final geotechnical engineering report
TRANSCRIPT
Final Geotechnical
Engineering Report Waverly Swim Club Pond Dam
Albemarle Road
Charlotte, North Carolina
July 16, 2015
Project No. 71135018
Prepared for:
Dewberry and Davis, Inc.
Charlotte, North Carolina
Prepared by:
Terracon Consultants, Inc.
Charlotte, North Carolina
Final Geotechnical Engineering Report Waverly Swim Club Pond Dam ■ Charlotte, North Carolina July 16, 2015 ■ Terracon Project No. 71135018
Responsive ■ Resourceful ■ Reliable i
TABLE OF CONTENTS
Page EXECUTIVE SUMMARY ............................................................................................................ ii 1.0 INTRODUCTION ............................................................................................................. 1 2.0 PROJECT INFORMATION ............................................................................................. 1
2.1 Site Location and Description .............................................................................. 1
2.2 Project Description ............................................................................................... 2 3.0 SUBSURFACE CONDITIONS ........................................................................................ 2
3.1 Geology ............................................................................................................... 2
3.2 Typical Profile ...................................................................................................... 3
3.3 Groundwater ........................................................................................................ 4 4.0 RECOMMENDATIONS FOR DESIGN AND CONSTRUCTION ...................................... 5
4.1 Geotechnical Considerations ............................................................................... 5
4.2 Slope Stability ...................................................................................................... 6
4.3 Earthwork ............................................................................................................ 6
4.3.1 Site Preparation ........................................................................................ 6
4.3.2 Material Types .......................................................................................... 7
4.3.3 Compaction Requirements ....................................................................... 8
4.3.4 Earthwork Construction Considerations .................................................... 9
4.3.5 Excavations .............................................................................................. 9
4.4 Foundations ........................................................................................................ 10
4.4.1 Foundation Design Recommendations ................................................... 10
4.4.2 Pipe Support Cradle Considerations ....................................................... 11
4.4.3 Foundation Construction Considerations ................................................ 11
4.5 Filter Diaphragm and Underdrain ........................................................................ 12
4.5.1 Filter Diaphragm Considerations ............................................................ 12
4.5.2 Underdrain Considerations ..................................................................... 12
4.6 Lateral Earth Pressures ..................................................................................... 12 5.0 GENERAL COMMENTS ............................................................................................... 14
APPENDIX A – FIELD EXPLORATION
Exhibit A-1 Site Vicinity Plan
Exhibit A-2 Boring Location Plan
Exhibit A-3 Field Exploration Description
Exhibits A-4 to A-11 Boring Logs
APPENDIX B – LABORATORY TESTING
Exhibit B-1 Laboratory Testing
APPENDIX C – SUPPORTING DOCUMENTS
Exhibit C-1 General Notes
Exhibit C-2 Unified Soil Classification System
Final Geotechnical Engineering Report Waverly Swim Club Pond Dam ■ Charlotte, North Carolina July 16, 2015 ■ Terracon Project No. 71135018
Responsive ■ Resourceful ■ Reliable ii
EXECUTIVE SUMMARY
A geotechnical evaluation has been performed for the existing Waverly Swim Club Pond Dam in
Charlotte, North Carolina. A total of eight (8) borings, designated W-01 through W-05 and W-HA-
01 through W-HA-03, were performed to depths ranging from approximately 4 to 30 feet below
the ground surface along the existing dam.
Based on the information obtained from our subsurface exploration, the site can be developed for
the proposed project. The following geotechnical considerations were identified:
Based on the data obtained from our subsurface exploration, the major geotechnical
concern for this site is the existing alluvial soils encountered in Borings W-HA-02 and W-HA-
03 and the loose to very loose fills soils encountered in Boring W-05. These soils will likely
compress under the weight of new fill and foundations and present a relatively high risk for
adverse long-term total and differential settlement of the proposed dam and spillway structures,
if constructed without remedial measures. In addition, pumping may occur at pavement
subgrades because of the relatively high moisture content of the alluvial soils.
To reduce the risk of excessive total and differential settlement associated with the alluvial and
very loose fill soils, we recommend undercutting the alluvial soils beneath the proposed pipe
cradle, headwall and weir foundations up to 4 feet below proposed bottom of footing elevations
prior to placing new engineered fill to finished grades.
Once existing alluvial and very loose fill soils are removed as recommended and the site is
backfilled with new engineered fill, it is our opinion that the proposed pipe cradles,
headwalls, overflow channel, and weir may be supported on conventional shallow
foundations with a net allowable bearing pressure of 2,500 psf. Assuming proper site
preparation and any necessary subgrade repair, total and differential settlement should be
less than 1 inch and ¾ inches, respectively.
Based on the estimated bottom of footing depths and the groundwater level encountered, we
anticipate that groundwater will be encountered during construction.
The below grade walls for the proposed concrete spillway channel and reinforced box
culvert should be designed to resist the lateral loads produced by the retained soil and by
hydrostatic forces.
This summary should be used in conjunction with the entire report for design purposes. It
should be recognized that details were not included or fully developed in this section, and the
report must be read in its entirety for a comprehensive understanding of the items contained
herein. The section titled GENERAL COMMENTS should be read for an understanding of the
report limitations.
Responsive ■ Resourceful ■ Reliable 1
FINAL GEOTECHNICAL ENGINEERING REPORT
WAVERLY SWIM CLUB POND DAM
CHARLOTTE, NORTH CAROLINA Project No. 71135018
July 16, 2015
1.0 INTRODUCTION
A geotechnical engineering report has been completed for the existing Waverly Swim Club Pond
Dam located in Charlotte, North Carolina. Five (5) design borings, designated W-01 through W-
05, were performed to depths of approximately 20 to 30 feet below the existing ground surface at
the existing dam. Additionally, three (3) hand auger borings, designated W-HA-01 to W-HA-03,
were performed in the footprint of the existing spillway. Logs of the borings along with a Site
Vicinity Plan and Boring Location Plan are included in Appendix A of this report.
The purpose of these services is to provide information and geotechnical engineering
recommendations relative to:
Subsurface Soil Conditions
Groundwater Conditions
Earthwork
Shallow Foundations
Slope Stability
Dam Evaluation
Lateral Earth Pressures
2.0 PROJECT INFORMATION
2.1 Site Location and Description
ITEM DESCRIPTION
Location
The Waverly Swim Club Pond is located north and adjacent to
Albemarle Road, south of Ivy Hollow Drive, east of Almond Road, and
west of Tamora Drive in Charlotte, North Carolina.
Existing Development
Approximately 17-acre pond and existing earthen dam with a concrete
spillway. The dam traverses approximately 600 feet along the south
edge of the pond and along the southern portions of the east and west
edges of the pond.
Current Ground Cover Mixture of landscaped areas, grass, and some trees.
Existing Topography The area around the dam varies from about 690 feet to 703 feet and
the normal water level is about 699.6 feet.
Terracon has been provided with a topographic map of the pond, dam, and surrounding area.
The pond appears to have been constructed by excavating from natural grades to
Final Geotechnical Engineering Report Waverly Swim Club Pond Dam ■ Charlotte, North Carolina July 16, 2015 ■ Terracon Project No. 71135018
Responsive ■ Resourceful ■ Reliable 2
approximately 703 feet mean sea level elevation (MSLE) and constructing a “C” shaped berm
around the south end of the pond. In general, the crest and both the upstream and
downstream slopes are covered with small trees and grassy undergrowth. A concrete spillway
approximately 120 feet long with an 8 foot notch weir is located towards the middle of the
dam. The spillway outflow is lined with riprap and leads to a box culvert that conveys water
underneath Albemarle Road and towards Marlwood Pond.
The majority of the upstream and downstream slopes that are covered in vegetation appear to
be at an inclination of approximately 3H:1V (horizontal to vertical) and vary in height from
approximately 3 to 6 feet. These slopes then transition to about 2.5H:1V or flatter at the pond
water elevation. The slopes adjacent to the outflow channel are sloped up to approximately
2H:1V.
2.2 Project Description
ITEM DESCRIPTION
Proposed Structures
Improvements to the existing dam will include construction of a new
120 foot weir structure, adding a siphon drain, and modification of the
existing outfall channel. The outfall channel will be paved with
concrete and a reinforced concrete box culvert will be used to channel
the water to a new concrete vault that will be constructed adjacent to
the south side of the dam.
Loads Not Provided. Estimated to be relatively light.
Grading Minimal cut and fill – estimated at less than 5 feet.
Should any of the above information or assumptions be inconsistent with the planned
construction, please let us know so that we can make any necessary modifications to the
report.
3.0 SUBSURFACE CONDITIONS
3.1 Geology
The project site is located in the Piedmont Physiographic Province, an area underlain by ancient
igneous and metamorphic rocks. The residual soils in this area are the product of in-place
chemical weathering of rock. The typical residual soil profile consists of clayey soils near the
surface where soil weathering is more advanced, underlain by sandy silts and silty sands that
generally become harder with depth to the top of parent bedrock. Alluvial soils are typically
present within floodplain areas along creeks and rivers in the Piedmont. According to the 1985
Geologic Map of North Carolina, the site is within the Charlotte Belt. The bedrock underlying the
site generally consists of meta-argillite.
