final presentation - pennsylvania state university › ae › thesis › portfolios › 2010 ›...

16
4/11/2010 1 Kyle Goodyear BAE in Construction Management Pennsylvania State University Senior Thesis Presentation April 12, 2010 Presentation Outline Project Background Information Solar Energy Collection y Electrical Breadth Precast Concrete Walls Special Thanks to: Kinsley Construction, Inc. y Structural Breadth Hangar Slab Sequence Design/Build Productivity Conclusions Questions and Answers 167 th Airlift Wing Penn State AE Faculty

Upload: others

Post on 07-Jun-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Final Presentation - Pennsylvania State University › ae › thesis › portfolios › 2010 › keg5031... · 4/11/2010 4 Solar Energy Collection Goal of Analysis yDetermine if the

4/11/2010

1

Kyle GoodyearBAE in Construction ManagementPennsylvania State UniversitySenior Thesis PresentationApril 12, 2010

Presentation Outline

Project Background InformationSolar Energy Collection

Electrical BreadthPrecast Concrete Walls

Special Thanks to:

Kinsley Construction, Inc.

Structural BreadthHangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers

167th Airlift Wing

Penn State AE Faculty

Page 2: Final Presentation - Pennsylvania State University › ae › thesis › portfolios › 2010 › keg5031... · 4/11/2010 4 Solar Energy Collection Goal of Analysis yDetermine if the

4/11/2010

2

Project Background

Client: 167th Airlift Wing – WV Air National GuardProject Background InformationProject Background InformationSolar Energy Collection

Electrical BreadthPrecast Concrete Walls

Presentation Outline

Site: Martinsburg, WVPrecast Concrete Walls

Structural BreadthHangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers

PurposeC-5 Galaxy Conversion Project

WV Eastern Regional Airport

Project Background

Project Background InformationProject Background InformationSolar Energy Collection

Electrical BreadthPrecast Concrete Walls

Presentation OutlineDesign/Build Contract

Kinsley Construction – Design/Build Manager○ Holds all subcontractsLSC Design – contracted by Kinsley Construction

167th Airlift WingOwner

Kinsley Construction

Precast Concrete WallsStructural Breadth

Hangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers

g y y○ Holds all design team subcontractsAll contracts based on lump sum

LSC Design

Design Team

Subcontractors

Page 3: Final Presentation - Pennsylvania State University › ae › thesis › portfolios › 2010 › keg5031... · 4/11/2010 4 Solar Energy Collection Goal of Analysis yDetermine if the

4/11/2010

3

Project Background

Cost: $26.8 millionProject Background InformationProject Background InformationSolar Energy Collection

Electrical BreadthPrecast Concrete Walls

Presentation Outline

ScheduleNTP for design: October 2008Precast Concrete Walls

Structural BreadthHangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers

NTP for design: October 2008Office Mobilization: March 2009Scheduled Completion: March 2010Expected Completion: July 2010 – extensions granted for additions to scope and weather delays

Breadth Topics

Electrical Breadth StudyAddition of solar collection system

Project Background InformationProject Background InformationSolar Energy Collection

Electrical BreadthPrecast Concrete Walls

Presentation Outline

St t l B dth St dPrecast Concrete WallsStructural Breadth

Hangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers

Structural Breadth StudyDesign of load-bearing concrete walls in place of masonry

Page 4: Final Presentation - Pennsylvania State University › ae › thesis › portfolios › 2010 › keg5031... · 4/11/2010 4 Solar Energy Collection Goal of Analysis yDetermine if the

4/11/2010

4

Solar Energy Collection

Goal of AnalysisDetermine if the installation of Solyndra panels is a positive addition○ Potential energy production

Project Background InformationSolar Energy CollectionSolar Energy Collection

Electrical BreadthPrecast Concrete Walls

Presentation Outline

○ Building power usage○ Purchase and installation costs○ Payback period

Precast Concrete WallsStructural Breadth

Hangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers

Solar Energy Collection

Solyndra, Inc. PanelsArray of cylindersCollects direct, diffuse, and reflected light○ Reflected light gain based on roof material

Project Background InformationSolar Energy CollectionSolar Energy Collection

Electrical BreadthPrecast Concrete Walls

Presentation Outline

e ec ed g ga based o oo a e aAirflow between cylinders○ Reduced wind uplift○ Cooler operating temperatures

Precast Concrete WallsStructural Breadth

Hangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers

Page 5: Final Presentation - Pennsylvania State University › ae › thesis › portfolios › 2010 › keg5031... · 4/11/2010 4 Solar Energy Collection Goal of Analysis yDetermine if the

4/11/2010

5

Electrical Breadth Study

How many Solyndra panels can be installed on the roof?

