final report - calvin college

141
Team 11: Design Report Anna Groendyk Josh Uitvlugt Amanda Hayes Calvin College Engineering 340 18 May 2011

Upload: others

Post on 11-Feb-2022

2 views

Category:

Documents


0 download

TRANSCRIPT

Team 11: Design Report

Anna Groendyk Josh Uitvlugt

Amanda Hayes Calvin College

Engineering 340 18 May 2011

Acknowledgements

This project would not have been possible without many willing and gracious people

who guided and helped our team throughout the year. Of particular note are:

Dr. David Wunder, Ph.D., Senior Design Advisor. Professor Wunder was a source of

great encouragement and guidance to our team, especially through the early stages of

project definition. Mrs. Navy Chann, Director of GCT. Mrs. Chann was our team’s main contact in

Cambodia, and spent hours helping us to understand GCT’s needs over Skype, despite

the 12-hour time difference. Mr. Roger Lamer, P.E., Industrial Consultant. Mr. Lamer was especially helpful in

giving our team a vision for how to start our floor plan design. Dr. Don Wotring, Ph.D, Soils Instructor. Dr. Wotring took the time to give us a basic

education in pile foundations, material that was several steps beyond the scope of our

class. Dr. Leonard De Rooy, Ph.D., Structural Professor. Professor De Rooy was our

team’s greatest resource in this project. Despite his busy schedule, he consistently

spent hours at a time teaching our team how to design a reinforced concrete building, a

topic that we had barely brushed in previous classes – and all with a smile on his face.

Thank you!

ii | P a g e

Executive Summary The nation of Cambodia is slowly developing into a stable and prosperous part of the

global community. Because of the devastation of the nation's political, educational, and

healthcare systems in recent history, much of the remaining population is young and

poorly educated. The Genesis Community of Transformation (GCT) was created as a

non-profit, Non-Governmental Organization (NGO) by Navy Chann and Ly Chhay to help

educate and improve the lives of Cambodian Citizens. GCT is currently renting office space

in Phnom Penh, but they would like to construct their own building to serve as a new base

of operations.

The Khmer Genesis Project focuses on the design of a nine-story building, which can

be seen in Figure 1 and a basic site plan for the location of GCT’s new office facility.

The building itself is designed with space for offices, hotel-style rooms, meeting rooms,

an assembly hall, a kitchen, a fitness center, a store, and a permanent residence for

GCT’s directors. The site plan for the property includes space for a garden, parking,

access for cars to drive through the site, a small pool, and the building itself. Through

this project, Team 11 has utilized culturally appropriate materials and construction

practices, provided clear and usable feedback to GCT, and designed a structure that

can be trusted. The final product delivered to GCT includes structural, architectural,

and promotional drawings of the building, plans for construction, a cost estimate and bill

of materials for the building and foundation, a proposed general layout of the developed

site, and feasibility-level suggestions for foundation design and management of waste

and drinking water.

iii | P a g e

From square meter estimates, the entire finished building was expected to cost

between 2 and 3.5 million dollars. The cost of materials for structural elements

alone was significantly less, as expected, around $502,000 without block walls and

$684,000 with blocks.

Figure 1: View of Building Design, Rendered in Source™.

iv | P a g e

TABLE OF CONTENTS ACKNOWLEDGEMENTS .................................................................................................................................................................. II

EXECUTIVE SUMMARY ................................................................................................................................................................... II

1. INTRODUCTION ........................................................................................................................................................................... 1

1.1. PROJECT STATEMENT................................................................................................................................................................ 1

1.2. TEAM....................................................................................................................................................................................... 1

1.2.1. Amanda Hayes............................................................................................................................................................ 1

1.2.2. Anna Groendyk ........................................................................................................................................................... 1

1.2.3. Josh Uitvlugt................................................................................................................................................................ 2

2. BACKGROUND ............................................................................................................................................................................. 3

2.1. CAMBODIAN HISTORY............................................................................................................................................................... 3

2.2. CAMBODIA TODAY.................................................................................................................................................................... 4

2.3. WEATHER DATA ....................................................................................................................................................................... 4

2.4. GENESIS COMMUNITY OF TRANSFORMATION ............................................................................................................................ 6

3. PROBL EM DEFINITION ............................................................................................................................................................... 7

4. PROJECT ......................................................................................................................................................................................10

4.1. SCOPE ....................................................................................................................................................................................10

4.2. TIMELINE................................................................................................................................................................................10

4.3. COST......................................................................................................................................................................................12

4.3.1. Design Costs ..............................................................................................................................................................12

4.3.2. Construction Costs ...................................................................................................................................................12

4.3.3. Costs Calculated from Bil l of Materials ................................................................................................................15

5. DESIGN CONSIDERATIONS ......................................................................................................................................................16

5.1. SITE .......................................................................................................................................................................................16

5.1.1. Site History ................................................................................................................................................................16

5.1.2. Topography ...............................................................................................................................................................16

5.1.3. Hydrology ..................................................................................................................................................................16

5.1.4. Soil...............................................................................................................................................................................17

5.2. FLOODING & FLOOD CONTROL OPTIONS .................................................................................................................................19

5.3. BUILDING CODE ......................................................................................................................................................................20

5.4. LOADING FACTORS .................................................................................................................................................................20

5.4.1. Wind load ..................................................................................................................................................................20

v | P a g e

5.4.2. Earthquake Load ......................................................................................................................................................27

5.4.3. Rainfall Load .............................................................................................................................................................29

5.4.4. Dead Loads ................................................................................................................................................................30

5.4.5. Live Load ....................................................................................................................................................................31

5.5. MATERIALS AND BUILDING STYLE ............................................................................................................................................31

5.5.1. Building Material......................................................................................................................................................31

5.5.2. Traditional Building Styles ......................................................................................................................................31

5.5.3. Alternate Building Materials ..................................................................................................................................32

5.5.4. Deep Foundations ....................................................................................................................................................33

6. DESIGN NORMS.........................................................................................................................................................................35

6.1. CULTURAL APPROPRIATENESS .................................................................................................................................................35

6.2. STEWARDSHIP ........................................................................................................................................................................35

6.3. INTEGRITY ..............................................................................................................................................................................36

6.4. TRUST ....................................................................................................................................................................................36

7. ALTERNATIVE SOL UTIONS.......................................................................................................................................................37

8. DESIGN ........................................................................................................................................................................................38

8.1. DESIGN MODELING ................................................................................................................................................................38

8.1.1. STAAD.Pro..................................................................................................................................................................38

8.1.2. Model Verification....................................................................................................................................................39

8.1.3. Cracked Element Analysis .......................................................................................................................................40

8.1.4. Source™ Modeling....................................................................................................................................................41

8.2. BEAM DESIGN ........................................................................................................................................................................42

8.3. COLUMN DESIGN....................................................................................................................................................................48

8.4. SLAB DESIGN ..........................................................................................................................................................................52

8.5. SHEAR WALL DESIGN..............................................................................................................................................................54

8 .6. MECHANICAL.........................................................................................................................................................................56

8.6.1. Plumbing ....................................................................................................................................................................56

8.6.2. Air Conditioning ........................................................................................................................................................56

8.7. PARKING DESIGN ....................................................................................................................................................................57

9. SUGGESTIONS ............................................................................................................................................................................59

9.1. FOUNDATION COST ESTIMATION.............................................................................................................................................59

9.2. DRINKING WATER ..................................................................................................................................................................60

9.2.1. Current Condition/Quality Needed .......................................................................................................................60

vi | P a g e

9.2.2. Current/Future Water Use......................................................................................................................................62

9.2.3. GCT Drinking Water Possibilities/Alternatives ....................................................................................................62

9.3. WASTEWATER ........................................................................................................................................................................64

9.3.1. Current/Future Water Use......................................................................................................................................64

9.3.2. GCT Sewage Possibilities/Alternatives .................................................................................................................64

9.3.3. Sewage Trench/Trench Control Options ..............................................................................................................65

9.4. UTILITIES ................................................................................................................................................................................65

9.4.1. Electricity ...................................................................................................................................................................65

9.4.2. City Water..................................................................................................................................................................65

9.4.3. City Sanitary Sewer ..................................................................................................................................................65

9.4.4. Gas ..............................................................................................................................................................................65

10. CONCLUSION AND RECOMMENDATIONS .........................................................................................................................66

10.1. CONCLUSION........................................................................................................................................................................66

10.2. RECOMMENDATIONS FOR FURTHER DESIGN ..........................................................................................................................66

APPENDIX A – REFERENCES.........................................................................................................................................................68

APPENDIX B – COST ESTIMATES.................................................................................................................................................72

APPENDIX C – DETAILED CALCULATIONS .................................................................................................................................83

C.1. LOAD CALCULATIONS..............................................................................................................................................................83

C.1.1. Wind Calculations ....................................................................................................................................................83

C.1.2. Seismic Loads ............................................................................................................................................................84

C.1.3. Dead Load Calculations...........................................................................................................................................85

C.1.4 Live Load Calculations ..............................................................................................................................................86

C.2. BEAM DESIGN ........................................................................................................................................................................87

C.2.1 Metric Concrete Excel Design Program Calculations ..........................................................................................87

C.2.2. Stirrup Calculations..................................................................................................................................................89

C.2.3. Whitney Stress Block Method ................................................................................................................................90

C.2.4. Hand Calculations ....................................................................................................................................................98

C.3. COLUMN DESIGN .................................................................................................................................................................109

C.3.1 Column Ties ..............................................................................................................................................................116

C.4. SHEAR WALL REINFORCEMENT .............................................................................................................................................117

C.5. WATER USAGE ESTIMATES ...................................................................................................................................................119

C.6. CAISSON FOUNDATION COST-ESTIMATE CALCULATIONS ........................................................................................................126

vii | P a g e

LIST OF TABLES

TABLE 1: ABBREVIATIONS USED IN REPORT .............................................................................................X TABLE 2: SUMMARY OF CAMBODIAN STATISTICS .....................................................................................4 TABLE 3: THE DAILY AVERAGE TEMPERATURES (°C).................................................................................5 TABLE 4: THE RECORD HIGH AND LOW TEMPERATURES ............................................................................5 TABLE 5: THE DAILY AVERAGE HUMIDITY ................................................................................................5 TABLE 6: THE DAILY WIND DATA FOR PHNOM PENH, CAMBODIA .................................................................5 TABLE 7: THE AVERAGE NUMBER OF PRECIPITATION EVENTS IN PHNOM PENH..............................................5 TABLE 8: PROJECT TASKS FOR FIRST AND SECOND SEMESTER.................................................................11 TABLE 9: ESTIMATION OF FEE AN ENGINEERING CONSULTATION FIRM WOULD CHARGE FOR THIS PROJECT. ..12 TABLE 10: PROJECT COST CALCULATION FROM GCT’S COST-PER-SQUARE-METER E STIMATION. ....................14 TABLE 11: BUILDING COST ESTIMATION BASED ON BUILDINGS IN PHNOM PENH ............................................14 TABLE 12: CALCULATION SUMMARY OF CONCRETE AND STEEL COSTS ......................................................15 TABLE 13: TOTAL STRUCTURAL AND BLOCK WALL MATERIAL COSTS........................................................15 TABLE 14: CAMBODIAN RAINFALL ........................................................................................................16 TABLE 15: WIND LOADS I N MODEL .......................................................................................................24 TABLE 16: WIND LOAD MINI-CASE MULTIPLIER FOR STAAD MODEL .........................................................26 TABLE 17: ASCE 7 TABLE 11.6-1 SEISMIC DESIGN CATEGORY BASED ON SHORT PERIOD RESPONSE

ACCELERATION PARAMETER ........................................................................................................27 TABLE 18: ASCE 7 TABLE 11.4-1 SITE COEFFICIENT ..............................................................................28 TABLE 19: ASCE 7 TABLE 20.3-1 SITE CLASSIFICATION .................................................................29 TABLE 20: DEAD LOADS .....................................................................................................................30 TABLE 21: LIVE LOADS .......................................................................................................................31 TABLE 22: THE TYPICAL SLUMP FOR VARIOUS PILE TYPES ......................................................................33 TABLE 23: THE TYPICAL MENARD PRESSURE-METER VALUES FOR VARIOUS SOIL TYPES .............................34 TABLE 24: CALCULATED A ND ALLOWABLE MAXIMUM DEFLECTION BY FLOOR .............................................40 TABLE 25A: LIST OF BEAM SIZES AND STRENGTHS .................................................................................44 TABLE 26: DEVELOPMENT LENGTH FACTORS FOR VARIOUS BAR CONDITIONS ............................................47 TABLE 27: COLUMN PLACEMENT: FOUR CUT VIEWS NORMAL TO X-AXIS....................................................49 TABLE 28: COLUMN DESIGN DETAILS....................................................................................................51 TABLE 29: COLUMN TIE DESIGN ...........................................................................................................51 TABLE 30: SPACING FOR SHEAR WALL REINFORCEMENT .........................................................................55 TABLE 31: THE RESULTS OF PARKING NEEDS INVESTIGATION...................................................................58 TABLE 32: CAISSON PLACEMENT BASED ON SOIL COMPRESSION STRENGTH [KN] ......................................59 TABLE 33: CAISSON DESIGN DETAILS ...................................................................................................60 TABLE 34: FUTURE WATER USE PROJECTIONS. ......................................................................................62 TABLE 35: OPTIONS FOR GCT’S DRINKING WATER TREATMENT ...............................................................63

viii | P a g e

TABLE 36: SUMMARY FOR THE FIRST METHOD OF TOTAL COST ESTIMATION ...............................................72 TABLE 37: CONSUMER PRICE INDEX......................................................................................................72 TABLE 38: CALCULATIONS OF CONSTRUCTION COST INDEXES ..................................................................73 TABLE 39: PURCHASING POWER PARITY INDEX FOR CAMBODIA ................................................................73 TABLE 40: COST OF CONCRETE FOR BEAMS ..........................................................................................74 TABLE 41A: LENGTH OF LONGITUDNAL REINFORCING STEEL FOR BEAMS ...................................................75 TABLE 42: COST OF LONGITUDNAL REINFORCING STEEL FOR BEAMS ........................................................76 TABLE 43: COST OF STIRRUPS; THE SHEAR REINFORCING FOR BEAMS .....................................................76 TABLE 44: APPROXIMATION OF THE COST AND NUMBER OF BLOCKS NEEDED FOR WALLS...........................77 TABLE 45: COST OF CONCRETE FOR COLUMNS ......................................................................................78 TABLE 46: COST OF LONGITUDNAL REINFORCING STEEL FOR COLUMNS ....................................................79 TABLE 47: COST OF TIES; THE SHEAR REINFORCING FOR COLUMNS .........................................................79 TABLE 48: COST OF CONCRETE FOR SHEAR WALLS................................................................................80 TABLE 49: COST OF THE STEEL REINFORCING FOR SHEAR WALLS ............................................................80 TABLE 50: COST OF CONCRETE FOR T HE SLAB.......................................................................................81 TABLE 51: COST OF THE STEEL REINFORCING FOR THE SLAB ...................................................................81 TABLE 52: COST OF CONCRETE FOR T HE ELEVATOR PLATFORM ...............................................................82 TABLE 53: COST OF CONCRETE FOR T HE STAIRS ....................................................................................82 TABLE 54: DEAD LOAD CALCULATIONS .................................................................................................85 TABLE 55: LIVE LOAD CALCULATIONS ..................................................................................................86 TABLE 58: CALCULATING TIE BAR SIZE REQUIREM ENTS ........................................................................ 116 TABLE 59: CALCULATING TIE SPACING REQUIREMENTS ......................................................................... 116 TABLE 60: TOTAL FIXTURES FOR BUILDING, BY LEVEL .......................................................................... 119 TABLE 60: DRAINAGE PIPE SIZE REQUIRED FOR ALL FIXTURES ON STACK 1 ............................................. 120 TABLE 62: DRAINAGE PIPE SIZE REQUIRED FOR ALL FIXTURES ON STACK 2 ............................................. 123

ix | P a g e

TABLE O F FIGURES

FIGURE 1: VIEW O F BUILDING DESIGN, RENDERED IN SOURCE™. ............................................................... III FIGURE 2: GCT'S PROPERTY IN PHNOM PENH, MARKED WITH THE PURPLE PIN.. ...........................................8 FIGURE 3: ARIAL VIEW O F GCT'S LAND. CORNERS OF THE PROPERTY ARE MARKED WITH BLUE PINS .............8 FIGURE 4: TONLE SAP FLOODPLAIN ......................................................................................................17 FIGURE 5: LOCATION OF BUILDING SITE O N MAP OF SOIL TYPES OF PHNOM PENH, CAMBODIA ......................18 FIGURE 6: DESIGN WIND PRESSURE ACTING ON EXTERIOR OF BUILDING BY ELEVATION ...............................22 FIGURE 7:TRIBUTARY AREA CASE O F EACH NODE FOR T HE WIND LOADS WITH BUILDING IN SIDE-VIEW ..........23 FIGURE 8: ORIENTATION OF WIND LOAD MINI-CASES F OR STAAD.PRO MODEL ..........................................25 FIGURE 9: APARTMENT COMPLEX IN PHNOM PENH FEATURING WRAP-AROUND BALCONY ............................31 FIGURE 10: RENDERING OF INTERIOR OF SOURCE™ MODEL .....................................................................41 FIGURE 11: LENGTH GUIDE FOR TABLE 25. ............................................................................................45 FIGURE 12: BEAM SIZE SCHEMATIC FOR LEVELS 1-8 ...............................................................................45 FIGURE 13: BEAM SIZE SCHEMATIC FOR LEVEL 9....................................................................................45 FIGURE 14: METHOD FOR DETERMINING INFLECTION POINTS ....................................................................46 FIGURE 15: MOMENT (MN) VS. AXIAL FORCE (PN) CURVES FOR COLUMNS .................................................50 FIGURE 16: LOCATION OF SHEAR WALLS...............................................................................................54 FIGURE 17: RDI CERAMIC FILTRATION ..................................................................................................61 FIGURE 18: FIGURE D-1 FO USGS "DOCUMENTATION FOR THE SOUTHEAST ASIA SEISMIC HAZARD MAPS" ....84 FIGURE 19: WHITNEY STRESS BLOCK DIAGRAM .....................................................................................91 FIGURE 20: BETA FACTOR FOR BEAMS..................................................................................................91 FIGURE 21: FIRST ITERATION BEAM WIDTH CALCULATOR IN EXCEL (M) ......................................................93 FIGURE 22: DETAILED CALCULATOR FOR BEAM SIZES .............................................................................94 FIGURE 23: B100’S BENDING MOMENT GRAPHS .....................................................................................95 FIGURE 24: B200’S BENDING MOMENT GRAPHS .....................................................................................95 FIGURE 25: B300’S BENDING MOMENT GRAPHS .....................................................................................96 FIGURE 26: B400’S BENDING MOMENT GRAPHS .....................................................................................97 FIGURE 27: B300’S BENDING MOMENT GRAPHS .....................................................................................97 FIGURE 28: MOMENT HAND CALCULATION LAYOUT .................................................................................99 FIGURE 29: COLUMN DESIGN DIMENSIONS ........................................................................................... 109 FIGURE 30: "EXACT COLUMN DESIGN.XLSX" CALCULATIONS.................................................................. 115 FIGURE 31: CALCULATIONS FROM EXCEL DOCUMENT "FOUNDATION DESIGN FOR COST ESTIMATE ONLY.XLSX"

.............................................................................................................................................. 127

x | P a g e

Table 1: Abbreviations Used in Report

Abbreviation DefinitionASCE American Society of Civil EngineersCO Community Organization (process)CPI Consumer Price IndexCRWRC Christian Reformed World Relief CommitteeDOL Department of LaborGCT Genesis Community of TransformationIBC International Building CodeLLC Limited Liability CompanyNGO Non-Government OrganizationPPP Purchasing Power ParityRDI Research Development International

1 | P a g e

1. Introduction

1.1. Project Statement

The Khmer Genesis project focuses on designing a multi-story office building for the

Cambodian non-profit Non-Government Organization (NGO) Genesis Community of

Transformation (GCT). GCT was created by Cambodian national Navy Chan to help

improve the lives of the people of Cambodia by training farmers, improving local

community organization, and providing educational opportunities to people who

would not normally have them. This proposed office bui lding would allow the

organization to expand significantly and greatly increase its ability to serve the

community.

