feasibility study report · minnesota pollution control agency in a letter received march 20, 1987....
TRANSCRIPT
FEASIBILITY STUDY REPORT
SLP4 GRADIENT CONTROL WELL DISCHARGE ST. LOUIS PARK, MINNESOTA
Prepared for
CITY OF ST. LOUIS PARK
JUNE 1987
BARR ENGINEERING CO. Minneapolis, Minnesota
FEASIBH.ITY STUDY REPORT
Str4 GRADIENT CONTROl WEU DISCHARGE ST. LOUIS PARK, MINNESOTA
Prepared for
CITY OF ST. LOUIS PARK
JUNE 1987
BARR ENGINEERING CO. Minneapolis, Minnesota
FEASIBILITY STUDY REPORT
SLF 4 GRADIENT CONTROL WELL DISCHARGE
TABLE OF CONTENTS
Page
INTRODUCTION 1
SECTION 1 - BACKGROUND 2
SECTION 2 - SURFACE WATER DISCHARGE ALTERNATIVES 5
SECTION 3 - NON-SURFACE WATER DISCHARGE ALTERNATIVES 21
SECTION 4 - EVALUATION OF COST-EFFECTIVE ALTERNATIVES 32
LIST OF TABLES
TABLE 1 COMPARISON OF SLP 4 WATER QUALITY AND CRITERIA
TABLE 2 WATER QUALITY DATA
TABLE 3 SLP 4 SURFACE DISCHARGE OPTIONS
TABLE 4 COST ESTIMATE FOR SANITARY SEWER DISCHARGE
TABLE 5 COST ESTIMATE FOR GRANULAR ACTIVATED CARBON
TABLE 6 COST ESTIMATE FOR GRANULAR MEDIA FILTRATION UP-GRADE
TABLE 7 COST ESTIMATE FOR OZONE TREATMENT
TABLE 8 COST ESTIMATE FOR REVERSE OSMOSIS
TABLE 9 NON-COST COMPARISON
TABLE 10 COST COMPARISON
LIST OF FIGURES
FIGURE 1 GRADIENT CONTROL WELL LOCATIONS
FIGURE 2 PRELIMINARY SURFACE WATER DISCHARGE LOCATIONS
FIGURE 3 SLP 4 SURFACE DISCHARGE OPTIONS
FIGURE 4 SAMPLING LOCATIONS - CH2M HILL STUDY
REITOe/346,O/msh
FEASIBILITY STUDY REPORT
SLP 4 GRADIENT CONTROL WELL DISCHARGE
INTRODUCTION
On September 4, 1986 a Consent Decree was approved between the United
States of America, State of Minnesota, City of St. Louis Park and Re^ly
Tar & Chemical Corporation. Section 7.2.1 of the Remedial Action Plan
(RAP), Exhibit A of the Consent Decree, requires submittal of "a jplan for
the feasibility study for discharge of 1,000 gallons per minute of water
from SLP 4". The required work plan submitted by St. Louis Park was
approved March 16, 1987 by the Environmental Protection Agency and
Minnesota Pollution Control Agency in a letter received March 20, 1987.
This report is submitted pursuant to the work plan.
This report examines the feasibility of discharging the water to
various surface waters as required by the RAP. It also discusses the
possible discharge to the sanitary sewer and the treatment and use of the
water for municipal water supply. The RAP only requires that the surface
water discharge options be investigated. The RAP does, however, recognize
that the quality of the water from SLP 4 might improve with time or that
the City of St. Louis Park might want to treat the water for use in the
municipal drinking water system. The options beyond surface water
discharge are included so that the public and decision makers have a more
complete understanding of the options available.
The report is divided into four sections. Section 1, Background,
describes the proposed overall remedy for the Prairie du Chien-Jordan
aquifer and the technology selected to implement the remedy. Section 2,
Surface Water Discharge Alternatives, discusses the surface water discharge
alternatives. Section 3, Non-Surface Water Discharge Alternatives,
discusses the sanitary sewer and water supply alternatives. Section 4,
Evaluation of Cost-Effective Alternatives, contains the comparison of
alternatives and the recommendation.
SECTION 1
BACKGROUND
HISTORY
The Reilly Tar & Chemical Corporation operated a coal tar refinery and
wood treating facility in St. Louis Park, Minnesota, from 1917 to 1972.
These operations resulted in groundwater and soil contamination. The
groundwater contamination affects deeper aquifers of regional concern. Six
St. Louis Park municipal drinking water wells completed in the Prairie du
Chien-Jordan aquifer, including Well SLP 4, have been closed due to the
presence of polynuclear aromatic hydrocarbons (PAH). One of the major
goals of the remedial action at this site is the management of the
migration of the contaminants in this aquifer.
The contamination in the Prairie du Chien-Jordan aquifer underlies a
large part of St. Louis Park as shown in Figure 1. Since 1969 numerous
studies have been completed which addressed this and other problems
associated with the former Reilly Tar site. These studies included the
development of various computerized groundwater flow models which were
used to develop the remedial action embodied in the RAP.
PROPOSED REMEDIAL ACTION
As a result of the numerous studies conducted over the years, most of
the remedial investigation and feasibility study work on the Prairie du
Chien-Jordan aquifer was completed prior to entering into the Consent
Decree. The Consent Decree requires that measures be implemented to
control what is believed to be one of the sources of contamination of this
aquifer. It requires that the spreading of contamination be controlled and
monitored. The Consent Decree also requires that contingent measures be
implemented if additional water supply wells are found to have levels of
PAH compounds above the health based criteria in the Consent Decree.
The source control will be accomplished by reconstructing and pumping
Well W23. This well is located on the former Reilly Tar site and is
believed to have acted as a pathway for contaminants to have been directly
Introduced into the Prairie du Chien-Jordan aquifer. The reconstructed
well will be pumped at 50 gallons per minute (gpra) to the sanitary sewer.
The contingency measure requirements for a water supply well which exceeds
the drinking water criteria include both replacing the lost system capacity
and maintaining the pumping at the well should such pumping be part of the
gradient control system.
PRELIMINARY REMEDIAL TECHNOLOGIES
There are four basic technologies that can be considered for migration
management. These are capping, contaminant barriers, groundwater pumping
and subsurface collection drains. These technologies were evaluated prior
to the Consent Decree.
Capping was found to be ineffective since the contamination was
already over 250 feet deep and covered over 3 square miles. These same
factors make it impractical to control the groundwater with containment
barriers or subsurface drains. The work done prior to the Consent Decree
therefore, focused on the design of a groundwater gradient control system.
The groundwater flow models developed in the prior work were used to
approximate the existing conditions and what would happen to the aquifer
under various pumping stresses. It was found that the spread of
contamination should be controlled by pumping SLP 10 and 15 at historic
rates, pumping the Methodist Hospital Well at historic rates and pumping
SLP 4 at approximately 900 gpm in the winter and 300 gpm in the summer.
SLP 10 and 15 are contaminated wells that were taken out of service. A
carbon adsorption system has been constructed to treat the water from SLP
10 and 15 and they have been back in service since July, 1986. The
Methodist Hospital well is used for cooling water with the discharge going
to Minnehaha Creek. SLP 4 is a municipal well which was taken out of
service due to the presence of levels of non-carcinogenic PAHs, which
although low, exceeded drinking water criteria.
The purpose of this study is to investigate the feasibility of various
options for using or discharging the water from SLP 4. This study does not
revisit the question of the design or pumping rates of the gradient control
system. It does not address monitoring of the effectiveness of the
pump-out system. It does look at the range of concerns associated with
each discharge or use option. The RAP requires that the feasibility study
be based on a 1,000 gpm pvunping rate. The actual pumping rates, expected
to approach 900 gpm from October to May and 300 gpm from May to October,
will be determined by the well and pvunp characteristics and the groundwater
system response to various pumping stresses.
REILFS/346,0/msh
SECTION 2
SURFACE WATER DISCHARGE ALTERNATIVES
DEVELOPMENT OF ALTERNATIVES
Various surface water discharge locations were identified for
receiving the SLP 4 discharge of 1,000 gpm. The surface water locations
identified are shown on Figure 2. The approved work plan requires the
evaluation of discharge to the Minneapolis Chain of Lakes, Minnehaha Creek
and the Mississippi River. Additional locations identified were Wolfe
Lake, Twin Lakes, Westwood Lake, Hannan Lake and Bass Lake in St. Louis
Park and Weber Field Pond in Edina.
The Minneapolis Chain of Lakes consists of five lakes on the western
edge of Minneapolis. Brownie Lake is connected to Cedar Lake which is
connected to Lake of the Isles which is connected to Lake Calhoun. A
pumping system from Lake Calhoun discharges to Lake Harriet which outlets
to Minnehaha Creek.
Minnehaha Creek flows from Lake Minnetonka, located west of St. Louis
Park, through the communities of Minnetonka, Hopkins, St. Louis Park,
Edina, and Minneapolis to the Mississippi River.
The Mississippi River is located east of St. Louis Park and flows
through Minneapolis.
INITIAL SCREENING OF ALTERNATIVES
Each potential location was screened for technical feasibility.
Factors considered in this initial screening were available storage, outlet
size, and distance from SLP 4.
Wolfe Lake in St. Louis Park and Weber Field Pond in Edina both were
close to SLP 4 but had storage insufficient to hold one day of 1,000 gpm
pumping. Because of the insufficient storage they were dropped from
consideration.
Twin Lakes, Westwood Lake, Hannan Lake and Bass Lake, all in St. Louis
Park had storage volumes of approximately one month for a discharge of
1,000 gpm. The distance to Westwood and Hannan Lakes was greater than four
miles and the storage volume was comparable to the other two lakes so these
options were not studied further. Twin Lakes is further from SLP 4 than
Bass Lake and they both ultimately discharge to the Chain of Lakes.
Therefore, Twin Lakes was not studied further. It was decided to consider
Bass Lake in greater detail. Bass Lake does not have a large enough volume
to be the primary body of surface water for the reception of the gradient
control discharge; however, combining Bass Lake and Lake Calhoun for the
surface waters to receive the gradient control discharge was an acceptable
alternative.
Brownie Lake, Cedar Lake, Lake of the Isles, and Lake Calhoun are four
of the five lakes in the Minneapolis Chain of Lakes. These four lakes are
connected and hydrologically act as one lake. Therefore discharging to any
of these four lakes would have the same environmental effect. Since Lake
Calhoun is closest to SLP 4, it was decided to only consider a discharge to
Lake Calhoun in greater detail.
