from, m/s nitin construction prop. nitin gupta s/o nanhkau...
TRANSCRIPT
Date: 24/10/2019
From, M/s Nitin Construction Prop. Nitin Gupta S/o Nanhkau Gupta Add.- 97/53, Behta, Sarojini Nagar, Lucknow, Uttar Pradesh.
To, The Director & Secretary (SEAC) Directorate of Environment, Govt. of U.P. Dr. Bhimrao Ambedkar Paryavaran Parisar, Vineet Khand-I, Gomti Nagar, Lucknow- (UP)-226010
Subject: Submission of Form-1, PFR, Mining Plan, Risk Assessment & EMP for Proposed “Ordinary
Earth Excavation Project” at Gata No.- 2467 Kha, 2490 Ga, 1212, 1213, Village- Thari,
Tehsil- Malihabad, District- Lucknow, Uttar Pradesh.. (Lease Area: 0.975 Ha.)
Respected Sir,
Please find enclosed herewith Form-1, PFR, Mining Plan & EMP for Proposed “Ordinary
Earth Excavation Project” at Gata No.- 2467 Kha, 2490 Ga, 1212, 1213, Village- Thari, Tehsil-
Malihabad, District- Lucknow, Uttar Pradesh.. (Lease Area: 0.975 Ha.)
We request you to kindly consider our application under Category B2 for the proposed
project for issue of the Environment Clearance.
Thanking You.
Enclosure: 1. Form-1 2. PFR 3. Mining Plan 4. EMP 5. Risk assessment
Yours Faithfully
(Nitin Gupta) Authorized Signatory
1.0 ORDINARY EARTH EXCAVATION
1.1 INTRODUCTION:
The land area of the Ordinary Earth excavation project is 0.975 hect. The Project site is located at
Khasra No.- 2467 Kha, 2490 Ga, 1212, 1213, Village- Thari, Tehsil- Malihabad, District- Lucknow,
Uttar Pradesh. The topography of the land is undulated and is not suitable for agriculture and this
land in Khasra/Khatauni mentioned as Agricultural land, so there is a need to excavate the Ordinary
Earth (14326.08 cubic meters) and to make the agricultural land as a recharge pit for ground water
and other purpose like Fish farming.
2.0 IMPACTS OF ORDINARY EARTH EXCAVATION & MITIGATION
The severity of the impact of Ordinary Earth excavation activities on environment may be
considered to be next only to that on maintenance of Agricultural land. No doubt, minerals are
indispensable for development and sustenance for the quality of life. At the same time, it is essential
that the Ordinary Earth excavation activities need to be continuously monitored and kept under
control for the management of the environment.
Most of the developmental activities generate environmental problems, but people do not
give due regard and attention to those problems. The question to be addressed with regard to
environmental issues of Ordinary Earth excavation pertains to conservation of minerals on the one
hand, and the environmental problems on the other. Depending on the location and the type of
excavation, the magnitude and the importance of environmental impact would vary. The impacts
can be broadly classified into four categories:
(1) Impact on Land
(2) Impact on air Environment
(3) Impact on Noise Environment
(4) Impact on Biological Environment
The first three impacts are often categorized collectively as physical impacts. All these impacts need
to be addressed properly to minimize the associated impacts. Depending on the nature of activities
and environmental screening, the impacts have been identified for their importance. Mitigating &
monitoring requirement are focused in the Environmental Management Plan for countering or
minimizing the potential environmental impacts associated with Ordinary Earth excavation. Impact
on various environmental parameters and likely mitigation measures to be adopted are described
below.
2.1 AIR ENVIRONMENT
2.1.1 Anticipated impacts
Although Ordinary Earth excavation does not cause any direct change in air environment,
transportation could cause atmospheric pollution. In Ordinary Earth excavation operations, the
source of air pollution may cause deterioration of air quality due to the fugitive dust emission
during scooping, loading-unloading operations, of Ordinary Earth and transportation. Loading and
unloading of Ordinary Earth would be associated with the fugitive emission in the active area
whereas fugitive emission during transportation would affect the areas/villages situated adjacent
to road side. Another source of air pollution would be emission from the trucks/tractor vehicles to
be used for transportation of Ordinary Earth.
2.1.2 Mitigation Measures:
2.1.2.1 For Fugitive dust Emission:
a) All trucks tractors will be covered by tarpaulin to prevent dust emission.
b) Water will be sprayed after loading activity (if Ordinary Earth would be in dry condition)
c) The dust suppression measures like water spraying will be done on the excavation site.
d) Overloading of trucks and trolleys will be prevented.
2.1.2.2 For Vehicular Emission:
a) Vehicular emission can pose serious health hazard. During the Ordinary Earth
excavation, tractor/truck would be used for transportation. Tractor/truck comprises of
diesel engine produce particles are dangerously fine of PM10 & PM2.5. It is well known fact
that combustion of diesel generates small particulate matter, nitrogen oxides and
sulphur dioxide (NO2, SO2).
b) Ultra low sulphur diesel would be used in vehicle. CPCB prescribed emission Standards
for the vehicle would be followed.
2.2 LAND ENVIRONMENT
Ordinary Earth excavation is the process of scooping of Ordinary Earth that actively
supports the Restoration and conservation of agricultural land in the area. The entire process is a
kind of man made erosion of materials otherwise segregated by the Mother Earth through its
geologic processes. The top Ordinary Earth is usually fertile in nature. The surface (top) layer is
several folds richer in N, P, K and other micro-nutrient elements than subsurface layers. But
according to some farmers of the region, the top Ordinary Earths of certain areas of the agricultural
land are unsuitable for agricultural activity. But the subsurface layers seem to be more fertile and
good for cultivation. In such cases, removal of a layer or two from the surface would be a beneficial
act.
