Page 1: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

Ms. Lamis T. Malak, P.E.(NJTA) Mr. Peter T. Kuhne, P.E., PMP (Atkins)

Ms. Malini Swaminathan (Atkins)New Jersey Turnpike Authority

PMINJ ChapterApril 21st Monthly Program 2015

Garden State Parkway

Phase 2

Widening Program

Page 2: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

Garden State Parkway Phase 2Widening ProgramProgram-Wide Coordination

Program Management Institute 2015

April 21, 2015

Page 3: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

Agenda

NJ Turnpike Authority Funding & project selection

Program OverviewGSP Widening MP 30 to 80

GSP Phase 2Widening program

PMBOKKnowledge areas

� Scope� Schedule� Costs� Communication� Risk

34/21/2015

Page 4: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

New Jersey Turnpike Authority Charter and funding

The Garden State Parkway (GSP)and the New Jersey Turnpikewere created by acts of the New Jersey Legislation

The New Jersey Highway Authority (NJHA)was organized in 1952 to build, own, maintain,and operate the GSP

The New Jersey Turnpike Authority (NJTA)was organized in 1948, to build, own, maintain,and operate the NJ Turnpike

44/21/2015

Page 5: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

Organization

NJTA and NJHA consolidated in 2003 and now manage both roads—two of the premiere toll roads in the country

More than 1,900 full-time employees including approximately 65 engineering staff and 30 professional engineers

Manages the $7 billion - 10 year Capital Improvement Program (CIP)

New Jersey Turnpike Authority charter and funding

54/21/2015

Page 6: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

Funding

CIP adopted in 2008

Funded through the sale of revenue bonds

Approval of a two step toll increaseon both roadways

Toll increase implemented to fully fundthe debt service to those bonds

New Jersey Turnpike Authority charter and funding

64/21/2015

Page 7: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

Project identification

GSP Phase 1 was part of the CIP

NJTA expanded the scope of the GSPbecause the Turnpike Widening programand other projects in the CIP came in under budget;

• Phases 2 and 3 were added in 2009 and 2011

Other projects are:

• New Jersey Turnpike widening from interchanges 6 to 9

• Interchange improvements

• Facilities improvements

New Jersey Turnpike Authority charter and funding

74/21/2015

Page 8: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

Bonding

NJTA sold its first bonds in 2009,but not for the total amount of the CIP

The bonding market has not been favorableand NJTA has been tracking its draw downof funds in anticipation of selling more

New Jersey Turnpike Authority charter and funding

84/21/2015

Page 9: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

Program overviewGSP Interchange 30 to 80 Widening

Page 10: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

Interchange 30Somers PointAtlantic County

Interchange 80 Toms RiverOcean County

Phase 1

Bass River MP 51.9

Phase 2

Mullica River MP 49.0

Patcong Creek MP 31.0

Phase 3

Phases implementationGSP Interchange 30 to 80 Widening Program Overview

104/21/2015

Page 11: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

Typical section – median wideningGSP Interchange 30 to 80 Widening Program Overview

Existing

SB NB

SB NB

Proposed

114/21/2015

Page 12: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

Mullica River Bridge

Completed Roadway Widening MP 66.5

Program limits

Counties

Municipalities

New structures

Modified structures

Toll plaza improvement

Acres of wetland impacts

Acres of T&E and critical wildlife habitat impacts

Secondary impacts at Interstate 58 and 69

3

297

7

51

23

14

1

GSP Interchange 30 to 80 Widening Program Overview

124/21/2015

Page 13: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

Mullica River Bridge – East Fascia

Patcong River Bridge – NB Structure Stage 1

Cost estimates

Total program cost

Construction

Utility relocations

Construction supervision

Design

Environmental

ROW acquisition

$900M$900M$900M

$655M

$22M

$69M

$94M

$60M

$1M

GSP Interchange 30 to 80 Widening Program Overview

134/21/2015

Page 14: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

Phase 1 Phase 2 Phase 3 Total MP 30-80

Design $22,000,000 $41,000,000 $31,000,000 $94,000,000

Construction $185,000,000 $275,000,000 $195,000,000 $655,000,000

Construction management $20,000,000 $31,000,000 $18,000,000 $69,000,000

Mitigation & Right-of-Way - - - $61,000,000

Utility relocation $22,000,000

Totals $227,000,000 $347,000,000 $244,000,000 $900,000,000

Costs associated with the Bass River Bridge, Mullica River Bridge and Patcong Creek Bridge are included in the Phase 2 program

