final report - damsafety.lk · dam safety and water resources planning project...
TRANSCRIPT
DAM SAFETY AND WATER RESOURCES PLANNING PROJECT
DSWRPP-AF/CS/QCBS/03-09
Final Report
ENVIRONMENTAL ASSESSMENT FOR REHABILITATION OF
MUTHUKANDIYA DAM
October 2016
Uni-Consultancy Services
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | ii
Table of Contents
1. INTRODUCTION ............................................................................................ i
1.1 Project Description and Justification ................................................................... 1
1.1.1 Background of the Project ................................................................................... 1
1.1.2 Project Location ................................................................................................... 2
1.2 Scope of the Project and Environmental Assessment ........................................ 3
1.2.1 Scope of the Project ............................................................................................. 3
1.2.2 Environmental Assessment Requirements .......................................................... 3
1.3 Objectives of the Study ....................................................................................... 5
1.4 Methodology ....................................................................................................... 5
2. DESCRIPTION OF THE EXISTING ENVIRONMENT ......................................... 16
2.1 Overview ............................................................................................................ 17
2.2 Physical Environment ........................................................................................ 17
2.3 Biological Environment with Flora and Fauna................................................... 28
2.3.1 Existing Habitats and ecological significance ..................................................... 28
2.4 Socioeconomic Environment ............................................................................. 36
2.4.1 Social justification of the rehabilitation of Muthukandiya dam ........................ 36
2.4.2 Existing Socio-economic Environment ............................................................... 37
2.4.3 Land Use ............................................................................................................. 39
2.4.4 Demographic Data Relevant to the Project Area ............................................. 40
2.4.5 Economic Activities of Project Related Population ........................................... 41
2.4.6 Other Water Uses .............................................................................................. 41
2.4.7 Sensitive places located in the vicinity of the irrigation scheme ....................... 42
2.4.8 Access to the project area .................................................................................. 42
2.4.9 Infrastructure available in the project area ......................................................... 42
2.5 Current Environmental Issues of the Project Area ............................................ 43
2.5.1 Physical Issues .................................................................................................... 43
2.5.2 Ecological Issues ................................................................................................. 43
2.5.3 Socioeconomic Issues ........................................................................................ 43
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | iii
3. Proposed Interventions ............................................................................. 45
3.1 Proposed Engineering Interventions ................................................................. 46
3.2 Proposed Borrowing Activities and Identified Borrow Sites ............................. 61
3.2.1 Turfing Materials ................................................................................................ 61
3.2.2 Earth ................................................................................................................... 61
3.2.3 Rubble/Boulders, aggregates and metal ........................................................... 61
3.2.4 Sand ................................................................................................................... 61
3.2.5 Gravel ................................................................................................................. 61
3.3 Proposed Interventions that could Affect Neighboring Communities ............. 62
3.4 Proposed Interventions that could affect the Natural Habitats ....................... 63
4. PROJECT INDUCED IMPACTS ...................................................................... 64
4.1 Identification of project induced impacts ......................................................... 65
4.2 Quantification of their significance ................................................................... 80
5. ENVIRONMENTAL MANAGEMENT PLAN .................................................... 82
5.1 General overview .............................................................................................. 83
5.2 Identification of impacts and their mitigations ................................................. 83
5.3 Procurement of material needed for implementing the proposed Interventions
110
5.4 Safety Issues .................................................................................................... 112
5.6 Implementation procedures of proposed mitigation ..................................... 114
5.8 Formal clearances and approval needed ........................................................ 116
6. MONITORING PLAN ................................................................................. 118
6.1 Environmental compliance and monitoring .................................................... 119
7. Cost Estimation for Environmental Management Plan .............................. 122
8. Conclusions and Recommendations ......................................................... 126
8.1 Conclusions ...................................................................................................... 127
8.2 Recommendations........................................................................................... 128
9. Annexures ............................................................................................... 131
ABREVIATIONS
AMSL - Average Mean Sea Level
BPL - Below Poverty Level
CEA - Central Environment Authority
D/S - Downstream
DBH - Diameter at Breast Height
DS Division - Divisional Secretariat Division
DSWRPP - Dam Safety & Water Resources Planning Project
EA - Environmental Assessment
EMP - Environmental Management Plan
EN - Species - Endangered Species
EPL - Environmental Protection License
FD - Forest Department
FFPO - Fauna and Flora Protection Act
GND - Grama Niladari Division
GoSL - Government of Sri Lanka
GSMB - Geological Survey and Mines Bureau
ICTAD - Institute for Construction Training and Development
ID - Irrigation Department
IEE - Initial Environmental Examination
IML - Industrial Mining License
IUCN - International Union for Conservation of Nature
KPI - Key Performance Indicators
MSL - Mean Sea Level
NEA - National Environmental Act
PM - Project Manager
PO - Project Office
PS - Pradeshiya Sabha
RB - Right Bank
TEC - Technical Evaluation Committee
ToR - Terms of Reference
U/S - Upstream
VU Species - Vulnerable Species
WB – The World Bank
Team of Consultants for EA study
Name Position
Eng. (Dr.) Mahesh Jayaweera Environmental Engineer/Civil Engineer (Team Leader)
Ms Samangi Hewage Ecologist (Flora, Fauna and Ecosystems)
Mr. K. Jinapala Sociologist/Socio-economist
Eng. (Dr.) Lalith Rajapakse Natural Resources Management Specialist
Uni-Consultancy Services Project Management
1. INTRODUCTION
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 1
1.1 Project Description and Justification
1.1.1 Background of the Project
Recent studies have revealed that major dams of the country are aging and suffering from various
structural deficiencies and short comings in operation and monitoring facilities. This situation
threatens the safety and operational efficiency of the dams and their appurtenant structures and as
a result increases the vulnerability of downstream populations and socio-economic infrastructure if
breached. The Dam Safety & Water Resources Planning Project (DSWRPP) intends to address these
issues through its dam safety and operational improvement component with financing from the
World Bank. One of the development objectives of the proposed project is to improve the
development management of water resources within the country, reduce water induced hazards to
public, and enhance the effectiveness of water related investments. The proposed project intends to
address this issue in a certain number of dams through its dam safety and operational improvement
component.
Over 350 Large/Medium Dams, Headwork and Trans-Basin canals of Sri Lanka are aging and
suffering from various structural deficiencies and shortcomings in operation and monitoring
facilities. Thirty-two dams have been identified as high risk with respect to their appurtenant
structures and operational efficiency. Those dams are required to have immediate interventions so
as to decrease the vulnerability of downstream populations and socio-economic infrastructure if
breached. This situation threatens the safety and operational efficiency of the dams and their
appurtenant structures and as a result increases the vulnerability of downstream populations and
socio-economic infrastructure if breached. The Dam Safety & Water Resources Planning Project
(DSWRPP) intends to address these issues through its dam safety and operational improvement
component with financing from the World Bank. One of the development objectives of the
proposed project is to improve the development management of water resources within the
country, reduce water induced hazards to public, and enhance the effectiveness of water related
investments. The proposed project intends to address this issue in 29 dams through its dam safety
and operational improvement component.
The Dam Safety and Water Resources Planning Project (DSWRPP), funded by the World Bank is
implemented by the Ministry of Mahaweli Development and Environment. The DSWRPP is of the
view that reservoir dams and related appurtenant structures need both regulatory and operational
safety measures and timely remedial repairs to ensure the sustainability of the social and economic
environment that has been developed. The important objective of dam owners and regulators
should be to ensure public safety and welfare and protect property, the environment, and cultural
resources.
The DSWRPP undertakes remedial works of critical dams, provision of basic safety facilities, in
addition to upgrading hydro-meteorological data collection, storage, management and
dissemination system, enhancing capacity of institutions involved in the water sector to acquire
knowledge and skills in using modern analytical tools and management practices to undertake
sustainable multi-sector planning, development and management of the water resources in the
country. In addition, project assists reviewing and exploring the development potential and
feasibility of existing water resources plans, including revised Mahaweli Water Resources
Development Plan.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 2
After successful completion, the DSWRPP received additional US $ 83 Million. This Term of
Reference sets out the problems associated with five dams which are operated by the Irrigation
Department proposes remedial works. The dams have been selected based on comprehensive risk
assessment studies carried out as part of project preparation from a list of vulnerable dams in order
to ensure their structural and functional safety. Under this TOR it is expected to carry out
Environmental Assessments for the proposed interventions under the DSWRPP Badulu Oya and
Muthukandiya dams under the DSWRPP-AF.
1.1.2 Project Location
Muthukandiya Dam is situated at the end of Monaragala District between Siyambalanduwa and
Madulla DS of Uva Province. This dam is situated around 6 km away from the Siyambalanduwa
Junction. There are around 800 farming families who rely on this scheme for irrigation of paddy
fields.
The location map of Muthukandiya Dam is given in Figure 1.1, 1.2 and 1.3.
General Specifications of Muthukandiya Dam
Name of Dam: Muthukandiya (Coordinate: M13.5, 2.15) - 06 58’31”N 81 30’32”E
River Basin: Hada Oya
Irrigable Area: 827 Ha
Capacity: 30.4 MCM
Catchment Area:25.4 sq miles
Reservoir capacity at FSL: 24,304 Acre-ft
Muthukandiya Dam top level:+320.00 m MSL
Spill way sill level at FSL:+312.0 m MSL
Bund top width: 40 m
Dead storage:1,800 Acre-ft
Spillway capacity:800 ft
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 1
Figure 1.1. Location map of the Muthukandiya Dam (Source: Survey Dept.)
Muthukandiya Dam
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 1
Figure 1.2. Location map of Muthukandiya Tank (marked as Meegaha Arawa Wewa) (Source: 1:50,000 map – Dept. of Surveys)
Muthukandiya Dam
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 2
Figure 1.3. Location Map of Muthukandiya Reservoir (Moneragala District Boundary is
shown in Red line) (Source: maps.google.lk)
Muthukandiya Reservoir
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 3
1.2 Scope of the Project and Environmental Assessment
1.2.1 Scope of the Project
The technical scope of the study is to carry out environmental assessment based on the identified
interventions and their associated issues for the Muthukandiya dam. The interventions to be carried
out during the rehabilitation work will be defined at the inception stage of the project based on the
conceptual designs done by respective engineers and the environmental assessment related to
physical, ecological and socioeconomic environment will then be carried out.
1.2.2 Environmental Assessment Requirements
The strategies on which the environmental assessment be done are based on the World Bank
Safeguard Policies and the National Environmental Regulations.
The World Bank Requirements
This environmental assessment is prepared pursuant to the World Bank’s Environmental Safeguard
Policies OP/BP 4.01 and that of Safety of Dams OP/BP 4.37.
The overall objective of the proposed environmental assessment is to carry out the following
conforming to the World Bank’s Environmental Safeguard Policies and Procedures. For each dam, an
Environmental Management Plan is prepared to address the objectives specified as given below.
The World Bank Policies and Guidelines, pertaining to environmental safeguards that require
consideration under this project, as these will most likely be triggered, are as follows:
OP/BP/GP 4.01 Environmental Assessment
OP/BP/GP 4.37 Safety of Dams
OP/BP/GP 4.11 Physical Cultural Resources
OP/BP/GP 4.04 Natural Habitats
In addition, GP 4.11 is particularly applicable which details out the procedures to be followed for
chance find of physical cultural property. OP/BP 4.37 requires that the dam upgrading be designed
and its civil works be supervised by experienced and competent professionals.
As of August 2016, The World Bank has drafted a new Environmental and Social Framework and
authorized for public disclosure. If approved by the Board, This Framework will replace the following
Operational Policy (OP) and Bank Procedures (BP): OP/BP4.00, Piloting the Use of Borrower Systems
to Address Environmental and Social safeguard Issues in Bank-Supported Projects, OP/BP4.01,
Environmental Assessment, OP/BP4.04, Natural Habitats, OP4.09, Pest Management, OP/BP4.10,
Indigenous Peoples, OP/BP4.11, Physical Cultural Resources, OP/BP4.12, Involuntary Resettlement,
OP/BP4.36, Forests, and OP/BP4.37, Safety of Dams. This Framework does not replace OP/BP4.03,
Performance Standards for Private Sector Activities, OP/BP7.50, Projects on International
Waterways, and OP/BP7.60, Projects in Disputed Territories.
Under the new World Bank Environmental and Social Framework, projects supported by the Bank
through Investment Project Financing are required to meet the following Environmental and Social
Standards (ESS):
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 4
Environmental and Social Standard 1: Assessment and Management of Environmental and
Social Risks and Impacts;
Environmental and Social Standard 2: Labor and Working Conditions;
Environmental and Social Standard 3: Resource Efficiency and Pollution Prevention and
Management;
Environmental and Social Standard 4: Community Health and Safety;
Environmental and Social Standard 5: Land Acquisition, Restrictions on Land Use and
Involuntary Resettlement;
Environmental and Social Standard 6: Biodiversity Conservation and Sustainable
Management of Living Natural Resources;
Environmental and Social Standard 7: Indigenous Peoples/Sub-Saharan African Historically
Underserved Traditional Local Communities;
Environmental and Social Standard 8: Cultural Heritage;
Environmental and Social Standard 9: Financial Intermediaries; and
Environmental and Social Standard 10: Stakeholder Engagement and Information
Disclosure.
Requirements under Environmental Regulations in Sri Lanka
The National Environmental Act (NEA) has made Environmental Assessments (EA) a legal
requirement for a range of development projects. A list of projects requiring an EA is prescribed in
Gazette (Extra Ordinary) No. 772/22 dated June 24, 1993. Accordingly, all river basin development
and irrigation projects excluding minor irrigation works requires an EIA, the guidelines are
ambiguous about the EIA requirement for upgrading and rehabilitation of existing dams. However,
agreement has been reached with the Central Environmental Authority (CEA) and Ministry of
Agriculture, Irrigation and Mahaweli Development that all dam upgrading and rehabilitation and
related activities financed under this project as well as any other activities that may lead to potential
adverse environmental impacts will be required to undertake an environmental impact assessment,
commensurate with the potential for environmental impacts and prepare detailed EMPs (including a
dam safety plan, where applicable) that will be included for implementation as part of the civil
works Contractor’s contract documents.
The Fauna & Flora Protection Ordinance Act No. 49 of 1993 & its amendments: This Act provides the
protection, conservation and preservation of the fauna and flora of Sri Lanka. Under the Fauna and
Flora Protection Ordinance (FFPO), five categories of protected areas are established viz. Strict
Nature Reserves, National Parks, Nature Reserves, Jungle Corridors and Intermediate Zones
including sanctuaries. According to this Act, any development activity of any description what so
ever proposed to be established within a national reserve or within one mile from the boundary of
any national reserve, is required to be subjected to EIA/IEE, and written approval should be
obtained from the Director General, Department of Wildlife Conservation prior to implementation
of such projects. The FFPO follows a similar process as the NEA in conducting scoping, setting the
TOR, preparation of EA, review of EA and public consultation and disclosure. The decision of project
approval or disapproval is finally granted by the Director General of the Department of Wildlife
Conservation.
Forest Ordinance No. 17 of 1907 and subsequent amendments: The Forest Ordinance of Sri Lanka is
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 5
the law for conservation, protection and management of forest and forest resources for the control
of felling and transport of timber and forest related matters. The Forest Ordinance of No. 17 of 1907
amended by several Acts up to 1995 – Act 34 of 1951, No. 49 of 1954, No. 13 of 1966, No. 56 of
1979, No. 13 of 1982, No. 84 of 1988, and the new Act No. 23 of 1995.Under Section 4 of Act No. 23
of 1995, the Minister is in charge of forests, has special powers to order and declare any specified
area of State land or the whole or any specified part of any reserve forest which has unique
ecosystems, genetic resources or a habitat or rare and endemic species of flora , fauna, micro-
organisms and of threatened species which need to be preserved in order to achieve an ecological
balance in the area by preventing landslides and fire hazards to human life, as a Conservation forest.
Under Section 5 of the Act, a Forest Officer of a specified area has special power to stop any public
or private way or watercourse in a reserved forest. It shall be lawful for the District Secretary to
determine the amount of compensation to be paid, in case that the water course injuriously affects
the interests or one or more individuals to whom on that account compensation should be paid.
1.3 Objectives of the Study
The objectives of this assignment are:
i. Identify and evaluate the potential environmental impacts that would arise as a result of the
proposed interventions
ii. Recommend appropriate mitigation measures to avoid, minimize, remedy or compensate for
the predicted negative impacts; and
iii. Provide a site-specific Environmental Management Plan that would give adequate project
options in terms of mitigation measures, project alternatives and a monitoring program to
achieve overall environmental sustainability of the project.
1.4 Methodology
Mobilization
The team of experts from Uni-Consultancy Ltd. commenced work on 22 July, 2016 with a meeting of
team members where the Team Leader briefed the team members on the methodology for
executing the consulting services. Documents required for the study were also identified and team
members requested to collect those pertaining to their areas of expertise. The team leader
thereafter prepared the Scope of Work for all team members to ensure that the quantum of work to
be carried out will be done in a uniform manner. Documents pertaining to the ecological resources
of the project area, topography, climate, and geology with soil demography were collected and
reviewed as an initial activity. The reconnaissance survey was carried out from the 30th and 31st of
July 2016. The team visited the dam site and its project areas.
The requirement outlined in the TOR and the methodology was studied in depth and responsibilities
of each team member were identified. Topographic sheet were studied to observe the current land
use and the geographical features of the area.
Subsequent to the meeting, the Team Leader consulted the DSWRPP officials and obtained the
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 6
contact details of technical personnel who are in charge of respective dams. These technical
personnel were contacted appointment were made to meet them at respective offices and
requested them to facilitate the field visits and the reconnaissance field visit. The team visited all the
dams and their project areas. The team visited on individual capacity several times to gather and
collate necessary data from time to time.
Scoping Meetings and Reconnaissance Visits
The reconnaissance survey to Muthukandiya Dam was carried out 30th and 31st of July, 2016. The
team visited the dam and its project areas, accompanied by
The main issues and the proposed interventions were identified during the reconnaissance survey
by having several meetings with key stakeholders in order to reach consensus on the issues and
mitigation measures required. Meetings were held with DSWRPP and Divisional Irrigation
Department officials, farmer / residents / in the project vicinity and fishermen engaged in inland
fishery activities. Findings gathered during these meetings helped to refine our approach to the
study and to focus on the following:
a. Proposed physical intervention – scale and nature of the intervention: Identification of physical
interventions including field inspections with the officers to assess the issues and magnitude of the
interventions.
b. Review of the work plan and Implementation schedule, including the time frame; Discussion
with relevant officers/engineers at the Irrigation Department and other relevant stakeholders at the
site to familiarize with the critical issues that are affecting the safety of the dams.
The details of the potential impacts due to proposed development interventions will be collected in
the follow up field studies to the reservoir area. The client’s confirmed list of development
interventions will be used for the impact identification with their magnitude in the next field studies
after Inception report is accepted by the client.
Data and Information Collection
A detailed literature review of available data was done by the team of consultants at the project
initiation. Relevant data to identify impacts were collected during a reconnaissance visit as and
when available, and also desk studies. The data gaps were identified and the detailed field plan was
prepared to carry out baseline surveys.
Baseline Surveys
The physical, biological and social environments will be described using the data collected by
following baseline surveys which are on-going:
Ecological surveys (covering aquatic & terrestrial flora and fauna, rare and endangered
species, wilderness):
The methodology used for the study was line transect method. Line was laid through identified
habitats/vegetation in the study site as well as burrow pits and quarry sites. Recently published and
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 7
unpublished materials/data also used to gather information. Further, relevant secondary
information were gathered from people living in nearby communities and relevant officials in order
to prepare species inventories.
A floristic survey of higher plants was carried out. During the survey, flora species found along
transect was recorded. In order to determine the floristic diversity of the area, direct recording
method was used. Observed plant species were identified using descriptions and keys published in
“Hand book to the Flora of Ceylon” volumes. The national conservation status of the species was
recorded according to the 2012 Red List of Threatened Fauna and Flora of Sri Lanka (ME&NR, 2012).
Nomenclature of flowering plant was based on Senaratna (2001).
Sampling of fauna was done in parallel to the floral transects. Visual Encounter Survey (VES) method
was used to record faunal species. Both direct and indirect observations (Calls, foot prints, pellets,
and tracks) were made. Faunal survey was carried out within the project site and 500 m away from
the project boundary. Secondary information on biodiversity and environmental issues were also
collected by personal communication with relevant officers and villagers. Reviewing of published
documents was also carried out. In addition photographic records were used to identify the visual
aspects of habitats of proposed project area.
The observed animal species were identified by using the most recent published descriptions and
taxonomic keys provided by D’Abrera (1998), Jayasinghe et al. (2013), Bedjanic et al. (2007),
Bedjanic et al. (2014), Harrison (2011), Warakagoda et al. (2012), Phillips (1935), Kotagama &
Goonatilake (2013), Yapa & Ratnavira (2013), Goonatilake (2007), De Silva et al. (2015), Fernando
(1990), Naggs & Raheem (2000), Manamendra-Arachchi and Pethiyagoda (2006), De Silva (2009),
Das and De Silva (2011), Somaweera (2007), Somaweera and Someweera (2009). The national
conservation status of the species was recorded according to the national red list 2012 of Sri Lanka
(MOE 2012).
Social Surveys and social impact studies
The reconnaissance field visit of the sociologist with the other disciplinary team members provided
opportunity to understand the rationale of the proposed development interventions under the
project. The officials of Irrigation Department (IE office in Monaragala) were consulted to obtain
data and their concerns related to the proposed development interventions.
The in-depth interviews held with Irrigation Officers were useful to understand the purpose of the
interventions, the types livelihoods of the people, socio-economic related issues that may arise
during construction period of the project. The sociologist will collect field data from Muthukandiya
irrigation scheme as follow up activity of the reconnaissance visit. The data will be collected to
identify the potential impacts on following aspects:
Livelihoods of the farming community
Other indirect livelihoods drinking water, Fisheries , domestic use
Disturbances to other routine activities of the communities in the project area
Following methods will be applied to collect data to measure the likelihood impacts on the
socio-economic environment due to the proposed project interventions.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 8
In-depth interviews with stakeholders relevant, leaders of Farmer Organizations, other
community leaders in the residential areas of the irrigation scheme , IE and TAs of ID, GN/s,
Samurdhi Niyamaka, Drinking water users of the wells, Leaders of fisheries Associations.
Focus Group discussions - With general farmers and fishermen and other community
members
Walk through survey in the project area and preparation of a community Map including the
salient features relevant to social environment.
