fugro foundation report bridge street bridge

60
FUGRO Foundation Report Bridge Street Bridge Rehabilitation Over Arroyo Grande Creek EXISTING Bridge No. 49C-0196 Federal Project No. BRLO-5199(027) Arroyo Grande, California Prepared for: Quincy Engineering, Inc. May 2017 Project No. 04.62120100

Upload: others

Post on 13-Mar-2022

11 views

Category:

Documents


0 download

TRANSCRIPT

FUGRO Foundation Report Bridge Street Bridge Rehabilitation Over Arroyo Grande Creek EXISTING Bridge No. 49C-0196 Federal Project No. BRLO-5199(027) Arroyo Grande, California Prepared for: Quincy Engineering, Inc. May 2017 Project No. 04.62120100

Fugro Project No. 04.62120100

Prepared for:

Quincy Engineering Inc. 11017 Cobblerock Drive, Suite 100 Rancho Cordova, California 95670

02 Final LB May 5, 2017

01 Draft LB MM GD March 8, 2017

Issue Document Status Prepared Checked Approved Date

FUGRO Foundation Report Bridge Street Bridge Rehabilitation Over Arroyo Grande Creek EXISTING Bridge No. 49C-0196 Federal Project No. BRLO-5199(027) Arroyo Grande, California Prepared for: Quincy Engineering, Inc. May 2017 Project No. 04.62120100

A member of the Fugro Group of companies with offices throughout the world.

FUGRO 4820 McGrath Street, Suite 100 Ventura, California 93003 T +1 805 650 7000 F +1 805 650 7010 www.fugro.com

May 5, 2017 Project No. 04.62120100 Quincy Engineering Inc. 11017 Cobblerock Drive, Suite 100 Rancho Cordova, California 95670 Attention: Mr. Greg Young Subject: Foundation Report, Bridge Street Bridge Rehabilitation over Arroyo Grande Creek, Existing Bridge

No. 49C-0196, Federal Project No. BRLO-5199(027), Arroyo Grande, California Dear Mr. Young, Fugro is pleased to submit this Foundation Report for design of the Bridge Street Bridge Rehabilitation over Arroyo Grande Creek in Arroyo Grande, California. Our services for the project were performed in accordance with our proposals dated February 7, 2012 and March 16, 2017, and our work was authorized by Quincy Engineering’s Standard Agreement for Subconsultant Services dated June 26, 2012 and Amendment 1 dated March 17, 2017. Our geotechnical services were generally performed in two phases. The first phase of our work consisted of preparing a Preliminary Foundation Report, dated November 28, 2012, that was based on available existing information and review of previous geotechnical studies for the existing bridge. The second phase of work consisted of performing a field exploration and laboratory testing program to characterize the subsurface conditions at the site, conducting various analyses to provide seismic design criteria and response spectra for the bridge design, developing geotechnical engineering recommendations for the design of the bridge foundations, and providing recommendations for the design of the roadway approaches. This Foundation Report provides geotechnical recommendations for the design of the bridge foundations, abutments and roadway approaches, as well as geotechnical considerations regarding corrosion for substructures, scour, seismic data for use with Caltrans design methods, and construction considerations. Field and laboratory data collected for this study are attached with this report.

QUINCY ENGINEERING, INC. BRIDGE STREET BRIDGE REHABILITATION ARROYO GRANDE, CALIFORNIA

Fugro Project No. 04.62120100

Please contact the undersigned if you have questions or if you require additional information.

Sincerely, Fugro USA Land, Inc.

Loree A. Berry, PE 73221 Gregory S. Denlinger, GE 2249 Associate Engineer/Senior Project Manager Principal Geotechnical Engineer

Copies: 4 – Addressee

QUINCY ENGINEERING, INC. BRIDGE STREET BRIDGE REHABILITATION ARROYO GRANDE, CALIFORNIA

Fugro Project No. 04.62120100 Page i of ii

CONTENTS Page

1. PROJECT DESCRIPTION .......................................................................................................................... 1 1.1 Existing Facility............................................................................................................................................ 1 1.2 Previous Studies ......................................................................................................................................... 1 1.3 Proposed Improvements ............................................................................................................................. 2

2. WORK PERFORMED ................................................................................................................................. 3 2.1 Purpose ....................................................................................................................................................... 3 2.2 Scope .......................................................................................................................................................... 3 2.3 Field Exploration ......................................................................................................................................... 4 2.4 Laboratory Testing ...................................................................................................................................... 4 2.5 General Conditions ..................................................................................................................................... 5

3. SITE CONDITIONS ..................................................................................................................................... 6 3.1 Geologic Setting .......................................................................................................................................... 6 3.2 Subsurface Conditions ................................................................................................................................ 6 3.3 Groundwater................................................................................................................................................ 8

4. GEOTECHNICAL EVALUATION ............................................................................................................... 9 4.1 Seismicity .................................................................................................................................................... 9 4.2 Ground Surface Fault Rupture .................................................................................................................. 10 4.3 Landslides and Slope Instability ................................................................................................................ 10 4.4 Liquefaction and Seismic Settlement ........................................................................................................ 11

4.4.1 Evaluation .................................................................................................................................. 11 4.4.2 Potential Design Impacts from Liquefaction and Seismic Settlement ....................................... 11

4.5 Geologic Profiles and Engineering parameters ........................................................................................ 12

5. CONCLUSIONS AND RECOMMENDATIONS ........................................................................................ 13 5.1 Summary of Findings ................................................................................................................................ 13 5.2 Foundation Types ..................................................................................................................................... 14 5.3 Foundation Design .................................................................................................................................... 14

5.3.1 Axial Capacity of CIDH Piles ..................................................................................................... 15 5.3.2 Lateral Pile Capacity .................................................................................................................. 15 5.3.3 Group Effects ............................................................................................................................. 16 5.3.4 Settlement .................................................................................................................................. 16 5.3.5 Pile Design Data Table .............................................................................................................. 17 5.3.6 Abutment Resistance ................................................................................................................. 17

5.4 Static Lateral Earth Pressures .................................................................................................................. 17 5.5 Dynamic Earth Pressures ......................................................................................................................... 18 5.6 Corrosion Considerations .......................................................................................................................... 18 5.7 Roadway Approaches ............................................................................................................................... 19

QUINCY ENGINEERING, INC. BRIDGE STREET BRIDGE REHABILITATION ARROYO GRANDE, CALIFORNIA

Fugro Project No. 04.62120100 Page ii of ii

5.7.1 Structure Approach Embankment.............................................................................................. 19 5.7.2 Use of On-site Materials ............................................................................................................ 19 5.7.3 Approach Fill Settlements .......................................................................................................... 20

5.8 Pavement Structural Section ..................................................................................................................... 20 5.9 Construction Considerations ..................................................................................................................... 20

5.9.1 Excavation ................................................................................................................................. 20 5.9.2 Temporary Slopes and Shoring ................................................................................................. 21 5.9.3 Groundwater and Dewatering .................................................................................................... 21 5.9.4 CIDH Pile Construction .............................................................................................................. 21

6. CONTINUATION OF SERVICES ............................................................................................................. 23 6.1 Review of Plans and Specifications .......................................................................................................... 23 6.2 Geotechnical Observation and Testing ..................................................................................................... 23

7. REFERENCES .......................................................................................................................................... 24

LIST OF PLATES

No. Vicinity Map ................................................................................................................................................................ 1 Exploration Location Map ........................................................................................................................................... 2 Cross Section A-A’...................................................................................................................................................... 3 Design Acceleration Response Spectrum .................................................................................................................. 4 Geotechnical Properties for Analyses ........................................................................................................................ 5 Log of Test Borings (1 sheet)

APPENDICES

APPENDIX A SUBSURFACE EXPLORATION

Key to Terms & Symbols Used on Logs ................................................................................................A-1 Log of Boring No. DH-101 .....................................................................................................................A-2

APPENDIX B LABORATORY TEST RESULTS

Summary of Laboratory Test Results ......................................................................................... B-1a to 1b Grain Size Curves .................................................................................................................................B-2 Plasticity Chart ......................................................................................................................................B-3 Consolidation Test Results ....................................................................................................................B-4 Unconfined Compression Test Results ............................................................................... B-5a and B-5b Unconsolidated, Undrained Triaxial Test Results .......................................................... B-6a through B-6c Compaction Test Results ......................................................................................................................B-7 R-Value Test Results ............................................................................................................................B-8

APPENDIX C REFERENCED EXISTING SUBSURFACE DATA

Log of Test Boring (ESP 2004) ............................................................................................................ C-1

QUINCY ENGINEERING, INC. BRIDGE STREET BRIDGE REHABILITATION ARROYO GRANDE, CALIFORNIA

Fugro Project No. 04.62120100 May 2017 Page 1 of 26

1. PROJECT DESCRIPTION

This Foundation Report provides geotechnical input for designing the proposed rehabilitation improvements to the Bridge Street Bridge over Arroyo Grande Creek (Existing Bridge No. 49C-0196) in Arroyo Grande, California. The existing two-span bridge carries two lanes of vehicle traffic and sidewalks exist on both sides of the bridge.

The location of the site relative to nearby streets and landmarks is shown on Plate 1 - Vicinity Map. The general layout of the site and proposed facility are shown on Plate 2 - Field Exploration Location Plan.

1.1 Existing Facility

Constructed in 1908, the existing Bridge Street Bridge at Arroyo Grande Creek consists of 2 spans totaling 135 feet in length, is approximately 34 feet wide, and has two travel lanes with no shoulders. The north span is a steel truss. The south span is a reinforced concrete deck on steel girders. Sidewalks with timber decking are cantilevered from both sides of the bridge.

The bridge is within the historic and downtown area of Arroyo Grande. The streets that approach the bridge are generally lined with buildings used for retail, restaurants and various businesses. Arroyo Grande Creek flows to the west within an approximately 38-foot-deep channel beneath the bridge. Kiwanis Park is located on the north bank of the creek just upstream of the bridge. A partially collapsed and undermined concrete retaining wall appears to be located along portions of the south bank of the creek opposite of the park. The stream channel beneath and downstream of the bridge is heavily vegetated with blackberries, vines and some trees.

The bridge was retrofitted with a supplement steel truss constructed beneath the north span in or about 1990 (Caltrans, 1939-2011; Fred H. Schott & Associates, 1989). The supplemental truss was supported on the existing abutments and pier wall; no foundation improvements were made as part of that project. The Bridge Inspection Reports (BIR) do not describe the foundation system for the existing bridge; however, the Caltrans 1939 BIR states that the south span was added to the bridge after the old pier at the south end of the truss had washed out.

1.2 Previous Studies

As part of our data collection, we reviewed a “Conceptual Soils Engineering Report” prepared for the bridge site in 2004 by Earth Systems Pacific (ESP). That study included data from three exploratory borings at the site: one at each approach to depths of approximately 70 to 74 feet below the surface of Bridge Street, and one on the westerly side of the bridge pier to approximately 59 feet below the ground surface.

In addition, we reviewed as-built Caltrans Log of Test Borings (1957) prepared for the two (2) Highway 101 bridges located approximately 1,100 feet downstream of Bridge Street.

QUINCY ENGINEERING, INC. BRIDGE STREET BRIDGE REHABILITATION ARROYO GRANDE, CALIFORNIA

Fugro Project No. 04.62120100 May 2017 Page 2 of 26

1.3 Proposed Improvements

We understand the project will consist of replacing the existing foundations and supplemental truss with new foundations and a stronger supplemental truss, and rehabilitating the existing historic truss. The new bridge foundations will be supported by cast-in-drilled-hole (CIDH) piles.

The Foundation Plan (Sheet 3 of 31 of Quincy’s 65 Percent Plans) indicates that Abutment 1 at the north end of the bridge will be supported by a single row of four, 48-inch-diameter CIDH piles. Pier 2 will be supported by a single 84-inch-diameter CIDH pile and Abutment 3 at the south end of the bridge will be supported by one row of five, 36-inch-diameter CIDH piles. Rock slope protection will be placed at the abutments for scour protection.

It is anticipated that the vertical profile for the bridge rehabilitation will be near the existing site grades. The approaches will be resurfaced with asphalt to match the adjacent pavement surface.

QUINCY ENGINEERING, INC. BRIDGE STREET BRIDGE REHABILITATION ARROYO GRANDE, CALIFORNIA

Fugro Project No. 04.62120100 May 2017 Page 3 of 26

2. WORK PERFORMED

2.1 Purpose

The purpose of this report is to provide geotechnical recommendations for the design of the Bridge Street Bridge Rehabilitation project over Arroyo Grande Creek. The main geotechnical considerations that we evaluated for the project were characterization of the soil and groundwater conditions encountered at the bridge site, design of new CIDH pile foundations to support lateral and vertical loads, seismic design considerations, corrosion considerations for concrete substructures, and construction considerations for the bridge foundation rehabilitation.

2.2 Scope

To evaluate the geotechnical considerations for the project, we performed the following scope of work:

■ Consulted with Quincy and the City of Arroyo Grande (City) to review our approach to providing geotechnical services for design, and visited the site to observe the general site conditions and mark the locations of our borings;

■ Submitted a Preliminary Foundation Report (Fugro, 2012) based on review of existing documents as input to the bridge type selection process;

■ Obtained an encroachment permit from the City, prepared a health and safety plan for our work, contacted Underground Service Alert to review our proposed boring location relative to existing utilities, and coordinated the field exploration program with our drilling subcontractor;

■ Performed a field exploration program consisting of one (1) hollow-stem auger boring to a depth of approximately 95-1/2 feet near the existing northern abutment location on July 6, 2015. On March 29, 2017, the same borehole was extended to a depth of approximately 131-1/2 feet.;

■ Performed laboratory tests on selected samples recovered from the boring; ■ Prepared this report and the attached Log of Test Borings sheet summarizing the data collected and

providing our conclusions and recommendations regarding: □ Soil and groundwater conditions encountered; □ Site geology, faulting and seismicity; □ Seismic design criteria for use with Caltrans design methods; □ Liquefaction potential and considerations relative to foundation design (negative skin friction,

estimated seismic settlement of approaches and drilled pier foundations, as needed); □ Structural sections for asphalt concrete pavements based on traffic indices provided to us; □ Embankment construction including suitability of excavated materials for use as fill, moisture

control, erosion control, and drainage considerations, expansive soils, estimated settlement and special treatments to reduce settlement, if needed;

□ Corrosion considerations for design of subsurface structures (minimum cement factors estimated in accordance with Caltrans guidelines);

□ Potential for Naturally Occurring Asbestos (NOA) to impact the project; □ Suitable foundation types for the conditions encountered (such as spread footings, driven concrete

or steel piles, CISS, or CIDH piles);

QUINCY ENGINEERING, INC. BRIDGE STREET BRIDGE REHABILITATION ARROYO GRANDE, CALIFORNIA

Fugro Project No. 04.62120100 May 2017 Page 4 of 26

□ Specified tip elevations, settlement and size for cast-in-drilled hole foundations and pile loading provided by Quincy (2016);

□ Lateral capacity of single pile foundations for free-head and fixed-head conditions based on p-y analysis;

□ Pile spacing and group reduction factors for vertical and lateral loads; □ Lateral earth pressures, spring constants, and passive pressure resistance for abutment retaining

wall design; □ Special considerations for approach fill settlements, allowable slope inclinations, waiting periods

and need for monitoring; and □ Construction considerations: need for dewatering, CIDH pile construction, adjacent structures,

temporary excavations and shoring.