Orientation of buildingDimensions of panels vs. Dimensions of roof

Project Background InformationSolar Energy CollectionSolar Energy Collection

Electrical BreadthElectrical BreadthPrecast Concrete Walls

Presentation Outline

Dimensions of panels vs. Dimensions of roofPrecast Concrete WallsStructural Breadth

Hangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers

3 sections of usable roof space on SW side13 panels lengthwise along slope of roof78 panels across the roof

1014 panels total

Electrical Breadth Study

Energy Production PotentialPower Rating of Solyndra panelMonthly insolation values for locationMax annual output: 274 kWh/panel

Project Background InformationSolar Energy CollectionSolar Energy Collection

Electrical BreadthElectrical BreadthPrecast Concrete Walls

Presentation Outline

Max annual output: 274 kWh/panelReflectivity reduction: 88%Potential annual output: 241 kWh/panel

241kWh/panel/year x 1014 panels = 244,374 kWh/year

Precast Concrete WallsStructural Breadth

Hangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers

Page 6: Final Presentation - Pennsylvania State University › ae › thesis › portfolios › 2010 › keg5031... · 4/11/2010 4 Solar Energy Collection Goal of Analysis yDetermine if the

4/11/2010

6

Electrical Breadth Study

Building Energy UsageExisting hangar energy usageAverage office energy usageTotal Expected Energy Usage = 213,773 kWh/year

Project Background InformationSolar Energy CollectionSolar Energy Collection

Electrical BreadthElectrical BreadthPrecast Concrete Walls

Presentation Outline

Total Expected Energy Usage 213,773 kWh/yearPrecast Concrete WallsStructural Breadth

Hangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers

Cost of Installing Solyndra System$7 per Watt per panel$7/W/panel x 200W x 1014 panels$1,419,600 to purchase and install

Electrical Breadth Study

Payback Period of SystemCost of electricity: 6.64 cents per kWh in WVExpected savings plus sale of electricity ○ $0.0664/kWh x 244,374 kWh/year = $16, 226/year

Project Background InformationSolar Energy CollectionSolar Energy Collection

Electrical BreadthElectrical BreadthPrecast Concrete Walls

Presentation Outline

$0 066 / ,3 /yea $ 6, 6/yeaPrecast Concrete WallsStructural Breadth

Hangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers

$1,419,600 / $16,226/year = 87.5 years

Page 7: Final Presentation - Pennsylvania State University › ae › thesis › portfolios › 2010 › keg5031... · 4/11/2010 4 Solar Energy Collection Goal of Analysis yDetermine if the

4/11/2010

7

Conclusion and Recommendation

System produces more than building uses

Payback period is extremely longLo cost of energ for project location

Project Background InformationSolar Energy CollectionSolar Energy Collection

Electrical BreadthElectrical BreadthPrecast Concrete Walls

Presentation Outline

Low cost of energy for project locationMore feasible in higher cost region

Precast Concrete WallsStructural Breadth

Hangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers

Recommendation: Do not install Solyndra system on this project.

Precast Concrete Walls

Goal of AnalysisIs precast concrete a better option than CMU for wall construction?○ Exterior façade

Project Background InformationSolar Energy Collection

Electrical BreadthPrecast Concrete WallsPrecast Concrete Walls

Presentation Outline

○ Interior load-bearing wallsPrecast Concrete WallsPrecast Concrete Walls

Structural BreadthHangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers

Page 8: Final Presentation - Pennsylvania State University › ae › thesis › portfolios › 2010 › keg5031... · 4/11/2010 4 Solar Energy Collection Goal of Analysis yDetermine if the

4/11/2010

8

Precast Concrete Walls

Exterior FaçadeCurrently split-face CMU to match existing buildingsCarbon Cast panels○ Thin-brick technology to match aesthetics

Project Background InformationSolar Energy Collection

Electrical BreadthPrecast Concrete WallsPrecast Concrete Walls

Presentation Outline

b c ec o ogy o a c aes e cs○ Produced in controlled conditions○ Higher quality product than masonry

Precast Concrete WallsPrecast Concrete WallsStructural Breadth

Hangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers

Structural Breadth Study

Load DeterminationDead Load: 21.3 PSFLive Load: 20 PSF

Project Background InformationSolar Energy Collection

Electrical BreadthPrecast Concrete WallsPrecast Concrete Walls

Presentation Outline

PD = 1193 lbsPL = 1120 lbsPrecast Concrete WallsPrecast Concrete Walls

Structural BreadthStructural BreadthHangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers

