ERCOT Update to ROS NERC TPL-001-004 Sept 4, 2014. NERC TPL-001-004 implementation Jan 1, 2015. NERC TPL changes impacting Transmission Planners and Planning Coordinator (ERCOT) Implementation date Jan 1, 2015 - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: ERCOT Update to ROS NERC TPL-001-004 Sept 4, 2014](https://reader030.vdocuments.site/reader030/viewer/2022032708/56812ee0550346895d947ccb/html5/thumbnails/1.jpg)
ERCOT Update to ROSNERC TPL-001-004
Sept 4, 2014
![Page 2: ERCOT Update to ROS NERC TPL-001-004 Sept 4, 2014](https://reader030.vdocuments.site/reader030/viewer/2022032708/56812ee0550346895d947ccb/html5/thumbnails/2.jpg)
2
• NERC TPL changes impacting Transmission Planners and Planning Coordinator (ERCOT)
– Implementation date Jan 1, 2015– In general the changes modify Planning Models, Steady-State Planning Analysis,
Dynamic Planning Analysis, as well as introducing Short-Circuit Analysis, extended Outage impacts, and Spare equipment analysis
• Numerous meetings conducted over the summer among TP’s and ERCOT to determine scope, interaction, and impacts of the NERC requirements
• Consensus that most of the modeling and analysis changes should be made with modifications to existing guidelines for the SSWG, DWG, and SPWG
– Agreement that most modeling and analysis are already being performed and only incremental revisions are needed
– Some revisions will need to be promoted to a higher stakeholder level and included in Planning Guide revision
• As the Planning Coordinator, ERCOT requests support of ROS to work with the individual working groups on the necessary coordination of guide revisions to achieve readiness in the November 2014 timeframe.
– ERCOT will provide monthly updates of progress and issues to ROS though the end of the year.
NERC TPL-001-004 implementation Jan 1, 2015