Social surveys and related studies will be carried out covering all the stakeholders, especially the
farmer and fishing communities in addition to other water users (e.g., villagers who use the water
for day-to-day activities, and/or other purposes). Grama Niladharis, Economic Development
Officers, Samurdhi Niyamakas, officials of the farmer organizations, and any other governmental
officers who are directly or indirectly involved with the functioning of the dam and its water
resources (such as the Divisional Secretariat, Divisional Irrigation Engineer). The data on number of
different water users such as farmers, fishermen, families depending on tank water for domestic
purposes (drinking, bathing and washing etc.) will be collected. Data and information gathered from
such social surveys will be based to identify and assess social impacts. Mitigation measures will also
be proposed with clear justifications based on the expectations of the stakeholders.
Identification and assessment of impacts, nature and magnitude
The EA will identify environmental issues that may arise as a result of project activities especially
considering impacts that can arise affecting natural habitats, natural resources and also on the social
environment (especially, water users in the tank). Impacts can be classified into several categories
depending on the nature of impacts.
(a) Interventions that will cause moderate to significant impacts (if not mitigated)
(b) Interventions that will cause impacts that are direct, while some other may have indirect impacts.
(c) Interventions that will cause impacts in the longer term rather than immediately following the intervention:
(d) Activities of certain interventions will yield only minor impacts that are short term and easily mitigated;
All the interventions and their implementation (Table 3.1) will be closely studied and will be
compared with environmental elements in order to find out the impact caused by every activity on
the every environmental element. Physical, biological and social including socio-economic
parameters will be considered for environmental elements. . Some of the socio-economic
parameters that will be used for monitoring the impacts are included below (Table 1.1) and there
can be changes on these depending on the findings of the detail field studies.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 9
Table 1.1. Data that need to be collected during the detailed study
Criteria Indicators Data need
Livelihoods of the
farming community
No of farmers/ families to be affected
The land area affected
(encroached land in the downstream
and upstream of the reservoir)
Details of cultivators under
the tank, yield and income,
details on encroachments of
the reservations.
Other indirect
livelihoods
No of drinking water users affected
No of fishing families affected
No of families used tank water for
bathing and washing
Data on the other water uses
in the tank
Disturbances to
other routine
activities of the
communities in the
project area
No of families in villages used the tank
bund top as access
Data on users of the tank
bund top as access road
Institutional Arrangements
The Acts, regulations, licenses, permits and other approvals that may be necessary for the
implementation of the proposed interventions were identified. These may include;
(a) Irrigation Ordinance No. 32 of 1946 Irrigation (Amendment) No. 1 of 1951 Irrigation
(Amendment) No. 48 of 1968 Irrigation (Amendment) No. 37 of 1973 Agrarian
Development Act, No. 40 of 2002
(b) The National Environmental Act (NEA) No. 47 enacted in 1980 and NEA Amendment Act
No. 56 of 1988
(c) National Environmental Protection and Quality Regulations under extraordinary gazette
notification No. 1534/18 and No. 1533/16 of 2008 under NEA section 32 & 23A, 23B
(d) Fauna and Flora Protection Act (FFPO) No.2 of 1937 amended in 1993 and 2009
(e) Felling of Trees Control Act No. 9 of 1951 as amended through Act No. 30 of 1953
(f) Water Resources Board Act, No. 29 of 1964 and (Amendment) Act, No. 42 of 1999
(g) Soil Conservation Act, No. 25 of 1951 and Amended No. 24 of 1996
(h) Agrarian Development Act No. 46 of 2000 (Section 32)
(i) Antiquities Ordinance No. 9 of 1940 and amendments
(j) Mines And Minerals Act (No. 33 of 1992)
(k) The World Bank Recommendations pertaining to Dam Safety & Social and Environment
Assessment (OP/BP4.37), Safety of Dams; and Proposed ESS4 – Annex 1. Safety of Dams
(Section B: Existing Dams)
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 10
It is also imperative that the proper institutional arrangement be made available for smooth
operations of the EMP. It is the Project Office that is in charge of the entire project and the client,
Irrigation Department would be solely responsible in getting the project implemented with a
selected contractor.
The contractor will be selected through a bidding process and the contractor is responsible in
implementing the EMP delineated herein this report. During the project implementation period, the
World Bank and the Project Office will evaluate the implementation of the EMP. Once the EMP is
implemented as per the World Bank Safeguard Policy Documents, review of implementation of EMP
would be done in order to ensure that all negative impacts are addressed successfully.
Environmental Impact Analysis, Proposed Mitigatory Strategies and preparation
of the Environmental Management Plan (EMP)
The objective of preparing the EMP is:
(i) To propose appropriate mitigation measures to reduce or minimize any adverse impacts
that have been identified, taking into account any associated constraints or consequential
environmental or social implications of such measures;
(ii) To identify, predict and evaluate the acceptability of the residual impact of the project
after the implementation of selected mitigation measures and to estimate and evaluate
any cumulative environmental impacts to which the project may contribute;
(iii) To identify, develop and specify methods, measures and standards to be included in the
operational phases of the project to reduce environmental impacts to acceptable levels;
Appropriate mitigation will be proposed to ensure the identification of potential environmental
issues and social concerns early in the implementation of a proposed project to incorporate
necessary safeguards in project design in order to prevent potential adverse impacts by determining
appropriate mitigation.
A site-specific EMP that will provide mitigation strategies, project alternatives and a plan for
monitoring programme will be prepared. Proper management of the catchment and the watershed
is essential for ensuring continued economic benefits envisioned from the dam are met. These will
also be considered in the EMP.
Preparation of the Environmental Monitoring Plan (EoMP)
The Project Proponent needs to implement a comprehensive environmental monitoring programme
soon after implementation of proposed interventions. This is very crucial in order to assess the
performance or success of the implemented mitigatory measures. There are 3 basic environmental
monitoring tasks to assess the success of mitigation and identifying residual impacts. They are;
Pre-construction monitoring to determine the baseline conditions in detail to identify impacts and
mitigation measures and costs
Construction compliance monitoring, and
Post construction monitoring of maintenance and operational project activities.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 11
It should be noted that during the construction phase both the contractor and the Project Proponent
should accept a major responsibility in undertaking the monitoring aspects with assistance from
competent authorities. With reference to undertaking environmental management issues, monitoring
aspects and implementation of mitigatory measures to prevent environmental impacts an
Environmental Monitoring Unit (EMU) should be established. This study will identify the composition of
this unit, its role and responsibilities etc.
In addition, for each significant impact, the environmental monitoring plan (EoMP) will propose:
- Mitigation measure
- Indicators/parameters to be monitored
- Frequency of monitoring – Time bounded monitoring
- Responsible entity for monitoring – institutional arrangements
- Responsible entity for supervising – institutional arrangements
Preparation of the cost estimate for implementation of the EMP and EMoP
Cost estimates for implementing the EMP and the EoMP will be prepared.
Recommendations and Conclusions
Findings and suggestions of the EA Report will assist the Project Proponent in formulating an
environmentally friendly and a socially acceptable project and to achieve the broader objectives of
the proposed project.
Documentation Procedure
Draft final reports EMP for each Dam will be submitted summarizing the findings of the study and
will be finalized after incorporating the comments.
1. Inception Reports for each Dam
Including the Physical Interventions finally proposed to be carried out at the site (project activities),
Construction Methodology, Equipment to be used, Pre construction activities, etc., outline of the
Potential Environmental Impact on Physical and Social Environmental and outline of the proposed
Mitigation Measures. The inception report will also highlight the areas where impacts may be
possible due to proposed Dam safety project in Muthukandiya Dam. The areas of impact will be
studied in detail in the follow-up field studies after Inception report is accepted by the client.
2. Draft Final Reports for each Dam
The Final Report will include the following:
A comprehensive Environmental Management Plan (EMP) to manage the onsite as well as offsite
environmental impact comprising the following.
(i) Mitigation strategies for each impact identified
(ii) Appropriate institutional arrangement to implement the proposed measures
(iii) Implementing schedule
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 12
(iv) Reporting procedures
(v) Cost estimates for implementing mitigation measures
- Environmental monitoring plan that will specify monitoring indicators to measure
the performance of the each mitigatory measure, monitoring mechanism and
frequency.
- Clearance approvals needed by the project prior to its implementation
- Recommendations on the adequacy of the assessment
- Final Conclusions and recommendations regarding environmental viability, of the
project based on the findings
- Annexures and Appendices
3. Submission of Final Reports
The Final Report will be submitted within two weeks after receiving comments from the client once
the TEC evaluates and reviews the Draft Final Report. The final report will be reviewed by the World
Bank as well.
The main activities to be followed to complete above deliverables are summarized in Work Plan
given below (Table 1.2).
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 13
Figure 1.4: Proposed Approach and Methodology for the Study
1.5 Work Plan
The steps described above can be summarized as a work plan as follows (Table 1.2)
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 14
Table 1.2. Work Schedule
Activity
DURATION
Month July. ‘16 August 2016 September 2016 Oct. ‘16
Week 1 2 1 2 3 4 1 2 3 4 1 2
1 Primary Data Collection
2 Reconnaissance Survey
3 Meetings to discuss about intervention/designs
4 Develop the detailed methodology
5 Scoping of environmental impacts
6 Submission of the Inception Report
7 Detailed field visits (Chapter 2 & 3)
8 Assessment of Anticipated Environmental Impacts (Chapter 4)
9 Formulation of the Environmental Management Plan (Chapter 5)
10 Identification of needs/approvals to implement EMP (Chapter 5)
11 Drafting of Environmental Monitoring Plan (Chapter 6)
12 Cost Estimates (Chapter 7)
13 Compilation of Conclusions and Recommendations (Chapter 8)
14 Compilation & Submission of the Draft Final Report
15 Compilation & Submission of the Final Report
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 15
Table 1.3 provides the details of the tasks assigned for each team member including the team
leader. All the key experts in the Consultancy Team have the qualifications and the experiences as
stipulated in the TOR.
Table 1.3. Tasks assigned to each team member and the responsibility
Main Discipline/Task Key Expert Responsible
Coordination of the entire assignment Team Leader and Support staff
Preparation of overall methodology Team Leader
Detailing the interventions and Scoping of environmental
issues to identify impacts
Activities related to environmental (physical) aspects
Environmental Engineer/ Natural
Resources Management
Specialist/Chartered Civil Engineer
Meeting with stakeholders, including officials from DSWRPP
and Irrigation Department
The entire team led by the Team
Leader
Description of the baseline:
- Physical environmental aspects
- Ecological/Biological impacts including migratory
mechanisms
- Sociological aspects
Environmental Engineer
Ecologist and Zoologist/ Faunal
Specialist
Sociologist
Drafting EMP and EoMP:
- Physical environmental aspects
- Ecological/Biological impacts
- Sociological/Economic aspects
Environmental Engineer
Ecologist and Zoologist/Faunal
Specialist
Sociologist
(input from Natural Resources
Management Specialist as needed)
Calculation of costs; Drafting Conclusions and
Recommendations
Team Leader with inputs from other
key experts
Drafting of the reports Team Leader with contribution from
other team members
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 16
2. DESCRIPTION OF THE EXISTING ENVIRONMENT
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 17
2.1 Overview
It is imperative that the existing environment in the project area and the borrow areas are
identified in terms of different environmental elements. In order to perceive the likely
alterations of the existing environment due to the proposed interventions present status of the
existing environment needs to be recorded and then the impacts on such elements need to be
discussed.
In general, the entire existing environment is described in three main components, namely,
physical, ecological and socioeconomic environments respectively. Data were collected
focusing on these three components and are presented below.
2.2 Physical Environment
The project area lies close to the Gal Oya basin which is separated by a valley by an east-west
ridge. There are isolated hillocks which are predominantly Precambrian in origin, in common
with the underlying formations throughout the project area. The geology of the basin area falls
under the Highland Complex and Eastern Vijayan Complex (Madduma Bandara, 2000).
a. Climate
The Muthukandiya Reservoir which is located near the Gal Oya basin, which falls within the dry
zone of Sri Lanka, where notable dry season occurs with an annual rainfall under 1,900 mm.
The dry climatic conditions are said to be prevailing most of the time where cooler climate is
expected only in the northeast monsoon period.
Monaragala's climate is classified as tropical. The summers are much rainier than the winters in
Monaragala. According to Köppen and Geiger, this climate is classified as Aw. In Monaragala,
the average annual temperature is 26.3 °C. About 1603 mm of precipitation falls annually.
b. Temperature
At an average temperature of 28.7 °C, May is the hottest month of the year. In January, the
average temperature is 24.6 °C. It is the lowest average temperature of the whole year.
Relatively minor temperature fluctuations are normally experienced compared with wider
fluctuations in precipitation and streamflow. The variation in annual temperature is around 2.8
°C.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 18
Figure 2.1: Monthly average, high and low temperature in Monaragala near Muthukandiya tank area
(Source: http://en.climate-data.org/location/511297/)
Table 2.1: Monthly average, high and low temperature and rainfall in Monaragala near Muthukandiya tank area
(Source: http://en.climate-data.org/location/511297/)
Between the driest and wettest months, the difference in precipitation is 279 mm. The
variation in temperatures throughout the year is 2.8 °C. Useful hints about reading the climate
table: For every month, you will find data about precipitation (mm), average, maximum and
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 19
minimum temperature (degrees Celcius and Fahrenheit). Meaning of the first line: (1) January,
(2) February, (3) March, (4) April, (5) May, (6) June, (7) July, (8) August, (9) September, (10)
October, (11) November, (12) December.
c. Rainfall
Precipitation is the lowest in June, with an average of 10 mm. The greatest amount of precipitation occurs in November, with an average of 289 mm.
The Gal Oya basin experiences a tropical climate, falling under the influence of the northeast
[December to February] and southwest [May to September] monsoons. The northeast
monsoon (Maha) brings most of the annual rainfall, and therefore runoff, in the catchment
area. The southwest monsoon (Yala) is typically dry due to the orographic effect of the Central
Highlands of Sri Lanka. Rainfall in the inter-monsoon periods can be caused by either
convective or cyclonic storms. Relatively minor temperature fluctuations are normally
experienced compared with wider fluctuations in precipitation and streamflow. The latter
fluctuations have important implications for the development of rain fed and irrigated
agriculture.
It is envisaged from the Figure 2.2 that the substantial rainfall in the project area occurs in the
first and second inter-monsoon periods falling in between March to April and October to
November, respectively. The highest average monthly rainfall recorded during last 5 years
ranged between 280 - 350 mm. Precipitation is the lowest in June, with an average of 8 mm.
Most precipitation falls in December, with an average of 356 mm. Annual average rainfall is
around 1,850 mm. Between the driest and wettest months, the difference in precipitation is
around 350 mm.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 20
Figure 2.2: Monthly average rainfall in Monaragala near Muthukandiya tank area
(Source: http://en.climate-data.org/location/511297/)
d. Wind
Wind data has not been recorded continuously in the vicinity. The Monaragala Meteorological Station gauges only rainfall at the moment and has no data collected for Wind.
From wind charts is can be deduced that the average wind patterns on a typical day would be between 4 – 15 km/h. However, this can rise to about 30 – 35 km/h during the north east monsoon periods. Occasional high winds can be expected any time during September – November and during mild troughs or cyclonic circulations.
e. Topography
The general topography of Sri Lanka comprises of three distinctive peneplains or erosion plains
made up of a central highland mass rising above 2,500 meters in altitude and a low gently
undulating plain surrounding it and extending to the sea. The lowest peneplain extends from
the coastline to approximately 20-30 kilometres inland in a steep step of about 300 meters
above mean sea (MSL). Gal Oya basin is located in the Moneragala and Ampara Districts, Uva
and Eastern Provinces, lies within this lowermost peneplain. The landscape in the vicinity of the
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 21
site is characterized by flatlands with occasional attitude changes. The area adjacent to the
Muthukandiya is relatively flat terrain and the land has already been cleared and prepared for
the cultivation, secondary development with people in-migrating to these areas recently (See
Figure 2.3 for land use map). There are stepped lands of 2~3 meters in height and exposure of
reddish soil in some parts of the area. It is evident from the location and contour maps that
Muthukandiya is aligned in the northeastern direction, in parallel to the pre-existed (natural)
flow direction of Gal Oya.
According to the present topographical variation, the downstream of the tank is characterized
by undulating slopes with 1.5% – 2.5% surface gradient in north-east direction. There are
isolated hillocks which have altitudes up to of 100 - 700 m MSL. According to the pre-existed
topography, the elevation in the area is approximately 100 -120 m MSL with a gently sloping
landscape in the north-west direction and also towards the southeastern direction.
Figure 2.3: Topography of the Area (Note: Muthukandiya is located within the 100 - 700 m contour line) (Source: Withanage et al., 2014)
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 22
f. Soil and Geology
The geology of the area is characterized by Precambrian rocks. They have given rise to a
mature, mantled and undulating peneplain which mere imperceptibly to the north and
northeast into the pleistocene and Miocene sediments of the coastal plain. Large, prominent
and isolated erosion remnants and prominent rides rise to heights of over 400 m above the
general level of the surrounding plain. The elevation of the latter varies from about 900 m
above sea level in the west to under 500 m in the south. The mantle covering the peneplain
rock is generally thin and sometimes nonexistent, as in areas of rock knob plain and
outcropping flat rock.
Two very different soils have developed on the Precambrian rocks. On those rice in
ferromagnesian minerals, moderately deep to shallow (100 cm), reddish to brown, sandy clay
loam soils have developed, on slopes which often exceed 2 percent and sometimes 4 percent.
These soils normally occur in association with prominent rock outcrops. On the rocks relatively
poor in ferromagnesian minerals but rich in quartz, moderately deep to shallow, grey brown,
loamy sand and sandy loam soils occur. These overlie impermeable rocks and usually occur on
slopes not exceeding 4 percent. The soils of the upper slopes tend to be ‘moderately well’ to
‘well drained’ while those of the lower slopes tend to be ‘imperfectly drained’.
Associated with these soils are ‘imperfectly’ to ‘poorly drained’ bottomland and old alluvial
soils of variable but usually sandy texture. These old alluvial soils are not necessarily associated
with the present – day drainage. A relatively wide band of ‘imperfectly’ to very poorly drained’
recent alluvium [with the exception of a low, narrow, moderately freely draining levee soil
occurs along the Gal Oya and Maduru Oya Basins.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 23
Figure 2.4: Distribution of Soil Groups (Source: Dept. of Town & Country Planning, University of Moratuwa, 2007)
The soil that is found in the Muthukandiya Reservoir command area is predominantly Reddish
Brown Earth and Low Humic Glay Soils. In addition, Reddish Brown Earth and Immature Brown
Loam Soils are also present at several locations (Figure 2.5(b)).
Muthukandiya Reservoir
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 24
Figures 2.5. (a) Agro-ecological zones, and (b) Soil Groups of the Monaragala District (Source: CEA, 1992).
Muthukandiya Reservoir
Muthukandiya Reservoir
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 25
g. Hydrology
The Muthukandiya sub-catchment and the stream network contributing to the flows are
located within the Agro-ecological Region IL2, in the Hydrological Region 2 (Figure 2.5(a).
Muthukandiya Tank is located in the Eastern part of the main catchment Gal Oya Basin
(Figures 2.6). The main basin consists of a catchment of 1,873 km2, and characterized by a
large reservoir located along the main channel.
Heda Oya originates from the Moneragala district and flows to the sea at the eastern coast
near Panama. It has 604.0 sq.kms of drainage area and the Oya is mostly untapped. The
Muthukandiya reservoir is the only existing reservoir in the Heda Oya basin and it is located
in the Monaragala district, but not across the main Heda Oya.
The main hydrologic data required for the hydrological and hydraulic assessments apart
from the topographic information are;
Rainfall Intensity-Duration-Frequency Curves (IDF Curves) for catchment areas
Information on runoff coefficients and time of concentration
The site is situated in the belt of monsoon climates and governed by its tropical location as
well by the monsoonal regime, thus rainfall exhibits a strong seasonal variation. More than
50% of the total rainfall is received during the Second Inter Monsoon and North-Eastern
Monsoon (October to December).
Except for the low-lying downstream catchment sections (30 - 60 m AMSL) in the most
downstream of the Gal Oya Basin, the majority of area is covered with a narrow ridge of
mountain protruding above 100 m rising out of flat terrain leading to invert/reverse flow
conditions at several sections north-west. However, the Heda Oya sub-catchment is located
in the further d/s (80-100 m AMSL) and away from the downstream regional floodplain.
Therefore, the sub-catchment area is presumably not subjected to any flooding under
seasonal monsoonal storm event, except for extreme events where backwater flows from
downstream accumulation due to flow constrictions may cause localized temporary
inundation in some areas. Historical flood data are not available in the area.
A dendritic drainage pattern of stream flow can be identified in the Gal Oya basin (Figure
2.6) and it is probably the most common drainage pattern identified in Sri Lankan river
basins as well as in the world. This is characterized by irregular branching of tributary
streams in many directions and at almost any angle usually less than 900. According to
Cooray (1984) the basin belongs to the Vijayan Complex and it also has meta-sedimentary
and meta-igneous rocks. Therefore, Dendritic patterns develop on rocks of uniform
resistance and indicate a complete lack of structural control.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 26
Figure 2.6: Rivers and streams within the Monaragala District. Muthukandiya is located in the Heda Oya River Basin (Source: Dept. of Town & Country Planning, University of Moratuwa, 2007).
h. Floods and Droughts
No flood damages have been recorded in the recent past, at least for last 30 years.
However, drought conditions are a common phenomenon in the Muthukandiya Reservoir
area. The area falls in the High Drought Hazard region according to the Drought Hazard Map
of Sri Lanka prepared by the Disaster Management Center (2014) – See Figure 2.7.
Muthukandiya Dam
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 27
Figure 2.7. Drought Hazard Map of Sri Lanka (Source: DMC and UNDP,2014)
i. Noise and Vibration
Background noise levels in the area were found to be very low varying in the range of 45 –
50 dB (A) during the site visit, indicating that no any artificial noise levels is generated in the
project area. The existing noise levels are attributed by the noise generated from the
rattling of leaves of trees by the wind and the occasional screech of birds passing and
roosting in the area. Occasional high noise is observed due to vehicles, motor bicycles and
three wheelers.
No significant vibration levels were perceived during the field visit indicating that vibration
induced activities were almost absent.
j. Air Quality
Occasional wind blows were observed during the site visit, which have been a common site
in the bund area. Such sporadic wind blowing has brought about airborne suspended
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 28
particles, but, this scenario was not significant enough to be reckoned as an issue. The
canopy trees that have rooted down in the vicinity of the bund have sheltered the bund
area from escaping the airborne particles hence, no air quality issues were found.
