future of renewables in victoria dr jeff washusen marsden jacob associates vpela 30 april 2012

11
M ARSDEN JACOB ASSO CIATES Future of Renewables in Victoria Dr Jeff Washusen Marsden Jacob Associates VPELA 30 April 2012

Upload: lenard-martin

Post on 11-Jan-2016

217 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Future of Renewables in Victoria Dr Jeff Washusen Marsden Jacob Associates VPELA 30 April 2012

MARSDEN JACOB ASSOCIATES

Future of Renewables in Victoria

Dr Jeff Washusen Marsden Jacob Associates

VPELA

30 April 2012

Page 2: Future of Renewables in Victoria Dr Jeff Washusen Marsden Jacob Associates VPELA 30 April 2012

MARSDEN JACOB ASSOCIATES 2

Points for discussion

Comment on the past and future electricity price trajectories and some of the things that are, and will, impact this.

Very brief and high level comparison of the long run costs of current and prospective fossil fuel technologies.

Personal views on past and future directions for “demand side” participation in energy markets and energy production and use.

Most material comes from an Expert Witness statement prepared for the EPA in the Dual Gas VCAT appeal.

Page 3: Future of Renewables in Victoria Dr Jeff Washusen Marsden Jacob Associates VPELA 30 April 2012

MARSDEN JACOB ASSOCIATES 3

Electricity price trajectories Energy production & consumption

10,000

20,000

30,000

40,000

50,000

60,000

Energy - VIC Region (GWh)

Customer Load

SECV AEMO

Energy Sent Out

HighMediumLow

AEMO Forecasts (Energy Sent Out)

Key Observations:

AEMO continued to forecast increased production (until 2012) – even though consumer load has been flat or falling since late 2007.

Change in rate of load growth is unprecedented in my life time.

Page 4: Future of Renewables in Victoria Dr Jeff Washusen Marsden Jacob Associates VPELA 30 April 2012

MARSDEN JACOB ASSOCIATES 4

Electricity price trajectories Maximum summer demand

2,000

4,000

6,000

8,000

10,000

12,000

14,000Maximum Summer Demand - VIC Region (MW)

SECV AEMO

Actual

HighMediumLow

AEMO Forecasts

Key Observations:

AEMO continues to forecast increase in maximum summer demand.

MSD is increasing in volatility due to combination of increasing penetration of AC and variability in extreme summer temperature ON WORKING WEEK DAYS.

The volatility in demand will also be impacted by proliferating Solar PV – although Solar PV seems unlikely to reduce extreme MSD (which typically occurs in late afternoon).

Page 5: Future of Renewables in Victoria Dr Jeff Washusen Marsden Jacob Associates VPELA 30 April 2012

MARSDEN JACOB ASSOCIATES 5

Electricity price trajectories NEM VIC Region demand and

energy

30,000

35,000

40,000

45,000

50,000

55,000

60,000

65,000

70,000

2,000

4,000

6,000

8,000

10,000

12,000Maximum Weekly Demand (MW) VIC

Rolling Annual Energy Sent Out (GWh)

Annual Consumer Load (GWh)

MAX WEEKLY DEMAND (MW)

NEM Start13 Dec 98

BASSLINK Start28 Apr 06

TAS Region Start

29 May 05

QNI commissioned

late 2001

ROLLING ANNUAL ENERGY (GWh)

Key Observations:

Rate of increase in energy production and consumption peaked in late 2007.

Both production and consumption have been falling since 2008.

Even maximum demand growth appears to be stalling – although “spread” is still increasing.

These changes most probably reflect the impact of increasingly demanding mandatory energy efficient measures reinforced by rapidly rising retail electricity price.

Page 6: Future of Renewables in Victoria Dr Jeff Washusen Marsden Jacob Associates VPELA 30 April 2012

MARSDEN JACOB ASSOCIATES 6

Electricity price trajectories NEM VIC Region demand and

energyKey

Observations: “True” base load

has remained flat for the last decade.

This has a major impact on the type of new generation capacity that will be needed in the NEM.

What these plots DO NOT show is that supply capacity has become increasingly flexible. Even brown coal plant now gains commercial benefit from flexible operation.

New capacity will capture value by being both reliable and flexible.

30,000

35,000

40,000

45,000

50,000

55,000

60,000

65,000

70,000

2,000

3,000

4,000

5,000

6,000

7,000

8,000

9,000

10,000

Maximum Weekly Demand (MW) VIC Minimum Weekly Demand (MW) VIC Rolling Annual Consumer Load (GWh) VIC

SYSTEM DEMAND (MW) CONSUMER LOAD ($GWh/y)

Page 7: Future of Renewables in Victoria Dr Jeff Washusen Marsden Jacob Associates VPELA 30 April 2012

MARSDEN JACOB ASSOCIATES 7

Electricity price trajectories NEM VIC Region spot price

$0

$20

$40

$60

$80

$100RAAv RRP ($/MWh) VIC

SKM-LRMC Coal VIC

SKM-LRMC CCGT VIC

12MMAv SPOT PRICE ($/MWh)

NEM Start13 Dec 98

New entrantLRMC range

base load thermal plant

BASSLINK Start28 Apr 06

TAS Region Start

29 May 05

QNI commissioned

late 2001

Key Observations:

Spot price is extremely volatile, with annual average changes in excess of 100% - both up and down.

