EVM Home Page = http://acc.dau.mil/evm http://www.dcma.mil = “One Book” DAU POC: (703) 805-2851 (DSN 655) eMail Address: [email protected] Revised 24 Feb 2004 TERMINOLOGY NCC Negotiated Contract Cost Contract price less profit / fee(s) AUW Authorized Unpriced Work Work contractually approved, but not yet negotiated / definitized CBB Contract Budget Base Sum of NCC and AUW OTB Over Target Baseline Sum of CBB and recognized overrun TAB Total Allocated Budget Sum of all budgets for work on contract = NCC, CBB, or OTB BAC Budget At Completion Total budget for total contract thru any given level PMB Performance Measurement Baseline Contract time-phased budget plan MR Management Reserve Budget withheld by Ktr PM for unknowns / risk management UB Undistributed Budget Broadly defined activities not yet distributed to CAs CA Control Account Lowest CWBS element assigned to a single focal point to plan & control scope / schedule / budget WP Work Package Near-term, detail-planned activities within a CA PP Planning Package Far-term CA activities not yet defined into WPs BCWS Budgeted Cost for Work Scheduled Value of work planned to be accomplished = PLANNED VALUE BCWP Budgeted Cost for Work Performed Value of work accomplished = EARNED VALUE ACWP Actual Cost of Work Performed Cost of work accomplished = ACTUAL COST EAC Estimate At Completion Estimate of total cost for total contract thru any given level; may be generated by Ktr, PMO, DCMA, etc. = EAC Ktr / PMO / DCMA LRE Latest Revised Estimate Ktr’s EAC or EAC Ktr SLPP Summary Level Planning Package Far-term activities not yet defined into CAs TCPI To Complete Performance Index Efficiency needed from ‘time now’ to achieve an EAC EVM POLICY: EVMS = DFARS 252.234-7000; 252.234-7001; & C/SSR = DFARS 252.242-7005; 252.242-7006; ANSI/EIA-748-A Jan 2002 / Mar 2003; DoDI 5000.2, Table E3.T2; & Defense Acquisition Guidebook MANAGEMENT REQUIREMENTS : Select pair of Contract Clauses based on cost, risk, criticality: Management Reserve Work Packages Planning Packages OVERRUN AUW Control Accounts NCC Undistribu ted Budget OTB CBB TAB Profit / Fees PMB Summary Level Planning Packages Contract Price EVM Home Page = http://acc.dau.mil/evm http://www.dcma.mil = “One Book” DAU POC: (703) 805-2851 (DSN 655) eMail Address: [email protected] Revised Feb 2004 TERMINOLOGY NCC Negotiated Contract Cost Contract price less profit / fee(s) AUW Authorized Unpriced Work Work contractually approved, but not yet negotiated / definitized CBB Contract Budget Base Sum of NCC and AUW OTB Over Target Baseline Sum of CBB and recognized overrun TAB Total Allocated Budget Sum of all budgets for work on contract = NCC, CBB, or OTB BAC Budget At Completion Total budget for total contract thru any given level PMB Performance Measurement Baseline Contract time-phased budget plan MR Management Reserve Budget withheld by Ktr PM for unknowns / risk management UB Undistributed Budget Broadly defined activities not yet distributed to CAs CA Control Account Lowest CWBS element assigned to a single focal point to plan & control scope / schedule / budget WP Work Package Near-term, detail-planned activities within a CA PP Planning Package Far-term CA activities not yet defined into WPs BCWS Budgeted Cost for Work Scheduled Value of work planned to be accomplished = PLANNED VALUE BCWP Budgeted Cost for Work Performed Value of work accomplished = EARNED VALUE ACWP Actual Cost of Work Performed Cost of work accomplished = ACTUAL COST EAC Estimate At Completion Estimate of total cost for total contract thru any given level; may be generated by Ktr, PMO, DCMA, etc. = EAC Ktr / PMO / DCMA LRE Latest Revised Estimate Ktr’s EAC or EAC Ktr SLPP Summary Level Planning Package Far-term activities not yet defined into CAs TCPI To Complete Performance Index Efficiency needed from ‘time now’ to achieve an EAC EVM POLICY: EVMS = DFARS 252.234-7000; 252.234-7001; & C/SSR = DFARS 252.242-7005; 252.242-7006; ANSI/EIA-748-A Jan 2002 / Mar 2003; DoDI 5000.2, Table E3.T2; & Defense Acquisition Guidebook MANAGEMENT REQUIREMENTS : Select pair of Contract Clauses based on cost, risk, criticality: Management Reserve Work Packages Planning Packages OVERRUN AUW Control Accounts NCC Undistribu ted Budget OTB CBB TAB Profit / Fees PMB Summary Level Planning Packages Contract Price

Upload: shanon-dalton

Post on 16-Jan-2016

225 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: EVM Home Page =   = “One Book” DAU POC: (703) 805-2851 (DSN 655) eMail Address: EVM@dau.milEVM@dau.mil Revised