Lake Harriet is the fifth lake in the Chain of Lakes. It is not
naturally connected to the other lakes. The outlet of Lake Harriet is to
Minnehaha Creek. There are potential discharge locations to Minnehaha
Creek that are closer to SLP 4 than Lake Harriet. The environmental
effects of discharging to Lake Harriet would be a combination of the
effects of discharging to Lake Calhoun or Minnehaha Creek. It was decided
to not consider discharge to Lake Harriet as an alternative but to evaluate
the environmental effects through the analysis of the Lake Calhoun and
Minnehaha Creek alternatives..
Discharge locations to Minnehaha Creek considered were Browndale Park
in Edina, Meadowbrook Park in St. Louis Park, and Yosemite Avenue in St.
Louis Park. The distances to these three locations are similar. Browndale
Park was dropped from consideration for Institutional reasons, since the
discharge Is not In St. Louis Park. It was decided to consider In greater-
detail the Yosemite Avenue discharge location because of Its proximity to
the waterworks facilities near SLP 6 and SLP 12. Meadowbrook Park was not
considered further because It was comparable In all features to the
Yosemite Avenue location except the proximity to the waterworks.
Two discharge locations to the Mississippi River were considered.
They were discharging to the I-35W storm sewer tunnel and the 1-394/Bassett
Creek storm sewer system. The outlets for these storm sewer systems are to
the Mississippi River. The distance from SLP 4 was similar for both
systems but the I-394/Bassett Creek option was preferable for Institutional
reasons. Minneapolis has concerns on the capacity of the I-35W storm
sewer tunnel. St. Louis Park prefers the I-394/Bassett Creek system
because It Is mostly In the City.
Four surface waters survived the Initial screening for feasibility of
discharge reception. These alternatives were Minnehaha Creek, Lake
Calhoun, Bass Lake, and the Mississippi River via I-394/Bassett Creek. The
locations of these alternatives and the routes for the discharge are shown
on Figure 3.
The alignment of the four discharge alternatives are described below.
The description Includes alignment, size and the portion of the line which
Is part of an existing system.
Bfiss Lake Alternative
The Bass Lake alternative alignment Is described first. A high
percentage of St. Louis Park stormwater Is conveyed to Bass Lake through
numerous storm sewers. Bass Lake acts as a sedimentation pond for
stormwater discharging to Lake Calhoun.
The pipe alignment assumed for the Bass Lake option is as follows,
beginning at SLP 4 location:
1,150 feet north along Natchez Avenue in new 8-inch forcemain,
Connecting to an existing 18-inch storm sewer at Natchez Avenue and Vallacher Avenue,
350 feet north along Natchez Avenue in an existing 18-inch storm sewer,
900 feet east along Excelsior Boulevard in an existing 42-inch diameter storm sewer.
1,000 feet north along Monterey Drive in an existing 54-inch diameter storm sewer.
600 feet north to Bass Lake inlet in an existing 60-inch diameter storm
The above alignment consists of 1,150 feet of new 8-inch forcemain and
2,850 feet of existing storm sewer.
A gate valve outlet near the eastern boundary of Bass Lake regulates
the amount of water discharged from Bass Lake.
Water discharged.from Bass Lake travels through an existing 42-inch
di^uneter conduit and discharges to an open ditch at Hinikahda Golf Course.
Water travels across the golf course through an open ditch and enters a
30-inch diameter storm sewer near the east edge of the golf course near
36th Street West. Water is conveyed 900 feet to Lake Calhoun.
Lake Calhoun Alternative
The Lake Calhoun alternative alignment is described next. An existing
storm sewer was located 300 feet from SLF 4 which could be used to convey
water to Lake Calhoun. The alignment for the Lake Calhoun discharge option
would be as follows, beginning at SLF 4;
300 feet south along the extension of Natchez Avenue in new storm sewer to an existing manhole,
1,850 feet east along 41st Avenue in an existing 54-inch diameter and 42-inch diameter storm sewer.
existing overflow to Weber Field Pond,
900 feet north in an existing 30-inch diameter storm sewer,
800 feet east in an existing 30-inch diameter storm sewer to France Avenue (existing storm sewer into Minneapolis),
400 feet north along France Avenue in an existing 30-inch diameter storm sewer.
700 feet east along 39th Street in an existing 42-inch diameter storm sewer.
600 feet north along Drew Avenue in an existing 48-inch diameter storm sewer.
2,000 feet east along 38th Street in an existing 48-inch and 54-inch diameter storm sewer.
700 feet north along Xerxes Avenue in an existing 54-inch diameter storm sewer.
outlet into Lake Calhoun.
The Lake Calhoun alignment consists of 300 feet of new storm sewer and
7,950 feet of existing gravity storm sewer. A dedicated pipeline to Lake
Calhoun for the SLF 4 discharge was also considered. The same alignment
was followed but the pipe was new 8-inch ductive iron pipe (DIP) with a
submerged outlet.
Minnehaha Creek Alternative
The Minnehaha Creek discharge alternative alignment is described next.
Pipe alignment for this option is proposed as follows, beginning at SLP 4:
2,500 feet west along 41st Street in a new 10-inch diameter forcemain,
700 feet south along Utica Avenue in a new 10-inch diameter forcemain.
400 feet west along 42nd Street in a new 10-inch diameter f orcemain,
400 feet south along T.H. 100 in a new 10-inch diameter f orcemain,
800 feet west along 42nd Street in a new 10-inch diameter f orcemain.
400 feet south along Yosemlte Avenue in a new 10-inch diameter forcemain.
100 feet west to SLP 6 in a new 10-inch diameter forcemain,
connect to existing storm drain at SLP 6,
450 feet south along Yosemite Avenue in an existing 30-inch diameter storm drain.
outlet into Minnehaha Creek.
The above alignment consists of 5,300 feet of new 10-inch diameter
forcemain and 450 feet of existing 30-inch diameter storm sewer. It is
also possible to connect to an existing gravity system at 42nd Street. The
10
alignment would then consist of 4,300 feet of new 10-inch diameter
forcemain and 1,450 feet of existing gravity storm sewer.
I-394/Basaett Creek Alternative
The alignment for the Mississippi River via I-394/Bassett Creek storm
sewer alternative is described next. The proposed pipe alignment for the
1-394/Bassett Creek alternative is as follows, beginning at SLF 4;
1,500 feet north along Natchez Avenue in a new 10-inch diameter forcemain,
4,000 feet northeast along Excelsior Boulevard in a new 10-inch diameter forcemain,
11,300 feet north along France Avenue and the St. Louis Park-Minneapolis boundary in a new 10-inch diameter forcemain.
connect to Minnesota Department of Transportation storm sewer near 1-394 and France Avenue.
The above alignment consists of 16,800 feet of new 10-inch diameter
forcemain. Water entering the 1-394 storm drainage system would travel
through a series of sedimentation ponds into Bassett Creek within a few
hundred feet of the mouth and into the Mississippi River.
EVALUATION OF ALTERNATIVES
The four alternatives were analyzed to evaluate technical,
environmental, public health and institutional concerns. Cost estimates
were prepared for each alternative. The results of these evaluations are
described in this section of the report.
11
Technical Analysis
The technical analysis of the alternatives addresses concerns on the
quantity, quality and timing of the discharge from SLP 4. A continuous
discharge of 1,000 gpm is 2 cfs or a daily increase in runoff volume of 4
acre-feet. This increase in runoff volume is significant for the Bass Lake
and Lake Calhoun alternatives. Presently, the approximate storage volume
of Bass Lake is 120 acre-feet. The storage volume was assumed to equal the
volume between the outlet's invert elevation and the point of low elevation
with 1 foot of freeboard. The point of low elevation is along a berm
protecting a parking lot from flooding. The parking lot is 1.9 feet lower
than the top of the berm. The low building elevation is 2.3 feet higher
than the top of the berm. The 120 acre-feet of storage is one month of
storage with no outflow for a 1,000 gpm inflow. Storm sewer drainage to
Bass Lake would reduce this storage volume during periods of stormwater
runoff. If there was outflow from Bass Lake to Lake Calhoun the storage
volume would not be depleted as quickly. The water discharge from Bass
Lake travels through an open ditch at the Minikahda Golf Course. Members
of the ground crew from the Minikahda Golf Course indicate that water
usually flows in the ditch year round. Flooding often occurs in the spring
and during some rain storms. Based on the cross-sectional area and slope
of the ditch, the capacity is on the order of 10 to 15 cfs. The increase
of 2 cfs during the summer months could potentially create short-term
flooding. Longer term flooding could occur during the spring snowmelt.
These problems could be mitigated by utilizing the temporary storage
available in Bass Lake or increasing the ditch area. The Minikahda Golf
Course ditch (County Ditch 14) discharges to Lake Calhoun.
At the present time, the potential for flooding in the Chain of Lakes
necessitates the occasional pumping from Lake Calhoun to Lake Harriet.
However, augmentation is occasionally required to maintain present lake
levels. In addition, the Chain of Lakes is a groundwater recharge zone.
There is the potential that in the future, because of increased stresses on
the aquifer from demands such as cooling of downtown office buildings,
augmentation would be necessary to maintain present lake levels. When
augmentation is not needed, pumping to Lake Harriet would be required to
12
prevent high water problems in Lake Calhoun. Presently, a pumping system
exists between the two lakes which is capable of discharging 7,000 gpm.
The outlet from Lake Harriet is a 42-inch diameter conduit. The discharge
for a lake elevation of 846 is 15 cfs and for an elevation of 847 is 30
cfs. An increase in discharge of 2 cfs would increase the Lake Harriet
level approximately 0.2 feet. If this increase causes difficulties, the
outlet could be modified. The Lake Harriet outlet discharges to Minnehaha
Creek.
An increase of 2 cfs to the discharges in Minnehaha Creek or Bassett
Creek would cause a stage increase of less than 0.1 feet. The increase in
flow in Minnehaha Creek, Bassett Creek or the Mississippi River would not
present problems.
The winter discharge of water to surface waters in Minnesota causes
concerns with Ice formation. Ice will not form or will be weak at the
discharge points to Bass Lake, Lake Calhoun and Minnehaha Creek because
the high temperature of groundwater retards ice formation. Without proper
notices and barriers, the weak ice would create a danger to the public.
