WHITE MOUNTAIN APACHE TRIBE RURAL WATER SYSTEM Project Overview WHITE MOUNTAIN APACHE TRIBE WATER RIGHTS QUANTIFICATION ACT OF 2010 The Proposed Action is the outcome of the WMAT Water Rights Quantification Act of 2010 (Act) in which Congress directed Reclamation to plan, design, and construct the WMAT Rural Water System. The Act also provides for operation of the completed system by Reclamation for three years following construction, after which WMAT would own, operate and maintain the water system. PURPOSE AND NEED FOR THE PROPOSAL Since the early 2000s, the Whiteriver area has experienced water outages, declining water quality and a diminishing water source. The WMAT needs a dependable and sustainable water supply for the Fort Apache Indian Reservation. The Proposed Action would fulfill Reclamation’s statutory mandate under the WMAT Water Rights Quantification Act to plan, design, construct, operate, maintain, and replace the WMAT Rural Water System until it is transferred to the Tribe as provided in the Act. For the WMAT, the purpose of the Proposed Action is to provide a secure, safe and dependable, good-quality, fresh water supply for its communities and tribal members. PROJECT BENEFITS This project would replace a failing groundwater supply and ensure a long-term and reliable fresh water supply for the Tribe well into the future. The project could also provide multipurpose benefits, including commercial water supply, recreation, hydropower potential, limited flood control, irrigation, improved instream flows for riparian and aquatic habitat, and stream temperatures suitable for production of endangered Apache trout at the Alchesay National Fish Hatchery. An environmental impact statement (EIS) is now being prepared to assess the potential environmental effects of constructing the White Mountain Apache Rural Water System to divert, store, and distribute water from the North Fork of the White River for the use and benefit of the White Mountain Apache Tribe (WMAT or Tribe). The Proposed Action would include construction and operation of the WMAT Rural Water System, which includes a dam, storage reservoir, pumping plant, treatment facilities, and a distribution system that would provide water to communities located on the Fort Apache Indian Reservation, Arizona, including Whiteriver, Fort Apache, Canyon Day, Cedar Creek, Carrizo, and Cibecue. In accordance with the National Environmental Policy Act of 1969 (NEPA), the Bureau of Reclamation (Reclamation) is the lead federal agency, and the WMAT and the Bureau of Indian Affairs (BIA) are cooperating agencies. The Bureau of Reclamation is the National Environmental Policy Act (NEPA) lead agency because of its statutory requirement to implement the Proposed Action WHICH AGENCIES ARE INVOLVED IN THE EIS? Bureau of Indian Affairs is a NEPA cooperating agency because of its statutory responsibility regarding Indian Trust Assets WMAT is a NEPA cooperating agency because it is the statutory owner/beneficiary of this project Fort Apache Indian Reservation B l a c k Riv er W hit e R i ver S alt R i v e r Project Study Area Mexico Mexico San Carlos Indian Reservation Tohono Indian Reservation Navajo Indian Reservation Barry Goldwater Air Force Range Gila River Indian Reservation Ve r d e Theodore Roosevelt Reservoir San Carlos Reservoir Gila River 40 19 10 8 17 89 191 89 191 89 191 180 60 60 191 60 60 191 89 60 60 191 180 70 79 286 77 87 87 77 86 77 377 260 82 87 90 88 77 487 288 85 Arizona Utah Prescott Scottsdale Mesa Tucson Glendale Phoenix Tempe Flagstaff L i ttl e C o l o r a d o Riv e r Gi l a R i v e r S a n P ed r o Ri v e r Wilcox Lake FALL 2013

Upload: others

Post on 29-Jan-2021

3 views

Category:

Documents


0 download

TRANSCRIPT

  • WHITE MOUNTAIN APACHE TRIBE RURAL WATER SYSTEM Project Overview

    WHITE MOUNTAIN APACHE TRIBE WATER RIGHTS QUANTIFICATION ACT OF 2010 The Proposed Action is the outcome of the WMAT Water Rights Quantification Act of 2010 (Act) in which Congress directed Reclamation to plan, design, and construct the WMAT Rural Water System.