1.2. Team

1.2.1. Amanda Hayes

Amanda Hayes will be graduating from Calvin in the spring of 2011 with a

Bachelor Degree of Science in Engineering and a concentration in the Civil and

Environmental discipline. She spent last summer in Atlanta working for the

Environmental Protection Agency, and the summer before doing engineering

research at Calvin. She grew up in suburban Pittsburgh, but hopes to spend the

rest of her life in the developing world or inner city, whether doing engineering

work, ministry, teaching, or anything else God leads her to. Currently, she is

planning to leave in July for an 11-month volunteer internship with Christian

Reformed World Missions in Cambodia. When she returns, she plans to learn to

be an inner-city physics teacher through the Memphis Teacher Residency.

1.2.2. Anna Groendyk

Anna Groendyk is a senior from Kalamazoo, Michigan. At Calvin, Anna is

pursuing a Bachelor Degree of Science in Engineering with a concentration in

Civil and Environmental Engineering. Last summer, she had an internship under

the City Engineer with the City of St. Joseph, Michigan. After graduating in the

spring of 2011, Anna plans to pursue a career in civil/environmental engineering.

2 | P a g e

1.2.3. Josh Uitvlugt

Josh Uitvlugt is a Grand Rapids resident who will graduate from Calvin in the

spring of 2011 with a Bachelor Degree of Science in Engineering with a Civil and

Environmental concentration. He is also an artist who owns and operates his

own web-comic site, which he continues to update regularly. After graduation,

Josh hopes to pursue a career in civil and environmental engineering.

3 | P a g e

2. Background

2.1. Cambodian History

During the last century, Cambodia was overwhelmed with war and political chaos

that destroyed infrastructure and crippled progress. Since October 1887, Cambodia

was a French protectorate as part of French Indo-China.16 In 1941, France gave

Cambodian nationalist Prince Norodom Sihanouk the throne expecting to manipulate

him because he was only 18 years old. However, Sihanouk became very popular

among the Cambodian people, and in 1953, he petitioned the French government

for independence. Cambodia achieved independence from France on November 9,

1953.9

In 1955, Sihanouk stepped down as King to run for President, for which he was

elected. Sihanouk was very popular politically but he was worried about his country

since bordering countries Vietnam and Laos each were involved in civil wars and

cold war tension was rising in Cambodia. A communist group called the Khmer

Rouge, which means Red Cambodians, was a growing source of resistance to

Sihanouk. In a 1970 coup, Sihanouk’s advisor and Prime Minister Lon Nol removed

Sihanouk from power, leaving Lon Nol as the head of government. Sihanouk went

into exile in China and allied himself with the Khmer Rouge to try to overthrow Lon

Nol’s new government.9

During the next few years, the Khmer Rouge, led by Pol Pot, gained power and

eventually captured Phnom Penh on April 17, 1975. The Khmer Rouge slaughtered

many educated Cambodian people and destroyed many libraries, hospitals, schools,

and cultural sites. In 1978, Vietnam invaded Cambodia to overthrow the Khmer

Rouge. Vietnamese troops took control of Phnom Penh on January 7, 1979.

Vietnam occupied Cambodia for 10 years. The United Nations intervened to help

Cambodia with democratic elections. Sihanouk broke all ties to the Khmer Rouge,

thus ending their regime. In 1991, a UN peace agreement was signed in Paris.9

4 | P a g e

2.2. Cambodia Today

Cambodia’s government is a constitutional monarchy. The current leaders are

Norodom Sihamoni, the King and Head of State; Hun Sen, the Prime Minister and

Head of Government; Chea Sim, the President of the Senate; and Heng Samrin, the

President of National Assembly. Table 2 has some current Cambodian statistics

from the CIA World Factbook.

2.3. Weather Data Table 3 - Table 7 show historical weather data from the Phnom Penh Airport that

was compiled by the Weather Underground.22 These data was collected daily from

January 1, 2001 to November 30, 2010 and these charts show averages as well as

extremes. Temperature data is important for consideration in construction. The

humidity data is important for design when thinking about indoor climate control for

the building as well as concrete curing. The wind data is important for looking at the wind loads on the building. Table 7 contains the average number of precipitation

events which, when compared to the rainfall depth data in Table 14 in Section 5.1.3

shows that the depth of rainfall is proportional to the number of rainfall events over

the course of the year.

Table 2: Summary of Cambodian Statistics.10

5 | P a g e

Table 3: The Daily Average Temperatures (°C) Listed by Month for Phnom Penh, Cambodia22

Table 4: The Record High and Low Temperatures for Each Month from January 2001 to November 2010 22

Table 5: The Daily Average Humidity for Each Month 22

Table 6: The Daily Wind Data for Phnom Penh, Cambodia by Month22

Table 7: The Average Number of Precipitation Events in Phnom Penh22

6 | P a g e

2.4. Genesis Community of Transformation

Genesis Community of Transformation is headed by Navy Chann and her husband

Ly Chhay, Cambodian nationals who grew up during the Khmer Rouge. They

moved to Canada until 1998, when they returned to Cambodia. Navy worked for 10

years for the Christian Reformed World Relief Committee (CRWRC) as the Country

Director for Cambodia. Later she resigned and started her own NGO, GCT, in 2009.

GCT uses the CRWRC’s Community Organization (CO) process, in which they train

a few people in a vi llage to help their vi llage establish a leadership committee,

discover their own resources, and decide how to organize themselves to solve

important issues faced by the villagers. GCT also supports and collaborates with

other NGOs in the area that have similar goals, such as World Hope International,

whose employees were trained by GCT in the CO process. Although the villages

they serve are in the countryside of southern Cambodia, GCT’s offices are located in

Phnom Penh, Cambodia’s capital.17

GCT is distinct from CRWRC in that it is much smaller-scale and works more directly

with villages. GCT has also purchased farmland to use for experimenting with and

demonstrating new agricultural techniques. These techniques show potential for

improving yields and environmental sustainability for small-time farmers in local

villages. Eventually, GCT will bring farmers to their facility to teach them these

techniques. GCT also specifically focuses on education and job training for women

and youth, including education about the effects of environmental health on human

health.17

7 | P a g e

3. Problem Definition GCT is currently renting office space in Phnom Penh. However, they would like to own

their own building to house their offices, a residence for the director, and a variety of

spaces to rent out in order to expand their organization and help more people. GCT

already owns a vacant plot of land where this building could be built. They would also

like to promote the farming methods they teach by planting a vegetable garden and by

selling some of their farmers’ crops through a farmer’s market and restaurant.

GCT desires a bui lding that can house their offices and commercial interests. Their

initial idea was for a building that would be twelve stories high, fifteen meters wide, and

twenty-four meters long. In comparison, other buildings in the area are six stories high

at most, although there are buildings in other areas of Phnom Penh that are much taller

than twelve stories.

This bui lding will need to be built in stages as funding becomes available. GCT hopes

to begin by building the foundation and first two floors. GCT will need drawings of their

future building and other promotional material to raise the funds to bui ld it.

The building will include GCT’s commercial investments: a restaurant, a fitness center,

office space for other NGOs to rent out, a large hall with small breakout rooms for

organizations to rent during conferences, and hotel-style rooms. It will also include

GCT’s offices and the director’s residence. On the site, GCT plans to build a pool with

landscaping around it and a garden. Most of the rest of the land will be used for

parking.

GCT has already purchased a 30-m x 60-m piece of land in Phnom Penh, down the street from GCT’s current rental office building, as seen in Figure 2 and Figure 3. The

land is low in elevation and floods knee-deep during the rainy season. This is especially

a problem because there is an open dirt trench along the side of the property through

which the neighborhood’s sanitary sewage line runs.

8 | P a g e

Figure 2: GCT's Property in Phnom Penh, Marked with the Purple Pin20

Figure 3: Arial View of GCT's Land. Corners of the Property are Marked with

Blue Pins.20

9 | P a g e

The land is low because it used to be a pond. GCT and the previous owners have both

added soil to the land, as much as three or four meters deep. However, the soil has

settled significantly, and the land still floods. The soil type and origin of this soil fi ll is

unknown, as is the soil type beneath the fill and the depth of bedrock.

GCT can connect to the city power grid and water supply. However, water used for

drinking and cooking or washing food must be treated further. GCT is interested in

alternatives to releasing sanitary sewage into the trench along their property.

10 | P a g e

4. Project

4.1. Scope

This project focuses on the design of the building only, involving:

• Identifying an optimal height for the bui lding

• Designing floor plans for each level

• Creating a working model of the concrete design in STAAD.Pro

• Considering site weather, hydrology, and soil type

• Honoring local culture, including architectural style

• Meeting international building standards

• Accommodating plumbing, electrical wiring, and elevator installation

• Estimating an accurate cost of construction

• Creating detailed drawings that a licensed engineer could check and expand

upon, and from which a contractor could build

4.2. Timeline Table 8 shows a schedule of tasks for both semesters of Senior Design Class. In

addition to the due dates required by the class, the schedule includes estimated

completion dates for deadlines set internally by the team.

11 | P a g e

Table 8: Project Tasks for First and Second Semester.

12 | P a g e

4.3. Cost

4.3.1. Design Costs

Since the final product is composed of drawings and computer models, since

STAAD.Pro software, as seen in Section 8.2.1, is available to this team through

Calvin College, and since team members have volunteered their time, this

project’s budget is minimal. Team 11 has budgeted $200 for purchasing

codebooks and other research material, and constructing a physical model of the building. Table 9 gives the results of estimating the equivalent value of time

spent working on the feasibility study and design. A tally of total hours spent on

the project for both semesters came to each team member spending 400 hours

on the project.

4.3.2. Construction Costs

GCT’s building, with nine floors, each dimensioned at 24m x 15m, is a total of

3240-m2. Using this area, rough per-square-meter costs were estimated using

two separate methods and used to estimate total construction costs.

Table 9: Estimation of Fee an Engineering Consultation Firm Would Charge for This Project.

13 | P a g e

In the first method, Means Assemblies37 was used to estimate per-square-foot

US 2009 costs for each floor, which were then summed and converted to SI

units, yielding $3.1 million. Using the Consumer Price Indexes (CPI) for 1992

and 2009, found on the US Department of Labor’s website,42 the estimate was

brought up to a present-day US value of $4.8 million. Then, using a construction

cost index from Turner & Townsend, an average developing countries

construction index and a US construction index were found.19 These were used

to scale the 2009 US estimate to a 2009 Cambodia estimate of $2.5 million.

Purchasing Power Parity (PPP), a measure of the purchasing power was also

used to scale the 2009 US estimate to a 2009 Cambodia estimate, which came

to $1.8 million.14

Error in these calculations is due to the following assumptions in order of least to

most error:

• The DOL’s CPI is essentially the price index for construction. This is

estimated to be at least 15% error from comparing the DOL and MEANS

CPIs for years previous to 1992.

• GCT’s parking garage, fitness center, program space, and hotel rooms are

well represented by Means’ parking garage, gymnasium, high rise offices,

and high rise apartments, respectively.

• For the construction cost index method, that Cambodia’s construction cost

index resembles that of China, Indonesia, India, and South Africa, the

countries whose indexes were averaged to use as Cambodia’s

construction cost index.

• For the PPP method, the basket of prices used to calculate PPP

represents construction costs accurately. It is believed that the actual cost

is within 200% of these cost estimates.

14 | P a g e

The second method for estimating the building cost was by using an estimate

per-square-meter that was given to the director of GCT by a contractor in Phnom

Penh. The estimate given by the contractor is $300/m2 with up to a 30%

variation. This includes both labor and materials. This estimation also has the engineering feasibility study and design cost shown in Table 9 added to it. The

results from cost estimation using the information GCT and a contractor in

Phnom Penh are shown in Table 10.

The third method for estimating per-square-meter costs was to find costs for

similar bui ldings being constructed in Phnom Penh. The results of these

estimates are shown in Table 11.

Between these three methods of cost estimation, the cost of the nine-story-

building design through construction will be between 2 and 3.5 million USD.

Table 11: Building cost estimation based on buildings that have been built recently or are currently being built in Phnom Penh.23,24,33

Table 10: Project cost calculation from GCT’s cost-per-square-meter estimation.

15 | P a g e

4.3.3. Costs Calculated from Bill of Materials

Based on the volumes of steel and concrete used in the structural design described in Section 8 of this report, as well as the cost of these materials in

Phnom Penh, Team 11 has calculated a cost of materials of $684,000, as shown in Table 12 and Table 13.

Table 12: Calculation Summary of Concrete and Steel Costs

Table 13: Total Structural and Block Wall Material Costs

TOTAL VOLUME

CONCRETE (m3)

TOTAL WEIGHT

CONCRETE (tonne)

COST OF CONCRETE

TOTAL LENGTH OF

STEEL (m)

TOTAL VOLUME STEEL

(m3)

TOTAL WEIGHT OF

STEEL (tonne)

COST OF STEEL

SLAB 676.4 1623.4 147,730 75520 5.36 42.3 30,700 PLATFORM 37.4 89.8 8,170 - - - -FOUNDATION 630 1512.0 137,590 - 0.839 6.56 4,760 STAIRS 179.8 431.5 39,270 - - - -BEAMS 145.4 349.0 31,755 22594.4 4.44 34.9 25,325 COLUMNS 114.9 275.8 25,100 8670.6 4.21 33 23,950 SHEAR WALL 126.3 303.1 27,580 2312.3 0.164 1.29 940 SUM 1910.2 4584.5 417,195 109,097.3 15.01 118 85,675

TOTAL COST 502,870

684,120 TOTAL COST WITH BLOCK WALLS

16 | P a g e

5. Design Considerations

5.1. Site

5.1.1. Site History

GCT’s property used to be a pond, which is why the elevation is so much lower

than the surrounding area. Over the course of many years, both GCT and the

property’s previous owner have tried to fill in the land with soil, in total of 2-m to

4-m deep, and they still hope to add another meter. For this reason, the soil on

their property may not be of the expected composition in that area.

5.1.2. Topography

At this time, the area several blocks around the site is low enough to flood

annually, but the site no longer acts as a pond during the rainy season. The

topography of most of Cambodia as a whole is relatively flat - to the extent that it

is possible for one of its main rivers, the Tonle Sap, to completely reverse its

direction of flow for a portion of the year.26

5.1.3. Hydrology

In Cambodia's rainy season, which generally occurs from May to October, the

Tonle Sap River reverses direction and floods the Tonle Sap Lake.6 During this

season, the area of the lake increases by almost 500%, as can be seen in Figure 4 on the next page. The city of Phnom Penh is located just outside of this

floodplain. However, parts of the neighborhood immediately around the site sti ll

flood to a depth of about 0.6-m during the rainy season. Table 14 lists the

average monthly rainfall in Cambodia.26

Table 14: Cambodian Rainfall26

17 | P a g e

5.1.4. Soil

According to the map “Soil Types of Phnom Penh” assembled by Josh Uitvlugt,

the soil in the area of the site is a Gleyi-plinthic Acrisol. This map was

constructed from the GIS file “Soil Map of the Lower Mekong Basin” published by the Mekong River Commission,41 and is shown in Figure 5. A gleyi soil is a type

of hydric soil, meaning that it has been saturated long enough to become

anaerobic, which allows it to store more organic carbon than other soils.18 An

acrisol is a soil with high content of red kaolinite clay.5 Therefore, Team 11

expects the original soil on GCT’s site to be an underconsolidated soil with high

kaolinite clay content and organic matter. This implies that loading the soil will

result in high levels of settlement.