Lake Calhoun and Minnehaha Creek are presently used for Ice skating and
other recreation. Bass Lake supports limited recreational uses. To at
least partially alleviate the weak Ice hazard on Lake Calhoun, an
alternative with a submerged outlet was Included In the cost analysis. By
submerging the outlet, the Ice formation would be stronger than for the
alternative with the outlet from the existing storm sewer system.
The other major concern with Ice Is the formation of frazil Ice which
could cause partial blockage of culverts downstream. Frazil Ice Is a
slushy accumulation of Ice In water that Is too turbulent for formation of
sheet Ice. Frazil Ice has dammed flow In streams at culverts If It extends
to the bottom of the stream. This Is not a concern for the Bass Lake, Lake
Calhoun or yfilssi^lppl—River—al"ternanvesT^Mlnnehaha Creek has had
problems with frazil Ic^ resulting from fluctuating winter discharges. The
creek does have grounditater discharge and discharges from Industries with
non-contact uses w^ch are at consistent quantities. Frazil Ice has not
13
formed for these continuous discharges. Because the SLP 4 discharge would
be a low volume continuous discharge, frazil ice should not be a concern.
Environmental Analysis
At meetings with representatives of communities and public agencies,
the major concern expressed is the quality of the water to be discharged.
There appears to be a misconception that the water being pumped for
gradient control in the Prairie du Chlen is of the quality of the surficial
aquifer on the site which is highly contaminated. Table 1 shows the
quality of water from SLP 4 compared to drinking water criteria and the
surface water discharge criteria required by the Consent Decree.
Existing data on water quality of SLP 4 indicate that the
concentrations of the carcinogenic PAHs are below the Minnesota
Department of Health (MDH) drinking water recommended allowable levels and
the concentration of the non-carcinogenic PAHs is Just above the criteria
set in the Consent Decree. The data from sixteen months of sampling (July
1981 to October 1982), which were higher concentrations than the earlier
data, had a mean concentration of 0.44 ng/L carcinogenic PAHs and 340 ng/L
non-carcinogenic PAHs'.
The Consent Decree established criteria for the quality of the
discharge to surface waters. Bass Lake, Lake Calhoun, Minnehaha Creek and
Bassett Creek are public waters unclassified by the Minnesota Pollution
Control Agency (MPCA) under 7050.0430 Unlisted Waters. The MPCA considers
all unclassified waters to be of a quality that will support cool or warm
water fishery and aquatic recreation of all kinds including swimming. The
criteria were developed for the case where ;the 7-day duration low flow
discharge was zero. The criteria in the Consent Decree are set at two
orders of magnitude below the acute toxicity level for aquatic life. The
National Pollution Discharge Elimination System (NPDES) criteria are a
maximum concentration of 34000 ng/L for PAH compounds and 2000 ng/L for
phenanthrene. The criteria for the 30-day' average concentration are
one-half the maximum concentration criteria. Phenanthrene is a PAH
compound which has been found to be toxic to aquatic life above the
14
criterion. The NPDES permit also has a criterion of 10 ug/L for phenolics.
A sample was collected from SLP 4 in July 1983 and analyzed by Acurex for
PAH and phenolic compounds. The total PAH concentration was 117 ng/L,
phenanthrene was detected at 21 ng/L and no phenolics were detected. None
of the samples fromi SLP 4 has exceeded a level of one-tenth the NPDES
criteria. A review of the research on aquatic toxicity for PAH compounds
found that the low levels of PAH found in SLP 4 were not toxic to aquatic
life and did not accumulate in the organisms. A list of references
reviewed is at the end of the report.
The November 1983 CH2M Hill report, "Evaluation of Groundwater
Treatment and Water Supply Alternatives for St. Louis Park, Minnesota"
presented results of chemical analyses for six storm sewer discharges.
Four of the storm sewers were along Minnehaha Creek, one outletted to Lake
Calhoun and one outletted to Lake Harriet. These locations are shown on
Figure 4. The results of these analyses all were higher than the results
from ^the SLP 4 analyses. The carcinogenic PAHs were more than two orders
of magnitude greater for the storm sewer water while the non-carcinogenic
PAHs were two to six times greater. In addition the study analyzed samples
from surface water stations on Minnehaha Creek, Lake Calhoun and Lake
Harriet, The downstream stations are also shown on Figure 4. The data from
these analyses were all below drinking water criteria for non-carcinogenic
PAHs but the carcinogenic PAHs exceeded the drinking water criteria in the
Minnehaha Creek 4 station. The results of the CH2M Hill analyses and the
Acurex chemical analyses for SLP 4 are shown on Table 2.
The quality of the SLP 4 discharge is better than the quality of the
water in the storm sewers presently discharging to the surface waters.
Stormwater contains PAH compounds because PAH compounds are present in
tires, asphalt runoff and combustion products of fuel for vehicles,
especially dlesel fuel. The quality of SLP 4 water is comparable to the
existing quality of these waters. The discharge of SLP 4 to Bass Lake,
Lake Calhoun, Minnehaha Creek or the Mississippi River will not have an
adverse environmental effect.
15
Public Health Analysis
The surface waters evaluated as potential receiving waters of the S'LP
4 discharge are not classified for human consiunption. Incidental injestion
may occur during recreational use of the waters. Because of the low
concentrations of PAH compounds in the SLP 4 discharge there will be no
measurable increase in the levels of PAHs In the receiving water.
Therefore, there will be no increase in any public health risk from
incidental injestion.
Consumption of the fish from these waters is a second route of
exposure. The NPDES criterion of 311 ng/L of carcinogenic PAH compounds is
based on the public health risk from eating aquatic organisms from waters
with carcinogenic PAH compounds. The level of carcinogenic PAHs in the
SLP 4 discharge is 100 to 1,000 times lower than this criteria. No public
health concerns are associated with the discharge of SLP 4 to any of the
alternatives.
Institutional Analvsis
The institutional concerns and requirements are very important for a
comparison of these alternatives. Each alternative will be evaluated
separately for this analysis because their institutional concerns are
unique.
Bass Lake would require the cooperation of many community groups and
public agencies. St. Louis Park would be involved because the discharge
utilizes existing storm sewer systems within the city and involves the
operation of the gated outlet valve. The operation of this outlet is
critical because improper operation would cause flooding of homes and
businesses. The cooperation of the Mlnikahda Golf Course is necessary
because the increase in discharge in County^ Ditch 14 could create flooding
and erosion problems for the golf course. These problems could be
addressed by enlarging the ditch capacity or by the golf course allowing
the inconvenience. The Minneapolis Park Board and the Minneapolis Public
Works Department are involved because the ultimate discharge is to Lake
16
Calhoun. The Minneapoillls Public Works Department Indicates that the
Minneapolis City Council would be involved in decisions for permits to
discharge to the storm sewers or the lakes. Bass Lake provides temporary
storage which could be utilized to mitigate impacts on lake levels or
discharges through Minneapolis storm sewers during runoff events which
could mitigate some concerns of the Minneapolis Park Board, Public Works
Department, and City Council. The Minneapolis concerns are ice problems,
pumping required to Lake Harriet and the perceived unacceptable quality of
the water. The Minnehaha Creek Watershed District would need to issue a
permit for the discharge. The Minnehaha Creek Watershed District has been
encouraging use of Bass Lake for stormwater runoff because of its
environmental effects as a sedimentation basin. A groundwater discharge
would use capacity that did not need a sedimentation pond. The Minnesota
Department of Natural Resources (DNR) would need to issue a permit for
appropriation of groundwater for all the alternatives . The MPCA would
need to issue an NPDES permit for the alternatives. The public hearing for
the NPDES permit would address water quality concerns.
The Lake Calhoun alternative requires the cooperation of many of the
groups mentioned for the Bass Lake alternative because the Bass Lake
alternative discharges into Lake Calhoun. The Minikahda Golf Course would
not be involved, but the other groups would be. However, the concerns are
not identical for the two alternatives. The Minneapolis concerns for the
gravity option are Increased flooding along the storm sewers. Ice problems,
pumping required to Lake Harriet and the perceived unacceptable quality of
the water. The dedicated line for the SLP 4 discharge addresses the first
two concerns but not the last two. The Minnehaha Creek Watershed District
would not have the concern of the sedimentation pond use for groundwater
that they would have for the Bass Lake alternative. The NPDES and water
appropriation permits would be required.
The Minnehaha Creek alternative requires a permit from the Minnehaha
Creek Watershed District, NPDES permit from the MPCA and an appropriations
permit from The DNR. Minneapolis has concerns on the frazil Ice effect on
the downstream bridges. These concerns should be addressed In the meetings
for the Watershed District permit.
17
The Mississippi River via I-394/Bassett Creek alternative requires the
cooperation of St. Louis Park because of the construction of the new
forcemaln In the city. The Minnesota Department of Transportation would be
Involved because the discharge would be to the drainage system It has
designed and will maintain for 1-394. A permit would be required from the
Bassett Creek Water Management Commission because the 1-394 drainage system
outlets Into Bassett Creek. An NPDES permit would be required from the
MPCA and an appropriations permit would be required from the DNR.
Although each of the alternatives requires many permits and the
Interaction of many communities and agencies, some of the local concerns
are harder than others to mitigate. It may be difficult to over come the
perception that the discharge water la highly contaminated.
Cost Analvsls
Costs were determined using prices from 1986 local bid tabulations.
The unit costs are shown on Table 3. The forcemalns for the Mississippi
and Minnehaha Creek alternatives were 10-Inch diameter DIP. The 10-Inch
diameter was chosen for the Mississippi alternative because of the friction
losses over the long distance and for the Minnehaha Creek alternative
because of the energy needed to pump through the treatment plant If the
discharge Is added to the municipal water supply. The forcemaln lines for
the dedicated Lake Calhoun and the Bass Lake alternatives were 8-Inch
diameter DIP because there were no extenuating circumstances. All new
gravity lines were assumed to be 18-Inch diameter reinforced concrete pipe
(RCP). The lump sum prices for jacking pipe under highways, railroads, and
four lane roadways are major expenses.
Costs for construction In the City of Minneapolis may be higher than
shown on Table 3. Some of the work performed In Minneapolis must be
performed by the City. These costs are sometimes higher than the
competitively bid prices.
18
The operation and maintenance costs Include labor for pumping and
maintenance. The pumping labor cost is for labor involved in the
maintenance of the pumps. One hour a week was assumed for the time for
maintenance of the pumps. The labor cost for maintenance is for the
placement and removal of fences at locations where weak ice conditions are
expected. The Bass Lake and Lake Calhoun alternatives include time for the
operation and maintenance of the pump from Lake Calhoun to Lake Harriet.
