Full Depth Reclamation Process In North Carolina
Part 1 ‐ Investigation
43rd Annual Southeastern Transportation Geotechnical Engineering Conference (STGEC)Geotechnical Engineering Conference (STGEC)
October 22 ‐ 25, 2012
Mohammed A. Mulla, P.E., CPM, MCE
Assistant State Geotechnical Engineer
Geotechnical Engineering UnitGeotechnical Engineering Unit
North Carolina Department of Transportation
![Page 2: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/2.jpg)
Presentation OutlinePresentation Outline
•• NCDOT Full Depth Reclamation (FDR) HistoryNCDOT Full Depth Reclamation (FDR) History•• NCDOT Full Depth Reclamation (FDR) HistoryNCDOT Full Depth Reclamation (FDR) History
••What is the basic FDR processWhat is the basic FDR process
•• FDR Selection and Design CriteriaFDR Selection and Design Criteria
•• Step By Step Investigation Step By Step Investigation ‐‐ PicturesPictures
•• Laboratory TestingLaboratory Testing
•• RecommendationRecommendation
![Page 3: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/3.jpg)
NCDOT FDR History
• Started in July 2003
• Have performed 80 FDR investigations in 11 of 14 N.C. Divisions
• Have investigated 319+ miles, whileHave investigated 319+ miles, while having actually performed FDR on over 107 miles (30 FDR)
• Project sizes range from ½ mile to 9 miles in length
![Page 4: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/4.jpg)
What is Full Depth Reclamation (FDR)?What is Full Depth Reclamation (FDR)?
FDRFDR is a process whereby both the existing asphalt is a process whereby both the existing asphalt p y g pp y g ppavement and underlying materials pavement and underlying materials (predetermined mix(predetermined mix‐‐design depth) are design depth) are first first pulverized, then mixed with cement, and pulverized, then mixed with cement, and compactedcompacted ((recycled inrecycled in‐‐place)place),, into a new base into a new base course, ready for paving. Design strength gain is course, ready for paving. Design strength gain is achieved by the measured addition of Portland achieved by the measured addition of Portland C d i h i i f h i lC d i h i i f h i lCement during the mixing of these materials.Cement during the mixing of these materials.
![Page 5: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/5.jpg)
What is Full Depth Reclamation (FDR)?What is Full Depth Reclamation (FDR)?
FDRFDR is also ais also a Green ProcessGreen Process: Asphaltic roadway : Asphaltic roadway p yp ymaterials are not removed from the project, materials are not removed from the project, thereby saving money, time, and landfill space, and thereby saving money, time, and landfill space, and not causing further damage to adjacent rural not causing further damage to adjacent rural roadways. Asphalt areas, which are too thick due roadways. Asphalt areas, which are too thick due to repeated patching or overlaying, can be milled to repeated patching or overlaying, can be milled off and reused for widening of shoulders.off and reused for widening of shoulders.
![Page 6: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/6.jpg)
When Should FDR Be Considered?When Should FDR Be Considered?
h d hh d h dd hhWhen a roadway is in suchWhen a roadway is in such poor condition poor condition that it that it
may be more economical over the long term tomay be more economical over the long term tomay be more economical over the long term to may be more economical over the long term to
make a new base course out of it than to make a new base course out of it than to
continually patch and/or overlay it.continually patch and/or overlay it.
NCDOT Selection CriteriaNCDOT Selection Criteria
![Page 7: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/7.jpg)
Potential FDRPotential FDR
![Page 8: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/8.jpg)
Potential FDRPotential FDR
![Page 9: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/9.jpg)
FDRFDR
![Page 10: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/10.jpg)
Step By Step Investigation (FDR) Full Depth Reclamation
![Page 11: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/11.jpg)
Is the average pavementthickness < 5” ?
FDR Selection Criteria Other Data Required for Selection
Approximate Length of Project: _______NO
If projectis a candidate
NOYES
ADT: _______
% of Trucks: _______
Project may not be aCandidate for FDR
For thin overlay, does > 10%area require full depth
patching?
YES
Anticipated Widening: Yes ____ NO ____
Anticipated Width of Widening: _____
Extensive Utilities: Yes NO
NO
Candidate for FDR
Is most of the subgrade firm?(soft areas are not extensive)
____ _____
Utilities Present: __________________
Are Ditches Open andFunctioning: Yes NO
Can road be closed to all butLocal traffic i e does a reasonable
YESFunctioning: Yes ____ NO ____
Approximate Depth of WaterTable: ________
NO
Local traffic, i.e. does a reasonabledetour exist?