Occasional vehicular movements were recorded along the bund, which sometimes causes
the airborne particles to be locally present. However, during the windy periods, one has to
be aware of airborne particles causing inconvenience to the pedestrians.
k. Water Quality
Water quality of Muthukandiya Reservoir seems to be relatively good with compared to
similar sized tanks. The water quality has not been degraded much as relatively less
anthropogenic activities are found to be operating in the surrounding of the tank. This is
evident from the color of water and clarity of the water column. In addition, there are no
floating macrophytes such as water hyacinth, which indicates that the nutrient levels in
water are relatively low. Chlorophyll concentrations are low to moderate, which shows
slight eutrophic conditions. It has been observed that the average pH is around 8.0, which
shows slight alkalinity in water, probably due to the geological formations. Apart from low
algal growth, slight turbidity issues were seen during the site visit, particularly in the area of
rip rap as the soil underneath was stirred up due to wind induced currents striking the rip
rap. This issue was very much localized and was not considered to be an adverse issue for
aquatic ecosystems.
2.3 Biological Environment with Flora and Fauna
2.3.1 Existing Habitats and ecological significance
As per the Figure 2.4 and 2.5(a), the area where Muthukandiya Reservoir is located is
classified as IL2- low country dry zone agro-ecologically, and this area has topography of
undulating terrain (Figure 2.3) and Reddish Brown Earth and Low Humic Glay as typical soil
types (Figure 2.4 and 2.5(a). Muthukandiya tank is located within the dry zone of the island
in Monaragala district. Natural vegetation types in this area belong to the ‘Dry and Arid
Lowlands’ floristic region. The typical natural climax vegetation types expected to be found
in this zone are tropical dry-mixed evergreen forests (Manilkara and mixed community)
tropical thorn forest, damana and villu grasslands, flood plain wetlands and riverine and
gallery forests. However, these habitats are not found in the area where the project
interventions are planned. The land use includes paddy lands, rain-fed upland crops, mixed
home gardens, scrublands, and natural forests. This tank is located close to Gal Oya
National park which is the nearest protected areas.
Problems identified during the site visit were, damages on the spillway basin in certain
areas, pot holes on the tank bund and damages of the existing riprap. Reconstruction of
the spillway basin may not affect the natural environment of the area as this part of the lake
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 29
is a manmade structure. However, extra care should be taken while disposing the
construction debris. It is recommended to use dumping sites approved by the Pradeshiya
Sabha to dispose construction debris.
Improvements of the spill access road required gravelling and slope correction. This activity
may not affect the natural environment in this area. Filling of potholes and gravelling of
tank bund road also not affect the natural environment in the project site. However, this
activity may require large amount of gravel. Required amount of gravel is purchased from a
licensed gravel mining site. Riprap of the dam needs to repair as there is no riprap currently.
This activity requires a large number of rubble. Rubble is purchased from a licensed quarry
site. There are 9 trees situated along the riprap and the bund that need to remove during
rubble laying. Further there are few ant-holes located along the bund that need to remove
before the repair. Replacement of the sluice gate may adversely affect the stability of the
aquatic environment. This tank is a home for number of fish species and several families
depend on the daily fish catch of the tank. Therefore, extra care should be taken during this
activity
Ecologically sensitive habitats such as natural undisturbed forests or wetlands are not found
where the proposed interventions will be implemented. Both aquatic and terrestrial
habitats are found in the project area. The aquatic habitats are the tank and water
stagnated habitats below the dam. Two main terrestrial habitats based on the floristic
composition are cultivated lands, and tank bund/ reservation. The tank reservations are
properly maintained without any encroachments. Seepage areas of the downstream include
several stagnated water pools with extensively growth green algae. Shallow areas of the
tank have been colonized by aquatic weeds, but the densities are low. Large extents of
paddy fields are located downstream area away from the tank.
Flora
Invasive species
An invasive plant was observed from the tank and surrounding habitats which includes the terrestrial species Lantana (Lantana camara).
Lantana camara has been currently spreading in the tank bund, tank reservation and surrounding habitats. Since periodic removal of weeds from tank bund, distribution of Lantana camara is controlled to some extent. A few bushes of Lantana can be seen in fences around the cultivations and uncultivated lands. In addition, invasive aquatic species such as Japan Jabara (Eichhornia crassipes) can be seen as small patches in shallow areas of the tank.
Shallow reservoir side near the spillway support a low growth of water hyacinth (Eichhornia
crassipes) which supports some water birds such as Indian Pond Heron (Ardeola grayii) and
Little Egret (Egretta garzetta).
List of flora recorded in Muthukandiya Reservoir project area is given in Table 2.2.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 30
Table 2.2. List of flora observed within the project site.
HA - Habitat; S - Shrub; H - Herb; T - Tree; C - Creeper
TS - Taxonomic status: N - Native; I - Introduced; E – Endemic; CS - Conservation Status
Family Scientific Name Common name HA TS CS
Amaranthaceae Achyranthes asper Gas Karal Heba H N
Anacardiaceae Mangifera indica Amba T I
Apocynaceae Ichnocarpus frutescens Garandi Wel C N
Apocynaceae Rauvolfia canescens Wal Ekaweriya H I
Apocynaceae Calotropis gigantea Wara S N
Asteraceae Eupatorium odoratum Podisinno Maran S I
Asteraceae Tridax procumbens Tridax S I
Asteraceae Vernonia cineria Monara Kudumbiya H N
Asteraceae Vernonia zeylanica Pupula C E
Capparaceae Capparis zeylanica Wellangiriya S N
Fabaceae Alysicarpus vaginalis Aswenna H N
Fabaceae Gliricidia sepium Gliricidia T I
Fabaceae Mimosa pudica Nidikumba H I
Fabaceae Tamarindus indica Siyambala T I
Lamiaceae Anisomeles indica Kon T N
Malvaceae Abutilon indicum Anoda S N
Malvaceae Hibiscus micranthus Bebila H N
Malvaceae Hibiscus vitifolius Maha Epala S N
Malvaceae Urenia lobata Patta Epala S N
Meliaceae Azadirachta indica Kohomba T N
Poaceae Panicum repens Etora H N
Polygonaceae Polygonum tomentosum Sudu Kimbuwenna H N
Rhamnaceae Ziziphus mauritiana Masan T N
Rhamnaceae Ziziphus oenopila Heen Eraminiya S N
Verbenaceae Lantana camara Gandapana S I
Verbenaceae Stachytarpheta jamaicensis Balu Nakuta H I
Several trees that situated along the tank bund needs to remove in order to facilitate construction activities. Therefore, it is proposed to replant the area with native plant species. A list of plant species that can be used for replanting is given below (Table 5.2).
The list of trees that need to be removed is given in Table 2.3.
Table 2.3. List of tree species that need to be removed during rehabilitation of the rip-rap
Family Scientific Name Common name DBH, cm Number of trees
Fabaceae Albizia sp Wal maara <10 6
Fabaceae Leucaena leucocephala Ipil Ipil <10 1
Lamiaceae Anisomeles indica Kon < 10 2
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 31
Fauna
The project area which belongs to Gal Oya catchment. Together with the National Park
there have been 32 terrestrial mammals have been recorded. The Sri Lankan elephant, Sri
Lankan axis deer, water buffalo, Sri Lankan sambar deer, Sri Lanka leopard, toque monkey
and wild boar are among them. Included amongst the reptile species of the park are the
mugger crocodile and star tortoise. More than 150 species of birds have been recorded in
Gal Oya. The lesser adjutant, spot-billed pelican and red-faced malkoha are some of the
park's resident birds. The Indian cormorant, Oriental darter, grey heron, and lesser whistling
duck are among the common water birds of the Senanayake reservoir. The white-bellied
sea eagle, and grey-headed fish eagle are the notable raptors of the area. Gal Oya National
Park's butterfly species include the endemic lesser albatross.
The research trials have introduced fingerling of rohu (Labeo rohita) and common carp
(Cyprinus carpio) in cages in Muthukandiya reservoir.
List of fauna recorded in Muthukandiya Reservoir project area is given in Table 2.4.
Table 2.4. List of fauna species observed within the project site.
TS - axanomic status: N - Native; BrR - Breeding Resident; I - Introduced
CS - Conservation Status: EN - Endangered; NT - Near Threatned
Family Scientific Name Common name TS CS
Birds
Accipitridae Ichthyophaga ichthyaetus Grey-headed Fish-eagle BrR
Aegithinidae Aegithina tiphia Common Iora BrR
Alcedinidae Halcyon smymensis White-throated Kingfisher
BrR
Anhingidae Anhinga melanogaster Darter BrR
Apodidae Cypsiurus balasiensis Asian Palm Swift BrR
Ardeidae Ardeola grayii Pond Heron BrR
Ardeidae Bubulcus ibis Cattle Egret BrR
Ardeidae Casmerodius albus Great Egret BrR
Ardeidae Egretta garzetta Little Egret BrR
Ardeidae Mesophoyx intermedia Intermediate Egret BrR
Charadriidae Himantopus himantopus Black-winged Stilit BrR
Charadriidae Vanellus indicus Red-wattled Lapwing BrR
Cisticolidae Cisticola juncidis Zitting Cisticola BrR
Cisticolidae Prinia sylvatica Jungle Prinia BrR
Cisticolidae Prinia socialis Ashy Prinia BrR
Cisticolidae Prinia inornata Plain Prinia BrR
Columbidae Ducula aenea Green Imperial Pigeon BrR
Columbidae Streptopelia chinensis Spotted Dove BrR
Columbidae Treron pompadora Pompadour Green- BrR
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 32
Family Scientific Name Common name TS CS
pigeon
Coraciidae Coracias benghalensis Indian Roller BrR
Crovidae Corvus macrorhynchos Large-billed Crow BrR
Crovidae Terpsiphone paradise
Asian Paradise-flycatcher
BrR
Cuculidae Dendrocygna javanica Lesser Whistling Duck BrR
Megalaimidae Megalaima rubricapilla Crimson-fronted Barbet BrR
Megalaimidae Megalaima zeylanica Brown-headed Barbet BrR
Meropidae Merops orientalis Green Bee-eater BrR
Muscicapidae Saxicoloides fulicata Indian Robin BrR
Nectariniidae Dicaeum erythrorhynchos Pale-billed Flower Pecker
BrR
Nectariniidae Nectarina zeylonica Purple-rumped Sunbird BrR
Nectariniidae Nectarina asiatica Purple Sunbird BrR
Passeridae Lonchura striata White-rumped Munia BrR
Passeridae Lonchura punctulata Scaly-breasted Munia BrR
Passeridae Lonchura Malacca Black-headed Munia BrR
Passeridae Passer domesticus House Sparrow BrR
Phalacrocoracidae Phalacrocorax fuscicollis Indian Cormorant BrR
Phalacrocoracidae Phalacrocorax niger Little Cormorant BrR
Phasianidae Pavo cristatus Indian Peafowl BrR
Pycnonotidae Pycnonotus cafer Red-vented Bulbul BrR
Pycnonotidae Pycnonotus luteolus White-browed Bulbul BrR
Sturnidae Acridotheres tristis Common Myna BrR
Sylviidae Orthoromus sutorius Common Tailorbird BrR
Sylviidae Turdoides affinis Yellow-billed Babbler BrR
Butterflies
Acraeidae Acraea viole Twany Coaster N
Danidae Danaus chrysippus Plain Tiger N
Danidae Danaus genutia Common Tiger N
Lycaenidae Caleta decidia Angled Pierrot N
Pieridae Belenois aurota Pioneer N
Pieridae Catopsilia pyranthe Mottled Emigrant N
Fresh Water Fish
Channidae Channa striata Murrel N
Channidae Channa sp Kanaya N
Cichilidae Etroplus suratensis Green Chromide N
Cichilidae Oreochromis niloticus Tilapia I
Cichilidae Oreochromis mossambicus Tilapia I
Claridae Clarias brachysoma Magura N NT
Cyprinidae Catla catla Catla I
Cyprinidae Labeo rohita Rohu I
Cyprinidae Puntius sp Petiya N
Penaeidae Penaeus sp Freshwater prawn N
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 33
Family Scientific Name Common name TS CS
Mammels
Bovidae Bubalus bubalis Water buffalo N
Bovidae Bos indicus Domestic Cow I
Cercopithecidae Macaca sinica Toque Monkey E EN
Cercopithecidae Semnopithecus priam Grey langer N NT
Herpestidae Herpestes edwardsi Gray mongoose N
Herpestidae Herpestes smithii Ruddy mongoose N
Hystricidae Hystrix indica Large porcupine N
Leporidae Lepus nigricollis Black-nape hare N
Pteropodidae Pteropus giganteus Flying fox N
Sciuridae Funambulus palmarum Striped palm squirrel N
Suidae Sus scrofa Wild boar N
Viverridae Paradoxurus hermaphroditus Asian Palm Civet cat N
Viverridae Viverricula indica Indian civet N
Reptiles
Agamidae Calotes versicolour Garden Lizard N
Colubridae Pytas mucosa Common Rat Snake N
Elapidae Bungarus caeruleus Common Krait N
Elapidae Naja naja Spectacled Cobra N
Varanidae Varanus bengalensis Land Monitor N
Viperidae Daboia russelii Russell’s Viper N
2.3.3 Rare, Threatened and Endemic Flora and Fauna
The habitats in the project area are degraded due to human influence. Therefore, plant and
animal communities found in natural undisturbed habitats are not represented in these
areas. Only a few threatened species, the Rock Pigeon (CR) is considered threatened. Five
endemic animal species were also recorded (one butterfly, two birds and two mammals)
from the habitats in the project area. These habitats are dominated by pioneer/ secondary
and exotic plant species.
2.3.4 Migratory Paths
Established migratory paths of mammals are not found in the project area or in the
surrounding area of the tank. Some wild animals such as wild boar migrate to the proposed
project area occasionally and severely damage agricultural crops. Also there are signs that
elephants rarely visit the area.
2.3.5 Proposed borrow area
Gravel borrow site is situated close to the proposed site towards the forest area. The
location of the gravel extraction site is in very close proximity to the right bank of the
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 34
spillway. However, that area proposed for the gravel borrow site is under the jurisdiction of
Forest Department.
Invasive shrub Lantana camera (gandapana) dominates the open area while a good tree
cover exists along the border of the site. There are some native trees planted within that
site.
Figure 2.8. Proposed borrow area 1 for gravel
Figure 2.9. Proposed borrow area 2 for gravel
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 35
Figure 2.9 (a). The access roads leading to the borrow areas (The two potos are for the two sites)
2.3.6 Areas proposed for material storage and stock piling
There are vast areas near the spillway which can be used for storage of material (earth, gravel, boulders and for rip rap construction etc.). These areas have no vegetation and therefore, storage of material will not create any negative impacts on flora, fauna or ecosystems.
Figure 2.9 (b). Proposed areas for material storage
The proposed area for material and spoil storage us located close to the spillway basin. This
area has no trees. Therefore, the area can be used for temporary storage of material,
including spoil. Machinery and vehicular yard will be located away from this area, which will
be selected by the contractor.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 36
Figure 2.10. Locations of gravel borrow site and material storage site
2.4 Socioeconomic Environment
2.4.1 Social justification of the rehabilitation of Muthukandiya dam
The stakeholders such as farmers, staff of irrigation department and local community
leaders highlighted the need of rehabilitation of certain features of the dam for its
sustainability for delivering the expected services. The views expressed by the stakeholders
justifying the proposed project are summarized below.
The head work of this irrigation scheme has not been comprehensively rehabilitated
since 1978. Therefore, it needs improvement.
The bund road is seriously dilapidated creating access problem for the users. This is
the road that connects Siyabalanduwa and Madulla DS divisions.
The surface of the 1100m long tank bund has large pot holes and these pot holes get
filled with storm water during rainy seasons. This has created deterioration of the
tank bund.
The height of the tank bund is low at the location it is connected to the me-al oya
through which this irrigation dam has been constructed. Therefore, some
stakeholders perceive this as a threat to the tank bund.
The sluice gates are continuously leaking and therefore, it is a loss to the water
resources retained in the tank.
Material storage area
Material storage area 1
Material storage area 2
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 37
Spill basin of the dam is dilapidated and therefore, downstream of the tank bund at
this location and also spill way canal banks are getting eroded.
Downstream slopes of the bund are not properly established and also bund on the
downstream has many locations where soil has subjected for erosion.
This dam has no downstream toe drain and also toe road to provide protection to
the tank bund.
The tank does not receive adequate inflow in most of the months and therefore, the
tank’s bund should be strong enough to retain limited inflow to the tank.
2.4.2 Existing Socio-economic Environment
The dam is located in Siyambalanduwa and Madulla DS divisions of Monaragala District in
Uva province. The specific locations of difference features of head works in Muthukandiya
irrigation scheme are shown in Table 2.5.
The irrigation command area of Muthukandiya irrigation scheme spread within the
jurisdiction of 5 GN divisions such as Muthukandiya, Yakkadurawa, Manabarana,
Siyambalanduwa and Wijithapura. The Muthukandiya command area has a separate
highland cultivate with other field crops and this highland area falls within another 5 GN
divisions including Ruhunadanawwa, Helamulla, Gal amuna, Samanala Badda and Barawaya.
Both irrigated area and highland area located within Siyambalnaduwa DS division.
A small portion of Muthukandiya irrigation area falls within Madulla DS division but the
major area is located in Siyambalanduwa DS division. Muthukandiya is the largest irrigation
scheme located in Monaragala District.
The settlement of farmers in Muthukandiya was established during 1981-1984. There are
800 farmer families and each family has been allocated with 1 ha of irrigation land and 0.75
acres of residential land. In addition to this 800 families another 456 families also have been
given 2 ha of high land for each family for growing other field crops.
Muthukandiya is an ancient irrigation scheme constructed by father of King Manabarana
and this person was also grandfather of queen Sugala. In local term grandfather is called
“Mutta” and therefore, this irrigation scheme is named as Muthukandiya. This irrigation
tank was fully rehabilitated in 1976.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 38
Table 2.5. Locations of the specific features of Muthukandiya Head works
Feature of head work
DS division GN division Village
Dam and water spread area
Siyambalanduwa and Madulla
Barawaya, Mari arwa and Alugalge
Barawaya, Mari arawa, Alugalla, Madiyagolla
Catchment area Siyambalanduwa and Madulla
Barawaya, Mari arwa and Alugalge
Barawaya, Mari arawa, Alugalla, Madiyagolla
Command area Siyambalanduwa Muthukandiya ,
Yakk adurawa, Manabarana , Siyabalanduwa ,Wijitha pura
Muthukandiya,
Yak adurawa, Manabarana, Siyabalanduwa, Wijitha pura, Hamlets 1, 2, 3 and 4, also fisheries village.
The social assessment covered different geographical area for the study to achieve some specific objectives as mentioned in Table 2.6.
Table 2.6. The geographical units studied and the purpose
Geographical unit Purpose
Tank catchment To verify whether there are encroachers doing agriculture or some other water based livelihood activities.
Upstream of the bund and Water spread area
To document the availability of livelihood activities based on water in the reservoir such as fishery, bathing, washing.
Tank bund To document the uses of tank bund as access, to observe the problem in riprap, and other features of the dam(sluices, spill ways etc.)
Downstream of the bund To verify whether there are encroachers of the reservation of the downstream area.
Command area To document the size of the command area and the socio economic profile of users of the command area
Other water uses of the reservoir
To verify the availability of the uses of water other than farming and fishing.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 39
2.4.3 Land Use
The social study team collected the information on land use pattern of different features of the irrigation scheme. The information collected is shown in Table 2.7.
Table 2.7. Existing land use pattern
Features of irrigation scheme
Observed land use pattern
Tank catchment About 20-25 farmers cultivate other field crops in maha season and each farmer has about 1-1.5 acres for this purpose. These farmers are residing in Mari arawa and Alugolla GN divisions in Madulla DS division. Another about 6 acres in the catchment area of the tank are about to cultivate with rubber plantation. Another 10-15 farmers from Siyambalnaduwa and Barawaya GN area also cultivate other field crops such as pumpkin and maize in maha season. In yala season also about 6-8 persons from these 2 GN divisions cultivate vegetables in catchment area. The catchment area of Muthukandiya is about 1160 acres including water spread area.
Water spread area The water spread area of Muthukandiya tank is about 960 acres. In this area about 50 persons are involved in fishing activities and this group has 27 fishing boats. The tank has 3 bathing spots and these bathing spots are used by 100 families for bathing and washing. In addition to local community pilgrims visiting the area also use these bathing spots(at least 3-4 groups visit per month to the tank for bathing)
Tank bund The length of the tank bund is about 1100 m. This bund is used as access and this access connects Siyambalnduwa and Madulla DS divisions. About 200-250 families from Alugalge, Polgahagama, Mari arawa, Muthukandiya, Hamlet 2 and Barawaya village use this bund as access to reach their residential areas. At least about 100 different vehicles run along this bund road. In addition to these road users the officers of irrigation department and IMD use this bund road for their official activities.
D/S of the bund Downstream of the bund including its reservation is free from encroachment.
Command area The command area is about 2096 acres. This is cultivated by 867 farmers under 6 farmer organizations (FO), Muthukandiya Ekamuthu FO with 75 farmer s and 268 acres, Muthukandiya Gamunu FO with 136 farmers and 303acres. Yakkadurawa ranamayura FO with 178 farmers and 493 acres, Manabarana Siriparakum FO with 137 farmers and 311 acres, Siyambalnaduwa eksat FO with 144 farmers and 324 acres and Wijithapura Sri Wijithapura FO with 199 farmers and 497 acres.
The command area is cultivated in both seasons (Maha 100 % paddy and Yala 95% paddy and 5% with other field crops)
Other water uses of the reservoir
During August to September is water scarcity period and at least about 5-6 water bourses are taken from the tank by local community (about 10 – 12 families for domestic consumption)
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 40
2.4.4 Demographic Data Relevant to the Project Area
The population in Siyambalnduwa DS division and its 5 GN divisions and also Madulla DS
division and its 2 GN divisions can be considered as indirectly beneficial population from the
Muthukandiya irrigation scheme. The details of population in these administrative units are
shown in Table 2.8.
