focus on fire protection
TRANSCRIPT
-
8/3/2019 Focus on Fire Protection
1/6
Fire Protection Shop Drawing Review
Process
One of the final stages of the sprinkler system design process (prior to the pipefitter beginninginstallation) is the review and acceptance of sprinkler shop drawings (a.k.a. working plans, as
defined by NFPA 13: Standard for the Installation of Sprinkler Systems). Typical submissionsthat are required are sprinkler system piping plans, hydraulic calculations, and materials
submitted. (For this column, lets assume that the materials submitted meet the project
specifications.)
Sprinkler shop drawings should include the details of the project, such as the exact locations ofsprinklers and the equipment necessary for the operation of the system. It is important to provide
a clear representation of the hazards and commodities to be protected, the system piping design
concept, available water supply information, sprinkler system hydraulic demands, and building
construction information important to system layout and detailing (i.e., fire separations). Theseplans also should reflect coordination with other trades.
Several parties usually conduct a review of the sprinkler shop drawings, including the owners
representatives (architect, engineer, and insurer) and the local authority having jurisdiction, suchas the fire marshal or building subcode official. Working plans should be submitted for approval
prior to any equipment installation.
SPRINKLER WORKING PLANS
NFPA 13 provides thorough checklists of the information required to be shown on sprinkler
working plans, water supply data, and hydraulic calculation forms. Not all of the items listedbelow may be applicable on every project and are subject to the reviewers discretion.
According to NFPA 13 Section 22.1.3, working plans shall be drawn to an indicated cale, on
sheets of uniform size, with a plan of each floor. They also shall show those items from the
following list that pertain to the design of the system:
Name of owner and occupant
Location, including street address
Point of compass
Full height cross-section, or schematic diagram, including structural member information
if required for clarity, ceiling construction, and method of protection for nonmetallicpiping
Locations of partitions and firewalls
Occupancy class of each area or room
Locations and sizes of concealed spaces, closets, attics, and bathrooms
Any small enclosures in which no sprinklers are to be installed
-
8/3/2019 Focus on Fire Protection
2/6
Size of city main in street and whether dead end or circulating if dead end, show the
direction and distance to the nearest circulating maincity main test results, and system
elevation relative to test hydrant
Other sources of water supply, with pressure or elevation
Make, type, model, and nominal K-factor of sprinklers, including sprinkler identification
number Temperature rating and location of high-temperature sprinklers
Total area protected by each system on each floor
Number of sprinklers on each riser per floor
Total number of sprinklers on each dry pipe system, preaction system, combined dry
pipe/preaction system, or deluge system
Approximate capacity in gallons of each dry pipe system
Pipe type and schedule of wall thickness Nominal pipe size and cutting lengths of pipe (or center-tocenter dimensions)where
typical branch lines prevail, size only one typical line
Locations and sizes of riser nipples
Type of fittings and joints and locations of all welds and bends Any sections to be shop-welded and the type of fittings or formations to be used (the
contractors responsibility to specify on the drawing)
Types and locations of hangers, sleeves, braces, and methods of securing sprinklers when
applicable
All control valves, check valves, drain pipes, and test connections
Make, type, model, and size of alarm or dry pipe valve and of preaction or deluge valve
Kind and location of alarm bells
Size and location of standpipe risers, hose outlets, hand hose, monitor nozzles, and
related equipment
Private fire service main size, length, location, weight, material, and point of connectionto city main; the sizes, types, and locations of valves, valve indicators, regulators, meters,
and valve pits; and the depth that the top of the pipe is laid below grade
Piping provisions for flushing
Where the equipment is to be installed as an addition to an existing system, with enough
of the existing system indicated on the plans to make all conditions clear
For hydraulically designed systems, the information on the hydraulic data nameplate
A graphic representation of the scale used on all plans
Name and address of contractor
Hydraulic reference points shown on the plan that correspond with comparable referencepoints on the hydraulic calculation sheets
The minimum rate of water application (density, flow, or discharge pressure), the design
area of water application, in-rack sprinkler demand, and the water required for hose
streams both inside and outside The total quantity of water and the pressure required noted at a common reference point
for each system
Relative elevations of sprinklers, junction points, and supply or reference points
If room design method is used, all unprotected wall openings throughout the floor
protected
-
8/3/2019 Focus on Fire Protection
3/6
Calculation of loads for sizing and details of sway bracing
The setting for pressure-reducing valves
Information about backflow preventers (manufacturer, size, and type)
Information about antifreeze solution used (type and amount)
Sizes and locations of hydrants, showing size and number of outlets and if outlets are to
be equipped with independent gate valves Whether hose houses and equipment are to be provided and by whom
Static and residual hydrants that were used in flow tests
Size, location, and piping arrangement of fire department connection
Ceiling and roof heights and slopes not shown in the full height cross-section
Edition year of NFPA 13 to which the sprinkler system is designed
WATER SUPPLY
In addition to the sprinkler system working plans, review of the available water supply is
necessary. Most municipalities require a flow test to be performed within 12 months of systeminstallation. The flow data can come from a hydrant flow test or from an existing fire pumpsystem test (if applicable).