Final Geotechnical Engineering Report Waverly Swim Club Pond Dam ■ Charlotte, North Carolina July 16, 2015 ■ Terracon Project No. 71135018
Responsive ■ Resourceful ■ Reliable 3
The boundary between soil and rock in the Piedmont is not sharply defined. A transitional zone
termed “partially weathered rock” is normally found overlying the parent bedrock. Partially
weathered rock is defined for engineering purposes as residual material with standard
penetration test resistance’s exceeding 100 blows per foot. The transition between hard/dense
residual soils and partially weathered rock occurs at irregular depths due to variations in degree
of weathering.
Groundwater is typically present in fractures within the partially weathered rock or underlying
bedrock in the Piedmont. Fluctuations in groundwater levels on the order of 2 to 4 feet are typical
in residual soils and partially weathered rock in the Piedmont, depending on variations in
precipitation, evaporation, and surface water runoff. Seasonal high groundwater levels are
expected to occur during or just after the typically cooler months of the year (November through
April).
3.2 Typical Profile
Based on the results of the borings, the subsurface conditions on the project site can be
generalized as follows:
Boring Existing Ground
Elevation 1
Boring Depth
2
(feet)
Approx. Water
Elevation 1
Approx. Elevation of
Fill Soils Encountered
1
Approx. Elevation of
Residual Soils Encountered
1
Approx. Elevation
1
of Top of PWR
3
W-01
702.5 25 NE 4
702.5 – 684.0 684.0 – 677.5 NE
W-02
703 24.3 694.7 5
703.0 – 689.5 689.5 – 679.5 679.5
W-03
704 20 NE NE 703.0 – 684.0 NE
W-04
703.5 20 NE 703.5 – 700.0 700.0 – 683.5 NE
W-05
701.5 30 686.5 701 – 683.5 683.5 – 671.5 NE
W-HA-01
703 3.6 NE 703 - 702 702 – 699.5 NE
W-HA-02
703 8.6 NE 703 - 702 702 – 694.5 NE
W-HA-03
703 10 NE 702.5 – 699.5 699.5 - 693 NE
1. Approximate elevations based off of topographic map provided by Dewberry 2. From the existing ground surface 3. PWR: Partially Weathered Rock 4. NE: Not Encountered 5. 24-hour water level reading
The soil test borings along the dam encountered approximately 2 to 3 inches of topsoil and
rootmat at the ground surface. Below the surface materials, the western borings (W-03 and W-
04) encountered up to 3.5 feet of fill soils and the eastern borings (W-01, W-02, and W-05)
encountered fill soils between 13.5 and 18.5 feet below the existing ground surface. Fill soils are
those soils that have been placed or reworked in conjunction with past construction grading. The
Final Geotechnical Engineering Report Waverly Swim Club Pond Dam ■ Charlotte, North Carolina July 16, 2015 ■ Terracon Project No. 71135018
Responsive ■ Resourceful ■ Reliable 4
engineering properties of the fill depend primarily on its composition, density, and moisture
content.
The fill soils at this site consist of sandy clay and sandy silt and classify as CL and ML,
respectively, in general accordance with the Unified Soils Classification System (USCS). The
standard penetration resistance values (N-values) in the fill material range from 2 to 15 blows per
foot (bpf), indicating a soft to stiff relative consistency.
Residual soils were encountered below the fill soils with the exception of boring W-03, in which
the residual soils were encountered directly below the topsoil. The residual soils consist of sandy
silt, silty sand, and sandy clay. These soils visually classify as ML, SM, and CL, respectively, in
general accordance with the USCS. N-values ranging between 8 and 32 bpf were encountered
in the silty sand, indicating a loose to dense relative density. The N-values range from 7 to 51 bpf
in the silts and clays indicating a medium stiff to hard relative consistency.
Partially weathered rock (PWR) was encountered below the residual soils in boring W-02. The
PWR was sampled and visually classified as hard sandy silt, ML in accordance with the USCS.
The soils encountered in the hand auger borings at the existing spillway footprint consisted of 1
to 3.6 feet of fill materials. The fill consisted of lean clay with varying amounts of sand and
classify as CL, in accordance with the USCS. Hand auger boring W-HA-02 and W-HA-03
encountered alluvial soils beneath the fill material. The alluvial soils consisted of lean clay with
sand and classify as CL. Residual soils were encountered to the boring termination depths. The
residual soils consisted of silty sand and sandy silt to silt with sand and classify as SM and ML,
respectively.
Conditions encountered at each boring location are indicated on the individual boring logs in
Appendix A of this report. Stratification boundaries on the boring logs represent the approximate
location of changes in soil types; in-situ, the transition between materials may be gradual.
3.3 Groundwater
The boreholes were observed while drilling and after completion for the presence and level of
groundwater. Groundwater was observed while drilling in boring W-05 at an approximate
elevation of 686.5 feet. Groundwater was not observed in the remaining borings immediately
after completion. Borings W-01, W-03, W-04, W-05, W-HA-01, W-HA-02, and W-HA-03 were
immediately backfilled with the auger cuttings, making subsequent water level readings
unobtainable; however, boring W-02 was left open for a 24-hour groundwater reading, and water
was encountered at an approximate elevation of 695.
It should be recognized that fluctuations of the groundwater table will occur due to seasonal
variations in the amount of rainfall, runoff and other factors not evident at the time the borings
were performed. Therefore, groundwater levels during construction or at other times in the life of
Final Geotechnical Engineering Report Waverly Swim Club Pond Dam ■ Charlotte, North Carolina July 16, 2015 ■ Terracon Project No. 71135018
Responsive ■ Resourceful ■ Reliable 5
the structure may be higher or lower than the levels indicated on the boring logs. The possibility
of groundwater level fluctuations should be considered when developing the design and
construction plans for the project.
4.0 RECOMMENDATIONS FOR DESIGN AND CONSTRUCTION
4.1 Geotechnical Considerations
Based on the data obtained from our subsurface exploration, the major geotechnical concern
for this site is the approximate 2 to 4 feet of alluvial soils encountered in hand auger Borings
W-HA-02 and W-HA-03 and the loose to very loose fill soils encountered in Boring W-05 at the
bearing elevation of the proposed concrete vault and pipe cradles for the siphon drain. These
soils will likely compress under the weight of the proposed new weir structure and present a
relatively high risk for adverse long-term total and differential settlement of the spillway, concrete
vault, and pipe cradles, if constructed without remedial measures. In addition, pumping may
occur at pavement subgrades because of the relatively high moisture content of the alluvial soils.
To reduce the risk of excessive total and differential settlement associated with the soft soils, and
to provide a stable subgrade for the weir, concrete vault, and pipe cradles, we recommend
undercutting four (4) feet beneath the proposed bottom of footing elevations of the proposed weir
and concrete vault. After these undercutting procedures are performed, the over-excavation
should be underlain with a geotextile (Mirafi HP570 or equivalent) and backfilled with new
engineered fill in accordance with the Earthwork section of this report.
Due to excessively soft alluvial soils, a “Bridge Lift” of up to 18 inches of new engineered fill may
be necessary at the bottom of the undercut areas. A Bridge Lift is a relatively thick lift of fill soil
that is placed over soft subgrade soils as the first lift in the grading operation. The lift is thick
enough to allow construction equipment to work, but since the subgrade is relatively soft, the
bridge lift may not achieve the desired compaction requirements (i.e., 95% relative compaction
as per Standard proctor). However, subsequent lifts can be placed and compacted properly.
Once the site is remediated as described above, it is our opinion that the proposed overflow
spillway, pipe cradles, weir, and concrete vault may be supported on conventional spread and
strip footings with a net allowable bearing pressure of 2,500 psf. Further details and
recommendations are provided herein. Assuming proper site preparation and any necessary
subgrade repair, total and differential settlement should be within anticipated tolerable limits.
The geotechnical engineer should be retained during the construction phase of the project to
observe earthwork and to perform necessary tests and observations during subgrade
preparation and footing excavation. Soil testing should include proofrolling, placement and
compaction of fill soils, backfilling of excavations upto the completed subgrade, and footing
subgrade evaluation.
Final Geotechnical Engineering Report Waverly Swim Club Pond Dam ■ Charlotte, North Carolina July 16, 2015 ■ Terracon Project No. 71135018
Responsive ■ Resourceful ■ Reliable 6
The contractor should expect that dewatering will be required during foundation excavation. It
is recommended that water levels be kept at least two feet below the bottom of the
foundations until the headwalls, weir and pipe cradles have been constructed. A more
complete discussion of these points and additional information is included in the following
sections.
4.2 Slope Stability
Based on our review of the proposed dam improvements, we understand that all permanent
slopes will be designed at a 3H:1V (Horizontal: Vertical) inclination or flatter. The North
Carolina Administrative Code, Title 15A, Subchapter 2K – Dam Safety, Section .0208 –
“Structural Stability and Slope Protection,” requires a minimum factor of safety of 1.5 for slope
stability for normal conditions. Improved permanent dam slopes will meet the minimum required
factor of safety of 1.5 provided they are constructed according to the reconditions in this report.