Since the mid-1990s, annual average spot price has only been close to (estimated) long-run marginal cost for new base load thermal plant in 2 years.

No irrational investors exist in the market.

The extreme volatility and (low) range in annual average spot price is a challenge for any new entrant investor – “old fuel” or renewable.

Page 8: Future of Renewables in Victoria Dr Jeff Washusen Marsden Jacob Associates VPELA 30 April 2012

MARSDEN JACOB ASSOCIATES 8

Electricity price trajectories NEM VIC Region futures contract

price

$20

$30

$40

$50

$60

$70

$80

$90

$100

$/M

Wh

RAAv RRP ($/MWh) VIC

CAL12 - Base VIC

CAL13 - Base VIC

CAL14 - Base VIC

Range CAL 07

Range CAL 08

Range CAL 09 Range

CAL 10

RangeCAL 11

Key Observations:

Futures contract prices are (almost) as volatile as annual average spot price.

Futures prices are impacted by forecast conditions – such as shortage of water during the prolonged drought.

Futures prices also appear to be impacted by spot market “sentiment”.

Impact of carbon price was impossible to gauge in late 2011 – and is likely to remain so until after next Federal election.

Page 9: Future of Renewables in Victoria Dr Jeff Washusen Marsden Jacob Associates VPELA 30 April 2012

MARSDEN JACOB ASSOCIATES 9

Comparison of fossil fuel costs

$0

$25

$50

$75

$100

$125

ACIL 2010 ACIL 2010 ACIL 2010 DG Proposal EPA Approval

E Class OCGT E Class CCGT IGCC-Brown Coal IDGCC

CAPEX Fixed Cost Fuel cost Variable Other Carbon Cost

Estimated Levelised Cost of Electricity ($/MWh Sent Out)Key

Assumptions: Gas $5.00/GJ

Coal $4.20/t

Carbon price $23/t

Public domain unit capex costs for OCGT, CCGT and IGCC.

Indicative Dual Gas unit capex for IDGCC.

$150M Government subsidy for IGCC & IDGCC.

30 year analysis.

10% Discount rate

Key Observation:

It is easy to see why rational investors will build OCGT – and then think about CCGT.

Page 10: Future of Renewables in Victoria Dr Jeff Washusen Marsden Jacob Associates VPELA 30 April 2012

MARSDEN JACOB ASSOCIATES 10

Electricity price trajectories Residential retail price

0

5

10

15

20

25

30

TIME (Quarter Ending)

Average Cost (¢/kWh) GST

Average Cost (¢/kWh) Variable Retail

Average Cost (¢/kWh) Fixed Retail

Average Cost (¢/kWh) Variable Network

Average Cost (¢/kWh) Fixed Network

AVERAGE COST (¢/kWh)

Key Observations:

Largest increase is retail variable energy, up 50% since 2006 – even though both spot prices and Futures prices remained weak.

Recently ~$110/MWh, compared to ~30/MWh spot price and $40-$50/MWh Futures price.

Unclear if this is due to risk presented by increasingly volatile load profiles of increasingly prolific & Solar – or the impact of another retail oligarchy.

Fixed network cost increase due to Government mandated “Smart Meter Rollout”.

Page 11: Future of Renewables in Victoria Dr Jeff Washusen Marsden Jacob Associates VPELA 30 April 2012

MARSDEN JACOB ASSOCIATES 11

Summary points

The electricity market is an extremely volatile and highly risky place to invest in long life capital assets. The risk is compounded by uncertainty about both existing and proposed renewable policy – and the “alarmingly” frequent refinement of renewable policy settings.

Potential investors in both fossil fuelled and (large scale) renewable generation are behaving in a logical and rational way. They will not invest unless they can mitigate investment risk through oligarchic relationships or other long-term hedge arrangements.

The investment challenges presented by volatility and uncertainty will be compounded by rapidly falling Solar PV costs and poor policy choices of Government.

Continued proliferation of Solar PV, which appears inevitable, will also present real challenges for current retail and network pricing policies in the very near future. Even without subsidies, Solar PV users will reduce their annual electricity costs under current

tariff policies. But current network technology cannot cope with rapidly changing 2-way flow of energy in the

low voltage networks. Substantial investment in networks will be required to monitor (and possibly control) varying load; and to allow network operation to accommodate highly variable 2-way energy flow.

But who then pays for supply volatility risk and network services? AC using households have benefited from archaic (network and retail) tariff policies for decades. Solar PV using households are benefitting from the same archaic tariff policies.