NFPA 13 Section 22.2.1 provides a checklist of required information as part of the
design/documentation process. Such information includes:
Location and elevation of static and residual test gauge with relation to the riser reference
point
Flow location
Static pressure, in pounds per square inch (psi)
Residual pressure, in psi Flow, in gallons per minute (gpm)
Date
Time
Who conducted the test or supplied the information
Other sources of water supply, with pressure or elevation
Table 1 Example detailed worksheet snapshot
ReferenceNozzle typeand location
Flow ingpm
Pipe size(inches)
Fittings anddevices
Pipe equiv.length
Friction loss(psi/ft) Req. psi
12 to 14qQ
0.00572.58
4.026120
E,DPV, GVlgthftg
tot
22.00034.000
56.000
0.092
Pt
PfP
e
13.51
5.17
11.2
7
14 to 13 q
Q
0.00
572.58
6.065 120 E, CV, E lgth
ftg
20.000
60.000
0.013 Pt
Pf
13.5
1
-
8/3/2019 Focus on Fire Protection
4/6
tot 80.000P
e
5.17
11.2
7
13 to 15 qQ 0.00572.58 6.065120 GV, T
lgth
ftgtot
54.000
33.00087.000
0.013
Pt
PfPe
24.0
11.090.00
15 to 16qQ
0.00572.58
7.981120
lgth
ftgtot
200.000
0.000200.000
0.003
Pt
PfP
e
25.1
00.66
0.00
Qt 822.58 Pt25.7
6
HYDRAULIC CALCULATIONS
Once the sprinkler system layout and the available water supply have been reviewed for
compliance with NFPA 13, you need to review the associated hydraulic calculations to verify
that the system doesnt exceed available water pressure or flow. Typically, hydraulic calculations
are developed using sprinkler system hydraulic calculation programs such as HASS orHydraCALC. Hydraulic calculations shall be prepared on form sheets that include a summary
sheet, detailed worksheets, and a graph sheet.
Summary Sheet
According to NFPA 13 Section 22.3.2, the summary sheet shall contain the followinginformation, where applicable:
Date
Location
Name of owner and occupant
Building number or other identification
Description of hazard, including the commodity classification, storage height, and rackconfiguration for storage applications
Name and address of contractor or designer
Name of approving agency
System design requirements, as follows:o Design area of water application, in square feet
o Minimum rate of water application (density), in gpm per square foot (Where
sprinklers are listed with minimum water application in gpm or pressure in psi,
the minimum rate of water application shall be indicated in gpm or psi.)
o Area per sprinkler, in square feet
-
8/3/2019 Focus on Fire Protection
5/6
-
8/3/2019 Focus on Fire Protection
6/6
Figure 1 Example hydraulic graph
Graph Sheet
A graphic representation (see Figure 1) of the complete hydraulic calculation shall include the
following:
Water supply curve (provided from water supply data)
Sprinkler system demand (provided from detailed worksheet)
Hose allowance (where applicable)
In-rack sprinkler demand (where applicable)
REFERENCES
NFPA 13Automatic Sprinkler Systems Handbook, Chapter 22: Working Plans. National Fire
Protection Association, 2009.
STEVE ZIGA, CPD, CET, CFPS, is a principal with hpeGROUP, LLC inBerwyn, Pennsylvania. He is an officer on the ASPE Philadelphia Chapter
board of directors. Contact him at sziga @ hpegroup.com. For more
information or to comment on this article, e-mail articles @ psdmagazine.org.
prev
Return to Index
http://www.psdmagazine.org/ASPE_memberpdf/20090708/PSD-JulAug09.php?page=21http://www.psdmagazine.org/ASPE_memberpdf/20090708/PSD-JulAug09.php?page=4http://www.psdmagazine.org/ASPE_memberpdf/20090708/PSD-JulAug09.php?page=4http://www.psdmagazine.org/ASPE_memberpdf/20090708/PSD-JulAug09.php?page=21