gbghnhn

Upload: darshan-raghu

Post on 04-Jun-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/13/2019 gbghnhn

    1/6

    IEEE TRANSACTIONS ON SMART GRID, VOL. 4, NO. 1, MARCH 2013 353

    Advanced Power Distribution System Configurationfor Smart Grid

    Jae-Chul Kim, Member, IEEE, Sung-Min Cho, Member, IEEE, and Hee-Sang Shin

    AbstractPower distribution systems should meet demandssuch as high reliability, efficiency, and penetration of renewableenergy generators (REGs) in a smart grid. In general, power dis-

    tribution systems are radial in nature. One-way power flow is theadvantage of a radial system. However, the introduction of REGs

    causes bidirectional power flow. Furthermore, there are limitsto improvements in reliability and efficiency in a radial system.Therefore, the upgrading of primary feeders from a radial to aloop configuration has been considered in the Korea Smart Distri-

    bution Project. An advanced power distribution system (APDS),

    in which primary feeders operate in a loop configuration, has beenexplored in this paper. First, the design scheme of a conventionalpower distribution system configuration that adopts distribution

    automation is introduced. Subsequently, an upgrading scheme ofloop configuration using normally opened tie switches and a tie

    switch selection algorithm for loss minimization are described.

    Finally, the advantages of the upgraded configuration are reportedthrough case studies. It is observed that the APDS configurationcan integrate more REGs from the viewpoint of voltage regulation.An advanced distribution system allowing greater use of REGswill be a major contribution to smart grid implementation.

    Index TermsPower distribution system configuration, renew-able energy generation, smart distribution, voltage regulation.

    I. INTRODUCTION

    C ONCERNS about global climate change have increasedthe penetration of REGs, which are connected to powerdistribution systems. The Korean government announced a na-

    tional objective to increase the share of REGs, which was 2.24%

    in 2006, to 11% by 2030. In general, power distribution sys-

    tems are radial in nature. In addition, given their relatively late

    development, REGs were not considered in the design phase

    of current power distribution systems. For these reasons, con-

    necting distributed generation units (i.e., REGs) to the distri-

    bution system may cause various interconnection problems in-

    cluding harmonic concerns, system overvoltage, fault coordina-

    tion, increased fault currents, and islanding concerns. To miti-

    gate these problems, the IEEE Std. 1547 for distributed gener-ator (DG) interconnection was published in 2003 [1]. In Korea,

    Manuscript received November 26, 2012; accepted December 09, 2012. Dateof publication February 06, 2013; date of current version February 27, 2013.This work was supported by the Power Generation & Electricity Delivery ofthe Korea Institute of Energy Technology Evaluation and Planning (KETEP)grant funded by the Korea government Ministry of Knowledge Economy (No.2009T100200067). Paper no. TSG-00821-2012.

    S.-M. Cho (corresponding author) is with the Department of Electrical Engi-neering, Soongsil University, Seoul 156-743, Korea (e-mail: [email protected]).

    J.-C. Kim and H.-S. Shin are with the Department of Electrical Engi-neering, Soongsil University, Seoul 156-743, Korea (e-mail: [email protected];[email protected]).

    Digital Object Identifier 10.1109/TSG.2012.2233771

    TABLE ICAPACITYLIMITS OFDG [2]

    KEPCO (Korea Electric Power Cooperation) also published a

    DG interconnection manual in 2005. In this manual, the capacity

    of a DG is limited by the voltage level and line configuration.

    Table I shows capacity limits of a DG [2].

    The main goal of these DG installment limitations is to keep

    the distribution system voltage within a permissible range. In

    Korean power distribution systems, the distribution voltage is

    controlled by an on-load tap changer (OLTC) through the line

    drop compensation (LDC) method. In some cases, the high pen-

    etration of REGs may cause voltage regulation failures [3].

    A fault occurrence in a feeder or lateral that is connectedto an REG leads to its interruption. For stable reclosing oper-

    ation and maintenance crew safety, the REGs must detect is-

    landing operationand be disconnected within 0.5 s according to

    the KEPCO DG interconnecting manual. Furthermore, REGs

    should wait 5 min to re-connect after the distribution system

    becomes stable [1], [2]. Therefore, the reliability of the power

    distribution system is important for REGs as well as for cus-

    tomers.

