    Zikreet Office Building - MJ154 Office Buil

    Ganesh 1

    Activity description Start date Finish date

    12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 2

    A001 Block work

    1 Preparation of area and materials arrangement

    2 Layout of block wall and fixing of rebar dowels from concrete slab

    3

    4

    5 Inspection of formwork and rebar prior to concreting

    6

    7 Water curing concrete up to 7 days

    8 Fixing of blocks up to bottom of the suspended slab level

    9 Curing of the block work up to 3 days

    10 Installation of the electromechanical services

    11 Inspection of electromechanical services prior to plaster works

    A002 Plaster works for internal walls

    1 Preparation for plaster work

    Installation of corner beads, plaster stop and joint lath2

    3 Applying of plaster 25 mm thick to made smooth finish surface

    4 Water curing for plastered surface for 3 days

    A003 Plaster works for external walls

    1 Preparation for plaster work

    Installation of corner beads, plaster stop and joint lath

    2

    3 Applying of plaster 25 mm thick to made smooth finish surface

    4 Water curing for plastered surface for 3 days

    A004 Window fins

    1 Marking location of windows fins

    2 Installation of GRC window fins and alignment

    3 Installation of embedded conduits

    4 Inspection of fins prior to applying the shining sand

    A005 Shining sand application

    1 Surface preparation and sanding

    2 Inspection of surface and survey report

    3 Application of undercoat

    4 Application of shining sand

    5 Final inspection

    A006 Waterproofing (roofs)

    1 Preparation of structural surface and soaking

    2 Installation of floor drains and testing3 Pouring of screed concrete to slope

    4 Application of primer

    5 Installation of waterproofing membrane

    6 Water leak test

    7 Installation of polystyrene board

    8 Installation of geo-textile cloth

    9 Laying of aggregate

    10 Installation of aluminum wall base and sealant application

    A007 Ceramic tiles for walls (toilets and pantries)

    1

    2

    3

    4 Cleaning and protection of the tiles

    5 Inspection of the ceramic tiles

    A008 Waterproofing wet areas

    1 Preparation of structural surface

    2 Inspection of structural surface

    3 Application of two coats Masterseal SP 120 PF and set for drying

    4 Filling of water and water leak test prior to proceeding the screed works

    5 Inspection of water leak test

    6

    7 Water curing for screed concrete up to 7 days

    A009 Ceramic tiles for floors (toilets and pantries)

    9 Installation of floor drains and clean-outs

    ActivityID

    TotalDays

    Fixing of blocks with all anchor and tie system up to bottom of the

    stiffener beam level

    Preparation of reinforcement and formwork for cast in-situ stiffener/lintelbeams and stiffener columns

    Concrete pouring for lintles/stiffner beams and stiffener columns OPC60N

    Applying of the rash coat over the block wall surface 24 hours prior toapplying the plaster

    Applying of the rash coat over the block wall surface 24 hours prior toapplying the plaster

    Surface preparation, tile layout and vertical alignment prior to fixing theceramic tiles

    Installation of the wall ceramic tiles by using of Nitotile-489manufactured by M/s Fosroc

    Grouting of tile joints by using of Nitotile epoxy grout manufactured byM/s Fosroc

    Preparation of elevations and pouring of the screed concrete up to bottomof the floor tiles in slope as per mentioned drawings

    Surface preparation, tile layout and alignment prior to fixing the ceramictiles

    Installation of the floor ceramic tiles by using of Nitotile-489manufactured by M/s Fosroc

    Grouting of tile joints by using of Nitotile epoxy grout manufactured byM/s Fosroc

  • 8/4/2019 Finishes 5th Level

    2/6

    Zikreet Office Building - MJ154 Office Buil

    Ganesh 2

    Activity description Start date Finish date

    12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 2

    ActivityID

    TotalDays

    10

    11 Cleaning and protection of the tiles

    A010 Gypsum wall cladding (Internal)

    1 Area preparation and marking for gypsum wall cladding

    2 Installation of the floor and ceiling runners

    3 Installation of the vertical studs at required spacing

    4 Installation of the concealed electromechanical services

    5

    6 Inspection of the wall framing system

    7 Fixing of the hardboard 10mm thick

    8 Fixing of the gypsum board over the hardboard

    A011 Paint woks (Internal) over gypsum and plaster surfaces

    1 Preparation of wall surfaces (plaster/gypsum)

    2 Inspection of the wall surfaces prior to applying the primer

    3 Application of the primer one coat

    4 Application of the filler and made smooth finish

    5 Inspection of the filler prior to first finish coat6 Application of the first finish coat

    7 Application of the second finish coat

    8 Inspection of the final surface

    A012 Suspended ceiling (Mineral fiber, linear metal and gypsum)