YES
NOProject may be aCandidate for FDR
Is project > ½ mile or can beCombined with other in a
contact?
YESNO
![Page 12: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/12.jpg)
Light Weight Deflectometer (LWD) PRIMA100
![Page 13: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/13.jpg)
Investigation and Sampling ProcedureInvestigation and Sampling ProcedureRock RipperRock Ripper
• Pavement Layer Thickness: 4” Core Teeth are carbide-tipped buttons or blades
• Subgrade Strength: DCP
• Subgrade Investigation:
buttons or blades.
Dead Stem Auguring to 5’
![Page 14: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/14.jpg)
Drive the Road to mark bad spots
![Page 15: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/15.jpg)
Traffic Control
![Page 16: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/16.jpg)
Air and Pavement Temperatures
![Page 17: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/17.jpg)
Mark 1, 3, 5, 7 and 9 foot 1’ from edge of pavement
![Page 18: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/18.jpg)
![Page 19: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/19.jpg)
First test area
Video
![Page 20: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/20.jpg)
![Page 21: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/21.jpg)
![Page 22: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/22.jpg)
Samples: B‐1, B‐3, B‐5, B‐6
![Page 23: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/23.jpg)
![Page 24: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/24.jpg)
Video
Auger borings
Pavement Layer Thickness:
![Page 25: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/25.jpg)
![Page 26: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/26.jpg)
Video DCPSubgrade Strength: DCP
![Page 27: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/27.jpg)
![Page 28: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/28.jpg)
Video Augur Boring
![Page 29: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/29.jpg)
![Page 30: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/30.jpg)
![Page 31: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/31.jpg)
![Page 32: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/32.jpg)
![Page 33: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/33.jpg)
Video Material Depths
![Page 34: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/34.jpg)
![Page 35: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/35.jpg)
![Page 36: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/36.jpg)
Mix well
VideoMix
![Page 37: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/37.jpg)
![Page 38: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/38.jpg)
![Page 39: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/39.jpg)
![Page 40: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/40.jpg)
![Page 41: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/41.jpg)
![Page 42: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/42.jpg)
Cold Patch both holes
![Page 43: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/43.jpg)
Samples: B‐1, B‐3, B‐5, B‐6
Samples for Lab Testing:
Classification, Gradation, and Unconfined
Take Samples to M&T Lab
Classification, Gradation, and Unconfined Compressive Strength with 4%, 6%, and 8%
Cement added.
![Page 44: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/44.jpg)
![Page 45: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/45.jpg)
Add Cement
![Page 46: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/46.jpg)
![Page 47: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/47.jpg)
![Page 48: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/48.jpg)
![Page 49: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/49.jpg)
![Page 50: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/50.jpg)
7 Days in Cure Room
![Page 51: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/51.jpg)
4 Hours soaked in Water before testing
![Page 52: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/52.jpg)
Ready for Unconfined Compressive Strength
![Page 53: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/53.jpg)
Sample Failure
![Page 54: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/54.jpg)
![Page 55: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/55.jpg)
RECOMMENDATIONS:
If FDR i h f th i t l 2 92 il f d thIf FDR is chosen for the approximately 2.92 miles of roadway, the Geotechnical Engineering Unit recommends a CEMENT APPLICATION RATE OF 46 LBS PER SQUARE YARD AND A MIXING DEPTH OF 12 INCHES.
We do not recommend that a greater depth of reclamation be usedWe do not recommend that a greater depth of reclamation be used unless the cement rate is increased. We highly recommend that the reclamation width be a minimum of two feet more (1 foot on each id f th d ) th th fi l t idth i l di llside of the roadway) than the final pavement width, including all
widened areas.
The Pavement Management Unit recommends overlaying the 12 inches of FDR with 1.25" SF9.5A. Special attention is needed in any areas which are to be widened, to ensure that the base closelyareas which are to be widened, to ensure that the base closely matches the composition of the mainline pavement.
![Page 56: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/56.jpg)
![Page 57: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/57.jpg)
http://www.ncdot.gov/about/finance/
Pavement Health 70%As of 10/23/2012/
![Page 58: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/58.jpg)
Before FDRBefore FDR
After FDRAfter FDR
![Page 59: Full Depth Reclamation Process In North Carolina … STGEC - Full...Full Depth Reclamation Process In North Carolina Part 1 ‐Investigation 43rd Annual Southeastern Transportation](https://reader035.vdocuments.site/reader035/viewer/2022071021/5fd5837eae64ae64c72a0abb/html5/thumbnails/59.jpg)
Premix/Pulverize Spread Cement Mix/Blend:Dry/H20
Compact Grade Pave
14