Program costsGSP Interchange 30 to 80 Widening Program Overview

144/21/2015

Page 15: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

Construction started

Program historyGSP Interchange 30 to 80 Widening Program Overview

Toll concept planCash vs. cashless analysis

1997 2000 2002 2003 2005 2009

Preliminary engineering & permitting started NJ SHPO deemed

Parkway is a historic corridorProject put on hold to assess impact

Project restarted

Preliminary engineering completedProject put on hold while Authority

reviewed long-range funding and priorities

Project was reactivated – design startedGovernor made completion of 63 to 80

segment a priority (by 2009); Mullica River deck replacement made a priority

154/21/2015

Page 16: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

Environmental consideration/permits timeline

Permitting process initiated in 2003

All permits secured in November 2008

Wetlands mitigation (for 7.7 acres impacts)completed in 2008

Threatened and endangered species mitigation (for 245 acres impacted)completed in 2010

Secondary impacts mitigationongoing

Reforestation mitigationongoing

Public access sitesongoing

GSP Interchange 30 to 80 Widening Program Overview

164/21/2015

Page 17: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

GSP Interchange 30 to 80 Widening Program Overview

Overall schedule

Milepost Limits2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017

1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

Environmental permits

Acquire permits

MP 63-80 Design Construction

MP 30-63 advanced clearing

Design Const

MP48-63 MP30-48 preparation

Design Construction

MP 35 - 48 Design Construction

Mullica River Bridge

Design Construction

Patcong River Bridge

Design Construction

Bass River Bridge

Design Construction

2018

1 2 3 4

Constr. in non regulated areas

Environmental permits expire

174/21/2015

Page 18: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

Phase 2 program GSP Interchange 30 to 63 Widening

Page 19: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

GSP Widening Phase 2 MP 30 to 63

Program needs

Mathis Creek construction MP 50.4

Funding available in 2009• Beneficial construction climate

� Savings in construction costs in Phase I and in the Turnpike Widening

Permit • Flood Hazard Permit

expires June 2013� This permit was issued for

5 years with no extension

• Design completion in less than 2 years

• Construction completion in less than 2 years

194/21/2015

Page 20: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

NJTALamis T. Malak, PE

Senior Highway Engineer

Program ManagerAtkins

P200.136

Michael Baker Jr

58 to 63 Widening

P200.135

The RBA Group Inc

52.5 to 58 Widening

P100.130

Hardesty& Hanover

Bass River Bridge

P200.134

Gannett Fleming Inc

48 to 52.5 Widening

P100.132

LSEA

Patcong Creek Bridge

P200.140

T&M Associates

Permit Construction30.0 to 48.0

Ocean County

GSP Widening Phase 2: MP 30 to 63

Program organization chart

Burlington County Atlantic County

204/21/2015

Page 21: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

GSP Widening Phase 2: MP 30 to 63

Program schedule

Managing to schedule• All flood hazard permits expired June 2013

• Construction should be completed before permit expiration date

214/21/2015

Page 22: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

Design oversight• Set program guidelines

• Provide technical guidance

• Oversee design engineers

• Review all submissions

• Longitudinal utility coordination

• State, county, local coordination

• Coordinate public meetings/hearings

• Environmental consultant coordination

• Conduct geotechnical exploration and testing

Administrative support• Invoice reviews

• Scope change reviews

• Meeting coordination

GSP Widening Phase 2: MP 30 to 63

Program manager - Atkins

224/21/2015

Page 23: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

GSP Widening Phase 2: MP 30 to 63

Program manager’s tasks

Tasks that are under the program manager in Phase 2 ( Based on lessons learned in Phase I)

Longitudinal utility engineering� G4S (formerly Adesta) fiber-optic facilities � AT&T, Verizon, Sprint fiber-optic facilities

Subsurface exploration� All borings and lab testing undertaken by PMT

Advanced clearing from MP 30 to 63� Migratory Bird Treaty Act restrictions on tree clearing

Coordination of MPT & sign layout in Phase A

� Developed program concept for MPT

234/21/2015

Page 24: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

Culvert Widening at MP 34.3

Drainage structures & gradingMP 30.2 TO 47.3 (P200.140)

� Design engineer –T&M Associates

� Contractor – Midlantic Construction

� Contract award – August 2011

� Construction cost - $8,713,399.00

GSP Widening Phase 2: MP 30 to 63

Contracts within phase 2 program

244/21/2015

Page 25: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

Interchange 50 ramp Bridge

GSP Widening MP 47.7 51.3 (P200.134)

� Design engineer – Gannett Fleming Inc.

