g.barber/peter cooke: mechanical design update imperial 22 july 20041 mechanical update for tracker...

11
1 arber/Peter Cooke: Mechanical Design Update Imperial 22 July 2004 Mechanical Update for Tracker workshop Contents:- New Station Layout Light Guide Map Station Connectors Patch Panel Connectors Progress at Liverpool Assembly Area Fabrication Plan Minimum Pitch

Upload: susan-robertson

Post on 21-Jan-2016

214 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: G.Barber/Peter Cooke: Mechanical Design Update Imperial 22 July 20041 Mechanical Update for Tracker workshop Contents:- New Station Layout Light Guide

1G.Barber/Peter Cooke: Mechanical Design Update Imperial 22 July 2004

Mechanical Update for Tracker workshop

Contents:-

New Station Layout

Light Guide Map

Station Connectors

Patch Panel Connectors

Progress at Liverpool

Assembly Area

Fabrication Plan

Minimum Pitch

Page 2: G.Barber/Peter Cooke: Mechanical Design Update Imperial 22 July 20041 Mechanical Update for Tracker workshop Contents:- New Station Layout Light Guide

2G.Barber/Peter Cooke: Mechanical Design Update Imperial 22 July 2004

New Station Layout

The new station layout has a total of 30 connectors, 10 per view. Each connector has 22 holes instead of the previous 18 but all of these are not used in every connector (this is shown in the light guide map).

Page 3: G.Barber/Peter Cooke: Mechanical Design Update Imperial 22 July 20041 Mechanical Update for Tracker workshop Contents:- New Station Layout Light Guide

3G.Barber/Peter Cooke: Mechanical Design Update Imperial 22 July 2004

Light Guide Map

View ‘X’ 213 Channels

View ‘W’ 213 Channels View ‘V’ 213 Channels

0-21

22-42

43-62

85-10663-84 107-128

191-212

129-150

151-170

171-190

20 20

22 22

21 20

22 22 22 22

0-21

22

22-43

44-65

66-85

22

22

19

86-104

105-126

127-148

149-170

171-192

193-212

20

22

22

22

20

22

20

2222

22

22

19

20

22

22

22

0-1920-41

42-63

64-85

86-107

108-127

128-146

147-168

169-190

191-212

Page 4: G.Barber/Peter Cooke: Mechanical Design Update Imperial 22 July 20041 Mechanical Update for Tracker workshop Contents:- New Station Layout Light Guide

4G.Barber/Peter Cooke: Mechanical Design Update Imperial 22 July 2004

Station Connectors

This is the new Station connector. The re-design will allow for easier assembly of the detector. We still need to carry out light transmission tests on this connector but cannot see any reason why it should perform less efficiently than the previous square connectors

Page 5: G.Barber/Peter Cooke: Mechanical Design Update Imperial 22 July 20041 Mechanical Update for Tracker workshop Contents:- New Station Layout Light Guide

5G.Barber/Peter Cooke: Mechanical Design Update Imperial 22 July 2004

Patch Panel Connectors

This is the 128 way patch panel connector. It is designed to maintain a vacuum in the bore of the cryostatThe 128 channels make it a match for the VLPC cassette. All the routing of the fibres takes place inside the chamber.

Page 6: G.Barber/Peter Cooke: Mechanical Design Update Imperial 22 July 20041 Mechanical Update for Tracker workshop Contents:- New Station Layout Light Guide

6G.Barber/Peter Cooke: Mechanical Design Update Imperial 22 July 2004

Patch Panel

This is the the patch panel model. It is not the definitive model as detailed drawings will be required to mate it to the magnet. This model gives space for 26 connectors, as only 25 are needed the 26th opening can be used for field monitoring services.

Page 7: G.Barber/Peter Cooke: Mechanical Design Update Imperial 22 July 20041 Mechanical Update for Tracker workshop Contents:- New Station Layout Light Guide

7G.Barber/Peter Cooke: Mechanical Design Update Imperial 22 July 2004

Progress at Liverpool

This sequence shows the station mould being produced in the Liverpool workshop

Page 8: G.Barber/Peter Cooke: Mechanical Design Update Imperial 22 July 20041 Mechanical Update for Tracker workshop Contents:- New Station Layout Light Guide

8G.Barber/Peter Cooke: Mechanical Design Update Imperial 22 July 2004

Assembly Area

The area has now been painted and the majority of the assembly equipment moved in. The lighting has been improved and we now need to re-connect the stages and the microscope. It is compared to our old assembly area, ‘quite roomy’, although non of the QA stations are set up yet.

Page 9: G.Barber/Peter Cooke: Mechanical Design Update Imperial 22 July 20041 Mechanical Update for Tracker workshop Contents:- New Station Layout Light Guide

9G.Barber/Peter Cooke: Mechanical Design Update Imperial 22 July 2004

Fabrication Plan

This is an outline of the tasks required to assemble the stations. It needs to be expanded and QA systems put in place. When all is agreed an assembly document can be compiled.

• Receive the planes from Fermilab• Inspect the planes to ensure that they have not been damaged in transit• The fibres are then grouped into ‘sevens’ and rubber sleeves fitted• The plane is then fitted onto the vacuum chuck and aligned• The vacuum chuck is transferred onto the assembly jig• The first plane is glued onto the station and allowed to cure• The second plane is then aligned on the vacuum chuck• The vacuum chuck is transferred onto the assembly jig• The second plane is glued onto the station and allowed to cure• The third plane is then aligned on the vacuum chuck• The vacuum chuck is transferred onto the assembly jig• The third plane is glued onto the station and allowed to cure

Page 10: G.Barber/Peter Cooke: Mechanical Design Update Imperial 22 July 20041 Mechanical Update for Tracker workshop Contents:- New Station Layout Light Guide

10G.Barber/Peter Cooke: Mechanical Design Update Imperial 22 July 2004

Fabrication Plan pt2

• The station will now need the connectors fitted• The centre fibre (this should be marked) is fitted in the correct

position• The fibre bunches are then fitted sequentially into the connectors • When a complete plane is ‘threaded’ the fibres are ‘tidied up’• This plane is then potted using vacuum to pull epoxy through the

holes• This procedure is repeated for the other 2 planes• When the epoxy has cured the station is taken to be diamond

polished• It should now be possible to conduct a series of tests to ascertain

its final quality

This is not exhaustive and will be added to during the coming weeks

Page 11: G.Barber/Peter Cooke: Mechanical Design Update Imperial 22 July 20041 Mechanical Update for Tracker workshop Contents:- New Station Layout Light Guide

11G.Barber/Peter Cooke: Mechanical Design Update Imperial 22 July 2004

Minimum Pitch

These two views show adjacent stations with a pitch of 100mm. It is difficult to assess the bend radius required on the fibres from this model therefore we will need to make a model using the carbon fibre stations and simulating an appropriate thickness where the fibre planes pass over the radius of the station. What the model shows is that it will be very tight