for personal use only · the society of petroleum engineers (spe) and an associate member of the...

45
Investor Presentation 10 August 2015 ABN 38 112 566 499 For personal use only

Upload: others

Post on 25-Sep-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Investor Presentation10 August 2015

ABN 38 112 566 499

For

per

sona

l use

onl

y

This presentation does not constitute investment advice. Neither this presentation not the information contained in it constitutes an offer, invitation, solicitation or recommendation in relation to the purchase or sale of shares in Elk Petroleum Ltd – ABN (the “Company”) - in any jurisdiction.

Shareholders should not rely on this presentation. This presentation does not take into account any person’s particular investment objectives, financial resources or other relevant circumstances and the opinions and recommendations in this presentation are not intended to represent recommendations of particular investments to particular persons. All securities transactions involve risks, which include (among others) the risk of adverse or unanticipated market, financial or political developments.

The information set out in this presentation does not purport to be all inclusive or to contain all the information which its recipients may require in order to make an informed assessment of the Company. You should conduct your own investigations and perform your own analysis in order to satisfy yourself as to the accuracy and completeness of the information, statements and opinions contained in this presentation.

To the fullest extent permitted by law, the Company does not make any representation or warranty, express or implied, as to the accuracy or completeness of any information, statements, opinions, estimates, forecasts or other representations contained in this presentation. No responsibility for any errors or omissions from this presentation arising out of the negligence or otherwise is accepted.

This presentation may include forward looking statements. Forward looking statements are only predictions and are subject to risks, uncertainties and assumptions which are outside the control of the Company. These risks, uncertainties and assumptions include commodity prices, currency fluctuations, economic and financial market conditions in various countries and regions, environmental risks and legislative, fiscal or regulatory developments, political risks, project delay or advancement, approvals and cost estimates.

Actual values, results or events may be materially different to those expressed or implied in this presentation. Any forward looking statements in this presentation speak only at the date of issue of this presentation. Subject to any continuing obligations under applicable law and the ASX Listing Rules, the Company does not undertake any obligation to update or revise any information or any of the forward looking statements in this presentation or an changes in events, conditions or circumstances on which any such forward looking statement is based.

The reserves and resources assessment follows the guidelines set forth by the Society of Petroleum Engineers – Petroleum Resource Management System (SPE-PRMS).

The Reserves and Contingent Resources in this announcement relating to the Grieve CO2 EOR project, operated by Denbury Resources, is based on an independent reviewand audit conducted by Pressler Petroleum Consultants, Inc. and fairly represents the information and supporting documentation reviewed. The review and audit was carriedout in accordance with the SPE Reserves Auditing Standards and the SPE-PRMS guidelines under the supervision of Mr. Grant Olsen, a Director of Pressler PetroleumConsultants, Inc., an independent petroleum advisory firm. Mr. Olsen is a Registered Professional Engineer in the State of Texas and his qualifications include a Bachelor ofScience and Master of Science (both in Petroleum Engineering) from Texas A&M University. He has more than 10 years of relevant experience. Mr. Olsen is a member ofthe Society of Petroleum Engineers (SPE) and an Associate Member of the Society of Petroleum Evaluation Engineers. Mr. Olsen meets the requirements of QualifiedPetroleum Reserve and Resource Evaluator as defined in Chapter 19 of the ASX Listing Rules and consents to the inclusion of this information in this report.

The information in this presentation that relates to Reserve and Contingent Resources estimates for the Grieve CO2 EOR project and the Contingent Resource estimates forthe Singleton CO2 EOR project have been compiled or in the case of the Singleton CO2 EOR project prepared by Mr. Brian Dolan, COO and VP-Engineering of ElkPetroleum USA who is a qualified person as defined under the ASX Listing Rule 5.11 and has consented to the use of the reserves figures in the form and context in whichthey appear in this presentation. Mr. Dolan is a full-time employee of the company. Mr. Dolan earned a degree in Mechanical Engineering from the University of Colorado atBoulder and has more than 23 years of relevant experience. Mr. Dolan has sufficient experience that is relevant to the company’s Reserves and Resources to qualify as aReserves and Resources Evaluator as defined in the ASX Listing Rules. Mr. Dolan consents to the inclusion in this presentation of the matters based on the information inthe form and context in which it appears