2.3 Field Exploration

The drilling subcontractor for the project was S/G Drilling Company (S/G) of Lompoc, California. S/G drilled one (1) hollow-stem-auger boring on July 6, 2015. The boring was drilled to a depth of approximately 95-1/2 feet below the existing ground surface using 8-inch-diameter hollow-stem augers. The boring was sampled at approximate five-foot intervals using a three-inch-outside-diameter modified California split-spoon sampler or a Standard Penetration Test sampler. The modified California sampler was equipped with one-inch high brass rings. The split-barrel samplers were driven into the materials at the bottom of the boring using a 140-pound automatic trip hammer with a 30-inch drop.

The blow count (N-value) shown on the boring logs is the number of blows from the hammer that were needed to drive the sampler one foot after the sampler had been seated at least six inches into the material at the bottom of the hole. Refusal is noted where the blow count exceeded 50 blows during seating. Bulk samples were collected from the drill cuttings retrieved from the auger flights. At completion, the boring was backfilled with one sack of cement slurry and capped with asphalt concrete patch.

The sample intervals, N-values, a description of the subsurface conditions encountered, and other field and laboratory data are presented on the log of the boring in Appendix A. The corresponding laboratory data is presented in Appendix B. The approximate location of Fugro’s 2015 boring and ESP’s 2004 borings are shown on Plate 2.

2.4 Laboratory Testing

Laboratory testing was performed on selected samples obtained during the field exploration program. Laboratory tests for moisture content, grain size analysis, plasticity (Atterberg limits), consolidation, unconfined compressive strength, unconsolidated undrained (UU) triaxial shear strength, laboratory compaction (modified Proctor), and R-value tests were performed by our laboratories in Ventura and Oakland, California. The tests were performed in general accordance with the applicable standards of ASTM. Corrosion tests were performed by Cooper Testing Laboratories of Palo Alto, California on selected samples using Caltrans test methods. Results of laboratory testing are presented on the boring logs in Appendix A and Appendix B.

QUINCY ENGINEERING, INC. BRIDGE STREET BRIDGE REHABILITATION ARROYO GRANDE, CALIFORNIA

Fugro Project No. 04.62120100 May 2017 Page 5 of 26

2.5 General Conditions

Fugro prepared the conclusions, recommendations and professional opinions of this report in accordance with the generally accepted geotechnical principles and practices at this time and location. This warranty is in lieu of all other warranties, either express or implied. This report was prepared for the exclusive use of Quincy Engineering, Inc. and their authorized agents only. It may not contain sufficient information for the purposes of other parties or other uses. If any changes are made in the project as described in this report, the conclusions and recommendations contained in this report should not be considered valid unless Fugro reviews the changes and modifies and approves, in writing, the conclusions and recommendations of this report.

The scope of geotechnical services performed and reported herein did not include any environmental assessments for the presence or absence of hazardous/toxic materials in the soil, groundwater, or atmosphere. Any statements, or absence of statements, in this report or data presented herein regarding odors, unusual or suspicious items, or conditions observed are strictly for descriptive purposes and are not intended to convey engineering judgment regarding potential hazardous/toxic assessment.

Soil and rock deposits can vary in type, strength, and other geotechnical properties between points of observations and exploration. Additionally, groundwater and soil moisture conditions can vary seasonally or for other reasons. Therefore, we do not and cannot have a complete knowledge of the subsurface conditions underlying the site. The conclusions and recommendations presented in this report are based upon the findings at the points of exploration, and interpolation and extrapolation of information between and beyond the points of observation, respectively. These findings are subject to confirmation based on the conditions revealed by construction.

QUINCY ENGINEERING, INC. BRIDGE STREET BRIDGE REHABILITATION ARROYO GRANDE, CALIFORNIA

Fugro Project No. 04.62120100 May 2017 Page 6 of 26

3. SITE CONDITIONS

3.1 Geologic Setting

The project is located in the Arroyo Grande Valley and within the Coast Ranges geologic and geomorphic province. That province consists of north-northwest-trending sedimentary, volcanic, and igneous rocks extending from the Transverse ranges at the south into northern California. Rock formations of the Coast Ranges province are predominantly of Jurassic and Cretaceous age; however, some pre-Jurassic, along with Paleocene-age to Holocene rock formations are present.

The Arroyo Grande Valley and adjacent hills are the dominant geomorphic features within the project vicinity. The valleys were formed during a period of low sea level (the Wisconsin glacial stage), as coastal streams adjusted to the drop in sea level by carving into the landscape. A subsequent rise in sea level produced a dynamic depositional environment reflected in the discontinuous and variable subsurface stratigraphy. Up to approximately 800 feet of interlayered and unconsolidated sediments have been deposited within the valleys that generally dip gently to the west. Fill and alluvium encountered at the site was underlain by sediments of the Paso Robles Formation.

Hall (1973) characterizes the Paso Robles Formation as unconsolidated or poorly consolidated gravel or conglomerate, sandstone, siltstone and claystone. Although designated as rock because of the formation, the sediments of the Paso Robles Formation are generally uncemented units of stiff to hard cohesive soils and medium dense to very dense granular soils and as a result, are described using soil classification terminology in this report. Holland (2013) maps the same unit as older alluvium and describes it as unconsolidated boulders, cobbles, gravel, sand, silt and clay with clasts generally consisting of Franciscan Complex, Obispo and Monterey Formation lithologies.

3.2 Subsurface Conditions

Fugro’s boring DH-101 was drilled in the north abutment area on July 6, 2015 to a depth of approximately 95-1/2 feet below the existing ground surface (bgs). On March 29, 2017 that same boring location was re-drilled and extended to a depth of approximately 131-1/2 feet bgs, corresponding to an approximate elevation (EL.) of EL. -19-1/2 feet above mean sea level (MSL). For the ESP (2004) exploration program, boring B-1 extended to about EL. +42 feet, and borings B-2 and B-3 extended to about EL. +35 feet. The approximate locations of the explorations are shown on Plate 2, a log of test borings (LOTB) depicting the Fugro boring is presented after Plate 5, and the ESP (2004) LOTB is presented in Appendix C.

The subsurface conditions encountered by Fugro and reported by ESP (2004) generally consisted of artificial fill (af) overlying alluvium (Qal) and Paso Robles Formation (Qpr). General descriptions of those units are provided below. It should be noted that ESP (2004) did not identify any materials encountered as Paso Robles Formation. Therefore, the depths estimated for the contact between alluvium and Paso Robles Formation are based on our interpretation and a comparison between ESP (2004) boring logs and the subsurface conditions encountered in boring DH-101.

QUINCY ENGINEERING, INC. BRIDGE STREET BRIDGE REHABILITATION ARROYO GRANDE, CALIFORNIA

Fugro Project No. 04.62120100 May 2017 Page 7 of 26

Artificial Fill (af). Artificial fill was encountered in boring DH-101 from the ground surface to about ten feet below the ground surface. The artificial fill consisted of very loose to medium dense clayey sand (SC), and very stiff sandy lean clay (CL). The ESP (2004) borings encountered artificial fill materials composed of loose to medium dense sand and clayey sand, and stiff sandy lean clay from the ground surface to depths ranging from about 1-1/2 to 8-1/2 feet. The artificial fill appears to be associated with grading performed during construction of the existing bridge. Artificial fill materials were encountered in all of the borings above alluvium.

Alluvium (Qa). The alluvium encountered in boring DH-101 consisted of medium dense to dense silty sand (SM) and poorly graded sand with clay and gravel (SP-SC), and soft to stiff fat clay (CH) with varying amounts of gravel. The ESP (2004) borings encountered alluvial materials that predominantly consisted of loose to dense poorly graded sand, silty and clayey sand with varying amounts of gravel, well-graded gravel with sand, and soft to stiff lean clay, silt and silty clay with varying amounts of sand and gravel.

We have logged the alluvial materials encountered in DH-101 extending to about EL. +74 feet and have interpreted the alluvial materials encountered in the ESP borings extending to EL. +74 at the north abutment (similar to DH-101), to about EL. +45 to +50 feet at the south abutment.

Paso Robles Formation (Qpr). Paso Robles Formation materials were encountered below alluvium at a depth of about 38 feet (about EL. +74 feet) in boring DH-101. The formational materials consisted of dense to very dense poorly-graded gravel with clay and sand (GP-GC), with interbedded clayey sand with gravel (SC) and silty sand with gravel (SM). Below the predominantly granular formational materials, we encountered a hard lean clay (CL) unit between a depth of about 83 feet (EL. +29 feet) to the final boring termination depth of approximately 131-1/2 feet (EL. -19.5 feet). The hard clay is massive with a high water content and low dry unit weight. On a visual basis, the material has the appearance similar to bentonite.

ESP (2004) encountered soils we that we interpret as formational materials from an approximate depth consistent with Fugro boring DH-101 extending to the maximum exploration depths of approximately 60 to 75 feet below the surface of the road. ESP (2004) logged materials within that interpreted formational zone as dense to very dense sand and gravel deposits.

Geotechnical Properties. The data presented below were developed on the basis of our recent field exploration effort and existing data presented in the Log of Test Borings (LOTB) prepared by ESP (2004). The results from selected laboratory tests and field data measured during the field exploration are summarized below. Plate 3 – Cross Section A-A’ also presents our interpreted contacts between geologic units consistent with Table 1.

QUINCY ENGINEERING, INC. BRIDGE STREET BRIDGE REHABILITATION ARROYO GRANDE, CALIFORNIA

Fugro Project No. 04.62120100 May 2017 Page 8 of 26

Table 1. Summary of Selected Geotechnical Properties by Unit

Geologic Unit Predominant Soil/Rock

Range of Dry Unit Weights

(pcf)

Range of Moisture Contents

(%)

SPT Field-N60

Value Range

Undrained Shear

Strength (ksf)1

Af/Qal1

Very loose to medium dense clayey SAND (SC) and silty SAND (SM) with layers of very stiff sandy lean CLAY (CL)

76 to 112 8 to 26 5 to 15 p: 2.5 (CL)

Qal2

Medium dense to very dense silty SAND (SM), clayey SAND (SC) and poorly graded sand with clay and gravel (SP-SC), trace cobbles, occasional very stiff to hard CLAY (CL) layers

84 to 101 12 to 21 8 to 50+ p: 4.0 (CL)

Qal3 Medium stiff to stiff lean CLAY (CL) to fat CLAY (CH) 90 to 100 30 to 31 14 to 33 p: 0.8 to 1.3

t: 0.7 to 1.7

Qpr

Dense to very dense poorly-to well-graded GRAVEL with sand and clay (GP-GC), occasional cobbles and/or boulders. Hard lean clay (CL) encountered below El. 28 feet

83 to 108 (GP-GC) 72 to 79

(CL)

17 to 36 (GP-GC) 36 to 47

(CL)

50 to Refusal

p: 4.5+ (CL) Q: 3.1 to 4.7

(CL) uu: 8.1 to 10.7

(CL)

Note: 1. Test to estimate undrained shear strength denoted: p = field pocket penetrometer; t = field torvane; Q = unconfined compression test; uu = unconsolidated, undrained triaxial compression testing

3.3 Groundwater

Groundwater was encountered in July 6, 2015 boring DH-101 at a depth of approximately 40-1/2 feet corresponding to EL. 71.5 feet. When DH-101 was extended on March 29, 2017, groundwater was measured in the boring at a depth of 28 feet bgs (EL. 84 feet). The ESP (2004) borings encountered groundwater at depths ranging from approximately 23-1/2 to 37 feet below the ground surface, corresponding to an elevation range of EL. 70 feet to EL. 77 feet. About two feet of water was observed within the creek channel on July 6, 2015 (approximate creek thalweg EL. 77 feet). For the purposes of our liquefaction and foundation analyses, we assumed a groundwater elevation of EL. 85 feet.

The groundwater level at the project site is likely influenced by the water level in Arroyo Grande Creek and local precipitation events. Groundwater and soil moisture conditions will vary in association with changes in precipitation, irrigation, runoff and other factors.

QUINCY ENGINEERING, INC. BRIDGE STREET BRIDGE REHABILITATION ARROYO GRANDE, CALIFORNIA

Fugro Project No. 04.62120100 May 2017 Page 9 of 26

4. GEOTECHNICAL EVALUATION

4.1 Seismicity

A design acceleration response spectrum (ARS) for the site was estimated using ARS Online and guidelines set forth in Appendix B of the Caltrans (2013) Seismic Design Criteria. The project site is within a seismically active region of California. We performed a fault search of the project area using current Caltrans Seismic Design Criteria and utilizing the Caltrans ARS Online V2.3.07 website. The ARS Online website is updated on an ongoing basis and we accessed the site on February 27, 2017.

ARS Online displays information for faults included in the Caltrans (2012b) Fault Database Version 2B and calculates both deterministic and probabilistic acceleration response spectra (ARS) as described in Appendix B of the Caltrans (2013) Seismic Design Criteria. ARS Online was used as a basis for developing the seismic design criteria and recommended response spectra for the site. The table below presents a list of three faults that are considered to be seismic sources closest to the site identified using ARS Online and site coordinates estimated as 35.122600 degrees latitude and -120.578600 degrees longitude.

Table 2. Nearby Faults

Fault Name Fault Type1 Rx Distance (km/miles)2

Maximum Magnitude (Mmax)3

San Luis Range (So Margin) (ID 238)

Reverse 45 degrees 0.62/0.78 7.1

San Luis Range – Oceano 2011 CFM (ID 240)

Reverse 45 degrees 5.00/3.11 6.8

Los Osos 2011 (ID 232)

Reverse 45 degrees 6.60/4.10 6.9

Notes: 1) Fault type per Caltrans (2012b) Fault Database Version 2B. 2) Horizontal perpendicular distance to the fault trace (*fictitious fault trace for sites offset from the mapped fault location) or surface projection of the top of rupture plane measured perpendicular to the fault from the site per ARS Online and Caltrans Geotechnical Services Design Manual. 3) Mmax values per ARS Online and Caltrans (2012b) Database.

