equipment design designed by eman a. khajah. outline design of heater. design of stripper
TRANSCRIPT
Equipment DesignDesigned by Eman A. Khajah
Outline• Design of Heater.• Design of Stripper.
Heater Design• Construction of Shell and Tube Heat Exchanger.
Objective• To heat up the streams before entering the
reactors.• To heat up the propane stream before
recycle it back to the feed.
Assumptions
• Counter current flow heat exchanger to provide more effective heat transfer.
• Assume the value of the overall heat transfer coefficient.
• Assume the outer, the inner diameter and the length of the tube on both the Shell and tube sides.
Design Procedure
• Calculate the duty or heat load.
Where,
m: mass flow rate, kg/hr
Cp: specific heat, kJ/kg°C
∆T: temperature difference, °C• Collect physical properties.
coldphotp TmCTmCQ
• Assume U : overall heat transfer coefficient, W/m2oC.• Calculate heat transfer area required.
Where,
Tm = Ft Tlm.
∆Tlm : log mean temperature difference.
T1 : inlet shell side fluid temperature.
T2 : outlet shell side temperature fluid temperature.
t1 : inlet tube side fluid temperature .
t2 : outlet tube side fluid temperature.
mo TU
QA
12
21
1221
lntT
tTtTtT
Tlm
• Choose tube size and material, then calculate number of tubes required.
• Calculate Ds : shell diameter.
• Estimate tube side heat transfer coefficient hi, W/m2°C.
• Choose Lb : baffle spacing.
• Calculate area of cross flow.
• Estimate shell side heat transfer coefficient ho, W/m2°C.
• Calculate U overall heat transfer coefficient using:
Where,Uo: overall coefficient based on outside area of the tube (W/m2oC).ho: outside fluid film coefficient (W/m2oC).hi : inside fluid film coefficient (W/m2oC ).hod : outside dirt coefficient (fouling factor) (W/m2oC).hid : inside dirt coefficient (fouling factor) (W/m2oC).kw : thermal conductivity of the wall material (W/m2oC ).di : tube inside diameter.do: tube outside diameter.
SdSw
i
oo
i
o
idio hhk
d
dd
d
d
hhU
11
2
ln111
• Estimate tube and shell side pressure drop.• Calculate shell thickness.
Where,P: design pressure, psia R: inside radius of shell, inchS: maximum allowable stress value, psiaE: the joint efficiency C: corrosion allowance• Select a material of construction and insulation.• Calculate cost.
CPSE
PRt
6.0
Results Equipment Heater E-102
Type Shell and tube heat exchanger
Material of construction Carbon Steel
Qtotal (kW) 11943.699
U(W/m² °C) 30
Inlet temperture, Shell side °C 327
Oultlet, Shell side °C 550
Inlet temperature, Tube side °C 600
Outlet temperature, Tube side °C 100
Number of tubes 5593
Shell diameter, m 1.56
LMTD, °C 155.6
Heat exchanger area, m² 2558.21
Insulation Glass wool
Cost, $ 77,300 $
Stripper Design
• Construction of stripper.
Objective• To separate CO2 from water and get a
stream of pure CO2.
Assumptions• Tray spacing= 0.75.• Efficiency= 75%.• Percent of flooding at maximum flow rate=85%.• Percent of downcomer area of total area=12%.• Percent of hole area of active area=10%.• Weir height=50 mm.• Hole diameter=5 mm.• Plate thickness=5 mm.
Design Procedure• Collect, or estimate, the system physical properties.• Calculate liquid vapor flow rate.
Where:
FLV= liquid vapor flow rate.
L= liquid flow rate.
V= vapor flow rate.
5.0
L
vLV V
LF
• Calculate the flooding velocity
Where:Uf= flooding velocity.K1= constant.
• Calculate the actual velocity.
Where:Uv= actual velocity.
5.0
1
)(
V
VLf KU
fV UxFloodingPercentageU
• Calculate the maximum volumetric flow rate.
Where:
Vmax= maximum volumetric flow rate.
MwtV= vapor molecular weight.• Calculate the net area required.
• Calculate the diameter.
V
VMwtV
max
Vnet U
VA max
5.04
netAD
• Calculate the maximum volumetric flow rate.
• Calculate the column area.
• Calculate the net area.
• Calculate the active area.
• Calculate weir length.
L
LxMwtrateliquidvolumetric
max
2
4DAC
dCn AAA
dca AAA 2
Dlengthweir 75.0
• Calculate the actual minimum vapor velocity.
• Calculate the thickness.
Where:t= thickness.P= pressure.r= radius.S= working stress.Ej= efficiency of joints.CC= allowance for corrosion.
• Calculate the cost.
hA
ratevaporvelocityvaporactual
.min.min
Ci CxPSxEj
Pxrt
6.0
ResultsEquipment Stripper T-102
Type Continuous distillation column
Material of construction Carbon steel
Insulation Mineral wool
Operating temperature, °C 110
Operating pressure, atm 3
Height of beds 0.75
Diameter, m 3.17
Thickness, m 0.0127
Number of beds 10
Height, m 13.2
Cost, $ 353,933