Table 2.8. Population in DS and 5 GN divisions
Admin unit Families Population total
female male
Siyambalnduwa DS 16,428 30,432 31,047 61,479
Muthukandiya GN 232 399 386 785
Yakkadurawa GN 341 685 682 1,367
Manabarana GN 356 669 719 1,388
Siyambalnduwa GN 225 292 442 734
Wijithapura GN 423 690 729 1,419
Barawaya GN 261 971 690 1,361
Madulla DS 8,220 16,007 15,231 31,238
Mari Arawa GN 268 522 499 1,021
Alugalge GN 149 270 297 567
Total of GN population
2,455 4,198 4,444 8,642
The population depending on different features of the irrigation scheme can be defined as
direct beneficiaries of the proposed project. The details of these direct beneficiaries are
included in Table 2.9.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 41
Table 2.9. Direct beneficiaries
Features of irrigation scheme
Families Population
Tank catchment (encroaches for agriculture)
40 140
Water spread area
Fishing families
Bathing and washing
50
98
98
380
Tank bund(uses of the bund road)
250 875
Downstream of the bund(there are no encroaches)
No No
Command area
irrigated land(there are no families residing in command area. They are staying in hamlet area
Muthukandiya Ekamuthu FO Muthukandiya Gamunu FO
Yakkadurawa ranamayura FO Manabarana Siriparakum FO Siyambalnaduwa eksat FO Wijithapura Sri Wijithapura FO
75 families(285 population)
134 families(482 Population)
178 families(694 Population)
137 families(506 Population)
144 families(547 Population)
199 families(776 Population)
Total (867 families & 3297 population)
Other water uses (families fetching water from tank during dry season)
12 46
2.4.5 Economic Activities of Project Related Population
The economic activities of the direct beneficiary population relevant to each feature of
irrigation scheme are summarized in Table 2.10.
2.4.6 Other Water Uses
There are other water users other than people involved in agriculture and fishery but it is not an economic activity (fetching water from the tank for domestic use through bowses).
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 42
Table 2.10. Economic activities of direct beneficiary population
Features of irrigation scheme Economic activities
Tank catchment 40 families cultivate maize, Pumpkin etc. in tank catchment during Maha seasons. Each family does this livelihood activity in about 1.5 acres and earns about Rs. 75000 from one acre/season.
Another 20 families are involved in other field crop cultivation in Yala seasons (mainly vegetable cultivation) and earn about Rs. 80,000 per acre.
Water spread area 50 fishing families carry out fishing activities in certain days of the month and their income during October to May is about Rs. 50,000/month but, income during June to September is only about Rs 25,000 per month.
Tank bund No economic activities performed
Downstream of the bund No economic activities performed
Command area The gross income possible from one acres of paddy is about Rs 88,000 in Maha season and Rs 82,500 in Yala season.( Annex 2 provides a case study to explain the cost benefit of 1 acre of paddy cultivation and also total yield and income of the entire irrigation scheme)
2.4.7 Sensitive places located in the vicinity of the irrigation scheme
A religious place (Wewe Devalaya known in local term) significant for farmers and a field
office of Irrigation Department including circuit bungalow are located within 250 m radius
from the tank bund.
2.4.8 Access to the project area
Muthukandiya Irrigation scheme can be reached through Ampara road that is connected to
Siyambaladuwa Junction. Muthukandiya Reservoir road in 4 Km length and it is connected
to Ampara road.
2.4.9 Infrastructure available in the project area
The roads up to the Reservoir are in good physical condition (recently improved).
The entire project area has access to electricity. Except few households most of the others
have obtained house connections. The people in the project area are dependents on ground
water for drinking purposes but, water quality is poor according to water users interviewed.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 43
There is a community water supply scheme in the area but, the quality of water even in that
water supply scheme is not good.
2.5 Current Environmental Issues of the Project Area
This subsection discusses the other issues pertaining to the area other than those to be
caused by the project activities. The project activities may trigger some of them, resulting in
adverse impacts. Hence it is of paramount to mention such issues in brief in order to lessen
such impacts, if envisaged.
2.5.1 Physical Issues
Most of the village roads are gravel roads. Dust emission is one of the issues that the
villagers are facing, especially the households who live close to the rods during the dry
season. The runoff from the agricultural fields enters the reservoir. Villagers may use this
nutrient loaded water (including heavy metals) for drinking and bathing purposes. Excessive
nutrients entering the reservoir may lead to eutrophication and appearance of algal blooms.
2.5.2 Ecological Issues
Encroachments and slash and burn agricultural practices lead to loss of green cover and
erosion of land. There are no other significant ecological issues identified in the proposed
project area. Some invasive plant species such as Lantana and guinea grass are found in the
natural habitats, tank and tank bund/ toe areas. The periodic cutting of these controls their
colonization in these in terrestrial habitats. The presence of these species prevents the
establishment of indigenous herbs, shrub and some tree species in these habitats.
2.5.3 Socioeconomic Issues
The issues related to different aspects of livelihood system were highlighted by the stakeholders including community leaders and community members interviewed. The issues they highlighted are mentioned below:
Economy related issues: The unstable prices for agriculture produces, significant unemployment rate among youths and lack of land for second and third generation children.
Health related issues: Unavailability of good quality water for drinking, tendency of increasing kidney related diseases, Respiratory diseases during dry seasons due to dust.
Social harmony related issues: Most of the issues on this aspect are related to addiction to alcohol by majority of men in the area
Environmental related issues: Encroachment of Muthukandiya Tank reservation for
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 44
Agriculture, Spread of Mana grass in the area, Encroachment of canal and interior road reservations.
Problems with water sources: Decrease of water levels in drinking water wells in dry seasons, serious contamination of water sources due to excessive application of agro-chemicals.
The proposals of the community: The farmer leaders consulted suggested following as problems to be solved in their irrigation scheme. The problems are mentioned below:
Demarcation and separation of tank related reservations ( with boundary stones
etc.)
Removal of encroachers from the tank catchment area
Construction of another 2 bathing spots for the communities in suitable locations.
Improvements to the spillway road to provide facilities to the communities to use
the access to reach their villages even during rainy days
Desiltation of tank bed
Explore possibility to enhance the inflow to the tank by diverting additional water
from Heda Oya.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 45
3. Proposed Interventions
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 46
3.1 Proposed Engineering Interventions
A list of current structural and operational issues of the dam was given to the consultants
for verification during the reconnaissance field visit. The consultants verified the issues in
the provided list to them and also included other issues not yet included in the original list.
The issues verified by the consultants and also the new issues identified with the assistance
of Irrigation officers of the Dam are summarized in Table 3.1.
Current Issues
The TOR identifies the following as the main issues pertaining to the Dam, and its structures:
Damage of the spillway basin
Appearance of pot-holes in the tank bund
Damages in the existing riprap
Proposed Interventions
The TOR identifies the following as the proposed interventions for the Dam and its structures as a
solution to address the above-mentioned issues:
Demolition and reconstruction of spillway basin
Improvements of the spill access road
Filling potholes and gravelling the tank bund
Improvements in riprap
Improvements to sluice gate and fence
Table 3.1: Current issues at Muthukandiya Tank and Proposed Construction Methodology
Issues identified as per the ToR
Issue Intervention Construction methodology
Damage of the
spillway basin
Demolition and
reconstruction of spillway
basin
Improvements of the spill
access road
Demolishing existing damaged 1:3:6
(40 mm) concrete layer (100 mm thk)
and removing debris outside of the
reservoir as directed
Demolishing existing damaged
Random rubble masonry (225 mm
HA) & Removing, debris outside of
the reservation as directed.
Earth excavation in foundation &
spoil to waste as directed, cut & lift
up to 1.5 m haul 30 m by manually.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 47
Earth Excavation from borrow areas
by machinery and placing,
compacting filling for dam and
including watering by manually (eut
& lift 0-1.5 m, haul 5 km)
supplying & laying Polythene 36/500
(gauge 150 g/sqm)
Mixing, placing, compacting & curing
1:4:8(40 mm) Cement concrete
including form work. & local
transport (machinery )
Supplying, making & fixing 16 mm
thick Plywood form work for each of
06 uses and removing same once
including local transport.
Mixing, placing, compacting & curing
1:3:6 (40 mm) Cement concrete
excluding form work. & including
local transport (machinery )
Furnishing, cutting, bending, binding
and placing for steel reinforcement
including local transport.
Mixing, placing, compacting & curing
1:2:4(20 mm) Cement concrete
including form work. & local
transport (machinery )
Furnishing &placing 225*150 mm
thick rubble packing including local
transport.
Fixing & removing 12 mm thk. 250
mm height Regiform with Tar Blinder
for Expansion joints
Demolition & Reconstruction of the Spill
Access Road in Muthukandiya scheme
Demolishing existing damaged 1:3:6
(40 mm) concrete layer (100 mm thk)
& Removing debris outside of the
reservation as directed.
Demolishing existing damaged
Random rubble masonry (225 mm
thk) & removing debris outside of the
reservation as directed.
Earth Excavation from borrow areas
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 48
by machinery and placing,
compacting filling for dam and
including watering by manually (cut
& lift 0-1.5 m, haul 5 km)
Supplying & laying polythene 36/500
(gauge 150 g/sqm)
Mixing, placing, compacting & curing
1:4:8(40 mm) Cement concrete
including form work. & local
transport (machinery )
Mixing, placing. Compacting & curing
1:2:4(20 mm) Cement concrete
including form work. & local
transport (machinery )
Furnishing, cutting, bending, binding
and placing for steel reinforcement
including local transport.
Fixing & removing 12 mm thick 250
mm height 3.2.8 Regiform with Tar
Blinder for Expansion joints
Appearance of
pot-holes in the
tank bund
Filling potholes and
gravelling the tank bund
Filling Pot Holes & Gravelling the Tank
Bund in Muthukandiya scheme (from
0+000 km to 1+100 km)
Earth Excavation from borrow areas
by machinery and placing,
compacting filling for darn and
including watering by manually for
Potholes.(cut & lift 0-1.5 m, haul 5
km)
Grave] Excavation from borrow areas
by machinery and placing,
compacting filling for darn and
including watering by manually (cut
& lift 0-1.5 m, haul 20 km)
Stripping top soil including removing
debris outside of the reservation-by
machinery.
Damages in the
existing riprap
Improvements in riprap Construction of Rip Rap (part) @ 0+150
km to 1+000 km in Muthukandiya
scheme
Striping top soil & spoil to waste by
machinery.
Earth Excavation from borrow areas
by machinery and placing,
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 49
compacting filling for dam and
including watering by manually.(cut
& lift 0-1.5 m, haul 51 km)
Gravel Excavation from borrow areas
by machinery and placing,
compacting filling for dam and
including watering by manually.(cut
& lift 0-1.5 m, haul 20 km)
Furnishing & Placing 450 mm thk
Rubble Rip Rap including local
transport
Malfunctioning of
the sluice gate
Improvements to sluice
gate and fence
Removing Existing Rod & main sluice
gate, Supplying & fixing new Rod & 3'
x 4' C.I main sluice gate including all
accessories.
Removing Existing Rod & Emergency
sluice gate, Supplying & fixing new
Rod & steel Emergency sluice gate
including all accessories.
Removing Existing hand rails, Supplying
& fixing new hand rails including all
accessories.
Removing existing hand rails in sluice
tower (manually)
Supplying & fabricating & fixing new
Handrail for sluice tower
OTHER INTERVENTIONS
Lack of safety in the
periphery of the
sluice
Removing Existing barbed wire
fence, Supplying & fixing new
PVC coated GI wire mesh fence
for sluice including all
accessories.
Demolishing & Removing existing
damaged Barbed wire fence &
Removing debris outside of the
reservation as directed.
Earth excavation in foundation &
spoil to waste as directed, cut & lift
up to 1 .5 m haul 30 m by manually.
Supplying & fixing fence post from
(2.575 m long) 2" diameter G.I. pipes
& supporting by two no of horizontal
pipes in (2.35 m long) 1.5" diameter
G.I. pipes between two no of fence
posts including cutting, welding &
furnishing the post & fence.
Mixing, placing, compacting & curing
1:3:6 (40 mm) Cement concrete
excluding form work. & including
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 50
local transport
Supplying, making & fixing 16 mm
thick Plywood form work for each of
06 uses and removing same once
including local transport.
Supplying & fixing 1.5 m*0.75 m size
gate for fence around the sluice.
Supplying & fixing approved quality
barbed wires for fence around the
sluice with necessary hooks &
washers as directed
Applying two coat of approved
quality enamel paint durable from
water after preparing surface as
directed.
Supplying & fixing approved quality
PVC coated gauge 10 chain link
fences as directed including
necessary tension wires fence posts
horizontal bars will be separately.
No steps along the
D/S slope to reach the
toe area
Construction of new steps for
access to D/S of the sluice
Earth excavation in foundation &
spoil to waste as directed, cut & lift
up to 1.5 m haul 30 m by manually.
Mixing, placing, compacting & curing
1:3:6 (40 mm) Cement concrete
excluding form work. & including
local transport (machinery )
Supplying, making & fixing 16 mm
thick Plywood form work for each of
06 uses and removing same once
including local transport.
No Name Board
available
Construction of new Name
board with reservoir data.
Demolishing existing damaged
Reservoir Name board foundation &
Removing debris outside of the
reservation as directed.
Earth excavation in foundation &
spoil to waste as directed, cut & lift
up to 1.5 m haul 30 m by manually.
Mixing, placing, compacting & curing
1:3:6 (40 mm) Cement concrete
excluding form work. & including
local transport (machinery )
Supplying, making & fixing 16 mm
thick Plywood form work for each of
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 51
06 uses and removing same once.
including local transport
112 mm thick Brick work in 1:5
cement & sand mortar,(size of the
brick should be L = 220 mm W = 105
mm H <65 mm)
16 mm thick smooth plaster for walls
in 1:1:5 cement lime sand mix
finished smooth with lime putty.
Applying one coat of approved
quality wall primer & two coats of
approved quality weather shield
paint to new walls after applying lime
putty & sand preparing, applying
plaster of pairs & preparing surface
as directed.
Installing Reservoir data for Name
board.(with 8’x 4' plastic board)
Photographic evidence for the identified issues in Table 3.1 is given in Figure 3.1 below.
In addition to above, there are further issues raised by the community. The farmer leaders those who were consulted suggested the following as issues that they are facing which need to be solved in their irrigation scheme. The problems are mentioned below:
Demarcation and separation of tank related reservations ( with boundary stones
etc.)
Removal of encroachers from the tank catchment area
Construction of another 2 bathing spots for the communities in suitable locations.
Improvements to the spillway road to provide facilities to the communities to use
the access to reach their villages even during rainy days
Desiltation of tank bed
Explore possibility to enhance the inflow to the tank by diverting additional water
from Heda Oya.
It is suggested that DSWRPP would look into the above issues, if possible.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 52
Figure 3.1: Photographs on Main Issues of Muthukandiya Dam
Figure 3.1a. Damages to the spillway basin
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 53
Figure 3.1b. Spill access road needs repairs
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 54
Figure 3.1c. Soil borrow site
Figure 3.1d. Gravel borrow site
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 55
Figure 3.1e. Soil borrow site access road and Gravel site access road need widening and clearing of road-side vegetation
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 56
Figure 3.1f. Po-holes in the tank bund needs filling and repairs
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 57
Figure 3.1g. Damages in the existing rip-rap
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 58
Figure 3.1h. Removal of ant holes is needed in the U/S bund slope
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 59
Figure 12. Removal of several small trees are needed in the U/S bund slope
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 60
3.1.1 Resource and Material Requirements for Proposed Interventions of Muthukandiya Reservoir
Only the major requirements are recorded below, which are presumed to have environmental impacts during extraction, transportation, storage and subsequent use in construction work. Other minor material requirements have not been considered here due to small quantities to be handled relative to the material requirements that have been recorded below:
(a) Demolition and reconstruction of spillway basin
- Demolition of existing concrete layer: 67.0 m3
- Demolition of exiting random rubble masonry: 151.0 m3
- Earth excavation for foundations and spoil to waste: 16.8 m3
- Earth needed from borrow areas: 50.25 m3
- Concrete needed for new construction: 1:4:8 (40 mm ): 67.0 m3 & 1:3:6 (40 mm): 25.63 m3 & 1:2:4 (20 mm): 100.5 m3
- Steel for reinforcement of concrete structures: 3,729 kg
- Rubble packing: 106.5 m3
(b) Improvements of the spill access road
- Demolition of existing concrete layer: 7.0 m3
- Demolition of exiting random rubble masonry: 15.75 m3
- Earth excavation for foundations and spoil to waste: 5.25 m3
- Earth needed from borrow areas: 5.25 m3
- Concrete needed for new construction: 1:4:8 (40 mm ): 7.0 m3 & 1:2:4 (20 mm): 10.5 m3
- Steel for reinforcement of concrete structures: 392 kg
(c) Filling potholes and Rehabilitation of the Tank Bund Road
- Stripping top soil and removal of debris: 511.20 m3
- Earth needed from borrow areas: 1,647.20 m3
- Gravel needed from borrow areas: 1,278.00 m3
(d) Rehabilitation of the Rip Rap:
- Stripping top soil and spoil to waste: 255.50 m3
- Earth needed from borrow areas: 1,358.00 m3
- Gravel needed from borrow areas: 675.00 m3
- Removing existing rip rap and relaying: 1,578 m3
- Placing rubble for rip rap (in addition to existing rubble in the rip rap): 910 m3
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 61
3.2 Proposed Borrowing Activities and Identified Borrow Sites
3.2.1 Turfing Materials
The turfing materials are required to prevent the soil erosion in slopes during the rainy
season. The grasses suitable for turfing are available in tank beds and in open grounds close
to the tanks.
3.2.2 Earth
Earth for spillway basin, spill access road, rehabilitation of bund road and rip rap
rehabilitation is about 3,060 m3. Earth will be obtained from the tank bund areas when they
are exposed during the dry season. There are several locations that have been identified as
earth borrow sites which are located near the spillway and bed areas near the Irrigation
Department office premises.
3.2.3 Rubble/Boulders, aggregates and metal
Rubble needed for rip rap construction is about 910 m3 and about 1,578 m3 of rubble in the
existing rip rap can be used for relaying. The spill access road construction needs 106.5 m3
of rubble. Therefore, the rubble requirement is about 1,015.5 m3. Aggregates and metal
required for concrete production for spillway basin, spill access road is about 105 m3.
Rubble, metal and aggregates can be procured from Licensed (GSMB) suppliers. Quotations
will be called according to accepted procurement guidelines and the suppliers will be
selected.
3.2.4 Sand
Sand required for concrete production for spillway basin, spill access road is about 75
m3.Sand mining of Mahaweli River is carried out by the GSMB at Mahiyanganaya. Sand
could be purchased at Mahiyanganaya or if another location is selected a permit for
extracting sand from the river would be required from the Geological Survey and Mines
Bureau (GSMB). Quotations will be called according to accepted procurement guidelines
and the suppliers will be selected.
3.2.5 Gravel
Gravel for rehabilitation of bund road and rip rap rehabilitation is about 1,953 m3. A site
located near the spillway has been selected as borrow area to extract gravel for the
construction work of the bund, bund road and the toe road (See Figure 2.10).
The location for the above identified borrow site is given in Figure 2.10.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 62
3.3 Proposed Interventions that could Affect Neighboring Communities
The Irrigation Department assumes that the proposed development interventions to repair
the rip rap will be implemented during water low period of the tank (just after Yala season
harvesting). If the contractor cannot complete the proposed sensitive development
interventions within the short dry spell there may be a need to keep the tank with low
water levels or postpone the sensitive construction work to the next season where tank
would experience low water levels. If water level is lowered there will be disturbances to
the cultivation planning in the irrigation scheme. Rehabilitation of the bund road and
construction of the spillway (and spill access road) are the most essential needs under the
proposed dam safety development interventions. There can be some temporary
disturbances to the local communities who use to access their villages/Chena over the bund
road during construction of the bund road and the spill access road.
Table 3.2. Potential impacts that would affect the neighborhood communities
Development Intervention
Likelihood impact on neighboring communities
Improvements to the
bund road and spill
access road
The soil for the Bund repairs will be brought from an area close to Tangal
Oya Mandiya Temple, The distance from this location to the Tank bund is
2Km and the communities residing close to the road will have some
disturbances due to dust and congestion of frequent running of heavy
vehicles, the gravel will be transported from an area located about 25 km
distance from the tank bund. This area is known as Kotiyagala watta and
the residents living close to the roads will have disturbances.
Repairs to the
downstream of the
tank bund with toe
drain and toe road
The metal will be transported from an area known as Dombagahawatta
quarry located about 4 Km distance from the tank. The communities living
close to the roads will have disturbances.
Almost all the interventions will affect the neighboring communities for a certain extent;
however, they are not significant. Following interventions that have been proposed can be
listed as interventions that could affect neighboring communities:
Material transport, stockpiling especially for graveling the bund road, rip rap
construction, correcting the slopes of the bund etc.
Transportation activities will create dust, noise and vibration which will be a
nuisance to the neighboring communities.
Constructing the rip rap, slope correction, etc. will obstruct the movements along
the bund
Rehabilitating the bund road will prevent access to the tank
.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 63
3.4 Proposed Interventions that could affect the Natural Habitats
The natural habitats found in the proposed project area and the identified borrow site are
highly degraded. The natural undisturbed habitats or vegetation formations are not found in
the project site or in the borrow site. The existing degraded habitats do not contain critical
elements of biodiversity such as endemic or threatened species confined to the dry zone of
Sri Lanka. The plant species found in these habitats mainly represented by the pioneer/
secondary species, exotic weeds and invasive species. Threatened and endemic species are
not present in these degraded habitats.
The proposed project interventions such as pilling of riprap rubble, packing of removed or
additional new rubble, do not make major disturbances to the existing habitats. Removal of
trees is minimal for any of the activities. Uprooting of herbs, shrubs and climbers in the rip
rap area should be carried out before repairing the rip rap. The clearing of herbs and shrubs
will have temporary impacts on some faunal species, e.g. butterflies and birds, since they
depend on nectar of flowers and fruits of these species. However, individuals of these plant
species are found in the nearby habitats and therefore the impacts would be negligible.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 64
4. PROJECT INDUCED IMPACTS
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 65
4.1 Identification of project induced impacts
Note: The anticipated impacts described under this section are mainly for the construction
phase only. However, any impacts that are induced during operational stages (if any) are
also presented where applicable. The impacts are confined to negative impacts, as the
positive impacts as a result of improved dam safety and improved operational capacities of
Head works are obvious and perceived.
Impacts were classified into three categories:
No: Environmental effects are perceived to have been no change at all.
Low: Environmental effects are not detectable or are so minor that they will neither
destabilize nor noticeably alter any important attribute of the resource.
Moderate: Environmental effects are sufficient to noticeably alter important attributes of
the resource, but not to destabilize them.
High: Environmental effects are clearly noticeable and are sufficient to destabilize the
resource.
