finale

8.4 Estimated Emission of Carbon Dioxide (CO2) from CTF1

Estimated emission of Carbon Dioxide (CO2) from CTF1 is done as part of

assessing amount of CO2 released from energy/electricity usage from the various

systems in CTF1. Beside this estimation is done to address nowadays issue such as

global warming. Global warming, as we know has become a matter of great concern

worldwide. One of the major contributors to the problem is uncontrolled release of

global warming agent, carbon dioxide (CO2).The harmful CO2 which is also a

greenhouse gas which released into the atmosphere each time the power plant

generate electricity.

One of the ways to address this issue is by building innovative sustainable

buildings or buildings that use energy efficiently. Efficient use of energy will reduce

the rate of harmful CO2 emission and contribute towards a better environment.

Buildings are responsible for approximately 40% of the greenhouse gas emission into

the environment due to the embodied energy used during its construction and

operation. The longer its lifespan, the higher accumulated energy is used and more

CO2 is released into the atmosphere.

31

Page 32: Energy Audit Finale

CO2 emission of CTF1 is determined as follow:

32

Electricity Audit CalculatorColumn A Column B Column C Column D Column E Column F Column G Column H Column I Column J Column K Column L Column M

EquipmentNumber of

itemsAverage

Wattage (w)

Hours in use per

day

Number of days in use per

year

kWh used per day

kWh used per year

Average Wattage on stand-

by (w)

Hours on stand-by per day

Number of days on stand-by during a

year

kWh left on stand-

by per day

kWh left on stand-

by per year

Total kg CO2 per

year for this item

Mounted Downlight 136 13 13 196 23 4505 0 0 4811Aluminium Up/Down Lighter 114 80 13 196 119 23238 0 0 24818Bare Channel Fluorescent

Fitting Colour 84 Tube 62 18 13 196 15 2844 0 0 3037Recessed Fluorescent Fitting 148 36 13 196 69 13576 0 0 14499

Self Contained Keluar Sign 32 13 13 196 5 1060 0 0 1132PLC Lamp Surface Mounted Light Fitting 68 13 13 196 11 2252 0 0 2406

Surface Mounted Light Fitting 6 18 13 196 1 275 0 0 294Recessed Mounted Downlight 96 18 13 196 22 4403 0 0 4702

Halogen Downlight 15 50 13 196 10 1911 0 0 2041PLC Recessed Type Downlight 57 18 13 196 13 2614 0 0 2792

Recessed Type Downlight 12 26 13 196 4 795 0 0 849PLC Ceiling Mounted Lighting 4 13 13 196 1 132 0 0 142

Open Cone Downlight 111 150 13 196 216 42424 0 0 45309Halogen Downlight 15 50 13 196 10 1911 0 0 2041Bare Channel Fluorescent

Fitting Colour 84 Tube 19 18 13 196 4 871 0 0 931PLC Recessed Type Downlight 57 18 13 196 13 2614 0 0 2792

Recessed Type Downlight 12 26 13 196 4 795 0 0 849Self Contained Essential Light 1 13 13 196 0 33 0 0 35

AHU/CTF 1/G/1 1 4000 13 196 52 10192 0 0 10885AHU/CTF 1/G/2 1 4000 13 196 52 10192 0 0 10885AHU/CTF 1/G/3 1 4000 13 196 52 10192 0 0 10885AHU/CTF 1/G/4 1 11000 13 196 143 28028 0 0 29934AHU/CTF 1/2F/1 1 5500 13 196 72 14014 0 0 14967AHU/CTF 1/2F/2 1 5500 13 196 72 14014 0 0 14967AHU/CTF 1/2F/3 1 5500 13 196 72 14014 0 0 14967XFU/CTF 1/G/1 1 1260 13 196 16 3210 0 0 3429

XCU/CTF 1/G/1 1 1260 13 196 16 3210 0 0 3429FUC/CTF 1/G/1 1 72 13 196 1 183 0 0 196FUC/CTF 1/G/2 1 72 13 196 1 183 0 0 196FUC/CTF 1/2F/1 1 72 13 196 1 183 0 0 196EF/CTF 1/G/1 1 340 13 196 4 866 0 0 925