We estimated the shear wave velocity for materials encountered in the borings using correlations to blow counts as presented in the Caltrans (2009) Geotechnical Services Design Manual. An average shear wave velocity of approximately 300 meters/second (m/s) was estimated for the top 100 feet of soil at the site, which corresponds to a Soil Profile Type D.

Plate 4 - Design Acceleration Response Spectrum shows the recommended five-percent damped design spectra estimated from ARS Online analysis. In accordance with Caltrans guidelines, the design ARS curve is taken as the upper envelope of the deterministic and probabilistic ARS curves. As shown on Plate 4, the design ARS curve is controlled by the deterministic spectra for the San Luis (So. Margin) and Los Osos faults. The estimated peak ground acceleration (PGA) for the bridge site is approximately 0.69g. The site response for periods less than about 0.35 second is controlled by a magnitude M6.9 earthquake on the Los Osos fault, mapped approximately 3 miles east of the site. The site response for periods greater than about

QUINCY ENGINEERING, INC. BRIDGE STREET BRIDGE REHABILITATION ARROYO GRANDE, CALIFORNIA

Fugro Project No. 04.62120100 May 2017 Page 10 of 26

0.35 seconds is controlled by a M7.1 earthquake on the San Luis Range fault system. We note the probabilistic spectrum corresponding to a 5-percent in 50 years probability of exceedance (975-year return period) is defined by a mean magnitude of M6.7 and an estimated peak ground acceleration (PGA) of 0.39g.

According to ARS Online, the Los Osos Fault does not contribute to the maximum spectral values. However, based on correspondence with Caltrans Division of Research and Innovation (personal communication with Tom Shantz, Caltrans Senior Research Engineer, in email dated January 21, 2014), we understand the southwest-dipping fault was mischaracterized by ARS Online as a southeast-dipping fault. Consequently, our development of the design ARS curve considered the Los Osos Fault as a southwest-dipping reverse fault.

A near-fault factor was applied to the ARS curve because the site is located less than 15 miles (25km) from a potentially controlling fault. Application of the adjustment factor consists of a 20 percent increase in spectral acceleration for periods greater than 1 second and is linearly tapered to zero percent increase from a period of 1 second to 0.5 seconds.

4.2 Ground Surface Fault Rupture

The closest active fault mapped by Holland (2013) is the Wilmar Avenue fault of the San Luis Range (Southern Margin) fault system, which trends northwest-southeast approximately 800 feet southwest of the site. According to the County of San Luis Obispo (1999) and PG&E (2015), the Wilmar Avenue fault should be characterized as potentially active because the fault displaces late Pleistocene marine terrace deposits interpreted to be approximately 120,000 years old.

In our opinion, there is a low potential for fault rupture to impact the proposed bridge site and ground surface rupture does not need to be considered for the design of this project.

4.3 Landslides and Slope Instability

Although we were unable to assess the bridge and channel conditions from within the channel, the adjacent channel slopes do not show distress or visual signs of instability. As noted above, a partially collapsed and undermined concrete retaining wall appears to be located along portions of the south bank of the creek upstream of the bridge, and the stream channel beneath and downstream of the bridge is heavily vegetated with blackberries, vines and some trees. However, there is no evidence of landsliding or global slope instability near the bridge site.

Quincy (2016) indicates that proposed abutment slopes will be constructed up to approximately 35 feet high and at inclinations of 1.5H:1V or flatter. The slopes will be lined with filter fabric and protected with approximately 6.1 feet of Rock Slope Protection (RSP) consisting of backing material and 1/2-ton rock. Static global slope stability of the proposed embankment slope geometry yields a factor of safety greater than 1.5 and is considered acceptable. Proposed RSP will help mitigate the potential for erosion, surficial slope instability and scour.

QUINCY ENGINEERING, INC. BRIDGE STREET BRIDGE REHABILITATION ARROYO GRANDE, CALIFORNIA

Fugro Project No. 04.62120100 May 2017 Page 11 of 26

4.4 Liquefaction and Seismic Settlement

Seismically induced liquefaction is a phenomenon that commonly affects loose, granular materials below the groundwater table. Seismic shaking causes transient shear stresses in the soil deposits, which in turn result in partial densification of the loose materials. As the saturated materials densify, pore water pressures can increase causing the effective shear strength of the soil to reduce. If pore pressures build to a significant level during or shortly after an earthquake event, the soil may begin to behave like a viscous fluid and result in lateral ground movement. In addition, pore pressure dissipation following the earthquake shaking may be accompanied by consolidation, which can cause ground settlement. Liquefaction potential of the soils was evaluated in accordance with the procedures described in the 1997 NCEER guidelines (Youd and Idriss, 2001).

Settlement from earthquake ground shaking can also occur in uncemented, granular soils above the groundwater. Because the soils are not saturated, the soils are not susceptible to liquefaction and settlement occurs from shaking-induced densification. Descriptions of the settlement caused by the densification of granular soils and the procedures we used to evaluate the potential magnitude of settlement that could occur are provided in Tokimatsu and Seed (1987) and Pradel (1998).

4.4.1 Evaluation

Liquefaction and seismic settlement hazards were evaluated for the site considering the 975-year return period earthquake, defined as a M6.7 event with a PGA of 0.39g. Groundwater was encountered in the area of the proposed bridge between about EL. 70 feet and EL. 82 feet during our March 2017, July 2015 and the ESP (2004) field exploration programs. This depth appeared to be near or slightly above the water level observed in the channel during our field exploration. A groundwater depth of 27 feet below the existing ground surface, corresponding to EL. 85 feet, was assumed for our liquefaction analyses of blow count data from boring DH-101 and the ESP (2004) borings.

4.4.2 Potential Design Impacts from Liquefaction and Seismic Settlement

Based on our analysis, the very loose to medium dense sandy artificial fill and shallow alluvial materials encountered, in boring DH-101 and the ESP (2004) borings, to a depth of about 15 feet below the ground surface are potentially liquefiable. However, those soils are located above the design groundwater elevation and therefore not susceptible to liquefaction. Although those shallow soils are not susceptible to liquefaction, the materials may be susceptible to seismic settlement or compression. Using the procedures outlined in Pradel (2008), we estimate that up to approximately ½-inch of seismically-induced settlement could occur within those unsaturated upper alluvial soils in response to the design earthquake. However, we anticipate some or all of those materials will be removed and replaced with engineered fill as part of the bridge rehabilitation project, which should reduce the potential for seismic settlement.

The alluvium and Paso Robles Formation encountered below a depth of about 15 feet were composed of predominantly medium stiff to hard clay deposits and dense to very dense sands and gravels that are not considered to be vulnerable to liquefaction or seismic settlement. Therefore, potential downdrag loads from liquefaction and lateral loading were neglected in our calculations for the specified pile tip elevations.

QUINCY ENGINEERING, INC. BRIDGE STREET BRIDGE REHABILITATION ARROYO GRANDE, CALIFORNIA

Fugro Project No. 04.62120100 May 2017 Page 12 of 26

4.5 Geologic Profiles and Engineering Parameters

Plate 5 - Geotechnical Properties for Analyses presents summary tables of the geotechnical engineering parameters used in our geotechnical analyses. Geotechnical engineering properties were assigned to units within the subsurface profile for use in evaluating the axial and lateral load capacity of CIDH pile foundations for the bridge rehabilitation. Soil unit weights and shear strength parameters have been estimated based on the results of laboratory tests and engineering judgment.

QUINCY ENGINEERING, INC. BRIDGE STREET BRIDGE REHABILITATION ARROYO GRANDE, CALIFORNIA

Fugro Project No. 04.62120100 May 2017 Page 13 of 26

5. CONCLUSIONS AND RECOMMENDATIONS

5.1 Summary of Findings

■ The existing bridge was retrofitted with a supplemental steel truss constructed beneath the north span in or about 1990. The supplemental truss was supported on the existing abutments and pier wall; no foundation improvements were made as part of the project. The bridge inspection reports do not describe the foundation system for the bridge, and we were not able to locate (nor were we provided) as-built subsurface information for the existing bridge.

■ The site subsurface is variable and composed of artificial fill overlying alluvium and Paso Robles Formation materials. The alluvium is composed of medium dense to dense coarse-grained soils, and medium stiff to stiff fine-grained soils. The Paso Robles Formation materials consisted of dense to very dense predominantly gravelly and sandy soils. A hard clay unit was encountered in boring DH-101 at the north abutment at an elevation of about EL. 29 feet to the termination depth of the boring at about EL. -19-1/2 feet. The hard clay unit was not encountered in the ESP (2004) borings to the maximum depth explored by ESP (2004), corresponding to EL. 35 feet. In addition, the Caltrans LOTB for Highway 101 at Arroyo Grande Creek (Caltrans 1957) suggests that similar hard clay materials were not encountered in those explorations.

■ Design subsurface profiles at the north abutment and center pier were primarily developed using the data obtained from boring DH-101, but also considered data from the ESP (2004) borings. The design subsurface profile at the south abutment was primarily developed using the data obtained from the ESP (2004) borings.

■ On the basis of the 65-percent foundation plan (Quincy, 2016) and correspondence with Quincy Engineering, we understand the rehabilitated bridge will be supported on CIDH pile elements deriving frictional resistance from the fine-grained alluvium and Paso Robles Formation materials at the site.

■ Our evaluations included axial and lateral capacity of 36-inch and 48-inch diameter cast-in-drill hole piles at the abutments and an 84-inch diameter CIDH pile at the center pier.

■ Groundwater was encountered in explorations performed by Fugro in 2015 and 2017 and Earth Systems Pacific in 2004 at depths ranging from about 23-1/2 feet to 40-1/2 feet below the ground surface. Groundwater and seepage should be expected during construction and drilling of the CIDH piles.

■ For the purposes of our liquefaction and foundation analyses, groundwater was assumed to be present at an elevation of about EL. 85 feet. We expect that wet placement methods will be needed to construct the CIDH piles, and that the potential for post-installation anomalies should be anticipated.

■ CIDH pile construction should assume “wet hole” conditions. The need for temporary casing and/or use of the slurry displacement methods consistent with Caltrans Standard Specifications should be anticipated to control caving of the sidewalls and to reduce water seepage into the excavation. Based on the anticipated conditions, the length of the temporary casing may be terminated once it is embedded at least 3 feet into the hard claystone encountered at EL. 29 feet in exploratory boring, DH-101, unless caving and water seepage cannot be controlled within the uncased section. Casing advanced drilling equipment or oscillating casing systems should be strongly considered for this project.

■ Permanent casing is not allowed for abutment piles because their capacity is provided by sidewall friction developed between the pile cut-off elevation and the SPTE. Although sidewall friction is also providing capacity for Pier 2, Caltrans requires that permanent casing extend at least 5 feet below a

QUINCY ENGINEERING, INC. BRIDGE STREET BRIDGE REHABILITATION ARROYO GRANDE, CALIFORNIA

Fugro Project No. 04.62120100 May 2017 Page 14 of 26

proposed construction joint. To accommodate that requirement, permanent casing may be used at Pier 2 but it shall only extend 5 feet below the construction joint. Further, it shall consist of corrugated metal pipe (CMP) that is set in an oversized drilled hole. The annular space between pile cutoff to provide adequate load transfer between the pile and excavation. The grout shall be placed under pressure with grout tubes from the bottom of the casing to fill any voids in the annular space.

■ Hard claystone anticipated below EL. 29 feet may become smeared and smooth during drilling resulting in a reduction of the frictional capacity assumed in the design for that geologic unit. The portion of shaft sidewalls exposed below EL. 29 feet or below the bottom of the temporary casing and within the hard clay/claystone should be scored and roughened prior to placing reinforcing steel and concrete.

5.2 Foundation Types

Several foundation types were reviewed and considered for this project including shallow foundations, driven piles, cast-in-steel shell (CISS) piles, and drilled shafts. A discussion of those foundation types and their suitability for this project were provided in Fugro’s Preliminary Foundation Report (Fugro, 2012).

5.3 Foundation Design

We understand the City of Arroyo Grande and the project team have selected CIDH piles as the preferred foundation system for the Bridge Street Bridge Rehabilitation. We consider the proposed CIDH piles feasible from a geotechnical standpoint. Design and construction of CIDH piles will need to consider relatively shallow groundwater within the drilled shaft excavation and the potential for caving of the drilled holes. Wet construction methods will be required and we recommend that temporary casing and drill slurry be used during excavation of the drilled holes. We strongly encourage the City and project team to consider specifying the use of a casing advanced drilling system to construct the foundations. In addition, quality assurance integrity testing of the constructed CIDH piles should be performed.

The following sections provide the results of our evaluations for axial and lateral capacity based on our field and laboratory testing program, and the foundation design data sheet and 65-percent foundation plan prepared by Quincy Engineering (2016).

Abutment 1 at the north end of the bridge will be supported by a single row of four, 48-inch diameter CIDH piles. The southern abutment (abutment 3) will be supported by a single row of five, 36-inch diameter CIDH piles. At pier 2, the foundation will consist of a single 84 inch-diameter CIDH pile. Rock slope protection will be placed at the abutments to counteract local scour impacts. The following foundation data table was provided by Quincy, dated December 15, 2016.

QUINCY ENGINEERING, INC. BRIDGE STREET BRIDGE REHABILITATION ARROYO GRANDE, CALIFORNIA

Fugro Project No. 04.62120100 May 2017 Page 15 of 26

Table 3. Foundation Data Table

Support No.

Design Method Pile Type

Approx. Finished Grade

(ft)

Approx. Cut-Off Elevation

(ft)

Pile Cap Size No of Piles per support B (ft) L (ft)

Abut 1 LRFD 48” Dia. CIDH 112.33 93.42 5 36.2 4

Pier 2 LRFD 60” Dia. Column to 84” Dia. CIDH 83.00 78.90 6.5 35 1

Abut 3 LRFD 36” Dia. CIDH 110.95 97.42 3.5 36.2 5

5.3.1 Axial Capacity of CIDH Piles

We evaluated the axial capacity of the proposed foundations based on the pile types and cut-off elevations provided above in Table 3. The nominal resistance (ultimate geotechnical capacity) of the proposed CIDH pile sizes were evaluated using the methods presented in Caltrans Memo to Designers 3-1, dated June 2014 and the computer program SHAFTv6.0 (ENSOFT, 2012a).

In accordance with Caltrans (2014a), Caltrans Amendments (2014b) and the AASHTO Load Resistance Factor Design (LRFD) Bridge Design Specifications (AASHTO, 2012), foundations for bridge abutments and bents/piers should be designed using Strength Limit State loads and LRFD methods. The nominal resistance of the pile and the estimated tip elevation is provided in Table 5 and is based on the minimum embedment into the alluvium and Paso Robles Formation needed to achieve the nominal resistance equal to the structural load and applied group efficiency and resistance factors. End bearing was not considered in the evaluation of nominal resistance.