Table 4.1 depicts the possible impacts together with their significance on each intervention
proposed.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 66
Table 4.1: Possible impacts due to the proposed interventions and their significance
Issues identified as per the ToR
Issue Intervention Anticipated Impacts Significance
Damage of the
spillway basin Demolition and
reconstruction of spillway
basin
Improvements of the spill
access road
Impact on ecological environment:
Adverse impact of the nearby habitats in spillway area will occur during the
construction phase. Also negative impacts in borrow sites due to the
removal of soil/ gravel would be expected. Excavated pits need to be filled
to prevent collecting rain water, and creating a habitat for mosquito
breeding during the rainy season.
Low
Impact on social environment:
This will be fairly significant and time consuming construction activity in this
dam. If it gets delays there can be some implications to fill the tank up to its
FSL level. Some community members’ access their villages/chenas through
the road across the spillway and there can be some disturbances to these
community members during construction period.
Low
Impacts on physical environment:
Removal and disposal of debris and excavated material
This activity involves the demolition of the existing concrete (67 m3). The
existing random rubble masonry will be removed (151 m3), which will be
part of the construction material (this will partially satisfy the need of
requirement of rubble for reconstruction). The surface preparation will
produce significant amounts of spoil material which need disposal.
Increasing the possibilities of erosion
The proposed construction need small amounts of soil excavation (16.8 m3
of excavation for foundations) before construction of the spillway, spillway
Low
Low
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 67
bed and the stilling bed.
Raw water quality of surface water bodies
Raw water quality of surface water bodies can be affected due to soil
erosion. Soil particles that enter nearby water bodies, such as the tank and
canals etc., can result in temporary turbidity problems. However, the
duration of this exposure is short in duration and hence adverse impacts
anticipated would be not be significant.
Hindrance to vehicular movements, damage to the crest road surface
due to movement of heavy vehicles, temporary storage of earth along
the crest road and elsewhere
The earthwork involved in the construction work is small (50.25 m3). Borrow
material once brought to the site (50.25 m3) has to be unloaded and
stockpiled for subsequent use. This might block the existing run on and off
paths which may create erosion problems elsewhere.
Material transport may result in congestion of local roads. There are
dwelling units along haulage routes and elevated levels of traffic matter can
become a minor temporary adverse impact during the construction period.
Noise and vibration
Earth excavation, demolition of the existing concrete surface (67 m3), and
most of the other activities will generate noise. Much of the proposed work
will be carried out using machinery. However, small machinery will be used
for excavating and rubble and earth transport. Noise and vibration is
expected to be high, however, will last only for several days because the
construction is small.
Dust generation
Small amounts of earth work (16.8 m3 of earth excavation, demolition of the
existing surface (67 m3), earth needed for filling (50.25 m3) and most of the
other activities would produce airborne dust, which are temporary and
Low
Low
Low
Low
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 68
limited to short durations and will be restricted to a small area. Therefore,
air pollution due to the proposed work can be considered not significant.
Pollution of Soil and Water via Fuel and Lubricants
Activities such as operation of construction vehicles, parking areas,
fuel/lubricants spills storage sites, machinery and equipment maintenance
and refueling will generate pollutants that have the potential to pollute soil
and water.
Health and sanitation of worker’s camps
This impact is common for all the activities. The temporary camps, if not
managed properly, may create an unhealthy environment causing health
hazards to both workers and nearby residents. However, the number of
workers to be employed seems not many. Hence the impact is insignificant.
Management of waste (other than construction and excavated material)
and wastewater
Significant quantities of construction waste (e.g., during stripping of top soil)
are expected. In contrast, food items even in small quantities may attract
stray animals. However, the overall impact is very low.
Safety of workers at work
The earthwork involved in the construction work is small. The proposed
construction activities are small-scale and would not pose a severe hazard
and are not potential to cause physical injury to workers during
construction.
Low
Low
Low
Low
Appearance of
pot-holes in the
tank bund
Filling potholes and
gravelling the tank bund Impact on Ecological Environment:
Damage to terrestrial and aquatic habitat
No impact is anticipated.
Threat of spreading of invasive species
The material to be extracted from the tank bed which is inundated during
Low
Low
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 69
the most of the time of the year. So there is a very less possibility of
spreading such species during material extraction.
Effect on fauna
There can be insignificant levels of noise and dust produced during material
transportation and construction work. In addition, due to heavy machinery
there may be temporary disturbances to the animals (especially migratory
birds) inhabiting the tank area.
However, the quantity of work will be less and hence the impact will be low.
Effect on aquatic habitat
Sediments, oil & grease and other chemicals that can be mixed into tank
water can pollute the aquatic habitat and will affect the fish and other
aquatic faunal species.
Low
Low
Impact on Social Environment
Impact due to Material Transportation
Transportation routes of the borrow material (earth and Gravel) not
associated with the residential area and hence impact will be low or none
Impact due to blockage of access
There will be some disturbances to the users of the bund road during
construction period; About 250 families in 5 villages use the bund road to
reach their villages. This impact will be temporary and confined to
construction period, they will have improved surface of the bund in the
post-construction period.
Low
Moderate
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 70
Impacts on Physical Environment:
Hindrance to surface runoff
Borrow material once brought to the site has to be unloaded and stockpiled
for subsequent use. This might block the existing run – on and off paths
which may create erosion problems elsewhere.
However the quantity to be handled seems to be small, hence the impact
may not be significant.
Raw water quality of surface water bodies
Runoff through material borrow areas and unloading sites could lead to
wash off of soil particles to nearby water bodies such as canals, tanks
streams etc. resulting in temporary turbidity problems. However, the
quantity to be handled seems to be very low, hence adverse impacts
anticipated would be insignificant.
Increasing the possibilities of erosion of the U/S/and D/S slopes
Exposed areas of the bund are susceptible to erosion.
Increase in vehicular traffic during transport of construction materials
Material transport may result in air pollution through giving rise to elevated
levels of airborne dust. There are dwelling units along haulage routes and
elevated levels of airborne particulate matter can become a minor
temporary adverse impact during the construction period.
Health and sanitation of worker’s camps and that of residents in the
adjoining areas
This impact is common for all the activities. The temporary camps, if not
managed properly, may create an unhealthy environment causing health
Moderate
Low
Moderate
Low
Low
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 71
hazards to both workers and nearby residents. However, the number of
workers to be employed seems not many. Hence the impact is insignificant.
Management of construction waste and excavated material and
wastewater
No significant quantities of construction waste are expected. In contrast,
food items even in small quantities may attract stray animals. However, the
overall impact is very low.
Generation of noise, vibration and dust affecting the social and biological
environment
Noise and vibration is very low due to the small-scale nature of construction
activities. Activities that would produce airborne dust are temporary and
limited to short durations and will be restricted to a small area.
Low
Low
Damages in the
U/S slope and
rip rap
Improvements in riprap Impact on ecological environment:
Adverse impact of the nearby habitats in rip rap area will occur during the construction phase. There are 9 trees situated along the riprap and the bund that need to remove during rubble laying. Further there are few ant-holes located along the bund that need to remove before the repair.
Common name Dbh, cm Number of trees
Wal maara <10 6
Ipil Ipil <10 1
Kon < 10 2
Also negative impacts in borrow sites due to the removal of soil/ gravel
would be expected. Excavated pits need to be filled to prevent collecting
rain water, and creating a habitat for mosquito breeding during the rainy
season.
Removal of existing vegetation in the rip rap, mainly herbs and shrubs will
Low
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 72
not be significant. Only shrubs and creepers are present in the rip rap. No
damages to ecosystems or habitats.
There can be significant levels of noise and dust produced during material
transportation and construction work. There may be temporary disturbances
to the animals (especially migratory birds and elephants during dry season)
visiting or inhabiting the tank area due to heavy machinery.
The earth will be obtained from the reservoir bed which goes underwater
during the HFL.
Impact on social environment:
If rip rap rehabilitation cannot be completed within the water low period in
the tank there may be a need for lowering the water level or to postpone
the work to the next water low period of the tank.
Significant
Impacts on physical environment:
Removal and disposal of debris and excavated material
This activity involves the clearing of and stripping of top soil (255.50 m3)
along the bund slope. Part of the existing riprap will be completely removed
and the surface has to be prepared for subsequent re-laying of the riprap.
The surface preparation will produce significant amounts of soil material
which need disposal.
Increasing the possibilities of erosion
The proposed construction need significant amounts of earth (1,358 m3) and
gravel (675 m3) excavation. Rip rap rehabilitation need stripping of top soil
along the U/S slope, filling and compaction. Such earth work will lead to soil
erosion, slope erosion and erosion of the exposed surfaces in the borrow
Low-Moderate
Moderate
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 73
areas.
Raw water quality of surface water bodies
Runoff through material borrow areas and unloading sites could lead to
wash off of soil particles. Raw water quality of surface water bodies can be
affected due to soil erosion. Soil particles that enter nearby water bodies,
such as the tank and canals etc., can result in temporary turbidity problems.
However, the duration of this exposure is short in duration and hence
adverse impacts anticipated would be not be significant.
Hindrance to vehicular movements, damage to the crest road surface
due to movement of heavy vehicles, temporary storage of earth along
the crest road and elsewhere
The earthwork involved in the construction work is large (earth - 1,358 m3
and gravel - 675 m3). Borrow material once brought to the site has to be
unloaded and stockpiled for subsequent use. This might block the existing
run on and off paths which may create erosion problems elsewhere.
Material transport may result in congestion of local roads. There are
dwelling units along haulage routes and elevated levels of traffic matter can
become a minor temporary adverse impact during the construction period.
Movement of heavy vehicles will damage the crest road and access roads in
the vicinity.
Material transport may result in air pollution through giving rise to elevated
levels of airborne dust. There are dwelling units along haulage routes and
elevated levels of airborne particulate matter can become a minor
temporary adverse impact during the construction period.
Moderate
Moderate
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 74
Dust generation
Large amounts of rubble (910 m3) and earth work (earth - 1,358 m3 and
gravel - 675 m3), stripping of the top soil along the slope (255 m3) and most
of the other activities would produce airborne dust, which are temporary
and limited to short durations and will be restricted to a small area.
Therefore, air pollution due to the proposed work can be considered not
significant.
Pollution of Soil and Water via Fuel and Lubricants
The rubble and earthwork need a large fleet of heavy vehicles and heavy
machinery. Activities such as operation of construction vehicles, parking
areas, fuel/lubricants spills storage sites, machinery and equipment
maintenance and refueling will generate pollutants that have the potential
to pollute soil and water.
Health and sanitation of worker’s camps
This impact is common for all the activities. The temporary camps, if not
managed properly, may create an unhealthy environment causing health
hazards to both workers and nearby residents. However, the number of
workers to be employed seems not many. Hence the impact is insignificant.
Management of waste (other than construction and excavated material)
and wastewater
Significant quantities of construction waste (e.g., during stripping of top soil)
are expected. In contrast, food items even in small quantities may attract
stray animals. However, the overall impact is very low.
Safety of workers at work
Placing the rubble for the riprap will be done manually. Placing and moving
Moderate
Low
Low
Low
Low
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 75
rubble from the bund crest towards the bund slopes involve extensive
amount of manual labour work. These activities pose a severe hazard and
potential to cause physical injury to workers during moving heavy loads
downhill/uphill.
Damages in the
spill access road
Improvements to access
road to tank bund
Impacts on ecological environment:
There are few alien invasive species recorded among the vegetation found
on tank bund U/S and D/S slopes as well as in the identified borrow areas
during the ecological survey and hence there is a possibility of introducing
such invasive species to the project impact area together with the material
brought into the site and disposal material transport from the site.
Low
Impacts on social environment:
There are about 30 households are residing across the spill basin on the
other side of the tank. These families will have disturbances in their present
flexible mobility along the access road and spillway basin. There will be
some other problems due to dust and noise. These impacts will be confined
to construction period.
Low
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 76
Impacts on physical environment:
Hindrance to surface runoff, hindrance to vehicular movements during
temporary storage of material along the crest road and elsewhere
Borrow material once brought to the site has to be unloaded and stockpiled
for subsequent use. This might block the existing run on and off paths which
may create erosion problems elsewhere.
The quantity to be handled seems to be moderate hence the impact may be
relatively not significant
Raw water quality of surface water bodies
Runoff through material borrow areas and unloading sites could lead to
wash off of soil particles to nearby water bodies such as canals, tanks
streams etc. resulting in temporary turbidity problems. However, the
quantity to be handled seems to be very low, hence adverse impacts
anticipated would be insignificant.
Hindrance to vehicular movements, damage to the crest road surface
due to temporary storage of rubble among the crest road and elsewhere
Material transport may result in air pollution through giving rise to elevated
levels of airborne dust. There are dwelling units along haulage routes and
elevated levels of airborne particulate matter can become a minor
temporary adverse impact during the construction period.
Health and sanitation of worker’s camps
This impact is common for all the activities. The temporary camps, if not
managed properly, may create an unhealthy environment causing health
hazards to both workers and nearby residents. However, the number of
workers to be employed seems not many. Hence the impact is insignificant.
Low
Low
Low
Low
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 77
Management of waste (other than construction and excavated material)
and wastewater
No significant quantities of construction waste are expected. In contrast,
food items even in small quantities may attract stray animals. However, the
overall impact is very low.
Generation of noise, vibration and dust affecting the social and
biological environment
Noise and vibration can occur during compaction of the aggregate layer and
related activities. Activities that would produce airborne dust are temporary
and limited to short durations and will be restricted to a small area.
Safety of workers at work
Placing the concrete will be done manually. These activities pose a moderate
hazard and potential to cause physical injury to workers during moving
heavy loads.
Low
Low
Low
Malfunctioning
of the sluice gate
Improvements to sluice
gate and fence
Impacts on ecological environment:
No significant ecological impact during the construction.
Low
Impacts on social environment:
No significant negative impacts during the construction are envisaged. This
activity can be carried out without negative impacts during water low period
of the tank
Low
Impacts on physical environment:
Lowering of water level is not necessary if the work is carried out during the
rehabilitation of the rip rap, hence the impact can be considered to be low.
Low
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 78
Issues identified during the initial site visit
Issue Intervention Anticipated Impacts Significance
Lack of safety in
the periphery of
the sluice
Removing Existing barbed
wire fence, Supplying &
fixing new PVC coated GI
wire mesh fence for sluice
including all accessories.
Impacts on ecological environment:
No significant ecological impact during the construction.
-
Impacts on social environment:
No significant negative impacts during the construction are envisaged. This
activity can be carried out without negative impacts during water low
period
Low
Impacts on physical environment:
Lowering of water level is not necessary, hence the impact can be
considered to be low.
Low
No steps along
the D/S slope to
reach the toe
area
Construction of new steps
for access to D/S of the
sluice
Impact on Ecological Environment:
No significant ecological impacts during construction is envisaged
-
Impact on Social Environment:
No significant negative impacts during the construction are envisaged.
-
Impact on Physical Environment:
No significant impacts during the construction are envisaged. However,
general impacts such as generation of construction waste, excavated
material, wastewater, generation of noise and vibration and dust which
affect the social and biological environment could be envisaged. Since the
amount of work that has to be carried out is small, the impact is
Low
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 79
insignificant.
No Name Board
available
Construction of new Name
board with reservoir data.
Impact on Ecological Environment:
No significant ecological impacts during construction is envisaged
-
Impact on Social Environment:
No significant negative impacts during the construction are envisaged.
-
Impact on Physical Environment:
No significant impacts during the construction are envisaged.
-
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 80
4.2 Quantification of their significance
Determining the significance of impacts places value on impact magnitude. It relates to the
importance society places on the resources affected, the importance of the impact to system
stability and sustainability.
Quantification of impact magnitude in this study has been objective-based backed by prior
experience of the team of consultants, rather than applying numerical and/or scientific
principles and theories. Once the impact magnitude was determined based on the proposed
construction methodology for each intervention, each expert has decided on the significance of
the impacts based on their area of expertise. Significant impacts will be the focus of mitigation
measures and subsequent monitoring, as outlined in the report.
Factors that have been considered in determining of impact significance include (but are not
limited to):
Area of Influence: Impact significance is often directly related to the size of the area
affected.
Amount of Resource Usage: The greater the amount of resource usage, the more
significant the impact.
Status of Resources: Impacts due to usage of limited resources are usually considered
more significant than impacts to common or abundant resources.
Persistence of Impacts: Permanent or long-term changes are usually more significant
than temporary ones. The ability of the resource to recover, after the activities are
complete, is related to this effect.
Sensitivity of Resources: Impacts to sensitive resources are usually more significant than
impacts to those that are relatively resilient to impacts.
Regulatory Status: Impacts to resources that are protected (e.g., endangered species,
air quality, cultural resources, water quality) typically are considered more significant
than impacts to those without regulatory status.
Societal Value: Some resources have societal value, such as archaeological, cultural and
sacred sites, traditional practices, and recreational areas.
Hence, quantification of impacts was done based on the above-mentioned criteria only for the
impacts that are perceived to be either moderate or high.
There will be no negative social impacts if the contractors could complete the rip rap
rehabilitation within the planned period in which water levels of the tank is low.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 81
Table 4.2. Significance of impacts
Impact Values indicating the significance
If rip rap rehabilitation cannot be completed
within the water low period in the tank there may
be a need for lowering the water level or to
postpone the work to the next water low period of
the tank.
The loss of one Yala season if forgone is about Rs 172.9 M. The average income from one acre is Rs 82,500 and the total extent is about 2,096 acres (See Annex 2).
There will be some disturbances to the users of the bund road during construction period,
About 250 families in 5 villages use the bund road to reach their villages.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 82
5. ENVIRONMENTAL MANAGEMENT PLAN
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 83
5.1 General overview
The purpose of this Environmental Management Plan (EMP) is to manage the anticipated on
and off-site environmental impacts due to the interventions proposed to remedy identified
issues of the dam. Therefore, it is necessary to first scan the issues that have arisen to
compromise the safety and operational efficiency of the Muthukandiya Reservoir. The
following issues and their mitigation measures were identified and presented in the EMP.
5.2 Identification of impacts and their mitigations
This section summarizes the mitigation measures to be implemented for the identified
environmental impacts that can potentially occur predominantly during the construction
phase of the proposed interventions (Table 5.1). This table indicates only the ones that need
mitigation measures and those that are not listed here would not require any mitigation
measures.
The DSWRPP has a strong focus on proper environmental management. Therefore, the
focus of environmental management of the project has not been limited to managing those
impacts arising due to the proposed interventions but also to improve adverse
environmental conditions that will prevail during rehabilitation work by applying proper
mitigation strategies.
As a part of the EMP, appropriate institutional arrangements to implement the proposed
measures and clearances and/or approvals needed by the project prior to its
implementation have been proposed after discussing with the responsible authorities
(Table 5.2). For each proposed intervention, the EMP defines the technical content, roles
and responsibilities of stakeholders, schedule of implementation and methods of
monitoring etc.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 84
Table 5.1: Proposed mitigatory measures for the identified impacts
Issues identified as per the ToR
Intervention and
intervention Anticipated Impacts Mitigation measure
Issue:
Damage of the spillway
basin
Interventions
Demolition and
reconstruction of spillway
basin
Improvements of the spill
access road
Impact on ecological environment:
Adverse impact of the nearby habitats in spillway area
will occur during the construction phase. Also negative
impacts in borrow sites due to the removal of soil/
gravel would be expected. Excavated pits need to be
filled to prevent collecting rain water, and creating a
habitat for mosquito breeding during the rainy season.
Proper management of the borrow site is needed. The spoil can be
used as a fill material to be disposed at the borrow pits.
Proper replanting programme is needed for the borrow areas and
other areas where green cover is removed. List of species is given
in Table 4.1.
Impact on social environment:
This will be fairly significant and time consuming
construction activity in this dam. If it gets delays there
can be some implications to fill the tank up to its FSL
level. Some community members’ access their
villages/chenas through the road across the spillway and
there can be some disturbances to these community
members during construction period.
The spillway basin is about 80 ft wide and therefore, one section of
the basin surface can be kept to be used as the road for users while
the other section is being improved,
There is possible alternative access also to reach the villages. The
road from Mari Arawe Junction to 4th mile post of Ampara road
through/via Alugalge and Hamlet 2 can be used as this alternative
access during construction period.
Impacts on physical environment:
Removal and disposal of debris and excavated
material
This activity involves the demolition of the existing
The mount of debris collection is small – demolished concrete 67
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 85
concrete (67 m3). The existing random rubble masonry
will be removed (151 m3), which will be part of the
construction material (this will partially satisfy the need
of requirement of rubble for reconstruction). The
surface preparation will produce significant amounts of
spoil material which need disposal.
Increasing the possibilities of erosion
The proposed construction need small amounts of soil
excavation (16.8 m3 of excavation for foundations)
before construction of the spillway, spillway bed and the
m3.. Therefore, the impacts are not significant.
Debris and spoil collected is construction and demolition waste
which is inert. These can be used for filling the borrow pits at the
gravel yards.
The random rubble can be used for re-construction.
Spoil and other disposal materials should only be dumped at sites
for which prior approval from relevant authorities such as the LA
has been obtained. Taking into account the following
- The dumping does not impact natural drainage courses
- No endangered / rare flora is impacted by such dumping
- Should be located in non-residential areas located in the
downwind side
- Located at least 100 m from the designated forest land.
- Avoid disposal on productive land.
- should be located with the consensus of the local
community, in consultation with the engineer and shall be
approved by the highways department
- Minimize the construction debris by balancing the cut and
fill requirements.
Erosion of material heaps can be minimized by covering them
during rainy seasons.
Avoid stockpiling of materials close to water bodies; Stripped
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 86
stilling bed.
Raw water quality of surface water bodies
Raw water quality of surface water bodies can be
affected due to soil erosion. Soil particles that enter
nearby water bodies, such as the tank and canals etc.,
can result in temporary turbidity problems. However,
the duration of this exposure is short in duration and
hence adverse impacts anticipated would be not be
significant.
Hindrance to vehicular movements, damage to the
crest road surface due to movement of heavy
vehicles, temporary storage of earth along the crest
road and elsewhere
materials should not be stored where natural drainage will be
disrupted. There are several areas identified (Figure 2.10) as
suitable for stockpiling. Use of these areas for such purposes might
not pose negative impacts on residential and cultivated areas and
also to the water body.
Surface run on and off paths should not be selected for material
unloading areas.
Erosion of material heaps can be minimized by covering them
during rainy seasons.
Avoid stockpiling of materials close to water bodies; Stripped
materials should not be stored where natural drainage will be
disrupted. There are several areas identified, especially the eastern
part of the bund (downstream side) as suitable for stockpiling and
for machinery, tools and vehicular parking spaces. Use of these
areas for such purposes might not pose negative impacts on
residential and cultivated areas and also to the water body.
Exposed areas of the bund slopes will be covered with turfing
material as soon as possible to prevent any erosion.