Figure 4: Tonle Sap Floodplain39

18 | P a g e

Figure 5: Location of Building Site on Map of Soil Types of Phnom Penh, Cambodia41

19 | P a g e

The site has been filled, as described in Section 5.1.1, and the soil type of the fill

is unknown. It is unlikely that the filling was done in a controlled manner, by

compacting the soil after every 0.3 meters of soil added. If this type of

compaction was not done, significant settlement will occur over time as the fi ll

soil becomes more compacted, particularly if the fi ll soil is loaded.

Although little is known about the soi l on GCT’s site, it is expected that it will

experience significant amounts of settlement if loaded; therefore, any foundation

design will need to accommodate or limit this settlement.

5.2. Flooding & Flood Control Options

Because of the current hydrologic conditions of the site, the site regularly floods to a

depth of about 0.6-m during Cambodia’s rainy season, which occurs between the

months of May and October.26 The ground floor of the building will consist of

structural columns and serve as space for uses such as motorcycle parking or

hosting a farmers' market. This raises the elevation of the lowest finished floor so

that it will not be damaged by floodwaters during flood conditions.

This space cannot be used for car parking because of the narrow spacing between

columns. This would cause difficulty in placing traffic flows through the building, and

increase the danger of cars hitting and damaging structural components. However,

it may be used for motorcycle and bicycle parking when it is not flooded.

20 | P a g e

While the building site is in the lowest part of the surrounding area, it is possible that

a flood relief channel could be constructed to a nearby stream or pond. Construction

of this channel is not feasible until more information on local hydrology and

topography become available. A dike and pump system could be constructed to

reduce the water level in the site during flood conditions. This option would be

prohibitively expensive and implementation is not likely to occur at any time.

Because raising the first finished floor onto stilts will reduce or eliminate all flood

damage to the building and the difficulties associated with the dike and relief channel

systems, Team 11 recommends that the building be raised on stilts and no other

flood control options be implemented at this time.

5.3. Building code

Cambodia does not yet have a widely recognized standardized building code. To

ensure that the constructed building is safe, the International Building Code1 (IBC)

was used for design. Because the metric system is widely used in Cambodia, the

metric system editions of the IBC and Structural Concrete Building Code from the

American Concrete Institute4 (ACI) were used. To calculate the design loads that

would act on the building, Team 11 used the American Society of Civil Engineers

(ASCE) Minimum Design Loads for Building and Other Structures.28 These codes

provided the necessary strength for the calculated design loads to provide a

structurally sound building. The specific code editions used were ACI 318M-05,

ASCE 7-98 and ASCE 7-05, and IBC 2006.

5.4. Loading Factors

5.4.1. Wind load

Wind loads acting on the structure were calculated according to Chapter 6 of

ASCE 7. The calculations to be described below can be seen in Appendix C.

Section 6.5.10 of ASCE 7 states that the velocity pressure due to wind (qz)

evaluated at height z is found according to Equation 6-13:

𝑞𝑞𝑧𝑧 = 0.613 ∙ 𝐾𝐾𝑧𝑧 ∙ 𝐾𝐾𝑧𝑧𝑧𝑧 ∙ 𝐾𝐾𝑑𝑑 ∙ 𝑉𝑉2 ∙ 𝐼𝐼 (N/m2) (6-13)28

21 | P a g e

where Kd is the wind directionality factor defined in ASCE 7 Section 6.5.4.4, Kz is

the velocity pressure exposure coefficient defined in ASCE 7 Section 6.5.6.4, Kzt

is the topographic factor defined in ASCE 7 Section 6.5.7.2, I is the importance

factor of the building defined in ASCE 7 Section 6.5.5, and V is the basic wind

speed of the area. Wind speeds in Cambodia can be as great as 60m/s, and the

values of Kzt, Kd, and I were found to be 1.0. The value of qz is only used for the

wind load on the windward side; for the leeward and other sides of the buildings,

a value of qh, or the value of qz for z equal to the height of the building, is used.

ASCE 7 Section 6.5.12.2.1 defines the design wind pressure (p) according to

Equation 6-15:

𝑝𝑝 = 𝑞𝑞 ∙ 𝐺𝐺 ∙ 𝐶𝐶𝑝𝑝 − 𝑞𝑞𝑖𝑖(𝐺𝐺 ∙ 𝐶𝐶𝑝𝑝) (N/m2) (6-15)28

Where G is the gust factor defined in ACI Section 6.5.8, Cp is the external

pressure coefficient from ASCE 7 Figure 6-3, and qi is the positive internal

pressure. The value of qi is taken to be equal to qh. A plot of the value of the

design wind pressure for the windward bui lding side can be seen in Figure 6.

The wind loads acting on this structure were applied as point loads to the nodes

at the intersection of the beams and columns assuming that all wind force acting

on the wall would act on the node closest to where the wind met the wall. This

was accomplished by dividing each of the faces of the building by area and

multiplying by the design wind pressure acting in that area. A map of the area

cases for the 24-m side of the building can be seen in Figure 7, and a list of the

base wind loads used in the STAAD model can be seen in Table 15. According

to Figure 6-9 of ASCE 7, the wind load must be modeled using a set of ten load

combinations. In order to accomplish this in STAAD, each of the windward and leeward loads for each wall were divided in half, as can be seen in Figure 8 and

applied the appropriate factors as shown in Table 16.

22 | P a g e

Figure 6: Design Wind Pressure Acting on Exterior of Building by Elevation

23 | P a g e

Figure 7:Tributary Area Case of Each Node for the Wind Loads with Building in Side-View

24 | P a g e

Table 15: Wind Loads in Model

25 | P a g e

Figure 8: Orientation of Wind Load Mini-Cases for STAAD.Pro Model

26 | P a g e

Table 16: Wind Load Mini-Case Multiplier for STAAD Model

27 | P a g e

5.4.2. Earthquake Load

ACI code requires that buildings be constructed to withstand seismic loads in

combination with live and dead loads according to design strength loading cases

9-5 and 9-7 o f ACI Section 9.2. It was determined, however, that these loads

were applied along the same directions as and of lower magnitude than the

factored design wind loads also applied to the structure. Load cases 9-4 and 9-6

are similar to load cases 9-5 and 9-7 respectively except that 9-4 and 9-6 have a

wind load term in place of the earthquake load term. Because of this, the

building can be designed without specific application of separate earthquake

loads in the understanding that any forces or moments generated by design

earthquake loads could be handled by structural elements designed to handle

the wind loads.

Seismic design is divided up into 6 categories, A to F, with A having the lowest

amount of earthquake threat and F having the highest. Table 11.6-1 of ASCE 7

2005 shows a determination of seismic design categories A to D based on the

structure’s occupancy category and sort period response acceleration parameter

SDS. The seismic design category for this project was determined to be design

category A. This table is shown as Table 17 below.

The value of SDS is found using equation 11.4-3 of ASCE 7 Section 11.4.4, where

SMS is the design short period spectral response acceleration. The value of SDS

was found to be 0.05.

𝑆𝑆𝐷𝐷𝑆𝑆 = 23𝑆𝑆𝑀𝑀𝑆𝑆 (11.4-3)28

Table 17: ASCE 7 Table 11.6-128 Seismic Design Category Based on Short Period Response Acceleration Parameter

28 | P a g e

𝑆𝑆𝐷𝐷𝑆𝑆 = 23∙ 0.075

𝑆𝑆𝐷𝐷𝑆𝑆 = 0.05

The value of SMS is found using equation 11.4-1 of ASCE 7 Section 11.4.3,

where Fa is the design site coefficient from Table 11.4-1 of Section 11.4.3, shown

below as Table 18, and SS is the mapped short period spectral response

acceleration. The value of SMS was found to be 0.075 based on an Fa value of

2.5 and an SS value of 0.03, found using Figure D-1 of the United States

Geological Survey document “Documentation for the Southeast Asia Seismic

Hazard Maps”, shown in Appendix C.

𝑆𝑆𝑀𝑀𝑆𝑆 = 𝐹𝐹𝑎𝑎 ∙ 𝑆𝑆𝑆𝑆 (11.4-1)28

𝑆𝑆𝑀𝑀𝑆𝑆 = 2.5 ∙ 0.03

𝑆𝑆𝑀𝑀𝑆𝑆 = 0.075

The site class is determined using Table 20.3-1 in Section 20.3 of ASCE 7,

shown below as Table 19. Although specific data on the soil conditions at the

site are not available, the soil type is assumed to be a soft clay soil with the aid of the soil map in Figure 5.

Table 18: ASCE 7 Table 11.4-128 Site Coefficient, Fa

29 | P a g e

Because the site falls into design category A, it need only be designed to handle

the loads described by Equation 11.7-1 of Section 11.7.2 of ASCE 7, where Fx is

the lateral load applied at story x and wx is the portion of the total dead load D

assigned to level x.

𝐹𝐹𝑥𝑥 = 0.01𝑤𝑤𝑥𝑥 (11.7-1)28

Seismic loads were determined to be 8.93kN per column and 11.16kN per

column applied at each normal floor, acting on the 24-meter and 15-meter faces,

respectively, and 9.58kN per column and 11.97kN per column applied at the roof,

acting on the 24-meter and 15-meter faces, respectively. These loads are almost

universally two orders of magnitude less than the unfactored wind load, which

means that seismic loads can be ignored in the analysis of this structure.

5.4.3. Rainfall Load

Rainfall load is determined according to Equation 8-1 of Section 8.3 of ASCE 7.

𝑅𝑅 = 0.0098(𝑑𝑑𝑠𝑠+ 𝑑𝑑ℎ) (8-1)28

This is an empirical formula with dh representing the depth of water on the

undeflected roof above the inlet of secondary drainage system at design flow

(mm); ds represents the depth on the undeflected roof up to the inlet of the

secondary drainage system when the primary drainage system is blocked (mm);

and R is the rain load (kN/m2).

Table 19: ASCE 7 TABLE 20.3-128 SITE CLASSIFICATION

30 | P a g e

Design of the drainage system of the roof of this structure is beyond the scope of

this project, but the rain load will be 9.8 N/m2 per millimeter of rain depth spread

across the entire roof. Only load cases 9-2 and 9-3 from Section 9.2.1 of ACI

318M-05 use this load, and in both cases, the largest of the roof live load, the

snow load, and the rain load must be used. The roof live load is 4790 N/m2,

which is substantially larger than the rain load for any reasonable depth of

rainfall, so specific determination of the rain load is not necessary for this project.

5.4.4. Dead Loads

Dead load is the weight of the building and anything in the building that will not

move over the building’s lifetime. It was identical between all floors except the

roof, as shown in Table 20. More detailed dead load calculations appear in

Appendix C.

Table 20: Dead Loads

31 | P a g e

5.4.5. Live Load

Live load, the weight of people, furniture, and anything in the building that will

move over the building’s lifetime, was identical between all floors except floor 8,

shown in Table 21. More detailed live load calculations appear in Appendix C.

5.5. Materials and Building Style

5.5.1. Building Material

Concrete has been chosen as a construction material because of its relatively

low cost and high availability in Cambodia.

5.5.2. Traditional Building Styles

Traditionally, many buildings in Cambodia are built with wrap-around balconies

on every floor.7 Figure 9 below shows an example of this pattern in Phnom

Penh. However, GCT has decided not to have this feature on this building

because of concerns of thieves gaining access to higher floors by climbing up the

balconies.

Figure 9: Apartment Complex in Phnom Penh Featuring

Wrap-Around Balcony.7

Table 21: Live Loads

32 | P a g e

5.5.3. Alternate Building Materials

5.5.3.1. Wood

IBC1 Section 2308.12.1 states that wood structures of conventional light-

frame construction cannot exceed one story in height in Seismic Design

Category D or E: representing stiff soil and soft soil as defined in IBC Section

1613.5. In addition, wood is rather expensive in Cambodia, and the land is

experiencing heavy deforestation. Because of Cambodia's wet climate,

termites are a large problem facing all wood construction, and measures

would need to be taken to reduce this threat. Due to its high cost,

environmental impact, and the fact that it fails to meet structural requirements,

wood is not recommended for this design.

5.5.3.2. Steel

Structural steel allows buildings to be constructed with a lower weight than

buildings of a similar strength in concrete. However, steel is much more

expensive and not as widely available as concrete in Cambodia. In addition,

structural steel requires off-site prefabrication and shipping of completed

structural members to the site. Because of the higher cost and reduced

availability of structural steel, it is not recommended for this design.

5.5.3.3. Concrete

Structural concrete is of lower cost and is more widely available in Cambodia

than structural steel. Concrete forms are constructed on-site, meaning that

no off-site prefabrication or shipping is required. The construction of forms

requires a large amount of labor, but labor is low-cost in Cambodia. Floors

and columns constructed with concrete are extremely heavy and must be

strong enough to handle the self-weight of the structure. However, despite

the increased strength required to hold the weight, concrete construction is

still significantly less expensive than steel. Due to of the significantly lower

cost of concrete, it is the recommended material for design.

33 | P a g e

5.5.4. Deep Foundations

The soil of the site is likely to have low bearing capacity and significant settlement, as discussed in Section 5.1.4. Team 11 expects that typical shallow

footings will not provide sufficient stability for the amount of settlement that could

occur on the site. Therefore, some type of deep foundation will be necessary.

Pile foundations were initially researched as a possible foundation option.

Pile foundations transfer the loads of a structure to deeper soil that has a higher

bearing capacity. They are used in the presence of poor shallow soils with low

bearing capacity. The piles can be driven or bored into the ground and they are

usually made from wood, steel, concrete, or a combination of these materials.3

Due to costs and availability of materials in Phnom Penh, concrete piles would be

most appropriate.

Concrete piles can be precast or cast-in-place. Cast-in-place piles can be cased

or uncased. One method of uncased piles are auger grout injected piles or

hollow stem auger piles. These piles are cast using a mandrel and typically are

cast to depths of 15m to 24m. The typical loads are from 222kN to 534kN.34

These piles have low initial costs. Table 22 gives values for the typical slump for

different types of concrete piles.

Table 22: The Typical Slump for Various Pile Types.34

34 | P a g e

The Menard pressure-meter values shown in Table 23 are good for estimating

soil conditions when experimental data is not available, and these values can be

used for preliminary design of pile foundations.34

Another type of deep foundations are caisson foundations. These are similar to

pile foundations, except that there is one large caisson beneath each column,

rather than several smaller piles. Caissons also must be bored rather than

driven. Foundation design was outside of the scope of this project, but it was

decided to do a cost-estimate design of a deep foundation, and to design it as a

caisson foundation for simplicity, and calculations are further explained in

Section 9.1. However, when GCT hires a geotechnical engineer to design the

foundation, the best option may be pile foundations or caisson foundations.

Table 23: The Typical Menard Pressure-Meter Values for Various Soil Types.34

35 | P a g e

6. Design Norms

6.1. Cultural Appropriateness

The building must use construction materials that are available in Cambodia. It must

also take into consideration the lower cost of labor in Cambodia in comparison to

building materials. GCT has requested that the outside design of the building look

traditionally Cambodian, although they want the inside to look more Western. The

design must also consider cultural expectations. For instance, since many

Cambodians ride motorcycles and bikes, parking should be available for these as

well as cars, and the number of car spaces should be modified accordingly.

Additionally, the final products, particularly the structural drawings, must also be

clear and specific enough to transcend culture and language barriers.

6.2. Stewardship

Some aspect of stewardship has guided most decisions in this project. Team 11

does want to design in a way that is responsible toward creation, particularly

because GCT is trying to raise environmental awareness. This comes into play

mainly through the recommendations for GCT’s sanitary sewage handling.

However, in most decisions, stewardship means making the best use of GCT’s

resources. GCT’s funding comes mainly from donations and grants, and while God

has graciously provided for GCT, these resources must be used wisely. The design

must take into consideration GCT’s limited land, and strive to use materials in the

most efficient way. One recommendation for efficient land use is for GCT to build

one taller building, rather than two shorter buildings. This allows more space to be

reserved for parking, which will be essential for GCT’s new business ventures to

thrive. Team 11 has also recommended a shorter building to cut down on GCT’s

foundation costs and worked hard to line up columns and plumbing from floor to

floor, avoiding the expenses of shifting columns or adding excessive connecting

pipes.

36 | P a g e

6.3. Integrity

Integrity in many ways combines the first two design norms. Similar to but more

broad than cultural appropriateness, integrity requires that the design be convenient

for users. Also similar to stewardship, the building must fit together in a harmonious

way. The rooms should be the most useful size and shape, and all the floor space

should be effectively used. Areas that people will use in conjunction should be

located close to one another. Mechanical rooms should be located in an area of the

building that can handle the extra noise, but is also easily accessible for

maintenance, and the elevator should be located in a convenient, wheelchair-

accessible area.

6.4. Trust

GCT must be able to trust this design. It must be structurally sound and dry during

seasonal flooding. The structure must be strong enough to resist all expected loads

and serve GCT reliably for many years. The design must also handle unexpected

situations, such as evacuation during a fire. Although Cambodia does not have a

required building code, Team 11 has designed the building to meet international

code. This will help to ensure that the design is trustworthy, taking advantage of the

foresight, experience, and modeling of many people over many years, rather than

only this team’s knowledge.

37 | P a g e

7. Alternative Solutions GCT wants this building to generate income for their organization. The original proposal

of a twelve-story building would be prohibitively expensive, so Team 11 looked into

alternative solutions. The first alternative Team 11 considered is a six-story building with

a larger footprint and comparable total area. This option is suboptimal because of the

limited space available to GCT. If the building were six stories, GCT would want to

have an additional building on their property, but due to space constraints, two buildings

would leave them with too little space left on the site for parking spaces. The building is

unable to house parking spaces on lower levels because the footprint is too small to fit a

parking ramp that meets IBC.1

Team 11 feels that in order for GCT’s facilities to be competitive with others in the area,

GCT needs to have more space for parking. Team 11 has chosen a second alternative:

a nine-story building with the recommendation of having only that building on this

property. This height was chosen because it was the minimum height that could fit all of

GCT’s requested components.