4.3 Earthwork
4.3.1 Site Preparation
Existing vegetation, topsoil, pavement materials and any otherwise unsuitable material should
be removed from the construction areas prior to placing fill. Based on the existing geometry
and proposed remediation to the existing dam, we recommend that the existing riprap remain
in place. The exposed subgrade soils in areas to receive fill or at the subgrade elevation in
cut areas should be evaluated by the geotechnical engineer to detect soft or loose soils and
identify unsuitable or poorly compacted fill. This evaluation may consist of visual observations,
utilizing a probe rod, and/or proofrolling.
Existing alluvial soils were encountered in hand auger borings W-HA-02 and W-HA-03 and
very loose to loose soils were encountered in boring W-05. To reduce the risk of excessive total
and differential settlement associated with these soils, and to provide a stable subgrade for the
foundations, we recommend performing the remedial recommendations as outlined in Section
4.1 of this report prior to constructing the new weir and overflow spillway. We do not recommend
reusing the alluvial soils as engineered fill in foundation areas; however, the existing fill soils
encountered within the dam appear suitable for reuse as engineered fill.
The soils encountered in the borings will be sensitive to disturbance from construction activity
and water seepage. If precipitation occurs prior to or during construction, the near-surface
soils could increase in moisture content and become more susceptible to disturbance.
Construction activity should be monitored, and should be curtailed if the construction activity is
causing subgrade disturbance. If subgrade soils are unsuitable, they will require removal and
replacement; however, if they are unstable due to excessive moisture, the most economical
solution for remediation may be to scarify, dry and recompact the material. This remediation is
most effective during the typically hotter months of the year (May to October). If construction is
Final Geotechnical Engineering Report Waverly Swim Club Pond Dam ■ Charlotte, North Carolina July 16, 2015 ■ Terracon Project No. 71135018
Responsive ■ Resourceful ■ Reliable 7
performed during the cooler period of the year, the timeline for scarifying, drying, and
recompacting typically increases considerably and may lead to alternative remediation
solutions. These solutions can include overexcavation of some or all of the unstable material
to be backfilled with either approved engineerd fill or geotextile and ABC Stone. A Terracon
representative can help with monitoring and developing recommendations to aid in limiting
subgrade disturbance.
Proofrolling should be performed with a fully-loaded, tandem-axle dump truck or similar
pneumatic-tired construction equipment. A Terracon representative should observe this
operation to aid in delineating unstable soil areas. Proofrolling should be performed after a
suitable period of dry weather to avoid degrading an otherwise acceptable subgrade. Soils
which continue to rut or deflect excessively under the proofrolling operations should be
remediated as recommended by the geotechnical engineer.
Proofrolling may not be feasible in the low lying areas adjacent to the existing pond or within
confined foundation excavations. In these instances the geotechnical engineer may use a probe
rod and engineering judgment to evaluate the stability of the exposed subgrade prior to fill
placement.
Unstable or unsuitable areas that are identified during the evaluation should be undercut to
suitable soils. The extent of undercut required should be determined in the field by an
experienced geotechnical engineer while monitoring construction activities. Construction traffic
should be avoided, if possible, on the exposed subgrade to reduce disturbance. After the
proofrolling and/or probing and evaluation by the geotechnical engineer has been completed and
approved, project grading should begin immediately to minimize exposure to degradation from
construction activities and inclement weather.
4.3.2 Material Types
Engineered fill should meet the following material property requirements:
Fill Type 1
USCS
Classification Acceptable Location for Placement
On-Site Soils SM, SC, ML, CL
(LL<50 & PI<20) All locations and elevations.
Imported Low
Plasticity Soils
SM, SC, CL, ML
(LL<50 & PI<20) All locations and elevations.
1. Controlled, compacted fill should consist of approved materials that are free of organic matter and
debris. Materials larger than 6 inches in diameter should not be used as fill. Frozen material should
not be used, and fill should not be placed on a frozen subgrade. A sample of each material type
should be submitted to the geotechnical engineer for evaluation.
Final Geotechnical Engineering Report Waverly Swim Club Pond Dam ■ Charlotte, North Carolina July 16, 2015 ■ Terracon Project No. 71135018
Responsive ■ Resourceful ■ Reliable 8
If new fill is proposed for the existing dam, proper benching techniques should be used to tie the
new fill into the existing slopes. Each bench should be keyed into the existing dam a minimum of
4 feet wide, or sufficiently wide to permit complete coverage with the compaction equipment
used. The base of the key should be graded horizontal, or inclined slightly into the existing dam
slope. The outside of the bottom key should be below the existing fill and loose soils to a depth
of at least two (2) feet. This benching recommendation is presented in the following sketch.
4.3.3 Compaction Requirements
We recommend that engineered fill be tested for moisture content and compaction during
placement. Should the results of the in-place density tests indicate the specified moisture or
compaction limits have not been met, the area represented by the test should be reworked
and retested as required until the specified moisture and compaction requirements are
achieved.
Engineered fill should meet the following compaction requirements:
ITEM DESCRIPTION
Fill Lift Thickness
8 to 10 inches or less in loose thickness when heavy, self-
propelled compaction equipment is used
4 to 6 inches in loose thickness when hand-guided equipment (e.g.
jumping jack or plate compactor) is used
Slopes should be such that sloughing or sliding does not occur.
Existing Slope
2' min.
W
Existing Dam Material
Typical Benching Detail
NOTE: The Key width "W" should be a minimum of 4 feet wide, or sufficiently wide to permit coverage with the compaction equipment.
Final Geotechnical Engineering Report Waverly Swim Club Pond Dam ■ Charlotte, North Carolina July 16, 2015 ■ Terracon Project No. 71135018
Responsive ■ Resourceful ■ Reliable 9
ITEM DESCRIPTION
Compaction Requirements Minimum 95% of the material’s maximum standard Proctor dry
density (ASTM D 698)
Moisture Content
Requirements
Within 3% of the optimum moisture content value as determined by
the standard Proctor test at the time of placement and compaction
Should the results of the in-place density tests indicate the specified moisture or compaction
limits have not been met, the area represented by the test should be reworked and retested as
required until the specified moisture and compaction requirements are achieved.
Some manipulation of the moisture content (such as wetting, drying) will be required during
the filling operation to obtain the required degree of compaction. The manipulation of the
moisture content is highly dependent on weather conditions and site drainage conditions.
Therefore, the grading contractor should be prepared to both dry and wet the fill materials to
obtain the specified compaction during grading.
4.3.4 Earthwork Construction Considerations
The near-surface sandy silts and clays at the site will lose strength and rut or deflect
excessively under construction traffic when they become wet. Performing earthwork operations
during warmer periods of the year (May through October) will reduce the potential for problems
associated with unstable subgrades. Earthwork can be performed at other times of the year, but
does lead to an increased potential for having to perform overexcavation and replacement or
some other form of remedial work. Protecting the exposed subgrade soils from infiltration of
surface water by keeping the site grades sloped to promote runoff and by “sealing” disturbed
silty/clayey soil surfaces with rubber-tired equipment in advance of rain events will also reduce
the potential for needing to perform remedial work on wet subgrades. Placing additional
“crusher run” stone base course as a protective layer and working surface in exposed
subgrade areas could also be considered to protect the subgrade soils. Should unstable
subgrade conditions develop, stabilization measures should be employed.
The site should also be graded to prevent ponding of surface water on the prepared
subgrades or in excavations. If the subgrade should become frozen, desiccated, saturated, or
disturbed, the affected material should be removed or these materials should be scarified,
moisture conditioned, and recompacted.
The geotechnical engineer should be retained during the construction phase of the project to
observe earthwork and to perform necessary tests and observations during subgrade
preparation. Soil testing should include proofrolling, placement and compaction of controlled
compacted fills, and backfilling of overexcavations.
4.3.5 Excavations
The soils within the upper 20 to 25 feet may be excavated with conventional construction
equipment, such as bulldozers, backhoes, and trackhoes. All excavations should be sloped or
Final Geotechnical Engineering Report Waverly Swim Club Pond Dam ■ Charlotte, North Carolina July 16, 2015 ■ Terracon Project No. 71135018
Responsive ■ Resourceful ■ Reliable 10
braced as required by Occupational Safety and Health Administration (OSHA) regulations to
provide stability and safe working conditions. Temporary excavations will probably be required
during grading operations. The grading contractor is usually responsible for designing and
constructing stable, temporary excavations and should shore, slope, or bench the sides of the
excavations as required to maintain stability of both the excavation sides and bottom. All
excavations should comply with applicable local, state and federal safety regulations, including
the current OSHA Excavation and Trench Safety Standards.
We recommend that all permanent slopes constructed be designed at a 3H:1V (Horizontal:
Vertical) inclination or flatter. Steeper slopes should be evaluated separately for local and
global stability.
Construction site safety is the sole responsibility of the contractor who controls the means,
methods, and sequencing of construction operations. Under no circumstances shall the
information provided herein be interpreted to mean that Terracon is assuming any responsibility
for construction site safety or the contractor's activities; such responsibility shall neither be
implied nor inferred.
