FPDS-NG Agency Day July 21, 2003. Recent Activities. Specifications Product Development Change Management. Specifications. Specifications published for Agency review on www.FPDSNG.com Web services specifications XML specifications Reviewed by IAE and GSA. Product Development. - PowerPoint PPT Presentation

TRANSCRIPT

FPDS-NGAgency Day

July 21, 2003

Recent Activities

Specifications

Product Development

Change Management

Specifications

Specifications published for Agency review on www.FPDSNG.com– Web services specifications– XML specifications

Reviewed by IAE and GSA

Product Development

Hardened the Reference Implementation from prototype to production quality codeIncreased functionality of FPDS-NG– IDV– Reference data– System Administrator functions– Portal – Modifications– Corrections/Voids– Enhanced reporting– Batch processing– FPDS data migration

Change Management

Outreach efforts to Agencies and vendors underwayBriefings scheduled with

– DOT– DHS– EPA

Briefings held with

– USCG– DOD– State– Commerce– IRS

– AMS– CACI– Compusearch– VA– HUD– Interior

Product Demonstration

System Administration

Data Collection

Reports

Lunch Break

Integrated Systems

USCG – Finance & Procurement Desktop (FPD)

USCG – PRISM

DOD – CACI

DOI – Procurement Desktop (PD)

HUD – HPS

Early Adoption Integration Methodology

Meet with Agency and technical representatives– Visualize the existing and desired architecture

Review of feeder systems and data warehouses

– Agreement on timeline and resource availability– Review by Agency technical staff of specifications– Determination of key integration points in source system(s)– Technical support as needed from GCE staff– Integration testing

This is an accelerated version of the FPDS-NG Agency Integration Plan

Integration Methodology

USCG – FP Desktop

Current/Proposed Integration Architecture

Technology

Integration Method

Duration

Demonstration

Q/A

Current Architecture

Integration

Technology– Web HTML/Java– Government owned system

Integration Method– GUI Object

Duration– 1 week

Demonstration

PRISM

Current/Proposed Integration Architecture

Technology

Integration Method

Duration

Demonstration

Q/A

Integration

Technology– Web ASP (Microsoft)– COTS product

Integration Method– GUI Object

Duration– 3-4 days

Demonstration

CACI – DOD

Current/Proposed Integration Architecture

Technology

Integration Method

Duration

Demonstration

Q/A

Integration

Technology– Progress– COTS product

Integration Method– GUI Object

Duration– 2 days

Demonstration

DOI – Procurement Desktop

Current/Proposed Integration Architecture

Technology

Integration Method

Duration

Demonstration

Q/A

Integration

Technology– PowerBuilder 6.5– COTS product

Integration Method– GUI Object

Duration– 2 days

Demonstration

HUD – HPS

Current/Proposed Integration Architecture

Technology

Integration Method

Duration

Demonstration

Q/A

Integration

Technology– PowerBuilder 6.5– Government owned system

Integration Method– GUI Object

Duration– 1 day

Demonstration

In Progress

IRS – GOTS

Commerce – CACI

DOD Ed. – CACI

Next Steps

FAC Briefing – July 29, 2003

FQT – July 30 – August 5, 2003

System Administrator Training – August