The ground level of the building is mostly open with columns so that the finished floors

are not damaged during the wet season when the site can flood. Because the first floor

of structural columns will be open, this area should not be used for car parking because

of the danger of cars hitting these columns and damaging the structure. Car parking will

be located away from the building and no routes of car traffic will travel under the

structure. However, when the land is dry, the space underneath the building can be

used for bicycle and motorcycle parking or GCT can use it for a farmer’s market.

38 | P a g e

8. Design

8.1. Design Modeling

8.1.1. STAAD.Pro

The system of structural design software that was used for this project was

STAAD.Pro, which stands for Structural Analysis and Design Professional, a

structural analysis and design suite by Bentley Systems, Incorporated. STAAD

enabled Team 11 to construct a 3-D representation of the structural components

and operational loads of the building and calculate the resultant moments, forces,

and displacements in the model. The model itself consists of over 10,000

individual nodes, beam members, and plates that represent all of the beams,

columns, floor slabs, and shear walls that make up the structure. Loads were

entered as sets of point loads, which act on nodes, and distributed loads, which

act along beams. ACI specifies loading factors that a structure must be designed

to withstand, resulting in a total of 105 unique combinations of loads acting on

the model. While STAAD does have capability to design steel reinforcement for

concrete members, Team 11 elected to design the reinforcement by hand,

because it allowed for more freedom and consistency in the design.

39 | P a g e

8.1.2. Model Verification

In order to check the moments calculated by STAAD.Pro, Team 11 used the

portal method of analysis to calculate rough moment values within a sample

section of the structure for a specific load case and compared these values to the

STAAD results. Most of the values were very close - within ten percent - but the

two sets of values became slightly more divergent at the lower floor where the

moments were highest. The moments that were calculated by hand were the

moments at each end of each beam span and the peak moment in the center of

the span.

The first step in calculating the moments was to establish a set of loads that act

on the structure. The load case used for this calculation set was load case

number 52, which features the dead load with a factor of 1.2, the full live load

with a factor of 1.0, the z-axis directional wind load with a factor of 1.6, and the

roof live load with a factor of 0.5. This set of forces was then used to calculate

the shear forces acting on the structure.

With all of the forces acting on the frame identified, the portal frame method was

used to calculate the moments due to horizontal forces, and a set of coefficients

was used to calculate the moments due to the vertical forces. Using the portal

frame method of analysis, a zero-moment hinge was assumed at the center of

each beam. From this assumption, free-body diagrams were drawn for each

node. These free-body diagrams list the forces acting on each beam and the

moments acting on the nodes from the horizontal forces, and are shown in Appendix C. The set of coefficients used to calculate moments due to vertical

forces were taken from an article in STRUCTURE magazine40 and ACI Section

8.3.3. These coefficients were used to determine the beam end and center span

maximum moments acting on each floor due to the uniform distributed loads

acting on the frame. Using the principle of superposition, the moments

calculated by both methods were added to produce the final checking. The

details of this calculation are shown in Appendix C.

40 | P a g e

8.1.3. Cracked Element Analysis

For structural concrete beams and columns subject to a bending moment, the

portion of the concrete that experiences a tension force due to the bending

moment may crack. These cracked sections have no effect on the structural

integrity of the building, but the presence of cracks can change the moment of

inertia of those sections and cause the bui lding to sway more in the wind.

According to Section 9.5.2.8 of ASCE 7, the maximum allowable deflection is

equal to 0.020hzx, where hzx is the height of the structure below Level x.

According to ACI Section 10.11.1, cracked sections are to be modeled by

multiplying the moment of inertia of members expected to crack by a reduction

factor: 0.35 for beams, 0.70 for columns, 0.35 for walls, and 0.25 for flat plates

and flat slabs. Although it is not expected that every member of the structure

would crack under operating conditions, the simplest way to evaluate a structure

using cracked element analysis is to first assume the worst-case scenario in

which all members are cracked. The cracked model must be refined if it fails to

meet deflection criteria. After ‘cracking’ all elements in STAAD, the maximum

horizontal deflection of nodes at a given floor were below the maximum vales

defined by the code. The model and allowable maximum deflections at each

floor can be seen in Table 24.

Table 24: Calculated and Allowable Maximum Deflection by Floor

Floor Model AllowedFloor 1 7.18 8Floor 2 11.82 14Floor 3 17.27 20Floor 4 23.53 26Floor 5 29.9 32Floor 6 36.22 38Floor 7 42.26 44Floor 8 48.21 50Roof 50.88 56

Deflection (mm)

41 | P a g e

8.1.4. Source™ Modeling

Team 11 created a 3-D interactive virtual model of this building in order to show

the final design in a more comprehensive and visual way. This was

accomplished using Valve® Software's Source™ Engine, a graphics and physics

engine used in popular modern computer games such as Portal™ and Half-Life®

2. The Source™ Engine can render near-photorealistic images in real time,

which was ideal for both generating still images and demonstrating the building

with a walk-through tour. The model was built using the Hammer World Editor, a

program created by Valve® to allow owners of Source™ games to construct their

own maps and levels. While the End User Licensing Agreement for Source™

games permits this use of Hammer and the Source™ Engine, images generated

with the Source™ Engine cannot be used by GCT to raise funds unless approval is granted by Valve®.42 A sample rendering of the building can be seen in Figure

10.

Figure 10: Rendering of Interior of Source™ Model

42 | P a g e

8.2. Beam Design

Beams within this structure are arranged along the edges of the 5m by 6m bays that

make up the structure of each floor, with eighteen beams 5m in length running

parallel to the shorter side of the building and sixteen beams 6m in length running

parallel to the longer side of the building. These beams were entered into the

STAAD.Pro model as sets of five or six beam members, each 1m in length and

connected rigidly end-to-end. Each of these beam members was identically sized at

200mm wide and 300mm deep for the first running of the STAAD model. This size

was chosen as a reasonable rough size simply to allow the STAAD model to

produce rough values for moments and forces acting within the beams. This first

iteration of the STAAD model was run with self-weight loads for members turned off.

The moments output by the first STAAD run were input into an Excel spreadsheet

that gave an approximate beam depth necessary for the beam to withstand its

maximum moment, assuming a specified beam width. This calculation was done

using the Whitney Stress Block Method assuming that the centroid of the beam was

also the neutral axis of the bending moment. The Whitney Stress Block Method is

described in ACI Section 10.2.7. An example of this method as well as the results of

the Excel spreadsheet can be seen in Appendix C.

The STAAD model was updated using these rough beam sizes, and STAAD-

calculated member self-weight was added to the dead load for all members except

the plates representing the floor slab. All loads caused by the self-weight of the floor

slab were calculated assuming a 180mm reinforced concrete slab and were already

included in the model as distributed loads along the beams. The moments output by

the second iteration of the STAAD model were put into Excel to find the maximum

absolute values of the moments within each beam.

43 | P a g e

These moments were then entered into a second, more complex Excel sheet that

calculated a more accurate beam size and flexural reinforcement based on the

Whitney Stress Block Method and tension-controlled conditions as defined in ACI

Section 10.3.4. ACI Section 10.3.4 defines a tension-controlled section as a section

in which the net tensile strain in the reinforcing steel is equal to or greater than 0.005

when the concrete in compression reaches its assumed strain limit of 0.003. A

sample of the operation of this second Excel document can be seen in Appendix C.

As additional changes were made to the STAAD model, including adding in the

designed column sizes, the beam sizes were continually updated using the method

described in the previous paragraph. After each small change, the model was

updated with adjusted beam sizes until the beam design no longer changed between

iterations.

It is important to note that, because the STAAD model is symmetrical, several wind

load cases were not included because they were directly rotationally symmetrical to

other wind loads that already existed in the STAAD model. Because of this, each

beam member was compared to its counterpart that would translate onto it if the

building were to be rotated 180 degrees at the center of the building. Both members

were designed based on the highest maximum moments felt by the two beams.

The beam design Excel document was then used to determine the necessary

reinforcement for the maximum positive and negative moments felt by each beam.

The beams were designed so that twelve configurations of size and reinforcement would be required. A list of the concrete sizes can be seen in Table 25, with a

schematic of cutoff lengths shown in Figure 11, and schematics showing the

locations of the different beam sizes are shown in Figure 12 and Figure 13.

Reinforcement in some of these beam sizes varies; these variations and their

placement are shown in the Design Drawing Set accompanying this report.

44 | P a g e

Table 25a: List of Beam Sizes and Strengths

Table 25b: List of Beam Sizes and Strengths

Table 25c: List of Beam Sizes and Strengths

BEAM TYPE

HEIGHT(mm)

WIDTH, bw

(mm)d

(mm)STIRRUP

SIZE

STIRRUP SPACING, S

(mm)

MAIN BAR SIZE

B101 400 300 340 10 167 19B102 400 300 340 10 167 19B201 500 450 440 10 215 19B202 500 450 440 10 215 19B203 500 450 440 10 215 19B301 500 450 440 10 215 19B302 500 450 440 10 215 19B401 500 450 437 13 215 19B402 500 450 437 13 215 19B403 500 450 437 13 215 19B501 560 500 497 13 240 19B502 560 500 497 13 240 19

BEAM TYPE

NUMBER OF BARS - TOP

STRENGTH REQUIRED - TOP

(kNm)

DESIGN STRENGTH -

TOP (kNm)

NUMBER OF CONTINUOUS BARS - TOP

BAR CUTOFF

LENGTH A (mm)

B101 2 50.6 68.41 2 0B102 4 112 129.7 4 2400B201 2 52 90.76 2 0B202 6 254 258.1 2 1950B203 5 197 218.0 2 1650B301 7 285 296.9 2 1550B302 7 284 296.9 2 1500B401 2 81 90.12 2 0B402 6 247 256.2 2 1750B403 5 209 216.4 2 1450B501 8 373 386.7 2 1250B502 8 367 386.7 2 1500

BEAM TYPE

NUMBER OF BARS -

BOTTOM

STRENGTH REQUIRED -

BOTTOM (kNm)

DESIGN STRENGTH -

BOTTOM (kNm)

NUMBER OF CONTINUOUS

BARS - BOTTOM

BAR CUTOFF

LENGTH B (mm)

B101 2 16.5 68.41 2 0B102 3 87 99.95 3 2400B201 2 11 90.76 2 0B202 3 101 134.4 2 1550B203 2 90 90.76 2 1250B301 4 148 176.8 2 1200B302 3 127 134.4 2 1200B401 2 10 90.12 2 0B402 4 140 175.5 2 1350B403 3 106 133.4 2 1200B501 6 254 296.4 2 1050B502 4 183 201.9 2 1150

45 | P a g e

Figure 12: Beam Size Schematic for Levels 1-8

Figure 13: Beam Size Schematic for Level 9

Figure 11: Length Guide for Table 25.

46 | P a g e

ACI Section 7.13.2 states that in order to prevent instantaneous structural collapse

in the event of catastrophic failure of concrete members, a fraction of flexural

reinforcement must run continuously through the entire length of the beam, even

where the bars are not needed to resist moments. According to ACI Sections

7.13.2.3 and 7.13.2.4, 1/6th of total negative moment reinforcement on the top of the

beam and 1/4th of total positive moment reinforcement on the bottom of the beam

must run the entire length of the beam, with a minimum of two bars in each case.

Because none of the beams in this structure have more than eight bars in any single

reinforcement layer, all of the beams will need only two bars on the top and two bars

on the bottom to meet this requirement.

According to ACI Section 12.1, reinforcement bars must extend a development

length, ld, past the relevant inflection point for that moment. That is, bars must

extend at least the length ld past the point at which the bar is no longer required to

act as tension reinforcement for that moment. The moment envelope for a beam is

the set of the highest positive and negative moments from all load cases at each

point along the length of the beam. Plots of moment envelopes for each of the

beams were made by STAAD.Pro and were used to determine the inflection points

for each beam. Figure 14 below shows the inflection points of a sample beam.

Figure 14: Method for Determining Inflection Points

47 | P a g e

See Appendix F for plots of the moment envelopes of each beam. ACI Section

12.2.2 defines ld as a function of the diameter of the bar based on the following

equations:

for bars ≤ No. 19

for bars ≥ No. 22

where Ψt represents the thickness factor, Ψe represents the reinforcement bar epoxy

coating factor, λ represents the lightweight concrete factor, and db is the bar

diameter. Because the reinforcement bars are not coated in epoxy and the beams

are not constructed out of lightweight concrete, Ψe and λ are both equal to 1.0. Ψt

equals 1.0 for normal beams, but 1.3 for beams in which the topmost layer of

reinforcement sits above 300mm or more of solid concrete.4 Bar diameter varies

from beam to beam. Using these equations, it was possible to find all relevant

values of a development length factor which could be multiplied by the bar diameter to provide the development length. Values are shown in Table 26 below:

Diagrams showing all beams with bars extended to their development lengths can

be seen in the Design Drawing Set. Shear reinforcement was designed to code. Sample calculations may be seen in Appendix C.

Table 26: Development Length Factors for Various Bar Conditions4

48 | P a g e

Several beams are placed within the shear wall and are intended to take all torsion

effects that would otherwise act on the wall. Designing these members for torsion is

beyond the scope of this project and would need to be done before this building

could be constructed. Torsional moment strength design is covered in ACI Section

11.6.3. According to ACI Section 11.6.3.8, any reinforcement required for torsion

shall be added to that required for shear, moment, and axial forces that act in

combination with the torsion.

8.3. Column Design

Column height was determined by floor-to-floor height, at 3m for each floor except

the bottom floor, which is 4m to allow for a meter of flooding without affecting the

elevator. These heights, along with a rough estimate of column cross-sectional

area, were entered into the STAAD.Pro model.

The STAAD.Pro model was run, after which the calculated axial loads were used to

roughly design the concrete cross-sectional area of several column designs, using a

safety factor of 0.65, as defined in ACI Section 9.3.2.2. The width and depth of the

column were set equal to limit the complexity of construction and design. The model

was run several times, and the area of the column was redesigned each time until

the areas became constant.

Next, three standard column designs for concrete size and reinforcement were

designed according to ACI code, accounting for the interaction of moment and axial

force and slenderness. One of these three column designs was assigned to each

column in the bui lding, as shown in Table 27.

49 | P a g e

Initially, five column sizes were used in the design of the structure. To avoid

slenderness, any column found to be slender was replaced with a column of the next

greater size, which resulted in the elimination of any column smaller than Column 1.

Maximum axial compressive force without moment was determined with the

standard ACI Equation 10.2 for tied, non-pre-stressed members:

𝑃𝑃𝑛𝑛 = 0.8 ∙ [0.85 ∙ 𝑓𝑓𝑐𝑐′�𝐴𝐴𝑔𝑔 − 𝐴𝐴𝑠𝑠𝑧𝑧 �+ 𝐴𝐴𝑠𝑠𝑧𝑧 ∙ 𝑓𝑓𝑦𝑦 ] (10.2)4

with an added safety factor of φ=0.65 for design strength, where fc ’ is the

compressive strength of concrete, Ag is the cross-sectional area of concrete, Ast is

the cross-sectional area of steel, and fy is the tensile strength of steel.

Next, to account for eccentric loading and moments, various values of axial strength

and moment resistance were calculated as the neutral axis moved through the depth

of the column. These points were plotted and connected to form a curve for each

column size.

Table 27: Column Placement: Four Cut Views Normal to X-Axis

x-coord 0 0 0 0 0 5 5 5 5 5 10 10 10 10 10 15 15 15 15 15 z-coord 0 6 12 18 22 0 6 12 18 22 0 6 12 18 22 0 6 12 18 22 Floor 8 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 Floor 7 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 Floor 6 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 Floor 5 1 1 1 1 1 1 2 2 2 1 1 2 2 2 1 1 1 1 1 1 Floor 2 1 1 1 1 1 1 2 2 2 1 1 2 2 2 1 1 1 1 1 1 Floor 1 1 1 2 2 1 1 2 2 2 1 1 2 2 2 1 1 2 2 1 1 Floor 2 1 1 2 2 1 1 3 3 3 1 1 3 3 3 1 1 2 2 1 1 Floor 1 1 1 2 2 1 1 3 3 3 2 2 3 3 3 1 1 2 2 1 1 Floor 0 2 2 2 2 2 2 3 3 3 2 2 3 3 3 2 2 2 2 2 2

50 | P a g e

Because of the relatively low values of moment in the columns according the

STAAD.Pro model, the minimum area of reinforcement (1% of concrete area) was initially used, though it was slightly increased as design continued (Table 28).

Cross-sectional area of steel was also checked to insure that it was great enough to

bear the tensi le axial forces calculated from STAAD.Pro.

For each column segment, the axial forces and moments from the STAAD.Pro

model for each load case were graphed alongside the column size curves to fit each

column segment to a standard column size. This can be seen in Figure 15. The

final column design dimensions appear in Table 28.

Figure 15: Moment (Mn) vs. Axial Force (Pn) Curves for Columns

-2.00E+03

0.00E+00

2.00E+03

4.00E+03

6.00E+03

8.00E+03

1.00E+04

0.0E+00 2.0E+02 4.0E+02 6.0E+02 8.0E+02 1.0E+03 1.2E+03

φPn

[N]

φMn [N-m]

Moment-Axial Force Column Diagram

Column 1 Maximum Compression

Column 1 M-P Curve

Column 2 Maximum Compression

Column 2 M-P Curve

Column 3 Maximum Compression

Column 3 M-P Curve

51 | P a g e

Finally, the new column sizes were entered into the STAAD.Pro model and the

resulting data was checked to insure that the column design was still appropriate to the axial forces and moments. See Appendix C for in-depth calculations.