4.4 Foundations
4.4.1 Foundation Design Recommendations
In our opinion, once the existing alluvial soils at the weir and very loose fill soils at the
proposed vault location are remediated and the site is backfilled with new engineered fill as
outlined in Sections 4.1 and 4.3 of this report, the proposed weir, outflow spillway, pipe
cradles, headwall structures and concrete vault can be supported by shallow, spread footing
foundation systems. Design recommendations for a shallow foundation system are presented
in the following table and paragraphs.
DESCRIPTION WEIR, SPILLWAY, PIPE
CRADLES, CONCRETE VAULT HEADWALLS
Net allowable bearing pressure 1 2,500 psf 2,500 psf
Minimum dimensions 30 inches 18 inches
Minimum protective embedment 18 inches 18 inches
Approximate total settlement 2 <1 inch < ½ inch over 50 feet
1. The recommended net allowable bearing pressure is the pressure in excess of the minimum
surrounding overburden pressure at the footing base elevation. Assumes any unsuitable fill or soft
soils, if encountered, will be undercut and replaced with engineered fill.
2. The foundation settlement will depend upon the variations within the subsurface soil profile, the structural
loading conditions, the embedment depth of the footings, the thickness of compacted fill, and the quality
of the earthwork operations.
Final Geotechnical Engineering Report Waverly Swim Club Pond Dam ■ Charlotte, North Carolina July 16, 2015 ■ Terracon Project No. 71135018
Responsive ■ Resourceful ■ Reliable 11
Foundations for the proposed headwalls and weir should be designed to resist any uplift
forces due to hydrostatic pressures. Foundation excavations should be observed by the
geotechnical engineer. If the soil conditions encountered differ from those presented in this
report, supplemental recommendations will be required.
4.4.2 Pipe Support Cradle Considerations
The proposed pipe support cradles for the pond siphon feature can be supported on the stable
residual soils encountered in our borings. These residual soils were encountered at an
approximate elevation of 683.5 feet MSL. It is estimated that to remove all of the very loose fill
soils beneath the pipe cradles would result in approximately 60 to 70 cubic yards of undercut.
Given that this amount of undercut is not desirable, we have determined that a partial removal
of the existing unsuitable soils may be performed and still allow for a suitable bearing strata for
each cradle and spillway pipe. The partial removal of these soils should include undercutting
the existing alluvial and fill soils four (4) feet beneath the proposed bottom of footing
elevations of the proposed weir and concrete vault, placement of a geotextile, and proper
backfilling with engineered fill as outlined in Sections 4.1 and 4.3 of this report.
4.4.3 Foundation Construction Considerations
The base of all foundation excavations should be free of water and loose soil and rock prior to
placing concrete. Concrete should be placed soon after excavating to reduce bearing soil
disturbance. Should the soils at bearing level become disturbed, saturated, or frozen, the
affected soil should be removed prior to placing concrete.
Groundwater seepage into foundation excavations is expected at this site, and the need for
dewatering in foundation excavations should be expected by the contractor. It is
recommended that water levels be kept at least two feet below the bottom of the foundations
until the headwalls, weir, overflow spillway, and pipe cradles have been constructed. A
temporary dewatering system that has performed adequately on previous projects consists of
sump pumps. Pumping from sumps should be maintained until the foundations are properly
installed. If sump pumps are not able to adequately remove the water and keep the site dry for
construction operations, conventional dewatering with drilled wells may be required.
Exposure to inclement weather can also introduce unwanted moisture into the footing
subgrade. If construction occurs during inclement weather, and concreting of foundations is
not possible at the time they are excavated, a layer of lean concrete should be placed on
exposed bearing surfaces for protection. Where high moisture conditions are encountered at
footing bearing elevations, the bottom of the excavations could be stabilized with a relatively
clean, well-graded crushed stone or gravel, or a lean concrete mud mat to provide a working
base for construction.
The foundation bearing materials should be evaluated at the time of the foundation
excavation. A representative of the geotechnical engineer should use a combination of hand
Final Geotechnical Engineering Report Waverly Swim Club Pond Dam ■ Charlotte, North Carolina July 16, 2015 ■ Terracon Project No. 71135018
Responsive ■ Resourceful ■ Reliable 12
auger borings and dynamic cone penetrometer (DCP) testing to determine the suitability of the
bearing materials for the design bearing pressure. DCP testing should be performed to a depth
of at least 4 feet below the bottom of footing excavation.
4.5 Filter Diaphragm and Underdrain
4.5.1 Filter Diaphragm Considerations
A Filter Diaphragm can be used to reduce the risk of erosion developing through the dam and
underneath the overflow spillway. If used, it is recommended that the Filter Diaphragm consist
of NCDOT “2S” sand (Table 1005-2, NCDOT Standard Specifications for Roads and
Structures, July 2006), or as described in the National Engineering Handbook, Part 628,
Chapter 45. The minimum dry density of the Filter Diaphragm sand should be equal to 95
percent of the dry density obtained by compacting a single specimen of sand using the energy
and methods described in ASTM D698A.
As per the Handbook, the Filter Diaphragm should be constructed downstream of the
centerline of the dam. The width of the Filter Diaphragm should be such that construction
equipment can readily place and compact the sand; however, the diaphragm width should be
at least 36 inches, and at least 24 inches of properly compacted engineered fill should cover
the top of the filter diaphram.
4.5.2 Underdrain Considerations
If a Filter Diaphragm is used, an Underdrain should be installed to collect water from the Filter
Diaphragm and carry it to a suitable outlet. It is recommended that the Underdrain consist of a
non-woven geotextile fabric encasing drainage stone (NCDOT No. 57) surrounding a 6-inch
diameter perforated PVC pipe. The perforated pipe should connect to a solid PVC outlet pipe
and extend to a suitable outlet.
4.6 Lateral Earth Pressures
The following section specifies the lateral earth pressure coefficients to be used for the below
grade walls for the proposed concrete spillway channel and reinforced concrete box culvert.
Reinforced concrete walls with unbalanced backfill levels on opposite sides should be designed
for earth pressures at least equal to those indicated in the following table. Earth pressures will
be influenced by structural design of the walls, conditions of wall restraint, methods of
construction and/or compaction and the strength of the materials being restrained. Active earth
pressure is commonly used for design of free-standing cantilever retaining walls and anticipates
wall movement. The "at-rest" condition anticipates no wall rotation. The recommended design
lateral earth pressures do not include a factor of safety.
Final Geotechnical Engineering Report Waverly Swim Club Pond Dam ■ Charlotte, North Carolina July 16, 2015 ■ Terracon Project No. 71135018
Responsive ■ Resourceful ■ Reliable 13
Earth Pressure Coefficients
Earth Pressure
Conditions
Earth Pressure Coefficient for Backfill Type
Equivalent Fluid Density
(pcf)
Surcharge Pressure,
p1 (psf)
Earth Pressure, p2 (psf)
Active (Ka) On-site sandy silt (ML) and
sandy clay (CL) – 0.38 45 (0.38)S (45)H1 + (22)H2
At-Rest (Ko)
On-site sandy silt (ML) and sandy clay (CL – 0.55
66 (0.55)S (66)H1 + (31)H2
Passive (Kp)
On-site sandy silt (ML) and sandy clay (CL) – 2.66
320 --- ---
Applicable conditions to the above include:
For active earth pressure, wall must rotate about base, with top lateral movements of about 0.002 H to 0.004 H, where H is wall height
For passive earth pressure to develop, wall must move horizontally to mobilize resistance Uniform surcharge, where S is surcharge pressure In-situ soil backfill weight a maximum of 120 pcf Unit weight of water (ɣw) is 62.4 pcf Horizontal backfill, compacted to 95 percent of standard Proctor maximum dry density Loading from heavy compaction equipment not included No dynamic loading No safety factor included Ignore passive pressure in frost zone
Backfill placed against structures should consist of granular soils or low plasticity cohesive soils.
High plasticity clay (CH) and elastic silt (MH) should not be used as backfill. To minimize the
Final Geotechnical Engineering Report Waverly Swim Club Pond Dam ■ Charlotte, North Carolina July 16, 2015 ■ Terracon Project No. 71135018
Responsive ■ Resourceful ■ Reliable 14
build-up of lateral soil pressures in excess of the recommended design pressures, over-
compaction of the fill behind the wall should be avoided; however, a lesser degree of
compaction may permit excessive post-construction settlements. In order to limit wall pressures
resulting from over-compaction of wall backfill, we recommend that backfill within 5 feet of a wall
be compacted by small, hand-operated compaction equipment to 95 percent of the standard
Proctor maximum dry density. Remaining backfill should be compacted in accordance with the
compaction recommendations provided in the Earthwork section of this report.
5.0 GENERAL COMMENTS
Terracon should be retained to review the final design plans and specifications so comments
can be made regarding interpretation and implementation of our geotechnical recommendations
in the design and specifications. Terracon also should be retained to provide observation and
testing services during grading, excavation, foundation construction and other earth-related
construction phases of the project.
