TERMINOLOGYNCC Negotiated Contract Cost Contract price less profit / fee(s)AUW Authorized Unpriced Work Work contractually approved, but not yet negotiated / definitizedCBB Contract Budget Base Sum of NCC and AUWOTB Over Target Baseline Sum of CBB and recognized overrun TAB Total Allocated Budget Sum of all budgets for work on contract = NCC, CBB, or OTB BAC Budget At Completion Total budget for total contract thru any given levelPMB Performance Measurement Baseline Contract time-phased budget planMR Management Reserve Budget withheld by Ktr PM for unknowns / risk managementUB Undistributed Budget Broadly defined activities not yet distributed to CAs CA Control Account Lowest CWBS element assigned to a single focal point to plan & control
scope / schedule / budgetWP Work Package Near-term, detail-planned activities within a CA PP Planning Package Far-term CA activities not yet defined into WPsBCWS Budgeted Cost for Work Scheduled Value of work planned to be accomplished = PLANNED VALUEBCWP Budgeted Cost for Work Performed Value of work accomplished = EARNED VALUEACWP Actual Cost of Work Performed Cost of work accomplished = ACTUAL COSTEAC Estimate At Completion Estimate of total cost for total contract thru any given level;
may be generated by Ktr, PMO, DCMA, etc. = EACKtr / PMO / DCMA
LRE Latest Revised Estimate Ktr’s EAC or EACKtr
SLPP Summary Level Planning Package Far-term activities not yet defined into CAs TCPI To Complete Performance Index Efficiency needed from ‘time now’ to achieve an EAC
EVM POLICY: EVMS = DFARS 252.234-7000; 252.234-7001; & C/SSR = DFARS 252.242-7005; 252.242-7006; ANSI/EIA-748-A Jan 2002 / Mar 2003; DoDI 5000.2, Table E3.T2; & Defense Acquisition
Guidebook
MANAGEMENT REQUIREMENTS: Select pair of Contract Clauses based on cost, risk, criticality:EVMS EIA-748 Management System Validated as Consistent with EIA-748 Standard at detailed level
Non-FFP contracts / agreements for R&D > $73M; & Proc or O&M > $315M (CY00$)Cost/Schedule Status Report (C/SSR) Management System not required to meet EIA-748 Standard;
Non-FFP contracts / agreements > $6.3M (CY00$) & > 12 months duration Integrated Baseline Review (IBR) Mandatory for both EVMS & C/SSR within 6 months of Contract Award
REPORT REQUIREMENTS: Tailor Data Requirements via CDRL, Select One:Cost Performance Report = DI-MGMT-81466 = Formats 1-5 (WBS, Organization, Baseline, Staffing, & Explanations)
CPR is Mandatory for EVMS EIA-748 contracts & optional for C/SSR contracts Cost/Schedule Status Report = DI-MGMT-81467 = 2 Formats (WBS & Explanations) or ‘Tailored’ CPR
Management Reserve
Work Packages Planning Packages
OVERRUN AUW
Control Accounts
NCC
UndistributedBudget
OTB CBB
TAB Profit / Fees
PMB
Summary Level Planning Packages
Contract Price
EVM Home Page = http://acc.dau.mil/evm http://www.dcma.mil = “One Book”DAU POC: (703) 805-2851 (DSN 655)
eMail Address: [email protected] Feb 2004
TERMINOLOGYNCC Negotiated Contract Cost Contract price less profit / fee(s)AUW Authorized Unpriced Work Work contractually approved, but not yet negotiated / definitizedCBB Contract Budget Base Sum of NCC and AUWOTB Over Target Baseline Sum of CBB and recognized overrun TAB Total Allocated Budget Sum of all budgets for work on contract = NCC, CBB, or OTB BAC Budget At Completion Total budget for total contract thru any given levelPMB Performance Measurement Baseline Contract time-phased budget planMR Management Reserve Budget withheld by Ktr PM for unknowns / risk managementUB Undistributed Budget Broadly defined activities not yet distributed to CAs CA Control Account Lowest CWBS element assigned to a single focal point to plan & control