    For several decades, the configuration of power distribu-

    tion systems has been typically designed in a radial form for

    easy control [4], [5]. However, some power utilities such as

    Taipower, Florida Power Company, Hong Kong Electric Com-

    pany, and Singapore Power have adopted normally closed loop

    configurations to serve their customers with high reliability

    [6][9]. Loop power distribution systems have the advantages

    of reliability and voltage regulation. To accommodate these

    strengths, an APDS including loop configuration is being

    developed in the Korea Smart Distribution System Project.

    In Korea, KEPCO has already adopted a distribution automa-

    tion system (DAS) with many normally opened tie switches to

    improve reliability [10]. Therefore, without feeders or lateral

    extensions, the power distribution system can simply be up-

    graded to an APDS through tie switch closure. However, to op-

    erate in loop configuration, the protection system should be up-

    graded as well. All reclosers and circuit breakers (CBs) in the

    1949-3053/$31.00 2013 IEEE

  • 8/13/2019 gbghnhn

    2/6

    354 IEEE TRANSACTIONS ON SMART GRID, VOL. 4, NO. 1, MARCH 2013

    Fig. 1. Conventional power distribution configuration in KEPCO.

    loop path should detect bi-directional fault currents. Thus, ap-

    propriate tie switches are selected to upgrade the radial configu-

    ration to a loop configuration with the minimum upgrading cost.

    The purposeof this paper is to introduce the advantages of the

    APDS, which is being studied in the Korea Smart Distribution

    Project, and to propose an algorithm for appropriate tie switch

    selection. In section two, the conventional power distribution

    system in Korea is described. The basic scheme of an APDS and

    the algorithm for tie switch selection are introduced in section

    three. In section four, the advantages of the APDS are examined

    through a case study.

    II. CONVENTIONALPOWERDISTRIBUTIONCONFIGURATION

    A. Design Scheme Which Considers Reliability

    The DAS is very useful for reliability enhancement. To min-

    imize interruption time, KEPCO has adopted the DAS for de-termination of fault location, fault isolation, and service restora-

    tion. A conventional power distribution configuration adopting

    the DAS is shown in Fig. 1.

    In the figure, CB, RA, and GA are substation circuit breakers,

    automatic reclosers, and remote-controlled switches, respec-

    tively. Distribution feeders are normally divided into three

    sections. Each section has one or more normally opened tie

    switches for service restoration. For example, if a fault occurs

    in section two as illustrated in Fig. 2, automatic equipment de-

    vices which experience a fault current generate a fault indicator

    (FI) signal within 30 s. At the same time, RA1 is opened to clear

    the fault. Subsequently, by considering the FI message, thefault location is determined. Next, GA3 and GA4 are opened to

    isolate the fault. Finally, RA1 and GA10 or GA6 are closed for

    service restoration. As these processes are completed within 5

    min, the DAS is very useful in improving reliability. However,

    because the REG interconnected in section three experiences

    momentary interruptions, it should be disconnected within 0.5

    s by an anti-islanding detection function. Furthermore, the

    REGs should wait 5 min to re-connect after service restoration

    is complete [2], [10] .

    In the conventional power distribution system, a service

    restoration scheme using normally opened tie switches is useful

    for minimizing interruption time. However, REG operation is

    sensitive to momentary interruptions due to anti-islanding de-

    tection. Therefore, the service restoration process in an APDS

    Fig. 2. Diagram of a conventional LDC voltage regulation method.

    Fig. 3. Diagram of a conventional LDC voltage regulation method.

    should reduce momentary interruptions to assure continuous

    operation of REGs.

    B. Voltage Regulation Scheme

    Power utilities are required to keep customers voltage pro-

    files on feeders close to therated value under all load conditions.

    In urban areas, the power transformer located in the substation

    with an under-load tap changer (ULTC) is the main voltage reg-

    ulation equipment. Pole-mounted voltage regulators (PVRs) are

    additionally installed in rural feeders. A ULTC controlled by the

    LDC method is used to keep the voltage constant at a fictitious

    regulation point (FRP) regardless of the magnitude or power

    factor of the load. Sending currents and voltages , as

    shown in Fig. 3, are used to calculate the FRP voltage according

    to (1). The power distribution system operator should set up pa-

    rameters such as dead band, time delay, reference voltage, resis-tance , and reactance for automatic voltage regulation

    [3][5].