The pumping cost is the electricity cost. The operation and maintenance
costs were evaluated for the present worth assuming 10 and 30 years of
operation of the system. An interest rate of 5 percent was assumed.
4
A summary of the cost analysis data is shown on Table 3. The Bass
Lake alternative has a capital cost of $81,000 and an annual operation and
maintenance cost of $50,000. The present worth costs are $559,000 for 10
years and $1,017,000 for 30 years.
The Lake Calhoun alternative has two costs shown. One is for
discharging into the existing storm sewer system and the other is for
discharging through a pipeline dedicated for the SLP 4 discharge. The
second alternative would address many of the concerns of the Minneapolis
Park Board and Public Works Department. The capital costs are $15,000 for
the gravity system and $556,000 for the dedicated system. The annual
operation and maintenance costs are $49,000 for the gravity system and
$48,000 for the dedicated system. The present worth costs for the gravity
system are $472,000 for 10 years and $922,000 for 30 years. The present
worth costs for the dedicated system are $1,112,000 for 10 years and
$1,552,000 for 30 years.
The Minnehaha Creek alternative has 10-inch diameter forcemain for the
entire length to maintain flexibility of this alternative. The flexibility
allowed is the option to treat the water at the waterworks at this location
and place it in the city's water supply. This option could be Implemented
in a phased manner by deleting 1,000 feet of 10-inch diameter forcemain
shown in the cost estimate ($72,000 of capital cost). The capital cost for
implementing the project in one.phase is $419,000 and in two phases is
$347,000. The annual operation and maintenance cost is $34,000. The
19
present worth costs for non-phased system is $819,000 for 10 years and
$1,133,000 for 30 years.
The Mississippi River alternative (I-394/Bassett Creek) has a capital
cost of $1,222,000 and the annual operation and maintenance cost is
$34,000. The present worth costs are $1,785,000 for 10 years and
$2,102,000 for 30 years.
RSEC2/346,0/msh 20
SECTION 3
NON-SURFACE WATER DISCHARGE ALTERNATIVES
This section evaluates the alternatives for managing the water pvimped
from SLP 4 by means other than surface water, discharge. This work was not
required by the Consent Decree. This portion of the study was done to have
the complete range of alternatives evaluated and presented for public
discussion.
DEVELOPMENT ALTERNATIVES
Two general methods of managing the SLP 4 discharge, other than by
surface water discharge, were identified. These were: 1) discharge to the
sanitary sewer and 2) use of the water with or without treatment. Use by
an industry for process or cooling water is an option that might not
require treatment. Use by a municipality as part of the water supply would
likely require treatment.
INITIAL SCREENING OF ALTERNATIVES
These alternatives were screened based on environmental effects,
technical feasibility and cost. Based on the initial screening only use
for a municipal water supply was evaluated further. Discharge to the
sanitary sewer was dropped primarily because of the cost. Based on a 1,000
gpm pumping rate there would be a Sewer Availability Charge of $2.8
million. The annual sewer charge would approach $600,000. The present
worth of the alternative is an order of magnitude higher than most of the
surface water discharge options discussed in Section 2. The cost estimate
for the sanitary sewer option is shown on Table 4. In addition, there are
indirect adverse environmental effects. Since the water being discharged
to the sanitary sewer meets surface water quality discharge standards
without treatment, the water is needlessly using hydraulic capacity of the
treatment plant that could better be used to treat typical wastewater. For
these reasons the sanitary sewer discharge option was not evaluated any
further.
21
The use of the' water by Industrial or commercial facilities was
evaluated. The water would be acceptable without treatment for most uses
except food processing. The problem with this option is implementability.
Previous work by the City of St. Louis Park identified two potential users
of the water. These uses were primarily for cooling and air conditioning
and would not by themselves have been able to utilize 1,000 gpm in the
winter. The negotiations were terminated when one of the industries and
the City could not agree on language concerning public health liability.
These industries have since made capital investments in equipment that
greatly reduces their need for this water. Since no potential users of the
water appear to exist at this time, this option becomes too speculative to
pursue. The time frame to identify types of industries which might locate
in the City and would need this amount of water, the time to promote the
idea and the time to actually design and build the facility are well beyond
the schedule specified in the RAP. This option could be pursued at a later
date should potential users show interest in locating in the City.
The third alternative is the use of the water for drinking water
supply. When use of the well was discontinued the water quality slightly
exceeded Minnesota Department of Health (MDH) guidelines. It is possible
that since that time or at some point in the future the quality of the
SLP 4 discharge may meet the drinking water guidelines and the water could
be used without treatment. Treatment of the water is also a feasible
option. The City presently operates a carbon adsorption treatment plant
for Wells SLP 10 and 15. Preliminary discussions with the City of Edina
indicate that there may be some interest in obtaining water from St. Louis
Park. The use of the water for drinking water supply was evaluated further
because it appeared to be a potentially feasible alternative.
EVALUATION OF ALTERNATIVES
In order to evaluate the water supply alternative, certain assumptions
were made regarding the design and location of the system. It was assumed
that the water from SLP 4 would first be pumped to the SLP 6 location.
This was done for three reasons. The first reason is the very limited
22
space at the SLP 4 location. Any construction that might be needed could
be more easily accommodated at SLP 6. The second reason is that the
existing sand filters at SLP 6 can be utilized in the treatment train. The
cost of new sand filters is approximately $1.5 million. Finally, storage
is not available at SLP 4 while the SLP 6 location has existing storage.
It was also assumed that if Edina obtained water from St. Louis Park,
they would interconnect at the SLP 6 location. For each of the factors
evaluated, except institutional impacts and costs, it was assumed that the
impacts were the same for use by either St. Louis Park or Edina.
Once the water was at SLP 6 it was assumed treatment would be required
before the water could be used for water supply. If the concentrations of
PAH compounds in the water were to decrease sufficiently for no treatment
of PAH compounds to be.required, the only costs for this option would be
the forcemain between SLP 4 and SLP 6 and the associated pumping costs.
Four different treatment processes were investigated for the situation
where the PAH concentrations do not decrease. These processes were carbon
adsorption, granular media filtration, chemical oxidation and reverse
osmosis.
The carbon adsorption process evaluated was a process in which a fixed
bed of granular activated carbon serves as the adsorption media. Depending
upon the quality of water being treated, backwash or surface washing
capabilities may be required. Carbon adsorption units can be operated as a
single unit or combined in series or in parallel.
The efficiency of a carbon adsorption unit depends upon the
following:
o flow rate
o carbon bed height and diameter
o contaminant concentrations
o natural organic content of the water
o pH
23
o competition for adsorption sites by individual contaminants
o affinity of the contaminant for the carbon surface.
For full-scale" design purposes, the following conditions were
assumed:
o flow rate of 1,000 gpm
o no pre-treatment of contaminated groundwater
o two units (each containing 20,000 pounds of GAG)
o carbon burn rate of 0.01 pounds of GAG per 1,000 gallons
o located at SLP 6
The granular media filtration (GMF) process is similar to the carbon
adsorption process. The media in granular media filtration is normally a
combination of silica sand and anthracite coal. The efficiency of the
process is dependent upon the water matrix, compounds to be removed,
concentration and flow conditions. If a bench and/or pilot scale test
proved that granular media filtration were a technically feasible solution,
the existing sand filters at SLP 6 could be upgraded to granular media
filters.
The chemical oxidation process breaks large.prganic constituents down
to smaller, less harmful organic constituents. Complete oxidation would
result in the production of only carbon dioxide and water. Smaller organic
constituents may be formed due to incomplete oxidation. These may require
additional treatment. Six methods of chemical oxidation of PAH compounds
were Identified:
o ozone (0^)
o ozone/ultra-violet light (UV)
o hydrogen peroxide (H2O2)
o hydrogen peroxide/ultraviolet light
o chlorine (CI2)
o chlorine dioxide (CIO2)
24
Bench scale tests of these chemical oxidation processes were conducted
by CH2M Hill and were presented in the report "Evaluation of Groundwater
Treatment and Water Supply Alternatives for St. Louis Park, Minnesota",
which was prepared for the MPCA in November, 1983 by CH2M Hill and Barr
Engineering Co.
The tests performed by CH2M Hill were done using water from Well
SLP 15. The average total PAH concentration of the water used in the pilot
study was 7,000 ng/L. In the bench scale test, only two chemical oxidation
processes were identified as technically feasible, ozone/UV and hydrogen
peroxide/UV. Ozone/UV dosage rates of 1 mg/L and 20-minute retention time
were able to reduce the influent PAH concentration to the desired criteria.
Peroxide/UV provided good results at 5 mg/L and 60-minute retention time.
The average total PAH concentration for SLP 4 data from 1978 through
1982 was 293 ng/L and the maximum value was 1730 ng/L. The maximiom value
in SLP 4 is approximately one fourth the value used for the bench scale
test water from SLP 15 (7000 ng/L) . The lower concentration in SLP 4 would
probably require lower dosage rates and/or shorter retention times. The
necessary design criteria cannot be adequately determined from the bench
test performed by GH2M Hill.
The lower concentrations in SLP 4 may make ozone of hydrogen peroxide
alone without UV technically feasible. This cannot be determined without
additional testing. Ozone is relatively unstable and must be produced on
site at the time of use. Ozone is produced by passing dry air or oxygen
between two high voltage electrodes. The chlorine and chlorine dioxide
oxidation processes would need further testing because of the possibility
that chlorinated PAH compounds might be formed as reaction products.
Because of the many design variables, only ozone oxidation was included in
the cost analysis for comparison to the other treatment methods.
25
The reverse osmosis process can be used to remove dissolved high
molecular weight organic compounds. The compounds are filtered through a
semi-permeable membrane. Pressure greater than the osmotic pressure
(pressure produced by the dissolved materials) is applied in order to
increase the rate and efficiency of organic compound removal. The pressure
may range from 1 atmosphere to 100 atmospheres..
Typical design variables of reverse osmosis are as follows:
o membrane type
o flux (product) rate
o operating pressure
o membrane configuration
o water recovery
A bench and pilot study would be necessary to define these design
criteria for the water matrix from SLP 4.
As with the surface water alternatives, the water supply alternative
was analyzed for technical, environmental, public health, institutional and
cost concerns. Where concerns were different for the treatment options,
the differences are noted.
