FASER LS2 works coordina3on: 3 rd Mee3ng Jamie Boyd 6/6/2019 1 Progress on a few unrelated areas reported (relevant for different WPs) Backup with more general slides (mostly from previous mee3ngs)

Upload: others

Post on 05-Jul-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: FASERLS2&works&coordinaon:& 3rd&Mee3ng& · 2019-07-17 · FASERLS2&works&coordinaon:& 3rd&Mee3ng& Jamie&Boyd& 6/6/2019 1 Progress&on&afew&unrelated&areas&reported&(relevantfor&different

FASER  LS2  works  coordina3on:  3rd  Mee3ng  

Jamie  Boyd  6/6/2019  

1  

Progress  on  a  few  unrelated  areas  reported  (relevant  for  different  WPs)  Backup  with  more  general  slides  (mostly  from  previous  mee3ngs)  

Page 2: FASERLS2&works&coordinaon:& 3rd&Mee3ng& · 2019-07-17 · FASERLS2&works&coordinaon:& 3rd&Mee3ng& Jamie&Boyd& 6/6/2019 1 Progress&on&afew&unrelated&areas&reported&(relevantfor&different

Op#cal  Fiber  installa#on  for  FASER  experiment  Discussed  with  Johannes  Troller  (EN-­‐EL-­‐FC)  21.5.19.  •   It  seems  it  should  be  fairly  simple  to  make  a  deriva3on  of  a  microduct  passing  TI12  to  bring  12  or  24  fibers  from  US15  (downstairs  in  p1)  to  TI12  

•   Not  a  big  cost  difference  for  12  or  24  fibers  •   Can  then  be  patched  to  exis3ng  fibers  that  go  from  US15  to  SR1    

•   It  maybe  that  a  fiber  carrying  clock/orbit  signals  could  be  patched  in  already  in  US15  (depending  on  the  choice  of  source  for  these  signals).    

•   Rack  we  want  the  fibers  to  go  to  in  SR1  is  4Y.02-­‐10=SR1,  need  to  define  the  details  of  the  rack  loca3on  in  TI12  (also  which  connec3on  we  need  there)  •   In  case  the  deriva3on  of  the  microduct  is  infeasible,  the  installa3on  of  a  new  duct  with  microducts  plus  fibre  cable  is  required  from  US15  to  TI12  •   Or,  as  a  backup  if  the  above  is  problema3c  could  also  try  to  use  BI  infrastructure  to  get  fibers  to  TI12,  but  not  preferred  solu3on.  •   Work  would  be  planned  to  be  done  by  May  2020  

•   By  that  3me  the  rack  in  TI12  and  cable  trays  would  need  to  be  installed  (will  require  some  coordina3on  at  the  3me)  

•   Johannes  will  look  into  detail  at  available  fibers,  channels  and  come  back  with  a  detailed  plan,  including  a  cost  es3mate  •   Liam  to  look  into  integra3on  details  (route  of  cable  trays  /  telex  in  UJ12/TI12,  final  loca3on  of  FASER  racks  in  TI12)  once  more  informa3on  from  Johannes  is  available  (by  August)  •   Followed  in  3cket:  RQF1152082  

Page 3: FASERLS2&works&coordinaon:& 3rd&Mee3ng& · 2019-07-17 · FASERLS2&works&coordinaon:& 3rd&Mee3ng& Jamie&Boyd& 6/6/2019 1 Progress&on&afew&unrelated&areas&reported&(relevantfor&different

Grounding  /  Earthing  •  Yann  Maurer  (EN-­‐EL-­‐EIC)  can  make  a  connec3on  to  the  LHC  earthing  cable  and  connect  this  to  FASER  infrastructure:  – Detector  baseplane  –  Electronics  rack  housing  

3  

Picture  from  Liam,  showing  suggested  (simplified)  earthing  cable  rou3ng  

Page 4: FASERLS2&works&coordinaon:& 3rd&Mee3ng& · 2019-07-17 · FASERLS2&works&coordinaon:& 3rd&Mee3ng& Jamie&Boyd& 6/6/2019 1 Progress&on&afew&unrelated&areas&reported&(relevantfor&different

Civil  Engineering  Strengthening  Frames  •  Discussed  with  Pierre  Thonet  if  it  could  be  problema3c  for  the  magne3c  field  if  we  have  a  steel  frame  that  is  not  ‘under’  the  magnet  but  also  level  with  it:  

4  

•  It  seems  this  will  not  be  problema3c  •  Going  ahead  with  steel  strengthening  frames  is  therefore  no  problem!  

Page 5: FASERLS2&works&coordinaon:& 3rd&Mee3ng& · 2019-07-17 · FASERLS2&works&coordinaon:& 3rd&Mee3ng& Jamie&Boyd& 6/6/2019 1 Progress&on&afew&unrelated&areas&reported&(relevantfor&different

Cooling    •  Have  asked  EN-­‐CV  if  they  can  take  responsibility  for  configuring  and  M&O  for  the  FASER  chiller  –  Informal  discussion  with  Olivier  quite  posi3ve,  awai3ng  from  from  Roberto  and  Mauro  

•  Olivier  will  run  a  fluidic  simula3on  of  the  cooling  in  TI12,  based  on  the  following  conserva3ve  simplified  model  of  heat  dissipa3on:  

5  

Page 6: FASERLS2&works&coordinaon:& 3rd&Mee3ng& · 2019-07-17 · FASERLS2&works&coordinaon:& 3rd&Mee3ng& Jamie&Boyd& 6/6/2019 1 Progress&on&afew&unrelated&areas&reported&(relevantfor&different

