yard etrorail station project€¦ · 8/20/2018  · pyca| august 20, 2018 16 questions? additional...

16
POTOMAC Y ARD METRORAIL STATION PROJECT Potomac Yard Civic Association Project Update August 20, 2018

Upload: others

Post on 24-Aug-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: YARD ETRORAIL STATION PROJECT€¦ · 8/20/2018  · PYCA| August 20, 2018 16 QUESTIONS? Additional Info: Jason Scofi, CCM, PMP 703-746-4060 (Direct) 571-969-0713 (Mobile) Jason.Scofi@AlexandriaVA.gov

POTOMAC YARD

METRORAIL STATION PROJECT

Potomac Yard Civic Association

Project Update

August 20, 2018

Page 2: YARD ETRORAIL STATION PROJECT€¦ · 8/20/2018  · PYCA| August 20, 2018 16 QUESTIONS? Additional Info: Jason Scofi, CCM, PMP 703-746-4060 (Direct) 571-969-0713 (Mobile) Jason.Scofi@AlexandriaVA.gov

PYCA| August 20, 2018

MEETING PURPOSE

• Contract Award

• Next Steps

• Station Access

• Ongoing Communication

2

Page 3: YARD ETRORAIL STATION PROJECT€¦ · 8/20/2018  · PYCA| August 20, 2018 16 QUESTIONS? Additional Info: Jason Scofi, CCM, PMP 703-746-4060 (Direct) 571-969-0713 (Mobile) Jason.Scofi@AlexandriaVA.gov

PYCA| August 20, 2018

WMATA DESIGN-BUILD CONTRACT AWARD

• Contract award status

• Includes enhancements to the station access from East Glebe Road

• Contractor’s representative will be at next PYMIG meeting on September 26.

3

Page 4: YARD ETRORAIL STATION PROJECT€¦ · 8/20/2018  · PYCA| August 20, 2018 16 QUESTIONS? Additional Info: Jason Scofi, CCM, PMP 703-746-4060 (Direct) 571-969-0713 (Mobile) Jason.Scofi@AlexandriaVA.gov

PYCA| August 20, 2018

CITY PLAN APPROVAL PROCESS

• Initial application for DSUP amendment submitted by staff on July 18, 2018

• PYMIG meeting on September 26, October, and November

• Planning Commission and City Council Public Hearings anticipated in December

• Board of Architectural Review meetings

4

Page 5: YARD ETRORAIL STATION PROJECT€¦ · 8/20/2018  · PYCA| August 20, 2018 16 QUESTIONS? Additional Info: Jason Scofi, CCM, PMP 703-746-4060 (Direct) 571-969-0713 (Mobile) Jason.Scofi@AlexandriaVA.gov

PYCA| August 20, 2018

PROJECT DESIGN AND PERMITTING

• Design will commence in Fall 2018 and continue thru the Fall of 2019

• Integrated Project Team – Contractor

– WMATA

– City

• Permitting

5

Page 6: YARD ETRORAIL STATION PROJECT€¦ · 8/20/2018  · PYCA| August 20, 2018 16 QUESTIONS? Additional Info: Jason Scofi, CCM, PMP 703-746-4060 (Direct) 571-969-0713 (Mobile) Jason.Scofi@AlexandriaVA.gov

PYCA| August 20, 2018

STATION ACCESS

• Contract includes enhancements to access from

East Glebe Road

• Refine station access from Potomac Greens

• Public input will be sought on design options at

PYMIG meetings

6

Page 7: YARD ETRORAIL STATION PROJECT€¦ · 8/20/2018  · PYCA| August 20, 2018 16 QUESTIONS? Additional Info: Jason Scofi, CCM, PMP 703-746-4060 (Direct) 571-969-0713 (Mobile) Jason.Scofi@AlexandriaVA.gov

PYCA| August 20, 2018

STATION ACCESS POINTS

7

Page 8: YARD ETRORAIL STATION PROJECT€¦ · 8/20/2018  · PYCA| August 20, 2018 16 QUESTIONS? Additional Info: Jason Scofi, CCM, PMP 703-746-4060 (Direct) 571-969-0713 (Mobile) Jason.Scofi@AlexandriaVA.gov

PYCA| August 20, 2018

CONSTRUCTION ACTIVITY

8

Page 9: YARD ETRORAIL STATION PROJECT€¦ · 8/20/2018  · PYCA| August 20, 2018 16 QUESTIONS? Additional Info: Jason Scofi, CCM, PMP 703-746-4060 (Direct) 571-969-0713 (Mobile) Jason.Scofi@AlexandriaVA.gov