The axial capacity evaluation did not include an assessment of the Extreme Event Limit State because Quincy did not provide the structural demand for that load case and it is our understanding that the Strength 2 Limit Strength loading conditions control the design. The granular soils at the site are generally dense to very dense and on a preliminary basis do not appear to be susceptible to liquefaction. Therefore, we have not considered downdrag loads from liquefaction in our assessment of axial capacity.

5.3.2 Lateral Pile Capacity

We evaluated the lateral pile load carrying capacity of the CIDH piles using the computer program LPILE Plus v6.35 (ENSOFT, 2012b), which uses a soil resistance - pile deflection model (p-y analysis) to estimate pile deflections and moment and shear forces in the pile. We used the program to estimate the lateral load at the pile head, maximum shear, maximum moment, and critical length of a single fixed and free head pile for pile head displacements of 0.25 and 1.0 inch.

For our LPILE analyses, the scour conditions provided by Quincy controlled design for the center pier. We assumed lateral loads are applied at the cut-off elevations provided by Quincy (2016b), that the soils surrounding the center pier are removed by scour to the design scour elevations and that level ground conditions exist at the scour elevations. Our LPILE analyses considered a “round concrete shaft (Bored pile)” Section type with a steel percentage of approximately 1.3 percent. We assumed an axial load per pile

QUINCY ENGINEERING, INC. BRIDGE STREET BRIDGE REHABILITATION ARROYO GRANDE, CALIFORNIA

Fugro Project No. 04.62120100 May 2017 Page 16 of 26

equal to the maximum Service-I Limit State axial load from (Quincy 2016b) and we applied the lateral load developed from the displacement analyses for 0.25 and 1-inch deflection. No other applied loads were assumed in our analyses.

Table 4 presents the results of our lateral load analyses to develop a critical length and tip elevation for a single pile. No factor of safety has been applied to the estimated loads or deflections. Piles should be designed to tolerate the estimated bending moments and shear forces for the range of lateral loads and deflections being considered. The estimated tip elevation for the lateral load was estimated from LPILE as 1.3 times the critical length of the pile. The critical pile length is defined as the approximate depth where lengthening the pile does not reduce the pile head deflection under the maximum lateral load considered.

Table 4. Single Pile Critical Length for Static Lateral Loading

Support Pile Type

Cut-off Elevation

(ft)

Pile Head Fixity

Deflection (inches)

Max Shear (kips)

Max Moment (kip-ft)

Estimated Critical Static

Length (ft)

Tip Elevation for Static Lateral

Capacity (ft)

Abutment 1**

48-inch CIDH 93.0

Fixed 0.25 135 1,060 55 +38

Fixed 1.0 303 2,396 55 +38

Free 0.25 71 493 55 +38

Free 1.0 162 1,039 55 +38

Pier 2 84-inch CIDH 78.9*

Fixed 0.25 187 3,855 78 +0.5

Fixed 1.0 404 8,008 78 +0.5

Free 0.25 68 1,546 78 +0.5

Free 1.0 158 4,034 78 +0.5

Abutment 3**

36-inch CIDH 97.0

Fixed 0.25 66 419 46 +51

Fixed 1.0 152 973 46 +51

Free 0.25 32 235 46 +51

Free 1.0 68 437 46 +51 * Scour depth at Pier 2 is 15.8 feet per Quincy (2006b) ** A p-multiplier of 0.8 was applied to the abutment piles to account for group effects

5.3.3 Group Effects

On the basis of the 65 Percent Foundation Plan (Sheet 3), our evaluation for axial and lateral capacity to develop a specified pile tip elevation assumed the center-to-center spacing for the single row of abutment piles will be 2.5-pile diameters at Abutment 1 and 2.6-pile diameters at Abutment 3. In accordance with Caltrans (2014b), we applied a p-multiplier of 0.8 for both axial and lateral capacity to account for group effects with a center-to-center spacing of 2.5-pile diameters.

5.3.4 Settlement

We estimate that static settlement for an isolated pile should not exceed one inch under the allowable design loads. Differential settlements between the supports can be estimated at about half of the estimated total settlement.

QUINCY ENGINEERING, INC. BRIDGE STREET BRIDGE REHABILITATION ARROYO GRANDE, CALIFORNIA

Fugro Project No. 04.62120100 May 2017 Page 17 of 26

5.3.5 Pile Design Data Table

The results of axial and lateral capacity evaluations described in the sections above are summarized in Table 5. Pile Design Data Table. Table 5 provides a summary of our design assumptions, controlling load case, and a recommended specified design tip elevation for the proposed CIDH piles at each bridge support location.

Table 5. Pile Design Data Table

Support Location and Pile

Type

Pile Type

Approx. Cut-Off

Elevation (ft)

Strength Limit State

Design Load

[per pile] (kips)

Required Nominal Resistance (kips) Estimated

Design Tip Elevation1

(ft) Strength Limit Extreme Event

Compression Tens-ion Compression Tens-

ion

Abutment 1

48” CIDH 93 690 1,232(2,3) 0 --(5) 0

16 (a) -- (b) 3 38 (c)

16

Pier 2 84” CIDH 78.9(4) 1,600 2,286(2) 0 --(5) 0

-6 (a) -- (b) 3 0.5 (c)

-6

Abutment 3

36” CIDH 97 180 321(2,3) 0 --(5) 0

39 (a) -- (b) 3 51 (c)

39

Notes: (1) Design tip elevations are controlled by: (a) Strength Limit compression, (b) Extreme Event Limit compression (c) Lateral Load (2) Resistance factor = 0.7 applied to Required Nominal Resistance to equal Design Load (3) Group efficiency factor = 0.8 applied to the Required Nominal Resistance to equal Design Load (4) Scour elevation at Pier 2 is 67.2 feet per Quincy (2016); Soil capacity from the upper 15.8 feet was neglected for potential scour (5) Extreme Event Design Load not provided in Quincy (2016)

5.3.6 Abutment Resistance

Caltrans design methods allow abutments to be designed to resist horizontal seismic forces using an estimated lateral passive force of five kips per foot. The value is likely appropriate provided analysis indicates that the abutments will move into the backfill materials such that the top of the abutment rotates over the base of the abutment or remains vertical.

5.4 Static Lateral Earth Pressures

We recommend the following equivalent fluid weights for use in estimating the lateral earth pressures that will act on bridge abutments designed as retaining walls. The recommended lateral earth pressures are for level backfill conditions and retaining wall backfill material that conforms to the Caltrans Standard Specifications.

QUINCY ENGINEERING, INC. BRIDGE STREET BRIDGE REHABILITATION ARROYO GRANDE, CALIFORNIA

Fugro Project No. 04.62120100 May 2017 Page 18 of 26

Table 6. Lateral Earth Pressures

Wall Loading Condition Lateral Earth Pressure Condition

Equivalent Fluid Weight (pcf)

Unbraced - Drained cantilever wall with level backslope and wall is free to rotate Active 35

Braced - Drained with level backslope and wall is not free to rotate At-rest 55

Unbraced - Undrained cantilever wall with level backslope and wall is free to rotate Active 80

Braced - Undrained with level backslope and wall is not free to rotate At-rest 90

The recommended equivalent fluid weights are provided for drained or undrained backfill conditions. The undrained equivalent fluid weights should be used when considering hydrostatic forces resulting from submerged conditions (i.e., standing water in the backfill material). The equivalent fluid weights do not provide for surcharge loads acting on the backfill. Surcharge traffic loads can be represented by the lateral earth pressures that result from an equivalent 2-foot soil surcharge with a total soil unit weight of 120 pounds per cubic foot (pcf). If surcharge loading from adjacent foundation loads are to be considered, then Fugro should be advised so that we can provide additional recommendations as needed.

5.5 Dynamic Earth Pressures

Dynamic earth pressures were estimated using the Mononobe Okabe approach with a reduced value of kh taken as a percentage of the design horizontal ground acceleration. AASHTO (2012) suggests using a horizontal seismic coefficient equal to about 50 percent of the peak ground acceleration. Based on a kh of 0.35g (about 50 percent of the peak horizontal ground acceleration of 0.69g), the additional force on the wall from earthquake loading is estimated to be about 27H2 (pounds per lateral foot of wall) where H is the wall height in feet. The distribution of seismic pressure can be assumed to be triangular and the resultant can be assumed to act at H/3. The dynamic lateral force increment should be considered as an additional load above the resultant static earth pressure.

5.6 Corrosion Considerations

Corrosion test results are summarized on Plate B-1 and in the table below. For this project, we performed corrosivity tests on samples of artificial fill, alluvium and Paso Robles Formation materials collected from boring DH-101 at the north abutment. According to Caltrans (2012a, 2014b) a site is considered to be corrosive if one or more of the following conditions exist:

■ The pH is 5.5 or less. ■ The soil has a minimal resistivity value of 1,000 ohm-cm or less. ■ Chloride concentration is 500 ppm or greater. ■ Sulfate concentration is 2,000 ppm or greater.

QUINCY ENGINEERING, INC. BRIDGE STREET BRIDGE REHABILITATION ARROYO GRANDE, CALIFORNIA

Fugro Project No. 04.62120100 May 2017 Page 19 of 26

In general, the fill, alluvium and Paso Robles Formation materials tested for this project do not meet the Caltrans criteria for a corrosive environment and in our opinion can be considered non-corrosive toward concrete and steel. We note ESP (2004) reported the results of corrosion tests performed on selected soil samples and those test results also suggest the soils tested would not be considered corrosive towards concrete and steel. Therefore, reinforced concrete piles and substructures can be designed using the minimum cement types and water-cement ratios in accordance with the Standard Specifications.

Most metals are subject to corrosion associated with oxidation. Therefore, metal piping and exposed steel should be designed with appropriate losses for corrosion, coatings or cathodic protection as needed. If needed, a corrosion engineer should be consulted to provide recommendations for test points, cathodic protection or coatings that may be needed for design. We recommend imported backfill material be tested for corrosion potential prior to use on the project.

Table 7. Results of Corrosion Analyses

Boring Depth (feet) Material pH

Chloride Content (ppm)

Sulfate Content (ppm)

Minimum Resistivity (ohm-cm)

DH-101 2.5 Artificial Fill: Clayey SAND (SC) 7.9 7 49 3,900

DH-101 24.0 Alluvium: Poorly-graded SAND with clay and gravel (SP-SC) 8.1 5 31 6,000

DH-101 64.0 Paso Robles Formation: Silty SAND with gravel (SM) 7.5 67 271 1,703

5.7 Roadway Approaches

Site preparation and fill placement for the roadway approaches should be performed according to Section 16, Clearing and Grubbing, and Section 19, Earthwork, of the Caltrans Standard Specifications (Caltrans, 2015b). The recommendations presented below are intended to provide a relatively uniform transition between the approach fill and the proposed structure. In general, approach fill embankments and cut slopes should be designed with a slope inclination of 2H:1V or flatter.

5.7.1 Structure Approach Embankment

The structure approach embankments should be designed according to Topic 670 of the Highway Design Manual (Caltrans, 2012c). Fill materials placed within the structure approach area should be compacted to at least 95-percent relative compaction, except where 90-percent relative compaction is permitted in the outer 5 feet of the embankment.

5.7.2 Use of On-Site Materials

Boring DH-101 and the ESP (2004) borings encountered predominantly silty and clayey sand artificial fill material in the upper 8-1/2 to 10 feet of the soil explored soil profile with fines contents on the order of 26 to 47 percent. Depending on the sand equivalent of those materials, they may not be suitable for use as structure backfill (per Section 19-3.02B of the Caltrans Standard Specifications, 2015b). Quality assurance

QUINCY ENGINEERING, INC. BRIDGE STREET BRIDGE REHABILITATION ARROYO GRANDE, CALIFORNIA

Fugro Project No. 04.62120100 May 2017 Page 20 of 26

acceptance testing should be performed on on-site soils where those soils are proposed for use as structure backfill.

The on-site artificial fill material encountered will likely be suitable for use as local borrow for embankment construction per Caltrans Standard Specifications (2015b).

5.7.3 Approach Fill Settlements

The approaches are anticipated to be constructed near existing site grades, without appreciable addition of embankment fill. Assuming the proposed finished grades are no higher than about two to three feet above existing grade, we expect that the static settlement of the approach fill should be less than about one-inch. In addition, we do not anticipate the CIDH piles will be subjected to downdrag loads from static settlement, and in our opinion, a post-construction waiting period should not be required.

5.8 Pavement Structural Section

One R-value test, which was performed on a sample of the near surface materials at boring DH-101, yielded an R-value of 21. Flexible pavement design sections were estimated using the Caltrans pavement design procedures (Caltrans, 2009) for assumed traffic indices ranging from 5 to 7 assuming an R-value of 21. Recommended preliminary asphalt pavement sections for the access roadway are listed below. R-value tests should be performed during rough grading to confirm that the assumed value of 21 is representative of the as-graded subgrade condition below proposed pavement sections. Imported fill should have an R-value of 21 or greater.

Table 9. Preliminary Asphalt Pavement Sections, R-value: 21

Traffic Index Thickness of Asphalt Concrete (ft)

Thickness of Aggregate Base (ft)

5.0 0.25 0.55

6.0 0.25 0.85

7.0 0.30 1.05

Earthwork and compaction should be performed in accordance with Section 19 of the Caltrans Standard Specifications. Pavement subgrade should consist of compacted materials placed under the observation of the geotechnical professional. If soft or unsuitable soils are exposed in the subgrade for the pavement structural section, stabilization or additional soil removal may be required. Pavement materials should conform to Sections 26 and 39 of the Caltrans Standard Specifications (2015b) (or equivalent) for aggregate base (AB) and hot mix asphalt (HMA), respectively.

5.9 Construction Considerations

5.9.1 Excavation

Materials encountered within the anticipated depth of excavation for the bridge abutments and pier consisted of artificial fill materials, alluvium and minimally-cemented Paso Robles Formation. We anticipate those materials can be excavated with typical heavy construction equipment in good working order. Based on the

QUINCY ENGINEERING, INC. BRIDGE STREET BRIDGE REHABILITATION ARROYO GRANDE, CALIFORNIA

Fugro Project No. 04.62120100 May 2017 Page 21 of 26

conditions encountered in our borings, we do not anticipate adverse geologic structures will be encountered within the anticipated depths of excavation.

5.9.2 Temporary Slopes and Shoring

Temporary slopes should be braced or sloped according to the requirements of OSHA. The contractor should be responsible for job site safety, reviewing the soil conditions encountered during construction, and the design of temporary slopes and shoring systems. Within the expected depth of excavation, the subsurface conditions are anticipated to consist of artificial fill over alluvium and Paso Robles Formation. Based on OSHA guidelines and the anticipated materials to be encountered, temporary slopes should be excavated no steeper than 1.5h:1v or be shored to support Type C soil conditions. It should be noted that driven shoring systems will not be allowed due to site’s proximity to historic buildings and the magnitude of potential vibrations that driven shoring systems could generate.