Technical Analvsis
The technical feasibility of treating the SLP 4 discharge for drinking
water use is well documented. St. Louis Park is presently treating
groundwater with higher levels of PAH compounds at SLP 10 and 15 to
drinking water standards. This is being done with carbon adsorption. To
determine the design parameters of the other treatment options will require
bench testing. Reverse osmosis has the lowest probability of meeting the
required standards since there is such a small difference between the
treatment goal and the influent water quality. Granular media filtration
has several unknowns since very few, if any, GMF systems have been designed
and operated for PAH removal to drinking water standards. The previously
26
referenced bench testing demonstrated that chemical oxidation will treat to
drinking water standards.
The operation and maintenance requirements for the water supply
treatment options can be quite extensive. The monitoring requirements for
a drinking water treatment system are much more extensive than for surface
water discharge treatment systems. The extent of this difference is
dependent upon the treatment process selected. The actual operation of the
various options is also quite different. The operation of the carbon
adsorption and granular media filtration are straightforward and require
minimal staff time. The ozone/UV and reverse osmosis each require about
two full-time staff to do the required operation and maintenance.
Of the four treatment options, only chemical oxidation results
directly in the destruction of the PAH compounds. With the other three
processes, it depends on how the residuals from the treatment process are
managed. In all likelihood the activated carbon will be regenerated
through incineration. This will result in the destruction of the PAH
compounds. The liquid residual from the reverse osmosis may be acceptable
for discharge into the sanitary sewer. This would result in at least
partial destruction of a percentage of the PAH compounds. A large
percentage would concentrate in the sludge and be destroyed during sludge
incineration. A small but unknown amount would pass through the treatment
plant and be discharged to the Mississippi River. This liquid could
alternatively be shipped to an off-site incinerator for treatment. The
granular media treatment option may present the most difficult residual
management problems. Since the principal design use of such systems is
fine particulate filtration, there is no need to regenerate or replace the
coal. However, when used to remove PAH compounds the media will require
regeneration. Since the coal may be mixed with sand, there will be
problems in regenerating the media through incineration. It is possible
that the media may be landfilled. More work on residual management would
have to be done before this option was selected.
One criteria to be considered in selecting a treatment option is if
the alternative can be phased. The treatment options themselves can not be
27
phased. One method of phasing the remedial actions would be the use of
temporary surface discharge to Minnehaha Creek during construction .
start-up of a drinking water treatment system. This could result in '
initiation of gradient control up to one year earlier..
Environmental Analysis
The use of the discharge from SLP 4 will result in environmental
benefits. Waters in Minnesota are classified for their highest and best
use. In the case of groundwater, Minnesota Rules Chapter 7060.0400
classifies all underground waters of suitable natural quality for potable
use. The treatment and use of this contaminated water would conserve
uncontaminated groundwater for other uses. This water would replace water
presently being pumped from deeper unaffected aquifers or from
uncontaminated portions of this aquifer. There were no environmental
problems identified with the water supply alternative.
Public Health Analysis ^ ^
Since the ultimate intended use of the wat^r in the water supply
alternative is for drinking purposes, there i.k a potential public health
risk. The risk is one that results from long-term exposure to the
carcinogenic PAH compounds. The public health^risk from the treatment and
water supply options are extremely small. Historic data on water quality
of SLP 4 consistently show that the concentrations of carcinogenic PAH
compounds, are below the drinking water criteria for these compounds. The
use of the well was discontinued because the concentration of
non-carcinogenic PAH compounds was above the drinking water criteria. The
non-carcinogenic PAH compound criteria was set to provide an additional
measure of safety beyond the carcinogenic PAH criteria. Research has not
been done establishing a risk level for non-carcinogenic PAH compounds.
These alternatives all assume that treatment will be provided to remove
even the non-carcinogenic PAHs to below the drinking water criteria.
Frequent monitoring of treated water allows for early detection of any
changes in treated water quality. This will preclude or at least greatly
minimize the possibility that water not meeting the criteria is placed in
28
the munlclpaiL system. Since the health risk associated with the drinking
water criteria is based on drinking the water for 70 years, the risk
associated with any short-term exposure between monitoring events would be
very small. The public health risk associated with these alternatives
would be no worse than the risks associated with the treatment system
presently operating on SLP 10 and 15 because the quality of the water being
treated at SLP 10 and 15 is worse than that historically found at SLP 4.
Institutional Analvsis
The regulatory involvement for the water supply alternative is
primarily limited to United States Environmental Protection Agency (EPA),
MPCA and MDH. MDH has the primary responsibility for regulating public
water supplies. However, plans and specifications for any treatment system
would have to be approved by EPA, MPCA and MDH according to the RAP. The
approval of the carbon adsorption option would be the most straightforward
since it is the only treatment process of the four options being evaluated
which has been demonstrated in Minnesota.
As with all the alternatives, the DNR will have to issue a water
appropriation permit for the pumping of SLP 4. The DNR has expressed a
definite preference for use rather than discharge.
The institutional concerns involved with a sale of water to Edina are
more complicated. In recent years, interconnections between municipal
systems have become more common. One aspect of the problem is working out
logistics of the physical delivery and operation. This would also involve
the cost negotiations. In this situation, there will also be a public
perception problem. The problems with the groundwater contamination in St.
Louis Park have been well publicized for many years. Even though the water
delivered will meet drinking water criteria, there may still be many
members of the public who will not recognize this fact. Still others might
believe that any risk, no matter how small, when it involves their drinking
water is unacceptable. An arrangement whereby St. Louis Park provides
water from one of its unaffected wells and only puts the treated water in
their system might alleviate some of the public concern.
29
flQst Analysis
Cost estimates were prepared for each of the four treatment options.
The degree of certainty and completeness varies between options. As
previously discussed, bench scale tests should be done on all the options
except carbon adsorption before the facilities are designed. It is most
probable that these tests would increase the costs rather than demonstrate
that the desired level of treatment could not be obtained. It should also
be recognized that there are no costs included in the granular media
filtration for treatment or disposal of the media or costs for disposal of
the removed contaminants in the reverse osmosis options. It was decided
that these costs were too speculative and would only be important if one of
the options would receive serious enough consideration to conduct bench
tests. At the conclusion of the testing, more realistic cost estimates
could be made.
The water supply options do not contain power costs for pumping the
water from SLP 4. It was assumed that this cost would be off set by the
reduced pvimping of wells presently used.
The capital cost of the carbon adsorption system was estimated to be
$1,190,000. This includes $349,000 for the connection between SLP 4 and
SLP 6. If this amount is subtracted, the cost estimate is very comparable
to the reported cost of the system installed at SLP 10 and 15. The annual
operation and maintenance cost is estimated to be $70,000 per year. At
this time, it is too early to compare this estimated cost to the actual
annual operation and maintenance cost at SLP 10 and 15. The present worth
costs for 10 and 30 years of operation are $1,731,000 and $2,266,000,
respectively. These costs are shown in Table 5.
The capital cost of $1,001,000 for the granular media filtration is
slightly less than that of the carbon adsorption system. The annual
operation and maintenance cost of $85,000 Is slightly higher than the
carbon adsorption system. As previously mentioned, the operation and
30
maintenance cost for the GMF system does not Include any cost for media
regeneration or disposal. The 10-year present worth is $iL,,657,000 and the
30-year is $2,308,000. These costs are shown in Table 6.
The capital cost of the ozone system is estimated to be $1,386,000.
The annual operation and maintenance cost is estimated to be $175,000,
nearly double either of the first two options. This results in
significantly higher present worth cost. The 10-year present worth is
$2,737,000 and the 30-year present worth is $4,076,000. The costs are
shown in Table 7.
Reverse osmosis has the highest estimated capital and annual operation
and maintenance costs of the four options. The costs are $3,095,000 for
capital and $97,000 for annual operation and maintenance. This results in
a 10-year present worth of $4,616,000 and a 30-year present worth of
$6,123,000. The costs are shown in Table 8.
SEC3/346,0/msh 31
SECTION 4
EVALUATION OF COST-EFFECTIVE ALTERNATIVES
Sections 2 and 3 presented analyses of the technical, environmental,
public health', institutional, and cost factors for each evaluated
alternative. This section will compare the attributes of the alternatives..
Only the most important attributes will be discussed. Where there are
distinct differences between alternatives these will be highlighted so the
policy decisions are clearly identified. For this evaluation it was
assumed that carbon absorption system would be used for drinking water
treatment.
PUBLIC HEALTH COMPARISON
The public health analysis did not identify any concerns with any of
the alternatives. All the alternatives will meet the appropriate water
quality standards which take into account public health. There is no
reason to differentiate between the alternatives based on public health.
ENVIRONMENTAL COMPARISON
No environmental problems were identified in the analyses. Although
water supply alternative does more appropriately makes use of the
groundwater, this is more of an institutional factor than an environmental
concern. There is no reason to differentiate between the alternatives
based on environmental quality.
TECHNICAL COMPARISON
All the options are technically feasible. There are some distinct
differences between the alternatives. The Bass Lake and Lake Calhoun
alternative will aggravate any existing high water problems in the Chain of
Lakes. During recent years, pumping out of Lake Calhoun has been
necessary. While this can be accomplished, the SLP 4 discharge may
increase the severity and duration of the problem. The Bass Lake
32
alternative has the added problem of increased flooding at the golf course.
There should be no water level problems with the Minnehaha Creek or
Mississippi River alternatives. There were no identified technical
problems with the water supply alternative. From a technical analysis
standpoint, the water supply, Minnehaha Creek and Mississippi River
alternatives are preferred. The Bass Lake and Lake Calhoun alternatives
present the greatest problems.
INSTITUTIONAL COMPARISON
The institutional factors could play a major role in the
implementation of the selected alternative. A great deal of concern and
reluctance has been expressed by Minneapolis and the Minneapolis Park Board
with the Lake Calhoun and Minnehaha Creek alternatives. Part of this
concern relates to the technical factors already discussed. An equal or
greater concern has been expressed that is based on public perception. The
view is that St. Louis Park would simply be imposing its problem on
Minneapolis with these options. The public thinks that the groundwater is
too contaminated to leave in the ground and therefore does not want it in
the lakes or streams. This alternative would likely apply to the Bass Lake
alternative also. This is an especially difficult problem for the Lake
Calhoun alternative, where permission from Minneapolis would be required.
The same concerns would be expressed with the Bass Lake and Minnehaha Creek
alternatives., but since the city would not exercise direct control, the
concerns could be more easily addressed. There were no negative
institutional concerns identified with the Mississippi River alternative.