2.2.1 Anticipated impacts
The major impacts of Ordinary Earth excavation on land are changes in land stability and
Ordinary Earth loss. Due to continued and unscientific Ordinary Earth excavation, pits of different
dimensions would be formed in the affected areas. Some of the pits may later be covered with water
to form irregular shape of agricultural lands. The irregular shape of agricultural lands created in
random locations due to indiscriminate Ordinary Earth excavation may lead to land stability
problems in the adjoining areas.
2.2.2 Mitigation measures
a) Ordinary Earth excavation depth will be limited to 2.0 mt along the topography. Only from
the surface.
b) No foreign material like polythene bag, jute bag and useless articles should be allowed to
remain/spill on the land, or no pits/pockets will be allowed to be filled with such material.
c) Excavation will not exceed beyond the agreed extraction depth.
d) No open bore hole is left.
2.3 NOISE ENVIRONMENT 2.3.1 Anticipated impacts
As far as noise pollution is concerned, Ordinary Earth excavation does not contribute much
to noise pollution, except the noise generated from the vehicles that transport excavated Ordinary
Earth from the lands. Noise level in the working environment is compared with the standards
prescribed by Central Pollution Control Board which has been adopted and enforced by the Govt. of
India through The Noise Pollution (Regulation and Control) Rules, 2000.
2.3.2 Mitigation measures
a) Well maintained vehicles will be used in order to reduce the noise during movement of
vehicles.
b) Regular and proper maintenance of transportation vehicles (trucks, tractor etc) would be
ensured.
c) There would be restriction on vehicular movement during night time.
2.4 BIOLOGICAL ENVIRONMENT
The area where Ordinary Earth excavation is practiced on agricultural land which are
generally devoid of any natural vegetation. The magnitude of which is proportional to the area
under brought under reclamation. There will not be any impacts on the biological environment in
the surrounding area. The land returned to a form and productivity in conformity with a prior land
use plan including a stable ecological state that does not continue substantially to environmental
deterioration and is consistent with surrounding aesthetic value.
2.4.1 CONSERVATION AND PROTECTION OF FLORA & FAUNA
Ordinary Earth excavation from the project site will not have any ecological impact. No
endangered and rare species of flora and fauna are found at the project site. The implementation for
development of green belt will be of paramount importance as it will not only add up as an aesthetic
feature, but also act as a pollution sink. a) The species to be grown in the area should be dust tolerant and fast growing species.
b) Apart from the green belt and aesthetic plantation for elimination fugitive of emission and
noise control, all other plantation efforts shall be decided and executed with the assistance
and co-operation of the local community.
2.5 SAFETY MEASURES DURING EXCAVATION
a) Trained the staff and other workers on safety measures and conduct safety drills to educate
them.
b) First-aid facilities would be provided to the laborer at the project site.
c) Conduct safety programs to create safety awareness among workers/staff.
2.6 ENVIRONMENTAL MANAGEMENT PLAN IMPLEMENTATION
Environmental Management Plan serves no purpose if it is not implemented with true spirit.
Thus, an implementation and monitoring programme has to be prepared. Implementation of
proposed control measures and monitoring programme has an implication on the surrounding area
as well as for the region. Therefore, Ordinary Earth excavation management should be strengthen
the existing control measures as elaborated earlier in this report and monitor the efficacy of the
control measures implemented within the Ordinary Earth excavation area relating to the following
specific areas:
Regular visual examination will be carried out to look for possibilities of erosion. Any
abnormal condition, if observed should be taken care of.
Examination of noise levels at excavation site, stationary and mobile sources, and adjacent villages would be done.
Conduct environmental awareness program to the workers, supervisory staff and contract
laborers during the excavation period.
Recommend necessary measures to improve Environmental conditions.
No need of temporary toilets as the workers will be hired from the nearby villages.
2.7 Solid Waste Management
Disposal of packing material, carried by the workers at the project site. This packing material
would include used sachet/gutka/pan masala pouches. Polythene bag used by the workers
to bring their foods etc. would be separately stored in bins and managed as per Solid Waste
Management Rules.
2.8 Information Record
Daily data of Ordinary Earth excavation at the project site would be recorded in the register
by the supervisory staff.
Number of employed workers would be entered in the register by the supervisory staff daily.
Number of vehicles used for the transportation of excavated Ordinary Earth should be
mentioned in the record register.
***************
Date: 24/10/2019
From, M/s Nitin Construction Prop. Nitin Gupta S/o Nanhkau Gupta Add.- 97/53, Behta, Sarojini Nagar, Lucknow, Uttar Pradesh.
To, The Director & Secretary (SEAC) Directorate of Environment, Govt. of U.P. Dr. Bhimrao Ambedkar Paryavaran Parisar, Vineet Khand-I, Gomti Nagar, Lucknow- (UP)-226010
Subject: Submission of Form-1, PFR, Mining Plan, Risk Assessment & EMP for Proposed “Ordinary
Earth Excavation Project” at Gata No.- 2467 Kha, 2490 Ga, 1212, 1213, Village- Thari,
Tehsil- Malihabad, District- Lucknow, Uttar Pradesh.. (Lease Area: 0.975 Ha.)