The analysis and recommendations presented in this report are based upon the data obtained
from the borings performed at the indicated locations and from other information discussed in
this report. This report does not reflect variations that may occur between borings, across the
site, or due to the modifying effects of construction or weather. The nature and extent of such
variations may not become evident until during or after construction. If variations appear, we
should be immediately notified so that further evaluation and supplemental recommendations
can be provided.
The scope of services for this project does not include either specifically or by implication any
environmental or biological (e.g., mold, fungi, bacteria) assessment of the site or identification or
prevention of pollutants, hazardous materials or conditions. If the owner is concerned about the
potential for such contamination or pollution, other studies should be undertaken.
This report has been prepared for the exclusive use of our client for specific application to the
project discussed and has been prepared in accordance with generally accepted geotechnical
engineering practices. No warranties, either express or implied, are intended or made. Site
safety, excavation support, and dewatering requirements are the responsibility of others. In the
event that changes in the nature, design, or location of the project as outlined in this report are
planned, the conclusions and recommendations contained in this report shall not be considered
valid unless Terracon reviews the changes and either verifies or modifies the conclusions of this
report in writing.
APPENDIX A
FIELD EXPLORATION
MAP IS FOR GENERAL LOCATION ONLY
2020 Starita Road, Suite E Charlotte, North Carolina 28206
PH. (704) 509-1777 FAX. (704) 509-1888
A-1
EXB No.SITE VICINITY PLAN
WAVERLY SWIM CLUB POND DAMALBEMARLE ROAD
CHARLOTTE, NORTH CAROLINA
Project Manager:
Drawn by:
Checked by:
Approved by:
SWG
PDM
DJC
DJC
Project No.
Scale:
File Name:
Date:
71135018
N.T.S
A-1 SVP
4/29/2014
APPROXIMATE SITE LOCATION
LEGEND:
= Approximate Location of Soil Test Borings
= Approximate Location of Hand Auger Borings
BORING LOCATION PLAN
WAVERLY SWIM CLUB POND DAMALBEMARLE ROAD
CHARLOTTE, NORTH CAROLINAA-2
71135018
4/29/2014
SWG
PDM
DJC
DJC
N.T.S.
Project Manager:
Drawn by:
Checked by:
Approved by:
Project No.
Scale:
File Name:
Date:
Exhibit
A-2 BLPDIAGRAM IS FOR GENERAL LOCATION ONLY, AND IS NOT INTENDED FOR
CONSTRUCTION PURPOSES
W-01
2020 Starita Road, Suite E Charlotte, North Carolina 28206
PH. (704) 509-1777 FAX. (704) 509-1888
W-02
W-03
W-04
W-05
W-HA-01
W-HA-02
W-HA-03
Final Geotechnical Engineering Report Waverly Swim Club Pond Dam ■ Charlotte, North Carolina July 16, 2015 ■ Terracon Project No. 71135018
Responsive ■ Resourceful ■ Reliable Exhibit A-3
Field Exploration Description
The boring locations were laid out on the site by Terracon personnel utilizing a site plan provided
and were measured from available site features. Right angles for the boring locations were
estimated. The locations of the borings should be considered accurate only to the degree
implied by the means and methods used to define them.
The borings were drilled with an ATV-mounted rotary drill rig using hollow stem augers method
to advance the boreholes. Samples of the soil encountered in the borings were obtained using
the split-barrel sampling procedure.
In the split barrel sampling procedure, the number of blows required to advance a standard 2
inch O.D. split barrel sampler the last 12 inches of the typical total 18 inch penetration by
means of a 140 pound hammer with a free fall of 30 inches, is the standard penetration
resistance value (SPT-N). This value is used to estimate the in-situ relative density of
cohesionless soils and consistency of cohesive soils.
An automatic SPT hammer was used to advance the split-barrel sampler in the borings
performed on this site. A significantly greater efficiency is achieved with the automatic
hammer compared to the conventional safety hammer operated with a cathead and rope. This
higher efficiency has an appreciable effect on the SPT-N value.
Hand auger borings were performed in conjunction with Dynamic Cone Penetrometer (DCP)
testing. Samples of the soil encountered in the borings were obtained from the hand auger
cuttings. The DCP test procedure is as follows.
The cone point of the penetrometer is first seated two inches into the bearing materials to embed
the point. The cone point is driven in 1¾-inch increments using a 15-pound weight falling from a
height of 20-inches. The penetrometer reading is the number of blows required to drive the cone
point each increment (blows-per-increment, bpi) and the penetrometer readings are recorded.
The penetrometer reading is similar to the SPT N-value, as defined by ASTM D1586. When
properly evaluated, the penetrometer test results provide an index for estimating soil strength and
relative density.
The samples were tagged for identification, sealed to reduce moisture loss, and taken to our
laboratory for further examination, testing, and classification. Information provided on the
boring logs attached to this report includes soil descriptions, consistency evaluations, boring
depths, sampling intervals, and groundwater conditions. The borings were backfilled with
auger cuttings prior to the drill crew leaving the site.
A field log of each boring was prepared by the drill crew. These logs included visual
classifications of the materials encountered during drilling as well as the driller’s interpretation
of the subsurface conditions between samples. Final boring logs included with this report
Final Geotechnical Engineering Report Waverly Swim Club Pond Dam ■ Charlotte, North Carolina July 16, 2015 ■ Terracon Project No. 71135018
Responsive ■ Resourceful ■ Reliable Exhibit A-3
represent the engineer's interpretation of the field logs and include modifications based on
laboratory observation and tests of the samples.
At the completion of each boring, Terracon attempted ground water measurements. The soil
test borings were backfilled immediately after the completion of the exploration, making
subsequent water measurements unobtainable. Water levels tend to fluctuate with seasonal
and climatic variations as well as with some types of construction operations. Therefore, water
may be encountered during construction at depths not indicated during this exploration.
0.3
6.0
18.5
23.5
25.0
8 Ft.:Dry Cave-In Depth
FILL - SANDY LEAN CLAY (CL), tan yellow, soft tomedium stiff, fine to coarse grained sand
FILL - SANDY LEAN CLAY (CL), gray tan, soft, fine tocoarse grained sand
Boring Terminated at 25 Feet
SANDY LEAN CLAY (CL), gray blue, medium stiff, fine tocoarse grained sand (Residual)
40-23-17 58
23
27
702+/-
696.5+/-
684+/-
679+/-
677.5+/-
18
18
10
4
18
18
15
2-2-3N=5
2-1-2N=3
1-1-2N=3
0-1-1N=2
1-1-1N=2
2-3-4N=7
6-10-22N=32
Stratification lines are approximate. In-situ, the transition may be gradual. Hammer Type: Automatic
LOCATION
GR
AP
HIC
LO
G
DEPTH
See Exhibit A-2
THIS
BO
RIN
G L
OG
IS N
OT
VA
LID
IF S
EP
AR
ATE
D F
RO
M O
RIG
INA
L R
EP
OR
T.
TE
RR
AC
ON
SM
AR
T LO
G-N
O W
ELL
711
3501
8 - W
AV
ER
LY P
ON
D D
AM
.GP
J T
ER
RA
CO
N20
12.G
DT
5/2
4/13
,
CLIENT: Dewberry Charlotte, North Carolina
Charlotte, North Carolina
A-4
See Exhibit A-3 for description of field procedures.
See Appendix B for description of laboratoryprocedures and additional data, (if any).
See Appendix C for explanation of symbols andabbreviations.
WATER LEVEL OBSERVATIONS
PROJECT: Waverly Swim Club Pond Dam
SITE:
Abandonment Method:Borings backfilled with soil cuttings upon completion.
Advancement Method:Hollow Stem Auger
BORING LOG NO. W-01
Notes:
Project No.: 71135018 Exhibit
Boring Completed: 4/24/2013
Drill Rig: CME-550X Driller: Ameridrill
Boring Started: 4/24/2013
Page 1 of 1
Dry at TOB
DR
Y U
NIT
WE
IGH
T (p
cf)
ATTERBERGLIMITS
LL-PL-PI
TES
T TY
PE
STR
AIN
(%)
CO
MP
RE
SS
IVE
STR
EN
GTH
(tsf)
PE
RC
EN
T FI
NE
S
WA
TER
CO
NTE
NT
(%)
SA
MP
LE T
YP
E
WA
TER
LE
VE
LO
BS
ER
VA
TIO
NS
DE
PTH
(ft)
5
10
15
20
25
Approximate Surface Elev.: 702.5 +/-ELEVATION
RE
CO
VE
RY
(%)
FIE
LD T
ES
TR
ES
ULT
S
STRENGTH TEST
TOPSOIL, 3" TOPSOIL/GRASSMAT
SILTY SAND (SM), orange tan to black brown, dense, fineto coarse grained sand (Residual)
0.3
13.5
18.5
23.5
24.3
10.5 Ft.:Wet Cave-In Depth19.5 Ft.:Dry Cave-In Depth
FILL - SANDY LEAN CLAY (CL), brown orange, soft tomedium stiff, fine to medium grained sand
Boring Terminated at 24.3 Feet
SANDY SILT (ML), brown gray to green white, hard, fineto medium grained sand (Residual)
SANDY SILT (ML), tan orange, very stiff, fine to mediumgrained sand (Residual)
PARTIALLY WEATHERED ROCK (PWR), sampled as tanolive sandy silt
40-22-18 60
30
27
702.5+/-
689.5+/-
684.5+/-
679.5+/-
678.5+/-
12
12
18
10
16
18
9
2-2-3N=5
2-2-2N=4
0-2-1N=3
1-1-1N=2
1-14-18N=32
4-9-11N=20
31-50/4"N=50/4"
Stratification lines are approximate. In-situ, the transition may be gradual. Hammer Type: Automatic
LOCATION
GR
AP
HIC
LO
G
DEPTH
See Exhibit A-2
THIS
BO
RIN
G L
OG
IS N
OT
VA
LID
IF S
EP
AR
ATE
D F
RO
M O
RIG
INA
L R
EP
OR
T.
