final presentation - pennsylvania state university › ae › thesis › portfolios › 2010 ›...
TRANSCRIPT
4/11/2010
1
Kyle GoodyearBAE in Construction ManagementPennsylvania State UniversitySenior Thesis PresentationApril 12, 2010
Presentation Outline
Project Background InformationSolar Energy Collection
Electrical BreadthPrecast Concrete Walls
Special Thanks to:
Kinsley Construction, Inc.
Structural BreadthHangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers
167th Airlift Wing
Penn State AE Faculty
4/11/2010
2
Project Background
Client: 167th Airlift Wing – WV Air National GuardProject Background InformationProject Background InformationSolar Energy Collection
Electrical BreadthPrecast Concrete Walls
Presentation Outline
Site: Martinsburg, WVPrecast Concrete Walls
Structural BreadthHangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers
PurposeC-5 Galaxy Conversion Project
WV Eastern Regional Airport
Project Background
Project Background InformationProject Background InformationSolar Energy Collection
Electrical BreadthPrecast Concrete Walls
Presentation OutlineDesign/Build Contract
Kinsley Construction – Design/Build Manager○ Holds all subcontractsLSC Design – contracted by Kinsley Construction
167th Airlift WingOwner
Kinsley Construction
Precast Concrete WallsStructural Breadth
Hangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers
g y y○ Holds all design team subcontractsAll contracts based on lump sum
LSC Design
Design Team
Subcontractors
4/11/2010
3
Project Background
Cost: $26.8 millionProject Background InformationProject Background InformationSolar Energy Collection
Electrical BreadthPrecast Concrete Walls
Presentation Outline
ScheduleNTP for design: October 2008Precast Concrete Walls
Structural BreadthHangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers
NTP for design: October 2008Office Mobilization: March 2009Scheduled Completion: March 2010Expected Completion: July 2010 – extensions granted for additions to scope and weather delays
Breadth Topics
Electrical Breadth StudyAddition of solar collection system
Project Background InformationProject Background InformationSolar Energy Collection
Electrical BreadthPrecast Concrete Walls
Presentation Outline
St t l B dth St dPrecast Concrete WallsStructural Breadth
Hangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers
Structural Breadth StudyDesign of load-bearing concrete walls in place of masonry
4/11/2010
4
Solar Energy Collection
Goal of AnalysisDetermine if the installation of Solyndra panels is a positive addition○ Potential energy production
Project Background InformationSolar Energy CollectionSolar Energy Collection
Electrical BreadthPrecast Concrete Walls
Presentation Outline
○ Building power usage○ Purchase and installation costs○ Payback period
Precast Concrete WallsStructural Breadth
Hangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers
Solar Energy Collection
Solyndra, Inc. PanelsArray of cylindersCollects direct, diffuse, and reflected light○ Reflected light gain based on roof material
Project Background InformationSolar Energy CollectionSolar Energy Collection
Electrical BreadthPrecast Concrete Walls
Presentation Outline
e ec ed g ga based o oo a e aAirflow between cylinders○ Reduced wind uplift○ Cooler operating temperatures
Precast Concrete WallsStructural Breadth
Hangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers
4/11/2010
5
Electrical Breadth Study
How many Solyndra panels can be installed on the roof?
Orientation of buildingDimensions of panels vs. Dimensions of roof
Project Background InformationSolar Energy CollectionSolar Energy Collection
Electrical BreadthElectrical BreadthPrecast Concrete Walls
Presentation Outline
Dimensions of panels vs. Dimensions of roofPrecast Concrete WallsStructural Breadth
Hangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers
3 sections of usable roof space on SW side13 panels lengthwise along slope of roof78 panels across the roof
1014 panels total
Electrical Breadth Study
Energy Production PotentialPower Rating of Solyndra panelMonthly insolation values for locationMax annual output: 274 kWh/panel
Project Background InformationSolar Energy CollectionSolar Energy Collection
Electrical BreadthElectrical BreadthPrecast Concrete Walls
Presentation Outline
Max annual output: 274 kWh/panelReflectivity reduction: 88%Potential annual output: 241 kWh/panel
241kWh/panel/year x 1014 panels = 244,374 kWh/year
Precast Concrete WallsStructural Breadth
Hangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers
4/11/2010
6
Electrical Breadth Study
Building Energy UsageExisting hangar energy usageAverage office energy usageTotal Expected Energy Usage = 213,773 kWh/year
Project Background InformationSolar Energy CollectionSolar Energy Collection
Electrical BreadthElectrical BreadthPrecast Concrete Walls
Presentation Outline
Total Expected Energy Usage 213,773 kWh/yearPrecast Concrete WallsStructural Breadth
Hangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers
Cost of Installing Solyndra System$7 per Watt per panel$7/W/panel x 200W x 1014 panels$1,419,600 to purchase and install
Electrical Breadth Study
Payback Period of SystemCost of electricity: 6.64 cents per kWh in WVExpected savings plus sale of electricity ○ $0.0664/kWh x 244,374 kWh/year = $16, 226/year
Project Background InformationSolar Energy CollectionSolar Energy Collection
Electrical BreadthElectrical BreadthPrecast Concrete Walls
Presentation Outline
$0 066 / ,3 /yea $ 6, 6/yeaPrecast Concrete WallsStructural Breadth
Hangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers
$1,419,600 / $16,226/year = 87.5 years
4/11/2010
7
Conclusion and Recommendation
System produces more than building uses
Payback period is extremely longLo cost of energ for project location
Project Background InformationSolar Energy CollectionSolar Energy Collection
Electrical BreadthElectrical BreadthPrecast Concrete Walls
Presentation Outline
Low cost of energy for project locationMore feasible in higher cost region
Precast Concrete WallsStructural Breadth
Hangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers
Recommendation: Do not install Solyndra system on this project.