� Contractor – Midlantic Construction LLC

� Contract award – August 2011

� Construction cost - $50,617,232.00

Contracts within phase 2 programGSP Widening Phase 2: MP 30 to 63

254/21/2015

Page 26: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

Mullica River SB Bridge – rehabilitation

Contracts within phase 2 programGSP Widening Phase 2: MP 30 to 63

Rehabilitation of GSP Bridge overMullica River P100.025 MP 48.5 to 49.7� Design engineer – Parsons Brinckerhoff� Included in contract P200.134 Widening from MP 47.7 to 51.3

264/21/2015

Page 27: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

Contracts within phase 2 program

Widening and rehabilitation of Bass River Bridge MP 51.9� Design engineer – Hardesty & Hanover, LLP� Contractor – Northeast Remsco� Contract award – January 2011� Construction cost - $55,814,955

Bass River Bridge Pier 1 with G1 for Span 1 in forefront

GSP Widening Phase 2: MP 30 to 63

274/21/2015

Page 28: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

Greenbush Road Bridge over GSP

Contracts within phase 2 program

GSP Widening MP 52.4 – 57.8 (P200.135) � Design engineer – The RBA Group

� Contractor – Richard E. Pierson

� Contract award – August 2011

� Construction cost - $46,657,1700

GSP Widening Phase 2: MP 30 to 63

284/21/2015

Page 29: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

Contracts within phase 2 program

GSP Widening MP 57.8 – 64.9 (P200.136) � Design engineer –Michael Baker Jr. Inc.

� Contractor – Earle Asphalt Co.

� Contract award – August 2011

� Construction cost - $52,063,413

Garden State Parkway over Route 72

GSP Widening Phase 2: MP 30 to 63

294/21/2015

Page 30: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

Strategic approach to program management

Need for Strategic Approach� Design and construction of

nearly $300 million worth of improvements to an existing highway while maintaining traffic makes the Garden State Parkway Widening a very complex project

Break down into 4 sections by Authority

Authority retains Program Manager

Control of Budget overruns by adding an “unanticipated services task”

Program Manager assigned Project Managers to oversee individual sections

Identified significant issues� Schedule

� Consistency

� Traffic Control Design

� Design to Permit

GSP Widening Phase 2: MP 30 to 63

304/21/2015

Page 31: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

Strategic approach to program managementGSP Widening Phase 2: MP 30 to 63

Stakeholdercoordination

Aggressive communication with design team

Scope and budget control monthly reviews

Workshops, on-board reviewsstrategic design guidance

Planned for quality guidance for consistent design, reviews for conformance to standards

Developed master plan for traffic control during construction

Team building led by example that end result for Authority was paramount

- Christmas cookies

- Donuts and coffee

- End of project bowl-o-rama

314/21/2015

Page 32: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

GSP Widening Phase 2: MP 30 to 63

PMBOK knowledge areas- Program scope management

- Program cost management

- Program schedule management

- Program communication management

- Program risk management

Page 33: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

Key challenges

ScheduleJune 13, 2013

� Completion before permits expire

Consistency between adjacent projects

� Consistency reviews, monthly program meetings

WeatherDelay by 2 months

� Used existing 10 year old plans at start to offset delay

Coordination of traffic stages with ongoing Bridge projects

� Significant potential for schedule delays and cost increases

Drainage design vs. permits

� Design should be within permit disturbance limits

GSP Widening Phase 2: MP 30 to 63

334/21/2015

Page 34: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

Program scope management

Scope of work for final design developed by Authoritybased on previous projects

High level scope breakdown part of response to RFP

Detailed scope breakdown and tracking of work breakdown structure tasks template provided by program management team

Gathering of scope requirements� Added Value - Lessons Learned

from Phase 1

� As-Built Plans

� Preliminary Design Aerials and Mapping

� Gather other agency requirements (NJDOT, Counties, SESC)

Control scopemonthly review

GSP Widening Phase 2: MP 30 to 63

344/21/2015

Page 35: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

Program scope management

Lessons learned from Phase 1

Barnegat toll plaza Birch Street Bridge

GSP Widening Phase 2: MP 30 to 63

Design Coordination Needs� NJTA staff needs support to manage and

coordinate the multiple projects involved in each phase of the Widening program

� An exclusive website for NJ Turnpike Authority, Program Manager and Section design engineers

MPT� Coordination required in staging

for adjacent contracts. Three roadway Widening contracts and Interchange 67 improvements construction were ongoing simultaneously