Respected Sir,
Please find enclosed herewith Form-1, PFR, Mining Plan & EMP for Proposed “Ordinary
Earth Excavation Project” at Gata No.- 2467 Kha, 2490 Ga, 1212, 1213, Village- Thari, Tehsil-
Malihabad, District- Lucknow, Uttar Pradesh.. (Lease Area: 0.975 Ha.)
We request you to kindly consider our application under Category B2 for the proposed
project for issue of the Environment Clearance.
Thanking You.
Enclosure: 1. Form-1 2. PFR 3. Mining Plan 4. EMP 5. Risk assessment
Yours Faithfully
(Nitin Gupta) Authorized Signatory
(I) Basic Information:
Sl. No.
Item Details
1 Name of the project Proposed Ordinary Earth Excavation at Khasra No-.- 2467 Kha, 2490 Ga, 1212, 1213, Village- Thari, Tehsil- Malihabad, District- Lucknow, Uttar Pradesh. (Lease Area: 0.975 Ha.)
2 S. No. of the schedule 1(a) 3 Proposed capacity /area/ length/
tonnage to be handled/command area / lease area/number of wells to be drilled
(Leased Area: 0.975 Ha.) Monthly Proposed production in Cum is mentioned below- Proposed Production: 14326.08 m3 for 3 Months.
4 New/Expansion/Modernization New
5 Existing Capacity/Area etc. Not Applicable (New Mine) 6 Category of project i.e. “A” or “B” As per EIA Notification dated 14.09.2006, as
amended on 01.12.2009 and 15.01.2016 this project falls under Category B (Sub-category B2)
7 Does it attract the general condition? If yes please specify
No, As per EIA Notification, 2006 as amended in 2009, General conditions are applicable to S. No. 1(a) of schedule. Since there are no protected areas notified under the Wildlife (Protection) Act, 1972 amended vide notification S.O. 1599 (E) dated 25th June 2014, critically polluted areas, notified Eco sensitive area, inter-state boundaries are falling in whole or in part within 05 km radius of the proposed project. General conditions are not applicable to proposed project.
8 Does it attract the specific condition? If yes please specify
No
9 Location
Co- ordinates of the site
Latitude and Longitude
Gata No- Latitude Longitude 27° 1'15.14"N 80°41'7.32"E
Khasra No. 2467 Kha, 2490 Ga, 1212, 1213
Village Thari
Tehsil Malihabad
District Lucknow
State Uttar Pradesh.
10 Nearest railway station/airport along With distance in kms.
The Nearest Railway Station is Dilwarnagar Railway station-7.10 Km towards (E) Direction and Nearest NH25A-4.88Km (SW) Aerial Distance in Approximation
11 Nearest Town, City, District headquarters along with distance in kms.
Malihabad – 11.87 Km (S) (Aerial Distance)
12 Villages- Panchayats, Jila Parishad, Municipal Corporation, Local body (complete postal address with telephone nos. to be given)
Villages- Panchayats - Thari Jila Parishad, - Lucknow Municipal Corporation- Malihabad District- Lucknow, Uttar Pradesh.
13 Name of the Applicant M/s Nitin Construction Prop. Nitin Gupta S/o Nanhkau Gupta Add.- 97/53, Behta, Sarojini Nagar, Lucknow, Uttar Pradesh.
14 Registered address - 15 Address for correspondence: -
Name M/s Nitin Construction
Prop. Nitin Gupta S/o Nanhkau Gupta Add.- 97/53, Behta, Sarojini Nagar, Lucknow, Uttar Pradesh.
Designation (Owner/Partner/CEO) Proprietor Address 97/53, Behta, Sarojini Nagar,
Lucknow, Uttar Pradesh. Pin Code - E-mail - Telephone No. - Fax No. -
16 Details of alternative sites examined, if any. Location of these sites should be shown on a toposheet.
No alternate site was examined.
17 Interlinked Projects None 18 Whether a separate application of
interlinked project has been submitted? No
19 If yes, date of submission No 20 If no, reason No 21 Whether the proposal involves
approval/clearance under: if yes, details of the same and their status to be given. (a) The Forest (Conservation) Act, 1980? (b) The Wildlife (Protection) Act, 1972? (c) The C.R.Z. Notification, 1991?
No Protected area notified under wildlife (Protection) Act 1972
22 Whether there is any Governmental Order/ Policy relevant/ relating to the site?
No
23 Forest land involved (hectares) No forest land is involved. 24 Whether there is any litigation pending
against the project and/or land in which the project is propose to be set up? (a) Name of the Court (b) Case No. (c) Order/directions of the court, if any and its relevance with the proposed projects.
No litigation or court case is pending against the proposed project.
Capacity corresponding to sectoral activity (such as production capacity for manufacturing, mining lease area and production capacity for mineral production, area for
mineral exploration, length for linear transport infrastructure capacity for power generation etc.)
(II) Activity:
1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)
S. No.
Information/Checklist confirmation
Yes/ No
Details there of (with approximate quantities /rates, wherever possible) with source of information data
1.1 Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan)
No The topography of the area is undulated land. The land will become suitable for recharging pit for ground water and other purpose like Fish farming at the end of excavation.
1.2 Clearance of existing land, vegetation and buildings?
No The proposed plan involves extraction of ordinary Earth from proposed gatas and does not require any clearance of existing land, vegetation and building.
1.3 Creation of new land uses? No The land will be use for Restoration and conservation of agricultural land in the area.