EF/CTF 1/G/2 1 340 13 196 4 866 0 0 925

EF/CTF 1/G/3 1 340 13 196 4 866 0 0 925

EF/CTF 1/G/4 1 340 13 196 4 866 0 0 925

EF/CTF 1/G/5 1 180 13 196 2 459 0 0 490

EF/CTF 1/G/6 1 70 13 196 1 178 0 0 190

EF/CTF 1/G/7 1 360 13 196 5 917 0 0 980

EF/CTF 1/G/8 1 180 13 196 2 459 0 0 490

EF/CTF 1/1F/1 1 740 13 196 10 1886 0 0 2014

EF/CTF 1/1F/2 1 180 13 196 2 459 0 0 490

EF/CTF 1/1F/3 1 180 13 196 2 459 0 0 490

EF/CTF 1/2F/1 1 180 13 196 2 459 0 0 490

EF/CTF 1/2F/2 1 250 13 196 3 637 0 0 680

EF/CTF 1/3F/1 1 370 13 196 5 943 0 0 1007

EF/CTF 1/3F/2 1 370 13 196 5 943 0 0 1007

EF/CTF 1/3F/3 1 370 13 196 5 943 0 0 1007

EF/CTF 1/3F/4 1 180 13 196 2 459 0 0 490

EF/CTF 1/3F/5 1 180 13 196 2 459 0 0 490

EF/CTF 1/3F/6 1 180 13 196 2 459 0 0 490

EF/CTF 1/3F/7 1 180 13 196 2 459 0 0 490TCHWP/CTF 1/1 1 11000 13 196 143 28028 0 0 29934TCHWP/CTF 1/2 1 11000 13 196 143 28028 0 0 29934TCHWP/CTF 1/3 1 5500 13 196 72 14014 0 0 14967

Computer 12 102 13 196 15.912 3118.752 35 3 46 1 58 3393Printer 3 70 13 196 2.73 535.08 15 3 46 0 6 578

Sound System 7 115 13 196 10.465 2051.14 17 3 46 0 16 2208Lift 1 15000 13 196 195 38220 500 11 166 6 913 41794

Projector 7 300 13 196 27.3 5350.8 35 3 46 1 34 5751Vending Machine 1 420 13 196 5.46 1070.16 42 11 166 0 77 1225Water Dispenser 1 900 13 196 11.7 2293.2 70 11 166 1 128 2586

Total 1789 350620 9 1232 375778

Page 33: Energy Audit Finale

[Table 8.5] CO2 Emission of CTF1

9.0 RECOMMENDATIONS

Energy saving measure can be performed without additional cost should be

implemented immediately. Items such as filter schedule changes and lighting control

scenarios lead the list of non-capital items that will improve building performance.

9.1 Lighting

Lighting must be providing a suitable visual environment within a particular

space, for example; sufficient and suitable lighting for the performance of a range of

tasks and provision of a desired appearance. Based on our study for CTF 1 building,

the total of electricity/energy consumption for lighting system is 41.7kW. Therefore,

our team strongly recommends using of more efficient lamp/ballast systems and

luminaires. The fluorescent ballast loss shall not exceed 6.0 W. The maximum of

lighting power must be 15W/m2, for each of seminar room (SR 1 – 6) and lecture hall.

Luminaires shall be selected for efficient distribution of light without producing

discomfort glare. Therefore, we recommend that for each seminar room, lecture hall

must use 300 – 500 illuminance (LUX), for office is 300 – 400 illuminance (LUX),

toilet and lift, 100 illuminace (LUX).

Manual switch control lighting should be provided for each room to minimize

the usage of indoor electrical power on lighting. If a room was not occupied, the room

light, computer, projector and all electrical devices must be switch off by the

technician in charge, so that, the power consumption of lighting and other electrical

devices can be reduced and can extend the bulb and other electrical devices lifetime.

Besides that, install more reflective mirrors as it can reduce the amount of bulb usage.

By combining the bulb and the reflective mirror, more lighting areas can be cover and

more efficient compare to a bulb only/change each bulb with low power.