TE
RR
AC
ON
SM
AR
T LO
G-N
O W
ELL
711
3501
8 - W
AV
ER
LY P
ON
D D
AM
.GP
J T
ER
RA
CO
N20
12.G
DT
5/2
4/13
,
CLIENT: Dewberry Charlotte, North Carolina
Charlotte, North Carolina
A-5
See Exhibit A-3 for description of field procedures.
See Appendix B for description of laboratoryprocedures and additional data, (if any).
See Appendix C for explanation of symbols andabbreviations.
WATER LEVEL OBSERVATIONS
PROJECT: Waverly Swim Club Pond Dam
SITE:
Abandonment Method:Borings backfilled with soil cuttings upon completion.
Advancement Method:Hollow Stem Auger
BORING LOG NO. W-02
Notes:
Project No.: 71135018 Exhibit
Boring Completed: 4/24/2013
Drill Rig: CME-550X Driller: Ameridrill
Boring Started: 4/24/2013
Page 1 of 1
Dry at TOB
24-Hour
DR
Y U
NIT
WE
IGH
T (p
cf)
ATTERBERGLIMITS
LL-PL-PI
TES
T TY
PE
STR
AIN
(%)
CO
MP
RE
SS
IVE
STR
EN
GTH
(tsf)
PE
RC
EN
T FI
NE
S
WA
TER
CO
NTE
NT
(%)
SA
MP
LE T
YP
E
WA
TER
LE
VE
LO
BS
ER
VA
TIO
NS
DE
PTH
(ft)
5
10
15
20
Approximate Surface Elev.: 703 +/-ELEVATION
RE
CO
VE
RY
(%)
FIE
LD T
ES
TR
ES
ULT
S
STRENGTH TEST
TOPSOIL, 3" TOPSOIL/GRASSMAT
0.2
3.5
6.0
18.5
20.0
14 Ft.:Dry Cave-In Depth
Boring Terminated at 20 Feet
SANDY SILT (ML), tan gray, hard, fine to medium grainedsand (Residual)
SANDY SILT (ML), tan olive, hard, fine to medium grainedsand (Residual)
SANDY SILT (ML), tan gray, hard, coarse to fine grainedsand (Residual)
SANDY SILT (ML), gray tan, very stiff, fine to mediumgrained sand (Residual)
704+/-
700.5+/-
698+/-
685.5+/-
684+/-
18
18
12
12
18
18
8-11-20N=31
9-19-26N=45
21-30-21N=51
12-20-21N=41
14-18-19N=37
7-10-13N=23
Stratification lines are approximate. In-situ, the transition may be gradual. Hammer Type: Automatic
LOCATION
GR
AP
HIC
LO
G
DEPTH
See Exhibit A-2
THIS
BO
RIN
G L
OG
IS N
OT
VA
LID
IF S
EP
AR
ATE
D F
RO
M O
RIG
INA
L R
EP
OR
T.
TE
RR
AC
ON
SM
AR
T LO
G-N
O W
ELL
711
3501
8 - W
AV
ER
LY P
ON
D D
AM
.GP
J T
ER
RA
CO
N20
12.G
DT
5/2
4/13
,
CLIENT: Dewberry Charlotte, North Carolina
Charlotte, North Carolina
A-6
See Exhibit A-3 for description of field procedures.
See Appendix B for description of laboratoryprocedures and additional data, (if any).
See Appendix C for explanation of symbols andabbreviations.
WATER LEVEL OBSERVATIONS
PROJECT: Waverly Swim Club Pond Dam
SITE:
Abandonment Method:Borings backfilled with soil cuttings upon completion.
Advancement Method:Hollow Stem Auger
BORING LOG NO. W-03
Notes:
Project No.: 71135018 Exhibit
Boring Completed: 4/24/2013
Drill Rig: CME-550X Driller: Ameridrill
Boring Started: 4/24/2013
Page 1 of 1
Dry at TOB
DR
Y U
NIT
WE
IGH
T (p
cf)
ATTERBERGLIMITS
LL-PL-PI
TES
T TY
PE
STR
AIN
(%)
CO
MP
RE
SS
IVE
STR
EN
GTH
(tsf)
PE
RC
EN
T FI
NE
S
WA
TER
CO
NTE
NT
(%)
SA
MP
LE T
YP
E
WA
TER
LE
VE
LO
BS
ER
VA
TIO
NS
DE
PTH
(ft)
5
10
15
20
Approximate Surface Elev.: 704 +/-ELEVATION
RE
CO
VE
RY
(%)
FIE
LD T
ES
TR
ES
ULT
S
STRENGTH TEST
TOPSOIL, 2" TOPSOIL/PINESTRAW
WA
TER
LE
VE
LO
BS
ER
VA
TIO
NS
DE
PTH
(ft)
5
10
15
20
Approximate Surface Elev.: 703.5 +/-ELEVATION
RE
CO
VE
RY
(%)
FIE
LD T
ES
TR
ES
ULT
S
STRENGTH TEST
0.2
3.5
13.5
18.5
20.0
14 Ft.:Dry Cave-In Depth
FILL - SANDY LEAN CLAY (CL), orange brown, stiff, fineto medium grained sand
Boring Terminated at 20 Feet
703.5+/-
700+/-
690+/-
685+/-
683.5+/-
8
18
18
18
18
18
3-5-10N=15
6-9-12N=21
10-18-15N=33
6-6-11N=17
6-7-16N=23
5-9-13N=22
Stratification lines are approximate. In-situ, the transition may be gradual. Hammer Type: Automatic
LOCATION
GR
AP
HIC
LO
G
DEPTH
See Exhibit A-2
THIS
BO
RIN
G L
OG
IS N
OT
VA
LID
IF S
EP
AR
ATE
D F
RO
M O
RIG
INA
L R
EP
OR
T.
TE
RR
AC
ON
SM
AR
T LO
G-N
O W
ELL
711
3501
8 - W
AV
ER
LY P
ON
D D
AM
.GP
J T
ER
RA
CO
N20
12.G
DT
5/2
4/13
,
CLIENT: Dewberry Charlotte, North Carolina
Charlotte, North Carolina
A-7
See Exhibit A-3 for description of field procedures.
See Appendix B for description of laboratoryprocedures and additional data, (if any).
See Appendix C for explanation of symbols andabbreviations.
WATER LEVEL OBSERVATIONS
PROJECT: Waverly Swim Club Pond Dam
SITE:
Abandonment Method:Borings backfilled with soil cuttings upon completion.
Advancement Method:Hollow Stem Auger
BORING LOG NO. W-04
Notes:
Project No.: 71135018 Exhibit
Boring Completed: 4/24/2013
Drill Rig: CME-550X Driller: Ameridrill
Boring Started: 4/24/2013
Page 1 of 1
Dry at TOB
DR
Y U
NIT
WE
IGH
T (p
cf)
ATTERBERGLIMITS
LL-PL-PI
TES
T TY
PE
STR
AIN
(%)
CO
MP
RE
SS
IVE
STR
EN
GTH
(tsf)
PE
RC
EN
T FI
NE
S
WA
TER
CO
NTE
NT
(%)
SA
MP
LE T
YP
E
TOPSOIL, 2" TOPSOIL/PINESTRAW
SANDY SILT (ML), olive tan, very stiff to hard, fine tomedium grained sand (Residual)
SANDY SILT (ML), tan olive, very stiff, fine to coarsegrained sand (Residual)
SANDY SILT (ML), olive gray, very stiff, fine to mediumgrained sand (Residual)
0.3
3.0
12.0
18.0
30.0
3" TOPSOILFILL - SILT WITH SAND (ML), brown, soft
FILL - SANDY SILT (ML), gray to brown, soft to medium-stiff
FILL - SILTY SAND (SM), gray, very loose to loose
SILTY SAND (SM), tan, black, to white, medium dense, residuum
Boring Terminated at 30 Feet
2-2-1N=3
1-2-1N=3
1-2-4N=6
2-2-4N=6
0-1-1N=2
2-3-5N=8
5-5-7N=12
8-14-15N=29
701+/-
698.5+/-
689.5+/-
683.5+/-
671.5+/-
8
13
12
12
16
9
10
8
Hammer Type: AutomaticStratification lines are approximate. In-situ, the transition may be gradual.