The preferred alternative from an institutional perspective is the water
supply option. It does not involve any local unit of government. It is
the stated preference of the DNR. It may be viewed by the citizens of St.
Louis Park as the most logical since it improves their water system rather
than pumping water to waste.
Table 9 summarizes the non-cost factors identified in the technical,
environmental, public health and institutional analysis sections.
33
COST COMPARISON
Table 10 sxuiunarlzes the capital and total present worth for 10 and 30
years of operation for each alternative. If the existing storm sewer
system can be used, the Lake Calhoun and Bass Lake alternatives have
comparable and- the lowest costs. The Minnehaha Creek and Lake Calhoun
alternative with a dedicated forcemain have comparable costs. The
Mississippi River and water supply alternatives have the highest costs
which are roughly equal.
OTHER CONSIDERATIONS
The only additional consideration identified was the flexibility
associated with the Minnehaha Creek alternative. With this alternative, if
the water quality at SLP 4 should improve to the degree that it meets
drinking water criteria the water could be put into the water supply system
at a minimal capital cost. This also allows the flexibility of adding a
water treatment system should the demand for water increase. If the timing
of expenditures is a concern, this alternative allows the gradient control
to begin with the surface water discharge and switch to the water supply
alternative when funds are available for treatment plant construction.
RECOMMENDATION
It is recommended that the discharge from SLP 4 be discharged to
Minneha^ Creek ajt SLP 6 (Yosemite Avenue). The institutional problems and
potential technical problems associated with the Bass Lake and Lake Calhoun
alternatives outweigh the possible cost savings. The two preferred
alternatives based on non-cost factors are the water supply and Mississippi
River alternatives. The institutional advantages of the water supply
alternative suggests that the Mississippi River alternative be eliminated.
The primary reason for recommending the Minnehaha Creek alternative over
the water supply alternative is flexibility. As discussed, the changes in
gr^und^ter quality in response to the pumping are not known. At this time'
it would be prudent to operate the system, for some time to determine what
the quality is and make better predictions on the likelihood that the water
34
may meet drinking water standards in the near future. Once the system is
operational, water treatment can be added without having incurred any
unnecessary capital expenditures, as the piping from SLP 4 to SLP 6 is
required for either alternative.
SLPS4/346,0/msh 35
REFERENCES
1. Bartell, S.M.; Gardner, R.H. and O'Neill, R.V. 1983/1984. The Fates
of Aromatlcs Model (FOAM): Description, Application and Analysis
Ecological Monitoring 22:109-121.
2. Breck, James E. and Bartell, S.M., 1985. Approaches to Modeling the
Fate and Effects of Toxicants in Pelagic Systems. Environmental
Sciences Division, Oak Ridge National Laboratory.
3. Conner, Michael Stewart, 1984. Fish/Sediment Concentration Ratios
for Organic Compounds Environmental Sciences Technologv 18:31-35
4. LaVoic, Edmond; Coleman, Daniel; Tonne, Robert; and Hoffmann, Dietrich
1983. Mutagenicity, Tumor Initiating Activity and Metabolism of
Methylated Anthracenes. Polvnuclear Aromatic Hvdrocarbons:
Formation. Metabolism and Measurement Battelle Press.
5. Staples, Carles; Dickson, Kenneth; Rodgers, John and Saleh, Farida
1985. A Model for Predicting the Influence of Suspended
Sediments on the Bioavailability of Neutral Organic Chemicals
in the Water Compartment. Aouatic Toxicoloev and Hazard
Assessment ASTM.
REREF/346,0/msh
TABLE 1
COMPARISON OF SLP 4 WATER QUALITY AND CRITERIA (concentrations in ng/L)
SLP 4 Accurex Report
Sum of Benzo(a)pyrene & 2 Dibenz(a,h)anthracene
Carcinogenic PAH Compounds
4
Other PAH Compounds 113
Phenanthrene 21
Phenolics NO
SLP 4 Avg. Cone. 7/81-10/82
0.4
340
Drinking Water Criteria
5.6
28
280
Ho Standard
No Standard
NPDES Permit Criteria
No Standard
311
17,000/34,000*
1,000/2,000*
10,000
* First nunber is 30-day average concentration. Second number is maximum concentration.
TABLI/346,0
TiBLE 2
WATER QUALITY DATA
a.p Btoni Btora Btn Btora Btora Btora mnnahriia Laka Laka 4 1 E 3 4 5 3 4 Calhoun Harrlat
DATEl m/2^m lOniVBS 1Q/iOk'B3 lOAIQ^BB 10^0^33 ICb'IIVBS 10711^33 07/21/23 07/21/23 07/21/23
ANALYSIS BVl Anurax CHEN Hill OCH HILL QCN HILL IWH HILL QCN HILL CKN HILL CWN HILL fSCH HILL QCN HILL
ANALYTICAL EDUIPNBITl BC/HB BC/NB BiyNB BG/NB BC^n BC/HB BC/m BiyHB G^NB ec/NB
tamtar
• (All valuas In ng/Ll Naphthalana BED E60 330 370 150 340 3B 1-Ha tliy I naph th ala na 180 EBO EBO 430 140 330 11 B-Hsthy Inaph thai ana 300 540 670 800 EBO 750 IB Aoanaphthylana 2 Acanaphthana 72 54 07 40 110 Pluorana a B1 31 40 35 73 Anthracana 4 87 30 E6 44 Riananlhrana SI 340 OO B30 170 35 300 E3 13 hrrana 4 130 130 110 103 5E 1E0 71 E7 3 Fluoranthana 4 EBO 170 170 160 54 130 35 14 11 Banzo(a)anthracana[*] SB 34 EB 34 E3 3.5 OiryaanaC) 2 130 83 6E 83 38 BE 8.3 Banio(b B k)anthraBana(*] 130 BE 51 BaiBo(a|pyrana(*] 2 30 Bania(a]pyrana Bamntgi h, 11pary lana E7 Indanoll •BiBrcdlpryanaC*]. , E3 D1bania(aih)anthraeana(*)
Total CarelnoBame PAHa 4 313 1BE 30 37 — 33 158 13.3 — Total "Othar- PAHa 113 1.B4E 1,733 1,780 E,113 741 E,E10 Ell EES 17
PAH enpound.
WaD/34B,a
T«i£ a ST. LOUIS nuiK vat aM
aURFAE DISHMSE DRAIN/IBE OPTmNS
LAKE CALHOUN IQrwIty Syatn)
LAKE CALHOUN (OadloBtad ^at«1
HINNnAHA nEBC Dladiarga at Hall aPS
BASS LAKE NSSISSIPPI RnBI/
BASSETT CREB I-3B4 Stora Baaar
Unit (bat II) Ouan. Eat. Eat. Eat. Ouan. Ouan. - Eat.
msaizATiaN (TBI L.B. 1846 90,39 98,90 14,49 98,810
nsraLATin lOP DIP A Httlnga L.F. B7JI0 6,39 19,19 18,800 49,89
B" DIP A Ftttlnaa UP. B1.B0 8,09 173,89 1,19 84,89
IB" RCP L.F. EC.00 39 B,B9
lir GV Eadi B30.00 8 1,89 8 3,79 8" OV Each Bsajm 1 90 3 1,69 1 90 4* m Each 1,09.00 1 1,09 1 1,09 1 1,09 1 1,09 1 1,09 Hay. Craaalng Each BE ,000 JIB • 1 86,90 1 86,000 RR CroaalnB Each eo,000.00 8 40,000 4-lana Btraat Craaalng &ch 10,000.00 8 80,90
EXCAVATSm A RBBTORATmH
Curb A Suttar Raoaa
A Raplaca L.F. 16.00 8,09 19,79 4,39 84,69 1,19 17,89 10,800 183,59 Roaora A Raplaca
gitiBlnoua Road 8.V. B.00 18,89 136,880 8,09 78,89 8,90 18,49 84,810 19,89
Raova A Raplaca Bidaalk S.F. 4J)0 3,800 14,90 7,90 9,90 Sod S.Y. 8J0 B9 8,886 1,886 4,90 8,09 80,09 Baad A Mulch B.Y. 1.9 1,39 8,09
aaar A Brub 8.Y. 8.50 89 1,860
cwsraicrin itua •
18,810 49,810 39,90 87,90 1,018,110
BBMEBIINB A AONIHIBTRATIM (i m 8,69 9,79 9,870 13,510 89,89
DRRATIDN A HAMTBIANCE
Annual Labor Puaptng
Oparatlana Hour 80.00 BB 1,380 84 1,89 9 1,09 38 1,380 68 1,09 Annual Labor Holntananca Hour ggjIO 64 1,89 18 39 IB 39 19 8,180 38 89 Annual Piaplng aP4 BBS daya L.SL 88,79 1 38,79 1 38,79 1 38,79 1 38,79 1 38,780 Annual Piaplng t Calhoun
BO daya L.8. 13,640 1 13,6« 1 13,69 1 13,59
RtanT VALUE R)R 0 A H (1=9, n^O yr) 378,130 370,19 93,700 384,830 98,170 FRSBIT VALUE FOR 0 A H (1=9, ir«0 yr) 79,79 79,90 94,870 788,39 98,89
10 YEAR OPBIAiTnil
SUBTOTAL 39,89 89,310 89,90 96,870 1,40,800
CDKTIISaCia (E91 78,79 19,89 19,69 9,19 80,69 TOTAL moiECT COST (Praaont ValuaJ 478,39 1,111,670 98,49 658,180 1,79,49
ag TEW DFBOiai SUBTOTAL. 79,89 1,89,010 844,89 347,380 1,751,89
C0KTIW9CIE8 (29) 19,90 868,800 19,89 19,470 39,380 TOTAL PROlEa COST (Praaant Value) 91,39 1,661,810 1 ,19,09 1,018,830 8,101,89
aiRDis'adB.a
TABLE 4
SANITARY SEWER DISCHARGE COSTS
MOBILIZATION (7%)
INSTALLATION 8" DIP & Fittings 18" RCF 8" GV 4' MH
EXCAVATION & RESTORATION Curb & Gutter Remove & Replace
Remove & Replace Bituminous Road
Unit Cost ($)
L.S.
L.F. L.F. Each Each
L.F.
S.Y.