EVM Home Page = http://acc.dau.mil/evm

http://www.dcma.mil = “One Book”DAU POC: (703) 805-2851 (DSN 655)

eMail Address: [email protected] 24 Feb 2004

TERMINOLOGYNCC Negotiated Contract Cost Contract price less profit / fee(s)AUW Authorized Unpriced Work Work contractually approved, but not yet negotiated / definitizedCBB Contract Budget Base Sum of NCC and AUWOTB Over Target Baseline Sum of CBB and recognized overrun TAB Total Allocated Budget Sum of all budgets for work on contract = NCC, CBB, or OTB BAC Budget At Completion Total budget for total contract thru any given levelPMB Performance Measurement Baseline Contract time-phased budget planMR Management Reserve Budget withheld by Ktr PM for unknowns / risk managementUB Undistributed Budget Broadly defined activities not yet distributed to CAs CA Control Account Lowest CWBS element assigned to a single focal point to plan & control

scope / schedule / budgetWP Work Package Near-term, detail-planned activities within a CA PP Planning Package Far-term CA activities not yet defined into WPsBCWS Budgeted Cost for Work Scheduled Value of work planned to be accomplished = PLANNED VALUEBCWP Budgeted Cost for Work Performed Value of work accomplished = EARNED VALUEACWP Actual Cost of Work Performed Cost of work accomplished = ACTUAL COSTEAC Estimate At Completion Estimate of total cost for total contract thru any given level;

may be generated by Ktr, PMO, DCMA, etc. = EACKtr / PMO / DCMA

LRE Latest Revised Estimate Ktr’s EAC or EACKtr

SLPP Summary Level Planning Package Far-term activities not yet defined into CAs TCPI To Complete Performance Index Efficiency needed from ‘time now’ to achieve an EAC

EVM POLICY: EVMS = DFARS 252.234-7000; 252.234-7001; & C/SSR = DFARS 252.242-7005; 252.242-7006; ANSI/EIA-748-A Jan 2002 / Mar 2003; DoDI 5000.2, Table E3.T2; & Defense Acquisition

Guidebook

MANAGEMENT REQUIREMENTS: Select pair of Contract Clauses based on cost, risk, criticality:EVMS EIA-748 Management System Validated as Consistent with EIA-748 Standard at detailed level

Non-FFP contracts / agreements for R&D > $73M; & Proc or O&M > $315M (CY00$)Cost/Schedule Status Report (C/SSR) Management System not required to meet EIA-748 Standard;

Non-FFP contracts / agreements > $6.3M (CY00$) & > 12 months duration Integrated Baseline Review (IBR) Mandatory for both EVMS & C/SSR within 6 months of Contract Award

REPORT REQUIREMENTS: Tailor Data Requirements via CDRL, Select One:Cost Performance Report = DI-MGMT-81466 = Formats 1-5 (WBS, Organization, Baseline, Staffing, & Explanations)

CPR is Mandatory for EVMS EIA-748 contracts & optional for C/SSR contracts Cost/Schedule Status Report = DI-MGMT-81467 = 2 Formats (WBS & Explanations) or ‘Tailored’ CPR

Management Reserve

Work Packages Planning Packages

OVERRUN AUW

Control Accounts

NCC

UndistributedBudget

OTB CBB

TAB Profit / Fees

PMB

Summary Level Planning Packages

Contract Price

EVM Home Page = http://acc.dau.mil/evm http://www.dcma.mil = “One Book”DAU POC: (703) 805-2851 (DSN 655)

eMail Address: [email protected] Feb 2004

TERMINOLOGYNCC Negotiated Contract Cost Contract price less profit / fee(s)AUW Authorized Unpriced Work Work contractually approved, but not yet negotiated / definitizedCBB Contract Budget Base Sum of NCC and AUWOTB Over Target Baseline Sum of CBB and recognized overrun TAB Total Allocated Budget Sum of all budgets for work on contract = NCC, CBB, or OTB BAC Budget At Completion Total budget for total contract thru any given levelPMB Performance Measurement Baseline Contract time-phased budget planMR Management Reserve Budget withheld by Ktr PM for unknowns / risk managementUB Undistributed Budget Broadly defined activities not yet distributed to CAs CA Control Account Lowest CWBS element assigned to a single focal point to plan & control

scope / schedule / budgetWP Work Package Near-term, detail-planned activities within a CA PP Planning Package Far-term CA activities not yet defined into WPsBCWS Budgeted Cost for Work Scheduled Value of work planned to be accomplished = PLANNED VALUEBCWP Budgeted Cost for Work Performed Value of work accomplished = EARNED VALUEACWP Actual Cost of Work Performed Cost of work accomplished = ACTUAL COSTEAC Estimate At Completion Estimate of total cost for total contract thru any given level;

may be generated by Ktr, PMO, DCMA, etc. = EACKtr / PMO / DCMA

LRE Latest Revised Estimate Ktr’s EAC or EACKtr

SLPP Summary Level Planning Package Far-term activities not yet defined into CAs TCPI To Complete Performance Index Efficiency needed from ‘time now’ to achieve an EAC