    (1)

    where

    Fictitious regulation point (FRP) voltage.

    Sending voltage.

    Sending current.

    Resistance of a feeder from ULTC to FRP.

    Reactance of a feeder from ULTC to FRP.

  • 8/13/2019 gbghnhn

    3/6

    KIMet al.: ADVANCED POWER DISTRIBUTION SYSTEM CONFIGURATION FOR SMART GRID 355

    In Korean power distribution systems, a power transformer

    bank has 6 to 8 feeders. The voltage of the feeders depends on

    the ULTC at the power transformer. If the load imbalance be-

    tween feeders exceeds an acceptable range, voltage regulation

    using only ULTC may fail. Furthermore, if many REGs are con-

    nected to the feeders, LDC detects sending currents that are less

    than the actual values. The output of REGs depends on weather

    conditions such as wind, solar radiation, and temperature, and is

    therefore uncontrollable. For this reason, it becomes more diffi-

    cult for the distribution system operator to predict the load bal-

    ance in advance as the penetration of REGs increases. There-

    fore, high penetration of REGs may cause voltage regulation

    failures [3].

    III. ADVANCEDPOWERDISTRIBUTIONCONFIGURATION

    A. Basic Scheme

    The configuration of a conventional power distribution

    system is radial because of its simplicity. However, as men-tioned above, the upgrading of primary feeders is needed

    because there are numerous problems for a radial structure to

    accommodate many REGs. In Korea, primary feeders have

    at least three normally opened tie switches. By closing the

    opened tie switches, the radial distribution configuration can

    be upgraded to a loop structure without installing additional

    electric power lines. Fig. 3 shows the upgrading scheme of an

    ADPS, which includes a loop feeder structure as an example.

    If tie switch GA4 is closed, feeder1 and feeder2 form a loop

    structure. In this case, other tie switches should be opened to

    avoid a mesh structure. Although additional electric power

    lines do not need to be installed, the protection devices shouldbe upgraded to operate the power distribution system in a

    loop structure. Therefore, the optimum tie switches should be

    selected to maximize the profits of ADPS upgrading for the

    loop structure.

    B. Loop Configuration Selection Algorithm for Loss

    Minimization

    Load imbalance between feeders increases loss in the power

    distribution system. In a radial structure, network reconfigura-

    tion is used for load imbalance alleviation, loss minimization

    and others [11]. However, in a loop structure, a loop path con-

    necting a heavily loaded feeder and a lightly loaded feeder canalleviate the load imbalance to minimize loss.

    The voltage drop in a heavily loaded feeder is larger than that

    in lightly loaded feeders. Therefore, by considering the voltage

    across the opened tie switch, we can infer which side of the

    tie switch is the heavily loaded feeder. If the voltage across an

    opened tie switch is high, loop operation using the tie switch

    is more effective for loss minimization. Therefore, we present

    a loop path selection algorithm using the voltage across open

    tie switches. The loop path selection algorithm considers a 24 h

    load profile because the output is for representing stable rather

    than temporary states. A flowchart of the loop path selection

    algorithm for loss minimization is shown in Fig. 4.

    The loop path selection algorithm is as follows.

    Step 1) Generate tie switch cases for loop configuration.

    Fig. 4. Flowchart of loop path selection algorithm for loss minimization.

    Step 2) Carry out powerflow analysis for 24 h.

    Step 3) Calculate accumulated switch voltage (ASV) for all

    tie switches according to (2).

    (2)

    where

    Tie switch number.

    Hours.

    Open voltage of switch n at hour h.

    Step 4) If all ASV calculations for tie switches are com-

    pleted, calculate the total ASV according to (3) for

    each case.

    (3)

    Step 5) Select the case with the maximum total ASV for loss

    minimization.

    IV. CASESTUDY

    In this section, we compared the conventional radial structure

    and the APDS loop structure to explore the advantages of the

    APDS from the perspective of loss reduction and voltage profile.