Precast Concrete Walls
Goal of AnalysisIs precast concrete a better option than CMU for wall construction?○ Exterior façade
Project Background InformationSolar Energy Collection
Electrical BreadthPrecast Concrete WallsPrecast Concrete Walls
Presentation Outline
○ Interior load-bearing wallsPrecast Concrete WallsPrecast Concrete Walls
Structural BreadthHangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers
4/11/2010
8
Precast Concrete Walls
Exterior FaçadeCurrently split-face CMU to match existing buildingsCarbon Cast panels○ Thin-brick technology to match aesthetics
Project Background InformationSolar Energy Collection
Electrical BreadthPrecast Concrete WallsPrecast Concrete Walls
Presentation Outline
b c ec o ogy o a c aes e cs○ Produced in controlled conditions○ Higher quality product than masonry
Precast Concrete WallsPrecast Concrete WallsStructural Breadth
Hangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers
Structural Breadth Study
Load DeterminationDead Load: 21.3 PSFLive Load: 20 PSF
Project Background InformationSolar Energy Collection
Electrical BreadthPrecast Concrete WallsPrecast Concrete Walls
Presentation Outline
PD = 1193 lbsPL = 1120 lbsPrecast Concrete WallsPrecast Concrete Walls
Structural BreadthStructural BreadthHangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers
Strength Design MethodLoad combination: 1.2D + 1.6LTotal Axial Load = 3.22 kips
PU = 1.2PD + 1.6PL = 3223 lbs = 3.22 kips
4/11/2010
9
Structural Breadth Study
Using 8” wall thicknessBearing CapacityAxial Load Capacity
Project Background InformationSolar Energy Collection
Electrical BreadthPrecast Concrete WallsPrecast Concrete Walls
Presentation Outline
Precast Concrete WallsPrecast Concrete WallsStructural BreadthStructural Breadth
Hangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers
Minimum Reinforcement#4’s @ 18”oc in vertical direction#4’s @ 12”oc in horizontal direction
Structural Breadth Study
Cost ComparisonMasonry package: $230,011Precast package: $506,084○ $38/SF estimate from High Concrete
Project Background InformationSolar Energy Collection
Electrical BreadthPrecast Concrete WallsPrecast Concrete Walls
Presentation Outline
$38/S es a e o g Co c e ePrecast Concrete WallsPrecast Concrete WallsStructural BreadthStructural Breadth
Hangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers
Increased Floor SpaceChange from 12” masonry to 8” concrete walls117 SF added at $340/SF$39,720 worth additional usable space
4/11/2010
10
Structural Breadth Study
Schedule ComparisonMasonry package: 25 days on-sitePrecast concrete package: 15 days on-siteNot on critical path: does not change project schedule
Project Background InformationSolar Energy Collection
Electrical BreadthPrecast Concrete WallsPrecast Concrete Walls
Presentation OutlineMASONRY LOGISTICS PLAN
Not on critical path: does not change project schedulePrecast Concrete WallsPrecast Concrete WallsStructural BreadthStructural Breadth
Hangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers
Productivity ImpactFewer workers for precastMore moving equipment for precast
PRECAST LOGISTICS PLAN
Conclusion and Recommendation
Cost of change is more than doubleOverall schedule not reducedIncreased floor spaceHi h lit f d
Project Background InformationSolar Energy Collection
Electrical BreadthPrecast Concrete WallsPrecast Concrete Walls
Presentation Outline
Higher quality facadePrecast Concrete WallsPrecast Concrete WallsStructural BreadthStructural Breadth
Hangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers
Recommendation: Use the masonry system as designed instead of precast concrete option.