All the measures mentioned above are valid for this impact as well.
Restrictions on the transportation activities:
a. Maximum axial loads and speed limits for vehicles moving on
the bund will be imposed
b. Time limits for carrying out transportation activities to
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 87
The earthwork involved in the construction work is small
(50.25 m3). Borrow material once brought to the site
(50.25 m3) has to be unloaded and stockpiled for
subsequent use. This might block the existing run on
and off paths which may create erosion problems
elsewhere.
Material transport may result in congestion of local
roads. There are dwelling units along haulage routes and
elevated levels of traffic matter can become a minor
temporary adverse impact during the construction
period.
Noise and vibration
Earth excavation, demolition of the existing concrete
surface (67 m3), and most of the other activities will
generate noise. Much of the proposed work will be
carried out using machinery. However, small machinery
will be used for excavating and rubble and earth
transport. Noise and vibration is expected to be high,
however, will last only for several days because the
construction is small.
control excessive noise generation and to prevent nuisance
to neighbouring communities (6.00 am – 6.00 pm)
Dust emission due to transport operations should be controlled by
wet spraying and tarpaulin covering in mandatory on trucks/lorries
which are used for transporting materials particularly in built up
areas.
Transport, loading and unloading of materials should be carried out
in such a way as not to cause nuisance to the people by way of
noise, vibration of dust. Care must be taken while unloading
material on the bund so as the material may be not rolled down on
either side of U/S and D/S slopes causing damages.
Hydraulically driven machinery is preferred over Pneumatic
machinery to minimize vibrations
No high noise generating machinery is encouraged. Extreme
precautions need to be taken on vibration levels as it could affect
the core of the bund. Watering may be necessary if any activity
generates dust particles.
Excessive noise and vibration at the quarry site has to be controlled.
Implement the conditions such as noise monitoring and other
recommendations stipulated in the permit; Obtain approval from
the Local Authority and Divisional Secretary and Controller of
Explosives (for quarry sites only) and CEA.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 88
Dust generation
Small amounts of earth work (16.8 m3 of earth
excavation, demolition of the existing surface (67 m3),
earth needed for filling (50.25 m3) and most of the other
activities would produce airborne dust, which are
temporary and limited to short durations and will be
restricted to a small area. Therefore, air pollution due to
the proposed work can be considered not significant.
Pollution of Soil and Water via Fuel and Lubricants
Activities such as operation of construction vehicles,
parking areas, fuel/lubricants spills storage sites,
machinery and equipment maintenance and refueling
will generate pollutants that have the potential to
pollute soil and water.
Health and sanitation of worker’s camps
This impact is common for all the activities. The
temporary camps, if not managed properly, may create
an unhealthy environment causing health hazards to
both workers and nearby residents. However, the
number of workers to be employed seems not many.
Hence the impact is insignificant.
Management of waste (other than construction and
excavated material) and wastewater
All raw materials (sand, rubble, metal, etc.) should be stored in
covered areas to ensure protection from dust emissions and such
materials should be handled in an environmentally friendly and
nuisance free manner.
These measures will also be the same for all other interventions
Any spills should be removed immediately. Parking areas and
maintenance yards for construction vehicles and machinery should
not be located close to water bodies.
Conditions of worker camps to be checked by the Public Health
Officer in charge of the relevant area on a regular basis.
All food leftovers and organic garbage should be disposed of in a
proper manner so that it will not attract stray and wild animals.
Solid waste should not be burnt in the open air within or outside the
proposed site.
Proper sanitation facilities should be provided on-site for the
workforce. Ideally, this can be a pit latrine in which the pit is located
above the ground water table. Covering the deposit (with earth or
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 89
Significant quantities of construction waste (e.g., during
stripping of top soil) are expected. In contrast, food
items even in small quantities may attract stray animals.
However, the overall impact is very low.
Safety of workers at work
The earthwork involved in the construction work is
small. The proposed construction activities are small-
scale and would not pose a severe hazard and are not
potential to cause physical injury to workers during
construction.
sawdust) is necessary to prevent smells and to discourage flies.
This measure is common for all the interventions and therefore
applicable for the whole project period.
Construction waste shall be collected regularly and disposed of
periodically in an environmentally safe and nuisance free manner.
Wastewater will be disposed, by way of a pit latrine/soakage
arrangement. This measure too will be common and valid for the
entire construction period.
Issue:
Appearance of pot-holes in
the tank bund
Intervention:
Filling potholes and
gravelling the tank bund
Impact on Ecological Environment:
Damage to terrestrial and aquatic habitat
No impact is anticipated.
Threat of spreading of invasive species
The material to be extracted from the tank bed which is
inundated during the most of the time of the year. So
there is a very less possibility of spreading such species
during material extraction.
Effect on fauna
There can be insignificant levels of noise and dust
produced during material transportation and
construction work. In addition, due to heavy machinery
there may be temporary disturbances to the animals
(especially migratory birds) inhabiting the tank area.
However, the quantity of work will be less and hence
Site specific mitigatory measures are not required.
Area proposed for gravel borrow site is within a forest area. Top
soil in the area that removed during gravel extraction should be
staked for rehabilitation of the site. It is proposed to level the tank
bed by remove extra silt and soil. Soil that is removed from the tank
bed should use to rehabilitate the gravel borrow area. Further,
plantlets of native plant species should reintroduce to this area in
order to compensate for other trees.
Native plant species proposed for rehabilitation of gravel borrow
site and other areas is given in Table 5.2.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 90
the impact will be low.
Effect on aquatic habitat
Sediments, oil & grease and other chemicals that can be
mixed into tank water can pollute the aquatic habitat
and will affect the fish and other aquatic faunal species.
Any spills should be removed immediately. Parking areas and
maintenance yards for construction vehicles and machinery should
not be located close to water bodies.
Impact on Social Environment
Impact due to Material Transportation
Transportation routes of the borrow material (earth and
Gravel) not associated with the residential area and
hence impact will be low or none
Impact due to blockage of access
There will be some disturbances to the users of the
bund road during construction period; About 250
families in 5 villages use the bund road to reach their
villages. This impact will be temporary and confined to
construction period, they will have improved surface of
the bund in the post-construction period.
The tank bund is about 40 ft wide and therefore, one section of the
bund surface can be kept for the bund road users while the other
section is being improved,
There is possible alternative access also to reach the villages that
are reached through the bund road. The road from Mari Arawe
Junction to 4th mile post of Ampara road through/via Alugalge and
Hamlet 2 can be used as this alternative access during construction
period.
The time schedule of material transportation need to be early
communicated to the communities in the close proximity of the
roads; This may be done through FO leaders and other grassroots
level stakeholders such as GNs. The Drivers of the heavy vehicles
transporting construction material should be educated to follow
certain principles of driving their vehicles through villages
Impacts on Physical Environment:
Hindrance to surface runoff
Borrow material once brought to the site has to be
Surface run on and off paths should not be selected for material
unloading areas.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 91
unloaded and stockpiled for subsequent use. This might
block the existing run – on and off paths which may
create erosion problems elsewhere.
However the quantity to be handled seems to be small,
hence the impact may not be significant.
Raw water quality of surface water bodies
Runoff through material borrow areas and unloading
sites could lead to wash off of soil particles to nearby
water bodies such as canals, tanks streams etc. resulting
in temporary turbidity problems. However, the quantity
to be handled seems to be very low, hence adverse
impacts anticipated would be insignificant.
Increasing the possibilities of erosion of the U/S/and
D/S slopes
Exposed areas of the bund are susceptible to erosion.
Erosion of material heaps can be minimized by covering them
during rainy seasons.
Avoid stockpiling of materials close to water bodies; Stripped
materials should not be stored where natural drainage will be
disrupted. There are several areas identified, especially the eastern
part of the bund (downstream side) as suitable for stockpiling and
for machinery, tools and vehicular parking spaces. Use of these
areas for such purposes might not pose negative impacts on
residential and cultivated areas and also to the water body.
Surface run on and off paths should not be selected for material
unloading areas.
Erosion of material heaps can be minimized by covering them
during rainy seasons.
Avoid stockpiling of materials close to water bodies; Stripped
materials should not be stored where natural drainage will be
disrupted. There are several areas identified, especially the eastern
part of the bund (downstream side) as suitable for stockpiling and
for machinery, tools and vehicular parking spaces. Use of these
areas for such purposes might not pose negative impacts on
residential and cultivated areas and also to the water body.
Exposed areas of the bund slopes will be covered with turfing
material as soon as possible to prevent any erosion.
All the measures mentioned above are valid for this impact as well.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 92
Increase in vehicular traffic during transport of
construction materials
Material transport may result in air pollution through
giving rise to elevated levels of airborne dust. There are
dwelling units along haulage routes and elevated levels
of airborne particulate matter can become a minor
temporary adverse impact during the construction
period.
Health and sanitation of worker’s camps and that of
residents in the adjoining areas
This impact is common for all the activities. The
temporary camps, if not managed properly, may create
an unhealthy environment causing health hazards to
both workers and nearby residents. However, the
number of workers to be employed seems not many.
Hence the impact is insignificant.
Management of construction waste and excavated
Restrictions on the transportation activities:
a. Maximum axial loads and speed limits for vehicles moving on
the bund will be imposed
b. Time limits for carrying out transportation activities to control
excessive noise generation and to prevent nuisance to
neighbouring communities (6.00 am – 6.00 pm)
Dust emission due to transport operations should be controlled by
wet spraying and tarpaulin covering in mandatory on trucks/lorries
which are used for transporting materials particularly in built up
areas.
Transport, loading and unloading of materials should be carried out
in such a way as not to cause nuisance to the people by way of
noise, vibration of dust. Care must be taken while unloading
material on the bund so as the material may be not rolled down on
either side of U/S and D/S slopes causing damages.
Conditions of worker camps to be checked by the Public Health
Officer in charge of the relevant area on a regular basis.
All food leftovers and organic garbage should be disposed of in a
proper manner so that it will not attract stray and wild animals.
Solid waste should not be burnt in the open air within or outside the
proposed site.
Proper sanitation facilities should be provided on-site for the
workforce. Ideally, this can be a pit latrine in which the pit is located
above the ground water table. Covering the deposit (with earth or
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 93
material and wastewater
No significant quantities of construction waste are
expected. In contrast, food items even in small
quantities may attract stray animals. However, the
overall impact is very low.
Generation of noise, vibration and dust affecting the
social and biological environment
Noise and vibration is very low due to the small-scale
nature of construction activities. Activities that would
produce airborne dust are temporary and limited to
short durations and will be restricted to a small area.
sawdust) is necessary to prevent smells and to discourage flies.
This measure is common for all the interventions and therefore
applicable for the whole project period.
Construction waste shall be collected regularly and disposed of
periodically in an environmentally safe and nuisance free manner.
Wastewater will be disposed, by way of a pit latrine/soakage
arrangement. This measure too will be common and valid for the
entire construction period.
Hydraulically driven machinery is preferred over Pneumatic
machinery to minimize vibrations
No high noise generating machinery is encouraged. Extreme
precautions need to be taken on vibration levels as it could affect
the core of the bund. Watering may be necessary if any activity
generates dust particles.
Excessive noise and vibration at the quarry site has to be controlled.
Implement the conditions such as noise monitoring and other
recommendations stipulated in the permit; Obtain approval from
the Local Authority and Divisional Secretary and Controller of
Explosives (for quarry sites only) and CEA.
All raw materials (sand, rubble, metal, etc.) should be stored in
covered areas to ensure protection from dust emissions and such
materials should be handled in an environmentally friendly and
nuisance free manner.
These measures will also be the same for all other interventions.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 94
Issue:
Damages in the U/S slope
and rip rap
Intervention:
Improvements in riprap
Impact on ecological environment:
Adverse impact of the nearby habitats in rip rap area
will occur during the construction phase. There are 9
trees situated along the riprap and the bund that need
to remove during rubble laying. Further there are few
ant-holes located along the bund that need to remove
before the repair.
Common
name
Dbh, cm Number
of trees
Wal maara <10 6
Ipil Ipil <10 1
Kon < 10 2
Also negative impacts in borrow sites due to the
removal of soil/ gravel would be expected. Excavated
pits need to be filled to prevent collecting rain water,
and creating a habitat for mosquito breeding during the
rainy season.
Removal of existing vegetation in the rip rap, mainly
herbs and shrubs will not be significant. Only shrubs and
creepers are present in the rip rap. No damages to
ecosystems or habitats.
There can be significant levels of noise and dust
produced during material transportation and
It is proposed to remove 9 trees before rehabilitation of the rip rap.
In order to compensate the loss of trees, native plant species in the
area can be planted along the road. Further, it is better to introduce
such plants in to the catchment as well.
See Table 5.2 for a list of native plants that can be planted in the
borrow area to compensate any loss of trees.
However, these trees are small (DBH < 10 cm) and no loss of
habitats is expected.
Area proposed for gravel borrow site is within a forest area. Top
soil in the area that removed during gravel extraction should be
staked for rehabilitation of the site. It is proposed to level the tank
bed by remove extra silt and soil. Soil that is removed from the tank
bed should use to rehabilitate the gravel borrow area. Further,
plantlets of native plant species should reintroduce to this area in
order to compensate for other trees.
The easily decomposable vegetation could either be utilized as a soil
conditioner after drying or be composted in a proper manner. Large
vegetation parts could be sold or else be used as firewood.
The contractor is responsible for proper management of all
vegetative parts that are to be uprooted.
The project area must be covered or fenced properly to avoid
disturbances to the surrounding habitats including the tank water
Native plant species proposed for rehabilitation of gravel borrow
site and other areas is given in Table 5.2.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 95
construction work. There may be temporary
disturbances to the animals (especially migratory birds
and elephants during dry season) visiting or inhabiting
the tank area due to heavy machinery.
The earth will be obtained from the reservoir bed which
goes underwater during the HFL.
Impact on social environment:
If rip rap rehabilitation cannot be completed within the
water low period in the tank there may be need to
lowering the water level or to postpone the work to the
next water low period of the tank.
The contractors will be encouraged to complete the work during
water low period of the tank and also continues monitoring of the
contractors' progress on completion of rip rap rehabilitation within
the planned period of time.
The most feasible solution that will have win-win situation for both
parties (farmers as well as project developer) is to attend rip rap
rehabilitation work during July to September in which water level of
the tank is significantly low. The maha season, 2016/17 will end at
the end of February 2017 and Yala season, 2017 should be started
early in March 2017 and it will end at June 2017. If this calendar is
followed there will be possibility to attend the work just after the
Yala season in which water level is low in the reservoir.
Impacts on physical environment:
Removal and disposal of debris and excavated
material
This activity involves the clearing of and stripping of top
soil (255 m3) along the bund slope. Part of the existing
riprap will be completely removed and the surface has
There will be 1,578 m3 of rubble removed from the existing riprap,
which will be piled along the crest road. In addition, 910 m3 of
rubble is needed for the construction of the rip rap. In addition to
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 96
to be prepared for subsequent re-laying of the riprap.
The surface preparation will produce significant
amounts of soil material which need disposal.
Increasing the possibilities of erosion
The proposed construction need significant amounts of
soil and gravel excavation. Rip rap rehabilitation need
stripping of top soil along the U/S slope, filling and
compaction. Such earth work will lead to soil erosion,
slope erosion and erosion of the exposed surfaces in the
borrow areas.
Raw water quality of surface water bodies
Runoff through material borrow areas and unloading
sites could lead to wash off of soil particles. Raw water
quality of surface water bodies can be affected due to
soil erosion. Soil particles that enter nearby water
bodies, such as the tank and canals etc., can result in
temporary turbidity problems. However, the duration of
this exposure is short in duration and hence adverse
impacts anticipated would be not be significant.
the more than 1,358 m3 of earth, 675 m3 of gravel and 270 m3 of
well-graded aggregate are required for the base construction of the
rip rap.
Debris material shall be disposed in such a manner that the tank,
canals and other existing drainage paths are not blocked (as
described above)
Drainage paths associated with the dam and other irrigation
structures should be improved / erected to drain rain water
properly.
Silt traps will be constructed to avoid siltation into the water ways,
the tank and canals, where necessary.
To avoid siltation, drainage paths should not be directed to the tank
and irrigation canals and they should be separated from these
water bodies
Bund Embankment slopes, slopes of cuts, etc. shall not be unduly
exposed to erosive forces. These exposed slopes shall be graded
and covered by grass or other suitable materials per the
specifications.
All fills, back fills and slopes should be compacted immediately to
reach the specified degree of compaction and establishment of
proper mulch.
Work that lead to heavy erosion shall be avoided during the raining
season. If such activities need to be continued during rainy season
prior approval must be obtained from the Engineer by submitting a
proposal on actions that will be undertaken by the contractor to
prevent erosion.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 97
Hindrance to vehicular movements, damage to the
crest road surface due to movement of heavy
vehicles, temporary storage of earth along the crest
road and elsewhere
The earthwork involved in the construction work is large
(earth - 1,358 m3 and gravel - 675 m3). Borrow material
once brought to the site has to be unloaded and
stockpiled for subsequent use. This might block the
existing run on and off paths which may create erosion
problems elsewhere.
Material transport may result in congestion of local
roads. There are dwelling units along haulage routes and
elevated levels of traffic matter can become a minor
temporary adverse impact during the construction
period. Movement of heavy vehicles will damage the
crest road and access roads in the vicinity.
The work, permanent or temporary shall consist of measures as per
design or as directed by the engineer to control soil erosion,
sedimentation and water pollution to the satisfaction of the
engineer. Typical measures include the use of berms, dikes
sediment basins, fiber mats, mulches, grasses, slope drains and
other devices. All sedimentation and pollution control works and
maintenance thereof are deemed, as incidental to the earthwork or
other items of work and no separate payment will be made for their
implementation.
The material transportation, and storage of this material should be
planned carefully. One half along the road can be used for piling the
rubble removed from the existing rip rap. Other material should be
stored appropriately, avoiding any erosion of stored earth and
gravel, not obstructing drainage pathways etc.
The work can proceed phase by phase, each phase restricted to
about 50-75 m. The surface of the slope can be prepared for
subsequent laying of the new rip rap without delay, using the
removed rubble and replenishing new material as needed. If such a
procedure is followed, the need for large amounts of handling
rubble at one occasion can be avoided, thus not requiring large
storage areas for piling material, especially along the crest road.
Noise from vehicles, machinery and equipment
Hydraulically driven machinery is preferred over Pneumatic
machinery to minimize vibrations
Noise generating work should be limited to day time (6:00 AM to
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 98
Material transport may result in air pollution through
giving rise to elevated levels of airborne dust. There are
dwelling units along haulage routes and elevated levels
of airborne particulate matter can become a minor
temporary adverse impact during the construction
period.
Dust generation
Large amounts of rubble (910 m3) and earth work (earth
- 1,358 m3 and gravel - 675 m3), stripping of the top soil
along the slope (255 m3) and most of the other activities
would produce airborne dust, which are temporary and
limited to short durations and will be restricted to a
small area. Therefore, air pollution due to the proposed
work can be considered not significant.
Pollution of Soil and Water via Fuel and Lubricants
The rubble and earthwork need a large fleet of heavy
vehicles and heavy machinery. Activities such as
operation of construction vehicles, parking areas,
fuel/lubricants spills storage sites, machinery and
equipment maintenance and refueling will generate
pollutants that have the potential to pollute soil and
water.
6:00 PM). No work that generates excessive noise should be carried
out during night hours where in close proximity (from 6:00 PM to
6:00 AM on the following day).
All equipment and machinery should be operated at noise levels
that do not exceed the permissible level of 75 dB (during
construction) for the day time. For all construction activities
undertaken during the night time, it is necessary to maintain the
noise level at below 50 dB as per the Central Environmental
Authority (CEA) noise control regulations
All equipment should be in good serviced condition. Regular
maintenance of all construction vehicles and machinery to meet
noise control regulations stipulated by the CEA in 1996 (Gazette
Extra Ordinary, No 924/12) must be conducted for
vehicles/machinery that will be used in construction on site and for
transport.
Ideally noise generating work should not be carried out during
public holidays and religious days. Special care should be taken as
there is a temple nearby.
Labor gangs should be warned to work with minimum noise. Strict
labor supervision should be undertaken in this respect. Number of
night time resident laborers should be minimized.
Vehicular noise pollution at residential / sensitive receptors
Idling of temporary trucks or other equipment should not be
permitted during periods of loading / unloading or when they are
not in active use. The practice must be ensured especially near
residential / commercial / sensitive areas.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 99
Stationary construction equipment will be kept at least 500m away
from sensitive receptors, where possible. These include places of
worship and households.
All possible and practical measures to control noise emissions
during drilling shall be employed.
Contractor shall submit the list of high noise/vibration generating
machinery & equipment to the engineer for approval.
Servicing of all construction vehicles and machinery must be done
regularly and during routine servicing operations, the effectiveness
of exhaust silencers will be checked and if found defective will be
replaced.
Maintenance of vehicles, equipment and machinery shall be regular
and up to the satisfaction of the Engineer to keep noise levels at the
minimum.
Dust Control
All construction materials such as sand, metal, lime, bricks etc.
should be transported under cover to the site and stored under
cover at the sight. Plastic sheeting (of about 6 mm minimum
thickness) can be used and held in place with weights, such as old
tires or cinder blocks, with the edges of the sheeting buried, or by
the use of other anchoring systems. This will minimize the levels of
airborne dust.
Mud patches caused by material transporting vehicles in the access
road should be immediately cleaned.
Continual water sprinkling should be carried out in the work and fill
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 100
Health and sanitation of worker’s camps
This impact is common for all the activities. The
temporary camps, if not managed properly, may create
an unhealthy environment causing health hazards to
both workers and nearby residents. However, the
number of workers to be employed seems not many.
Hence the impact is insignificant.
areas and the access road if dust stir is observed. Water sprinkling
should be done more frequently on days that are dry and windy (at
least four time’s day) as the levels of dust can be elevated during
dry periods.
Dust masks should be provided to the laborers for the use at
required times.
All construction vehicle parking location, fuel/lubricants storage
sites, vehicle, machinery and equipment maintenance and refueling
sites shall be located away from the reservoir, at least 200 m away,
and irrigation canal/ponds.
All vehicle/machinery and equipment operation, maintenance and
refueling will be carried out in such a fashion that spillage of fuels
and lubricants does not contaminate the ground.
Collect, store and dispose oily wastes to the pre-identified disposal
sites approved by the Engineer. All spills and collected petroleum
products will be disposed of in accordance with standards set by
the CEA/MoE, certified by the Engineer.
Construction waste shall be collected regularly and disposed of
periodically in an environmentally safe and nuisance free manner.