    The conventional Korean power distribution system adopting

    the DAS, which is shown in Fig. 5, is used as the test distribu-

    tion system model [12]. In the test model, there are four feeders

    and six normally opened tie switches. There are three available

    cases for upgrading the primary feeder from a radial to a loop

    configuration. All test cases are summarized in Table II. Case 1

  • 8/13/2019 gbghnhn

    4/6

    356 IEEE TRANSACTIONS ON SMART GRID, VOL. 4, NO. 1, MARCH 2013

    Fig. 5. Conventional Korea power distribution system adopting DAS.

    TABLE IITEST CASES FORCASESTUDY

    Fig. 6. Load profile of each feeder in the test distribution system model.

    involves a radial structure and cases 2, 3, and 4 involve a loop

    structure.

    Each feeder supports electric power of various loads for res-

    idential, commercial, and industrial customers. Most load pro-

    files depend on the type of customer. Fig. 6 shows feeder load

    profiles in the test model. Feeder 3 shows a relatively light load

    throughout the day. Alternatively, feeders 1 and 2 show a heavy

    load. The load profiles are derived from actual load patterns in

    Korea.

    Fig. 7. Losses during 24 h in the test distribution system model.

    A. Loss Reduction Study

    Powerflow analysis was performed for loss analysis using the

    cases summarized in Table II. Fig. 7 shows the losses accumu-

    lated during 24 h for each case. Upgrading to case 3, in which

    the loss is reduced from 6.74 to 6.42 MWh, is the best solution

    for loss minimization. However, to compare loss reduction be-

    tween cases, powerflow analysis should be conducted for eachcase. Yet if there are more tie switches, the processing time will

    increase. Therefore, to compare loss reduction more efficiently,

    we applied the proposed loop path selection algorithm to test the

    power distribution system model. In the radial case, the ASVs

    for each tie switch calculated by (2) are shown in Fig. 8.

    The total ASVs for each case are summarized in Table III.

    The total ASV is highest in case 3. Therefore, this case is the

    best loop-upgrading solution for loss minimization. This shows

    that we can select a loop-upgrading path without conducting

    powerflow analysis for each case.

    B. Voltage Control Study

    Voltage regulation in the test power distribution system

    model mainly depends on ULTC control by the LDC method.

  • 8/13/2019 gbghnhn

    5/6

    KIMet al.: ADVANCED POWER DISTRIBUTION SYSTEM CONFIGURATION FOR SMART GRID 357

    Fig. 8. ASV for each tie switch.

    TABLE IIICALCULATEDTOTAL ASV

    Fig. 9. Maximum and minimum voltage profiles for case 1 and case 3.

    Maximum and minimum voltage profiles for cases 1 and 3 arecompared in Fig. 9. The difference between the maximum and

    minimum voltages for case 3 is narrower than that for case 1

    (radial). Therefore,voltage regulation is easier in case 3.

    The voltage regulation of power distribution systems in

    which many REGs are interconnected may fail. Therefore, we

    compared the robustness of voltage regulation between cases

    1 and 3. The REGs were interconnected at line sections F25,

    F36, and F414, respectively. Subsequently, we changed the

    generation capacity from 1 to 10 MW. The maximum and

    minimum voltages in the test power distribution system are

    shown in Fig. 10. In case 1, undervoltage occurred because

    the LDC method failed as a result of the 24 MW generated bythe REGs. In contrast, in case 3, the power distribution system

    could accommodate the 30 MW generated by the REGs within

    a permissible voltage range.

    V. CONCLUSION

    In this paper, we analyzed the advantages of an APDS loop

    structure from the perspective of loss reduction and voltage reg-

    ulation. In addition, we presented a loop path selection algo-

    rithm for loss minimization. The results of case studies using

    the test power distribution system are summarized as follows:

    1) Appropriate upgrading of primary feeders from a radial to

    a loop configuration reduces loss in the power distribution

    system

    Fig. 10. Maximum and minimum voltages with REGs of case 1 and case 3.

    2) The robustness of voltage regulation in the loop structure

    allows the APDS to accommodate more REGs than the

    radial structure.