Backup…  

6  

Page 7: FASERLS2&works&coordinaon:& 3rd&Mee3ng& · 2019-07-17 · FASERLS2&works&coordinaon:& 3rd&Mee3ng& Jamie&Boyd& 6/6/2019 1 Progress&on&afew&unrelated&areas&reported&(relevantfor&different

Proposed  Workpackages  1.  Prepara3on  (F.  Sanchez  Galan  (EA),  L.  Dougherty*  (ACE))  

–  Lowering  cable  trays  in  UJ12    –  Removing  obsolete  ven3la3on  ducts  in  UJ12/TI12  –  Removing  GSM  cable,  installing  GSM  antenna  –  Installa3on  of  handling  equipment  Work  to  be  completed  in  2019  

2.  Civil  Engineering  (J.  Gall  (SMB))    Work  to  be  completed  during  iden3fied  6  week  (+4  weeks  out  of  working  hours)  slot  in  Jan/Feb/March  2020    

3.  Installa3on  (J.  Boyd  (EP),  M.  Bernardini  (ACE))  –  Transport  of  detector  components    –  Installa3on  of  power    –  Installa3on  of  compressed  air  –  Installa3on  of  op3cal  fibers  Work  to  be  completed  before  cool  down  of  sector  81  (early  June  2020)  

4.  Detector  Commissioning  (J.  Boyd  (EP))    Work  to  be  completed  before  end  of  LS2  

ECRs  to  be  wrinen  for  WP1,  2,  3  to  outline  technical  details  of  needed  work.    WP1  ECR  to  be  released  soon.  

7  *  -­‐  L.  Dougherty  would  be  worksite  supervisor  

Reminder!  

Page 8: FASERLS2&works&coordinaon:& 3rd&Mee3ng& · 2019-07-17 · FASERLS2&works&coordinaon:& 3rd&Mee3ng& Jamie&Boyd& 6/6/2019 1 Progress&on&afew&unrelated&areas&reported&(relevantfor&different

Coordina3on  •  Propose  bi-­‐weekly  coordina3on  mee3ngs  

–  Chaired  by  J.  Boyd  (EP,  Project  Leader)  (B.  Petersen  (deputy))  –  Include:  

•  Work-­‐package  coordinators  •  F.  Sanchez-­‐Galan,  L.  Dougherty  •  J.  Gall  •  LHC  coordina3on:  M.  Bernardini  •  LHC  Safety  coordinators:  J.  Etheridge,  S.  Grillot  •  When  necessary  contacts  for  different  teams:  

–  EL-­‐EIC  –  Y.  Maurer      –  EL-­‐FC  –  Gael  Girardot  –  EA  –  M.  Papamichali  –  CV  –  O.  Crespo-­‐Lopez  –  HE  –  C.  Bertone  –  SMB  –  E.  Perez-­‐Duenas  –  HSE  –  M.  Andreini  (FASER  safety  contact)  –  RP  –  C.  Adorisio  

•  Mee3ng  slot  14-­‐15h  Thursdays  (every-­‐other-­‐week)  –  Next  slot  is  a  CERN  holiday,  so  propose  next  mee3ng  in  3  weeks  (June  6th)  

•  Indico  category  for  our  mee3ngs:  hnps://indico.cern.ch/category/11281/  

8  

Page 9: FASERLS2&works&coordinaon:& 3rd&Mee3ng& · 2019-07-17 · FASERLS2&works&coordinaon:& 3rd&Mee3ng& Jamie&Boyd& 6/6/2019 1 Progress&on&afew&unrelated&areas&reported&(relevantfor&different

e-­‐group  •  I  have  setup  an  e-­‐group  for  FASER  LS2  work  coordina3on:  –  faser-­‐ls2-­‐works-­‐[email protected]  

9  Updated  since  last  mee3ng…  

Page 10: FASERLS2&works&coordinaon:& 3rd&Mee3ng& · 2019-07-17 · FASERLS2&works&coordinaon:& 3rd&Mee3ng& Jamie&Boyd& 6/6/2019 1 Progress&on&afew&unrelated&areas&reported&(relevantfor&different

FASER  EDMS  •  FASER  EDMS  node  has  been  setup:  – hnps://edms.cern.ch/ui/#!master/navigator/project?P:100368375:100368375:subDocs  

10  

Page 11: FASERLS2&works&coordinaon:& 3rd&Mee3ng& · 2019-07-17 · FASERLS2&works&coordinaon:& 3rd&Mee3ng& Jamie&Boyd& 6/6/2019 1 Progress&on&afew&unrelated&areas&reported&(relevantfor&different

Reminder  Safety  

•  Launch  Safety  Agreement  (LSA)  released  by  Marco  Andreini  (FASER  HSE  contact)  – EDMS  link  from  AOB  – Long  list  of  safety  documenta3on  needed,  please  make  sure  relevant  documenta3on  is  produced  

•  Expect  relevant  teams  to  produce  safety  documenta3on  for  their  works  –  If  you  have  ques3ons  please  check  with  HSE  (keep  me  in  the  loop)  

11  

Page 12: FASERLS2&works&coordinaon:& 3rd&Mee3ng& · 2019-07-17 · FASERLS2&works&coordinaon:& 3rd&Mee3ng& Jamie&Boyd& 6/6/2019 1 Progress&on&afew&unrelated&areas&reported&(relevantfor&different

Cost  so  far…  

•  Overview  of  the  costs  incurred  so  far:  

12  

Work   Cost  kCHF  

Lowering  cable  trays   3.4  

Passerelle   9.1  

Hoist  for  UJ12   27.1  

Moving  lights  in  UJ12   0.8  

Moving  cables/electronic  equipment  

1.5  

SAS   ?  

Total   42.8