� Identical MPT Pay Items Different pay items in adjacent contracts makes RE work complicated

� Construction DetailsFor example - Specific details for construction vehicle access at each stage

354/21/2015

Page 36: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

Cost management

Controlsreview of work vs. costs

Elimination� Removed design work that

was identified for P200.140- Moved the design to Phase 3

Mitigation� Design engineers collaboration

Sharing special details to reduce re-work costs (savings on each design)

� PMT developed detailed advisories to minimize changes

� Construction specs include penalty clause

GSP Widening Phase 2: MP 30 to 63

Acceptance“Unanticipated” line item budget

for designSet aside in funding approval

to address change orders

364/21/2015

Page 37: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

Schedule management

Controlsmonthly schedule reviews

Adjusted design submissions � Allow slack in interim submissions

- Example Moved the MPT submission to a separate item

Assistance to section design consultant� On board monthly review and

mark-ups to keep design schedule

� Sharing special details to reduce re-work costs (savings on each design)

Contract specifications� Interim construction dates

with penalties

� Ongoing stage construction coordination – design and construction

GSP Widening Phase 2: MP 30 to 63

374/21/2015

Page 38: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

Program communication management

Website� One Calendar (all meetings posted)

- Meeting Minutes (Attached to calendar item)

� Submissions and reviews (ERC)� Documents – 40,000 on website alone

Communications management manual� Detailed hierarchy� Website and ERC Layout

Meetings� Monthly Progress meetings

- Program-wide to address common issues -also team bonding

- Meetings to discuss issues/progress of each design

� Public meetings/ hearings� Stakeholder meetings & communication� Design Workshops

GSP Widening Phase 2: MP 30 to 63

384/21/2015

Page 39: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

SUB-FOLDER FOLDER

Boring Contract

MPR (Monthly Progress Reports)Program Meetings

Schedule

Longitudinal Utilities

LIBRARY

Lateral Utilities

MPR (Monthly Progress Reports)Design Meetings Schedule

Correspondence RFI’s Shop Drawings

GSP Widening 52.5 TO 58.0 (CC P200.135)

GSP Widening 58.0 TO 63.0 (CC P200.136)

Permit Related 30.0 TO 48.0 (CC P200.140)

GSP Widening 48.0 TO 52.5 (CC P200.134)

Bass River Bridge(CC P100.130 & P100.131)

Patcong Creek Bridge(CC P100.132)

GSP Widening 30 TO 80 –Program Documents

GSP Widening 63 TO 80

Mullica River Bridge (CC P100.024)

P100.024 Plans Soils RPT

70-75 P200.045 Phase D

75-80 P200.044 Phase C

63-70 P200.046

General Correspondence

Submissions

Geotechnical

Program Reporting

Utility Coordination

Garden State Parkway Widening Interchange 30 – 63 OPS-3243 Program Website Filing Directory

September 21, 2009

ATT As-BuiltsAdesta Existing Fiber Optic As-Builts

NJTA CADD Manual

Swale Data Evaluations

Final Permit Plans Details 8.11.8

PDF Files (.tif)Microstation

Files

Access to

these folders is

restricted

to select

website users

Environmental/Permits

GSP WIDENING 30 TO 63 –PROGRAM MANAGEMENT

(OPS-3243)

Phase A Package

Phase B Package

Phase C Package

Phase D Package

Other Deliverables

MCI As-Builts

Design Documents

Utility Coordination

Construction

Project Procedures

Permits/Environmental

Agreements/MOU’s

Geotechnical

Public Hearing

General Correspondence

Submissions

Program Reporting

Design Components Cost Estimates

Design Element Modification

Reference Material

Reports Specifications

Submission Reviews

Survey & ROW

Environmental Permits & Secured

Documents

Reports

Survey Control Reports

Technical Memoranda

Program Manuals

Existing Utilities

Permit Plans

Swale Data394/21/2015

Page 40: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

Program stakeholder management

NJ DOT and three counties� Separate kickoff meeting with each agency - predesign� Major submissions review and comment� Specifications include agency requirements and contacts

Utilities� Kickoff meeting with utilities � Ongoing coordination� Signed utility agreement listing responsibilities and payment

Federal and state permit agencies� Ongoing coordination – continued from preliminary design� Submission final plans to show compliance� Field meetings to obtain concurrence with design approach� Additional permits obtained where needed� Permit modifications requested where needed