    1 Transportation and arrangement of the materials

    2 Layout and marking of center lines for suspension system hangers

    3 Installation of the suspension hangers on concrete slab

    4 Marking and installation of the perimeter angles

    5

    6 Inspection of the electromechanical services prior to closing the ceiling

    7 High level clearance by electromechanical trades

    8

    9 Alignment and leveling of the suspension system at required elevation

    10

    A013 Blast resistant and metal doors

    1 Area preparation and marking

    2 Transportation and handling of doors to location

    3 Installation of door frames

    4 Installation of door leafs

    5 Fixing of door hardware6 Installation access control system

    7 Alignment and grouting for doors

    8 Final inspection

    A014 Marble flooring

    1 Area preparation and marking layout

    2 Transportation and handling of marble tiles

    3 Soaking of concrete slab

    4 Placing of mortar bedding and application of sealer behind tiles

    5 Installation of marble tiles/treads/raisers

    6 Cleaning and filling the grout

    7 Surface buffing/grinding

    8 Polishing and application of wax

    9 Final inspection

    A015 Terrazzo flooring at service staircases

    1 Area preparation and marking layout

    2 Transportation and handling of terrazzo tiles

    3 Soaking of concrete slab

    4 Placing of mortar bedding

    5 Installation of terrazzo tiles/treads/raisers

    6 Cleaning and filling the grout

    7 Surface buffing/grinding

    8 Polishing and application of wax

    9 Final inspection

    A016 Wooden doors

    1 Area preparation and marking

    2 Transportation and handling of doors to location

    3 Installation of door frames4 Installation of door leafs

    5 Paint touchup and protection

    6 Final inspection

    A017 Pantry units

    1 Marking of location for wall and floor units

    2 Installation of pantry units

    3 Fixing of hardware

    4 Cleaning and touchup

    5 Final inspection and protection

    A018 Aluminum windows and curtain walls

    Grouting of ceramic tiles by using of Nitotile epoxy grout manufacturedby M/s Fosroc

    Inspection of the electromechanical services prior to closing the wallboard

    Installation of the electromechanical services prior to fixing thesuspension system

    Installation of the suspension system main grid T runners and cross Trunners

    Laying of the ceiling tiles with cut-outs where required for sprinklersystem and fire detectors