1.4 Pre-construction investigations e.g. bore houses, Ordinary Earth testing?
No Not Applicable
1.5 Construction works? No No Construction of permanent nature is required.
1.6 Demolition works? No Not Applicable 1.7 Temporary sites used for
construction works or housing of construction workers?
No Mining will be confined to day time for 3 Months only, and laborers from local area will be hired, thus no housing of construction workers is required.
1.8 Above ground buildings, structures or Earthworks including linear structures, cut and fill or excavations
No No civil work is required in the mine lease area.
1.9 Underground works including mining or tunneling?
No Not Applicable
1.10 Reclamation works? No Not Applicable 1.11 Dredging? No Not Applicable 1.12 Offshore structures? No Not Applicable 1.13 Production and manufacturing
processes? Yes Not Applicable
1.14 Facilities for storage of goods or materials?
No The excavated Ordinary Earth will be loaded will be loaded and transported directly through the trucks or trolleys; hence no temporary or permanent storage will be required.
1.15 Facilities for treatment or disposal of solid waste or liquid effluents?
No There would be no construction laborers inhabit at site thus there will be very less or no generation of solid waste is anticipated. However, provision of dustbin will be done for domestic waste collection. No generation of liquid effluents is anticipated.
1.16 Facilities for long term housing of operational workers?
No Mining activities is confined to day time for 2 months only, thus do not involve long term housing of operational workers.
1.17 New road, rail or sea traffic during construction or operation?
No No new road, rail will be constructed.
1.18 New road, rail, air waterborne or other transport infrastructure including new or altered routes and stations, ports, airports etc?
No Not Applicable
1.19 Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements?
No The project does not involve any closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements
1.20 New or diverted transmission lines or pipelines?
No Not Applicable
1.21 Impoundment, damming, culverting, realignment or other changes to the hydrology of
No Not Applicable
watercourses or aquifers? 1.22 Stream crossings? No Not Applicable 1.23 Abstraction or transfers of water
from ground or surface waters? Yes The water requirement for the operational
workers will be met by private tankers. It is estimated that approx. 30 local labors will be hired from nearby villages for 2 Months only.
1.24 Changes in water bodies or the land surface affecting drainage or run-off?
No Mining shall be done upto a depth of 2.0 m, hence ground water will not be affected. After the excavation the gata will be repaired. Hence, drainage or run-off remains unaffected.
1.25 Transport of personnel or materials for construction, operation or decommissioning?
Yes Excavation of ordinary Earth will be done by backhoe Loader machines and will be transported to the required sites through Dumper, Truck.
1.26 Long-term dismantling or decommissioning or restoration works?
No Not Applicable
1.27 Ongoing activity during decommissioning which could have an impact on the environment?
No Not Applicable
1.28 Influx of people to an area in either temporarily or permanently?
Yes Not Applicable
1.29 Introduction of alien species? No Not Applicable 1.30 Loss of native species or genetic
diversity? No Not Applicable
1.31 Any other actions? No Not Applicable 2. Use of Natural resources for construction or operation of the Project (such as
land, water, materials or energy, especially any resources which are non-renewable or in short supply):
Sl. No.
Information/checklist confirmation
Yes/ No
Details thereof (with approximate quantities/ rates, wherever possible) with source of information data
2.1 Land especially undeveloped or agricultural land (ha)
Yes Unfertile Agricultural Land Land Ownership: Gram Samaj Bhoomi
2.2 Water (expected source & competing users) unit: KLD
Yes Total water requirement for the project is
3.20 KLD, it shall be supplied from the
nearby villages & its breakup is as under-
S.
N
o.
Purpose Water
Requirement
(KLD)
1 Dust Suppression 2.70
2 Plantation 0.20
3 Domestic
(Drinking)
0.30
Total 3.20
2.3 Minerals (MT) Yes Only ordinary Earth will be extracted.
Proposed production: 14326.08 m3
2.4 Construction material – stone,
aggregates, Sand/Morrum Ordinary
Earth (expected source – MT)
No Not Applicable
2.5 Forests and timber (source – MT) No Not Applicable 2.6 Energy including electricity and
fuels (source, competing users)
Unit: fuel (MT), energy (MW)
Yes Since mining activity will be carried out for 3
Months in day time only, and no housing
facility for laborers is proposed. Thus no
electricity or any fuel for energy is required.
2.7 Any other natural resources (use appropriate standard units)
No Not Applicable
3. Use, storage, transport, handling or production of substances or materials, which
could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health.
Sl. No.
Information/Checklist confirmation
Yes/ No
Details there of (with approximate quantities/rates, wherever possible) with source of information data
3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies)
No Only Ordinary Earth excavation will be done. Thus no hazardous and toxic material will be used or to be generated during operational phase or after activity.
3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases)
No It is an opencast semi-mechanized mining project which will not cause any changes in occurrence of disease or affect disease
vectors.
3.3 Affect the welfare of people e.g. by changing living conditions?
Yes The proposed project will generate employment opportunities to the nearby local people, thus will have short term and positive impact on Socio – Economic development.
3.4 Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc.,
No There are no sensitive areas like school, hospital are present in the vicinity of excavation site that are vulnerable to be affected.
3.5 Any other causes No Not Applicable
4. Production of solid wastes during construction or operation or decommissioning (MT/month)
Sl. No.
Information/Checklist confirmation
Yes/ No
Details thereof (with approximate quantities/rates, wherever possible) with source of information data
4.1 Spoil, overburden or mine wastes No No waste generation is anticipated.
4.2 Municipal waste (domestic and or commercial wastes)
Yes Excavation activities are confined to day time only, thus do not involve long term housing of the operational workers at site, hence no or very insignificant quantity of food waste is expected to generate.