GSP Widening Phase 2: MP 30 to 63

404/21/2015

Page 41: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

Public Outreach

NJTA held the following public activities:

Public hearing for the Widening permit application in January 2007

Three public Information centers in March 2007

Public hearing for Mullica River Bridge construction in October 2007

Public hearing for Phase I in October 2008

Public hearing for Phase 2 in September 2010

Public hearing for tree clearing in August 2011

GSP Widening Phase 2: MP 30 to 63

414/21/2015

Page 42: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

Risk management - schedule risks

Environmental� Wetlands and Flood Hazard permits expire

June 2013 (no extensions)

� Design and construction to adhere to permit impact limitations- Tree clearing between November 1 and March 31

- Snake/turtle incursion protectionduring dormant period

Commitments to Public� Authority was committed to opening three lanes

south of Interchange 63 by Summer 2013

These constraints dictated the schedule for

completion of construction

GSP Widening Phase 2: MP 30 to 63

Diamondback terrapin

Northern pine snake

424/21/2015

Page 43: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

Risk management - schedule risks

Design Schedule� Permit impact limitations

� Coordination of design between Widening sections

� Coordination of design with Bridge projects

� Weather

Construction Schedule� Permit impact restrictions

� Utility relocation

� Coordination between contracts

� Weather

GSP Widening Phase 2: MP 30 to 63

Winter 2009-2010Snow cover prevents survey

434/21/2015

Page 44: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

Risk management – other risks

Utility� Fiber-optic line relocation

� Gas line restrictions

Coordination between contracts� Leads to delays

� Leads to delay claims by adjacent contractor (cost)

Unknown unknowns� Comptroller reviews

(+2 months to design)

� Delay of “letting”

� Severe winter delayed survey at start of design

Geotechnical issues roadway soil conditions

GSP Widening Phase 2: MP 30 to 63

Underlying muck causes long term roadway settlement

444/21/2015

Page 45: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

Convert unknowns to knowns MPT coordination elimination

� Separate contracts let early – P200.140 & P200.159Eliminated permit restrictions for wetlands and tree clearing

� Utility work that can commence early

Mitigation� Construction specs include liquidated damages clause

- For delay by one contractor of adjacent contractor’ s staged work

- For failure to open 3rd lane in southbound direction by summer 2013

- For failure to complete all work within wetlands by permit date

Acceptance� CE team identified workarounds for utility delays

� Authority extended contract completion dates

Risk management strategiesGSP Widening Phase 2: MP 30 to 63

454/21/2015

Page 46: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

Scope Of The ClearingClearing in 2011, completed in anticipation of Parkway Widening from Interchange 30 to 63, included:

� Clearing to accommodate third lane and shoulders, water quality swales and Bridge reconstruction

� Clearing to re-establish the roadside clear zone for safety – “CLEAR ZONE” IS AN UNOBSTRUCTED AREA THAT ALLOWS A DRIVER TO STOP OR REGAIN CONTROL OF A VEHICLE THAT HAS LEFT THE ROADWAY

� Consisted of the clearing, removing and disposal of trees, logs, dead trees, and other vegetation including shrubs

Before clearing

After clearing

Risk management – elimination exampleGSP Widening Phase 2: MP 30 to 63

464/21/2015

Page 47: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

Garden State Parkway - After clearing

Right-of-Way

Southbound Northbound

35’ 35’ 35’ 35’

Garden State Parkway - Before clearing

Right-of-Way

Southbound Northbound

Project results – safety achievedGSP Widening Phase 2: MP 30 to 63

474/21/2015

Page 48: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

Fatal accidents involving trees is most prevalent in the proposed Widening limits than any other area on the GSP.

Fatalities involving trees for the entire GSP during 2001 to 2010 accounted for approximately 30%of all fatalities.

Fatalities Involving Trees Interchange 30 to 80

YearFatalities with tree impacts

Total fatalities

% of total fatalities

2001 11 15 73

2002 3 9 33

2003 4 8 50

2004 12 14 85

2005 4 8 50

2006 5 11 45

2007 5 11 45

2008 4 6 67

2009 3 7 42

2010 2 5 40

2011 0 7 0

2012 0 2 0

2013 2 4 50

2014 1 7 14

Project results – safety achievedGSP Widening Phase 2: MP 30 to 63

484/21/2015

Page 49: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

Results in Phase I – similar results anticipated

GSP Widening Phase 2: MP 30 to 63

Project results – motorist benefits

Summer of 2008 (two-lane section pre-construction)