Ties for the columns were determined according to ACI Section 7.10.5. The final tie design is shown in Table 29.

Table 28: Column Design Details

Table 29: Column Tie Design

Column Design

Number Width, b

[mm] Height, h

[mm] Bar Size

Number of Bars

Area of Steel [mm2]

Bar Cover [mm]

1 200 200 No. 29 8 5.2 50 2 550 550 No. 29 8 5.2 66 3 700 700 No. 29 8 5.2 71

Column Design Number

Compressive Design

Strength, φPn [kPa]

Tie Spacing

[mm] Tie

Sizes Tie

Cover [mm]

1 2996 150 No. 10 20 2 2728 250 No. 11 50 3 7007 250 No. 16 50

52 | P a g e

8.4. Slab Design

The floor slab system for this structure was designed to be a one-way system. The

floor slabs run parallel to the 15-meter wall and span 5m on center from beam to

beam. The minimum thickness of the slab based on deflection criteria is 𝑙𝑙/28 for

one-way slabs with both ends continuous, according to Table 9.5(a) of ACI Section

9.5.2.1. This gave a minimum slab thickness of 180mm. Analysis of the 180mm

thick floor slab as a 1m wide beam segment showed that this thickness of concrete

was sufficient to support the maximum factored moment (12.75kNm) when

reinforced with four No. 10 bars for a design moment of 15.2kNm, which is less than

the minimum reinforcement required by Equation 10-3 as described below.

Therefore, the floor slab design is deflection-controlled at 180mm thick, and the

reinforcement is controlled by the minimum area requirements.

Equation 10-3 of ACI Section 10.5.1 defines the minimum area of steel flexural

reinforcement for a floor slab. By assuming a beam of 1m width, a necessary steel

area per meter can be found.

𝐴𝐴𝑠𝑠,𝑚𝑚𝑖𝑖𝑛𝑛 = 0.25 ∙ �𝑓𝑓𝑐𝑐′𝑓𝑓𝑦𝑦

∙ 𝑏𝑏𝑤𝑤 ∙ 𝑑𝑑 (10-3)4

𝐴𝐴𝑠𝑠,𝑚𝑚𝑖𝑖𝑛𝑛 = 0.25 ∙ �27.5414

∙ 1000 ∙ (180− 25)

𝐴𝐴𝑠𝑠 ,𝑚𝑚𝑖𝑖𝑛𝑛 = 491.63𝑚𝑚𝑚𝑚2

Spacing of reinforcement bars in one-way slabs is governed by Equation 10-4 of ACI

Section 10.6.4, with calculated stress fs equal to 23fy, and cc representing the least

distance from surface of reinforcement steel to the tension face. The value of cc is

equal to 20mm as defined in ACI Section 7.7.1 - minimum cover for slab cast in

place not exposed to weather or in contact with ground.

𝑠𝑠 = 380�280𝑓𝑓𝑠𝑠� − 2.5𝑐𝑐𝑐𝑐 (10-4)4

𝑠𝑠 = 380 ∙ 280276

− 2.5 ∙ 20

𝑠𝑠 = 335.5𝑚𝑚𝑚𝑚

53 | P a g e

According to ACI Section 10.6.4, spacing must also be less than

𝑠𝑠 = 300 ∙ 280𝑓𝑓𝑠𝑠𝑚𝑚𝑚𝑚 = 304𝑚𝑚𝑚𝑚

This second value is less than the value from Equation 10-4, so the system is

controlled by this second value, and reinforcement must be spaced at closer than

304.4mm.

For the flexural reinforcement in the direction parallel to the slab’s span, the

minimum area requirement of 491.63mm2 may be met by eight No. 10 bars, each

with an area of 71mm2. Therefore, reinforcement of No. 10 bars every 125mm at the

top and bottom of the slab will be sufficient for flexural reinforcement. The final

flexural reinforcement is No. 10 bars every 120mm. Because this slab is intended to

operate as a one-way slab, minimum reinforcement will be sufficient in the direction

perpendicular to its span. The maximum allowable spacing from the above

calculations is 304mm, but Team 11 has decided to use a spacing of 300mm for

simplicity of construction and design.

54 | P a g e

8.5. Shear Wall Design

Shear walls were placed at opposing corners of the building, around the outside of stairwells, mechanical room, and elevator shaft, as shown in Figure 16. They

transfer shear in the floor slab diaphragms (caused by wind loads) to the foundation.

The shear walls run 5m in length on the shorter wall and 6m in length on the longer

wall. The shear walls span vertically from floor to floor, resulting in wall heights of

4m for the bottom floor and 3m for all other floors.

Using the total value of wind loads to determine necessary shear resistance, the

equation from ACI Section 11.10.3 was used to calculate the minimum shear wall

thickness: 𝑉𝑉𝑛𝑛 ≤ 0.83�𝑓𝑓𝑐𝑐 ′ℎ ∙ 𝑑𝑑 , where Vn is the factored shear force in the plane of the

wall, h is the wall thickness, and d is the wall length.

Figure 16: Location of Shear Walls

55 | P a g e

The minimum shear wall thickness for handling shear forces was found to be

0.129m and 0.060m for the east-west and north-south facing walls, respectively, but

was increased to 0.15m in both cases for ease of construction. The only exception

is the bottom floor, in which the shear wall was increased to 0.16m because of the

wall’s greater height. In accordance with ACI Section 14.5.3, the wall thickness

must equal or exceed 4% of the lesser of wall height or length, which increases the

thickness of the walls on the lowest level to 0.16m.

Columns will handle axial tension and moment in the plane of the wall. However,

the shear walls bear significant compressive axial forces. According to ACI Section

14.4, they must be designed as compression members. Shear walls in compression

may be designed empirically according to ACI Section 14.5 if the eccentricity of the

moment curling around the top of the wall is low enough that the resultant force falls

in the middle third of the wall’s thickness.

According to the STAAD.Pro model, this moment is too eccentric for the walls to be

empirically designed. Therefore, the beams within these walls wi ll be torsion-

reinforced to handle this moment, so that the walls can be empirically designed for

axial compression. See Section 8.2. Beam Design, for more information.

8.5.1. Shear Wall Reinforcement

Because the shear wall does not require reinforcement to handle the shear load,

and because all moments that would otherwise act on the shear wall are taken

up by adjacent members, the shear walls need only be designed to meet

minimum reinforcement requirements according to Section 14.3 of ACI. These

requirements are met by placing No. 10 bars in the spacing shown in Table 30.

Table 30: Spacing for Shear Wall Reinforcement

56 | P a g e

8 .6. Mechanical

8.6.1. Plumbing

Space has been left in this building to fit the plumbing; however, specific design

for plumbing is outside the scope of this project. See Appendix C for drainage

pipe details.

8.6.2. Air Conditioning

Window or wall mounted air conditioning units could be used in areas that require

air conditioning. Centralized air could also be used, but it is more expensive than

the individual air conditioning units are.

Due to the wide variety of use of the building, Team 11 recommends the use of

central air conditioning to provide a more comfortable environment for the

residents and clientele. Since the building will be built in stages, each floor shall

have its own air conditioning unit in the mechanical space on that floor. This

simplifies the ductwork since it will not need to go through the floor slabs. This

also is more efficient, since a single unit would initially need to be oversized in

anticipation for additional floors, or else the existing unit would need to be

replaced each time a floor is added.

57 | P a g e

8.7. Parking Design

A parking study was conducted to determine the minimum amount of parking that

the multi-purpose building should have. Using the “Parking Provision for New

Developments: Supplementary Planning Document,” a parking design guide from

England, Team 11 determined that there can be enough parking on GCT’s property.30 Table 31 shows the results of this investigation. This guide provides

standards for “central-areas” and “non-central-areas.” The central-areas require less

parking because things are closer together and because of the available public

transit. The non-central-areas require more parking because more people need to

drive to be to this location. Table 31 has the amount of parking required according

to this guide for both central- and non-central-areas. The parking required for

central-areas is 24-spaces.30

This initial analysis was done while condominiums were still planned as part of the

building. Although there will no longer be condominiums in the building, Team 11

believes that it is in GCT’s best interest to leave this space available for parking.

GCT has space for at least 26 car parking spaces, but there may be more parking

available that cannot be determined right now due to uncertainty with the sewage

channel. GCT’s property is in the capital of Cambodia where public transit is

available, so the site can be classified as a central-area with sufficient parking

available.

58 | P a g e

Table 31: The Results of Parking Needs Investigation Using the New Development Parking Planning Guide from England30

59 | P a g e

9. Suggestions The following are feasible options for GCT, though not part of design.

9.1. Foundation Cost Estimation

Many assumptions were made about the soil because not enough soil data was

available for foundation design. However, many assumptions were made, and a

basic caisson foundation was designed for cost estimate purposes. Table 32 and

Table 33 show the results of this design. See Appendix C for calculation details.

Assumptions Include:

• Soil is saturated, normally consolidated clay.

• Soil density = 19,600N/m3

• Friction angle = 0

• Nc = 7.5, 27

• Nq = 1, 27

• 𝑓𝑓𝑠𝑠 = 𝛼𝛼 ∙ 𝜎𝜎𝑣𝑣’

Where fs is the strength of soil for skin friction, α is a constant dealing with the

coefficient of friction between the soil and the caisson, and σv’ is the total

vertical stress at caisson midpoint.

• For concrete drilled shafts, α=0.55,36

• 𝑆𝑆𝑢𝑢 = 0.22𝜎𝜎𝑝𝑝 ’ ,44

• Where Su is undrained shear strength, and σp’ is maximum past compression.

Table 32: Caisson Placement Based on Soil Compression

Caisson Placement x\z 0 6 12 18 22 0 3 2 2 2 1 5 3 3 3 3 2

10 2 3 3 3 3 15 1 2 2 2 3

60 | P a g e

9.2. Drinking Water

9.2.1. Current Condition/Quality Needed

In Cambodia, there is no guarantee that city water pipes will not leak, allowing

infiltration of untreated groundwater and even sewage into drinking water pipes.

A high concentration of chlorine is used by the city’s water treatment plant to

combat this, but sometimes the water is still not potable. According to GCT,

about 10% of the city’s population drinks the city water without treatment, but

others use additional treatment. Therefore, GCT will require a system to reduce

chlorine content and insure that there are no pathogens in the water.

GCT uses city water for everything but drinking and washing food. Currently,

they are using the Research Development International (RDI) Ceramic Filtration

System, to treat their water.35 This is a simple filter made from clay mixed with

ground rice husks that burn away during firing, leaving tiny pores. Silver nitrate,

which kills any bacteria, coats the inside of the pot. The clay pot is set inside a

plastic container with a spout, shown in Figure 17. These filters are very

inexpensive, about $10 for a product that lasts two years. However, the flow

through one ceramic filter is only 2-L per hour. However, if GCT wanted to purify

all the water used by guests in their facility, they would need about five-hundred

of these pots. This is not feasible; therefore, it is necessary to purchase a

different system.

Table 33: Caisson Design Details

Caisson Type Number Radius

[m] Height

[m] Steel Area [mm]

Unit Cost [$]

Total Cost [$]

1 2 0.25 12.1 6.16 2275 2950 2 8 0.67 17 12.1 6615 52921 3 10 0.85 18.5 22.7 11587 115868

All 20 - 171721

61 | P a g e

Figure 17: RDI Ceramic Filtration35

62 | P a g e

9.2.2. Current/Future Water Use

GCT’s director gave the estimated current population, current water use, and

projected populations, from which the future water use was projected as shown

in Table 34. The current water use includes the water used in GCT’s office

space, as well as in the director’s residence. The projections of future water use

assume that per capita water use will be constant for the current and future

populations. For this reason, they are extremely rough, since they do not include

irrigation or pool maintenance.

9.2.3. GCT Drinking Water Possibilities/Alternatives

Extent of system:

• Filters for drinking water

• Filters for specific appliances

• Whole-building filtration system

• Water heating technology:

GCT mentioned the possibility of pumping water to a tank on the roof and

using a solar water heater. A Korean NGO in Cambodia has done this. Filtration technology alternatives are shown in Table 35.

Table 34: Future Water Use Projections.

Estimate Units

Current building

population14 Employees

20 m3/month

667 L/day

48 L/day/person

Low High Units

Projected building

population at 2 stories20 30

Employees and

guests

Projected water use at 2

stories952 1429 L/day

Projected building

population at 9 stories400 500

Employees and

guests

Projected water use at 9

stories19048 23810 L/day

Current water use

63 | P a g e

Table 35: Options for GCT’s Drinking Water Treatment.29, 31

64 | P a g e

9.3. Wastewater

9.3.1. Current/Future Water Use

It is assumed that the future wastewater production will be approximately the

same as the future drinking water use.

9.3.2. GCT Sewage Possibilities/Alternatives

• Sending waste down the current sewage stream is always an option.

• Must be a sewage system (that is, it wi ll include water and human waste)

because GCT would like to have western-style flush toilets.

• Separating human waste products makes composting more efficient, since

feces have the correct ratio of carbon to nitrogen, but urine adds too much

nitrogen.

• Composting of the feces needs to occur before use as fertilizer in order to kill

pathogens, but urine is useful as fertilizer with minimal treatment, since it is

sterile and high in nitrogen and phosphorus. Team 11 is proposing utilization

of Novaquatis NoMix Toilets for separation of urine for fertilizer and feces for

composting.29

• Composting on-site may be an option, even without separation, since

landscaping will provide carbon-rich material to balance out overly

nitrogenous human waste. Additionally, GCT can demonstrate composting

by land-applying the treated waste in the garden. GCT has expressed an

interest in composting waste.

• Aerobic vs. Anaerobic – Aerobic might work better for space constraints,

since it heats up faster, but would probably require stirring machinery – at a

greater expense. Anaerobic also produces methane (which is only beneficial

if it is captured).

• Space constraints and the high water table level rule out on-site infiltration of

liquids.

• It might also be possible to treat a fraction of the waste for composting, and

send the rest into the sewer.

65 | P a g e

• Consider using greywater from sinks for irrigation, though only if non-toxic

soaps and detergents are used.

• Find a company that will empty septic tanks and take care of the waste.

9.3.3. Sewage Trench/Trench Control Options

A pipe was constructed to transfer sewage across the site, but the neighbor on

the south side constructed a large wall directly over top of the buried pipe

resulting in the pipe being crushed. Sewage now flows along the edge of the site

in an open, unlined channel. This event took place before GCT came to own the

site. The government intended to construct a sewage pipe to replace the pipe

that was destroyed by the construction of the neighbor’s wall, but this has not

happened yet.

The sewage channel could be lined with concrete to contain the sewage and

reduce sewage exposure to ground water. This system would sti ll be vulnerable

to flooding, but a concrete cap could be added after main construction to

eliminate this problem. This, however, is outside the scope of the project. GCT

is in contact with the local authorities to have them replace the pipe as soon as

possible.

9.4. Utilities

Team 11 recommends that GCT connect to the available utilities.

9.4.1. Electricity

Connections can be made with help from Cambodian authorities.

9.4.2. City Water

Connections can be made with help from Cambodian authorities.

9.4.3. City Sanitary Sewer

Connection to sanitary sewer can be made at the open sewage trench running

along the edge of the property.

9.4.4. Gas

There are no natural gas pipelines in the area; gas tanks will need to be used.

66 | P a g e

10. Conclusion and Recommendations

10.1. Conclusion

Team 11 believes that it has established and accomplished substantial goals over

the course of this project. Through constant communication with GCT, they have

created a design that meets GCT’s needs and is much more feasible than GCT's

original suggestion. Their proposed 12-story structure next to a smaller residence

would be prohibitively expensive and would not make good use of the available land.

The 9-story structure described in this report will meet all of the usage needs that

GCT has expressed as well as providing a more reasonable cost and making better

use of the site. The set of drawings and schematics provided with this report detail

Team 11’s designs of the structural concrete beams, columns, walls, and floor slabs

that make up this structure. Because of time and manpower constraints, Team 11

decided to limit the scope of this project to the design of the building, with only

feasibility-level study on the site plan, water management, foundations, utilities, and

other topics. When this structure is built, additional design will need to be done on

each of these topics, and a licensed engineer will need to approve the structural

designs.

10.2. Recommendations for Further Design

A number of important elements that must be designed prior to construction were

outside the scope of this project. The following list is not exhaustive, but is meant as

a starting point for others who continue this work:

• Have a licensed engineer check and stamp design.

• Design torsion reinforcement in beams within shear walls, and ensure that

this will eliminate moments in shear walls.

• GCT should have the soil on their site tested, and foundations designed by a

licensed geotechnical engineer.

67 | P a g e

• Fully plan construction and excavation. The Design Drawing Set includes a

depiction of what areas would need to be excavated for the basic caisson

cost-estimate design, but once foundations are designed by a geotechnical

engineer, these plans will need to be edited. More thought must also be put

into the placement and movement of excess soil and construction equipment,

once it is determined how much excess soil and what type of equipment will

be in use. Care should be taken not to compact the soil in areas that will be

used for gardening and landscaping.

• Design construction joints if concrete in each level cannot be poured all at

once.

• Design stairs and wheelchair ramp on bottom level.

• A rubber membrane or other covering should be acquired to enable the top

floor slab to act as a roof between building projects.

• Other considerations for modular construction.

• Fire Considerations (sprinklers, structural protection): currently, the floor plans

are designed with the exits and seat spacing requirements required by fire

code.

• Decorative roof covering: the roof of the bui lding is expected to be used as a

restaurant, with a raised covering over it to protect from the elements. This

covering may be designed to evoke traditional Khmer architecture (upward

curving corners, etc.)

• Plan and design non-structural, finishing elements of building. This includes

carpet, insulation, doors, windows, etc.

• Fully design or choose pipe system, electric wiring, duct system, and elevator

(as well as emergency generator and sump pump for elevator).