scope / schedule / budgetWP Work Package Near-term, detail-planned activities within a CA PP Planning Package Far-term CA activities not yet defined into WPsBCWS Budgeted Cost for Work Scheduled Value of work planned to be accomplished = PLANNED VALUEBCWP Budgeted Cost for Work Performed Value of work accomplished = EARNED VALUEACWP Actual Cost of Work Performed Cost of work accomplished = ACTUAL COSTEAC Estimate At Completion Estimate of total cost for total contract thru any given level;
may be generated by Ktr, PMO, DCMA, etc. = EACKtr / PMO / DCMA
LRE Latest Revised Estimate Ktr’s EAC or EACKtr
SLPP Summary Level Planning Package Far-term activities not yet defined into CAs TCPI To Complete Performance Index Efficiency needed from ‘time now’ to achieve an EAC
EVM POLICY: EVMS = DFARS 252.234-7000; 252.234-7001; & C/SSR = DFARS 252.242-7005; 252.242-7006; ANSI/EIA-748-A Jan 2002 / Mar 2003; DoDI 5000.2, Table E3.T2; & Defense Acquisition
Guidebook
MANAGEMENT REQUIREMENTS: Select pair of Contract Clauses based on cost, risk, criticality:EVMS EIA-748 Management System Validated as Consistent with EIA-748 Standard at detailed level
Non-FFP contracts / agreements for R&D > $73M; & Proc or O&M > $315M (CY00$)Cost/Schedule Status Report (C/SSR) Management System not required to meet EIA-748 Standard;
Non-FFP contracts / agreements > $6.3M (CY00$) & > 12 months duration Integrated Baseline Review (IBR) Mandatory for both EVMS & C/SSR within 6 months of Contract Award
REPORT REQUIREMENTS: Tailor Data Requirements via CDRL, Select One:Cost Performance Report = DI-MGMT-81466 = Formats 1-5 (WBS, Organization, Baseline, Staffing, & Explanations)
CPR is Mandatory for EVMS EIA-748 contracts & optional for C/SSR contracts Cost/Schedule Status Report = DI-MGMT-81467 = 2 Formats (WBS & Explanations) or ‘Tailored’ CPR
Management Reserve
Work Packages Planning Packages
OVERRUN AUW
Control Accounts
NCC
UndistributedBudget
OTB CBB
TAB Profit / Fees
PMB
Summary Level Planning Packages
Contract Price
Earned Value Management‘‘Gold Card’Gold Card’
Defense Acquisition University
VARIANCES Favorable is Positive, Unfavorable is Negative
Cost Variance CV = BCWP – ACWP CV % = (CV / BCWP) *100
Schedule Variance SV = BCWP – BCWS SV % = (SV / BCWS) * 100
Variance at Completion VAC = BAC – EAC
PERFORMANCE INDICES Favorable is > 1.0, Unfavorable is < 1.0Cost Efficiency CPI = BCWP / ACWPSchedule Efficiency SPI = BCWP / BCWS
OVERALL STATUS
% Schedule = (BCWSCUM / BAC) * 100
% Complete = (BCWPCUM / BAC) * 100
% Spent = (ACWPCUM / BAC) * 100
ESTIMATE AT COMPLETION #
EAC = Actuals to Date + [(Remaining Work) / (Efficiency Factor)]EACCPI = ACWPCUM + [(BAC – BCWPCUM) / CPICUM ] = BAC / CPICUM
EACComposite = ACWPCUM + [(BAC – BCWPCUM) / (CPICUM * SPICUM)]
TO COMPLETE PERFORMANCE INDEX (TCPI) #
TCPIEAC = Work Remaining / Cost Remaining = (BAC – BCWPCUM) / (EAC – ACWPCUM)
# To Determine Either TCPI or EAC; You May Replace BAC with TAB
Management Reserve
Cost Variance
Schedule Variance
ACWP
BCWP
BCWS
$
EAC
TimeNow
Completion Date
PMB
TAB
BAC
time
Earned Value Management‘‘Gold Card’Gold Card’
Defense Acquisition University
VARIANCES Favorable is Positive, Unfavorable is Negative
Cost Variance CV = BCWP – ACWP CV % = (CV / BCWP) *100
Schedule Variance SV = BCWP – BCWS SV % = (SV / BCWS) * 100
Variance at Completion VAC = BAC – EAC
PERFORMANCE INDICES Favorable is > 1.0, Unfavorable is < 1.0Cost Efficiency CPI = BCWP / ACWPSchedule Efficiency SPI = BCWP / BCWS
OVERALL STATUS
% Schedule = (BCWSCUM / BAC) * 100
% Complete = (BCWPCUM / BAC) * 100
% Spent = (ACWPCUM / BAC) * 100
ESTIMATE AT COMPLETION #
EAC = Actuals to Date + [(Remaining Work) / (Efficiency Factor)]EACCPI = ACWPCUM + [(BAC – BCWPCUM) / CPICUM ] = BAC / CPICUM
EACComposite = ACWPCUM + [(BAC – BCWPCUM) / (CPICUM * SPICUM)]
TO COMPLETE PERFORMANCE INDEX (TCPI) #
TCPIEAC = Work Remaining / Cost Remaining = (BAC – BCWPCUM) / (EAC – ACWPCUM)
# To Determine Either TCPI or EAC; You May Replace BAC with TAB
Management Reserve
Cost Variance
Schedule Variance
ACWP
BCWP
BCWS
$
EAC
TimeNow
Completion Date
PMB
TAB
BAC
time