Wastewater will be disposed, by way of a pit latrine/soakage
arrangement. This measure too will be common and valid for the
entire construction period.
The mitigation measures and general conditions are described in
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 101
Management of waste (other than construction and
excavated material) and wastewater
Significant quantities of construction waste (e.g., during
stripping of top soil) are expected. In contrast, food
items even in small quantities may attract stray animals.
However, the overall impact is very low.
Safety of workers at work
Placing the rubble for the riprap will be done manually.
Placing and moving rubble from the bund crest towards
the bund slopes involve extensive amount of manual
labour work. These activities pose a severe hazard and
potential to cause physical injury to workers during
moving heavy loads downhill/uphill.
Section 5.5 (Operation of labour camps).
The mitigation measures and general conditions are described in
Section 5.4 (Safety at work)
Work should proceed phase by phase, each phase involving the
work of about 50-75 m. This will prevent huge amount of rubble
handling and storing along the crest, minimizing the safety issues.
Laborers should be instructed to coordinate properly while carrying
heavy loads. Any injuries should be attend to complying with
emergency procedures.
Issues:
Damages in the spill access
road
Interventions:
Improvements to access
road to tank bund
Impacts on ecological environment:
There are few alien invasive species recorded among the
vegetation found on tank bund U/S and D/S slopes as
well as in the identified borrow areas during the
ecological survey and hence there is a possibility of
introducing such invasive species to the project impact
area together with the material brought into the site
and disposal material transport from the site.
It is proposed to remove 18 trees before construction of the toe
access road. In order to compensate the loss of trees, native plant
species in the area can be planted along the road. Further, it is
better to introduce such plants in to the catchment as well.
See Table 5.2 for a list of native plants that can be planted in the
borrow area to compensate any loss of trees.
Impacts on social environment:
There are about 30 households are residing across the
spill basin on the other side of the tank. These families
will have disturbances in their present flexible mobility
The tank bund is about 40 ft wide and therefore, one section of the
bund surface can be kept for the bund road users while the other
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 102
along the access road and spillway basin. There will be
some other problems due to dust and noise. These
impacts will be confined to construction period.
section is being improved,
There is possible alternative access also to reach the villages that
are reached through the bund road. The road from Mari Arawe
Junction to 4th mile post of Ampara road through/via Alugalge and
Hamlet 2 can be used as this alternative access during construction
period.
The time schedule of material transportation need to be early
communicated to the communities in the close proximity of the
roads; This may be done through FO leaders and other grassroots
level stakeholders such as GNs. The Drivers of the heavy vehicles
transporting construction material should be educated to follow
certain principles of driving their vehicles through villages
Impacts on physical environment:
Hindrance to surface runoff, hindrance to vehicular
movements during temporary storage of material
along the crest road and elsewhere
Borrow material once brought to the site has to be
unloaded and stockpiled for subsequent use. This might
block the existing run on and off paths which may create
erosion problems elsewhere.
The quantity to be handled seems to be moderate
hence the impact may be relatively not significant
Raw water quality of surface water bodies
Runoff through material borrow areas and unloading
sites could lead to wash off of soil particles to nearby
During site clearance activities, removal of vegetation and debris
must be carried out swiftly and in well-planned manner.
Identify the sites for disposal of material cleared is needed prior to
commencement of the work.
Plants, shrubs and other vegetation cleared should not be burned
on site.
Spoil and other disposal materials should only be dumped at sites
for which prior approval from relevant authorities such as the LA
has been obtained. Taking into account the following
- The dumping does not impact natural drainage courses
- No endangered / rare flora is impacted by such dumping
- Should be located in non-residential areas located in the
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 103
water bodies such as canals, tanks streams etc. resulting
in temporary turbidity problems. However, the quantity
to be handled seems to be very low, hence adverse
impacts anticipated would be insignificant.
Hindrance to vehicular movements, damage to the
crest road surface due to temporary storage of
rubble among the crest road and elsewhere
Material transport may result in air pollution through
giving rise to elevated levels of airborne dust. There are
dwelling units along haulage routes and elevated levels
of airborne particulate matter can become a minor
temporary adverse impact during the construction
period.
Health and sanitation of worker’s camps
This impact is common for all the activities. The
temporary camps, if not managed properly, may create
an unhealthy environment causing health hazards to
both workers and nearby residents. However, the
number of workers to be employed seems not many.
Hence the impact is insignificant.
Management of waste (other than construction and
excavated material) and wastewater
No significant quantities of construction waste are
expected. In contrast, food items even in small
quantities may attract stray animals. However, the
overall impact is very low.
downwind side
- Located at least 100 m from the designated forest land.
- Avoid disposal on productive land.
- should be located with the consensus of the local
community, in consultation with the engineer and shall be
approved by the highways department
- Minimize the construction debris by balancing the cut and
fill requirements.
The contractor should avoid any spillage of spoil when transporting
such materials to the approved material dumping sites.
Debris material shall be disposed in such a manner that the tank,
canals and other existing drainage paths are not blocked (as
described above)
Drainage paths associated with the dam and other irrigation
structures should be improved / erected to drain rain water
properly.
Silt traps will be constructed to avoid siltation into the water ways,
the tank and canals, where necessary.
To avoid siltation, drainage paths should not be directed to the tank
and irrigation canals and they should be separated from these
water bodies
Work that lead to heavy erosion shall be avoided during the raining
season. If such activities need to be continued during rainy season
prior approval must be obtained from the Engineer by submitting a
proposal on actions that will be undertaken by the contractor to
prevent erosion.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 104
Generation of noise, vibration and dust affecting the
social and biological environment
Noise and vibration can occur during compaction of the
aggregate layer and related activities. Activities that
would produce airborne dust are temporary and limited
to short durations and will be restricted to a small area.
Safety of workers at work
Placing the concrete will be done manually. These
activities pose a moderate hazard and potential to cause
physical injury to workers during moving heavy loads.
The work, permanent or temporary shall consist of measures as per
design or as directed by the engineer to control soil erosion,
sedimentation and water pollution to the satisfaction of the
engineer. Typical measures include the use of berms, dikes
sediment basins, fiber mats, mulches, grasses, slope drains and
other devices. All sedimentation and pollution control works and
maintenance thereof are deemed, as incidental to the earthwork or
other items of work and no separate payment will be made for their
implementation.
Noise from vehicles, machinery and equipment
Hydraulically driven machinery is preferred over Pneumatic
machinery to minimize vibrations
Noise generating work should be limited to day time (6:00 AM to
6:00 PM). No work that generates excessive noise should be carried
out during night hours where in close proximity (from 6:00 PM to
6:00 AM on the following day).
All equipment and machinery should be operated at noise levels
that do not exceed the permissible level of 75 dB (during
construction) for the day time. For all construction activities
undertaken during the night time, it is necessary to maintain the
noise level at below 50 dB as per the Central Environmental
Authority (CEA) noise control regulations
All equipment should be in good serviced condition. Regular
maintenance of all construction vehicles and machinery to meet
noise control regulations stipulated by the CEA in 1996 (Gazette
Extra Ordinary, No 924/12) must be conducted for
vehicles/machinery that will be used in construction on site and for
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 105
transport.
Ideally noise generating work should not be carried out during
public holidays and religious days. Special care should be taken as
there is a temple nearby.
Labor gangs should be warned to work with minimum noise. Strict
labor supervision should be undertaken in this respect. Number of
night time resident laborers should be minimized.
Vehicular noise pollution at residential / sensitive receptors
Idling of temporary trucks or other equipment should not be
permitted during periods of loading / unloading or when they are
not in active use. The practice must be ensured especially near
residential / commercial / sensitive areas.
Stationary construction equipment will be kept at least 500m away
from sensitive receptors, where possible. These include places of
worship and households.
All possible and practical measures to control noise emissions
during drilling shall be employed.
Contractor shall submit the list of high noise/vibration generating
machinery & equipment to the engineer for approval.
Servicing of all construction vehicles and machinery must be done
regularly and during routine servicing operations, the effectiveness
of exhaust silencers will be checked and if found defective will be
replaced. Maintenance of vehicles, equipment and machinery shall
be regular and up to the satisfaction of the Engineer to keep noise
levels at the minimum.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 106
Dust Control
All construction materials such as sand, metal, lime, bricks etc.
should be transported under cover to the site and stored under
cover at the sight. Plastic sheeting (of about 6 mm minimum
thickness) can be used and held in place with weights, such as old
tires or cinder blocks, with the edges of the sheeting buried, or by
the use of other anchoring systems. This will minimize the levels of
airborne dust.
Mud patches caused by material transporting vehicles in the access
road should be immediately cleaned.
Continual water sprinkling should be carried out in the work and fill
areas and the access road if dust stir is observed. Water sprinkling
should be done more frequently on days that are dry and windy (at
least four time’s day) as the levels of dust can be elevated during
dry periods.
Dust masks should be provided to the laborers for the use at
required times.
All construction vehicle parking location, fuel/lubricants storage
sites, vehicle, machinery and equipment maintenance and refueling
sites shall be located away from the reservoir, at least 200 m away,
and irrigation canal/ponds.
All vehicle/machinery and equipment operation, maintenance and
refueling will be carried out in such a fashion that spillage of fuels
and lubricants does not contaminate the ground.
Collect, store and dispose oily wastes to the pre-identified disposal
sites approved by the Engineer. All spills and collected petroleum
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 107
products will be disposed of in accordance with standards set by
the CEA/MoE, certified by the Engineer.
The mitigation measures and general conditions are described in
Section 5.5 (Operation of labour camps).
Construction waste shall be collected regularly and disposed of
periodically in an environmentally safe and nuisance free manner.
Wastewater will be disposed, by way of a pit latrine/soakage
arrangement. This measure too will be common and valid for the
entire construction period.
The mitigation measures and general conditions are described in
Section 5.4 (Safety at work)
Work should proceed phase by phase, each phase involving the
work of about 100 m. This will prevent huge amount of rubble
handling and storing along the sloping areas of the toe of the bund,
minimizing the safety issues. Laborers should be instructed to
coordinate properly while carrying heavy loads. Any injuries should
be attended to complying with emergency procedures.
No mitigation needed.
Issue:
Malfunctioning of the sluice
gate
Intervention:
Improvements to sluice
gate and fence
Impacts on ecological environment:
No significant ecological impact during the construction.
No specific mitigation measures are needed.
Impacts on social environment:
No significant negative impacts during the construction
are envisaged. This activity can be carried out without
negative impacts during water low period of the tank.
No mitigation measures are needed, if the improvements are done
during the rip rap rehabilitation.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 108
Impacts on physical environment:
Lowering of water level is not necessary if the work is
carried out during the rehabilitation of the rip rap),
hence the impact can be considered to be low.
Issue:
Lack of safety in the
periphery of the sluice
Intervention:
Removing Existing barbed
wire fence, Supplying &
fixing new PVC coated GI
wire mesh fence for sluice
including all accessories.
Impacts on ecological environment:
No significant ecological impact during the construction.
No specific mitigation measures are needed.
Impacts on social environment:
No significant negative impacts during the construction
are envisaged. This activity can be carried out without
negative impacts during water low period
No specific mitigation measures are needed.
Impacts on physical environment:
Lowering of water level is not necessary, hence the
impact can be considered to be low
Follow good construction practices.
Issue:
No steps along the D/S
slope to reach the toe area
Intervention:
Construction of new steps
for access to D/S of the
sluice
Impact on Ecological Environment:
No significant ecological impacts during construction is
envisaged
No specific mitigation measures are needed.
Impact on Social Environment:
No significant negative impacts during the construction
are envisaged.
No specific mitigation measures are needed.
Impact on Physical Environment:
No significant impacts during the construction are
Follow mitigation measures list for above impacts for erosion
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 109
envisaged. However, general impacts such as generation
of construction waste, excavated material, wastewater,
generation of noise and vibration and dust which affect
the social and biological environment could be
envisaged. Since the amount of work that has to be
carried out is small, the impact is insignificant.
control.
Follow good construction practices.
Issue:
No Name Board available
Intervention:
Construction of new Name
board with reservoir data
Impact on Ecological Environment:
No significant ecological impacts during construction is
envisaged
No specific mitigation measures are needed.
Impact on Social Environment:
No significant negative impacts during the construction
are envisaged.
No specific mitigation measures are needed.
Impact on Physical Environment:
No significant impacts are envisaged.
No specific mitigation measures are needed.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 110
Table 5.2 Native plant species proposed for rehabilitation of gravel borrow site and other areas
Family Species Local name
Apocynaceae Carissa spinarum Heen Karamba
Boraginaceae Carmona retusa Heen Thambala
Arecaceae Phoenix farinifera Wild date palm
Euphorbiaceae Flueggea leucopyrus Katu Pila
Fabaceae Bauhinia racemosa Maila
Fabaceae Cassia auriculata Ranawara
Fabaceae Cassia fistula Ehala
Fabaceae Tephrosia purpurea Pila
Aristolochiaceae Aristolochia bracteolata Sapsanda
Euphorbiaceae Phyllanthus emblica Nelli
Meliaceae Azadirachta indica Kohomba
Rhamnaceae Ziziphus mauritiana Masan
Rubiaceae Catunaregam spinosa Kukurumanna
Rubiaceae Ixora pavetta Maha Ratambala
Rutaceae Limonia acidissima Divul
Rubiaceae Ixora jucunda Rathmal
Verbenaceae Stachytarpheta jamaicensis Balu Nakuta
Fabaceae Tamarindus indica Siyambala
Lamiaceae Anisomeles indica Kon
Sapotaceae Madhuca longifolia Mi
Sapotaceae Manilkara hexandra Palu
Combrataceae Terminalia arjuna Kumbuk
Combrataceae Terminalia bellirica Bulu
Euphorbiaceae Drypetus sepiaria Weera
5.3 Procurement of material needed for implementing the proposed Interventions
5.3.1 Material Sourcing The proposed interventions for Muthukandiya Reservoir need large amounts of ruble (about 1,015
m3), gravel (about 1,953 m3) and earth (about 3,010 m3), aggregates (about 270 m3) sand (75 m3).
Therefore, significant impacts on geological resources is anticipated at quarry sites and borrow
areas, and therefore the contractors should ensure that sand, aggregates and other quarry material
is sourced from licensed sources.
The contractor is required to maintain the necessary licenses and environmental clearances for all
borrow and quarry material they are sourcing to obtain soil , fine aggregate and coarse aggregate.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 111
Sourcing of any material from protected areas and/or designated natural areas are strictly
prohibited.
If the contractor uses non-commercial burrow/quarry sites, the sites should be remediated
accordingly once material sourcing has been completed. The Project Supervision Engineer will
require maintaining the numbers and relevant details of all necessary licenses etc. and report of
their status accordingly.
5.3.2 Management of Borrow Sites
- Any earth excavated within the project area arising from construction works may be
used as fill material if properties of the soil are suitable for such filling. At Muthukandiya,
the excavated soil can be used for filling if the Engineer finds approves its use.
- The material supplier and/or the contractor shall comply with the environmental
requirements/guidelines issued by the CEA and the respective local authorities with
respect of locating borrow areas and with regard to all operations related to excavation
and transportation of earth from such sites.
- The material supplier and/or the contractor can also find suitable soil/earth materials
from currently operated licensed burrow pits in the surrounding area, subject to
approval of the Engineer
- No borrow-sites be used (current approved) or newly established within areas protected
under FFPO and FO
- Borrow areas shall not be opened without having a valid mining license from the GSMB.
The location, depth of excavation and the extent of the pit or open cut area shall be as
approved by the engineer.
- All borrow pits/areas should be rehabilitated at the end of their use by the contractor in
accordance with the requirements/guidelines issued by the CEA and the respective local
authority.
- Establishment of borrow pits/areas and its operational activities shall not cause any
adverse impact to the near-by properties. Also shall not be a danger of health hazard to
the people.
Contractor shall take all steps necessary to ensure the stability of slopes including those related to
temporary works and burrow pits.
5.3.3 Quarry Operations and Management of Quarry Sites
- Utilizing the existing quarry sites available in the project influential area as much as possible
which are approved by GSMB with valid EPL and Industrial Mining Licenses;
- If new quarries are to be opened, prior approval should be obtained from GSMB, CEA and
local authorities such as Pradeshiya Sabha.
- Selected quarry sites should have proper safety measures such as warnings, safety nets etc.,
and third party insurance cover to protect external parties that may be affected due to
blasting.
- Quarry sites should not be established within protected sites identified under the FFPO and
FO
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 112
- It is recommended not to seek material from quarries that have ongoing disputes with
community.
- The maintenance and rehabilitation of the access roads in the event of damage by the
contractors operations shall be a responsibility of the contractor.
Copies of all relevant licenses should be maintained by the contractor for review and documentation
by the Engineer.
5.4 Safety Issues
Table 5.2. General safety issues that need to be addressed
Public and Worker
Safety
The construction site should be barricaded at all time in a day with adequate
marking, safety tape, flags, reflectors etc. for safety of individuals using the
site daily basis. (Items such as parking cones, lights, tubular markers, orange
and white strips and barricades of a luminous nature for night visibility shall
be procured where deemed necessary).
At all times, the Contractor shall provide safe and convenient passage for
vehicles, pedestrians and livestock. Work that affects the use of existing
accesses shall not be undertaken without providing adequate provisions to
the prior satisfaction of the Engineer.
The construction site should be clearly demarcated by the above means and
restriction of access to public to the site will help the safety of public.
Safety signboards should be displayed at all necessary locations.
The contractor should obtain a Third Party Insurance to compensate any
damages, injuries caused to the public or laborers during the construction
period.
All construction vehicles should be operated by experienced and trained
operators under supervision.
Basic onsite safety training should be conducted for all laborers during the
EMP training prior to the start of the construction activities.
All digging and installation work should be completed in one go, if this task is
not accomplished the area should be isolated using luminous safety tape and
barricading structures surrounding the whole area.
Trenches should be progressively rehabilitated once work is completed.
Material loading and unloading should be done in an area, well away from
traffic and barricaded
Construction wastes should be removed within 24 hours from the site to
ensure public safety.
Safety Gear for
Labors
Protective footwear and protective goggles should be provided to all workers
employed on mixing of materials like cement, concrete etc.
Welder's protective eye-shields shall be provided to workers who are
engaged in welding works.
Earplugs shall be provided to workers exposed to loud noise, and workers
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 113
working in crushing, compaction, or concrete mixing operation.
The contractor shall supply all necessary safety appliances such as safety
goggles, helmets, safety belts, ear plugs, mask etc. to workers and staffs.
In addition, the contractor shall maintained in stock at the site office, gloves,
ear muffs, goggles, dust masks, safety harness and any other equipment
considered necessary.
A safety inspection checklist should be prepared taking into consideration
what the workers are supposed to be wearing and monitored on a monthly
basis and recorded.
Prevention of
accidents
Prevention of accidents involving human beings, animals or vehicles falling or
accidents due to open trenches/manholes during construction period. This
needs to be ensured with proper barricading, signage boards and lighting etc.
A readily available first aid unit including an adequate supply of sterilized
dressing materials and appliances should be available at the site office at all
times
Availability of suitable transport at all times to take injured or sick person(s)
to the nearest hospital should also be insured.
Names and contact information for emergency services such as Ambulance
services, hospitals, police and the fire brigade should be prepared as a sign
board and displayed at the work site.
5.5 Operation of Labour Camps
The following aspects are important to follow when constructing of labor camps
The location, layout and basic facility provision of labor camp must be submitted to
Engineer prior to their construction.
The construction will commence only upon the written approval of the Engineer.
The contractor shall maintain necessary living accommodation and ancillary facilities
in functional and hygienic manner and as approved by the Engineer.
All temporary accommodation must be constructed and maintained in such a
fashion that uncontaminated water is available for drinking, cooking and washing.
The sewage system for the camp must be planned and implemented with
concurrence from the Local Public Health Officer (PHI)
Adequate health care is to be provided for the work force. The layout of the
construction camp and details of the facilities provided should be prepared and shall
be approved by the engineer.
Labor camp sites after use should be cleared and the site should be reinstated to
previous condition at the close of the construction work.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 114
The following aspects have to be looked into when operating labor camps.
The Contractor shall construct and maintain all labor accommodation in such a
fashion that uncontaminated water is available for drinking, cooking and washing.
Supply of sufficient quantity of potable water (as per SLS) in every workplace/labor
camp site at suitable and easily accessible places and regular maintenance of such
facilities.
The sewage system for the camp are designed, built and operated in such a fashion
that no health hazards occurs and no pollution to the air, ground water or adjacent
water courses take place. Ensure adequate water supply is to be provided in all
toilets and urinals.
The contractor shall provide garbage bins in the camps and ensure that these are
regularly emptied and disposed of in a hygienic manner
5.6 Implementation procedures of proposed mitigation
The specific mitigation measures given in the Table 5.1 should be implemented by the
contractor when each and every intervention is done. In addition to the specific measures,
the contractor must adhere to the civil engineering best practices as practical as possible.
Most of such practices are described in ICTAD specifications and the contractor is
recommended to follow them when appropriate.
Time of the implementation of mitigation measures should be decided by the contractor
and they should be informed to the Project Engineer in advance and his approval should be
obtained. The key performing indicators (KPIs) for every mitigation measure carried out
must be worked out and should be informed to the PM for subsequent checks and
balances. Once the KPIs are accepted such indicators should be monitored by the PM to
ensure that measures are taken to minimize or avoid environmental degradation or
pollution that is very likely due to the said project.
It should be necessary that all mitigation measures mentioned in the report be
implemented by the contractor and for such implementation budgetary allocation must be
set aside. It has to be done during the bidding process and the allocation so kept must be
utilized by the contractor in an efficient manner.
Implementation responsibility: for all tasks identified below fall under the purview of the
contractor. The contractor is contractually bound to implement the activities outlined in the
EMP during the implementation of the physical works outlined in the work plan
Supervision responsibility: The Project Proponent, i.e. the project engineer, technical
officers of the respective project management units and Dam safety PMUs environmental
unit will be responsible for the monitoring of all activities and reporting on compliance of
implementation as well as providing technical guidance to the contractor and staff on
ensuring field level implementation is achieved in a satisfactory manner.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 115
5.7 Information Disclosure among Stakeholders
Discussions should be conducted with the residents who reside around the
immediate vicinity of the construction site; provide them with information on the
project activities muster their views for possible impact mitigation as this will also
ensure a good rapport and fewer complaints. This should be done immediately once
the contractor is mobilized.
The contractor will maintain a log of any grievances/complains and actions taken to
resolve them.
A copy of the EMP should be available at all times at the project supervision office
on site.