68 | P a g e

Appendix A – References 1. 2006 International Building Code. International Code Counsel, 2006. Print. 2. 2009 International Plumbing Code. International Code Counsel. 4th Printing. 604.3:

604.5; 710.1. Web. 7 Apr. 2011. <http://publicecodes.citation.com/icod/ipc/2009/index.htm>

3. Abebe, Ascalew, and Dr. Ian GN. Smith. "Pile Foundation Design: A Student Guide.

"School of the Built Environment, Napier University, Edinburgh, May 1999. Web. 19 Nov. 2010. <http://www.sbe.napier.ac.uk/projects/piledesign/guide/index.htm>

4. ACI Committee 318. Bui lding Code Requirements for Structural Concrete and

Commentary –Metric (ACI 318M-05). 2005. Print. 5. "Acrisol." Encyclopedia Britannica Online. Encyclopedia Britannica, 2011. Web. 13

May. 2011. <http://www.britannica.com/EBchecked/topic/707275/Acrisol> 6. "Annual Mekong Flood Report 2006." Mekong River Commission, Mar. 2007. Web.

Nov. 2010. <www.mrcmekong.org> 7. "Architecture of Phnom Penh, The." Canby Publications Co., Ltd. Web. 2010.

<http://www.canbypublications.com/phnompenh/phnom-penh-architecture.htm> 8. "CAMBODIA COUNTRY REPORT ON FLOOD INFORMATION IN CAMBODIA."

Mekong River Commission, May 2006. Web. Nov. 2010. <http://www.mrcmekong.org/download/free_download/AFF-4/session1/Cambodia_country_report.pdf>

9. Cambodia. Europa World Plus Online. London, Routledge. Calvin College, Hekman

Library. Oct. 2010. <http://www.europaworld.com/entry?id=kh&go_country=GO> 10. "Cambodia." The World Factbook. CIA, Nov. 2010. Web. Nov. 2010.

<https://www.cia.gov/library/publications/the-world-factbook/geos/cb.html> 11. Charles, D. and D. Crocker. General Soil Map. Map. Ministry of Agriculture, 1963.

<http://eusoils.jrc.ec.europa.eu/esdb_archive/eudasm/asia/images/maps/download/kh2000_so.jpg>

69 | P a g e

12. "Disaster Risk Management Programs for Priority Counties." Country Programs for Disaster Risk Management & Climate Adaptation. Global Facility for Disaster Reduction and Recovery, 2009. Web. Nov. 2010. <http://gfdrr.org/ctrydrmnotes/Cambodia.pdf>

13. "Drainage Fixture Unit Values (DFU); Drainage Fixture Unit Loads for Sanitary

Piping."The Engineering Toolbox, 7 Apr. 2011. Web. 9 May 2011. <http://www.engineeringtoolbox.com>

14. Economy Watch: Economy, Investment, & Financial Reports. Stanley St Labs,

2009. Web. <http://www.economywatch.com/economic-statistics/country/Cambodia/>

15. Entrepreneur. Entrepreneur Media, Inc., Web. 2010.

<http://www.entrepreneur.com> 16. "French Indochina." Educational, Entertainment, and Research Material Relevant to

the Study of the Vietnam War. Dec. 2010. <http://www.vietnamwar.net/FrenchIndochina.htm>

17. Genesis Community of Transformation. Newsletter of Transformation. 2 Aug. 2010:

1-4. Print. 18. “Gley Soil.” Wikipedia. Wikipedia, 2011. Web. 13 May 2011.

<http://en.wikipedia.org/wiki/Gley_soil> 19. "Global Construction Costs." Turner and Townsend. Turner and Townsend, Sept.

2009. Web. <www.turnerandtownsend.com> 20. Google Maps. Google. Web. <maps.google.com> 21. Hazarika, Dr. M. K.; Bormudoi, A.; Kafle, T. P.; Samarkoon, Dr. L.; Noun, K.;

Savuth, Y.; and Narith, R. "FLOOD HAZARD MAPPING IN FOUR PROVINCES OF CAMBODIA UNDER THE MEKONG BASIN." Geo-Informatics Center. Asian Institute of Technology. May 2007. Web. Oct. 2010. <http://geoinfo.ait.ac.th/publications/paper_cambodia.pdf>

22. "History Data - Phnom Penh, Cambodia." Weather Underground.

<http://www.wunderground.com>

70 | P a g e

23. Invest in Cambodia. Web. Nov. 2010. <http://investincambodia.com/property.htm> 24. "Korean centre invests in closer relations." Khmer Property Magazine 2009. Web.

Nov. 2010. <http://www.khmerpropertynews.com/?inc=content.php&id=326> 25. "MCR Flood Management and Mitigation Programme Component 2: Structural

Measures and Flood Proofing." Mekong River Commission, Dec. 2009. Web. 13 Nov. 2010. <mcrmekong.org>

26. Mekong River Commission 2005. Overview of the Hydrology of the Mekong Basin.

Mekong River Commission, Vientiane, November 2005. 27. Meyerhoff, G.G., 1976, "Bearing Capacity and Settlement of Pile Foundations," J.

of Geot. Eng Div., Proc. ASCE, Vol. 102, GT3, pp. 197-227 28. Minimum Design Loads for Buildings And Other Structures (Asce Standard No. 7-

98, -05). Reston, VA: American Society of Civil Engineers, 1998, 2005. Print. 29. Novaquatis. Novaquatis, 5 Nov. 2010. Web.<http://www.novaquatis.eawag.ch> 30. "Parking Provision for New Developments: Supplementary Planning Document."

Stockton-on-Tees Borough Council, Nov. 2006. Web. Nov. 2010. <http://www.stockton.gov.uk/resources/transportstreets/48506/parkprov/parkingprov.pdf>

31. Perfect Web. Spectra Watermakers. Spectra Watermakers, 2008. Web

<http://www.spectrawatermakers.com/landbased/> 32. Petersen, Mark; Stephen Harmsen; Charels Mueller; Kathleen Haller; James

Dewey; Nicolas Luco; Anthony Crone; David Lidke; and Kenneth Rukstale. " Documentation for the Southeast Asia Seismic Hazard Maps." U.S. Geological Survey, 30 Sept. 2007. Web. 8 Mar. 2011.

<http://earthquake.usgs.gov/hazards/products/images/SEASIA_2007.pdf> 33. Phnom Penh Tower. HYUNDAI AMCO, 2010. Web. Nov. 2010. <http://office-cambodia.com/phnom-penh-tower-cambodia.html> 34. Prakash, Shamsher, and Hari D. Sharma. Pile foundations in Engineering Practice.

New York: John Wiley & Sons, Inc., 1990. Print.

71 | P a g e

35. RDI Cambodia: For a Hope and a Future. Research Development International. Web. <http://www.rdic.org/waterfiltrationsystems.htm>

36. "Reinforced Soil Structures: Training Course in Geotechnical and Foundation

Engineering: Earth Retaining Structures - Participants Manual." Federal Highway Administration, Geotechnical Engineering. US Department of Transportation, 1999. Web. 25 Apr. 2011. FHWA-NHI-99-025.

37. RS Means Assemblies. Reed Construction Data, 1992. Print. 38. Rybczynski, Witold, Chongrak Polprasert, and Michael McGarry. “Appropriate

Technology for Water Supply and Sanitation: Low-Cost Technology Options for Sanitation, a State-of-the-Art Review and Annotated Bibliography.” International Development Research Centre, Health Sciences Divisions and World Bank, 1982. Print.

39. Salidjanova, Nargiza. "ICE Case Study #218: Chinese Damming of Mekong and

Negative Repercussions for Tonle Sap." The Inventory of Conflict & Environment (ICE). American University, The School of International Service, 9 May 2007. Web. 13 Nov. 2010. <http://www1.american.edu/ted/ice/mekong-china.htm>

40. Silva, Pedro, and Sameh S. Badie. "Optimum Beam-To-Column Stiffness Ratio for

Portal Frames." STRUCTURE magazine. Mar. 2008. Web. 18 May 2011. <http://www.structuremag.org/article.aspx?articleID=560>

41. "Soil Map of the Lower Mekong Basin." Mekong River Commission, 23 Sept. 2005.

Web. <http://www.mrcmekong.org/spatial/meta_html/soil.htm#240976032> 42. "Steam Subscriber Agreement." Steampowered.com. Valve, Web. 2011.

<http://store.steampowered.com/subscriber_agreement/> 43. U.S. Department Of Labor, Bureau of Labor Statistics, Consumer Price Index <ftp://ftp.bls.gov/pub/special.requests/cpi/cpiai.txt> 44. Wotring, Donald. "ENGR 318: Soil Mechanics." Calvin College. Grand Rapids.

Spring 2011.

72 | P a g e

Appendix B – Cost Estimates

Table 36: Summary for the First Method of Total Cost Estimation.37

Table 37: Consumer Price Index.43

73 | P a g e

Table 38: Calculations of Construction Cost Indexes.19

Table 39: Purchasing Power Parity Index for Cambodia.14

74 | P a g e

Table 42 - Table 55 contain the information needed to estimate the cost of materials based on Team 11’s structural design. These tables contain the dimensions necessary to compute the weight of concrete and rebar needed and from this, the costs were estimated. The prices of materials in Phnom Penh were supplied by GCT. Steel costs $725/tonne and concrete is $91/tonne. The cost of blocks for the block walls was estimated to be $2/block.

Table 40: Cost of Concrete for Beams

BEAM LABEL

HEIGHT (mm)

HEIGHT MINUS SLAB

THICKNESS OF 180 mm

(mm)

WIDTH (mm)

AREA BELOW SLAB (mm2)

TOTAL LENGTH OF BEAM TYPE ON LEVEL (BUILDING

DIMENSION MINUS C2 AND C3, BEAMS LARGER THAN C1)

(mm)

AREA BASED ON NUMBER OF LEVELS

WITH CONFIGURATION (mm2)

VOLUME (mm3)

VOLUME (m3)

WEIGHT (tonne)

COST OF CONCRETE FOR BEAMS

LEVEL 0 1B100s 400 220 300 66000 65100 66000 4.30E+09 4.3 10.3 938 B200s 500 320 450 144000 43300 144000 6.24E+09 6.24 15.0 1,362 B300s 500 320 450 144000 42400 144000 6.11E+09 6.11 14.7 1,333

LEVEL 1, 2 2B100s 400 220 300 66000 65100 130200 8.48E+09 8.48 20.3 1,851 B200s 500 320 450 144000 48800 97600 4.76E+09 4.76 11.4 1,040 B300s 500 320 450 144000 42400 84800 3.60E+09 3.6 8.63 785

LEVEL 3-5 3B100s 400 220 300 66000 67400 198000 1.33E+10 13.3 32.0 2,915 B200s 500 320 450 144000 48800 432000 2.11E+10 21.1 50.6 4,604 B300s 500 320 450 144000 45500 432000 1.97E+10 19.7 47.2 4,293

LEVEL 6 AND 7 2B100s 400 220 300 66000 68000 132000 8.98E+09 8.98 21.5 1,960 B200s 500 320 450 144000 48800 288000 1.41E+10 14.1 33.7 3,069 B300s 500 320 450 144000 48800 288000 1.41E+10 14.1 33.7 3,069

ROOF BEAMS AND SLAB, COLUMNS FROM 8 TO 9 1B100s 400 220 300 66000 67500 66000 4.46E+09 4.46 10.7 973 B400s 500 320 450 144000 48800 144000 7.03E+09 7.03 16.9 1,535 B500s 560 380 500 190000 48800 190000 9.27E+09 9.27 22.3 2,025 SUM 1.45E+11 145.4 349.0 31,754

75 | P a g e

Table 41a: Length of Longitudnal Reinforcing Steel for Beams

Table 41b: Length of Longitudnal Reinforcing Steel for Beams

BEAM LABEL

TOTAL # TOP BARS

HOOK LENGTH (2 PER BAR)

(mm)

LENGTH OF CUT STEEL,

TOP (mm)

NUMBER OF CUT BARS,

TOP

LENGTH CONTINUOUS,

TOP (mm)

NUMBER OF CONTINUOUS,

TOP

TOTAL, TOP (mm)

NUMBER IN

BUILDING

TOTAL LENGTH OF

BARS IN BEAMS

(mm)B101 2 700 0 0 5000 2 11400 18 205,200 B102 4 700 0 0 5000 4 22800 117 2,667,600 B201 2 700 0 0 6000 2 13400 16 214,400 B202 6 700 5770 4 6000 2 39280 32 1,256,960 B203 5 700 5170 3 6000 2 31010 16 496,160 B301 7 700 4970 5 6000 2 41750 32 1,336,000 B302 7 700 4870 5 6000 2 41250 32 1,320,000 B401 2 700 0 0 6000 2 13400 2 26,800 B402 6 700 5370 4 6000 2 37680 4 150,720 B403 5 700 4970 3 6000 2 30410 2 60,820 B501 8 700 4370 3 6000 2 30710 4 122,840 B502 8 700 4870 6 6000 2 46820 4 187,280

SUM 8,044,780

BEAM LABEL

TOTAL # BOTTOM

BARS

HOOK LENGTH (2 PER BAR)

(mm)

LENGTH OF CUT STEEL,

BOTTOM (mm)

NUMBER OF CUT BARS, BOTTOM

LENGTH CONTINUOUS,

BOTTOM (mm)

NUMBER OF CONTINUOUS,

BOTTOM

TOTAL, BOTTOM

(mm)

NUMBER IN

BUILDING

TOTAL LENGTH OF

BARS IN BEAMS

(mm)B101 2 700 0 0 5000 2 11400 18 205,200 B102 3 700 0 0 5000 3 17100 117 2,000,700 B201 2 700 0 0 6000 2 13400 16 214,400 B202 3 700 4740 1 6000 2 18840 32 602,880 B203 2 700 4940 0 6000 2 13400 16 214,400 B301 4 700 5340 2 6000 2 25480 32 815,360 B302 3 700 5040 1 6000 2 19140 32 612,480 B401 2 700 0 0 6000 2 13400 2 26,800 B402 4 700 5140 2 6000 2 25080 4 100,320 B403 3 700 5040 1 6000 2 19140 2 38,280 B501 6 700 5940 4 6000 2 39960 4 159,840 B502 4 700 5140 2 6000 2 25080 4 100,320

SUM 13,135,760

76 | P a g e

Table 42: Cost of Longitudnal Reinforcing Steel for Beams

Table 43: Cost of Stirrups; The Shear Reinforcing for Beams

WEIGHT OF #19 BAR

(kg/m)

WEIGHT OF BAR (kg)

WEIGHT OF BAR

(tonne)2.235 29358.4 29.4

COST OF STEEL FOR LONGITUDNAL

REINFORCEMENT IN BEAMS21,284

TOTAL LENGTH OF BARS IN BEAMS

(m)13135.8

BEAM LABEL

STIRRUP SPACING, S

(mm)

STIRRUPS PER BEAM

NUMBER OF BEAMS IN BUILDING

BAR LENGTH

PER STIRRUP

(mm)

TOTAL LENGTH

(mm)

TOTAL LENGTH

(m)

STIRRUP BAR SIZE

WEIGHT OF BAR (kg/m)

WEIGHT (kg)

WEIGHT (tonne)

COST OF STEEL FOR

STIRRUPS IN BEAMS

B100s 167 30 135 990 4009500 4010 10 0.560 2245 2.25 1,628B200s 215 28 64 1350 2419200 2419 10 0.560 1355 1.35 982B300s 215 28 64 1350 2419200 2419 10 0.560 1355 1.35 982B400s 215 28 8 1380 309120 309 13 0.994 307 0.31 223B500s 200 25 8 1550 310000 310 13 0.994 308 0.31 223SUM 9467 5570 5.57 4,038

77 | P a g e

Table 44: Approximation of the Cost and Number of Blocks Needed For Walls

LEVELAREA (m2)

HEIGHT (m)

VOLUME OF BLOCK WALL

(m3)

APPROXIMATE NUMBER OF

BLOCKS

COST OF BLOCKS

LEVEL 0 18 4 72 4500 9,000 LEVEL 1 55.5 3 167 10438 20,875 LEVEL 2 51.6 3 155 9688 19,375 LEVEL 3 57.7 3 173 10813 21,625 LEVEL 4 64.1 3 193 12063 24,125 LEVEL 5 55.3 3 166 10375 20,750 LEVEL 6 55.3 3 166 10375 20,750 LEVEL 7 55.3 3 166 10375 20,750 LEVEL 8 60.8 3 182 11375 22,750 LEVEL 9 3.3 3 10 625 1,250

SUM 477 31 1450 90625 181,250

78 | P a g e

Table 45: Cost of Concrete for Columns

COLUMN LABEL

CROSS SECTION AREA OF COLUMN

(mm)

INITIAL LENGTH

(mm)

SLAB THICKNES OR BEAM DEPTH AT

COLUMN, WHICHEVER IS GREATER

(mm)

COLUMN HEIGHT MINUS SLAB

THICKNESS OR BEAM DEPTH

(mm)

VOLUME PER

COLUMN (mm3)

COULMNS PER LEVEL

VOLUME PER LEVEL

(mm3)

TOTAL VOLUME

(mm3)

TOTAL VOLUME

(m3)

WEIGHT (tonne)

COST OF CONCRETE

FOR COLUMNS

LEVEL 0 1C2 302,500 4000 180 3820 1.16E+09 14 1.62E+10 1.62E+10 16.2 38.8 3,533 C3 490,000 4000 180 3820 1.87E+09 6 1.12E+10 1.12E+10 11.2 27.0 2,453

LEVEL 1, 2 2C1 160,000 3000 500 2500 4.0E+08 10 4.0E+09 8.0E+09 8 19.2 1,747 C2 302,500 3000 180 2820 8.53E+08 4 3.41E+09 6.82E+09 6.82 16.38 1,490 C3 490,000 3000 180 2820 1.38E+09 6 8.29E+09 1.66E+10 16.6 39.8 3,621