21.60 22.00 530.00
1,050.00
15.00
8.00
Quantity
800 300 1 1
1,100
2,322
Extension
$4,240
17,280 6,600
530 1,050
16,500
18,580
CONSTRUCTION TOTAL ENGINEERING & ADMINISTRATION (20%)
$64,780 $12,960
OPERATION & MAINTENANCE SAC Charge L.S. Annual User Charge L.S. Annual Labor Pumping Operations ' Hour
Annual Pumping SLP4 365 Days L.S.
20.00
32,780
52
2,759,120 587,460
1,040
32,790
PRESENT VALUE FOR 0 & M (1-5%, n-10 yr.) PRESENT VALUE FOR 0 & M (1-5%, n-30 yr.)
$7,556,530 $12,309,900
10-YEAR OPERATION SUBTOTAL CONTINGENCIES (5%) TOTAL PROJECT COST (Present Value)
30-YEAR OPERATION SUBTOTAL CONTINGENCIES (5%) TOTAL PROJECT COST (Present Value)
$7,634,270 381,710
8,015,980
$12,387,640 619,380
13,007,020
SSDC/346,0
TABLE 5
COST ESTIMATE FOR GRANULAR ACTIVATED CARBON
Canltal Eouioment Quantity Unit Unit Cost Cost
Contactors 2 Each $70,000 $140,000 Carbon Inventory 40,000 Lbs. .90 36,000 Ins trumentat ion 1 L.S. 35,000 35,000 Internal Piping 1 L.S. 26,000 26,000 Electrical 1 L.S. 44,000 44,000 Building 1 L.S. 123,000 123,000 Piping from SLP4 1 L.S. 349,000 349,000 Installation 1 L.S. 44,000 44,000 Restoration 1 L.S. 18,000 18,000
DIRECT COST $ 815,000
Engineering & Administration (20%) $163,000 Contractors Fee (6%) 49,000 Contingency (20%) i63.000
TOTAL CAPITAL COST $1,190,000
Annual Cost
Labor 1,300 Hour $20.00 $26,000 Power 104,000 KWH 0.05 5,000 Maintenance 1 L.S. 5,000 5,000 Lab Analysis 12 Each 1,000 12,000 Carbon Regeneration 13,000 Lb. 0.70 9,000 Make-up Carbon 1,300 Lb. 0.90 1.000
SUBTOTAL 58,000 Contingency (20%) 12,000
TOTAL $ 70,000/yr
Present Worth (5% net annual interest rate)
10 years in operation
30 years in operation
$1,731,000
$2,266,000
SLPTBL/346,0/1
TABLE 6
COST ESTIMATE FOR GRANULAR MEDIA FILTRATION UP-GRADE
Caoital Eauioment Ouantltv Unit Unit Cost Cost
Granular Media 10,000 G.F. $17.00 $170,000 Capital Equipment 1 L.,S,. 20,000 20,000 Pilot Study 1 L.S. 20,000 20,000 Instrumentation 1 L.S. 21,000 21,000 w Internal Piping 1 L.S. 21,000 21,000 Electrical 1 L.S. 11,000 11,000 Building 1 L.S. -0- -0-Piping from SLP4 1 L.S. 349,000 349,000 Installation 1 L.S. 53,000 53,000
• Restoration 1 L.S. 21,000 21,000
DIRECT COST $ 686,000
Engineering & Administration (20%) $137,000 Contractors Fee (6%) 41,000
• Contingency (20%) 137.000
TOTAL CAPITAL COST $1,001,000
Annual, Cost
• Labor 1,300 Hour $20.00 $26,000 Power 44,000 KWH 0.05 2,000 Maintenance 1 L.S. 5,000 5,000 Lab Analysis 12 Each 1,000 12,000 Make-up Granular Media 1,500 C.F. 17.00 26,000
SUBTOTAL 71,000 Contingency (20%) 14.000
TOTAL $ 85,000/yr
Present Worth (5% net annual Interest rate)
10 years In operation $1,657,000
30 years in operation $2,308,000
SLPTBL/346,0/2
TABLE 7
COST ESTIMATE FOR OZONE TREATMENT
Capital Equipment Quantity Unit Unit Cost
Ozone Generator- (120 lbs/day) Reactor Air Dryer Ins trumentat ion Internal Piping Electrical Building Piping from SLP4 Installation Restoration
DIRECT COST
Engineering & Administration (20%) Contractors Fee (6%) Contingency (20%)
Each Each Each L.S. L.S. L.S. L.S. L.S. L.S. L.S.
$129,000 82,000 15,000 45,000 34,000 57,000
158,000 349,000 57,000 23,000
TOTAL CAPITAL COST
•Cost
$129,000 82,000 15,000 45,000 34,000 57,000
158,000 349,000 57,000 23.000
$ 949,000
$190,000 57,000
190.000
$1,386,000
Annual Cost
Labor Power Maintenance Lab Analysis
4,000 284,000
1 12
SUBTOTAL
Hour KWH L.S. Each
Contingency (20%)
TOTAL
Present Worth (5% net annual Interest rate)
10 years In operation
30 years in operation
$20.00 0.05
40,000 1,000
$80,000 14,000 40,000 12,000
146,000 29.000
$175,000/yr
$2,737,000
$4,076,000
SLPTBL/346,0/3
TABLE 8
COST ESTIMATE FOR REVERSE OSMOSIS
Canital Eauioment Unit Unit Cost Cost
Osmosis Unit 1 Each $720,000 $720,000 Instrvunentation 1 L.S. 144,000 144,000 Internal Piping 1 L.S. 108,000 108,000 Electrical 1 L.S. 180,000 180,000 Building 1 L.S. 500,000 500,000 Piping from SLP4 1 L.S. 216,000 216,000 Installation 1 L.S. 180,000 180,000 Restoration 1 L.S. 72,000 72.000
DIRECT COST $2,120,000
Engineering & Administration (20%) $424,000 Contractors Fee (6%) 127,000 Contingency (20%) 424.000
TOTAL CAPITAL COST $3,095,000
Annual qp^t
Labor 3,700 Hour $20.00 $74,000 Power 454,000 KWH 0.05 23,000 Membrane Replacement 100 Each 500 50,000 Maintenance 1 L.S. 5,000 5,000 Lab Analysis 12 Each 1,000 12,000
SUBTOTAL 164,000 Contingency (20%) 33.000
TOTAL $197,000/yr
Present Worth (5% net annual interest rate)
10 years in operation
30 years in operation
$4,616,000
$6,123,000
SLPTBL/346,0/4
TABLE 9
NON-COST COMPARISON.
Bass Lake
Technical Analvaia
High .water at golf course and Lake Calhoun
Environmental Public Health. Analysis Analysis
No problems No problems
Institutional Analysis
Public perception of poor quality water
Lake Calhoun Grayity System
High water Unsafe ice
No problems No.problems Public perception of poor quality water. Interjurisdictional with Npls.
Lake Calhoun Dedicated System
High water No problems No problems Public perception of poor quality water. Interjurisdictional with Mpls
Minnehaha Creek Unsafe ice No problems No proble Public perception of poor quality water
Mississippi River 1394/Bassett Creek
No problems No problems No problems No proble
Water Supply Carbon Adsorption
No proble No problems No problems No problems Preferred by DNR
T9NCC/346,0/
TABLE 10
COST COMPARISON
Bass Lake
Lake Calhoun
Gravity System Dedicated System
Minnehaha Creek
Mississippi River 1394/Bassett Creek
Water Supply Carbon Adsorption
Capital Cost
81,000
419,000
lO-Year Present Worth Value
30-year Present Worth Value
559,000 1,017,000
15,000 472,000 922,000 556,000 1,112,000 1,552,000
819,000 1,133,000
1,222,000 1,785,000 2,102,000
1,190,000 1,779,000 2,362,000
LakB Harriet
Scale In Feet
Gradient Control Well
Approximate Area of Contamination
Figure 1
GRADIENT CONTROL WELL LOCATIONS
fr
11 4 I'
,.JI 2000
i9f
A ifk;„ SVESrwoOO
L>*>CE m •n-:;s :.i^-
, 5M8Si ll. Scale in Feet
">&'c
^•f.^
^^Cauniry-Ciuo . _,. -JHiigii 6ch 211 -•~Wt -h
BROWNIE lAKP
ii:i^-4r'-
7 ^ -f
EaiKr"^^-
•V
. S«h.i
' UlU Nl
MOOOIT _w'HoaD
^^•'!l. !, \ W-
~ III; ill ifl! '-rv^
>
>-,fir::/vJi; lD<ta<ti«-»en"H' i/T^ * •
c v4W«ni •*•«
.W«k^
TWIN LAKES ^ ^LAKE Ti/
Ji5;
^ Hootn =k
I Sen
Cedmr^
s, .1 ^ te ID =—G
. ,/-\M: 1-
. • -,j Binilde- — - #'^5^ Hlgn Sch
a.Ledu
HANNAN
.| -:^>;i==^S=-^:S%^;.Pa,K " ij
-32 ^-1
^"^asoaurn • arrOaVs-
/•.V ri; r SiinnMBOlia . „
;j fllorrn m" Sar'ic m I! W>*r-
— JK \\ \ u 'i' n /' •= -r,_.., . ^ •PosaQtOo^ ir^ -^irnP;: i-..-.I. :S=N
•":: -J=-i£ttP.iA,P Ojyi^3_:i|J-™« ^ , ^'~^' t • §|i
^ ' =ia=' '"
\^J
LAK^ OF
THE I^ES 35^
Part • >>Ie£fe •» • "Menenen •-^' n/,^'; /'M: ji£-^''.si^_ azr_—L " 'f
11^33:^^ — J 34
sr;'
I6I\ i "Whittiar ScH I
:i
• . ; • ^ ii ;' : • 11 'f •ilWater/iTaoii/^': !K ,r^- !•
IM. . ~ •
-'• = =^S=J' .1 «'• ^ awtsnm® / i^oSi. - .
Ij,^: PlaygTOuiwn'jj
i^n :|::|r.rf=^,,,
r\i: •^"ii ii ii '•v.ig
•\
aaPw^hifr"
4l!'^;- *ST* ^t-"^ I -1 : ' ^ ,
l>^.fc7::29'N aavorT^ /p?10l.
ALZ^': .M Ii N N E A,:PQ^ L; I .-.vv ?.«r>- •*' sr'-
.1 , —- =_ II
PAf?K , , . 'V/ 3_ /: Sen *
"uZBtT^ ^T'? PKOt Bill 3eh-X-p" n.' ~
Caihoun B«ach
CHlQAaO ' r,^..