33

Page 34: Energy Audit Finale

For exterior lighting, it is suggestible to install an automatic switch. This is to

prevent any wasted power by switch on the light during days as there is no need to

switch on the light because there is a day light at outside CTF 1. The light will be

automatically switched on when it is dark/night.

9.2 Air-conditioning and mechanical ventilation (ACMV) system

Room comfort condition is dependent on various factors including air

temperature, mean radiant temperature, humidity, clothing, metabolic rate and air

movement preference of the occupant. From the AHU data of CTF1, the actual

temperature, supply air with average temperature between 18-200C shows slight

changes in temperature increase which is approximately 4-50C.

Therefore, for air-conditioning and mechanical ventilation system we

recommend to install at least one thermostat for the regulation of temperature in each

room. Each thermostat should be capable of being set by adjustment or selection of

sensors over a minimum range of between 22 °C to 27 °C, to control the temperature

in the room. Multi-stage thermostat should be provided for equipment exceeding

35/65 kWh.

Besides that, we also recommend for each system should be equipped with a

readily accessible means of shutting off or reducing the energy used during periods of

non-use or alternate uses of the building spaces or zones served by the system such as

manually adjustable automatic timing devices. Not all seminar room was occupied at

the same time, therefore it is really important to install the manually adjustable

automatic timing devices. Just on the system when the room is occupy only.

34

Page 35: Energy Audit Finale

It is recommended that consideration be given to the use of recovery systems

which will conserve energy (provided the amount expended is less than the amount

recovered) when the energy transfer potential and the operating hours are considered.

Recovered energy in excess of the new source of energy expended in the recovery

process may be used for control of temperature and humidity. Examples include the

use of condenser water for reheat, desuperheater heat reclaim, heat recovery wheel,

heat pipe or any other energy recovery technology.

For the mechanical ventilation system, each mechanical ventilation system

(supply and/or exhaust) should be equipped with a readily accessible switch or other

means for shut-off or volume reduction when ventilation is not required. Examples of

such devices would include timer switch control, thermostat control, duty cycle

programming and CO/CO2 sensor control.

Installation of an automatic door at the main entrance and shut permanently

back door of the room will reduced the air leakage of the room as at certain time, the

door always open even though it is supposedly close. Use the back door only if got

any emergency happen.

9.3 Other

For other electrical devices such as microphone, computer, projector, speaker,

and etc, it is advisable to turn off when the device is not used. The technician must

make sure that this equipment is properly used. It is better if this entire device was

control by a switch so that the device use according to its need.

35

Page 36: Energy Audit Finale

10.0 CONCLUSION

Based on data completion, electricity/energy consumption in kilowatts for

lighting system is 41.7kW, air-conditioning system is 83.79kW, and general

equipment is 20.66kW. The percentages of electricity/energy consumption for these

three aspects are 30.31%, 59.93% and 15.02% respectively.

To minimized the usage of the power in CTF 1, it is recommend to implement

energy saving measures in the building so that, it will create an awareness among the

user of the building on how to manage the energy usage in the building such as

lighting, aircond, and etc., efficiently.

REFERENCES

Yik, F. W. H, et al. (2001). A Detailed Energy Audit for Commercial Office Building

in Hong Kong. Hong Kong Institution of Engineers, 5(3).

California Energy Commission. (2000). How To Hire An: Energy Auditor To Identify

Energy Efficiency Projects. California.

CEC (2000). “Guide to Preparing Feasibility Studies of Energy Efficiency Projects,”

Report P400-00-002, California Energy Commission.

Milan, C. B. (2002). “A Guidebook for Preparing Walk-Through Energy Audits of

Industrial Facilities,’ Bonneville Power Administration,

http://www.bpa.gov/Energy/N/reports/audit/index.shtml.

SESCO (2010). Electricity Tariff of Commercial Bulding. Retrieved from

http://www.sesco.com.my/sesco/english/tariff/html

36

Page 37: Energy Audit Finale

APPENDICES

Energy Audit Pictures:

37

Auditor inside the Lift Motor Room AHU Room

Aluminium Up/Down Lighter Mounted Downlight

Recessed Fluorescent Fitting PLC Lamp Surface Mounted Light Fitting