LEVEL 3-5 3C1 160,000 3000 500 2500 4.0E+08 14 5.6E+09 1.68E+10 16.8 40.32 3,669 C2 302,500 3000 180 2820 8.53E+08 6 5.12E+09 1.54E+10 15.4 36.9 3,354

LEVEL 6 AND 7 2C1 160,000 3000 500 2500 4.0E+08 20 8.0E+09 1.6E+10 16 38.4 3,494

1C1 - B400 160,000 3000 500 2500 4.0E+08 10 4.0E+09 4.0E+09 4 9.60 874 C1 - B500 160,000 3000 560 2440 3.9E+08 10 3.9E+09 3.9E+09 3.90 9.37 853

SUM 1.15E+11 114.9 275.7 25,088

ROOF BEAMS AND SLAB (COLUMNS FROM LEVEL 8 TO 9)

jcg6
Line

79 | P a g e

Table 46: Cost of Longitudnal Reinforcing Steel for Columns

Table 47: Cost of Ties; The Shear Reinforcing for Columns

COLUMN HEIGHT

(mm)

NUMBER OF

COLUMNS

BARS PER COLUMN

AVERAGE LENGTH OF LAP

TO COLUMN ABOVE (mm)

LENGTH PER BAR

(mm)

TOTAL LENGTH

(mm)

TOTAL LENGTH

(m)

BAR SIZE

WEIGHT OF STEEL FOR BAR

(kg/m)

WEIGHT (kg)

TOTAL WEIGHT (tonne)

COST OF STEEL FOR LONGITUDNAL

REINFORCEMENT IN COLUMNS

4000 20 8 1130 5130 8.21E+05 820.8 29 5.060 4,153 4.15 3,011 3000 160 8 1130 4130 5 29E+06 5286 4 29 5 060 26 749 26 7 19 3933000 160 8 1130 4130 5.29E+06 5286.4 29 5.060 26,749 26.7 19,393

SUM 30.9 22,404

COLUMN LABEL

COLUMN HEIGHT

(mm)

NUMBER OF TIES PER COLUMN

LENGTH PER TIE

(mm)

TIE SIZE

NUMBER OF COLUMNS IN

BUILDING

TOTAL LENGTH

(mm)

TOTAL LENGTH

(m)

WEIGHT OF STEEL FOR TIES

(kg/m)

WEIGHT (kg)

WEIGHT (tonne)

COST OF STEEL FOR

TIES

C2 4000 10 1950 13 14 2.73E+05 273 0.994 271.4 0.271 197 C3 4000 10 2580 16 6 1 55E+05 154 8 1 552 240 2 0 240 174C3 4000 10 2580 16 6 1.55E+05 154.8 1.552 240.2 0.240 174 C1 3000 9 1350 10 122 1.48E+06 1482.3 0.560 830.1 0.830 602 C2 3000 8 1950 13 26 4.06E+05 405.6 0.994 403.2 0.403 292 C3 3000 8 2580 16 12 2.48E+05 247.68 1.552 384.4 0.384 279

SUM 2.13 1,544

80 | P a g e

Table 48: Cost of Concrete for Shear Walls

Table 49: Cost of the Steel Reinforcing for Shear Walls

SHEAR WALL LOCATION

LENGTH MINUS COLUMN WIDTH

(mm)

HEIGHT MINUS DEPTH OF BEAM

ABOVE (mm)

THICKNESS (mm)

VOLUME OF SHEAR WALLS

FOR ONE LEVEL (mm3)

VOLUME FOR NUMBER OF

LEVELS WITH CONFIGURATION

(mm3)

VOLUME FOR NUMBER OF

LEVELS WITH CONFIGURATION

(m3)

WEIGHT (tonne)

COST OF CONCRETE FOR SHEAR

WALLS

LEVEL 0 400,500 1SHEAR WALL (6m) 5375 4875 160 8.39E+09 8.39E+09 8.39 20.1 1,831 SHEAR WALL (5m) 4375 3975 160 5.57E+09 5.57E+09 5.57 13.4 1,215

LEVEL 1 AND 2 2SHEAR WALL (6m) 5375 4875 150 7.86E+09 1.57E+10 15.72 37.7 3,434 SHEAR WALL (5m) 4375 3975 150 5.22E+09 1.04E+10 10.43 25.0 2,279

LEVEL 3-9 6SHEAR WALL (6m) 5600 5100 150 8.57E+09 5.14E+10 51.41 123.4 11,228 SHEAR WALL (5m) 4600 4200 150 5.80E+09 3.48E+10 34.78 83.5 7,595

SUM 1.26E+11 126.3 303.1 27,582

WALL LOCATION

WALL LENGTH

(mm)

BAR DIRECTION

NUMBER OF

LEVELS

BAR SIZE

LENGTH (mm)

NUMBER OF BARS

LENGTH OF HOOKS

(ACCOUNTS FOR ONE ON EACH SIDE

OF BAR) (mm)

TOTAL LENGTH OF BARS

(mm)

TOTAL LENGTH OF BARS

(m)

WEIGHT OF STEEL FOR

BAR (kg/m)

WEIGHT (kg)

WEIGHT (tonne)

COST OF STEEL FOR

SHEAR WALL REINFORCE-

MENT(mm)

LEVEL 0 6000 VERTICAL 1 10 4000 16 250 6.8E+04 68 0.560 38.08 0.038 28LEVEL 0 6000 HORIZONTAL 1 10 5375 20 250 1.13E+05 112.5 0.560 63 0.063 46LEVEL 0 5000 VERTICAL 1 10 4000 13 250 5.53E+04 55.25 0.560 30.94 0.031 22LEVEL 0 5000 HORIZONTAL 1 10 4375 20 250 9.25E+04 92.5 0.560 51.8 0.052 38

LEVEL 1-8 6000 VERTICAL 8 10 3000 16 250 4.16E+05 416 0.560 232.96 0.233 169LEVEL 1-8 6000 HORIZONTAL 8 10 5375 15 250 6.75E+05 675 0.560 378 0.378 274LEVEL 1-8 5000 VERTICAL 8 10 3000 13 250 3.38E+05 338 0.560 189.28 0.189 137LEVEL 1-8 5000 HORIZONTAL 8 10 4375 15 250 5.55E+05 555 0.560 310.8 0.311 225

SUM 1.29 939

81 | P a g e

Table 50: Cost of Concrete for the Slab

Table 51: Cost of the Steel Reinforcing for the Slab

LENGTH (mm)

WIDTH (mm)

DEPTH (mm)

VOLUME PER SLAB

(mm3)

NUMBER OF SLABS

TOTAL VOLUME

(mm3)

TOTAL VOLUME

(m3)

WEIGHT (tonne) COST

24400 15400 180 6.7637E+10 10 6.764E+11 676.4 1623.4 147,729

COST OF CONCRETE FOR SLAB

24400 15400 180 6.7637E+10 10 6.764E+11 676.4 1623.4 147,729

STEEL REINFORCEMENT

FOR SLAB

BAR SIZE

BARS PER

SLAB

LENGTH PER BAR

(mm)

NUMBER OF SLABS

TOTAL LENGTH

(mm)

TOTAL LENGTH

(m)

WEIGHT OF

STEEL (kg/m)

WEIGHT (kg)

WEIGHT (tonne)

COST FOR STEEL REINFORCEMENT

OF SLAB

TOP MAIN BAR 10 204 15400 10 3.14E+07 31,416 0.560 17593 17.6 12,755BOTTOM MAIN BAR 10 204 15400 10 3.14E+07 31,416 0.560 17593 17.6 12,755TEMPERATURE BAR 10 52 24400 10 1.27E+07 12,688 0.560 7105 7.1 5,151SUM 42.3 30,661

82 | P a g e

Table 53: Cost of Concrete for the Stairs

Table 52: Cost of Concrete for the Elevator Platform

LENGTH (mm)

WIDTH (mm)

HEIGHT (mm)

VOLUME (mm3)

VOLUME (m3)

WEIGHT (tonne)

COST OF CONCRETE

6340 6000 1000 3.8E+10 38 91.2 8,299 CORNER CUTOUT: 1200 500 1000 6.0E+08 -0.6 -1.44 -131SUM 37.4 89.8 8,168

VOLUME OF CONCRETE FOR PLATFORM

STAIRSNUMBER

OF LEVELS

VOLUME PER STEP

(m3)

NUMBER OF STAIRS (BOTH STAIRWELLS)

VOLUME OF LANDING (BOTH STAIRWELLS)

(m3)

TOTAL VOLUME

(m3)

WEIGHT (tonne)

COST OF CONCRETE

LEVEL 0 1 0.559 44 1.33 25.94 62.3 5,669 OTHER LEVELS 8 0.559 32 1.33 153.82 369.2 33,597 SUM 179.8 431.5 39,267

83 | P a g e

Appendix C – Detailed Calculations

C.1. Load Calculations

C.1.1. Wind Calculations

The following calculations were performed for each height level:

Calculated by: JJU

Checked by: JACG, ALH

84 | P a g e

C.1.2. Seismic Loads

Figure 18: Figure D-1 fo USGS "Documentation for the Southeast Asia Seismic Hazard Maps"32

85 | P a g e

C.1.3. Dead Load Calculations

Dead Load calculations were based on ASCE-7. A more detailed calculation is shown in Table 56. These values were converted into kg/m using the

gravitational constant and the tributary width of the beams, then entered into

STAAD.Pro as lineal loads.

Table 54: Dead Load Calculations

86 | P a g e

C.1.4 Live Load Calculations

Live loads were based on ASCE-7 and estimated at 40psf for the residence floor

and at 100psf for all other floors. As shown in the table below, this was

converted into N/m2, and then into kg/m using the gravitational constant and the

tributary width of the beams. These values were entered into STAAD.Pro as

lineal loads.

Table 55: Live Load Calculations

87 | P a g e

C.2. Beam Design

C.2.1 Metric Concrete Excel Design Program Calculations

88 | P a g e

89 | P a g e

C.2.2. Stirrup Calculations

Calculated by: JACG, JJU

Checked by: ALH

90 | P a g e

C.2.3. Whitney Stress Block Method

The Whitney stress block method creates an approximation of the compressive

force in a section of beam under a bending moment in order to calculate the

appropriate tensile reinforcement of the beam. The compressive force is

approximated as a pressure of 0.85f’c acting the entire width of the beam

according to Figure 19.

Calculated by: JACG

Checked by: ALH

91 | P a g e

Figure 19: Whitney Stress Block Diagram

Figure 20: Beta Factor for Beams4

92 | P a g e

Where β1 is a factor dependent on f’c as seen in Figure 20 above, and c

represents the distance from the extreme compressive fiber to the centroid for

the reinforcement steel.

For safety reasons, these beams have been designed according to tension-

controlling conditions, which means that strain within the tension steel is greater

than or equal to 0.005 when the concrete reaches 0.003 in compressive strain.

The tensile strain of the steel when concrete strain reaches 0.003 is:

𝑧𝑧𝑠𝑠 = 0.003 𝑑𝑑−𝑐𝑐𝑐𝑐

.

The reinforcing ratio is:

𝜌𝜌 = 𝐴𝐴𝑠𝑠𝑏𝑏𝑑𝑑

Where As is the area of reinforcing steel and b is the width of the beam.

According to section 10.5.1 of ACI:

The minimum reinforcing ratio of steel is:

𝜌𝜌𝑚𝑚𝑖𝑖𝑛𝑛 = 𝑓𝑓 ’𝑐𝑐𝐹𝐹𝑦𝑦 ∗𝐴𝐴

,

The maximum reinforcing ratio is:

𝜌𝜌𝑚𝑚𝑎𝑎𝑥𝑥 = 0.75 ∙ 0.85 𝑓𝑓𝑐𝑐′ ∗𝛽𝛽1

𝐹𝐹𝑦𝑦∙ 600

600 +𝐹𝐹𝑠𝑠

Next, the maximum allowable moment must be calculated. The maximum design

moment of the beam is:

𝑀𝑀𝑛𝑛 = 𝐴𝐴𝑠𝑠 ∙ 𝑓𝑓𝑦𝑦 ∙ 𝑑𝑑.

If all of the above conditions are met, then the specified beam reinforcement

design is acceptable.

Figure 21 on the next page shows the initial resulting beam widths in meters

using the Whitney Stress Block Method for each floor, and Figure 22 on the

following page shows a screen shot of the more complex Excel sheet that

calculates beam size and flexural reinforcement based on ACE 10.3.4.

93 | P a g e

Figure 21: First Iteration Beam Width Calculator in Excel (m)

94 | P a g e

Figure 22: Detailed Calculator for Beam Sizes

Figure 23 to Figure 27 are the worst-case bending moment graphs for each of the beams. To design where the rebar can go in the beams, the locations of the moment inflection points need to be determined. The rebar must extend the development length of the bar past the inflection point.

Figure 23a: B101 Moment Graph

Figure 24a: B201 Moment Graph

-20

-10

0

10

20

30

40

50

60

0 1 2 3 4 5

BEN

DIN

G M

OM

ENT

(kN

m)

DISTANCE ALONG BEAM (m)

B101 BENDING MOMENT DIAGRAM

-100

-50

0

50

100

150

0 1 2 3 4 5

BEN

DIN

G M

OM

ENT

(kN

m)

DISTANCE ALONG BEAM (m)

B102 BENDING MOMENT DIAGRAM

-15

0

15

30

45

60

0 1 2 3 4 5 6

BEN

DIN

G M

OM

ENT

(kN

m)

DISTANCE ALONG BEAM (m)

B201 BENDING MOMENT DIAGRAM

-125

-100

-75

-50

-25

0

25

50

75

100

125

150

175

200

225

250

275

0 1 2 3 4 5 6

BEN

DIN

G M

OM

ENT

(kN

m)

DISTANCE ALONG BEAM (m)

B202 BENDING MOMENT DIAGRAM

95 | P a g e

Figure 23a: B101 Moment Graph

Figure 24b: B202 Moment Graph

95 | P a g e

96 | P a g e

Figure 25b: B302 Moment Graph

Figure 24c: B203 Moment Graph

Figure 26a: B401 Moment Graph

-100

-80

-60

-40

-20

0

20

40

60

80

100

120

140

160

180

200

0 1 2 3 4 5 6

BEN

DIN

G M

OM

ENT

(kN

m)

DISTANCE ALONG BEAM (m)

B203 BENDING MOMENT DIAGRAM

-150

-125

-100

-75

-50

-25

0

25

50

75

100

125

150

175

200

225

250

275

300

0 1 2 3 4 5 6

BEN

DIN

G M

OM

ENT

(kN

m)

DISTANCE ALONG BEAM (m)

B301 BENDING MOMENT DIAGRAM

-150

-125

-100

-75

-50

-25

0

25

50

75

100

125

150

175

200

225

250

275

300

0 1 2 3 4 5 6

BEN

DIN

G M

OM

ENT

(kN

m)

DISTANCE ALONG BEAM (m)

B302 BENDING MOMENT DIAGRAM

-25

0

25

50

75

100

0 1 2 3 4 5 6

BEN

DIN

G M

OM

ENT

(kN

m)

DISTANCE ALONG BEAM (m)

B401 BENDING MOMENT DIAGRAM

Figure 25a: B301 Moment Graph

97 | P a g e

Figure 26b: B402 Moment Graph

Figure 27b: B502 Moment Graph

-150

-125

-100

-75

-50

-25

0

25

50

75

100

125

150

175

200

225

250

0 1 2 3 4 5 6

BEN

DIN

G M

OM

ENT

(kN

m)

DISTANCE ALONG BEAM (m)

B402 BENDING MOMENT DIAGRAM

-125

-100

-75

-50

-25

0

25

50

75

100

125

150

175

200

225

0 1 2 3 4 5 6

BEN

DIN

G M

OM

ENT

(kN

m)

DISTANCE ALONG BEAM (m)

B403 BENDING MOMENT DIAGRAM

-300

-250

-200

-150

-100

-50

0

50

100

150

200

250

300

350

400

0 1 2 3 4 5 6BEN

DIN

G M

OM

ENT

(kN

m)

DISTANCE ALONG BEAM (m)

B501 BENDING MOMENT DIAGRAM

-200

-150

-100

-50

0

50

100

150

200

250

300

350

400

0 1 2 3 4 5 6

BEN

DIN

G M

OM

ENT

(kN

m)

DISTANCE ALONG BEAM (m)

B502 BENDING MOMENT DIAGRAM

Figure 27a: B501 Moment Graph

Figure 26c: B403 Moment Graph

98 | P a g e

C.2.4. Hand Calculations

Calculated by: JJU

Checked by: ALH, JACG

99 | P a g e

Factored moments were added to moments from free-body diagrams, shown

below, using consistent sign conventions to produce total moments in beams. Figure 28 shows the overall building cross-section that was used for the moment

hand calculations that verified the STAAD model. It has the loads and labels for the free body diagrams. Figures A1 – E9 are the free body diagrams used in the

hand calculations of the bending moments on the building.

Figure 28: Moment Hand Calculation Layout

100 | P a g e

FORCES IN kN

MOMENTS IN kNm

101 | P a g e

FORCES IN kN

MOMENTS IN kNm

102 | P a g e

FORCES IN kN

MOMENTS IN kNm

103 | P a g e

FORCES IN kN

MOMENTS IN kNm

104 | P a g e

FORCES IN kN

MOMENTS IN kNm

105 | P a g e

FORCES IN kN

MOMENTS IN kNm

106 | P a g e

FORCES IN kN

MOMENTS IN kNm

107 | P a g e

FORCES IN kN

MOMENTS IN kNm

108 | P a g e

FORCES IN kN

MOMENTS IN kNm

109 | P a g e

C.3. Column Design

The below calculations were done in an Excel spreadsheet for each column at seven

values different values of c. The geometric dimensions involved in the calculations

are depicted in Figure 29. In order to construct curves into which the factored axial

forces and moments from each column in the STAAD.Pro model must fit, the values

for design axial force were graphed verses the design moment, with a horizontal line

depicting the maximum axial load, as shown in Figure 15. Figure 30 shows a

screenshot of the above calculations in the Excel file “Exact Column Design.xlsx”:

Figure 29: Column Design Dimensions

110 | P a g e

111 | P a g e

112 | P a g e

113 | P a g e

Calculated by: ALH

Checked by: JJU

114 | P a g e

115 | P a g e

Figure 30: "Exact Column Design.xlsx" Calculations

116 | P a g e

C.3.1 Column Ties

Column ties were designed based on ACI 7.10.5.