    The Act also provides for operation of the completed system by Reclamation for three years following construction, after which WMAT would own, operate and maintain the water system.

    PURPOSE AND NEED FOR THE PROPOSALSince the early 2000s, the Whiteriver area has experienced water outages, declining water quality and a diminishing water source. The WMAT needs a dependable and sustainable water supply for the Fort Apache Indian Reservation.

    The Proposed Action would fulfill Reclamation’s statutory mandate under the WMAT Water Rights Quantification Act to plan, design, construct, operate, maintain, and replace the WMAT Rural Water System until it is transferred to the Tribe as provided in the Act.

    For the WMAT, the purpose of the Proposed Action is to provide a secure, safe and dependable, good-quality, fresh water supply for its communities and tribal members.

    PROJECT BENEFITSThis project would replace a failing groundwater supply and ensure a long-term and reliable fresh water supply for the Tribe well into the future.

    The project could also provide multipurpose benefits, including commercial water supply, recreation, hydropower potential, limited flood control, irrigation, improved instream flows for riparian and aquatic habitat, and stream temperatures suitable for production of endangered Apache trout at the Alchesay National Fish Hatchery.

    An environmental impact statement (EIS) is now being prepared to assess the potential environmental effects of constructing the White Mountain Apache Rural Water System to divert, store, and distribute water from the North Fork of the White River for the use and benefit of the White Mountain Apache Tribe (WMAT or Tribe). The Proposed Action would include construction and operation of

    the WMAT Rural Water System, which includes a dam, storage reservoir, pumping plant, treatment facilities, and a distribution system that would provide water to communities located on the Fort Apache Indian Reservation, Arizona, including Whiteriver, Fort Apache, Canyon Day, Cedar Creek, Carrizo, and Cibecue.

    In accordance with the National Environmental Policy Act of 1969 (NEPA), the Bureau of Reclamation (Reclamation) is the lead federal agency, and the WMAT and the Bureau of Indian Affairs (BIA) are cooperating agencies.

    The Bureau of Reclamation is the National Environmental Policy Act (NEPA) lead agency

    because of its statutory requirement to implement the Proposed Action

    WHICH AGENCIES ARE INVOLVED IN THE EIS?

    Bureau of Indian Affairs is a NEPA cooperating agency because of its statutory responsibility

    regarding Indian Trust Assets

    WMAT is a NEPA cooperating agency because it is the statutory owner/beneficiary of this project

    Fort ApacheIndian Reservation

    Bla

    ck River

    Whi

    te R

    iver

    Salt R

    iver

    ProjectStudy Area

    M e x i c oM e x i c o

    Ne

    w M

    ex

    ico

    Ne

    w M

    ex

    ico

    San CarlosIndian Reservation

    TohonoIndian Reservation

    NavajoIndian Reservation

    Barry GoldwaterAir Force Range

    Gila RiverIndian Reservation

    Verde

    TheodoreRoosevelt Reservoir

    San CarlosReservoir

    GilaRiver

    40

    19

    10

    8

    17

    89

    191

    89

    191

    89

    191

    180

    60

    70

    60

    191

    60

    60

    191

    89

    60

    60

    191

    180

    70

    79

    286

    77

    87

    289

    87

    77

    92

    80

    86

    77

    377

    260

    82

    87

    90

    88

    77

    487

    288

    85

    Arizona

    Utah

    Prescott

    Scottsdale

    Mesa

    Tucson

    Glendale

    Phoenix Tempe

    Flagsta�Little Colo rado River

    Gila River

    San Pedro River Wilcox

    Lake

    FALL 2013

  • WHITE MOUNTAIN APACHE TRIBE RURAL WATER SYSTEM

    2

    Cibecue

    Carrizo

    Cedar Creek

    Canyon DayFort Apache

    East Fork

    Whiteriver

    North

    Fork W

    hite R

    iver

    Whit e R

    iver

    Salt River

    East For

    k White RiverLEGEND

    Sources: ESRI, Bing Imagery, USGSMorrison and Maierle, Inc.Carollo EngineersGannett Fleming, Inc.