LOCATION
DEPTH
GR
AP
HIC
LO
G See Exhibit A-2
THIS
BO
RIN
G L
OG
IS N
OT
VA
LID
IF S
EP
AR
ATE
D F
RO
M O
RIG
INA
L R
EP
OR
T.
GE
O S
MA
RT
LOG
-NO
WE
LL 7
1135
018
- WA
VE
RLY
SW
IM C
LUB
PO
ND
DA
M -
FIN
AL.
GP
J T
EM
PLA
TE U
PD
ATE
3-3
1-14
.GP
J 7
/25/
14
Charlotte, North CarolinaSITE:
Page 1 of 1
Advancement Method:Hollow Stem Auger
Abandonment Method:Borings backfilled with soil cuttings upon completion.
2020-E Starita RoadCharlotte, North Carolina
Notes:
Project No.: 71135018
Drill Rig: CME-550X
Boring Started: 4/10/2014
BORING LOG NO. W-05DewberryCLIENT:Charlotte, North Carolina
Driller: C. Fredrychowski
Boring Completed: 4/10/2014
Exhibit: A-8
See Exhibit A-3 for description of field procedures.
See Appendix B for description of laboratoryprocedures and additional data (if any).See Appendix C for explanation of symbols andabbreviations.
PROJECT: Waverly Swim Club Pond Dam
FIE
LD T
ES
TR
ES
ULT
S
PE
RC
EN
T FI
NE
S
WA
TER
CO
NTE
NT
(%)
ATTERBERGLIMITS
LL-PL-PI
ELEVATION (Ft.)
Approximate Surface Elev: 701.5 (Ft.) +/- DE
PTH
(Ft.)
5
10
15
20
25
30
SA
MP
LE T
YP
E
WA
TER
LE
VE
LO
BS
ER
VA
TIO
NS
RE
CO
VE
RY
(In.
)
Water Initially ObservedWATER LEVEL OBSERVATIONS
0.3
1.0
3.0
3.6
3" CONCRETEFILL - LEAN CLAY (CL), trace sand, brown to orange
SILTY SAND (SM), gray, redisuum
SILTY SAND (SM), tan to gray
Hand Auger Refusal at 3.6 Feet
703+/-
702+/-
700+/-
699.5+/-
7-8-7
13-19-23
13-25+
20-25+
25+
Stratification lines are approximate. In-situ, the transition may be gradual.
LOCATION
DEPTH
GR
AP
HIC
LO
G See Exhibit A-2
THIS
BO
RIN
G L
OG
IS N
OT
VA
LID
IF S
EP
AR
ATE
D F
RO
M O
RIG
INA
L R
EP
OR
T.
GE
O S
MA
RT
LOG
-NO
WE
LL 7
1135
018
- WA
VE
RLY
SW
IM C
LUB
PO
ND
DA
M -
FIN
AL.
GP
J T
EM
PLA
TE U
PD
ATE
3-3
1-14
.GP
J 7
/25/
14
Charlotte, North CarolinaSITE:
Page 1 of 1
Advancement Method:Hand Auger with DCP
Abandonment Method:Borings backfilled with soil cuttings upon completion.
2020-E Starita RoadCharlotte, North Carolina
Notes:
Project No.: 71135018
Drill Rig: N/A
Boring Started: 4/30/2014
BORING LOG NO. W-HA-01DewberryCLIENT:Charlotte, North Carolina
Driller: P. McCloud/W. Galloway
Boring Completed: 4/30/2014
Exhibit: A-9
See Exhibit A-3 for description of field procedures.
See Appendix B for description of laboratoryprocedures and additional data (if any).See Appendix C for explanation of symbols andabbreviations.
PROJECT: Waverly Swim Club Pond Dam
ELEVATION (Ft.)
Approximate Surface Elev: 703 (Ft.) +/- DE
PTH
(Ft.)
SA
MP
LE T
YP
E
WA
TER
LE
VE
LO
BS
ER
VA
TIO
NS
DY
NA
MIC
CO
NE
PE
NE
TRO
ME
TER
(DC
P)
BLO
WS
PE
R 1
-3/4
"
WATER LEVEL OBSERVATIONS
0.3
1.0
4.6
8.6
3" CONCRETEFILL - SANDY LEAN CLAY (CL), brown to tan
LEAN CLAY WITH SAND (CL), trace roots, gray, alluvium
SILT WITH SAND (ML), gray to tan, residuum
Hand Auger Refusal on Cobble at 8.6 Feet
703+/-
702+/-
698.5+/-
694.5+/-
5-6-6
3-3-2
2-2-3
1-2-1
2-1-2
6-7-11
10-17-20
18-23-25+
13-15-23
Stratification lines are approximate. In-situ, the transition may be gradual.
LOCATION
DEPTH
GR
AP
HIC
LO
G See Exhibit A-2
THIS
BO
RIN
G L
OG
IS N
OT
VA
LID
IF S
EP
AR
ATE
D F
RO
M O
RIG
INA
L R
EP
OR
T.
GE
O S
MA
RT
LOG
-NO
WE
LL 7
1135
018
- WA
VE
RLY
SW
IM C
LUB
PO
ND
DA
M -
FIN
AL.
GP
J T
EM
PLA
TE U
PD
ATE
3-3
1-14
.GP
J 7
/25/
14
Charlotte, North CarolinaSITE:
Page 1 of 1
Advancement Method:Hand Auger with DCP
Abandonment Method:Borings backfilled with soil cuttings upon completion.
2020-E Starita RoadCharlotte, North Carolina
Notes:
Project No.: 71135018
Drill Rig: N/A
Boring Started: 4/30/2014
BORING LOG NO. W-HA-02DewberryCLIENT:Charlotte, North Carolina
Driller: P. McCloud/W. Galloway
Boring Completed: 4/30/2014
Exhibit: A-10
See Exhibit A-3 for description of field procedures.
See Appendix B for description of laboratoryprocedures and additional data (if any).See Appendix C for explanation of symbols andabbreviations.
PROJECT: Waverly Swim Club Pond Dam
ELEVATION (Ft.)
Approximate Surface Elev: 703 (Ft.) +/- DE
PTH
(Ft.)
5
SA
MP
LE T
YP
E
WA
TER
LE
VE
LO
BS
ER
VA
TIO
NS
DY
NA
MIC
CO
NE
PE
NE
TRO
ME
TER
(DC
P)
BLO
WS
PE
R 1
-3/4
"
WATER LEVEL OBSERVATIONS
0.4
3.6
5.8
10.0
3" CONCRETE
FILL - LEAN CLAY WITH SAND (CL), tan
LEAN CLAY WITH SAND (CL), trace roots, gray, alluvium
SANDY SILT (ML), gray to tan, residuum
Hand Auger Terminated in Residual Soil at 10 Feet
702.5+/-
699.5+/-
697+/-
693+/-
2-2-2
3-3-3
2-2-4
3-3-4
4-3-4
6-6-8
6-6-11
13-21-23
25+
25+
Stratification lines are approximate. In-situ, the transition may be gradual.
LOCATION
DEPTH
GR
AP
HIC
LO
G See Exhibit A-2
THIS
BO
RIN
G L
OG
IS N
OT
VA
LID
IF S
EP
AR
ATE
D F
RO
M O
RIG
INA
L R
EP
OR
T.
GE
O S
MA
RT
LOG
-NO
WE
LL 7
1135
018
- WA
VE
RLY
SW
IM C
LUB
PO
ND
DA
M -
FIN
AL.
GP
J T
EM
PLA
TE U
PD
ATE
3-3
1-14
.GP
J 7
/25/
14
Charlotte, North CarolinaSITE:
Page 1 of 1
Advancement Method:Hand Auger with DCP
Abandonment Method:Borings backfilled with soil cuttings upon completion.
2020-E Starita RoadCharlotte, North Carolina
Notes:
Project No.: 71135018
Drill Rig: N/A
Boring Started: 4/30/2014
BORING LOG NO. W-HA-03DewberryCLIENT:Charlotte, North Carolina
Driller: P. McCloud/W. Galloway
Boring Completed: 4/30/2014
Exhibit: A-11
See Exhibit A-3 for description of field procedures.
See Appendix B for description of laboratoryprocedures and additional data (if any).See Appendix C for explanation of symbols andabbreviations.
PROJECT: Waverly Swim Club Pond Dam
ELEVATION (Ft.)
Approximate Surface Elev: 703 (Ft.) +/- DE
PTH
(Ft.)
5
10
SA
MP
LE T
YP
E
WA
TER
LE
VE
LO
BS
ER
VA
TIO
NS
DY
NA
MIC
CO
NE
PE
NE
TRO
ME
TER
(DC
P)
BLO
WS
PE
R 1
-3/4
"
WATER LEVEL OBSERVATIONS
APPENDIX B
LABORATORY TESTING
Final Geotechnical Engineering Report Waverly Swim Club Pond Dam ■ Charlotte, North Carolina July 16, 2015 ■ Terracon Project No. 71135018
Responsive ■ Resourceful ■ Reliable Exhibit B-1
Laboratory Testing
Samples retrieved during the field exploration were taken to the laboratory for further
observation by the project geotechnical engineer and were classified in accordance with the
Unified Soil Classification System (USCS) described in Appendix C. At that time, the field
descriptions were confirmed or modified as necessary and an applicable laboratory testing
program was formulated to determine engineering properties of the subsurface materials.