7.10.5.1: Ties must be No. 10 or greater, with a diameter of not less than 2% of the column’s greatest dimension, as shown in Table 58.

7.10.5.2: Vertical spacing must not exceed the least of: a) the column’s least

dimension, b) 16 bar diameters, or c) 48 tie diameters, shown in Table 44.

The limiting spacing for column 1 is the least dimension, so tie spacing in column

1 shall not exceed 400mm. However, it was found that a smaller spacing worked

better in this column, so spacing for column 1 is one tie every 350mm. The

limiting spacing for columns 2 and 3 is 16 bar diameters, so tie spacing in these

columns shall not exceed 450mm.

Table 57: Calculating Tie Spacing Requirements

Table 56: Calculating Tie Bar Size Requirements

Column Least Dimension[mm]

Bar Diameter [mm]

16 Bar Diameters

Tie Diameter

[mm]

28 Tie Diameters

[mm] 1 200 28.7 259.2 10 280 2 550 28.7 259.2 11 622 3 700 28.7 259.2 16 768

Column Greatest Dimension[mm]

Minimum Tie Diameter [mm]

Minimum Bar Size

1 200 8 No. 10 2 550 11 No. 11 3 700 12 No. 16

117 | P a g e

C.4. Shear Wall Reinforcement

Because the shear wall does not require reinforcement to handle the shear load, and

because all moments that would otherwise act on the shear wall are taken up by

adjacent members, the shear walls need only be designed to meet minimum

reinforcement requirements:

ACI 14.3.2 Vertical Reinforcement

For reinforcement bars smaller than No. 16:

𝐴𝐴𝐴𝐴𝐴𝐴𝑎𝑎𝐴𝐴𝐴𝐴𝑖𝑖𝑛𝑛𝑓𝑓𝑟𝑟𝐴𝐴𝑐𝑐𝐴𝐴𝑚𝑚𝐴𝐴𝑛𝑛𝑧𝑧 ≥ 0.0012 ∗ 𝐴𝐴𝐴𝐴𝐴𝐴𝑎𝑎𝑐𝑐𝑟𝑟𝑛𝑛𝑐𝑐𝐴𝐴𝐴𝐴𝑧𝑧𝐴𝐴

𝐴𝐴𝐴𝐴𝐴𝐴𝑎𝑎𝑁𝑁𝑟𝑟 .10 𝑏𝑏𝑎𝑎𝐴𝐴 = 71𝑚𝑚𝑚𝑚2

For a 1-meter unit width at the bottom floor (wall thickness = 160mm):

𝐴𝐴𝐴𝐴𝐴𝐴𝑎𝑎𝐴𝐴𝐴𝐴𝑖𝑖𝑛𝑛𝑓𝑓𝑟𝑟𝐴𝐴𝑐𝑐𝐴𝐴𝑚𝑚𝐴𝐴𝑛𝑛𝑧𝑧 ≥ 0.0012 ∗ 160𝑚𝑚𝑚𝑚 ∗ 1000𝑚𝑚𝑚𝑚 = 192𝑚𝑚𝑚𝑚2

𝑆𝑆𝑝𝑝𝑎𝑎𝑐𝑐𝑖𝑖𝑛𝑛𝑔𝑔 𝑟𝑟𝑓𝑓 𝑁𝑁𝑟𝑟.10 𝑏𝑏𝑎𝑎𝐴𝐴 ≤ 360𝑚𝑚𝑚𝑚

For a 1-meter unit width at all other floors (wall thickness = 150mm):

𝐴𝐴𝐴𝐴𝐴𝐴𝑎𝑎𝐴𝐴𝐴𝐴𝑖𝑖𝑛𝑛𝑓𝑓𝑟𝑟𝐴𝐴𝑐𝑐𝐴𝐴𝑚𝑚𝐴𝐴𝑛𝑛𝑧𝑧 ≥ 0.0012 ∗ 150𝑚𝑚𝑚𝑚 ∗ 1000𝑚𝑚𝑚𝑚 = 180𝑚𝑚𝑚𝑚2

𝑆𝑆𝑝𝑝𝑎𝑎𝑐𝑐𝑖𝑖𝑛𝑛𝑔𝑔 𝑟𝑟𝑓𝑓 𝑁𝑁𝑟𝑟.10 𝑏𝑏𝑎𝑎𝐴𝐴 ≤ 390𝑚𝑚𝑚𝑚

ACI 14.3.3 Horizontal Reinforcement

𝐴𝐴𝐴𝐴𝐴𝐴𝑎𝑎𝐴𝐴𝐴𝐴𝑖𝑖𝑛𝑛𝑓𝑓𝑟𝑟𝐴𝐴𝑐𝑐𝐴𝐴𝑚𝑚𝐴𝐴𝑛𝑛𝑧𝑧 ≥ 0.0020 ∗ 𝐴𝐴𝐴𝐴𝐴𝐴𝑎𝑎𝑐𝑐𝑟𝑟𝑛𝑛𝑐𝑐𝐴𝐴𝐴𝐴𝑧𝑧𝐴𝐴

𝐴𝐴𝐴𝐴𝐴𝐴𝑎𝑎𝑁𝑁𝑟𝑟 .10 𝑏𝑏𝑎𝑎𝐴𝐴 = 71𝑚𝑚𝑚𝑚2

For a 1-meter unit height at the bottom floor (wall thickness = 160mm):

𝐴𝐴𝐴𝐴𝐴𝐴𝑎𝑎𝐴𝐴𝐴𝐴𝑖𝑖𝑛𝑛𝑓𝑓𝑟𝑟𝐴𝐴𝑐𝑐𝐴𝐴𝑚𝑚𝐴𝐴𝑛𝑛𝑧𝑧 ≥ 0.0012 ∗ 160𝑚𝑚𝑚𝑚 ∗ 1000𝑚𝑚𝑚𝑚 = 320𝑚𝑚𝑚𝑚2

𝑆𝑆𝑝𝑝𝑎𝑎𝑐𝑐𝑖𝑖𝑛𝑛𝑔𝑔 𝑟𝑟𝑓𝑓 𝑁𝑁𝑟𝑟.10 𝑏𝑏𝑎𝑎𝐴𝐴 ≤ 220𝑚𝑚𝑚𝑚

For a 1-meter unit height at all other floors (wall thickness = 150mm):

𝐴𝐴𝐴𝐴𝐴𝐴𝑎𝑎𝐴𝐴𝐴𝐴𝑖𝑖𝑛𝑛𝑓𝑓𝑟𝑟𝐴𝐴𝑐𝑐𝐴𝐴𝑚𝑚𝐴𝐴𝑛𝑛𝑧𝑧 ≥ 0.0012 ∗ 150𝑚𝑚𝑚𝑚 ∗ 1000𝑚𝑚𝑚𝑚 = 300𝑚𝑚𝑚𝑚2

𝑆𝑆𝑝𝑝𝑎𝑎𝑐𝑐𝑖𝑖𝑛𝑛𝑔𝑔 𝑟𝑟𝑓𝑓 𝑁𝑁𝑟𝑟.10 𝑏𝑏𝑎𝑎𝐴𝐴 ≤ 235𝑚𝑚𝑚𝑚

118 | P a g e

ACI 14.3.5 Maximum Spacing

𝑆𝑆𝑝𝑝𝑎𝑎𝑐𝑐𝑖𝑖𝑛𝑛𝑔𝑔 ≤ 450𝑚𝑚𝑚𝑚

or

𝑆𝑆𝑝𝑝𝑎𝑎𝑐𝑐𝑖𝑖𝑛𝑛𝑔𝑔 ≤ 3 ∗ 𝑧𝑧ℎ𝑖𝑖𝑐𝑐𝑖𝑖𝑛𝑛𝐴𝐴𝑠𝑠𝑠𝑠 (= 460𝑚𝑚𝑚𝑚 𝑓𝑓𝑟𝑟𝐴𝐴 𝑏𝑏𝑟𝑟𝑧𝑧𝑧𝑧𝑟𝑟𝑚𝑚 𝑓𝑓𝑙𝑙𝑟𝑟𝑟𝑟𝐴𝐴 𝑎𝑎𝑛𝑛𝑑𝑑 450𝑚𝑚𝑚𝑚 𝑓𝑓𝑟𝑟𝐴𝐴 𝑟𝑟𝑧𝑧ℎ𝐴𝐴𝐴𝐴 𝑓𝑓𝑙𝑙𝑟𝑟𝑟𝑟𝐴𝐴𝑠𝑠),

whichever is higher.

Therefore, the vertical spacing of 360mm and 390mm and the horizontal spacing of

220mm and 235mm for the bottom and other floors, respectively is acceptable.

Calculated by: JJU

Checked by: ALH

119 | P a g e

C.5. Water Usage Estimates

Table 58: Total Fixtures For Building, By Level

LEVEL FIXTURE TYPE QUANTITYLEVEL 0

SERVICE OR MOP BASIN 1

LEVEL 1TOILET 5URINAL 2BATHROOM SINK (LAVATORY) 7SHOWER 7DRINKING FOUNTAIN 2SERVICE OR MOP BASIN 1

LEVEL 2KITCHEN SINK 2TOILET 4URINAL 2BATHROOM SINK (LAVATORY) 4SHOWER 0DRINKING FOUNTAIN 2SERVICE OR MOP BASIN 1

LEVEL 3TOILET 4URINAL 2BATHROOM SINK (LAVATORY) 4DRINKING FOUNTAIN 2SERVICE OR MOP BASIN 1

LEVEL 4TOILET 9TOILET 9SHOWER 9BATHROOM SINK (LAVATORY) 9DRINKING FOUNTAIN 0BAR SINK 1SERVICE OR MOP BASIN 1

LEVEL 5, 6, AND 7TOILET 6BATHROOM SINK (LAVATORY) 6KITCHEN SINK 3DRINKING FOUNTAIN 6SERVICE OR MOP BASIN 3

LEVEL 8TOILET 3SHOWER 2BATHROOM SINK (LAVATORY) 5KITCHEN SINK 1DISHWASHER, DOMESTIC 1CLOTHES WASHER 1SERVICE OR MOP BASIN 1

120 | P a g e

Table 59a: Drainage Pipe Size Required for All Fixtures on Stack 1

LEVEL FIXTURE QUANTITYDRAINAGE

FIXTURE UNIT VALUES

TOTAL DFU

MINIMUM PIPE SIZE BASED ON TOTAL

DFU FOR HORIZONTAL

FIXTURE BRANCHFIXTURE BRANCH LEVEL 0

LEVEL 1 80mmTOILET 1 4 4URINAL 2 2 4URINAL 2 2 4BATHROOM SINK (LAVATORY) 3 1 3SHOWER 3 2 6DRINKING FOUNTAIN 0 0.5 0

17LEVEL 2 100mmLEVEL 2 100mm

KITCHEN SINK 2 2 4TOILET 4 4 16URINAL 2 2 4BATHROOM SINK (LAVATORY) 4 1 4SHOWER 0 2 0SHOWER 0 2 0DRINKING FOUNTAIN 2 0.5 1

29LEVEL 3 100mm

TOILET 4 4 16URINAL 2 2 4URINAL 2 2 4BATHROOM SINK (LAVATORY) 4 1 4DRINKING FOUNTAIN 2 0.5 1

25

121 | P a g e

LEVEL FIXTURE QUANTITYDRAINAGE

FIXTURE UNIT VALUES

TOTAL DFU

MINIMUM PIPE SIZE BASED ON TOTAL

DFU FOR HORIZONTAL

FIXTURE BRANCHFIXTURE BRANCH LEVEL 4 100mm

TOILET 4 4 16SHOWER 4 2 8BATHROOM SINK (LAVATORY) 4 1 4DRINKING FOUNTAIN 0 0 5 0DRINKING FOUNTAIN 0 0.5 0BAR SINK 1 1 1

29LEVEL 5, 6, AND 7 40mm

TOILET 0 4 0BATHROOM SINK (LAVATORY) 0 1 0BATHROOM SINK (LAVATORY) 0 1 0KITCHEN SINK 0 2 0DRINKING FOUNTAIN 2 0.5 1

1LEVEL 8 80mm

TOILET 1 4 4TOILET 1 4 4SHOWER 0 2 0BATHROOM SINK (LAVATORY) 1 1 1KITCHEN SINK 1 2 2DISHWASHER, DOMESTIC 1 2 2CLOTHES WASHER 1 3 3CLOTHES WASHER 1 3 3

12

Table 59b: Drainage Pipe Size Required for All Fixtures on Stack 1

122 | P a g e

LEVEL FIXTURE QUANTITYDRAINAGE

FIXTURE UNIT VALUES

TOTAL DFU

MINIMUM PIPE SIZE BASED ON TOTAL

DFU FOR HORIZONTAL

FIXTURE BRANCHFIXTURE BRANCH

115LEVEL 0 - LEVEL 4 100mmLEVEL 5 - LEVEL 8 80mm

TOTAL DFU OF STACK 1:

STACK SIZE CHOSEN BASED ON LARGEST SIZE REQUIRED BY A GIVEN LEVEL AND ALL THE LEVELS ABOVE IT BECAUSE STACK SIZE MAY NOT DECREASE AS GOING DOWN, IT MAY ONLY INCREASE.

Table 59c: Drainage Pipe Size Required for All Fixtures on Stack 1

123 | P a g e

Table 60a: Drainage Pipe Size Required for All Fixtures on Stack 2

LEVEL FIXTURE QUANTITYDRAINAGE

FIXTURE UNIT VALUES

TOTAL DFU

MINIMUM PIPE SIZE BASED ON TOTAL

DFU FOR HORIZONTAL

FIXTURE BRANCHFIXTURE BRANCH LEVEL 0 50mm

SERVICE OR MOP BASIN 1 3 33

LEVEL 1 100mmTOILET 4 4 16TOILET 4 4 16URINAL 0 2 0BATHROOM SINK (LAVATORY) 4 1 4SHOWER 4 2 8DRINKING FOUNTAIN 2 0.5 1SERVICE OR MOP BASIN 1 3 3SERVICE OR MOP BASIN 1 3 3

29LEVEL 2 40mm

KITCHEN SINK 0 2 0TOILET 0 4 0URINAL 0 2 0URINAL 0 2 0BATHROOM SINK (LAVATORY) 0 1 0SHOWER 0 2 0DRINKING FOUNTAIN 0 0.5 0SERVICE OR MOP BASIN 1 3 3

33LEVEL 3 40mm

TOILET 0 4 0URINAL 0 2 0BATHROOM SINK (LAVATORY) 0 1 0DRINKING FOUNTAIN 0 0 5 0DRINKING FOUNTAIN 0 0.5 0SERVICE OR MOP BASIN 1 3 3

3

124 | P a g e

LEVEL FIXTURE QUANTITYDRAINAGE

FIXTURE UNIT VALUES

TOTAL DFU

MINIMUM PIPE SIZE BASED ON TOTAL

DFU FOR HORIZONTAL

FIXTURE BRANCHFIXTURE BRANCH LEVEL 4 100mm

TOILET 5 4 20SHOWER 5 2 10BATHROOM SINK (LAVATORY) 5 1 5DRINKING FOUNTAIN 0 0 5 0DRINKING FOUNTAIN 0 0.5 0BAR SINK 0 1 0SERVICE OR MOP BASIN 1 3 3

38LEVEL 5, 6, AND 7 80mm

TOILET 2 4 8TOILET 2 4 8BATHROOM SINK (LAVATORY) 2 1 2KITCHEN SINK 1 2 2DRINKING FOUNTAIN 0 0.5 0SERVICE OR MOP BASIN 1 3 3

1515LEVEL 8 80mm

TOILET 2 4 8SHOWER 2 2 4BATHROOM SINK (LAVATORY) 4 1 4KITCHEN SINK 0 2 0KITCHEN SINK 0 2 0DISHWASHER, DOMESTIC 0 2 0CLOTHES WASHER 0 3 0SERVICE OR MOP BASIN 1 3 3

19

Table 60b: Drainage Pipe Size Required for All Fixtures on Stack 2

125 | P a g e

LEVEL FIXTURE QUANTITY

DRAINAGE FIXTURE UNIT

VALUES

TOTAL DFU

MINIMUM PIPE SIZE BASED ON TOTAL

DFU FOR HORIZONTAL

FIXTURE BRANCHFIXTURE BRANCH

140LEVEL 0 - LEVEL 4 100mmLEVEL 5 - LEVEL 8 80mm

TOTAL DFU OF STACK 2:

STACK SIZE CHOSEN BASED ON LARGEST SIZE REQUIRED BY A GIVEN LEVEL AND ALL THE LEVELS ABOVE IT BECAUSE STACK SIZE MAY NOT DECREASE AS GOING DOWN, IT MAY ONLY INCREASE.

Table 60c: Drainage Pipe Size Required for All Fixtures on Stack 2

126 | P a g e

C.6. Caisson Foundation Cost-Estimate Calculations

Below is an example calculation for Caisson Design 1. Calculations were done in Excel; a screenshot of this document is shown in Figure 31.

127 | P a g e

128 | P a g e

Calculated by: ALH

Checked by: JJU

129 | P a g e

130 | P a g e

Figure 31: Calculations from Excel Document "Foundation Design for Cost Estimate Only.xlsx"