Disclaimer & Important Notice

2

For

per

sona

l use

onl

y

Elk Petroleum – Where we are

3

ELK PROJECTS

Grieve Singleton

Location of current CO2 EOR projects and pipeline infrastructure Source: NETL 2010

For

per

sona

l use

onl

y

Corporate Summary

Only ASX-listed Enhanced Oil Recovery (EOR) company

Focused on oil field redevelopment with proven technologies

Key projects in proven EOR production fairways

Committed to delivering current US projects

Near term potential to capture additional growth projects

Longer-term growth bringing core EOR expertise into untapped maturing Australasian oil provinces

4

Capital Structure

ASX code ELK

Ordinary Shares 201.1m

52-week Low-High (A$ cps) 0.02-0.11

Market cap @ 6.5cps A$13m

Enterprise Value (USD 1: AUD 0.73) A$36m

Cash (30 June 2015) A$1.6m

Reserves + Resources (2P+2C)* ~6.5 mmbls

Reserves and Resources for the Grieve Project were the subject of the Company’s ASX Announcement of 29 January 2015. This presentation includes the first announcement of Contingent Resources for the Singleton CO2 EOR Project and these details are included in slide 44.

Major shareholdersRobert Healy 25.23%

Begley Superannuation 11.52%

Republic Investment Management Pte. Ltd 10.89%

HSBC (Including Republic Investment Management) 9.9%

Board & Management 3.4% - Pre Placement7.0% - Post Placement

0

0.02

0.04

0.06

0.08

0.1

0.12

A$ c

ps

Axis Title

Elk one-year share price chart12-months ending 6 August 2015

For

per

sona

l use

onl

y

Investment Case

5

• Strong leadership with proven track record of value creation

• Extensive experience and expertise in Enhanced Oil Recovery (EOR)

• Existing US assets provide strong foundation

• Significant further EOR project growth potential in core areas

• Current oil price environment presents unique opportunity for low cost EOR project asset accumulation

• Significant opportunity to apply EOR in largely untapped areas of Australia, Indonesia and Malaysia

• Focused and differentiated strategy to deliver shareholder value

• Strong news flow pipeline to first oil - targeted for early CY2017For

per

sona

l use

onl

y

Managing Director & Chief Executive

Brad Lingo Appointed 1 August 2015

Former MD & CEO of Drillsearch Energy 15-fold increase in market valuation / 8-fold increase in share price

Became Australia’s 3rd largest onshore oil producer

Finance - successfully raised ~A$450m in equity and debt

Delivered 29 new conventional discoveries

Drilled 98 wells over 6-years with 73% success rate

Oversaw the production commencement of 12 new fields

Expertise: Proven upstream/midstream oil & gas company building track record

Business development, New Ventures, M&A and corporate finance

Experience: Tenneco Energy

El Paso Corporation

Sunshine Gas

Commonwealth Bank of Australia (SVP & Head of Oil & Gas)

6

0

100

200

300

400

500

600

700

A$ m

illio

nMarket cap growth of Drillsearch from 2009 to 2014

For

per

sona

l use

onl

y

Enhanced & Improved Oil RecoveryEOR / IOR Overview

7

For

per

sona

l use

onl

y

What is EOR / IOR ?

EOR/IOR are proven approaches successfully deployed for over 40 years

Substantially increase overall oil recovery from & productive life of fields

Deliver attractive economics even in low oil price markets

Used extensively in North America & Middle East

Largely under-utilized in Australasia

Widely implemented techniques include: CO2 injection Chemical injection Nitrogen injection Waterfloods Natural Gas injection Steamfloods

20-25%

10-20%

10-20%

35-60%

Overall Oil Recovery

Primary Recovery Secondary Recovery - IOR

Tertiary Recovery - EOR Remaining Oil

8

Our Focus

Source: Advances in Enhanced Oil Recovery Processes – Romero-Zeron – University of New Brunswick (2012)

For

per

sona

l use

onl

y

How does CO2 EOR work?