� 34 southbound incidentsof major delays

� Average length of backup 10 miles

� 28 northbound incidents of major delays

� Average length of backup 11.5 miles

Summer of 2011(three-lane section post-construction)

� 7 southbound incidents of major delays

� Average length of backup 2.9 miles

� All 7 incidents were limited to only Friday or Saturday

� 1 northbound incident of a major delay

� Backup of 14 miles

� This northbound is an anomaly occurred on Sunday, August 14th

at 7 pm linked to an incident initially occurring at Interchange 88

494/21/2015

Page 50: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

Improved evacuation route� With Contra-flow six-lane evacuation route

� Increased capacity - 50%

Extend GSP service life� Improved pavement

� Reduction in vehicles per lane – less wear and tear

� Replaced drainage systems

� Improved signage

� Replaced 50+ years old bridges

Protect wildlife� Installed specially designed permanent terrapin fence

– Prevents migration across parkway pavement

– Prevent accidents – people stopped for turtles

GSP Widening Phase 2: MP 30 to 63

Project results – other

504/21/2015

Page 51: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

Project planning• Avoid winter issues by early

planning – (e.g.- aerial survey by PMT)

• Develop program specific project reporting spreadsheets

• Start schedule issues early

� Right-of-way appraisals early to save 4 months

� SUE investigations under PMT

� GPR to identify underground utilities that are not known to exist

Project execution• Use website to track all file

exchanges

• Streamline system to provide design guidance communication

• Document monitoring of risks

GSP Widening Phase 2: MP 30 to 63

Lessons learned

514/21/2015

Page 52: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

What worked• Program manager to oversee

design

• Website based phase submission reviews

• Early and frequent coordination with other agencies

• Approach to team building

� “Walk the talk” – adversarial approach is out.

� In difficult issues keep the Authority’s needs as prime

� Common goal – successful project delivery is a win for all

� Blame game is out – help when mis-steps occur

• Project Closeout

What did not work• Document management

� More than 40,000 files

� Retrieval is a challenge

� Better naming and filing system is needed for electronic documents

• 3 separate advisory systems

� Tech memos, spec guidelines and design advisories

� Combine all three into one system

� Develop tracking and versioning

• Document monitoring of risks

� Past meeting minutes was used

� Got lucky – formal tracking needed

GSP Widening Phase 2: MP 30 to 63

Lessons learned

524/21/2015

Page 53: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

Summary – schedule and costs

July 2013Construction ongoing – 3 lanes

southbound open at Interchange 63

Planned Actual

Design Completion June 2011 June 2011

Permit Areas Construction

June 2013 June 2013

Open 3 lanes to Traffic Summer 2013Limited areas Summer 2013

Design & Construction Supervision Budget

$60 million $55 million

Construction Budget $190 million $163 million

534/21/2015

Page 54: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

Q&AGarden State Parkway Widening Program Interchange 30 – 63

Page 55: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

GSP Widening Phase 2: MP 63 to 80

Construction progress

Interchange 48

BEFORE AFTER

CONSTRUCTION

554/21/2015

Page 56: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

GSP Widening Phase 2: MP 63 to 80

Construction progress

Other roadway construction shots GSP Bridge over Patcong CreekBridge Widening

564/21/2015

Page 57: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

GSP Widening Phase 2: MP 63 to 80 - Construction Complete

Before and after views

Parkway Southbound MP 57

BEFORE AFTER

574/21/2015

Page 58: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

GSP Widening Phase 2: MP 63 to 80 - Construction Complete

Before and after views

Parkway Southbound MP 52

BEFORE AFTER

584/21/2015

Page 59: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

GSP Widening Phase 2: MP 63 to 80 - Construction Complete

Before and after views

Parkway Southbound MP 61.2

BEFORE AFTER

594/21/2015

Page 60: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

GSP Widening Phase 2: MP 63 to 80 - Construction Complete

Before and after views

Parkway Northbound Stage Road

BEFORE AFTER

604/21/2015

Page 61: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

GSP Widening Phase 2: MP 63 to 80

Construction progress

Roadway construction in P200.135 contract Interchange 63 sign structure erection

614/21/2015

Page 62: Garden State Parkway Phase 2 Widening Program - · PDF fileGarden State Parkway Phase 2 Widening Program. Garden State Parkway Phase 2 Widening Program ... 23 14 1 GSP Interchange

GSP Widening Phase 2: MP 63 to 80

Construction progress

GSP Bridge over Bass River – Pier 1 columns Water quality basin at MP 53.8 NB

624/21/2015