5.8 Post-construction activities
Clearing/Closure of Construction Site/Labor Camps
Site restoration plans have to be formulated for approval by the engineer. The plan
is to be implemented by the contractor prior to demobilization. This includes borrow
sites and storage yards as well.
On completion of the works, all temporary structures will be cleared away, all
rubbish cleared, excreta or other disposal pits or trenches filled in and effectively
sealed off and the site left clean and tidy, at the contractor’s expenses, to the entire
satisfaction of the engineer.
Environmental Enhancement/Landscaping
Landscape plantation, including turfing of bund walls, re-vegetation of
embankments and other slopes, edge treatment of water bodies shall be taken up as
per either detailed design or typical design guidelines given as part of the Bid
Documents.
The contactor also shall remove all debris, piles of unwanted earth, spoil material,
away from the dam site and from other work places and disposed at locations
designated or acceptable to the Engineer.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 116
5.8 Formal clearances and approval needed
Table 5.2 gives the details of the clearances and approvals for the project
Table 5.2: Formal clearances and approval needed
No Issues / Activity / Intervention needing the permit or approval
The Reasons for the Approval (Law, act or enforcements etc.)
Authority from which permit or approval or Clarence is required
Prior Approval and Acts
1 National Environmental Protection and Quality Regulations under Extraordinary Gazette notification No. 1534/18 and No. 1533/16 of 2008 under NEA section 32 & 23A, 23B
Environmental Protection License (EPL) from CEA, in particular prescribed activities in gazette No. 1533/16 of 2008 (i.e., Concrete batching plants, treatment plants, sewerage networks, mechanized mining activities etc.) is required during construction period and license need to be obtained to collect, transport, store, recover, recycle or dispose waste or establish any site or facility for the disposal of any waste during the construction and operation period.
CEA and The Local Authority Environmental Protection License (EPL) from CEA/ Divisional Secretariat - Siyambalanduwa and Madulla for identifying waste dumping sites /Local Authority for waste collection and to issue machinery permits
2 Mines & Minerals Act No. 33 of 1992
The Act regulates the process of approval required for exploration, mining, trading and transport of geological material (sand, earth, gravel, metal etc.)
Geological Survey and Mines Bureau Industrial Mining License (IML) from Geological Survey and Mines Bureau
Note: Refer Section 1.1.2: Environmental Assessment Requirements for further details on The World Bank Requirements, and National Environmental Legislation framework relevant to this Project.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 117
5.9 Procedures for Dealing with Chance Finds
5.9.1 Chance found Flora and Fauna
The contractor will take reasonable precaution to prevent workmen or any other
persons from removing and damaging any flora (plant/vegetation) and fauna
(animal) including fishing in any water body and hunting of any animal.
If any wild animal is found near the construction site at any point of time, the
contractor will immediately upon discovery thereof acquaint the Engineer and carry
out the Engineer's instructions for dealing with the same.
The Engineer will report to the nearby Forest Department /Department of Wildlife
Conservation (range office or divisional office) and will take appropriate steps/
measures, if required in consultation with the forest officials.
5.9.2 Chance found Archaeological Property
All fossils, coins, articles of value of antiquity, structures and other remains or things
of geological or archaeological interest discovered on the site shall be the property
of the Government and shall be dealt with as per provisions of the relevant
legislation.
The contractor will take reasonable precautions to prevent his workmen or any
other persons from removing and damaging any such article or thing. He will,
immediately upon discovery thereof and before removal acquaint the Engineer of
such discovery and carry out the instructions for dealing with the same, waiting
which all work shall be stopped.
The Engineer will seek direction from the Archaeological Department of Sri Lanka
and inform the project EO to follow the Chance Find Procedures set forth.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 118
6. MONITORING PLAN
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 119
6.1 Environmental compliance and monitoring
Environmental monitoring is required in order to make sure that the anticipated adverse
impacts are kept minimal with the implementation of mitigation measures as and when
required. The monitoring objectives are therefore focused on the mitigation of likely impacts.
In addition, compliance with the existing regulations and legislation is also guaranteed. Table
6.1 enumerates the summary of monitoring plan (MP) required for the entire project.
The monitoring will be required to record the stakeholder complaints/concerns to the delays of
the contractors on completing the riprap rehabilitation, sluice gates repairs of the tank. The
Dam safety project’s PMU has comprehensive monitoring mechanism on the contractors
progress on the construction contract packages offered to them but specific monitoring will be
required to verify the implementation of mitigatory measures recommended in this EA report.
The most required mitigatory measure is contractors’ performance to complete the critical
work that need to be completed during water low period of the tank.
The irrigation department should take the overall responsibility for mitigating the negative
impacts during the construction period. The recommended mitigatory measures need to be
implemented through a committee established at irrigation scheme level with the participation
of representatives from other relevant stakeholder agencies. The members of this committee
should be comprised with the following member.
Irrigation engineer and engineering assistant of Monaragala irrigation scheme
Project Manager and Institutional Development Officer of IMD of Muthukandiya
Scheme
Divisional secretaries of Siyambalanduwa and Madulla DS divisions
Grama Niladharis of Muthukandiya, Uakkadurawe, Manabarana, Siyambalanduwa,
Wijithapura, Barawaya, MariArawe and Alugalge divisions
Presidents of Muthukandiya Ekamuthu, Muthukandiya Gamunu, Yakkadurawe
Ranamayura, Manabarana Siri Parakum, Siyambalanduwa Eksath, Wijithapura Sri
Wijitha FOs
Representatives of PMU and CEA
This committee can meet just before the commencement of construction work and discuss
about the plans for meeting to monitor the process of mitigatory measures implementation.
After their first meeting the committee can meet when need arises. The Engineering Assistant
of Monaragala Divisional Irrigation Department scheme can act as conveyer of the committee
meetings.
This system can be used for the monitoring of the proposed dam safety activities and the
Project committee (PMC) will be attended by the representatives of PMU of Dam safety
project and contractors as new participants.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 120
Table 6.1: Summary of monitoring requirement
Specific intervention
Monitoring Parameters
Monitoring Frequency
Total Time Period Months
Responsible
Institution/ person for implementation
Responsible Key Persons for supervision
Framework of the Institutional Arrangement to incorporate the Findings of MP to Project implementation
Rehabilitation of Rip rap and other damages on the upstream of the tank bund
Improvements to the spill access road
Rehabilitation of the spill basin
Turbidity in the working section of the tank
When such incidents occur
During the whole activity
Contractor
Project Manager or his nominee
PM to inform the contractor of the monitoring and the contractor to submit the reports as agreed;
Reports to be submitted to the Project Office (PO) and then the reports to be evaluated by the World Bank (WB) and PO for approval.
Airborne dust
(along haulage routes)
When complaints are received or dust found in dwelling units
During the whole intervention
Contractor Project Manager or his nominee
Stock piling plan At the beginning of the intervention
During the whole intervention
Contractor Project Manager or his nominee
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 121
Material haulage from borrow areas
Noise levels
Vibration levels
Airborne dust levels
Presence of invasive species
When a complaint is received
When a complaint is received
When a complaint is received
One in 10 vehicles of borrow martials brought in to the site
During the material transport
During the material transport
During the material transport
During the material transport
Contractor
Contractor
Contractor
Contractor
Project Manager or his nominee
Project Manager or his nominee
Project Manager or his nominee
Project Manager or his nominee
As mentioned above
As mentioned above
As mentioned above
As mentioned above
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 122
7. Cost Estimation for Environmental Management Plan
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 123
7.1 Cost Estimate of Environmental Management Plan
General costs to be incurred in implementing the EMP is given in Table 7.1
Table 7.1: Cost Estimate of EMP
Issue Mitigation Details of Costing Itemized Cost
Activities such as material
transport, soil stockpiling,
etc. may result in air
pollution through airborne
dust. If there are dwelling
units along haulage routes
there may be a minor
temporary adverse impact
during this period.
Dust emission due to
transport operations
should be controlled by
wet spraying and
tarpaulin covering in
mandatory on
trucks/lorries which are
used for transporting
materials particularly in
built up areas.
Sprinkling of water has
to be carried out using
bowsers, or tractors
where there are
dwelling unit only when
necessary.
Lorries and trucks should
be covered (with
tarpaulin sheets) when
transporting earth and
gravel.
Sprinkling of water:
- Bowser: Rs. 5,000
- 6,000 per
bowser
- Tractor: Rs. 2,500
– 3,000 per tractor
Covering with
tarpaulin sheets:
Rs. 200 - 250/m2
Health and sanitation of
worker’s camps and that
of residents in the
adjoining areas:
The temporary camps if
not managed properly
may create an unhealthy
environment causing
health hazards to both
workers and nearby
residents.
(see section 5.4)
Proper sanitation
facilities should be
provided on-site for the
workforce. Ideally, this
can be a pit latrine in
which the pit is located
above the ground water
table. Covering the
deposit (with earth or
sawdust) is necessary to
prevent smells and to
discourage flies.
Costs involved in
providing pit latrines
Cost in providing
provisions for proper
waste management
Rs. 15,000 – 20,000
Nominal costs
Operation of borrow areas
causes
Erosion and slides in
borrowing areas occurring
in hillocks would lead to
loss of topsoil and
vegetation loss, hence
habitat loss.
Re-establishment of
After borrowing the
slope/gradient of the
area should be graded to
match or blend with the
existing terrain.
Plant the area with
native trees and water
regularly
The costs that may incur
involve grading of
borrow pit edges
Cost of construction
depends on the
scale of the borrow
pit.
The cost of the
rehabilitation of the
borrowing area
with turfing will be
Rs. 500 per 1 m2.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 124
Issue Mitigation Details of Costing Itemized Cost
vegetation would be
hindered due to loss of
fertile soil
Any borrow pits on the
tank bed also should be
graded properly.
Replanting/
rehabilitation of
habitats (e.g. in
borrow sites) need
a budget of
Rs. 400,000 /ha for
replanting.
Safety of Workers and
Public
(as outlined in Table 5.2)
Provision of proper
safety equipment, safety
gear, taking precautions
and preventive measures
etc. as outlined in Table
5.2
Safety gear, appliances
and equipment, signage
and warning signs, third
party insurance and
worker liability
insurance, cost of
training provided to
workers
Nominal sums to be
included in the
engineering
estimates to be
borne by the
Contractor
Closure of Construction
Site/Labor Camps
Environmental
Enhancement/Landscaping
Site restoration plans
have to be formulated
for the construction site
All temporary structures
shall be cleared away, all
rubbish cleared, excreta
or other disposal pits or
trenches filled in and
effectively sealed off and
the site left clean and
tidy.
Remove all debris, piles
of unwanted earth, spoil
material and disposed at
designated locations.
Landscape plantation,
including turfing of bund
walls, re-vegetation of
embankments and other
slopes, etc.
Nominal sums to be
included in the
engineering
estimates to be
borne by the
Contractor.
Nominal sums to be
included in the
engineering
estimates to be
borne by the
Contractor.
Rs. 40/m2 for
turfing
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 125
Major issues that need mitigation and the related costs are provided in Table 7.1. Most of the
mitigation measures are related to good construction practices and related mitigation costs for
most of the items are embedded in the Engineering Cost Items. However, if the following items
are not directly given under the Engineering Cost, the construction contractor should make
necessary provisions to undertake the relevant items and costs should be included in
contractor’s rates.
Salary for officer to monitor environmental management plan implementation (as
provided in Table 6.1)
Costs for environmental monitoring for specific interventions and measuring
parameters as stipulated in project specific environmental assessment (See Table 5.1
and 6.1)
Miscellaneous fees for the organizations involving in monitoring activities.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 126
8. Conclusions and Recommendations
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 127
8.1 Conclusions
The proposed interventions for the repair work of the rehabilitation of the rip rap and other
damages on the upstream of the tank bund, Improvements to the spill basin and spill access
road and repairs to the damaged locations of the tank bund road are the proposed major
construction activities.
Removal and disposal of debris and excavated material, and increasing the possibilities of
erosion can deteriorate water quality of surface water bodies. Hindrance to vehicular
movements, damage to the crest road surface due to movement of heavy vehicles, temporary
storage of earth along the crest road and elsewhere, impacts due to parking of vehicles and
machinery have to be monitored closely. Noise and vibration and dust generation also can
occur due to large-scale construction using heavy machinery.
The Muthukandiya tank project area can be categorized mainly as having human-influenced-
habitats. This is amply reflected by the habitats and species assemblages recorded during the
survey. The areas identified for project interventions do not contain any critical habitats or
restricted or endangered species. The main impact anticipated in these habitats includes the
habitat degradation, fragmentation and loss of habitat. There will not be a total loss of habitat
for any animal or plant species in the project area. Therefore, habitat or species specific
mitigatory measures are not required. No specific migratory paths or routes were identified
within the project area. The proposed development will not have an impact on migratory birds.
The proposed project will not impair animal movements in the project area, and it will not have
a significant impact on any known critical animal migration paths.
The rip rap rehabilitation in the Dam are the sensitive work items from the social impact point
of view. Low water levels will be a requirement to complete these activities. The water level in
the tank goes down for short period just after the Yala harvesting. This is the period to be used
for the completion of these sensitive construction activities proposed.
The farmers should be given firm and highly committed promise to complete the riprap rehabilitation work just after completion of 2017 Yala season. If so, there will be no need to forgo any cultivation season. Farmers are prepared to tolerate even significant loss to them to get this riprap rehabilitated. They are very particular to get head work of their irrigation scheme improved under the dam safety project.
The irrigation department should use this opportunity as strength of the proposed project and implement proposed development interventions within the planned period. The construction material should be mobilized during early stage of the construction schedule and store them in close proximity to the riprap rehabilitation site to use them quite efficiently.
If the contractors fail to complete the sensitive work items during the short dry spell in which
water level is naturally low there will be negative implications on seasonal agriculture in the
scheme. Therefore, this crucial issue should be considered as most priority activity to be
monitored by PMU and also the Irrigation Department through its existing joint management
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 128
committee system (UMCs, BMC and PMC) where farmer representatives and agency officers
sit together to discuss the problems in their irrigation scheme in every month.
Other interventions are accepted and the project can go ahead without any specific
environmental mitigation measures. Nevertheless, best practices listed on the EMP should be
practiced as practical as possible. ICTAD specifications on civil engineering practices must be
followed as and when applicable.
All the borrow sites need better managements in order to avoid or minimize pollution potential
and best practices for managing sites should be adopted.
The proposed project will therefore be carried out together with the implementation of
mitigation measures stated in this report.
8.2 Recommendations
The project area is situated in the dry zone of the country. Compared to the wet zone habitats
the dry zone does not support critical elements of Sri Lanka’s biodiversity such as endemic and
threatened species as was observed during the field study. The habitats present in the project
site are highly degraded. The majority of habitats and species that are affected by the proposed
project are found commonly throughout the dry zone and therefore the overall impact is not
significant considering the extent and magnitude of the impact. It is recommended that project
proponent develop and execute an environmental management plan to ensure best practices
during the implementation of the project. It is also recommended that project proponent
undertake to restore the habitats with indigenous species in order to partially compensate for
the loss of habitats due to the implementation of the proposed project. Finally it is
recommended that an appropriate independent monitoring mechanism with relevant funds be
established to ensure that the project proponent complies with the proposed mitigation
measures.
Removal and disposal of debris and excavated material, and increasing the possibilities of
erosion can deteriorate water quality of surface water bodies. Hindrance to vehicular
movements, damage to the crest road surface due to movement of heavy vehicles, temporary
storage of earth along the crest road and elsewhere, impacts due to parking of vehicles and
machinery have to be monitored closely. Noise and vibration and dust generation also can
occur due to large-scale construction using heavy machinery.
Engineering best practices must be recommended to be adopted by the contractor for the
sound engineering work.
Borrow sites must be utilized with a proper rehabilitation and safety plan for the protection of
fauna inhabiting the area. All the borrow/quarry areas should be accepted for material
exploitation only if proper approvals from the relevant authorities are obtained.
When complaints are received from the neighbourhood on the environmental issues,
immediate attention and solutions to such issues are recommended.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 129
The farmers should be given firm and highly committed promise to complete the riprap
rehabilitation work just after completion of 2017 Yala season. If so, there will be no need to
forgo any cultivation season. Farmers are prepared to tolerate even significant loss to them to
get this riprap rehabilitated. They are very particular to get head work of their irrigation
scheme improved under the dam safety project.
The irrigation department should use this opportunity as strength of the proposed project and
implement proposed development interventions within the planned period. The construction
material should be mobilized during early stage of the construction schedule and store them in
close proximity to the riprap rehabilitation site to use them quite efficiently.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 130
References
Bedjanic, M., Conniff, K. and G. de S. Wijeyratne (2007). Gehan’s photo guide; Dragonflies of Sri Lanka. Jetwing Eco Holidays.
CEA (1992). An Environmental Profile of The Moneragala District, Central Environmental Authority, Battaramulla
Cooray, P.G. (1984). An Introduction to Geology of Sri Lanka (Ceylon), National Museums
of Sri Lanka Publication, Colombo.
D’ Abrera, B. (1998). The Butterflies of Ceylon. Wildlife Heritage Trust, Colombo, Sri Lanka.
Das, I. and De Silva, A. (2005). Photographic guide to the Snakes and other Reptiles of Sri Lanka. New Holland Publishers.
Dassanayake, M. D. and Clayton, W. D. (eds.) (1996 ‐ 2000). A Revised Handbook to the Flora of Ceylon, Vols. X – XIV, Oxford & IBH Publishing, New Delhi.
Dassanayake, M. D. and Fosberg, F. R. (eds.) (1980). A Revised Handbook to the Flora of Ceylon, Vol. I, Amerind Publishing, New Delhi.
Dassanayake, M. D. and Fosberg, F. R. (eds.) (1981 ‐ 1991). A Revised Handbook to the Flora of Ceylon, Vols. II ‐ VII, Oxford & IBH Publishing, New Delhi.
Dassanayake, M. D., Clayton, W. D. and Shaffer‐Fehre, M. (eds.) (2006). A Revised Handbook to the Flora of Ceylon, Vols. XV Part A & Part B, Science Publishers, USA.
Dassanayake, M. D., Fosberg, F. R. and Clayton, W. D. (eds.) (1994 ‐ 1995). A Revised Handbook to the Flora of Ceylon, Vols. VIII ‐ IX, Oxford & IBH Publishing, New Delhi.
Goonatilake, W. L. D. P. T. S. (2007) Freshwater Fishers of Sri Lanka (text in Sinhala). Biodiversity Secretariat, Ministry of Environment and Natural Resources, Sri Lanka.
Harrison, J. and Worfolk, T. (2011). A Field Guide to the Birds of Sri Lanka, Oxford University Press Inc, New York, USA.
Kotagama, S. (2004). Mammals in Sri Lanka. Pictorial Pocket Guide – 3. Field Ornithology Group of Sri Lanka. Colombo, Sri Lanka.
Manamendra‐Arachchi, K. and Pethiyagoda, R. (2006). Amphibians of Sri Lanka. (text in Sinhala). Wildlife Heritage Trust of Sri Lanka.
MOE 2012. The National Red List 2012 of Sri Lanka; Conservation Status of the Fauna and Flora. Ministry of Environment, Colombo, Sri Lanka. viii + 476pp
Withanage, N.S., Dayawansa, N.D.K. and R.P. De Silva (2014). Morphometric Analysis of the Gal Oya River Basin Using Spatial Data Derived from GIS, Tropical Agricultural Research Vol. 26 (1): 175– 188.
.
Environmental Assessment for Rehabilitation of Muthukandiya Dam
Page | 131
9. Annexures
Page | 132
Annex 1- List of persons consultant
Date Name Address Position
2016/8/31 S.P.A. Jayathissa District engineers office/ irrigation department , Monaragala
IE
2016/8/31 A.J.M.I Jayasundara District engineers office/ irrigation department , Monaragala
TA
2016/9/1 M. Samantha DS office ,Siyambalanduwa Assistant Planning Director
2016/9/1 D.M.Punchibanda DS office ,Siyambalanduwa Head Quarters GN
2016/9/1 K.M. Wasantha Udayakumara
IMD office, Muthukandiya Institutional Development Officer
2016/9/1 R.M. Piyarathana IMD office, Muthukandiya Institutional Development Officer
2016/9/1 S.Kumari Dissanayake Development officer, Muthukandiya-GN office
Development Officer
2016/9/2 D.M Jayathissa No3, fishery village, Muthukandiya
Former President of Fishery Association
2016/9/2 D.M Chamila Muthumali Fishery village, Kanda Uda Panguwa, Muthukandiya
Community leader
2016/9/2 R.M Rathnayake No 4 Hamlet- Muthukandiya President of Ekamuthu FO
2016/9/2 J.M Nimal Karunathilaka 118, 4th village Muthukandiya Secretary Siri Parakum FO
2016/9/2 T.W. Punchi Banda 3 ala road, 1st village, Muthukandiya
Farmer
2016/9/2 D.M. Muthubanda 1st village, Muthukandiya Farmer
2016/9/2 K.G. Kiriwatte 5th village, Muthukandiya Farmer
2016/9/2 P.Nanda Kumara 6th village, Muthukandiya Farmer
Page | 133
Contact details of responsible officers of Muthukandiya Dam
Name Designation Contact Information
1. Eng. S.P.A. Jayathissa, Divisional Irrigation Engineer
Monaragala
071-8566674
2. Mr. A.J.M.I. Jayasundara Technical Officer
Muthukandiya Dam
Monaragala IE scheme
071-6038095
Page | 134
Annex 2- Details of the cost benefit of an acre of paddy land
Activity Amounts Rs.
Preparation of field bunds (activity 1) 3 x 1,200 3,600
Ploughing 1 acres 8,500
Preparation of field bunds (activity 2) 5 x 1,200 6,000
Seed paddy 40 kg x 100 4,000
sowing 4 x 1,200 4,800
Basel fertilizer 50 kg x 50 2,500
Urea 75 kg x 50 3,750
Fertilizer during Booting period 25 kg x 50 1,250
Weedicides 400 ml 5,000
Application of Weedicides 1 x 1,200 1,200
Insecticides 400 ml 1,200
Application of Insecticides 1 x 1,200 1,200
Harvesting through machinery 1 acres 7,500
Other manual processing of paddy 2 x 1,200 2,400
Transport of production 40 800
Total 53,700
Notes:
Yield of 1 acre = 1 650 kg
Total income = 1,650 kg x Rs. 50 (Rs. 82,500)
Total Expenditure = Rs. 53,700
Net Income = Rs. 28,800 (Rs. 82,500- Rs. 53,700)
Total income of Muthukandiya irrigation scheme = Rs Million 172.9 ( 2,096 acres
command area x Rs. 82,500 - 1 acre total income)