9

Proven technology and most commonly-used form of EOR

Accounts for nearly 60% of EOR production in the US

Frequently sourced from existing natural fields with high CO2 contents

CO2 can be supplied from man-made sources such as power plants

Known as ‘Green Oil’ due to ability to sequester CO2

Currently only profitable carbon capture & storage (CCS) without subsidy

Recognising cost of carbon will only further enhance CO2 EOR potential

Secure CO2supply

Transport via pipeline

or truckInject into

oil field

For

per

sona

l use

onl

y

Strategy for Value Creation

10

For

per

sona

l use

onl

y

Global EOR potential

11

Global EOR market*• Projected to grow at

8.8% CAGR• Estimated to be

worth $34.4bn by 2019

*BCC Research, August 2013

For

per

sona

l use

onl

y

Market Opportunity - US

Proven technology projected to deliver substantial growth in oil recovery and production from existing fields

First commercial CO2 EOR production commenced in 1972

~100bn to 160bn barrels of stranded oil forecast for recovery by EOR technology*

1.5bn barrels produced through CO2 EOR over past 25 years**

*US Department of Energy**Visiongain Research, October 2014

12

For

per

sona

l use

onl

y

Market Opportunity – Wyoming

13

2630

2425

542431

191 46 29

Cumulative Oil Production (MMBO)Basin Name Total CO2 EOR Candidate ReservoirsPowder River 289Bighorn 105Wind River 45Greater Green River 49Overthrust Belt 12Laramie 11Denver-Cheyene 6

Source: SPE-122921-MS-Estimates of Potential CO2 Demand for CO2 EOR in Wyoming Basins

Rockies Region contains ~2-6bn technically recoverable barrels through CO2 EOR*

*2013 Dept. of Energy NETL Next Gen EOR

For

per

sona

l use

onl

y

Market Opportunity – Australasia

14

Source: SPE-165487-Opportunities and Challenges of CO2 Flooding in Indonesia

“”To date the recovery has been only 3-4% of the original-oil-in-place, and simulation studies indicate a recovery at abandonment ofsome 5-10%. Hence, it is envisaged that a suitable EOR schememay help improve recovery. With a suitable gas injection process, itis estimated that the ultimate recovery would increase to 20-30%implying that some 2.5 MMstb of oil could be recovered.

Company Fields Resevoirs Miscible ImmisibleMedco 14 76 18 25Conoco Philips 8 27 18 5EP Prabumulih 3 59 55 0Ubep Adera 3 181 181 0Ubep Ramba 12 8 6 2Ubep Limau 3 10 10 0Prabumulih & Pendopo 10 154 92 62TAC / KSO 5 20 2 2Pertamina 5 36 1 16Total 63 571 383 112

Screening Criteria for CO2 Injection in South Sumatera

Source: SPE-88451-Technical Evaluation of CO2 Flood for EOR Benefitsin the Cooper Basin, South Australia

For

per

sona

l use

onl

y

Elk’s EOR Capabilities

10-years focused EOR experience in a proven EOR production fairway

JV with leading US independent entirely focused on CO2 EOR project development

Established relationships with CO2 suppliers, pipelines & EOR engineering and oil field service companies

Secured CO2 supply and access to necessary infrastructure to deliver key Grieve Project

Existing supply arrangement could provide access to additional CO2 supply for growth in current and new projects

Key personnel with track record of EOR field screening, selection and development experience across multiple technologies – Water flood, CO2, Chemical, Thermal

Established second EOR growth production fairway – Denver-Julesburg Basin –rejuvenating mature oil assets through CO2 EOR from man-made sources

15

For

per

sona

l use

onl

y

16

Current Projects

For

per

sona

l use

onl

y

Elk Petroleum – Where we are

17

ELK PROJECTS

Grieve Singleton

Location of current CO2 EOR projects and pipeline infrastructure Source: NETL 2010

For

per

sona

l use

onl

y

Where we are….

18

For

per

sona

l use

onl

y

Flagship Grieve Oil Field CO2 EOR Development

19

For

per

sona

l use

onl

y

Elk (35%) / Denbury Resources (65% & operator)

2P Reserves 12.0 mmbbls (gross) 3.5 mmbbls (Elk net WI after royalties)

Estimated Gross Project Cost = ~US$100m Gross Project Investment to date = US$75m Elk Estimated Net CAPEX to First Oil = US$35m Elk Remaining CAPEX = US$12-13m Investment to date includes CAPEX/OPEX & CO2