Strength Design MethodLoad combination: 1.2D + 1.6LTotal Axial Load = 3.22 kips

PU = 1.2PD + 1.6PL = 3223 lbs = 3.22 kips

Page 9: Final Presentation - Pennsylvania State University › ae › thesis › portfolios › 2010 › keg5031... · 4/11/2010 4 Solar Energy Collection Goal of Analysis yDetermine if the

4/11/2010

9

Structural Breadth Study

Using 8” wall thicknessBearing CapacityAxial Load Capacity

Project Background InformationSolar Energy Collection

Electrical BreadthPrecast Concrete WallsPrecast Concrete Walls

Presentation Outline

Precast Concrete WallsPrecast Concrete WallsStructural BreadthStructural Breadth

Hangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers

Minimum Reinforcement#4’s @ 18”oc in vertical direction#4’s @ 12”oc in horizontal direction

Structural Breadth Study

Cost ComparisonMasonry package: $230,011Precast package: $506,084○ $38/SF estimate from High Concrete

Project Background InformationSolar Energy Collection

Electrical BreadthPrecast Concrete WallsPrecast Concrete Walls

Presentation Outline

$38/S es a e o g Co c e ePrecast Concrete WallsPrecast Concrete WallsStructural BreadthStructural Breadth

Hangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers

Increased Floor SpaceChange from 12” masonry to 8” concrete walls117 SF added at $340/SF$39,720 worth additional usable space

Page 10: Final Presentation - Pennsylvania State University › ae › thesis › portfolios › 2010 › keg5031... · 4/11/2010 4 Solar Energy Collection Goal of Analysis yDetermine if the

4/11/2010

10

Structural Breadth Study

Schedule ComparisonMasonry package: 25 days on-sitePrecast concrete package: 15 days on-siteNot on critical path: does not change project schedule

Project Background InformationSolar Energy Collection

Electrical BreadthPrecast Concrete WallsPrecast Concrete Walls

Presentation OutlineMASONRY LOGISTICS PLAN

Not on critical path: does not change project schedulePrecast Concrete WallsPrecast Concrete WallsStructural BreadthStructural Breadth

Hangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers

Productivity ImpactFewer workers for precastMore moving equipment for precast

PRECAST LOGISTICS PLAN

Conclusion and Recommendation

Cost of change is more than doubleOverall schedule not reducedIncreased floor spaceHi h lit f d

Project Background InformationSolar Energy Collection

Electrical BreadthPrecast Concrete WallsPrecast Concrete Walls

Presentation Outline

Higher quality facadePrecast Concrete WallsPrecast Concrete WallsStructural BreadthStructural Breadth

Hangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers

Recommendation: Use the masonry system as designed instead of precast concrete option.

Page 11: Final Presentation - Pennsylvania State University › ae › thesis › portfolios › 2010 › keg5031... · 4/11/2010 4 Solar Energy Collection Goal of Analysis yDetermine if the

4/11/2010

11

Hangar Slab Sequence

Goal of AnalysisDetermine most efficient sequence for concrete placement in hangar area○ Cost

Project Background InformationSolar Energy Collection

Electrical BreadthPrecast Concrete Walls

Presentation Outline

○ Duration○ Productivity

Precast Concrete WallsStructural Breadth

Hangar Slab SequenceHangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers

Hangar Slab Sequence

Industry SurveyLarger pour size = higher productivity

Project Background InformationSolar Energy Collection

Electrical BreadthPrecast Concrete Walls

Presentation Outline

3 SequencesPrecast Concrete WallsStructural Breadth

Hangar Slab SequenceHangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers

3 SequencesAs-builtMore pours/smaller widthLess pours/greater width

Page 12: Final Presentation - Pennsylvania State University › ae › thesis › portfolios › 2010 › keg5031... · 4/11/2010 4 Solar Energy Collection Goal of Analysis yDetermine if the

4/11/2010

12

Hangar Slab Sequence

Cost and Duration ComparisonLarger pour width costs less and completed fasterSmaller pour width costs more and completed slower

Project Background InformationSolar Energy Collection

Electrical BreadthPrecast Concrete Walls

Presentation Outline

Precast Concrete WallsStructural Breadth

Hangar Slab SequenceHangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers

Quality ComparisonLarger width makes finishing more difficultHigher quality with smaller width pours

Conclusion and Recommendation

Quality vs. Cost

Hangar dimensions

Project Background InformationSolar Energy Collection

Electrical BreadthPrecast Concrete Walls

Presentation Outline

Precast Concrete WallsStructural Breadth

Hangar Slab SequenceHangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and Answers

Recommendation: Employ the slab pour sequence that was chosen by project team.