Temporary slopes should not be considered stable if they will be excavated below the groundwater table or there is a potential for seepage to daylight on the slope face. Dewatering should be performed in advance of excavation if temporary slopes are expected to extend below the water table, and the presence of groundwater should be considered in the design of temporary slopes and shoring.

5.9.3 Groundwater and Dewatering

Groundwater conditions are discussed in Section 3.3 of this report. The depth to groundwater measured in the Fugro and ESP (2004) borings at depths ranged from approximately 23-1/2 to 40-1/2 feet below the existing road surface, corresponding to an elevation range of EL. 70 feet to EL. 82 feet. Groundwater levels are likely influenced by flows in the creek, precipitation/storm runoff, the time of year, irrigation levels, and other factors, and future groundwater levels could be higher than those encountered for this study.

The contractor should be responsible for both designing and maintaining the dewatering system for construction. Dewatering facilities, such as sump pits and wells should be designed by a qualified registered professional and with filters such that sand and fine-grained materials are not removed from the soil during dewatering operations. Dewatering facilities should be installed prior to beginning excavation, and time should be allowed for lowering of the groundwater table before beginning excavation. Shoring systems should be embedded adequately below the base of the excavation to cutoff groundwater and help stabilize the base of the excavation.

5.9.4 CIDH Pile Construction

CIDH piles will extend through predominantly coarse-grained alluvium above the design groundwater elevation and finer grained alluvium and Paso Robles Formation materials at depth. A generalized profile of the subsurface conditions encountered is shown on Plate 3. Excavations for CIDH piles will likely encounter groundwater and soils susceptible to sloughing or caving. Project specifications should indicate that drill casing for the length of the excavation, Caltrans wet construction methods and temporary casing will be required. Additionally, we strongly encourage that a casing advanced type drilling system be considered to install the CIDH piles.

QUINCY ENGINEERING, INC. BRIDGE STREET BRIDGE REHABILITATION ARROYO GRANDE, CALIFORNIA

Fugro Project No. 04.62120100 May 2017 Page 22 of 26

Because of the presence of shallow groundwater and younger alluvial soils at the site, it will be important to maintain a differential head in drilling slurry relative to the groundwater level during construction. The contractor should provide a detailed submittal describing the proposed construction methods, equipment, personnel, sequencing of events, materials, type of slurry, and procedures to monitor and test the condition of the slurry prior to concrete placement. That submittal should be reviewed by the engineer or record prior to mobilization. Procedures for monitoring and testing the slurry should conform to Caltrans requirements. After excavation of a shaft to the design tip elevation, loose or disturbed materials should be removed from the bottom of the pile excavations. The conditions of the drilled hole should be reviewed for stability before placing reinforcing steel and concrete. The concrete should be tremied to displace groundwater (and loose soils) present at the bottom of the hole. If temporary casing is used, the casing should be pulled as the concrete level rises in the drilled shaft. The tremie pipe should remain in the fresh concrete through completion of concrete placement. Improper retrieval of the casing or reinsertion of the tremie pipe can cause necking or contamination of the concrete.

Inspection tubes for gamma-gamma and cross sonic logging (CSL) should be installed by the contractor, and the City of Arroyo Grande should provide for gamma-gamma and CSL testing and evaluation of the completed CIDH piles. Personnel employed to perform and interpret the non-destructive tests should have specific expertise in that type of work.

The contractors' construction submittal should include methods for handling anomalies that are detected from the logging. At the contractors' expense, additional non-destructive logging and/or concrete coring may be performed to confirm or reject detected anomalies. Concrete defects still recognized by the City or the project team after additional testing is performed should be repaired at the contractors' expense or may be deducted from their payment, so long as the design team confirms that the constructed foundation meets all design capacity requirements. Design should consider the potential for irreparable piles and the possibility of replacement or supplemental piles.

We recommend that a geotechnical professional observe the construction of the drilled shaft foundations. The purpose of this observation is to evaluate if the soil conditions encountered and methods of construction are consistent with those assumed for this report. The project specifications should provide for expected variations in the drilling conditions and materials encountered, and for deepening the drilled shaft foundations, if needed.

QUINCY ENGINEERING, INC. BRIDGE STREET BRIDGE REHABILITATION ARROYO GRANDE, CALIFORNIA

Fugro Project No. 04.62120100 May 2017 Page 23 of 26

6. CONTINUATION OF SERVICES

The geotechnical evaluation consists of an ongoing process involving the planning, design and construction phases of the project. To provide this continued service, we recommend that the geotechnical engineer be provided the opportunity to review the project plans and specifications, and observe portions of the construction.

6.1 Review of Plans and Specifications

The geotechnical engineer should review the foundation and grading plans for the project. The purpose of the review is to evaluate if the plans and specifications were prepared in general accordance with the recommendations of this report.

6.2 Geotechnical Observation and Testing

Field exploration and site reconnaissance provides only a limited view of the geotechnical conditions of the site. Substantially more information will be revealed during the excavation and grading phases of the construction. Subsurface conditions, excavations and fill placement should be reviewed by the geotechnical professional during construction to evaluate if the materials encountered during construction are consistent with those assumed for this report.

QUINCY ENGINEERING, INC. BRIDGE STREET BRIDGE REHABILITATION ARROYO GRANDE, CALIFORNIA

Fugro Project No. 04.62120100 May 2017 Page 24 of 26

7. REFERENCES

American Association of State Highway and Transportation Officials [AASHTO] (latest edition), AASHTO LRFD Bridge Specifications, with Caltrans amendments.

California Department of Transportation (Caltrans), Materials Testing Manual (latest edition).

Caltrans (2015a), Foundation Manual, Revision 2, October.

Caltrans (2015b), Standard Specifications.

Caltrans (2014a), Memo to Designers 3-1, Deep Foundations, June.

Caltrans (2014b), California Amendments (to the AASHTO LRFD Bridge Design Specification, 6th Edition).

Caltrans (2013), Seismic Design Criteria, Version 1.7, April 2013, Division of Engineering Services, Structures Design.

Caltrans (2012a), Corrosion Guidelines, Version 2.0, Division of Engineering Services, Materials Engineering and Testing Services, Corrosion and Structural Concrete Field Investigation Branch, November.

Caltrans (2012b), Spreadsheet entitled “Caltrans_Fault_Database_V2b_121312”, at http://dap3.dot.ca.gov/ARS_Online/technical.php, accessed in October 2013.

Caltrans (2012c), Highway Design Manual, dated May 7.

Caltrans (2009), Geotechnical Services Design Manual Version 1.0, dated August 2009.

Caltrans (1939-2011), Bridge Inspection Records, “Bridge Number 19C-0196, Bridge Street, 0.1 MI S. of S.R. 227, Arroyo Grande”, 121 pages of reports dated June 28, 1939 through May 3, 2011.

Caltrans (1957), Log of Test Borings, Arroyo Grande Creek, Bridge 49-175 R/L, Drawing C-4695-9, As-Built Document No. 50000913.

California Geologic Survey (2008), Guidelines for Evaluating and Mitigating Seismic Hazards in California, Special Publication 117A, revised and re-adopted September 11, 2008.

Cao, T., Bryant, W. A., Rowshandel, B., Branum, D., & Wills, C. J., (2002), The Revised 2002 California Probabilistic Seismic Hazard Maps.

County of San Luis Obispo (1999), Safety Element, San Luis Obispo County General Plan, Department of Planning and Building, December.

QUINCY ENGINEERING, INC. BRIDGE STREET BRIDGE REHABILITATION ARROYO GRANDE, CALIFORNIA

Fugro Project No. 04.62120100 May 2017 Page 25 of 26

Earth Systems Pacific [ESP] (2004), Conceptual Soils Engineering Report, Bridge Street Bridge, Bridge Street at Arroyo Grande Creek, Arroyo Grande, California, File No. SL-14066-SA, consultant report prepared for John L. Wallace & Associates, dated March 26, 2004.

Ensoft, Inc. (2012), “Lpile 2012.6.37, a program for analyzing stress and deformation of individual piles or drilled shafts under lateral load”, Austin, Texas.

Ensoft, Inc. (2012), “SHAFT 2012.7.10, a program for analyzing the axial capacity and short-term settlement of drilled shafts under axial load”, Austin, Texas.

Federal Highway Administration [FHWA] (2010), Drilled Shafts: Construction Procedures and LRFD Design Method, Publication No. FHWA-NHI-10-016, NHI Course No. 132014, dated May.

Fred H. Schott & Associates (1989), Plans Entitled “Fabrication and Erection of Supplemental Support System for Bridge Street Bridge, Arroyo Grande, California” Project No. 90-89-2, prepared for the City of Arroyo Grande, dated December 13, 1989. Presented with Caltrans (1939-2011).

Fugro (2015), “Project Memorandum, Preliminary Pile Tip Elevations and Input Parameters for Lateral Loading Analyses, Bridge Street Bridge Replacement, Arroyo Grande, California” Project No. 04.62120100, dated August 11.

Fugro Consultants (2012), Preliminary Foundation Report “Bridge Street Bridge over Arroyo Grande Creek (Bridge No. 49c-0196), Arroyo Grande, California”, Project No. 04.6212.0100, dated November 28.

Holland, Peter J. (2013), Preliminary Geologic Map of Oceano 7.5’ Quadrangle, San Luis Obispo County, California: A Digital Database, Version 1.0. Digital Preparation by Peter J. Holland and Matt D. O’Neal. California Department of Conservation, California Geological Survey, scale 1:24,000.

Hall, C.A., (1973), Geology of the Arroyo Grande 15’ Quadrangle, San Luis Obispo County, California: California Division of Mines and Geology, scale 1:48,000.

Nitchman, S.P., and Slemmons, D.B. (1994), The Wilmar Avenue fault: A late Quaternary reverse faults near Pismo Beach, California: in Alterman, I.B., McMullen, R.B., Cluff, L.S., and Slemmons, D.B. (editors), Seismotectonics of the Central California Coast Range, Geological Society of America Special Paper 292, pp. 103-110.

Pacific Gas and Electric Company (PG&E), (2015), Seismic Source Characterization for the Diablo Canyon Power Plant, San Luis Obispo County, California; report on the results of a SSHAC level 3 study, Rev. A, March. Available online at http://www.pge.com/dcpp-ltsp.

QUINCY ENGINEERING, INC. BRIDGE STREET BRIDGE REHABILITATION ARROYO GRANDE, CALIFORNIA

Fugro Project No. 04.62120100 May 2017 Page 26 of 26

Pradel, D. (1998), "Procedure to Evaluate Earthquake-Induced Settlements in Dry Sandy Soils," Journal of Geotechnical and Geoenvironmental Engineering, Vol. 124, No. 4, April, pp. 364-368 (erratum in the October 1998 issue).

Tokimatsu, K. and Seed, H. B. (1987), "Evaluation of Settlements in Sands Due to Earthquake Shaking," Journal of the Geotechnical Engineering Division, American Society of Civil Engineers, Vol. 113, GT8, pp. 861-878.

Quincy Engineering, Inc. (2016), Foundation Plan, Bridge Street Bridge – Rehabilitation, (Sheet 3 of 31), received December 2016.

Quincy Engineering, Inc. (2016b), Bridge Street Bridge Pile Loads, dated 12/15/16.

Youd, T. L. and Idriss, I.M. (2001), “Liquefaction Resistance of Soils: Summary Report from the 1996 NCEER and 1998 NCEER/NSF Workshops on Evaluation of Liquefaction Resistance of Soils, Co-chairs Youd, T.L. and Idriss, I.M., Journal of Geotechnical and Geoenvironmental Engineering, Vol. 127, No. 10, pp. 817-833.

QUINCY ENGINEERING, INC. BRIDGE STREET BRIDGE REHABILITATION ARROYO GRANDE, CALIFORNIA

Fugro Project No. 04.62120100 Plates

PLATES

_̂Site

Location

5780000

5780000

5790000

5790000

2230

000

2230

000

2240

000

2240

000

2250

000

2250

000

Quincy EngineeringProject No. 04.62120100

VICINITY MAPBridge St. Bridge Rehabilitation

Arroyo Grande, California PLATE 1

Service Layer Credits: Sources: Esri, HERE, DeLorme, USGS, Intermap, increment P Corp.,NRCAN, Esri Japan, METI, Esri China (Hong Kong), Esri (Thailand), MapmyIndia, ©OpenStreetMap contributors, and the GIS User Community

Ü1:48,000

0 4,000 8,0002,000Feet

Y:\J

obdo

cs\0

4_20

12\0

4.62

1201

00_B

ridge

StBr

idge

\GIS

\Out

puts

\201

7_04

_26_

Geo

tech

Rep

ort_

Fina

l\mxd

\Pla

te1_

Vici

nity

Map

.mxd

, 4/2

7/20

17, c

.dea

n

!<

!<

!<

!P

Arroyo Grande Creek

Bridge Street

Olohan Alley

A

A'

B-3

B-2

B-1DH-101

80

80

80

80

80

80

85

85

85

85

85

90

90

90

90

90

90

95

95

95

95

100

100

100

100

100

100

105

105

105

5

105

110110

110

110

110

110

115

5790400

5790400

5790600

5790600

5790800

5790800

2240

600

2240

600

2240

800

2240

800

2241

000

2241

000

Quincy EngineeringProject No. 04.62120100

EXPLORATION LOCATION MAPBridge St. Bridge Rehabilitation

Arroyo Grande, California

PLATE 2

Ü0 60 12030

Feet

1:600

Legend

Topography Contours

!P Approximate Fugro 2015 Boring Location

!< Approximate Earth Systems Pacific2004 Boring Location

Major Contour

Minor Contour

Base Map

Cross Section Location

Service Layer Credits: Source: Esri, DigitalGlobe, GeoEye, EarthstarGeographics, CNES/Airbus DS, USDA, USGS, AEX, Getmapping, Aerogrid,IGN, IGP, swisstopo, and the GIS User Community

Y:\J

obdo

cs\0

4_20

12\0

4.62

1201

00_B

ridge

StBr

idge

\GIS

\Out

puts

\201

7_04

_26_

Geo

tech

Rep

ort_

Fina

l\mxd

\Pla

te2_

Expl

_Pla

n.m

xd, 4

/27/

2017

, c.d

ean

@@@@

@@

@@

@@

@@@@ @@ @@@@ @@ @@ @@ @@ @@ @@ @@ @@ @@

@@

@@ @@ @@ @@ @@

@@ @@@@

@@@@

@@@@

@@@@ @@

@@@@ @@

!P!<!<

!<

-20

0

20

40

60

80

100

-20

0

20

40

60

80

100

00+00 0+20 0+40 0+60 0+80 1+00 1+20 1+40 1+60 1+80 2+00

ELEV

ATIO

N (F

EET)

ELEV

ATIO

N (F

EET)

DISTANCE (FEET)

AN31W

A'S31E

DH

-101

7 ft,

Eas

t

B-1

6 ft,

Wes

t

B-2

5 ft,

Wes

t

B-3

4 ft,

Wes

t

<11><7>4

<6>12

<24>

33

<32>

22

<10>

<49>

<93/11.5">

<38>

<42>

<35>

<48>

<45>

<Ref/5">

<50/5">

38

<50/4">

<92/12"><46>

<88/10.5">

42

<85/9">

60

70

<16>

<14>

8

30

58

<36>

12

<52>

37

80

54

<8>

<28>

40

<36>

22

23

<50/5">

66

50/4.5"

<12>

<50/6">

50/5"

<19>

13

50/5"

<18>

50/6"

83

50/5"

80

Arroyo Grande Creek Channel

Qal 3

Qpr

Qal 3

Qal 2

Qal 2

af/Qal 1

af/Qal 1

Design Water Elevation (El. +85)80 80

CROSS SECTION A-A'Bridge Street Bridge Rehabilitation

Arroyo Grande, California

PLATE 3

Subsurface profile is interpolated between points of exploration and will vary from that shown.