Project approximately 70% complete to first oil

Major remaining project works

Construct Operator processing/recompression facilities

Scheduled to commence late 2015

Attractive economics and material cash flow outlook

Near-term opportunity to increase JV interest & resume operatorship

Grieve CO2 EOR Project - Overview

20

Source: Elk ASX Release 29 January 2015 – Grieve Reserve Update

Reserve Summary as 31 December 2014

Scenario Net Oil to Elk(Mbbls)

Capital Expenditures(US$MM)

2P (Probable Reserves) 3,455 25.8

3P (Probable + Possible Reserves) 4,660 22.4

3C (Contingent Resources) 4,685 21.1

Source: Elk ASX Release 29 January 2015 – Grieve Reserve Update

100

1,000

10,000

Gro

ss O

il Ra

te, B

bls/

D

Time, Years

Grieve - 3C

Grieve - 3P

Grieve - 2P

For

per

sona

l use

onl

y

Grieve CO2 EOR Project – A Field-level View

* Based on Elk’s own estimates

Central Facilities Location- Office- Power- Oil storage- Processing & compression- Distribution and gathering manifold centre

CO2MeteringStation

Project Update:- CO2 injection started March 2013- CO2 injection at 40 MMCFD- Water well completed April 2013- Water injection at 17 MBPD

First Oil expected Q1 2017

21

For

per

sona

l use

onl

y

Grieve CO2 EOR Project – Milestones Achieved

22

Work Completed New injection and production wells

In-field CO2/water injection& Oil production flow lines

Power supply from local grid installed

Site works & production manifold

3-mile CO2 supply line

Elk-owned crude oil export pipeline upgrade

Reservoir re-pressurizing 10+ million barrels of water injected

17+ Bcf of CO2 injected

Est 30 BCF CO2 required to achieve first oil

Currently injecting CO2 at 40 MMCFD

Reservoir pressure rising in line or ahead forecast

First oil expected early 2017

For

per

sona

l use

onl

y

Grieve Field Re-pressurisation – Actual vs Projected

0

200

400

600

800

1000

1200

1400

1600

1800

2000

2200

2400

2600

2800

3000

3200

3400

Res

ervo

ir Pr

essu

re (p

sig)

First Oil March 2017

First Oil Sept. 2016

Well #20

Well #22

Well #11

Well #5

Well #10

Well #18

Well #12

Well #6A

Well #30

MMP = 2256 Psig

BHP is at Free Flowing

First Oil March 2017 BHP = 3180

Last Survey Date June 24, 2015

23

For

per

sona

l use

onl

y

Grieve CO2 EOR Project – Remaining Steps to First Oil

Construction of oil processing & CO2 recompression facilities

Scheduled to commence in late 2015

Additional facility construction cost to be borne by operator

Continue injection of water and CO2 to re-pressurize the reservoir

Upgrade water injection system capacity scheduled to be increased to 38,000 BWPD

Facilities construction expected to be finished for first oil in Q1 CY2017

24

For

per

sona

l use

onl

y

Access to Markets - Grieve Crude Oil Export Pipeline

Grieve Crude Oil Export Pipeline owned 100% by Elk Enables Grieve oil production to be directly shipped to Casper Refinery avoiding costly transport BLM Grieve Project Environmental Approvals only allow oil export via pipeline – not trucking Pipeline commissioning works now scheduled to be likely undertaken in 1st half 2016 Discussions on-going with prospective 3rd parties – shippers & potential pipeline purchasers Significant potential for Elk to monetise the pipeline resulting in a material cash inflow

Refinery

25

For

per

sona

l use

onl

y

Grieve CO2 EOR Project – How does the Project look economically?

26

Evaluation is based on Reserves announced in ASX Release of 29 Jan 2015

Project economics reflect current field development plan and timing of first oil Q1 CY2017

2P Reserves Case based on Pressler 2P reserves estimates of 12.0 mmbbls

3P Reserves Case recovers 16.1 mmbbls under the current field development plan through achieving higher recovery factors

3C Contingent Resource Case recovers 16.3 mmbbls reflecting use of greater CO2 volumes in the EOR field redevelopment

2P Reserves Case is based on an overall field development scenario utilizing less CO2 volumes than previous Company 2P development scenarios

2P Case is inherently conservative in terms of volumes recovered

Significant upside in project economics can be realized by expanding the CO2 flood to recover additional oil and from oil price increases

