focus on fire protection

Upload: mushtaq-siddiqui

Post on 06-Apr-2018

223 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/3/2019 Focus on Fire Protection

    1/6

    Fire Protection Shop Drawing Review

    Process

    One of the final stages of the sprinkler system design process (prior to the pipefitter beginninginstallation) is the review and acceptance of sprinkler shop drawings (a.k.a. working plans, as

    defined by NFPA 13: Standard for the Installation of Sprinkler Systems). Typical submissionsthat are required are sprinkler system piping plans, hydraulic calculations, and materials

    submitted. (For this column, lets assume that the materials submitted meet the project

    specifications.)

    Sprinkler shop drawings should include the details of the project, such as the exact locations ofsprinklers and the equipment necessary for the operation of the system. It is important to provide

    a clear representation of the hazards and commodities to be protected, the system piping design

    concept, available water supply information, sprinkler system hydraulic demands, and building

    construction information important to system layout and detailing (i.e., fire separations). Theseplans also should reflect coordination with other trades.

    Several parties usually conduct a review of the sprinkler shop drawings, including the owners

    representatives (architect, engineer, and insurer) and the local authority having jurisdiction, suchas the fire marshal or building subcode official. Working plans should be submitted for approval

    prior to any equipment installation.

    SPRINKLER WORKING PLANS

    NFPA 13 provides thorough checklists of the information required to be shown on sprinkler

    working plans, water supply data, and hydraulic calculation forms. Not all of the items listedbelow may be applicable on every project and are subject to the reviewers discretion.

    According to NFPA 13 Section 22.1.3, working plans shall be drawn to an indicated cale, on

    sheets of uniform size, with a plan of each floor. They also shall show those items from the

    following list that pertain to the design of the system:

    Name of owner and occupant

    Location, including street address

    Point of compass

    Full height cross-section, or schematic diagram, including structural member information

    if required for clarity, ceiling construction, and method of protection for nonmetallicpiping

    Locations of partitions and firewalls

    Occupancy class of each area or room

    Locations and sizes of concealed spaces, closets, attics, and bathrooms

    Any small enclosures in which no sprinklers are to be installed

  • 8/3/2019 Focus on Fire Protection

    2/6

    Size of city main in street and whether dead end or circulating if dead end, show the

    direction and distance to the nearest circulating maincity main test results, and system

    elevation relative to test hydrant

    Other sources of water supply, with pressure or elevation

    Make, type, model, and nominal K-factor of sprinklers, including sprinkler identification

    number Temperature rating and location of high-temperature sprinklers

    Total area protected by each system on each floor

    Number of sprinklers on each riser per floor

    Total number of sprinklers on each dry pipe system, preaction system, combined dry

    pipe/preaction system, or deluge system

    Approximate capacity in gallons of each dry pipe system

    Pipe type and schedule of wall thickness Nominal pipe size and cutting lengths of pipe (or center-tocenter dimensions)where

    typical branch lines prevail, size only one typical line

    Locations and sizes of riser nipples

    Type of fittings and joints and locations of all welds and bends Any sections to be shop-welded and the type of fittings or formations to be used (the

    contractors responsibility to specify on the drawing)

    Types and locations of hangers, sleeves, braces, and methods of securing sprinklers when

    applicable

    All control valves, check valves, drain pipes, and test connections

    Make, type, model, and size of alarm or dry pipe valve and of preaction or deluge valve

    Kind and location of alarm bells

    Size and location of standpipe risers, hose outlets, hand hose, monitor nozzles, and

    related equipment

    Private fire service main size, length, location, weight, material, and point of connectionto city main; the sizes, types, and locations of valves, valve indicators, regulators, meters,

    and valve pits; and the depth that the top of the pipe is laid below grade

    Piping provisions for flushing

    Where the equipment is to be installed as an addition to an existing system, with enough

    of the existing system indicated on the plans to make all conditions clear

    For hydraulically designed systems, the information on the hydraulic data nameplate

    A graphic representation of the scale used on all plans

    Name and address of contractor

    Hydraulic reference points shown on the plan that correspond with comparable referencepoints on the hydraulic calculation sheets

    The minimum rate of water application (density, flow, or discharge pressure), the design

    area of water application, in-rack sprinkler demand, and the water required for hose

    streams both inside and outside The total quantity of water and the pressure required noted at a common reference point

    for each system

    Relative elevations of sprinklers, junction points, and supply or reference points

    If room design method is used, all unprotected wall openings throughout the floor

    protected

  • 8/3/2019 Focus on Fire Protection

    3/6

    Calculation of loads for sizing and details of sway bracing

    The setting for pressure-reducing valves

    Information about backflow preventers (manufacturer, size, and type)

    Information about antifreeze solution used (type and amount)

    Sizes and locations of hydrants, showing size and number of outlets and if outlets are to

    be equipped with independent gate valves Whether hose houses and equipment are to be provided and by whom

    Static and residual hydrants that were used in flow tests

    Size, location, and piping arrangement of fire department connection

    Ceiling and roof heights and slopes not shown in the full height cross-section

    Edition year of NFPA 13 to which the sprinkler system is designed

    WATER SUPPLY

    In addition to the sprinkler system working plans, review of the available water supply is

    necessary. Most municipalities require a flow test to be performed within 12 months of systeminstallation. The flow data can come from a hydrant flow test or from an existing fire pumpsystem test (if applicable).