— ill T,U?Q
CiUbon SSh :!2t2!i'lMF .,•370
•^rneWf;
••''-,WlatanTanK» •n>_-i o; ^-
^ST-' Fi:/
W,^ %
LAKE
CALHOUN
• Bryant^.'^ iSauarei- '.
fc- -igp' —
JK:
= !—^\\.
--•I . ,' IV li jarHif
. V.-Wa*er!? ila
-rrrT..j»ii
= S4ii , •* LAKE
• V ^rPaigjp
r*" '• IT; cAMsmit
J'
===%V:
C'HarKi
ilQ?/
\WOLFE^°"' ParK •)C
LAKE iiSae.'-
£.-•<'...I !: = lJ;ILymUi«{ -.—• 3UTH
' Mmntanoa
^as'. —JgTtt—
! /35W Hr= STORM
i TUNNEL
T\'-i ->tou
so.-n.. [ I ' ' " ~ - —
•-4'; !•-
•I Ti
• Jj"* 1 I'll
LAKE'vVOC^sii.CEME7/£>^ . - -
^S=--.FiMhii :-i^^r
rrf-... • - .,1.-==^. -. •- - - . •^.
SI±
:r"r :" -l «|F^w--InKitaiofth. ^
iW''""' i,i^Ine«niauon sr , assi:
=^^==i==dt^'i^3yU^iQi -ilT, • ! .J •ijj; j «iiL'-ViCli'/Zin
Aiitaioii3i I !i 51 i;-^vi --,
x:t- ^1
Linaen Hiiis'w if *r/fZn. - '^'
- ;; ;• i:*" ., •. •: Jik^l "i ii !i :1 : ii
— I ST - I /^'l
LYNOAtE _ PARK
Q
'.-.ii'
- ;p.|i/—1!,- ;j_Y ;i Y'. •• - -i a -i-^ii ll-'4 Ii ;•
i: «lNicoiiel saMt^BSi II
^ N T'eiC
ar4\
\\ a Blaie* / 'i'~ • annnaifu,] leiL,,-. -^i- •• I
• 1 -ip ! ~ Ihtkriachan .-
.^ark L
_C 1^^ ,c ^ooksio* • wl ;;_—
z iBmApOWBROpK^I isU...-"", ''=i60LF COWflSEl'^
• X C ffi
• i-iinii.- • .1 -BnntmilSclllC
•ZZLJ——.12'^^ "«5-KJ I: :i i ••'
;: ii. ! • Hmn i«*T
® Oil': iOi\5jl' ^ sjj ilo-;"^
LAKE
HARRIET 3^7
•• /htarda Plaisance
IM f :iJ-L III ̂ •<1==':#='^== //«^ /1;ii( Sip,
• I
•; . ;/ |nf^r== •' V I
T —
"Ii P^—^ • SF • IROWNDALE ; ^ N -i I*" •• ,':; CilC'p' ;: !• :j^::
W' i PSrvuM i; I: h i|i
Figure 2
PRELIMINARY SURFACE WATE DISCHARGE LOCATIONS
'/r 4 I--J
1394/BA^ETT C^EEK 2000 -r
JM. /-»' •
5M88i 28 Scale in Feet
, • N v;. • d/^ "7'h-;-: • T^'K ir?
'iiC B«*i •Vw ^7*U«— I M_il- ^
- —W«UI I l.<
;'r(nn€»ooris 'Cjuntry Ciuo J ••v»9iwooa =®®
./Hiiw 6ch :
•i? -f^^^^^tildiiii Manor,
- •« ' "• " :•/ • .'' •PiaygK4mflt:i=:3arf«v ,11
I 1. "i -i' "W
NO?. -
Kenwwtt'l'!"
4 J!tKi)]i Park- 1
=m^
-• N<=
.1 T
I r,
,. Cedar JUibr-K^tdie:;
^r|i ;:i"-^ --gsr*^ •^l! '^'.r— i^JSOIV 4
'•^ 3-^ TWIN LAKES ^
CEDAR I/r K ''OKI- '
•'' yv/T -r//
^Ti::,-: ;iij[*^(|-K»iiwooii Sch P
Ji • ••! I Ddodiaa^^ed-fa:
"•SBooti • 'falHnan
IvensiSquarei
LAKE^ 4s'';ijii
211
.7 ~:; ^ * " Q'J
#' r:3. ' B«ildr— /"Ci^ Kign Sch r
.'9. /IllUr^l;
H ANNAN
hm ,«>i» ortnii
=^qs^^=:. ./ii. -- • - J • iaJii: ujiK-. . '
5SA o2.!^7li y "•^7
•^s?v
Pirkl
,.:_ STTCtiaiiiod
jc "^ST" • 1::^ ir2ir:^"'n^^^3-teA all s«r • r "-tmiaL- ' • — * * •-• ,
•.ri.V 7^
Paraf=,
UinanmUa IrvAaaoanw
uixridt InaututaiiK^
y . •! 1 ;i \
'"^aawiurn -aart-Oakd.
Marrrt in' aanti Ptl
LAKE OF \
yji! '. "^,
, - "Jtftfer—p n/iSv.; / 'BlJr Hi»a Sck
^'^imegTow^ 'M'IHI ^ Att^
i?33. ,{ :l34
ill I
T THE IStES /ti__^f~- :M I; N Nl
i6>\ Whitti»r ScH • $$*• i / ' *
t •\ 3L VO t|
STL^
i; Sil li • ; • ' II ii ; ~" |i ly; i; •ilWaner/Taok^'! ;. !K
•dar^ T— •- ' diwwcTawxa
• . y.\ ; -«i'|aiLenai^ : »®« '
.quila dkhs i! III
-!['- v//; - aouiia Park
-io I. e]F~; ?"•'! i -'i::; -i^i •' • ^ '• XuihfV P&riM -I-— -ar^' !
^ri== ^Lrs&-Laj5!i::Rki'ii ill •|::iri:1^t^
.Hame- i /ia.:::! .'_>»i' :3Z»^ ' = • ':ST;'_1 r
Sujtsnr |i Playipouriqir-^ll n
'^T^^arS/^"
iHUSdh PARK ,T 'iHi^ San*
.Z?af* -yr Baawn^b
i! II' ' T,^ 'J; ;* i; !• ii •' / iH 'v^-Wwadir. •.i: -: ii i; ii -•'.•• J'h ^
rr ^.fcT:-29'N ~-flavirr^'-L •''—.-H S ••^j! • J, >j^ ^"1
XiZ8 ir* r^<; pnw-Biii
ci;_ ^\ v
CaJhoun Beach
latiL E APOiDI
c;H/ca<30~'^' '
{IILPQ
• CilbonSah ;. •-W- N^efr^
,•^570 ;.
^roeWf!
•*>; , ̂ tTaaui Park==^ XylbO'Pafki ,1
•|i,,VViicaf\Tank'» T, 2',"--' ji[
. V,17V HitB&h
-Til: y ^3?" S.
- p .:i.-y.>._,.?£| ° s>*s5 --- •
•ti •'» - ~ 'F-% Z_ 9f.
-;• i ;| .If'HarldlKnolUir i Pi Id II jafx" " •
I anoDpinq
y.-*n*grir jj
LAKE
CALHOUN
• Brvant^-^ iSauarei- '-:
^ 3go'- —
•1 3l: 1" i
jU!juLl_fe=J L
— , . , ;'EiarldlKnoll,,r ; Pbrnil :;ji, v^ Idii jarHTT 1 • jith .sr-'i ; J'
LAKE OA HUH
SWOOCfUTS -enter'
"a itth _3!iL
W :':-
/ PpPTrfT
er —
mWOLFE^^^^l^i"' •! LAKE Q.
^ e5rf5«,<iA^'
•)0
H^-. ParK
^2?=^'!sk^ihy_S " ~^- '••'i I* HII' asm • . I I'"
CT /'^•J. H '-a- ':--"^fK. ; ^ : • :
3:. JKi 11 II
• ii-=^=
141
- bbrnnaliaa
" Golf 'CourM"
/351V ==Hr= STORM -P i TUNNEL
uni I iii; :li
. 3»TH LAKEWOC; y=
;ICEMEX£>^ • " -JtZi.
A.Sel?"^ ,. *1 III Jlneamauon I "i ;jarx I>4 ST . aasii :i ui. •! "• • .i 'il
ii Snopcms Camtet—i.
-AdMertkodist V?
illl. TI.-I
KHosDital
i'^iSKS;21-,
FIELD: -?•• I il\\
^iS=i='|
• yi| I / L;:^ •iaOBOWICHii ST-
till; HI f
'Ii' ir ',i" 1-^ p ~^i!^ t :n =-LfS^PgiP i
-pOND ;;." 2- /—
vipf -7' •: " ijjD::. -"^!' i "-•r iw'-- kjci .ijll
i.YNOAtE _ PARK
Q
\r r-r.:i^ij.i-„
' 'Al
•41 l! '.-1: ulNicoiieL
-^iL '' i^ii o: c ^"ooksioa: w
Linoen dilis'di ^Id
^ ni^bowBRopii::%i tst f XbOLF COURSElJ %
Wareriaorks
its "K
•'S-- '•J«a»aiajjd_~p'^ ^.Paik
.1-BmwgtWt
5. - - , -aa. 'j?Ountfy-CMb —-Wa.-'-'- '-7- 1 -'i^^;^)•,.
,—•• I'f 4 -'T„ 4 • IffliMli ;• ,ij "•-•S'l I'C "••• Iis^iii •;!' ii 5sr^4/.'/i*.-.j/
-r^-a 1: . :• -dVuTUimt Ha '• ^ 11-^
M^PARK 'i K-^' I rarMuog ; -J5 !: i: ii iji _.
® " ;,a . *ir :;' ipiii
T. -4^' ;i t:, :p- >F»eic
,430 •' ;; •sri'lG • g65
^^innenn j n
"• Jii '7 Hian detr .4 '
•1 •• I
!i TI T :i -^1 ii; if • 4 '! — I I ki) • P'l
Figure 2
PRELIMINARY SURFACE WATER DISCHARGE LOCATIONS
0 I.
2000 I
Scale In Feet
CLOSED CONDUIT OPEN CHANNEL
Figure 3
ST. LOUIS PARK WELL SLPA SURFACE DISCHARGE OPTIONS
}/
^ *
© Figure 4
SAMPLING LOCATIONS CH2M HILL STUDY