PYCA| August 20, 2018

CONSTRUCTION TIMELINE

• Late 2018 – Pre-design site activity

• Late 2019 – Site preparation

• Early 2020 – Initiation of station construction

• Early 2022 – Project completion

• Contractor will provide a schedule

9

Page 10: YARD ETRORAIL STATION PROJECT€¦ · 8/20/2018  · PYCA| August 20, 2018 16 QUESTIONS? Additional Info: Jason Scofi, CCM, PMP 703-746-4060 (Direct) 571-969-0713 (Mobile) Jason.Scofi@AlexandriaVA.gov

PYCA| August 20, 2018

INITIAL ON-SITE ACTIVITIES

• Contractor information gathering activities on-site

• Mobilize office trailers, laydown areas, and parking facilities

• Bulk of the effort for the first year will be Design and Permitting

• Pre-construction survey of surrounding properties

10

Page 11: YARD ETRORAIL STATION PROJECT€¦ · 8/20/2018  · PYCA| August 20, 2018 16 QUESTIONS? Additional Info: Jason Scofi, CCM, PMP 703-746-4060 (Direct) 571-969-0713 (Mobile) Jason.Scofi@AlexandriaVA.gov

PYCA| August 20, 2018

INITIAL ON-SITE ACTIVITIES

• Pre-design activities:

– Land Surveying

– Geotechnical Investigations

– Pre-Construction Assessment of Adjacent Buildings

– Utility Locations and Condition Assessment

• Fencing, clearing, and erosion protection

measures associated with this work

11

Page 12: YARD ETRORAIL STATION PROJECT€¦ · 8/20/2018  · PYCA| August 20, 2018 16 QUESTIONS? Additional Info: Jason Scofi, CCM, PMP 703-746-4060 (Direct) 571-969-0713 (Mobile) Jason.Scofi@AlexandriaVA.gov

PYCA| August 20, 2018

PROJECT MAP

12

Page 13: YARD ETRORAIL STATION PROJECT€¦ · 8/20/2018  · PYCA| August 20, 2018 16 QUESTIONS? Additional Info: Jason Scofi, CCM, PMP 703-746-4060 (Direct) 571-969-0713 (Mobile) Jason.Scofi@AlexandriaVA.gov

PYCA| August 20, 2018

CONSTRUCTION IMPACTS AND MITIGATION

13

Potential Impacts Potential MitigationConstruction Traffic & Parking Hour of Operation

Bus WorkersSecure SiteInspector Presence

Contaminated Soils Testing of Materials Prior to RemovalEnsure Proper HandlingSoil Management Plan

Night Work Provide Advance NoticeMinimize Frequency

Page 14: YARD ETRORAIL STATION PROJECT€¦ · 8/20/2018  · PYCA| August 20, 2018 16 QUESTIONS? Additional Info: Jason Scofi, CCM, PMP 703-746-4060 (Direct) 571-969-0713 (Mobile) Jason.Scofi@AlexandriaVA.gov

PYCA| August 20, 2018

COMMUNICATION

• Project updates provided:

– PYMIG meetings

– Briefings at regular PYCA meetings

– Pertinent information provided to PYCA leadership,

and disseminated to members

– Project website

– Alexandria eNews

– Call or email Jason or Mitch directly

14

Page 15: YARD ETRORAIL STATION PROJECT€¦ · 8/20/2018  · PYCA| August 20, 2018 16 QUESTIONS? Additional Info: Jason Scofi, CCM, PMP 703-746-4060 (Direct) 571-969-0713 (Mobile) Jason.Scofi@AlexandriaVA.gov

PYCA| August 20, 2018

UPCOMING PROJECT SCHEDULE

15

Aug 2018 Sep Oct Nov Dec Jan 2019

WMATA Contract

Award and Notice to Proceed

DSUP Amendment

Initial Submission

Community Outreach

PYMIG

DSUP PC and City Council

Consideration

Initial On-Site Activities*

* survey, geotechnical investigations, utility locations, construction trailers

Page 16: YARD ETRORAIL STATION PROJECT€¦ · 8/20/2018  · PYCA| August 20, 2018 16 QUESTIONS? Additional Info: Jason Scofi, CCM, PMP 703-746-4060 (Direct) 571-969-0713 (Mobile) Jason.Scofi@AlexandriaVA.gov

PYCA| August 20, 2018 16

QUESTIONS?

Additional Info:

Jason Scofi, CCM, PMP

703-746-4060 (Direct)

571-969-0713 (Mobile)

[email protected]

eNews Sign up, select Potomac Yard Metro Station updates:

www.AlexandriaVA.gov/eNews

For more information, visit:

www.AlexandriaVA.gov/PotomacYard