    3) The proposed loop path selection algorithm gives the best

    solution for loss minimization using only a power flow

    analysis of the radial system.

    Coordination of protection using communication technology

    may permit the upgrading of primary feeders from radial to loop

    configurations. We expect the APDS presented here to support

    a more suitable environment for high penetration of REGs in

    smart grids.

    APPENDIX

    The line impedance and load profiles of the test power dis-

    tribution system used in the case study are listed in Tables IV

    and V, respectively. All per units are based on 22.9 kV and 100

    MVA. All power factors are 0.9.

    TABLE IVLINE IMPEDANCE

  • 8/13/2019 gbghnhn

    6/6

    358 IEEE TRANSACTIONS ON SMART GRID, VOL. 4, NO. 1, MARCH 2013

    TABLE VAVERAGE LOAD AT END OFLINE SECTION

    REFERENCES

    [1] IEEE Standard for Interconnecting Distributed Resources With Elec-tric Power Systems, IEEE Std. 1547-2003.

    [2] Korea Electric Power Co.,A Guide to the Distributed Generation In-terconnection to Distribution System 2005.

    [3] J.-H. Choi and J.-C. Kim, Advanced voltage regulation method ofpower distribution systems interconnected with dispersed storage andgeneration systems (Revised), IEEE Trans. Power Del., vol. 16, no.2, pp. 329334, Apr. 2001.

    [4] T. A. Short, Electric Power DistributionHandbook. Boca Raton, FL,USA: CRC, 2004.

    [5] T. Gonen, Electric Power Distribution System. New York, NY, USA:McGraw-Hill, 1986.

    [6] B. Pagel, Energizing international drive,Transm. Distrib. World, pp.

    1834, Apr. 2000.

    [7] T. C. Yu, Prin ciples and Design of Low Voltage S ystems. Singapore:Byte Power Publ., 1996, pp. 1314.

    [8] W. T. Huang, T. H. Chen, G. C. Pu, Y. F. Hsu, and T. Y. Guo, As-sessment of upgrading existing primary feeders from radial to nor-mally closed loop arrangement, inProc. 2002 IEEE Power Eng. Soc.Transm. Distrib. Conf., pp. 21232128.

    [9] T. H. Chen, W. T. Huang, J. C. Gu, G. C. Pu, Y. F. Hsu, and T. Y. Guo,Feasibility study of upgrading primary feeders from radial and open-loop to normally closed-loop arrangement, IEEE Trans. Power Syst.,vol. 19, no. 3, pp. 13081316, 2004.

    [10] N.-G. James, Robert Wilson, Control and Automation of ElectricalPower Distribution Systems. Boca Raton, FL, USA: CRC, 2006.

    [11] S. M. Cho, H. S. Shin, J. H. Park, and J. C. Kim, Distribution systemreconfiguration consideringcustomer and DG reliability cost,J. Elect.

    Eng. Technol., vol. 7, no. 4, Jul. 2012.[12] H. T. Lee, A study on the reliability analysis of loop power distribu-

    tion systems with microgrid structure, Ph.D. dissertation, Dept Electr.Eng., Soongsil Univ., Seoul, Korea, 2009.

    Jae-Chul Kim (M84) received the B.S. degree from Soongsil University,Korea, in 1979, and M.S. and Ph.D. degrees from Seoul National University,Korea, in 1983 and 1987, respectively.

    He hasbeena professor of ElectricalEngineering at Soongsil University since1988. His research interests include power system reliability, smart distributionsystems, and smart grids.

    Sung-Min Cho(S08M13) received the B.S., M.S. and Ph.D. degrees in elec-trical engineering from Soongsil University, Korea, in 2003, 2008 and 2012, re-spectively.

    Currently, he is a Postdoctoral Researcher with Soongsil University. His re-searchinterests include powersystem reliability, smart distribution systems, anddistributed generation interconnection.

    Hee-Sang Shin received the B.S. and M.S. degrees in electrical engineeringfrom Soongsil University, Korea, in 2007 and 2009, respectively. Currently, heis working toward the Ph.D. degree at Soongsil University Graduate School.

    His research interests include smart distribution systems, and electric railways.