Laboratory tests were conducted on selected soil samples and the test results are presented
on the boring logs. The laboratory test results were used for the geotechnical engineering
analyses, and the development of foundation and earthwork recommendations. Laboratory
tests were performed in general accordance with the applicable ASTM, local or other accepted
standards.
Selected soil samples obtained from the site were tested for the following engineering
properties:
In-situ Water Content
Sieve Analysis
Atterberg Limits
Descriptive classifications of the soils indicated on the boring logs are in accordance with the
enclosed General Notes and the USCS. Also shown are estimated Unified Soil Classification
Symbols. A brief description of this classification system is attached to this report. All
classification was by visual manual procedures. Selected samples were further classified using
the results of Material Finer than No. 200 Sieve and Atterberg limit testing. The Material Finer
than No. 200 Sieve and Atterberg limit test results are provided in the tables below, and are
also provided on the boring logs.
Sample Location,
Depth
In-situ
Moisture
(%)
% Material
Finer than No.
200 Sieve
Liquid
Limit, (%)
Plastic
Limit, (%)
Plasticity
Index, (%)
W-01, 3.5’ – 5.0’ 23 NT 1 NT NT NT
W-01, 6.0’ – 7.5’ 27 58 40 23 17
W-02, 1.0’ – 2.5’ 30 NT NT NT NT
W-02, 8.5’ – 10.0’ 27 60 40 22 18
1. NT = Not Tested
APPENDIX C
SUPPORTING DOCUMENTS
Exhibit C-1
GENERAL NOTES
DRILLING & SAMPLING SYMBOLS:
SS: Split Spoon – 1-3/8" I.D., 2" O.D., unless otherwise noted HS: Hollow Stem Auger
ST: Thin-Walled Tube - 2" O.D., unless otherwise noted PA: Power Auger
RS: Ring Sampler - 2.42" I.D., 3" O.D., unless otherwise noted HA: Hand Auger
DB: Diamond Bit Coring - 4", N, B RB: Rock Bit
BS: Bulk Sample or Auger Sample WB: Wash Boring or Mud Rotary
The number of blows required to advance a standard 2-inch O.D. split-spoon sampler (SS) the last 12 inches of the total 18-inch
penetration with a 140-pound hammer falling 30 inches is considered the “Standard Penetration” or “N-value”.
WATER LEVEL MEASUREMENT SYMBOLS:
WL: Water Level WS: While Sampling N/E: Not Encountered
WCI
:
Wet Cave in WD: While Drilling
DCI
:
Dry Cave in BCR: Before Casing Removal
AB: After Boring ACR: After Casing Removal
Water levels indicated on the boring logs are the levels measured in the borings at the times indicated. Groundwater levels at other times and other locations across the site could vary. In pervious soils, the indicated levels may reflect the location of groundwater. In low permeability soils, the accurate determination of groundwater levels may not be possible with only short-term observations.
DESCRIPTIVE SOIL CLASSIFICATION: Soil classification is based on the Unified Classification System. Coarse Grained Soils
have more than 50% of their dry weight retained on a #200 sieve; their principal descriptors are: boulders, cobbles, gravel or sand. Fine Grained Soils have less than 50% of their dry weight retained on a #200 sieve; they are principally described as clays if they are plastic, and silts if they are slightly plastic or non-plastic. Major constituents may be added as modifiers and minor constituents may be added according to the relative proportions based on grain size. In addition to gradation, coarse-grained soils are defined on the basis of their in-place relative density and fine-grained soils on the basis of their consistency.
CONSISTENCY OF FINE-GRAINED SOILS RELATIVE DENSITY OF COARSE-GRAINED SOILS
Unconfined
Compressive
Strength, Qu, psf
Standard Penetration or N-
value (SS) Blows/Ft.
Consistency Standard Penetration
or N-value (SS) Blows/Ft.
Relative Density
< 500 0 – 1 Very Soft 0 – 3 Very Loose
500 – 1,000 2 – 4 Soft 4 – 9 Loose
1,001 – 2,000 4 – 8 Medium Stiff 10 – 29 Medium Dense
2,001 – 4,000 8 – 15 Stiff 30 – 49 Dense
4,001 – 8,000 15 – 30 Very Stiff > 50 Very Dense
8,000+ > 30 Hard
RELATIVE PROPORTIONS OF SAND AND GRAVEL GRAIN SIZE TERMINOLOGY
Descriptive Term(s) of other
Constituents
Percent of
Dry Weight
Major Component
of Sample Particle Size
Trace < 15 Boulders Over 12 in. (300mm)
With 15 – 29 Cobbles 12 in. to 3 in. (300mm to 75 mm)
Modifier > 30 Gravel 3 in. to #4 sieve (75mm to 4.75 mm)
Sand #4 to #200 sieve (4.75mm to
0.075mm)
Silt or Clay Passing #200 Sieve (0.075mm)
RELATIVE PROPORTIONS OF FINES PLASTICITY DESCRIPTION
Descriptive Term(s) of other
Constituents
Percent of
Dry Weight Term
Plasticity
Index
Trace < 5 Non-plastic 0
With 5 – 12 Low 1 – 10
Modifiers > 12 Medium 11 – 30
High > 30
Exhibit C-2
UNIFIED SOIL CLASSIFICATION SYSTEM
Criteria for Assigning Group Symbols and Group Names Using Laboratory Tests A
Soil Classification
Group
Symb
ol
Group Name B
Coarse Grained Soils:
More than 50%
retained on No. 200
sieve
Gravels:
More than 50% of
coarse fraction
retained on No. 4
sieve
Clean Gravels:
Less than 5% fines C
Cu 4 and 1 Cc 3 E
GW Well-graded gravel F
Cu 4 and/or 1 Cc 3 E
GP Poorly graded gravel F
Gravels with Fines:
More than 12% fines
C
Fines classify as ML or MH GM Silty gravel F,G,H
Fines classify as CL or CH GC Clayey gravel F,G,H
Sands:
50% or more of
coarse fraction
passes No. 4 sieve
Clean Sands:
Less than 5% fines D
Cu 6 and 1 Cc 3 E
SW Well-graded sand I
Cu 6 and/or 1 Cc 3 E
SP Poorly graded sand I
Sands with Fines:
More than 12% fines
D
Fines classify as ML or MH SM Silty sand G,H,I
Fines classify as CL or CH SC Clayey sand G,H,I
Fine-Grained Soils:
50% or more passes
the No. 200 sieve
Silts and Clays:
Liquid limit less than
50
Inorganic: PI 7 and plots on or above “A”
line J
CL Lean clay K,L,M
PI 4 or plots below “A” line J ML Silt
K,L,M
Organic: Liquid limit - oven
dried 0.75 OL Organic clay
K,L,M,N
Liquid limit - not dried Organic silt K,L,M,O
Silts and Clays:
Liquid limit 50 or more
Inorganic: PI plots on or above “A” line CH Fat clay
K,L,M
PI plots below “A” line MH Elastic Silt K,L,M
Organic: Liquid limit - oven
dried 0.75 OH Organic clay
K,L,M,P
Liquid limit - not dried Organic silt K,L,M,Q
Highly organic soils: Primarily organic matter, dark in color, and organic odor PT Peat
A Based on the material passing the 3-inch (75-mm) sieve
B If field sample contained cobbles or boulders, or both, add “with cobbles
or boulders, or both” to group name. C
Gravels with 5 to 12% fines require dual symbols: GW-GM well-graded
gravel with silt, GW-GC well-graded gravel with clay, GP-GM poorly
graded gravel with silt, GP-GC poorly graded gravel with clay. D
Sands with 5 to 12% fines require dual symbols: SW-SM well-graded
sand with silt, SW-SC well-graded sand with clay, SP-SM poorly graded
sand with silt, SP-SC poorly graded sand with clay
E Cu = D60/D10 Cc =
6010
2
30
DxD
)(D
F If soil contains 15% sand, add “with sand” to group name.
G If fines classify as CL-ML, use dual symbol GC-GM, or SC-SM.
H If fines are organic, add “with organic fines” to group name.
I If soil contains 15% gravel, add “with gravel” to group name.
J If Atterberg limits plot in shaded area, soil is a CL-ML, silty clay.
K If soil contains 15 to 29% plus No. 200, add “with sand” or “with gravel,”
whichever is predominant. L
If soil contains 30% plus No. 200 predominantly sand, add “sandy” to
group name. M
If soil contains 30% plus No. 200, predominantly gravel, add
“gravelly” to group name. N
PI 4 and plots on or above “A” line. O
PI 4 or plots below “A” line. P
PI plots on or above “A” line. Q
PI plots below “A” line.