0

10

20

30

40

50

60

70

80

90

100

0 10 20 30 40 50 60 70 80 90 100

IRR,

%

Oil Price, $/Bbl

2P Scenario

3P Scenario

3C Scenario

0

10

20

30

40

50

60

70

80

90

100

0 10 20 30 40 50 60 70 80 90 100

PV-1

0, $

Mill

ion

Oil Price, $/Bbl

2P Scenario

3P Scenario

3C Scenario

For

per

sona

l use

onl

y

Singleton Oil Field CO2 EOR Development

27

For

per

sona

l use

onl

y

Corn Ethanol Producers – A Potential New Large-Scale CO2 Supply

28

For

per

sona

l use

onl

y

Denver-Julesburg Basin – Significant Growth Area for Elk

DJ Basin has over 1000 oil fields (shown in yellow) in Colorado and Nebraska

Intensive drilling activity began in 1950

DJ Basin was the most active drilling area in the Rockies from 1950 to 1966

More than 52,000 wells drilled

Primary producing formation is the Lower Cretaceous Muddy (“J”) Sandstone – same as Grieve

Conventional “J” sandstone reservoirs are stratigraphic traps – same as Grieve

Water flooding of the “J” reservoirs began in the early 1960’s

Most fields are nearing end of secondary recovery efforts and approaching abandonment without EOR

DJ Basin is a mature oil basin that has not had any tertiary oil recovery projects

Bridgeport CO2 Supply

29

For

per

sona

l use

onl

y

Singleton Oil Field – D-J Basin Entry & Strong CO2 EOR Candidate

100% Elk-owned & operated project

Contingent Resources

2C = 3.0 mmbbls

3C = 4.0 mmbbls

Excellent sand quality

Setting ideal for CO2-oil miscibility

Modest acquisition cost

Existing wells available for field redevelopment

Expect rapid response to injected CO2

Field in close proximity to CO2 supply source

Potential to develop in conjunction with near-by satellite fields to improve overall economics

30

Singleton Unit - J Sand Isopach

For

per

sona

l use

onl

y

Singleton Oil Field – Green Oil Production

CO2 supply comes from Bridgeport Corn Ethanol Plant

Project uses man-made CO2 from industrial process which is otherwise vented

Project effectively acts as a Carbon Capture & Storage Project

Capture of CO2 through EOR results in more CO2 captured than generated from oil produced

Environmental benefits contribute to overall economic potential from Carbon Negative Oil

“Green” Carbon Negative Oil from CO2EOR production attracts sale premium

31

Source: K.Y. Hornafius, J.S. Hornafius / International Journal of Greenhouse Gas Control 37 (2015) 492-503

Four to six barrels of liquid CO2 at reservoir conditions (0.5 to 0.7metric tons) are needed to recover one barrel of oil in a CO2-EORproject. The carbon dioxide created by combustion of one barrel of oil(~0.43 metric tons) is less than the amount of CO2 sequestered.F

or p

erso

nal u

se o

nly

Singleton Oil Field – Green Oil Production

32

Source: K.Y. Hornafius, J.S. Hornafius / International Journal of Greenhouse Gas Control 37 (2015) 492-503

For

per

sona

l use

onl

y

Singleton AOI CO2 EOR Development Hub

Area of Interest (AOI) has 10 oil fields

AOI Fields produced a combined 51 mmbbls

AOI Goal to develop 5 largest fields on a staged CO2 project

AOI Indicative CO2 EOR Potential 25 mmbbls

Potential Bridgeport CO2-source sufficient to supply AOI Hub

Development of CO2 EOR Hub markedly improves overall economics

Singleton

Bridgeport

33

For

per

sona

l use

onl

y

Singleton CO2 EOR Project Economics

Singleton stand-aloneReserves – Development Case MI3 (2014)

Resources – 3C (mmbbls) 4.0

Gross Project Investment (US$ million) 48

Capex + Opex (US$/bbl) 42

F&D (US$/bbl) 15

Undiscounted PV (US$ million) 47

Undiscounted PIR 1.0

Discounted PV10% (US$ million) 10

Discounted PIR 0.2

IRR% 15

Based on the oil price forecast provided in Appendix slide page 42

34

For

per

sona

l use

onl

y

35

Investment Summary

For

per

sona

l use

onl

y

Core Assets Lay Foundation for Growth

Deliver First Oil from Grieve Project by Early 2017 Existing interest in Grieve expected to deliver significant operating cash flow