4/11/2010
11
Hangar Slab Sequence
Goal of AnalysisDetermine most efficient sequence for concrete placement in hangar area○ Cost
Project Background InformationSolar Energy Collection
Electrical BreadthPrecast Concrete Walls
Presentation Outline
○ Duration○ Productivity
Precast Concrete WallsStructural Breadth
Hangar Slab SequenceHangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers
Hangar Slab Sequence
Industry SurveyLarger pour size = higher productivity
Project Background InformationSolar Energy Collection
Electrical BreadthPrecast Concrete Walls
Presentation Outline
3 SequencesPrecast Concrete WallsStructural Breadth
Hangar Slab SequenceHangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers
3 SequencesAs-builtMore pours/smaller widthLess pours/greater width
4/11/2010
12
Hangar Slab Sequence
Cost and Duration ComparisonLarger pour width costs less and completed fasterSmaller pour width costs more and completed slower
Project Background InformationSolar Energy Collection
Electrical BreadthPrecast Concrete Walls
Presentation Outline
Precast Concrete WallsStructural Breadth
Hangar Slab SequenceHangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers
Quality ComparisonLarger width makes finishing more difficultHigher quality with smaller width pours
Conclusion and Recommendation
Quality vs. Cost
Hangar dimensions
Project Background InformationSolar Energy Collection
Electrical BreadthPrecast Concrete Walls
Presentation Outline
Precast Concrete WallsStructural Breadth
Hangar Slab SequenceHangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers
Recommendation: Employ the slab pour sequence that was chosen by project team.
Slightly larger pours if dimensions allow
4/11/2010
13
Design/Build Productivity
Goal of AnalysisDoes design/build construction increase productivity for the management and design team as well as in the field?
Project Background InformationSolar Energy Collection
Electrical BreadthPrecast Concrete Walls
Presentation Outline
Precast Concrete WallsStructural Breadth
Hangar Slab SequenceDesign/Build ProductivityDesign/Build ProductivityConclusionsQuestions and Answers
Design/Build Productivity
MeasurementsPreconstruction activity timePaperwork during constructionAbility to work ahead
Project Background InformationSolar Energy Collection
Electrical BreadthPrecast Concrete Walls
Presentation Outline
Ability to work aheadPrecast Concrete WallsStructural Breadth
Hangar Slab SequenceDesign/Build ProductivityDesign/Build ProductivityConclusionsQuestions and Answers
4/11/2010
14
Design/Build Productivity
Project Background InformationSolar Energy Collection
Electrical BreadthPrecast Concrete Walls
Presentation OutlineResearch Steps
Project Manager SurveyOwner PerspectiveCauses of DelaysPrecast Concrete Walls
Structural BreadthHangar Slab SequenceDesign/Build ProductivityDesign/Build ProductivityConclusionsQuestions and Answers
Causes of DelaysPotential Benefits
Design/Build Productivity
Findings of ResearchPreconstruction time reduced○ Design is better the first time○ Estimating is completed simultaneously
Project Background InformationSolar Energy Collection
Electrical BreadthPrecast Concrete Walls
Presentation Outline
Less paperwork during construction○ RFI’s handled in open meetings○ Change Orders almost completely eliminatedg p y
○ Subcontractors acquired earlier for design-assistPrecast Concrete Walls
Structural BreadthHangar Slab SequenceDesign/Build ProductivityDesign/Build ProductivityConclusionsQuestions and Answers
g p y○ Submittal process much shorter: subcontractors
know the specifications
4/11/2010
15
Design/Build Productivity
Findings of Research continuedAble to start activities sooner○ Procurement of long-lead items○ Subcontractors determine means and methods of
Project Background InformationSolar Energy Collection
Electrical BreadthPrecast Concrete Walls
Presentation Outline
Success of delivery method depends on the team○ Good contractor with good design can make any
method workconstruction during design phase
○ Subcontractors can schedule labor and equipment to reduce chance of delays
Precast Concrete WallsStructural Breadth
Hangar Slab SequenceDesign/Build ProductivityDesign/Build ProductivityConclusionsQuestions and Answers
○ D/B requires background knowledge of project○ Owner must know what they want
Conclusion
If the design/build team and owner coordinate well, there is potential for higher productivity
Project Background InformationSolar Energy Collection
Electrical BreadthPrecast Concrete Walls
Presentation Outline
Precast Concrete WallsStructural Breadth
Hangar Slab SequenceDesign/Build ProductivityDesign/Build ProductivityConclusionsQuestions and Answers
4/11/2010
16
Conclusions
Project Background InformationSolar Energy Collection
Electrical BreadthPrecast Concrete Walls
Presentation OutlineProject Team made good decisions in selection of systems and design methodsFor other projects, proposed changes may be more beneficialPrecast Concrete Walls
Structural BreadthHangar Slab SequenceDesign/Build ProductivityConclusionsConclusionsQuestions and Answers
more beneficialUse of Design/Build delivery should continue to be implemented at greater levels
QUESTIONS?
Project Background InformationSolar Energy Collection
Electrical BreadthPrecast Concrete Walls
Presentation Outline
QUESTIONS?Precast Concrete WallsStructural Breadth
Hangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and AnswersQuestions and Answers