See text and logs for additional description and data concerning subsurface conditions.

All locations and information are approximate.

Boring Legend

20 SPT Blow Counts

80 Final Water Levels

<32>CA Liner Blow Counts Convertedto Equivalent Blow Count

Lean CLAY (CL)

Silty CLAY (CL-ML)

! !

! !

Lean CLAY with Sand (CL)

! ! !

! ! !

! ! !

Sandy Lean Clay (CL)

Fat CLAY (CH)

! ! ! ! ! !

! ! ! ! ! !

! ! ! ! ! !

! ! ! ! ! !

Sandy SILT (ML)

! ! ! ! ! !

! ! ! ! ! !

! ! ! ! ! !

! ! ! ! ! !

! ! ! ! ! !

! ! ! ! ! !

! ! ! ! ! !

! ! ! ! ! !

! ! ! ! ! !

! ! ! ! ! !

Poorly-Graded SAND (SP)

! ! ! ! ! !

! ! ! ! ! !

! ! ! ! ! !

! ! ! ! ! !

! ! ! ! ! !

! ! ! ! ! !

! ! ! ! ! !

! ! ! ! ! !

! ! ! ! ! !

! ! ! ! ! !

Poorly-Graded SAND with Clay (SP-SC)

Well-Graded SAND (SW)

Well-Graded SAND with Clay (SW-SC)

Clayey SAND (SC)

Clayey to Silty SAND (SC-SM)

Silty SAND (SM)

! ! !

! ! !

! ! !

! ! !

! ! !

Poorly-Graded GRAVEL with Clay (GP-GC)

Well-Graded GRAVEL with Clay (GW-GC)

! ! ! ! !

! ! ! ! !

! ! ! ! !

! ! ! ! !

Sandy Well-Graded GRAVEL (GW)

Asphaltic Concrete

20 ft

20 ftVertical Exaggeration = 1.0X

Quincy EngineeringProject No. 04.62120100

Notes

af/Qal 1- Artificial Fill/Alluvium- very loose to medium dense clayey and silty sandwith layers of sandy lean clay

Qal 2- Alluvium- medium dense sand, silty sand and clayey sand with little to somegravel, cobbles, occasional very stiff to hard clay layers

Qal 3- Alluvium- medium stiff to stiff lean to fat clay

Qpr- Paso Robles Formation- dense to very dense poorly to well graded gravel with sand and clay, occasional cobbles and boulders. hard clay encountered below El. 20 feet.

Geology Legend

Y:\J

obdo

cs\0

4_20

12\0

4.62

1201

00_B

ridge

StBr

idge

\GIS

\Out

puts

\201

7_04

_26_

Geo

tech

Rep

ort_

Fina

l\mxd

\Pla

te3_

Prof

A.m

xd, 4

/27/

2017

, c.d

ean

Quincy EngineeringProject No. 04.62120100

DESIGN ACCELERATION RESPONSE SPECTRUMBridge Street Bridge Rehabilitation

Arroyo Grande, California

0.0

0.2

0.4

0.6

0.8

1.0

1.2

1.4

1.6

0 0.5 1 1.5 2 2.5 3 3.5 4 4.5 5

Spec

tral

Acc

eler

atio

n, S

a (g

)

Period , T (sec)

Los Osos Deterministic Spectrum

Southern San Luis Range Deterministic Spectrum

Probabilistic Response Spectrum

PGA of Design Response Spectrum = 0.69g

Design Response Spectrum

Estimated Shear Wave Velocity: 300 m/sSite Coordinates: 35.1226 lat -120.5786 longLos Osos Maximum Magnitude: 6.9So. San Luis Range Maximum Magnitude: 7.1Spectral Damping = 5 percent(Updated 2/27/17)

T(sec) Sa(g)0.01 0.6980.05 0.8440.1 1.0580.15 1.2160.2 1.3090.25 1.340.3 1.340.4 1.3360.5 1.3420.6 1.3260.7 1.3130.85 1.2631 1.2021.2 1.0441.5 0.8582 0.5953 0.3264 0.215 0.16

PLATE 4

Quincy EngineeringProject No. 04.62120100

GEOTECHNICAL PROPERTIES FOR ANALYSESBridge Street Bridge Rehabilitation

Arroyo Grande, CaliforniaPLATE 5

Worksheet: Geotechnical Properties For AnalysesClient: Quincy Engineering Project No. 4.62120100Job Name: Bridge Street Bridge RehabilitationEngineer: LBDate: 4/28/17

Notes: Scour estimate provided by Quincy Lpile analyses utilized default values for ks and E50

NORTH ABUTMENT (DH-101, B-1 [ESP,2004])

Existing Ground el: 112.0 feetPile Cutoff el. 93.0 feetExisting Streambed 77.0 feetEstimated Scour el. 93.0 feetDesign GW el. 85.0 feet

Elevation Interval (feet)

Depth below Ground

Depth below Scour

Depth below Footing: Predominant Material Type within Unit Unit Weight Eff. Unit Wt. Blowcounts Friction

Angle Cohesion

(top/bottom) (feet) (feet) (feet) (pcf) (pcf) N60 (degrees) (psf)

112 0 --- -19

102 10 --- -9

102 10 --- -9

83 29 10 10

83 29 10 10

74 38 19 19

74 38 19 19

28 84 65 65

28 84 65 65

-19 131 112 112

SOUTH ABUTMENT (B-2 [ESP, 2004])

Existing Ground el: 110.0 feetPile Cutoff el. 97.0 feetExisting Streambed 77.0 feetEstimated Scour el. 97.0 feetDesign GW el. 85.0 feet

Elevation Interval (feet)

Depth below Ground

Depth below Scour

Depth below Footing: Predominant Material Type within Unit Unit Weight Eff. Unit Wt. Blowcounts Friction

Angle Cohesion

(top/bottom) (feet) (feet) (feet) (pcf) (pcf) NField (degrees) (psf)

110 0 --- -13

86 24 11 11

86 24 11 11

77 33 20 20

77 33 20 20

44 66 53 53

44 66 53 53

33 77 64 64

CENTER PIER (B-3 [ESP, 2004])

Existing Ground el: 94.0 feetPile Cutoff el. 79.0 feetExisting Streambed 77.0 feetScour elevation (estimated) 67.2 feetConstruction Joint elevation (estimated)Design GW el. 85.0 feet

Elevation Interval (feet)

Depth below Ground

Depth below Scour

Depth below Footing: Predominant Material Type within Unit Unit Weight Eff. Unit Wt. Blowcounts Friction

Angle Cohesion

(top/bottom) (feet) (feet) (feet) (pcf) (pcf) NField (degrees) (psf)

94 0 --- -15

89 5 --- -10

89 5 --- -10

75.5 18.5 --- 3.5

75.5 18.5 --- 3.5

50 44 17.2 29

50 44 17.2 29

28 66 39.2 51

28 66 39.2 51

-- -- -- --

600

--

4700

--

Medium Dense to Dense Sand with Gravel (modeled as API Sand in LPILE and Sand in

SHAFT)110 48 50+ 35 --

--

--

600

--

4700

Qal2Dense to Very Dense Sand with Gravel

(modeled as API Sand in LPILE and Sand in SHAFT)

100 38 35 --

14

17 to 50+ --

50+

50+

50+

50+

9 to 48

--

35

--

--

600

af/Qal1 Stiff Sandy Lean Clay 105 43

Qpr

Dense to Very Dense Sand with Gravel (modeled as API Sand in LPILE and Sand in

SHAFT)100 38

38

Geologic Unit

Geologic Unit

Qal3 Medium Stiff to Stiff Lean/Fat Clay(modeled as Soft Clay in LPILE and Clay in SHAFT)

af/Qal1

22 to 50+

50+

7 to 13

15 to 29

13 to 45

Soft to Stiff Sandy Silt(modeled as Soft Clay in LPILE and Clay in SHAFT)

Medium Stiff to Very Stiff Sandy Lean Clay (modeled as Soft Clay in LPILE and Clay in SHAFT) 100 38

--

Very Loose Clayey Sand and Stiff to Very Stiff Sandy Lean Clay

QprHard Lean to Fat Clay

(modeled as Mod. Stiff Clay w/o Free Water in LPILE and Clay in SHAFT)

QprMedium Dense to Dense Sand with Gravel

(modeled as API Sand in LPILE and Sand in SHAFT)

38

Geologic Unit

Loose to Dense Clayey Sand(modeled as API Sand in LPILE and Sand in

SHAFT)

Qal3

105 43

Qal2Medium Dense to Dense Sand with Gravel

(modeled as API Sand in LPILE and Sand in SHAFT)

100

110 48

35

100

--

50+ 35

QprDense to Very Dense Sand with Gravel

(modeled as API Sand in LPILE and Sand in SHAFT)

110 48

100

af/Qal1 95 33

63125

30

--

38

Qal3

Qal2

--QprHard Lean to Fat Clay

(modeled as Mod. Stiff Clay w/o Free Water in LPILE and Clay in SHAFT)

125 63

35

--

May 1, 2017

QUINCY ENGINEERING, INC. BRIDGE STREET BRIDGE REHABILITATION ARROYO GRANDE, CALIFORNIA

Fugro Project No. 04.62120100 Appendices

APPENDIX A SUBSURFACE EXPLORATION

PLATE A-1

Quincy EngineeringProject No. 04.62120100

10

Symbol for:

CA Liner Sampler, driven

Vibracore Sample

Pitcher Sample

Lexan Sample

BASALT

Sonic Soil Core Sample

No Sample Recovered

CA Liner Sampler, Bagged

13

(25)

6

11

4

Poorly graded SAND (SP)

COARSE

GRAINED

MATERIAL DESCRIPTION

Silty CLAY (CL-ML)

Silty SAND (SM)

Paving and/or Base Materials

SANDSTONE

Poorly graded GRAVEL (GP)

MUDSTONE

SY

MB

OL

SILTSTONE

Well graded SAND (SW)

Fat CLAY (CH)

MA

TE

RIA

L

SA

MP

LE N

O.

Hand Auger Sample

ANDESITE BRECCIA

7

9

5

Thin-walled Tube, pushed

CONGLOMERATE

3

FINE

GRAINED

ROCK

-12

-14

-16

-18

-20

-22

-24

-26

-28

-30

-32

-34

-36

-38

-40

-42

-44

-46

-48

2

4

6

8

10

12

14

16

18

20

22

24

26

28

30

32

34

36

38

25

Silty, Clayey SAND (SC-SM)

(25)

Elastic SILT (MH)

(25)

(25)

Lean CLAY (CL)

Sampler Driving Resistance

p = Pocket Penetrometer

Q = Unconfined Compressionu = Unconsolidated Undrained Triaxial

Initial or perched water level

Seepages encounteredFinal ground water level

Bulk Bag Sample (from cuttings)

Number of blows with 140 lb. hammer, falling30" to drive sampler 1 ft. after seatingsampler 6"; for example,

CLAYSTONE

LOCATION:

SILT (ML)

2

5

13

9

1

8

7

SA

MP

LES

Clayey SAND (SC)

The drill hole location referencing locallandmarks or coordinates

Well graded GRAVEL (GW)B

LOW

CO

UN

T /

t = Torvane

Blows/ft Description

25

Blow counts for California Liner Samplershown in ( )

Geologic Formation noted in bold font atthe top of interpreted interval

Classification of Soils per ASTM D2487 orD2488

Strength Legend

Length of sample symbol approximatesrecovery length

Water Level Symbols

SURFACE EL: Using local, MSL, MLLW or other datum

KEY TO TERMS & SYMBOLS USED ON LOGS

12

m = Miniature Vane

Samplers and sampler dimensions

Soil Texture Symbol

General Notes

Sloped line in symbol column indicatestransitional boundary

(unless otherwise noted in report text) are as follows:

3 CA Liner Sampler, disturbed

11

1 SPT Sampler, driven

6

8

2

4

CME Core Sample

12

10

BORING LOG KEY VENTURA C:\USERS\GECKRICH\DESKTOP\ACTIVE PROJECTS\04.62120100 BRIDGE ST. BRIDGE\GINT\04_6212_0100_VQ15B.GPJ 6/1/16 02:22 p

30"/30"

20"/24"

DE

PT

H, f

t

RE

C"/

DR

IVE

"

18"/30"

20"/24"

ELE

VA

TIO

N, f

t

50 blows drove sampler 3" duringinitial 6" seating interval

Ref/3"

50 blows drove sampler 6" afterinitial 6" of seating

After driving sampler the initial 6"of seating, 36 blows drovesampler through the second 6"interval, and 50 blows drove thesampler 5" into the third interval

50/6"

86/11"

25 blows drove sampler 12" afterinitial 6" of seating

Rock Quality Designation (RQD) is thesum of recovered core pieces greater than4 inches divided by the length of the coredinterval.