    NFPA 13 Section 22.2.1 provides a checklist of required information as part of the

    design/documentation process. Such information includes:

    Location and elevation of static and residual test gauge with relation to the riser reference

    point

    Flow location

    Static pressure, in pounds per square inch (psi)

    Residual pressure, in psi Flow, in gallons per minute (gpm)

    Date

    Time

    Who conducted the test or supplied the information

    Other sources of water supply, with pressure or elevation

    Table 1 Example detailed worksheet snapshot

    ReferenceNozzle typeand location

    Flow ingpm

    Pipe size(inches)

    Fittings anddevices

    Pipe equiv.length

    Friction loss(psi/ft) Req. psi

    12 to 14qQ

    0.00572.58

    4.026120

    E,DPV, GVlgthftg

    tot

    22.00034.000

    56.000

    0.092

    Pt

    PfP

    e

    13.51

    5.17

    11.2

    7

    14 to 13 q

    Q

    0.00

    572.58

    6.065 120 E, CV, E lgth

    ftg

    20.000

    60.000

    0.013 Pt

    Pf

    13.5

    1

  • 8/3/2019 Focus on Fire Protection

    4/6

    tot 80.000P

    e

    5.17

    11.2

    7

    13 to 15 qQ 0.00572.58 6.065120 GV, T

    lgth

    ftgtot

    54.000

    33.00087.000

    0.013

    Pt

    PfPe

    24.0

    11.090.00

    15 to 16qQ

    0.00572.58

    7.981120

    lgth

    ftgtot

    200.000

    0.000200.000

    0.003

    Pt

    PfP

    e

    25.1

    00.66

    0.00

    Qt 822.58 Pt25.7

    6

    HYDRAULIC CALCULATIONS

    Once the sprinkler system layout and the available water supply have been reviewed for

    compliance with NFPA 13, you need to review the associated hydraulic calculations to verify

    that the system doesnt exceed available water pressure or flow. Typically, hydraulic calculations

    are developed using sprinkler system hydraulic calculation programs such as HASS orHydraCALC. Hydraulic calculations shall be prepared on form sheets that include a summary

    sheet, detailed worksheets, and a graph sheet.

    Summary Sheet

    According to NFPA 13 Section 22.3.2, the summary sheet shall contain the followinginformation, where applicable:

    Date

    Location

    Name of owner and occupant

    Building number or other identification

    Description of hazard, including the commodity classification, storage height, and rackconfiguration for storage applications

    Name and address of contractor or designer

    Name of approving agency

    System design requirements, as follows:o Design area of water application, in square feet

    o Minimum rate of water application (density), in gpm per square foot (Where

    sprinklers are listed with minimum water application in gpm or pressure in psi,

    the minimum rate of water application shall be indicated in gpm or psi.)

    o Area per sprinkler, in square feet

  • 8/3/2019 Focus on Fire Protection

    5/6

  • 8/3/2019 Focus on Fire Protection

    6/6

    Figure 1 Example hydraulic graph

    Graph Sheet

    A graphic representation (see Figure 1) of the complete hydraulic calculation shall include the

    following:

    Water supply curve (provided from water supply data)

    Sprinkler system demand (provided from detailed worksheet)

    Hose allowance (where applicable)

    In-rack sprinkler demand (where applicable)

    REFERENCES

    NFPA 13Automatic Sprinkler Systems Handbook, Chapter 22: Working Plans. National Fire

    Protection Association, 2009.

    STEVE ZIGA, CPD, CET, CFPS, is a principal with hpeGROUP, LLC inBerwyn, Pennsylvania. He is an officer on the ASPE Philadelphia Chapter

    board of directors. Contact him at sziga @ hpegroup.com. For more

    information or to comment on this article, e-mail articles @ psdmagazine.org.

    prev

    Return to Index

    http://www.psdmagazine.org/ASPE_memberpdf/20090708/PSD-JulAug09.php?page=21http://www.psdmagazine.org/ASPE_memberpdf/20090708/PSD-JulAug09.php?page=4http://www.psdmagazine.org/ASPE_memberpdf/20090708/PSD-JulAug09.php?page=4http://www.psdmagazine.org/ASPE_memberpdf/20090708/PSD-JulAug09.php?page=21