4.3 Hazardous wastes (as per Hazardous Waste Management Rules)
No Not Applicable
4.4 Other industrial process wastes No Not Applicable
4.5 Surplus product No Not Applicable 4.6 Sewage sludge or other
sludge from effluent treatment No Not Applicable
4.7 Construction or demolition wastes No Not Applicable 4.8 Redundant machinery or
equipment No Mining will be done semi-mechanized/
manually 4.9 Contaminated Ordinary Earths or
other materials No Not Applicable
4.10 Agricultural wastes No Not Applicable 4.11 Other solid wastes No Not Applicable
5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr).
Sl. No
Information/Checklist confirmation
Yes/ No
Details thereof (with approximate quantities/rates, wherever possible) with source of information data
5.1 Emissions from combustion of fossil fuels from stationary or mobile sources.
Yes During operational phase there may be emissions by movement of vehicles (vehicular exhaust) which will be minimized by using only PUC certified vehicles in the mining lease area.
5.2 Emissions from production processes
Yes Not Applicable
5.3 Emissions from materials handling including storage or transport
Yes There will be minor emissions i.e. dust, vehicular exhaust anticipated during loading, unloading and transportation of excavated material. The transported Ordinary Earth will be covered by the canvas sheet to minimize the loss of Ordinary Earth during transportation.
5.4 Emissions from construction activities including plant and equipment.
No Not Applicable
5.5 Dust or odors from handling of materials including construction m a t e r i a l s , sewage and waste.
Yes There will be emissions anticipated during loading, unloading and transportation of excavated material.
5.6 Emissions from incineration of waste
No Not Applicable
5.7 Emissions from burning of waste in open air (e.g. slash materials, construction debris)
No Not Applicable
5.8 Emissions from any other sources No Not Applicable
6. Generation of Noise and Vibration, and Emissions of Light and Heat:
Sl. No.
Information/Checklist confirmation
Yes/
No
Details thereof (with approximate quantities/rates, wherever possible) with source of information data
6.1 From operation of equipment e.g. engines, ventilation plant, crushers.
Yes Semi-mechanized extraction for ordinary Earth mining is proposed. Trucks/Dumper will be used during transportation; it is being ensured that it does not exceed the norms/prescribed standards.
6.2 From industrial or similar processes.
No Not Applicable
6.3 From construction or demolition. No Not Applicable
6.4 From blasting or piling No Not Applicable 6.5 From construction or operational
traffic Yes Vehicular movement for transportation of
mining material from site will generate noise. Regular and proper maintenance of vehicles will reduce the impact.
6.6 From lighting or cooling systems. No Not Applicable 6.7 From any other sources No Not Applicable
7. Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:
Sl. No.
Information/Checklist confirmation
Yes/
No
Details thereof (with approximate quantities/rates, wherever possible) with source of information data
7.1 From handling, storage, use or spillage of hazardous materials
No No hazardous material is being used or Generated.
7.2 From discharge of sewage or other effluents to water or the land (expected mode and place of discharge)
Yes Not Applicable
7.3 By deposition of pollutants emitted to air into the land or into water.
No Not Applicable
7.4 From any other sources No Not Applicable 7.5 Is there a risk of long term build
up of pollutants in the environment from these sources?
No There is no such risk.
8. Risk of accidents during construction or operation of the Project, which could affect human health or the environment.
Sl. No.
Information/Checklist confirmation
Yes/ No
Details thereof (with approximate quantities/rates, wherever possible) with source of information data
8.1 From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances
No No storage is proposed at site, material will directly transported to the market.
8.2 From any other causes No Not Applicable
8.3 Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)?
No Probability of earth quake is high as the area falls in high damage risk seismic zone IV.
9. Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality.
Sl. No.
Information/Checklist confirmation
Yes/ No
Details thereof (with approximate quantities/rates, wherever possible) with source of information data
9.1 Lead to development of supporting. Lights, ancillary development or development stimulated by the project which could have impact on the environment e.g.: Supporting infrastructure (roads,
power supply, waste or waste water treatment, etc.)
Housing development Extractive industries Supply industries Other
No
No
No No No No
Project proponent will organize regular medical checkup camps and recreational activities.
Employment to local people will be generated.
Overall living standard of nearby people will have positive impact.
No supporting infrastructure is required since the site has good connectivity with local roads, MDR and highways.
Also the laborers will be hired locally thus no permanent or temporary housing is required at site.
9.2 Lead to after-use of the site, which could have an impact on the environment.
No Land use proposed is undulated land, Which will facilitate better agricultural yields after Ordinary Earth excavation. Thus providing a positive effect.
9.3 Set a precedent for later developments.
No Not Applicable.
9.4 Have cumulative effects due to proximity to other existing or planned projects with similar effects.
No Not Applicable
(III) Environmental Sensitivity:
Sl. No.
Areas Name/ Identity
Aerial distance (within 15 km.) Proposed project location boundary
1 Area protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value.
No Not Applicable
2 Areas which are important or sensitive for ecological reasons -Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests.
No Not Applicable
3 Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration.
No Not Applicable
4 Inland, coastal, marine o r underground waters.
No Not Applicable
5 State, National boundaries No Not Applicable
6 Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas
No NH- 25A – 4.88 Km (E) Dir.