    Proposed Miner Flat Reservoir

    Proposed Water Treatment Plant and Diversion

    Proposed Pipeline

    Fort Apache Indian Reservation BoundaryWhite River

    0 1 2 3 4Miles

    Proposed Pipeline

    Proposed Miner Flat Reservoir

    Proposed Miner Flat Dam

    Proposed Water Treatment Plant and Diversion

    Con�uence with Black River

    Black River

    08/12/13 S:\GRAPHICS-WORKING FILES\Apache_WMAT\Figures 032613

    DRAFT

    WMAT Rural Water System - Major Project Components

    Fort Apache Indian Reservation

    San Carlos Indian Reservation

    Fort Apache Indian Reservation

    Project Overview Map

  • WHITE MOUNTAIN APACHE TRIBE RURAL WATER SYSTEM

    THE DAM AND RESERVOIR• The proposed dam site is about 7.5 miles south of the

    intersection of Highway 260 and Indian Route 73, about 12 miles north of Whiteriver.

    • The proposed Miner Flat Dam, a roller compacted concrete dam, would be about 160 feet in height, and would have a crest length of 450 feet.

    • The reservoir created by the dam would have a surface area of about 160 acres at an elevation of about 6,062 feet, and a storage capacity of about 8,620 acre-feet.

    • The dam and reservoir would provide long-term stability and reliability in water diversions for the water distribution system. The dam would also release water back into the North Fork of the White River.

    • The dam site would have new access roads, associated facilities for operations and maintenance, and possible recreational facilities.

    DIVERSION/WATER INTAKE AND WATER TREATMENT PLANT (WTP)• The water treatment system is designed to treat 14.55 million

    gallons of water per day.

    • WTP options include expanding the existing plant, building a new plant, or a combination of the two. Expanding the existing WTP is currently the preferred alternative.

    • The expanded system would require a new raw-water intake from the North Fork of the White River at a site near the existing intake and pump station. Water would be conveyed in a 24-inch pipeline to the WTP.

    • Treated water would be delivered to storage tanks via a gravity or pressurized pipeline.

    • During the 4- to 5-month WTP construction phase, communities would continue to be served by the Miner Flat wells.

    Project Components

    What a Proposed Water System Would Look Like

    WATER DISTRIBUTION SYSTEM• The project would install a pipeline from the treated water storage site at the WTP to existing water distribution systems

    serving the communities of Whiteriver, Fort Apache, Canyon Day, Cedar Creek, Carrizo, and Cibecue.

    • The distribution system consists of 60 miles of new pipeline, storage tanks for each of the receiving communities, and pumping stations.

    • The pipeline alignment would mostly follow existing roadways (except between Carrizo Creek and Cibecue Ridge).

    reservoir

    Dam

    Community Storage

    Water Treatment Plant

    water diversion

    Community Distribution

    pipeline

    3

  • Environmental Impact Statement Timeline

    Federal Register Notice of Intent to Prepare EISSeptember 6, 2013

    EIS Scoping Period Sept 6, 2013 - Nov 12, 2013

    Preparation of Draft EISWinter 2014-Spring 2015

    Federal Register Notice of Availability of Draft EIS

    Summer 2015

    Draft EIS Public Comment Period

    Summer/Fall 2015

    Preparation of Final EISFall 2015-Spring 2016

    Federal Register Notice of Availability of Final EIS

    Summer 2016

    30-Day Final EIS Waiting PeriodSummer 2016

    Record of DecisionSummer 2016

    For more information, contact: Mr. John McGlothlen, Bureau of Reclamation, 6150 West Thunderbird Road, Glendale, AZ 85306-4001; e-mail: [email protected]