  • 8/4/2019 Finishes 5th Level

    3/6

    Zikreet Office Building - MJ154 Office Buil

    Ganesh 3

    Activity description Start date Finish date

    12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 2

    ActivityID

    TotalDays

    1 Site survey for actual measurements and verticality

    2 Area preparation and marking of windows and curtain walls

    3 Transportation and handling of the materials

    4 Installation of the framing system and alignment

    5 Application of the blast resistant film over the glass panels

    6 Installation of the glass panels and final fix of the frames

    7 Application of the sealant all around the windows and curtain walls

    8 Installation of the integrated aluminum doors in curtain walls

    9 Installation of the hardware for doors and windows

    11 Final cleaning of the all aluminum works

    12 Final inspection and testing

    A019 Installation of Revolving door

    1 Floor preparation and cutting knock outs

    2 Installation of floor tracks and floor spring

    3 Installation of enclosure

    4 Installation of swing leafs

    5 Installation of hardware

    6 Installation of door lighting

    7 Installation of access control system8 Testing and commissioning

    9 Final inspection

    A020 Demountable partition

    1 Site preparation and marking layout for top and bottom runners

    2 Materials handling and transportation to site

    3 Instillation of the metal framing system

    4 Installation of electrical and network conduits & services

    5 Inspection of the metal framing system

    6 Instillation of the gypsum boards and filling the joints

    7 Surface preparation and installation of the wall cloth

    8 Installation of the external trims and skirting

    9 Installation of the wooden doors and hardware

    10 Final alignment and cleaning prior to inspection

    11 Final inspection and testing

    A021 Free standing partition

    1 Marking of location

    2 Installation of bottom track

    3 Installation of wall frames and top rails

    4 Alignment and final fix

    5 Final inspection

    A021 Vinyl tiles

    1 Site cleaning and preparation for vinyl tile area

    2 Inspection of the surface

    3 Installation of the vinyl tiles

    4 Installation of the vinyl wall base

    5 Cleaning and application of wax

    6 Final inspectionA022 Carpet

    1 Surface cleaning and preparation for carpet area

    2 Inspection of the surface

    3 Transpiration and storage of the carpet tiles to site

    4 Installation of the carpet

    5 Installation of floor boxes

    6 Installation of the edge guards and carpet gripper

    7 Final inspection of carpet works

    8 Protection of the carpet works

    A023 Handrails

    1 Transportation of materials and handling

    2 Marking and fixing of the base plates

    3 Installation of the handrails and railing

    4 Joints welding

    5 Grinding and polishing

    6 Protection of handrails

    7 Final inspection

    A024 Toilet cubicles

    1 Site preparation and marking layout for cubicles

    2 Materials transportation and handling to site

    3 Assembling and fixing of bottom framing system

    4 Installation of the cubicle walls

    5 Installation of hardware

    6 Final alignment

    7 Final inspection

    A025 Sanitary items

    1 Site preparation and marking

    2 Materials handling and transportation to site

    3 Installation of the sanitary ware and accessories

    4 Testing commissioning

    5 Protection of the sanitary works

    6 Final inspection

    A026 Internal signage

    1 Preparation of room titles index

    2 Marking and installation of signage

    A027 Expansion joint covers

    1 Materials transportation and handling

    2 Installation of expansion joint covers on walls and floor

  • 8/4/2019 Finishes 5th Level

    4/6

    Zikreet Office Building - MJ154 Office Building Finis

    Ganesh 4 of 6

    Activity description Start date Finish date

    12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1

    ActivityID

    TotalDays

    3 Final inspection

    A028 Testing

    A029 Pre-commissioning

    A030 Commissioning

    A031 Snagging

    A032 De-snagging

  • 8/4/2019 Finishes 5th Level

    5/6

    Zikreet Office Building - MJ154 Sub-Station W

    Ganesh 5

    Activity description Start date Finish date May-10

    11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

    Block work

    1 Preparation of area and materials arrangement

    2 Layout of block wall and fixing of rebar dowels from concrete slab

    3

    4

    5 Inspection of formwork and rebar prior to concreting

    6

    7 Water curing concrete up to 7 days

    8 Fixing of blocks up to bottom of the suspended slab level

    9 Curing of the block work up to 3 days

    10 Installation of the electromechanical services

    11 Inspection of electromechanical services prior to plaster works

    Plaster works

    1 Preparation for plaster work

    2

    3 Applying of plaster 25 mm thick to made smooth finish surface

    4 Water curing for plastered surface for 3 days

    Ceramic tiles for walls (toilets and pantries)

    1

    2

    3

    4 Cleaning and protection of the tiles

    5 Inspection of the ceramic tiles

    1 Preparation of structural surface

    2 Inspection of structural surface

    3 Application of two coats Masterseal SP 120 PF and set for drying

    4 Filling of water and water leak test prior to proceeding the screed works

    5 Inspection of water leak test

    6

    7 Water curing for screed concrete up to 7 days

    8

    9 Installation of floor drains and clean-outs

    10

    11 Cleaning and protection of the tiles

    Gypsum wall cladding

    Area preparation and marking for gypsum wall cladding

    Installation of the floor and ceiling runners

    Installation of the vertical studs at required spacing

    Installation of the concealed electriomechanical services

    Inspection of the wall framing system

    Fixing of the hardboard 10mm thick

    Fixing of the gypsum board over the hardboard

    Paint woks (Internal) over gypsum and plaster surfaces

    Preparation of wall surfaces (plaster/gypsum)

    Inspection of the wall surfaces prior to applying the primer

    Application of the primer one coat

    Application of the filler and made smooth finish

    Inspection of the filler prior to first finish coat

    Application of the first finish coat

    Application of the second finish coat

    Inspection of the final surface

    Suspended ceiling

    Transportation and arrangement of the materials

    Layout and marking of center lines for suspension system hangers

    Installation of the suspension hangers on concrete slab

    Marking and installation of the perimeter angles

    Inspection of the electromechanical services prior to closing the ceiling

    High level clearance by electromechanical trades

    ActivityID

    TotalDays

    Fixing of blocks with all anchor and tie system up to bottom of thestiffener beam level

    Preparation of reinforcement and formwork for cast in-situ stiffener/lintelbeams and stiffener columns

    Concrete pouring for lintles/stiffner beams and stiffener columns OPC60N

    Applying of the rash coat over the block wall surface 24 hours prior toapplying the plaster

    Surface preparation, tile layout and vertical alignment prior to fixing theceramic tiles

    Installation of the wall ceramic tiles by using of Nitotile-489manufactured by M/s Fosroc

    Grouting of tile joints by using of Nitotile epoxy grout manufactured byM/s Fosroc

    Waterproofing and installation of floor ceramic tiles for toilets andpantries

    Preparation of elevations and pouring of the screed concrete up to bottomof the floor tiles in slope as per mentioned drawings

    Installation of floor ceramic tiles by using of Nitotile-489 manufacturedby M/s Fosroc

    Grouting of ceramic tiles by using of Nitotile epoxy grout manufacturedby M/s Fosroc

    Inspection of the electromechanical services prior to closing the wallboard

    Installation of the electromechanical services prior to fixing thesuspension system

    Installation of the suspension system main grid T runners and cross Trunners

  • 8/4/2019 Finishes 5th Level

    6/6

    Zikreet Office Building - MJ154 Sub-Station Works

    Ganesh 6 of 6

    Activity description Start date Finish date May-10

    11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

    ActivityID

    TotalDays

    Alignment and leveling of the suspension system at required elevation

    Laying of the ceiling tiles with cut-outs where required for sprinklersystem