1-3/8" ID, 2" OD

2-3/8" ID, 3" OD

2-3/8" ID, 3" OD

2-7/8" ID, 3" OD

p 2.5

p 4.0

p 0.8

t 0.7

p 1.3

t 1.7

A

1

2

3

4

5

6

7A

7B

8

9A

9B

10

11

47

35

25

16

9

10

27

45

N/A

(18)

(11)

4

(10)

12

(39)

33

(51)

22

(16)

(79)

13

14

21

17

12

30

19

127

127

121

119

117

126

ARTIFICIAL FILL (af) 3.5" AC over 9" Base material over geotextile fabricClayey SAND (SC): medium dense, dark brown to

black, moist, fine to medium sand, some to mostlymoderate to high plasticity fines

- loose at 2.5'- very loose at 4'

Sandy lean CLAY (CL): very stiff, black matrix, moist,fine sand to fine angular gravel up to 2" diameter,asphalt inclusions

ALLUVIUM (Qal)Silty SAND (SM): medium dense, light brown, moist,

fine sand

Clayey SAND with gravel (SC): medium dense, blackto dark brown, moist, fine to coarse sand, fine tomedium angular gravel up to 2" diameter, pale grayshale and red sandstone clasts

Fat CLAY (CH): very stiff to hard, black, moist

Poorly graded SAND with clay and gravel (SP-SC):medium dense, gray to dark gray matrix, moist, littleto some fine to coarse sand, fine to medium angulargravel up to 2" diameter, shale and sandstone clasts

- dense at 24'

Fat CLAY (CH): medium stiff, brown with light brownmottling, moist, few subangular fine to mediumgravel up to 1" diameter, trace decomposed roots,grades to clayey SAND (SC) from 30-30.5 ft,medium dense, brown, moist

- medium stiff to stiff at 34'

PASO ROBLES FORMATION (QTp)Poorly graded GRAVEL with clay and sand (GP-GC):

very dense, brown to light brown, wet, few moderate

112

112

101

101

90

106

11

24

% P

AS

SIN

G#2

00 S

IEV

E

The log and data presented are a simplification of actual conditions encountered at the time of drilling at the drilled location. Subsurface conditions may differ at other locations and with the passage of time.

SA

MP

LER

SMATERIAL DESCRIPTION

PLA

ST

ICIT

YIN

DE

X, %

DEPTH TO WATER: 28.0 ft

LOG OF DRILL HOLE NO. DH-101

SURFACE EL: 112 ft +/- (rel. MSL datum)

Refer to Exploration Location MapN 2,240,890.1 E 5,790,597.9CA State Plane, Zone 5, NAD83, Feet

UN

IT D

RY

WE

IGH

T, p

cf

2

4

6

8

10

12

14

16

18

20

22

24

26

28

30

32

34

36

38

LIQ

UID

LIM

IT, %

UN

IT W

ET

WE

IGH

T, p

cf

SA

MP

LE N

O.

MA

TE

RIA

LS

YM

BO

L

ELE

VA

TIO

N, f

t

WA

TE

RC

ON

TE

NT

, %

LOCATION:

DRILLING METHOD: 8-inch-dia. Hollow Stem AugerHAMMER TYPE: Automatic Trip

DRILLED BY: S/G Drilling CompanyLOGGED BY: G Eckrich and T Gebhart

CHECKED BY: G S Denlinger

COMPLETION DEPTH: 131.5 ft

DRILLING DATE: March 29, 2017BACKFILLED WITH: 2-Sack Slurry with Asphalt Concrete Cap

110

108

106

104

102

100

98

96

94

92

90

88

86

84

82

80

78

76

74

DE

PT

H, f

t

PLATE A-2a

UN

DR

AIN

ED

SH

EA

RS

TR

EN

GT

H, S

u, k

sf

SA

MP

LER

BLO

W C

OU

NT

Project No. 04.62120100Quincy Engineering

Bridge Street Bridge RehabilitationArroyo Grande, California

BORING LOG VENTURA N:\PROJECTS\04_2012\04_6212_0100_BRIDGESTBRIDGE_INWC_DONOTUSE\EXPLORATIONS\GINT\2015\04_6212_0100_VQ15B.GPJ 4/27/17 05:11 p

12

13

14

15

16A16B

17

18

19

15

18

26

19

(93/11.5")

(60)

(67)

(56)

(77)

(72)

(Ref/5")

(50/5")

36

20

32

23

17

126

127

109

121

125

plasticity fines, fine to coarse sand, fine to mediumsubangular to angular gravel up to 1" diameter,shale clasts

- dense at 49'

- grades to clayey sand with gravel (SC)

- some to mostly angular to subrounded gravel up to2" diameter, trace lenses of lean clay (CL)

- grades to silty sand with gravel (SM)

- sulphur odor

93

106

83

99

108

% P

AS

SIN

G#2

00 S

IEV

E

The log and data presented are a simplification of actual conditions encountered at the time of drilling at the drilled location. Subsurface conditions may differ at other locations and with the passage of time.

SA

MP

LER

SMATERIAL DESCRIPTION

PLA

ST

ICIT

YIN

DE

X, %

DEPTH TO WATER: 28.0 ft

LOG OF DRILL HOLE NO. DH-101

SURFACE EL: 112 ft +/- (rel. MSL datum)

Refer to Exploration Location MapN 2,240,890.1 E 5,790,597.9CA State Plane, Zone 5, NAD83, Feet

UN

IT D

RY

WE

IGH

T, p

cf

42

44

46

48

50

52

54

56

58

60

62

64

66

68

70

72

74

76

78

LIQ

UID

LIM

IT, %

UN

IT W

ET

WE

IGH

T, p

cf

SA

MP

LE N

O.

MA

TE

RIA

LS

YM

BO

L

ELE

VA

TIO

N, f

t

WA

TE

RC

ON

TE

NT

, %

LOCATION:

DRILLING METHOD: 8-inch-dia. Hollow Stem AugerHAMMER TYPE: Automatic Trip

DRILLED BY: S/G Drilling CompanyLOGGED BY: G Eckrich and T Gebhart

CHECKED BY: G S Denlinger

COMPLETION DEPTH: 131.5 ft

DRILLING DATE: March 29, 2017BACKFILLED WITH: 2-Sack Slurry with Asphalt Concrete Cap

70

68

66

64

62

60

58

56

54

52

50

48

46

44

42

40

38

36

34

DE

PT

H, f

t

PLATE A-2b

UN

DR

AIN

ED

SH

EA

RS

TR

EN

GT

H, S

u, k

sf

SA

MP

LER

BLO

W C

OU

NT

Project No. 04.62120100Quincy Engineering

Bridge Street Bridge RehabilitationArroyo Grande, California

BORING LOG VENTURA N:\PROJECTS\04_2012\04_6212_0100_BRIDGESTBRIDGE_INWC_DONOTUSE\EXPLORATIONS\GINT\2015\04_6212_0100_VQ15B.GPJ 4/27/17 05:11 p

p 4.5+

p 4.5+u 10.7

p 4.5+

p 4.5+

p 4.5+u 8.1

p 4.5+

p 4.5+u 8.4

20

21

22A22B

23

24

25

26

88 Q 4.7Q 3.1

38

(50/4")

(92/12")

(73)

(88/10.5")

42

(85/9")

36

39

47

38

45

107

108

105

108

109

Lean to Fat CLAY (CL to CH): hard, light gray towhite, moist, strong sulphur odor, occasional darkercolored seams

79

78

72

79

75

% P

AS

SIN

G#2

00 S

IEV

E

The log and data presented are a simplification of actual conditions encountered at the time of drilling at the drilled location. Subsurface conditions may differ at other locations and with the passage of time.

SA

MP

LER

SMATERIAL DESCRIPTION

PLA

ST

ICIT

YIN

DE

X, %

DEPTH TO WATER: 28.0 ft

LOG OF DRILL HOLE NO. DH-101

SURFACE EL: 112 ft +/- (rel. MSL datum)

Refer to Exploration Location MapN 2,240,890.1 E 5,790,597.9CA State Plane, Zone 5, NAD83, Feet

UN

IT D

RY

WE

IGH

T, p

cf

82

84

86

88

90

92

94

96

98

100

102

104

106

108

110

112

114

116

118

LIQ

UID

LIM

IT, %

UN

IT W

ET

WE

IGH

T, p

cf

SA

MP

LE N

O.

MA

TE

RIA

LS

YM

BO

L

ELE

VA

TIO

N, f

t

WA

TE

RC

ON

TE

NT

, %

LOCATION:

DRILLING METHOD: 8-inch-dia. Hollow Stem AugerHAMMER TYPE: Automatic Trip

DRILLED BY: S/G Drilling CompanyLOGGED BY: G Eckrich and T Gebhart

CHECKED BY: G S Denlinger

COMPLETION DEPTH: 131.5 ft

DRILLING DATE: March 29, 2017BACKFILLED WITH: 2-Sack Slurry with Asphalt Concrete Cap

30

28

26

24

22

20

18

16

14

12

10

8

6

4

2

0

-2

-4

-6

DE

PT

H, f

t

PLATE A-2c

UN

DR

AIN

ED

SH

EA

RS

TR

EN

GT

H, S

u, k

sf

SA

MP

LER

BLO

W C

OU

NT

Project No. 04.62120100Quincy Engineering

Bridge Street Bridge RehabilitationArroyo Grande, California

BORING LOG VENTURA N:\PROJECTS\04_2012\04_6212_0100_BRIDGESTBRIDGE_INWC_DONOTUSE\EXPLORATIONS\GINT\2015\04_6212_0100_VQ15B.GPJ 4/27/17 05:11 p

p 4.5+

p 4.5+

27

28

60

70

- gray to dark gray below 125 feet

7/6/15: Borehole terminated at 95.5 feet,Groundwater measured at 40.5 feet, Backfilled with1-sack slurry

3/29/17: Borehole extended to 131.5 feet,Groundwater measured at 28 feet, Backfilled with2-sack slurry

% P

AS

SIN

G#2

00 S

IEV

E

The log and data presented are a simplification of actual conditions encountered at the time of drilling at the drilled location. Subsurface conditions may differ at other locations and with the passage of time.

SA

MP

LER

SMATERIAL DESCRIPTION

PLA

ST

ICIT

YIN

DE

X, %

DEPTH TO WATER: 28.0 ft

LOG OF DRILL HOLE NO. DH-101

SURFACE EL: 112 ft +/- (rel. MSL datum)

Refer to Exploration Location MapN 2,240,890.1 E 5,790,597.9CA State Plane, Zone 5, NAD83, Feet

UN

IT D

RY

WE

IGH

T, p

cf

122

124

126

128

130

132

134

136

138

140

142

144

146

148

150

152

154

156

158

LIQ

UID

LIM

IT, %

UN

IT W

ET

WE

IGH

T, p

cf

SA

MP

LE N

O.

MA

TE

RIA

LS

YM

BO

L

ELE

VA

TIO

N, f

t

WA

TE

RC

ON

TE

NT

, %

LOCATION:

DRILLING METHOD: 8-inch-dia. Hollow Stem AugerHAMMER TYPE: Automatic Trip

DRILLED BY: S/G Drilling CompanyLOGGED BY: G Eckrich and T Gebhart

CHECKED BY: G S Denlinger

COMPLETION DEPTH: 131.5 ft

DRILLING DATE: March 29, 2017BACKFILLED WITH: 2-Sack Slurry with Asphalt Concrete Cap

-10

-12

-14

-16

-18

-20

-22

-24

-26

-28

-30

-32

-34

-36

-38

-40

-42

-44

-46

DE

PT

H, f

t

PLATE A-2d

UN

DR

AIN

ED

SH

EA

RS

TR

EN

GT

H, S

u, k

sf

SA

MP

LER

BLO

W C

OU

NT

Project No. 04.62120100Quincy Engineering

Bridge Street Bridge RehabilitationArroyo Grande, California

BORING LOG VENTURA N:\PROJECTS\04_2012\04_6212_0100_BRIDGESTBRIDGE_INWC_DONOTUSE\EXPLORATIONS\GINT\2015\04_6212_0100_VQ15B.GPJ 4/27/17 05:11 p

QUINCY ENGINEERING, INC. BRIDGE STREET BRIDGE REHABILITATION ARROYO GRANDE, CALIFORNIA

Fugro Project No. 04.62120100 Appendices

APPENDIX B LABORATORY TEST RESULTS

DH-101 0.0 A Clayey SAND (SC) 114.0 8.5 21

DH-101 1.0 1 Clayey SAND (SC) 127 112 13 47

DH-101 2.5 2 Clayey SAND (SC) 127 112 14 3900 7.90 7 49.0

DH-101 4.0 3 Clayey SAND (SC) 35

DH-101 9.0 4 Sandy Lean CLAY (CL) 121 101 21 27 11

DH-101 10.5 5 Silty SAND (SM) 25

DH-101 14.0 6 Clayey SAND with gravel (SC) 119 101 17 16

DH-101 24.0 8 Poorly graded SAND with clay and gravel (SP-SC) 12 9 6000 8.10 5 31.0

DH-101 34.0 10 Lean CLAY (CL) 117 90 30 45 24

DH-101 39.0 11 Poorly graded GRAVEL with clay and sand (GP-GC) 126 106 19 10

DH-101 44.0 12 Poorly graded GRAVEL with clay and sand (GP-GC) 126 93 36

DH-101 54.0 14 Clayey SAND with gravel (SC) 127 106 20 15

DH-101 64.0 16A Silty SAND with gravel (SM) 109 83 32 18 1703 7.50 67 271.0

DH-101 69.0 17 Silty SAND with gravel (SM) 121 99 23 26

DH-101 79.0 19 Silty SAND with gravel (SM) 125 108 17 19

DH-101 89.0 21 Lean to Fat CLAY (CL to CH) 107 79 36 10.7(10.7)

DH-101 94.0 22A Lean to Fat CLAY (CL to CH) 108 78 39 88 9.3

DH-101 94.5 22B Lean to Fat CLAY (CL to CH) 105 72 47 6.1

DH-101 100.0 24 Lean to Fat CLAY (CL to CH) 108 79 38 8.1(7)

DH-101 115.0 26 Lean to Fat CLAY (CL to CH) 109 75 45 8.4(7)

CO

MP

RE

SS

IVE

ST

RE

NG

TH

TE

ST

S

Bridge Street Bridge RehabilitationArroyo Grande, California

DRILLHOLE

Qu,ksf

FINES%

MAXDDpcf

LA

B S

UM

MA

RY

TA

BL

E V

EN

TU

RA

_N:\P

RO

JEC

TS

\04_2012\04_6212_01

00_BR

IDG

ES

TB

RID

GE

_INW

C_D

ON

OT

US

E\E

XP

LOR

AT

ION

S\G

INT

\2015\04_6212_0100

_VQ

15B.G

PJ_ 4/28/17 09:00 A

M-cab

MC%

UDWpcf

SA

ND

EQ

UIV

ALE

NT

(SE

)

SA

MP

LE N

UM

BE

R

AT

TE

RB

ER

GLI

MIT

S

DE

PT

H, f

t

LL

UWWpcf

OPTMC%

DIR

EC

TS

HE

AR

ClR pH

CORROSIVITY TESTS

PLA

TE

B-1

MATERIAL DESCRIPTION

PHIdeg

SUMMARY OF LABORATORY TEST RESULTS

So4

(ppm)

