Fire Station 203: Project Introduction and Site Layout Presentation: March 31, 2016

Fire Station 203

Project Introduction &

Site Layout Presentation

March 31, 2016

Page 2: Fire Station 203 - alexandriava.gov

Fire Station 203: Project Introduction and Site Layout Presentation: March 31, 2016

Presentation Overview

Project Team Introductions

(Jeremy McPike, Director, General Services)

Project Background and Schedule

(Irina Jamison, Project Manager, General Services)

Fire Service Needs

(Robert Dubé, Fire Chief)

Site Layout

(Jeremy Kline, Project Architect, WGM Architects)

Questions

2

Page 3: Fire Station 203 - alexandriava.gov

Fire Station 203: Project Introduction and Site Layout Presentation: March 31, 2016

Project Background

• Comprehensive Needs Assessment for

Alexandria Fire Stations Commenced

• City Council Authorizes Funding

• Request For Proposals (RFP) Solicitations for

Qualified Architectural Firms

• Interviews with Top Ranked Architectural

Firms

• Contract Negotiations and Award to Wheeler

Goodman Masek (WGM) Architects

2005

2014

Spring 2015

Summer 2015

Fall 2015

3

Page 4: Fire Station 203 - alexandriava.gov

Fire Station 203: Project Introduction and Site Layout Presentation: March 31, 2016 4

Project Budget

Total Project Budget*

$7,905,000

Design Cost

10%

Project Construction

70%

Furniture, Fixtures and Equipment 9%

Construction and Management Services 6%

Project Contingency 5%

*Additional Contingency Submitted in Proposed FY 2017 Capital Budget

Page 5: Fire Station 203 - alexandriava.gov

Fire Station 203: Project Introduction and Site Layout Presentation: March 31, 2016

Project Milestones

• Design Contract Awarded

• Design and Community Outreach

• Development Special Use Permit

(DSUP) Consideration by Planning

Commission and City Council

• Construction Bid and Award

• Fire Station 203 Construction

• Construction Completion

October 2015

Spring/Summer 2016

Fall 2016

Spring 2017

2017/2018

Winter 2018

5

Page 6: Fire Station 203 - alexandriava.gov

Fire Station 203: Project Introduction and Site Layout Presentation: March 31, 2016

Existing Site

6

Page 7: Fire Station 203 - alexandriava.gov

Fire Station 203: Project Introduction and Site Layout Presentation: March 31, 2016

Station 203 History

7

• Built in 1948

• Smaller structure at

5,900 ft2 as volunteers

responded from home

to serve the community

• Original responding

apparatus was smaller.

• Around-the-clock

career personnel

increased over time

Fire Station 203 – Beverly Hills

Construction Project Community

Presentation

Page 8: Fire Station 203 - alexandriava.gov

Fire Station 203: Project Introduction and Site Layout Presentation: March 31, 2016

Station 203 Current Facility Issues

8

• Administrative and

living accommodations

not adequate for

increased staffing

• Modern fire and EMS

vehicles are

significantly larger

• No space to provide

additional units to meet

service needs

Fire Station 203 – Beverly Hills Construction Project Community Presentation

Page 9: Fire Station 203 - alexandriava.gov

Fire Station 203: Project Introduction and Site Layout Presentation: March 31, 2016

Station 203 Public Safety Needs

9

• Target Fire & EMS arrival within 4 minutes

• Surrounding stations cannot meet arrival times

• Temporary facility will remain in the community to

support a medic (transport) unit and an engine

company

• New, three bay station will have flexibility to support

a wider variety of units and personnel to meet

changing demands of community

Fire Station 203 – Beverly Hills Construction Project Community Presentation

Page 10: Fire Station 203 - alexandriava.gov

Fire Station 203: Project Introduction and Site Layout Presentation: March 31, 2016

Station 203 Response Profile

10 Fire Station 203 – Beverly Hills Construction Project Community Presentation

Page 11: Fire Station 203 - alexandriava.gov

Fire Station 203: Project Introduction and Site Layout Presentation: March 31, 2016

Existing Site

11

Page 12: Fire Station 203 - alexandriava.gov

Fire Station 203: Project Introduction and Site Layout Presentation: March 31, 2016 12

Site Plan Concept

Page 13: Fire Station 203 - alexandriava.gov

Fire Station 203: Project Introduction and Site Layout Presentation: March 31, 2016

Site Development: Existing Site 13

Page 14: Fire Station 203 - alexandriava.gov

Fire Station 203: Project Introduction and Site Layout Presentation: March 31, 2016

Site Development: Temporary Facility 14

Page 15: Fire Station 203 - alexandriava.gov

Fire Station 203: Project Introduction and Site Layout Presentation: March 31, 2016

Site Development: Temporary Facility 15

Page 16: Fire Station 203 - alexandriava.gov

Fire Station 203: Project Introduction and Site Layout Presentation: March 31, 2016

Site Development: New Station - Concept 16

Page 17: Fire Station 203 - alexandriava.gov

Fire Station 203: Project Introduction and Site Layout Presentation: March 31, 2016 17

Site Plan Concept

Page 18: Fire Station 203 - alexandriava.gov

Fire Station 203: Project Introduction and Site Layout Presentation: March 31, 2016

Questions

18

Contact: Irina Jamison

Phone: 703-746-3209

Email: [email protected]

Project information can be found on City of

Alexandria, General Services website:

https://www.alexandriava.gov/generalservices