Delivers long-life reserves with gradual decline to supports other projects

Focused on resolution of historical issues with JV Partner giving rise to opportunity to acquire 100% of project

Additional JV interest would significantly increase Company’s production and operating cash flow

Deliver Singleton bio-CO2 EOR project and other AOI Fields Existing interest in Singleton expected to average ~1100 BOPD over first 5-years

Delivers long-life reserves with gradual decline to supports other projects

Acquire additional Nebraska AOI Fields & commence staged development

Acquire Additional Wyoming CO2 EOR Project currently on market Debt-distressed operators currently exiting CO2 EOR pre-development assets

Provides growth path with remaining Grieve CO2 contract rights

Potential to build production in Wyoming to 8,800 BOPD within 5-years

Expand bio-CO2 EOR operations from Nebraska into Colorado Use Singleton & AOI Fields as anchor to secure larger CO2 supplies

Acquire additional suitable fields in the DJ Basin CO2 EOR fairway

With anchor CO2 Supply & DJ Basin Fields sponsor Nebraska-to-Colorado CO2 EOR pipeline project

Commence development the DJ Basin fields along the CO2 EOR pipeline corridor

36

For

per

sona

l use

onl

y

Near-term Activity Pipeline

37

CY2015 CY2016 CY2017

Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2

Commence construction of Grieve Facility

Potential acquisition of additional Grieve interest

Complete Singleton bio-CO2 EOR prefeasibility study

Secure support from CSM for final pre-FID Singleton pilot

Grieve Field re-pressurisation complete

Commence commissioning of Grieve Facility

First oil production - Grieve Co2 EOR Project

For

per

sona

l use

onl

y

Path to Production

Elk now attracting significant institutional investor support to see it well positioned to deliver Grieve Project and grow beyond

Secure funding for development of Grieve CO2 EOR Project

Multiple options via debt, equity & internal JV funding mechanisms

Board & Management committed to participation in funding

Elk focused on executing funding option that delivers shareholder value

Significant first oil production from Grieve CO2 EOR Project targeted within next 12-18 months

Shareholder value to be delivered through both capital appreciation and payment of dividends as material production and cash flows commence

38

For

per

sona

l use

onl

y

39

Contact:Level 9, 341 George St, Sydney, 2000

02 9299 9690

For

per

sona

l use

onl

y

40

Appendix

For

per

sona

l use

onl

y

Board & Management

Neale TaylorNon-Executive Director and Chairman, Melbourne

Over 40 years of technical, operating and commercial experience in oil and gas exploration, production, planning and evaluation, acquisition and joint venture management with major industry players, including Esso Australia. Former Chairman of Tap Oil Ltd, former CEO of Nexus Energy Ltd and Cambrian Oil & Gas PLC

Matthew HealyNon-Executive Director, Sydney

Mr Healy currently holds a management position at one of Australia’s foremost property development and infrastructure groups, is an active investor in the resources sector and has over 15 years of experience working in management and operational roles.

41

Scott HornafiusPresident – Elk Petroleum USA (Elk wholly owned US subsidiary, Denver)

Over 29 years of exploration, technical, management, and funding experience in the oil and gas industry including 16 years with Mobil in the US, PNG and UK before founding MegaEnergy in 2000. As President of MegaEnergy, he was responsible for joint ventures involving play identification, land acquisitions, drilling and development programs and major funding programs and developed a 100,000 acre position in the Marcellus shale prior to being sold for over $100 million. He is a founding Director of Canning Petroleum Pty Ltd, which now holds very large onshore permit areas in Western Australia.

Brad LingoManaging Director and Chief Executive Officer, Sydney

Over 25 years of experience in all phases of the oil & gas business ranging from business development, new ventures, exploration, development and production as well as mergers and acquisitions, equity capital raising and debt financing for both listed and private companies. Currently Chairman of Mont Dór Petroleum, a private oil & gas exploration and production company with operations in Indonesia and New Zealand and the former Managing Director & CEO of Drillsearch Energy Ltd and former CEO of Sunshine Gas Ltd.

