facility modifications and preparations (fmp)

20
4/25/11 G1100469-v3 1 Facility Modifications and Preparations (FMP) Technical Status Annual NSF Review of Advanced LIGO Project April 25 - 27, 2011 John Worden LHO

Upload: coby

Post on 05-Jan-2016

30 views

Category:

Documents


2 download

DESCRIPTION

Facility Modifications and Preparations (FMP). Technical Status Annual NSF Review of Advanced LIGO Project April 25 - 27, 2011. John Worden LHO. 1. FMP Functions. Prepare for assembly tasks (buildings, laboratories): $3M, WBS .2.1, .3, .5 Create spaces for use as clean assembly areas - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Facility Modifications and Preparations (FMP)

4/25/11

G1100469-v3 1

Facility Modifications and Preparations (FMP)

Technical StatusAnnual NSF Review of Advanced LIGO Project

April 25 - 27, 2011

John WordenLHO

Page 2: Facility Modifications and Preparations (FMP)

4/25/11

G1100469-v3

FMP Functions

Prepare for assembly tasks (buildings, laboratories): $3M, WBS .2.1, .3, .5

Create spaces for use as clean assembly areas

Procure large, soft-walled, clean rooms for assembly

Procure vacuum bake ovens, parts washers.

Create clean/bake & conditioned storage space

Purchase supplies for wrapping, palletizing, storing assembled components

Purchase additional material handling equipment, installation fixtures, optics lab supplies, clean room supplies, etc.

Store completed assemblies

Provide clean/bake service, support the assembly groups.

Design & Build Vacuum System Modifications $5.7M, WBS .4

Convert 2 km at Hanford Observatory to 4 km

Move HAM Chambers for Input Optics (IO) and Interferometer Sensing & Control (ISC) use

Supply new IO tubes (input and output mode cleaner tubes)

Prepare for installation tasks: $2.4M, WBS .1, .2.2, .2.3, .2.4

Stage completed assemblies, procure installation equipment

Does not include installation (INS WBS scope) or system/subsystem test/acceptance (PM/systems WBS scope)

2

Budget total for FMP ~$12M

DONE

Underway with GNB Corp.

Page 3: Facility Modifications and Preparations (FMP)

4/25/11

G1100469-v3 3

FMP Requirements

Parts processing and assembly performed in Class 100 clean room work spaces.

Processing includes either vacuum bake or air bake (for large plates) to remove Low-Volatile Residue (out-gassing)

Clean storage for parts and completed assemblies.

Track processing and storage of parts and assemblies.

New IO Tubes to meet LIGO vacuum requirements, new mid/end station spools for 2K-4K conversion.

Page 4: Facility Modifications and Preparations (FMP)

4/25/11

G1100469-v3

FMP Status

Work spaces completed and commissioned fall of 09.

Ongoing effort to support assembly activity – clean and bake, shipping/receiving, packaging, storing, hiring techs. This is a bigger effort than originally thought.

Procurement activity for IO Tubes/Vacuum System mods ––GNB – contract awarded in April 2010, first components undergoing vacuum bake April 2011 with shipment of Mid Station Spools by end of April.

4

Page 5: Facility Modifications and Preparations (FMP)

4/25/11

G1100469-v3

aLIGO Corner Station LHO

Page 6: Facility Modifications and Preparations (FMP)

4/25/11

G1100469-v3

aLIGO End Station LHO

Page 7: Facility Modifications and Preparations (FMP)

4/25/11

G1100469-v3

Assembly Space LHO

7

Page 8: Facility Modifications and Preparations (FMP)

4/25/11

G1100469-v3

Clean/Bake LHO

8

Page 9: Facility Modifications and Preparations (FMP)

4/25/11

G1100469-v3

LHO HEPI Pump Carts

9

Page 10: Facility Modifications and Preparations (FMP)

4/25/11

G1100469-v3

Assembly Space LLO

10

Page 11: Facility Modifications and Preparations (FMP)

4/25/11

G1100469-v3

Clean/Bake LLO

11

Page 12: Facility Modifications and Preparations (FMP)

4/25/11

G1100469-v3

LLO:

3 Vacuum Bake Ovens

1 large Air Bake Oven

LHO:

3 Vacuum Bake Ovens

1 large Air Bake Oven

Vacuum Bake Oven

Vacuum Prep Warehouse Drying Station

Clean Parts ready for HAM-ISI assembly

12

Clean & Bake

Page 13: Facility Modifications and Preparations (FMP)

4/25/11

G1100469-v3

FMP to do

Design & Build Vacuum System Modifications WBS .4

Convert 2 km at Hanford Observatory to 4 km

Move HAM Chambers for Input Optics (IO) and Interferometer Sensing & Control (ISC) use

Does not include installation (INS WBS scope)

Get RFP out on the street in Fall of 2009

Underway:

Procure H2 Electronics Building – Slab is in place, modular building delivery ~May 5 ($130K)

Procure Install Cleanrooms. – First delivery has arrived at LHO. ($384K)

Procure Cartridge Install Test Stands. – First unit complete April 28 ($296K)

Procure Cartridge Install Work Platforms. - In design and fab with vendor ($472K)

Remaining work:

HVAC required for H2 electronics building, H1 electronics, PSL Diode Room

Mezzanine for H1 electronics.

13

Fabrication underway.

Page 14: Facility Modifications and Preparations (FMP)

4/25/11

G1100469-v3

Mid Station Spool Washing

Page 15: Facility Modifications and Preparations (FMP)

4/25/11

G1100469-v3

MC Tube Rollups

Page 16: Facility Modifications and Preparations (FMP)

4/25/11

G1100469-v3

Cartridge Install Test Stand

Page 17: Facility Modifications and Preparations (FMP)

4/25/11

G1100469-v3

Work Platforms

Page 18: Facility Modifications and Preparations (FMP)

4/25/11

G1100469-v3

Install Cleanrooms

Page 19: Facility Modifications and Preparations (FMP)

4/25/11

G1100469-v3

Challenges, risks, and mitigations

Low technical risk

Maintaining Particulate Cleanliness

Handling the Simultaneous Assembly Tasks and Space Needs will be Challenging

Will need to fit “noisy” construction activities around operating IFO schedules.

Safety – assembly and on site transport of heavy components (8000 pounds for assembled BSC system). New laser safety issues – higher power in test labs.

Track and store many parts – will need some manpower and an inventory system to control incoming materials as well as completed components.

Small quantities of cleaning fluids to be stored and disposed of. Not new for us.

19

Page 20: Facility Modifications and Preparations (FMP)

4/25/11

G1100469-v3

FMP Near term activities

Take delivery of new Vacuum components and supervise the install.

Install modular building for H2 electronics.

Procure HVAC for H2 modular building, H1 and Laser Diode room.

20