example of project

6
ID Task Mode Task Name Duration Start Finish 1 Definição do Produto 1 mon Wed 29/04/15 Tue 26/05/15 2 Estudo Ambiental 3 wks Wed 27/05/15 Tue 16/06/15 3 Estudo de Processos de Fabrico 1 mon Wed 27/05/15 Tue 23/06/15 4 Estudo de Mercado 1 mon Wed 27/05/15 Tue 23/06/15 5 Estudo de Patentes 1 mon Wed 27/05/15 Tue 23/06/15 6 Estudo da Localização 1 mon Wed 24/06/15 Tue 21/07/15 7 Desenhar Fábrica 3 mons Wed 22/07/15 Tue 13/10/15 8 Procurar Investidor 5 mons Wed 14/10/15 Tue 01/03/16 9 Obter Licença Para Construção 2 mons Wed 02/03/16 Tue 26/04/16 10 Obter Licenças de Produção 4 mons Wed 02/03/16 Tue 21/06/16 11 Concurso Para Empreitada 2 mons Wed 27/04/16 Tue 21/06/16 12 Comprar Terreno 3 mons Wed 27/04/16 Tue 19/07/16 13 Assinar Contracto 1 mon Wed 20/07/16 Tue 16/08/16 14 Comprar Equipamentos/Máquinas 3 mons Wed 17/08/16 Tue 08/11/16 15 Preparação do Terreno 1 mon Wed 17/08/16 Tue 13/09/16 16 Iluminação 45 days Wed 17/08/16 Tue 18/10/16 17 Construir Lagoas 5 mons Wed 19/10/16 Tue 07/03/17 18 Construir Armazéns 3 mons Wed 19/10/16 Tue 10/01/17 19 Piping 2 mons Wed 19/10/16 Tue 13/12/16 20 Construir Escritório 2 mons Wed 19/10/16 Tue 13/12/16 22/03 12/04 03/05 24/05 14/06 05/07 26/07 16/08 06/09 01 April 21 May 11 July 01 Septem Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 1 Project: Project1.mpp Date: Wed 29/04/15

Upload: gaspartano

Post on 07-Nov-2015

212 views

Category:

Documents


0 download

DESCRIPTION

Gantt Project

TRANSCRIPT

  • ID Task Mode

    Task Name Duration Start Finish

    1 Definio do Produto 1 mon Wed 29/04/15Tue 26/05/152 Estudo Ambiental 3 wks Wed 27/05/15Tue 16/06/153 Estudo de Processos de

    Fabrico1 mon Wed

    27/05/15Tue 23/06/15

    4 Estudo de Mercado 1 mon Wed 27/05/15Tue 23/06/155 Estudo de Patentes 1 mon Wed 27/05/15Tue 23/06/156 Estudo da Localizao 1 mon Wed 24/06/15Tue 21/07/157 Desenhar Fbrica 3 mons Wed 22/07/15Tue 13/10/158 Procurar Investidor 5 mons Wed 14/10/15Tue 01/03/169 Obter Licena Para

    Construo2 mons Wed

    02/03/16Tue 26/04/16

    10 Obter Licenas de Produo

    4 mons Wed 02/03/16

    Tue 21/06/16

    11 Concurso Para Empreitada

    2 mons Wed 27/04/16

    Tue 21/06/16

    12 Comprar Terreno 3 mons Wed 27/04/16Tue 19/07/1613 Assinar Contracto 1 mon Wed 20/07/16Tue 16/08/1614 Comprar

    Equipamentos/Mquinas3 mons Wed

    17/08/16Tue 08/11/16

    15 Preparao do Terreno 1 mon Wed 17/08/16Tue 13/09/1616 Iluminao 45 days Wed 17/08/16Tue 18/10/1617 Construir Lagoas 5 mons Wed 19/10/16Tue 07/03/1718 Construir Armazns 3 mons Wed 19/10/16Tue 10/01/1719 Piping 2 mons Wed 19/10/16Tue 13/12/1620 Construir Escritrio 2 mons Wed 19/10/16Tue 13/12/16

    22/03 12/04 03/05 24/05 14/06 05/07 26/07 16/08 06/0911 February 01 April 21 May 11 July 01 September

    Task

    Split

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    Deadline

    Progress

    Page 1

    Project: Project1.mppDate: Wed 29/04/15

  • ID Task Mode

    Task Name Duration Start Finish

    21 Contratar Staff Escritrio 1 mon Wed 14/12/16Tue 10/01/1722 Contratar Engenheiros 2 mons Wed 14/12/16Tue 07/02/1723 Contratar Operrios 3 mons Wed 08/02/17Tue 02/05/1724 Montagem de

    Mquinas/Equipamentos2 mons Wed

    08/03/17Tue 02/05/17

    25 Rede Eltrica 1 mon Wed 03/05/17Tue 30/05/1726 Testes Piloto 4 mons Wed 31/05/17Tue 19/09/17

    22/03 12/04 03/05 24/05 14/06 05/07 26/07 16/08 06/0911 February 01 April 21 May 11 July 01 September

    Task

    Split

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    Deadline

    Progress

    Page 2

    Project: Project1.mppDate: Wed 29/04/15

  • 06/09 27/09 18/10 08/11 29/11 20/12 10/01 31/01 21/02 13/03 03/04 24/04 15/05 05/06 26/06 17/07 07/08 28/08 18/09 09/1001 September 21 October 11 December 01 February 21 March 11 May 01 July 21 August

    Task

    Split

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    Deadline

    Progress

    Page 3

    Project: Project1.mppDate: Wed 29/04/15

  • 06/09 27/09 18/10 08/11 29/11 20/12 10/01 31/01 21/02 13/03 03/04 24/04 15/05 05/06 26/06 17/07 07/08 28/08 18/09 09/1001 September 21 October 11 December 01 February 21 March 11 May 01 July 21 August

    Task

    Split

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    Deadline

    Progress

    Page 4

    Project: Project1.mppDate: Wed 29/04/15

  • 09/10 30/10 20/11 11/12 01/01 22/01 12/02 05/03 26/03 16/04 07/05 28/05 18/06 09/07 30/07 20/08 10/09 01/10 22/10 12/1121 August 11 October 01 December 21 January 11 March 01 May 21 June 11 August 01 October

    Task

    Split

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    Deadline

    Progress

    Page 5

    Project: Project1.mppDate: Wed 29/04/15

  • 09/10 30/10 20/11 11/12 01/01 22/01 12/02 05/03 26/03 16/04 07/05 28/05 18/06 09/07 30/07 20/08 10/09 01/10 22/10 12/1121 August 11 October 01 December 21 January 11 March 01 May 21 June 11 August 01 October

    Task

    Split

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    Deadline

    Progress

    Page 6

    Project: Project1.mppDate: Wed 29/04/15