7 Defense installations No Not Applicable
8 Densely populated or built-up area Yes Malihabad – 11.87 Km (S) Direction (Aerial Distance).
9 Areas occupied by sensitive man-made land uses. (hospitals, schools, places of worship, community facilities
No Not Applicable
10 Areas containing important, high quality or scarce resources. (Ground water resources, surface resources, forestry, agriculture, fisheries, tourism, minerals)
No None
11 Areas a l r e a d y subjected to pollution o r environmental damage. (Those where existing legal environmental standards are exceeded)
No No
12 Areas susceptible to natural hazard which could cause the project to present environmental problems. (Earthquakes, subsidence,
No Not Applicable
DECLARATION
“I hereby given undertaking that the data and information given in the application and enclosures are true to the best of my knowledge and belief and I am aware that if any part of the data and information submitted is found to be false or misleading at any stage, the project will be rejected and clearance give, if any to the project will be our risk and cost. Date: 19/10/2019
Place: Lucknow
(Nitin Gupta)
Authorized Signatory R/o- Add.- 97/53, Behta, Sarojini Nagar, Lucknow, Uttar
Pradesh..
1. EXECUTIVE SUMMARY
The land area of the Ordinary Earth excavation project is Area: 0.866 hect., and falls under
Category- B (Sub-category B2), as per EIA Notification 2006 of the MOEP&CC. The Project Site is
located at Khasra No-2467 Kha, 2490 Ga, 1212, 1213, Village- Thari, Tehsil- Malihabad, District-
Lucknow, Uttar Pradesh. (Lease Area: 0.975 Ha.)
Project Area 0.975 Ha.
Location of excavation site
Toposheet No. 63A/12
Khasra No. 2467 Kha, 2490 Ga, 1212, 1213
Topography undulated
Minerals of excavation site Ordinary Earth excavation
Proposed production of
excavation site Proposed Production14326.08 m3 for 3 Months.
Method of mining Manual
Drilling/Blasting No drilling and blasting is proposed
Water demand
S. No.
Purpose Water Requirement (KLD)
1 Dust Suppression 2.70 2 Plantation 0.20 3 Domestic (Drinking) 0.30 Total 3.20
Sources of water Water will be supplied from portable water from tanker
supplier.
Ultimate depth of excavation
site 2.0 meters
Man power 30
Solid Waste No waste is expected.
Nearest Railway station Dilwarnagar Railway station-7.10 Km towards (E)
Nearest state highway/
National highway NH- 25A – 4.88 Km (E) Dir.
Nearest Airport N/A
2. INTRODUCTION
2.1 Identification of Project and Project Proponent
The project will execute by M/s Nitin Construction Prop. Nitin Gupta S/o Nanhkau Gupta
Add.- 97/53, Behta, Sarojini Nagar, Lucknow, Uttar Pradesh.. The details of the project and its Proponents are given below:
Name of the applicant Shri Nitin Gupta S/o shriNanhkau Gupta Address R/o- 97/53, Behta, Sarojini Nagar, Lucknow, Uttar
Pradesh
Khasra No.- 2467 Kha, 2490 Ga, 1212, 1213
Area 0.975 Ha. Mineral Ordinary Earth Status of Mine Fresh application for Environmental Clearance for
Excavation of Ordinary Earth. 2.2 Brief description of the nature of the project
It has been proposed to collect approximately 14326.08 m3 of Ordinary Earth. Excavation
activity will be proposed after the grant of environment clearance.
Surface Excavation: The excavation of Ordinary Earth from the land will be Opencast
Manual/Semi-mechanized. Ordinary Earth excavation will be carried out only 2.0 meters.
Excavation will be carried out only during the day time.
2.3 Need for the project and its importance to the country and region
The proposed land is undulated land. To make the land flat suitable make the pond as a
recharging pit for ground water and other purpose like Fish farming, the excavated Ordinary Earth from
the undulated land would be used for commercial purpose. The excavation work will provide
employment to the local laborers. 2.4 Demands-Supply Gap
Not Applicable
2.5 Domestic/ Export Markets
Not applicable.
2.6 Employment Generation
This project operation will provide livelihood to the poorest section of the society. It will
provide employment to the people residing in vicinity.
3 PROJECT DESCRIPTION
3.1 Type of project including interlinked and interdependent projects, if any
3.2 Location
The site is located in Khasra No-2467 Kha, 2490 Ga, 1212, 1213, Village- Thari, Tehsil-
Malihabad, District- Lucknow, Uttar Pradesh. (Lease Area: 0.975 Ha.) . The excavation lease area
falls in Survey of India. The project site is located at:
Gata No-2467 Kha, 2490 Ga, 1212, 1213
Latitude Longitude
27° 1'15.14"N 80°41'7.32"E 3.3 Details of alternate sites considered
The Ordinary Earth excavation site is site specific, hence there are no alternative sites
considered.
3.4 Size or magnitude of operation
The proposed excavation area is 2.751 hect. The total excavated material would be 51352.47
m3.
3.5 Project description with process details
3.5.1 Method for developing and working the deposits
The excavated Ordinary Earth would be used for the leveling purpose.
3.5.2 Method of excavation
The excavation of Ordinary Earth on the project site will be done Semi-mechanized.
Excavation will be carried out only during the day time.
3.6 Raw Material Required Along With Estimated Quantity, Likely Source, Marketing Area
of Final Product/S, Mode of Transport of Raw Material and Finished Product
No raw material will be required in the proposed project. The operation involves the
excavation of Ordinary Earth in its existing form and loaded into tractor trolleys which will
transport to the dumping site for leveling the down land.