Slightly larger pours if dimensions allow

Page 13: Final Presentation - Pennsylvania State University › ae › thesis › portfolios › 2010 › keg5031... · 4/11/2010 4 Solar Energy Collection Goal of Analysis yDetermine if the

4/11/2010

13

Design/Build Productivity

Goal of AnalysisDoes design/build construction increase productivity for the management and design team as well as in the field?

Project Background InformationSolar Energy Collection

Electrical BreadthPrecast Concrete Walls

Presentation Outline

Precast Concrete WallsStructural Breadth

Hangar Slab SequenceDesign/Build ProductivityDesign/Build ProductivityConclusionsQuestions and Answers

Design/Build Productivity

MeasurementsPreconstruction activity timePaperwork during constructionAbility to work ahead

Project Background InformationSolar Energy Collection

Electrical BreadthPrecast Concrete Walls

Presentation Outline

Ability to work aheadPrecast Concrete WallsStructural Breadth

Hangar Slab SequenceDesign/Build ProductivityDesign/Build ProductivityConclusionsQuestions and Answers

Page 14: Final Presentation - Pennsylvania State University › ae › thesis › portfolios › 2010 › keg5031... · 4/11/2010 4 Solar Energy Collection Goal of Analysis yDetermine if the

4/11/2010

14

Design/Build Productivity

Project Background InformationSolar Energy Collection

Electrical BreadthPrecast Concrete Walls

Presentation OutlineResearch Steps

Project Manager SurveyOwner PerspectiveCauses of DelaysPrecast Concrete Walls

Structural BreadthHangar Slab SequenceDesign/Build ProductivityDesign/Build ProductivityConclusionsQuestions and Answers

Causes of DelaysPotential Benefits

Design/Build Productivity

Findings of ResearchPreconstruction time reduced○ Design is better the first time○ Estimating is completed simultaneously

Project Background InformationSolar Energy Collection

Electrical BreadthPrecast Concrete Walls

Presentation Outline

Less paperwork during construction○ RFI’s handled in open meetings○ Change Orders almost completely eliminatedg p y

○ Subcontractors acquired earlier for design-assistPrecast Concrete Walls

Structural BreadthHangar Slab SequenceDesign/Build ProductivityDesign/Build ProductivityConclusionsQuestions and Answers

g p y○ Submittal process much shorter: subcontractors

know the specifications

Page 15: Final Presentation - Pennsylvania State University › ae › thesis › portfolios › 2010 › keg5031... · 4/11/2010 4 Solar Energy Collection Goal of Analysis yDetermine if the

4/11/2010

15

Design/Build Productivity

Findings of Research continuedAble to start activities sooner○ Procurement of long-lead items○ Subcontractors determine means and methods of

Project Background InformationSolar Energy Collection

Electrical BreadthPrecast Concrete Walls

Presentation Outline

Success of delivery method depends on the team○ Good contractor with good design can make any

method workconstruction during design phase

○ Subcontractors can schedule labor and equipment to reduce chance of delays

Precast Concrete WallsStructural Breadth

Hangar Slab SequenceDesign/Build ProductivityDesign/Build ProductivityConclusionsQuestions and Answers

○ D/B requires background knowledge of project○ Owner must know what they want

Conclusion

If the design/build team and owner coordinate well, there is potential for higher productivity

Project Background InformationSolar Energy Collection

Electrical BreadthPrecast Concrete Walls

Presentation Outline

Precast Concrete WallsStructural Breadth

Hangar Slab SequenceDesign/Build ProductivityDesign/Build ProductivityConclusionsQuestions and Answers

Page 16: Final Presentation - Pennsylvania State University › ae › thesis › portfolios › 2010 › keg5031... · 4/11/2010 4 Solar Energy Collection Goal of Analysis yDetermine if the

4/11/2010

16

Conclusions

Project Background InformationSolar Energy Collection

Electrical BreadthPrecast Concrete Walls

Presentation OutlineProject Team made good decisions in selection of systems and design methodsFor other projects, proposed changes may be more beneficialPrecast Concrete Walls

Structural BreadthHangar Slab SequenceDesign/Build ProductivityConclusionsConclusionsQuestions and Answers

more beneficialUse of Design/Build delivery should continue to be implemented at greater levels

QUESTIONS?

Project Background InformationSolar Energy Collection

Electrical BreadthPrecast Concrete Walls

Presentation Outline

QUESTIONS?Precast Concrete WallsStructural Breadth

Hangar Slab SequenceDesign/Build ProductivityConclusionsQuestions and AnswersQuestions and Answers