EVM POLICY: EVMS = DFARS 252.234-7000; 252.234-7001; & C/SSR = DFARS 252.242-7005; 252.242-7006; ANSI/EIA-748-A Jan 2002 / Mar 2003; DoDI 5000.2, Table E3.T2; & Defense Acquisition

Guidebook

MANAGEMENT REQUIREMENTS: Select pair of Contract Clauses based on cost, risk, criticality:EVMS EIA-748 Management System Validated as Consistent with EIA-748 Standard at detailed level

Non-FFP contracts / agreements for R&D > $73M; & Proc or O&M > $315M (CY00$)Cost/Schedule Status Report (C/SSR) Management System not required to meet EIA-748 Standard;

Non-FFP contracts / agreements > $6.3M (CY00$) & > 12 months duration Integrated Baseline Review (IBR) Mandatory for both EVMS & C/SSR within 6 months of Contract Award

REPORT REQUIREMENTS: Tailor Data Requirements via CDRL, Select One:Cost Performance Report = DI-MGMT-81466 = Formats 1-5 (WBS, Organization, Baseline, Staffing, & Explanations)

CPR is Mandatory for EVMS EIA-748 contracts & optional for C/SSR contracts Cost/Schedule Status Report = DI-MGMT-81467 = 2 Formats (WBS & Explanations) or ‘Tailored’ CPR

Management Reserve

Work Packages Planning Packages

OVERRUN AUW

Control Accounts

NCC

UndistributedBudget

OTB CBB

TAB Profit / Fees

PMB

Summary Level Planning Packages

Contract Price

Page 2: EVM Home Page =   = “One Book” DAU POC: (703) 805-2851 (DSN 655) eMail Address: EVM@dau.milEVM@dau.mil Revised

Earned Value Management‘‘Gold Card’Gold Card’

Defense Acquisition University

VARIANCES Favorable is Positive, Unfavorable is Negative

Cost Variance CV = BCWP – ACWP CV % = (CV / BCWP) *100

Schedule Variance SV = BCWP – BCWS SV % = (SV / BCWS) * 100

Variance at Completion VAC = BAC – EAC

PERFORMANCE INDICES Favorable is > 1.0, Unfavorable is < 1.0Cost Efficiency CPI = BCWP / ACWPSchedule Efficiency SPI = BCWP / BCWS

OVERALL STATUS

% Schedule = (BCWSCUM / BAC) * 100

% Complete = (BCWPCUM / BAC) * 100

% Spent = (ACWPCUM / BAC) * 100

ESTIMATE AT COMPLETION #

EAC = Actuals to Date + [(Remaining Work) / (Efficiency Factor)]EACCPI = ACWPCUM + [(BAC – BCWPCUM) / CPICUM ] = BAC / CPICUM

EACComposite = ACWPCUM + [(BAC – BCWPCUM) / (CPICUM * SPICUM)]

TO COMPLETE PERFORMANCE INDEX (TCPI) #

TCPIEAC = Work Remaining / Cost Remaining = (BAC – BCWPCUM) / (EAC – ACWPCUM)

# To Determine Either TCPI or EAC; You May Replace BAC with TAB

Management Reserve

Cost Variance

Schedule Variance

ACWP

BCWP

BCWS

$

EAC

TimeNow

Completion Date

PMB

TAB

BAC

time

Earned Value Management‘‘Gold Card’Gold Card’

Defense Acquisition University

VARIANCES Favorable is Positive, Unfavorable is Negative

Cost Variance CV = BCWP – ACWP CV % = (CV / BCWP) *100

Schedule Variance SV = BCWP – BCWS SV % = (SV / BCWS) * 100

Variance at Completion VAC = BAC – EAC

PERFORMANCE INDICES Favorable is > 1.0, Unfavorable is < 1.0Cost Efficiency CPI = BCWP / ACWPSchedule Efficiency SPI = BCWP / BCWS

OVERALL STATUS

% Schedule = (BCWSCUM / BAC) * 100

% Complete = (BCWPCUM / BAC) * 100

% Spent = (ACWPCUM / BAC) * 100

ESTIMATE AT COMPLETION #

EAC = Actuals to Date + [(Remaining Work) / (Efficiency Factor)]EACCPI = ACWPCUM + [(BAC – BCWPCUM) / CPICUM ] = BAC / CPICUM

EACComposite = ACWPCUM + [(BAC – BCWPCUM) / (CPICUM * SPICUM)]

TO COMPLETE PERFORMANCE INDEX (TCPI) #

TCPIEAC = Work Remaining / Cost Remaining = (BAC – BCWPCUM) / (EAC – ACWPCUM)

# To Determine Either TCPI or EAC; You May Replace BAC with TAB

Management Reserve

Cost Variance

Schedule Variance

ACWP

BCWP

BCWS

$

EAC

TimeNow

Completion Date

PMB

TAB

BAC

time