3.6.1 Use of Mineral
Minor mineral namely Ordinary Earth would be used for commercial purpose.
3.6.2 Mineral Beneficiation
No mineral beneficiation is involved.
3.6.3 Surface Transport The transportation of Ordinary Earth will be carried out by trolleys to the dumping site.
There is metalled road and then an un-metalled link road right up to the mine to dispatch the
material from mine to the market.
3.7 Resource optimization/ recycling and reuse
Not envisaged.
3.8 Availability of water its source, energy/ power requirement and source
3.8.1 Water Requirement
S. No. Purpose Water Requirement (KLD)
1 Dust Suppression 2.70 2 Plantation 0.20 3 Domestic (Drinking) 0.30 Total 3.20
3.8.2 Power Requirement
The operation will be done only from sun rise to sun set. Hence there is no power
requirement.
3.9 Quantity of wastes to be generated (liquid and solid) and scheme for their
management/disposal.
3.9.1 Solid Waste Generation & its Disposal
The entire Ordinary Earth excavated will be used for selling in open market.
3.9.2 Liquid Effluent
No liquid effluent will be generated at the excavation site.
3.9 Schematic representation of the feasibility drawing which give information of EIA
purpose-
. SITE ANALYSIS 4.1 Connectivity:
Dilwarnagar Railway station-7.10 Km towards (E)
NH- 25A – 4.88 Km (E) Dir.
4.2 Land form, land use and land ownership
Land Form: The mine agreement area is agricultural private land.
Land Use: All the land given is Agricultural plain.
The existing land use pattern of the area is agricultural and the pattern of the area as per
Requirement during mining will be as tabulated below.
Category Area in Ha
Area Left in Berm 750.501
Quarrying 8549.5
Total Mining Area 0.975
Land Ownership:
Private Land - Required lands are followed by agreement among project proponent and land
owner. The proposed activity is to take place in the Plot(s) as per agreement and hence there will be
no change in land use.
4.3 Topography
The district forms a part of Ganga basin with flat alluvial terrain. Geomorphologically the district is
divided into two geomorphic units (i) Older flood plains & (ii) Active flood plain. Older flood plains
are represented by two level of terraces viz Erosional terrace (Te) occupying at higher level and
Depositional terrace (Td) at lower depressions. Older flood plain exists between elevation of 103
and 110 mamsl. Both the terraces are developed on the either side of Gomti river. Erosional Terrace
is also developed along Sai Nadi. Active flood plains are restricted to present day bank line of the
rivers. These are represented by land forms like point bars channel bars and lateral bars.
Quaternary sediments have been divided upto older & newer alluvium. The older alluvium is
comprised of grey to brown coloured silt clay and sand with or without Kankar of middle to late
Pleistocene age. The Newer alluvium overlies the older alluvium and has been sub divided into
terrace alluvium and channel alluvium & belongs to Holocene age. The newer alluvium comprises of
light Khaki grey silt, clay and fine to medium and coarse grained grey sand which is micaceous in
nature. Earths in the district exhibits a wide variation in composition texture and appearance. The
major position of the district is occupied by Earths locally known as "Bhur" or "Silty Sand" on the
ridges. "Matiyar" or "Clay Earths" occurs along topographic lows and "Dumat or Loamy Earths" in
the level lands. Clay is dominant in the areas where "Reh" (Usar) prevails. Along the river valleys, a
very fertile Earth called "Dumat" is prevalent which is youngest.
The average elevation of the area is 116.0 mRl & general slope of the area is from
south to north directions.
4.4 Existing land use pattern
Not Applicable, There is no forest land in the proposed mine lease area. The existing land use
pattern of the area is agricultural.
4.5 Ordinary Earth classification
Ordinary Earth is characterized mainly by yellow Ordinary Earths.
4.6 Climatic data from secondary sources
Climate:
Lucknow has a warm humid subtropical climate with cool, dry winters from December to
February and dry, hot summers from April to June. The rainy season is from mid-June to mid-
September, when Lucknow gets an average rainfall of 1010 mm (40 in) mostly from the south-west
monsoon winds. In winter the maximum temperature is around 25° Celsius and the minimum is in
the 6° to 8° Celsius range. Fog is quite common from late December to late January. Summers are
very hot with temperatures rising to the 40° to 45° Celsius range.
The district receives a normal rainfall of 1019 mm with 47 rainy days experiences sub-
tropical climate. The district is mainly drained by river Gomti and its tributary Sai which are
perennial in nature.
4.8 Social Infrastructure
5. PLANNING BRIEF 5.1 Planning concept
Excavation plan is not required for the Ordinary Earth excavation at the project site. The
excavated Ordinary Earth is meant for sale.
5.2 Population projection
The project will employ the workers from nearby villages. There will not be any increase in
population due to the project.
5.3 Landuse planning
The land is proposed for excavation of Ordinary Earth to level the land.
5.4 Assessment of Infrastructure Demand
Extracted Ordinary Earth transported directly to the dumping site, there is no stock yard
required for storage, also the workers are hired locally and temporarily, no housing facility is
required.
5.5 Amenities/facilities
Drinking water and first aid facility will be made available to the mine workers.
6. PROPOSED INFRASTRUCTURE
6.1 Industrial area (Processing Area)
No industrial area is proposed.
6.2 Residential area (Non Processing Area)
The project will employ most of the workers from nearby villages. So, no need of temporary rest shelters.
6.3 Green belt
It is proposed to plant trees along the road sides and nearby civic amenities in consultation with district administration.