Spe

cific

Gra

vity

R-V

ALU

E

CO

MP

AC

TIO

NT

ES

T

SU(Cell Prs.)

ksfCksf

PI EX

PA

NS

ION

IND

EX

Project N

o. 04.6212

0100Q

uincy Engin

eering

0

10

20

30

40

50

60

70

80

90

100

0.0010.010.1110100

SANDSILT or CLAY

Fine Coarse

PE

RC

EN

T F

INE

R B

Y W

EIG

HT

Medium FineCoarse

GRAIN SIZE IN MILLIMETERS

GRAVEL

GRAIN SIZE CURVES

PLATE B-2

Project No. 04.62120100Quincy Engineering

Bridge Street Bridge RehabilitationArroyo Grande, California

GRAIN SIZE CURVES VENTURA (C:\USERS\GECKRICH\DESKTOP\ACTIVE PROJECTS\04.62120100 BRIDGE ST. BRIDGE\GINT\04_6212_0100_VQ15B.GPJ) 6/1/16 02:26 p-sz

HYDROMETER ANALYSIS

20

LEGEND

40 1003 1.5 3/4 3/8 4

(depth,ft)CLASSIFICATION Cc Cu

38.885.6

Clayey SAND with gravel (SC)Poorly graded SAND with clay and gravel (SP-SC)

Poorly graded GRAVEL with clay and sand (GP-GC)Silty SAND with gravel (SM)

DH-101DH-101DH-101DH-101

(location)

US STD SIEVE SIZEINCHES

200

US STD SIEVE SIZENUMBERS

14.024.039.064.0

3.65.3

10

0

10

20

30

40

50

60

70

80

90

100

0 10 20 30 40 50 60 70 80 90 100

9.0

34.0

DH-101

DH-101

27

45

CH or OH

ML or OL

MH or OH

LEGENDlocation

LIQUID LIMIT (LL)

PLASTICITYLIQUIDLIMIT(LL)

PLASTICLIMIT(PL)

Sandy Lean CLAY (CL)

Lean CLAY (CL)

depth, ft

ATTERBERG LIMITS TEST RESULTS

PLA

ST

ICIT

Y IN

DE

X (

PI)

INDEX (PI)CLASSIFICATION

CL-ML

PLASTICITY CHART

PLATE B-3

16

21

11

24

CL or OL

PLASTICITY CHART VENTURA C:\USERS\GECKRICH\DESKTOP\ACTIVE PROJECTS\04.62120100 BRIDGE ST. BRIDGE\GINT\04_6212_0100_VQ15B.GPJ 6/1/16 02:26 p

Project No. 04.62120100Quincy Engineering

Bridge Street Bridge RehabilitationArroyo Grande, California

Quincy EngineeringProject No. 04.62120100

X Y X YMax Curvature 4 3Max Curve Tangent 2 2.314802

4 311 4

Horiz Max 4 311 3

Bisect 4 311 3.5

Virgin 6 116 7

Intersect 8.87361 3.393825

Vertical Stress, ksf

---0.10452124---

2.65

SAM

PLE

ID

Water Content, %Dry Unit Weight, pcf

USCS Classification:Boring, Sample #, Depth

Saturation, %

PRO

PER

TIES

97%88.6

31.9%

Diameter, inHeight, in

Void Ratio 0.872.42

DH-101 , #10 , 34.0 ft

0.82

26.3%98.3

102%0.682.420.74

Lean CLAY (CL): brown, moist

FinalInitialPassing #200Estimated Gs

SUM

MA

RY

REM

AR

KS Test Method: D2435

Plasticity Index

Inundation Increment, ksfPreconsolidation Pressure, ksf

Liquid LimitPlastic Limit

0

2

4

6

8

10

12

14

16

18

20

0.1 1 10 100

Stra

in, %

Vertical Stress, ksf

CONSOLIDATION TEST RESULTSBridge Street Bridge Rehabilitation

Arroyo Grande, California PLATE B-4

Quincy EngineeringProject No. 04.62120100

Unit Dependent TextCompressive Strength, ksfUndrained Shear Strength, ksf94.0 ftDry Unit Weight, pcfDiameter, inHeight, in

Sieve Size % Passing3/8-in. (9.5mm) --- ---#4 (4.75mm) --- ---#16 (1.18mm) --- ---#30 (0.6mm) --- 2.65#100 (0.150mm) ---

46.0% #200 (0.075mm) ---73.297%1.262.415.03

Height/Diameter 2.09

Test Method: ASTM D2166

JB

Diameter, in

Estimated Gs

Liquid Limit

4.020.90

Plasticity Index

CLA

SSIF

ICA

TIO

N

USCS Classification:

Sample Number.:Plastic Limit

Other ParametersDH-101

9.3

SAM

PLE

PRO

PER

TIES

Void Ratio

Water Content, %Dry Unit Weight, pcfSaturation, %

Axial Strain at Failure, %Strain Rate, %/min

Date Tested: 7/29/15

4.7

Tested By:

Compressive Strength, ksfUndrained Shear Strength, ksf

Boring Number.:

Sample Depth:

SAM

PLE

IMA

GES

REM

AR

KS

TEST

SU

MM

AR

Y

Height, in

SAM

PLE

ID

Fat CLAY (CH): white, moist

22A94.0 ft

0

1

2

3

4

5

6

7

8

9

10

0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 5.5 6.0 6.5 7.0 7.5 8.0 8.5 9.0 9.5 10.0

Com

pres

sive

Str

engt

h, k

sf

Axial Strain, %

Interpreted Point of Failure

UNCONFINED COMPRESSION TEST RESULTSBridge Street Bridge Rehabilitation

Arroyo Grande, California PLATE B-5a

Quincy EngineeringProject No. 04.62120100

Unit Dependent TextCompressive Strength, ksfUndrained Shear Strength, ksf94.5 ftDry Unit Weight, pcfDiameter, inHeight, in

Sieve Size % Passing3/8-in. (9.5mm) --- ---#4 (4.75mm) --- ---#16 (1.18mm) --- ---#30 (0.6mm) --- 2.65#100 (0.150mm) ---

47.0% #200 (0.075mm) ---71.595%1.312.416.04

Height/Diameter 2.51

Test Method: ASTM D2166

Boring Number.:

Sample Depth:

SAM

PLE

IMA

GES

REM

AR

KS

TEST

SU

MM

AR

Y

Height, in

6.1

SAM

PLE

PRO

PER

TIES

Void Ratio

Water Content, %Dry Unit Weight, pcfSaturation, %

Axial Strain at Failure, %Strain Rate, %/min

Date Tested: 8/6/15

3.1

Tested By:

SAM

PLE

ID

Fat CLAY (CL): white, moist

Compressive Strength, ksfUndrained Shear Strength, ksf

22b94.5 ft

Plasticity Index

CLA

SSIF

ICA

TIO

N

USCS Classification:

Sample Number.:Plastic Limit

Other ParametersDH-101

JB

Diameter, in

Estimated Gs

Liquid Limit

2.380.80

0

1

2

3

4

5

6

7

0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 5.5 6.0 6.5 7.0 7.5 8.0 8.5 9.0 9.5 10.0

Com

pres

sive

Str

engt

h, k

sf

Axial Strain, %

Interpreted Point of Failure

UNCONFINED COMPRESSION TEST RESULTSBridge Street Bridge Rehabilitation

Arroyo Grande, California PLATE B-5b

Quincy EngineeringProject No. 04.62120100

Confining Stress: 10.7 ksf

Sieve Size % Passing3/8-in. (9.5mm) --- ---#4 (4.75mm) --- ---#16 (1.18mm) --- ---#30 (0.6mm) --- 2.65#100 (0.150mm) --- ---#200 (0.075mm) --- ---

35.7%78.886%1.102.415.82

Test Method: ASTM 2850

RE

MA

RK

S

Saturation, %

SA

MP

LE

ID

Boring Number:

Sample Depth:USCS Classification:

Sample Number:DH-10121

Fat CLAY (CH): white, moistEstimated GsSu from Tv, ksfSu from PP, ksf

21.510.7

Liquid LimitPlastic Limit89.0 ft

SA

MP

LE

IM

AG

ES

Diameter, inHeight, in

SA

MP

LE

PR

OP

ER

TIE

S

Void Ratio

Water Content, %Dry Unit Weight, pcf

10.7

Plasticity Index

CL

AS

SIF

ICA

TIO

N

Other Parameters

AS8/24/15

Tested By:

Axial Strain at Failure, %

TE

ST

SU

MM

AR

Y

Strain Rate, %/min

Date Tested:

Maximum Deviator Stress, ksfUndrained Shear Strength, ksf

Cell Pressure, ksf

8.50.7

0

5

10

15

20

25

30

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

Dev

iato

r S

tres

s (σ

1-σ

3), k

sf

Axial Strain, %

Confining Stress: 10.7 ksf

Interpreted Point of Failure

UNCONSOLIDATED, UNDRAINED TRIAXIAL TEST RESULTSBridge Street Bridge Rehabilitation

Arroyo Grande, CaliforniaPLATE B-6a

Quincy EngineeringProject No. 04.62120100

Confining Stress: 7.0 ksf

Sieve Size % Passing3/8-in. (9.5mm) --- ---#4 (4.75mm) --- ---#16 (1.18mm) --- ---#30 (0.6mm) --- 2.65#100 (0.150mm) --- ---#200 (0.075mm) --- ---

37.8%78.791%1.102.425.14

Test Method: ASTM 2850

RE

MA

RK

S

Saturation, %

SA

MP

LE

ID

Boring Number:

Sample Depth:USCS Classification:

Sample Number:DH-10124

Fat CLAY (CH): gray, moistEstimated GsSu from Tv, ksfSu from PP, ksf

16.28.1

Liquid LimitPlastic Limit100.0 ft

SA

MP

LE

IM

AG

ES

Diameter, inHeight, in

SA

MP

LE

PR

OP

ER

TIE

S

Void Ratio

Water Content, %Dry Unit Weight, pcf

7.0

Plasticity Index

CL

AS

SIF

ICA

TIO

N

Other Parameters

JB4/4/17

Tested By:

Axial Strain at Failure, %

TE

ST

SU

MM

AR

Y

Strain Rate, %/min

Date Tested:

Maximum Deviator Stress, ksfUndrained Shear Strength, ksf

Cell Pressure, ksf

10.80.7

0

5

10

15

20

25

30

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

Dev

iato

r S

tres

s (σ

1-σ

3), k

sf

Axial Strain, %

Confining Stress: 7.0 ksf

Interpreted Point of Failure

UNCONSOLIDATED, UNDRAINED TRIAXIAL TEST RESULTSBridge Street Bridge Rehabilitation

Arroyo Grande, California PLATE B-6b

Quincy EngineeringProject No. 04.62120100

Confining Stress: 7.0 ksf

Sieve Size % Passing3/8-in. (9.5mm) --- ---#4 (4.75mm) --- ---#16 (1.18mm) --- ---#30 (0.6mm) --- 2.65#100 (0.150mm) --- ---#200 (0.075mm) --- ---

45.2%74.999%1.212.435.06

Test Method: ASTM 2850

RE

MA

RK

S

Saturation, %

SA

MP

LE

ID

Estimated GsSu from Tv, ksfSu from PP, ksf

16.88.4

Boring Number:

Sample Depth:USCS Classification:

Sample Number:DH-10126b

Fat CLAY (CH): gray, moist

Liquid LimitPlastic Limit115.0 ft

SA

MP

LE

IM

AG

ES

Diameter, inHeight, in

SA

MP

LE

PR

OP

ER

TIE

S

Void Ratio

Water Content, %Dry Unit Weight, pcf

7.0

Plasticity Index

CL

AS

SIF

ICA

TIO

N

Other Parameters

JB4/4/17

Tested By:

Axial Strain at Failure, %

TE

ST

SU

MM

AR

Y

Strain Rate, %/min

Date Tested:

Maximum Deviator Stress, ksfUndrained Shear Strength, ksf

Cell Pressure, ksf

11.60.8

0

5

10

15

20

25

30

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

Dev

iato

r S

tres

s (σ

1-σ

3), k

sf

Axial Strain, %

Confining Stress: 7.0 ksf

Interpreted Point of Failure

UNCONSOLIDATED, UNDRAINED TRIAXIAL TEST RESULTSBridge Street Bridge Rehabilitation

Arroyo Grande, California PLATE B-6c

100

105

110

115

120

125

130

135

0 5 10 15 20 25

OPTIMUM WATERCONTENT, %

MOISTURE CONTENT, %

UN

IT D

RY

WE

IGH

T, p

cf

LEGENDMAXIMUM UNIT

DRY WEIGHT, pcf

Test Method: ASTM D1557(Gs = 2.65 to 2.75)

CLASSIFICATION

114.0 8.5

depth, ft

PLATE B-7

COMPACTION TEST RESULTS

(location)

Clayey SAND (SC)

ZERO AIR VOIDS CURVES

0.0DH-101

COMPACTION TEST VENTURA C:\USERS\GECKRICH\DESKTOP\ACTIVE PROJECTS\04.62120100 BRIDGE ST. BRIDGE\GINT\04_6212_0100_VQ15B.GPJ 6/1/16 02:27 p

Project No. 04.62120100Quincy Engineering

Bridge Street Bridge RehabilitationArroyo Grande, California

Quincy EngineeringProject No. 04.62120100

Sample No. "A" (8032) Depth: 0.0' - 5.0'Description: Clayey SAND (SC) - Very Dark BrownDate Tested: 7/24/2015 Test Method: ASTM D2844, CT301Initial Moisture Content: 11.0%

Dry Unit Water Exudation ExpansionWeight Content Pressure Pressure R-Value

(pcf) (%) (psi) (psf)112.5 14.2 206 0 17113.8 13.6 290 0 20114.6 13.1 375 0 23

R-value at Exudation Pressure of 300 psi: 21R-value by Expansion Pressure: TI = 4 N/A

Remarks: R-value by stabilometer controls.

R-VALUE TEST RESULTSBridge Street Bridge Rehabilitation

Arroyo Grande, California

PLATE B-8

0

10

20

30

40

50

60

70

80

90

1000100200300400500600700800

R-V

alue

Exudation Pressure (psi)

0.00

0.50

1.00

1.50

2.00

2.50

3.000.00 0.50 1.00 1.50 2.00 2.50 3.00

Cov

er T

hick

ness

by

Stab

ilom

eter

(fee

t)

Cover Thickness by Expansion Pressure (feet)

QUINCY ENGINEERING, INC. BRIDGE STREET BRIDGE REHABILITATION ARROYO GRANDE, CALIFORNIA

Fugro Project No. 04.62120100 Appendices

APPENDIX C REFERENCED EXISTING SUBSURFACE DATA