Tim HargreavesNon-Executive Director, Sydney

Over 35 years experience in technical and managerial roles in the petroleum and mining sectors in Asia and the Middle East for major companies including BHP, Fletcher Challenge and Union Texas Petroleum as well as start ups and small to mid-sized independents. He has led successful exploration and commercialisation campaigns in Pakistan and Egypt, which were dependent upon technical and commercial innovation in complex regulatory environments. Since 2009 he has been Research Director of Resources for Republic Investment Management, a Singapore-based investment fund, which is a major investor in ELK and the major participant in the Convertible Loan recently raised by the Company and, until recently, he was a Director of The Environmental Group Limited (ASX : EGL).

Russell KrauseNon-Executive Director, Melbourne

Over 25 years experience in Stockbroking and Investment Management with a primary focus on the resources sector. He has held a number of Directorships and Senior Management positions with a number of Australia’s leading firms, including firms with US oil and gas assets. For the past ten years he has worked on a number of North American oil and gas projects in relation to Capital Raising and Corporate Advisory.

For

per

sona

l use

onl

y

Grieve CO2 EOR Project Economics – Oil Price Forecast

46.00

48.00

50.00

52.00

54.00

56.00

58.00

60.00

62.00

64.00

66.00

OIL

PR

ICE

(US$

/BB

L)

WTI OIL PRICE FORECAST

42

For

per

sona

l use

onl

y

Singleton CO2 EOR Project – Contingent Resources

Elk holds 100% of the working interest in Singleton Unit in Nebraska

Elk assumed ownership of the Singleton Unit in May 2014

The Singleton Oil Field was discovered by Sinclair Oil in 1955 and commenced oil production in 1957

Production continued on a secondary water flood basis through 2013

Over this period, the Singleton Oil Field produced ~10.9 mmbbls of 37.5 API oil and 2020 MMCF of gas

Elk engaged MI3 Petroleum Engineering in 2013 for evaluation of the Singleton Oil Field as a future CO2 EOR project

Elk’s internal studies and MI3 have identified 3 primary oil pay intervals in the Muddy Formation – J1, J2 and J3 sands

Studies have indicated that the J1 and J2 sands have excellent rock properties for a CO2 EOR project

Studies indicate that Singleton oil properties are ideal for a miscible CO2 EOR project, with most likely reserves of 3.0 MMBO in the J1 and J2 sands, and with a high side case of 4.0 MMBO if J3 sands are included in the assessment

The Company has determined that based on the geotechnical evaluation and reservoir studies and simulations undertaken by the Company and with MI3 that the Singleton Unit may be redeveloped through the use of CO2 enhanced oil recovery, a proven tertiary oil recovery and production process

In parallel with these studies, the Company has secured a conditional CO2 supply contract sufficient to satisfy the amount of CO2 required to implement this project

Water injection has resumed to assist with the re-pressurization of the field in advance of undertaking an expanded CO2 EOR pilot project

Singleton CO2 EOR Project As of 30 June 2015

Gross Contingent Resources

Resource Category 1C 2C 3C

Mmbbls - 3.0 4.0

43

The above estimate of Contingent Resources for the Singleton Unit isbased on a potential redevelopment of the field through a CO2 EORProject.

This Contingent Resources assessment follows the guidelines set forth bythe Society of Petroleum Engineers – Petroleum Resource ManagementSystem (SPE-PRMS).The Contingent Resources have been assessedusing deterministic methods.

The estimate of the Singleton Unit on this basis has been prepared by Mr.Brian Dolan, COO and VP-Engineering of Elk Petroleum USA who is aqualified person as defined under the ASX Listing Rule 5.11 and hasconsented to the use of the reserves figures in the form and context inwhich they appear in this presentation.

Mr. Dolan is a full-time employee of the company. Mr. Dolan earned adegree in Mechanical Engineering from the University of Colorado atBoulder and has more than 24 years of relevant experience.

Mr. Dolan has sufficient experience that is relevant to the company’sReserves and Resources to qualify as a Reserves and ResourcesEvaluator as defined in the ASX Listing Rules. Mr. Dolan consents to theinclusion in this presentation of the matters based on the information in theform and context in which it appears.

For

per

sona

l use

onl

y

Primary & Secondary Oil Recovery Processes

44

Source: Advances in Enhanced Oil Recovery Processes – Romero-Zeron – University of New Brunswick (2012)

For

per

sona

l use

onl

y

EOR Processes

45

Source: Advances in Enhanced Oil Recovery Processes – Romero-Zeron – University of New Brunswick (2012)

For

per

sona

l use

onl

y