6.4 Connectivity
There are metalled roads and unmetalled at the project site.
6.5 Social Infrastructure Temporary rest shelters, drinking water and first aid facility are made available to the
mine workers.
6.6 Drinking Water Management
Water for drinking is required to be 0.30 KLD. It is proposed to obtain water from
construction/potable water from tanker supplier.
6.7 Sewerage System
Not applicable.
6.8 Industrial Waste Management
Not applicable.
6.9 Solid Waste management
Not applicable.
6.10 Power Requirement & Supply/ Source
The operation will be done only from sun rise to sun set. Hence, there is no power
requirement for the project at site.
7. REHABILITATION AND RESETTLEMENT (R&R) PLAN Not Applicable.
8. PROJECT SCHEDULE & COST ESTIMATES The project will commence once Environmental Clearance and other necessary certificates
are obtained from the respective departments. Break-up of Project Cost:
Machinery Uses in Project
S. N.
Type / Name Quantity Rate ( Rs) Total / Per Year Rs
Capital Cost 1 Dumper 1 0.50 Lakh per Month 1,50,000 2 Loader 1 (Rs.50,000 per Month for per unit) 1,50,000 Operative Cost
1 No of Laborer will be depend upon production as per market demand
Average 10
Rs- 280 for one laborer 10X280 X 90 days
2,52,000
2 Environment management Plan (plantation and water sprinkling)
1,20,000
Total Project Cost Will be Rs. 3,82,000 Say Rs. 4.0 lacs
Corporate Environmental responsibility (CER) • Total cost of the project is: Rs. 7.0 lacs • 2% amount allocated for CER amounting is: Rs 14,000/-
9.0 ANALYSIS OF PROPOSAL ( FINAL RECOMMENDATION)
Overall the project will have positive and long term impact on environment. The project will
also bring positive changes in terms of socio economic development by way of generating direct
and indirect employment opportunities to the people of vicinity. Also the project will bring
economic benefit to the state in terms of revenue generation.
***********
Date: 24/10/2019
1.0 Disaster Management and Risk Assessment: The mining is proposed in a gentler agricultural field. The mining will go up to the economical depth of 2.0 m and thereafter backfilling will commence to restore the topography of the area. The mining faces shall be dressed properly because any hanging boulders/loose material may create fatal accidents to the laborers while working in the pit. The area falls in Seismic Zone-III (low damage risk zone). Although complete precautions will be taken during the project activity to suppress the chances of any accident. Therefore precautionary measures shall be adopted. Tin shaded wooden houses shall be constructed in place of cemented houses in and around the area & lessee shall provide the sufficient amount of funds for these activities.
Some of the aspects to be included in emergency plan are as follow: 1. Organization-details of command structure, working systems, implementation procedures,
and emergency control centre & have of incident controller, site main controller, their duties & other key personnel.
2. Communication centers & persons involved call signs & list of telephone numbers. 3. Availability of special emergency equipment e.g. heavy lifting gear, bulldozers, trucks, special
firefighting equipment. 4. Details of voluntary organizations with names of organizers, telephone numbers, resources
etc. 5. Humanitarian arrangements e.g. transport evacuation centers, emergency feeding, treatment
of injured, first aid, ambulances etc. 6. No other accidents like subsidence of flood, tailing dam failure etc. shall be observed during
mining in hilly region. 1.2 Care & maintenance during temporary discontinuance:
During monsoon period (i.e. from June to September) every year mining operations shall be temporarily discontinued and. Local person shall be employed to supervise the area fencing around pit, etc shall be repaired immediately.
2.0 Economic repercussions of closure of mine and manpower retrenchments: All the workers to be employed are contractor labours. Any industry will provide direct and indirect employment. The local residents will earn tremendous amount of money due to mining activities. It will change their life style. Due to closure of mine, it will create very negative impact on the economy of the workers for their survival. Those earning good money will get some occupation for survival of their families. The literate workers will move here and there for the search of job. In the overall view the closure of mine will give very bad impact on the society and surrounding areas. Page 3 Project: Proposed Ordinary Soil Excavation at Gata No.- 2467 Kha, 2490 Ga, 1212, 1213, Village- Thari, Tehsil- Malihabad, District- Lucknow, Uttar Pradesh.. (Lease Area: 0.975 Ha.) Disaster Management & Risk Assessment.
2.1 Mining shall be carried out through contractor in the proposed area & likely to be continued in the same manner. So no retrenchment of manpower is envisaged. Status of joining the family business back on the event of closure of mine & will depend on the circumstances prevailing at that time. However, chances of joining the family business back will not be so bright. 2.2 The compensation to given will depend on the labour laws prevalent at that time. Since 80% employees will be contract. They will not be compensated. Other will get benefit of compensation as per labor laws, while the staff will get only notice pay. 2.3 There are some satellite occupations connected to mining operations at present with in a distance of 5km. e.g. workshop/truck repair shops, tyre shops, general stores, small restaurants, fruit shops, tea shops etc. Such business at the time of closure is likely to get closed down, however the effect of single mine closure may not be fell at all. 2.4 Since the lessee will hand over the lease area to State Govt. there are no chances of continued engagement in the backfilled/reclaimed status. Once the lease is determined then all the remnant activities will come to an end barring the period of reclamation period. 2.5 The closure of mine will have grave repercussion on the expectations of society since the obvious advantages received will cease & the closure will directly affect their livelihood. Land owners will cease to get compensation in lien of surface rights. The local habitant in general will feel insecure as their education, health standards & life expectancy will be badly affected.