FRIENDSHIP RECREATION CENTER

ANC 3E UPDATE

January 12, 2017

Page 2: FRIENDSHIP RECREATION CENTER ANC 3E UPDATE January 12, … · 2017-01-18 · FRIENDSHIP RECREATION CENTER ANC 3E UPDATE January 12, 2017 . ... • January 2017- Completion of Foundation

Project Update

Page 3: FRIENDSHIP RECREATION CENTER ANC 3E UPDATE January 12, … · 2017-01-18 · FRIENDSHIP RECREATION CENTER ANC 3E UPDATE January 12, 2017 . ... • January 2017- Completion of Foundation

Construction Progress

Backfill & Compact Soil – New Storm Line Removal Process of Existing Storm Line

Page 4: FRIENDSHIP RECREATION CENTER ANC 3E UPDATE January 12, … · 2017-01-18 · FRIENDSHIP RECREATION CENTER ANC 3E UPDATE January 12, 2017 . ... • January 2017- Completion of Foundation

Construction Progress

Cast In Place Manhole Structures for New Storm Line

Page 5: FRIENDSHIP RECREATION CENTER ANC 3E UPDATE January 12, … · 2017-01-18 · FRIENDSHIP RECREATION CENTER ANC 3E UPDATE January 12, 2017 . ... • January 2017- Completion of Foundation

Construction Progress

Foundation Trenching Foundation Work Underway

Page 6: FRIENDSHIP RECREATION CENTER ANC 3E UPDATE January 12, … · 2017-01-18 · FRIENDSHIP RECREATION CENTER ANC 3E UPDATE January 12, 2017 . ... • January 2017- Completion of Foundation

Construction Progress

Foundation Work Underway Foundation Work Underway

Page 7: FRIENDSHIP RECREATION CENTER ANC 3E UPDATE January 12, … · 2017-01-18 · FRIENDSHIP RECREATION CENTER ANC 3E UPDATE January 12, 2017 . ... • January 2017- Completion of Foundation

Construction Progress

Splash Pad Vault Concrete Pad for Splash Pad Vault

Page 8: FRIENDSHIP RECREATION CENTER ANC 3E UPDATE January 12, … · 2017-01-18 · FRIENDSHIP RECREATION CENTER ANC 3E UPDATE January 12, 2017 . ... • January 2017- Completion of Foundation

Next Steps Moving Forward

• January 2017- Completion of Foundation / Start of Walls

• February 2017 – Building Shell Construction

• March 2017– Building Shell Completion

• April 2017- Interior Building Completion

• April 2017 – Playground Construction & Completion

• Spring 2017 - Project Completion (Memorial Weekend)

Page 9: FRIENDSHIP RECREATION CENTER ANC 3E UPDATE January 12, … · 2017-01-18 · FRIENDSHIP RECREATION CENTER ANC 3E UPDATE January 12, 2017 . ... • January 2017- Completion of Foundation

Contact Information

Department of General Services (DGS)

Jackie Stanley, Community Outreach Specialist [email protected]

Shahrokh Ghahramani, Project Manager

[email protected]

Department of Parks & Recreation (DPR)

Brent Sisco, Landscape Architect [email protected]