epc-4 package status update september 16-09-2011
TRANSCRIPT
September 2011
Hydrocracker Package Hydrocracker Package
STATUS UPDATESTATUS UPDATE
Walid Abughander
OUTLINE
2
3
ORGANIZATION CHART
4
RSRC
Riyadh Refinery
Jizan Refine
ry
SATORPSASREF
Ras Tunura Refinery
SCOPE OVERVIEW
Riyadh Refinery
Jizan Refine
ry
SATORPSASREF
Ras Tunura Refinery
RSRC
• Substation and Process Interface Building
• Site Preparation & Development
• Automation & Communications Scope
5
SCOPE OVERVIEW
CDU
HCK
HGU
6
SCOPE OVERVIEW
Block Flow Diagram
7
SCOPE OVERVIEW
Fractionation Section
Off gasLPGLight NaphthaHeavy NaphthaDiesel
Recycle GasCompressor
AGO (CDU-110)LVGO (CDU-110)HVGO (CDU-110)HCGO (DCU-113)Blend
Reactor SectionTrain 1
HP, LP Separation
Train 2
HP, LP Separation
Train 1
Recycle GasCompressor
Reactor SectionTrain 2
454 °C 2,650 psig2,650 psig
8
CONTRACT VALUEPackage Cost:
SCHEDULE & PROGRESS STATUS
Q4Q3 Q1 Q2 Q4 Q1Q3 Q1 Q2 Q4Q3
Q4Q3 Q1 Q2 Q4 Q1Q3 Q1 Q2 Q4Q3
Q3Q2 Q4 Q1 Q3 Q4Q2 Q4 Q1 Q3Q2
PLANACTUAL
Award MC
Q1
Q2 Q3
9
ACHIEVEMENTS
• Closed 181 (94%) interface points out of 193
• Completed Primary Process HAZOP
• Completed Supplementary HAZOP for Compressors
• Finalized all equipment data sheets for vendors to start fabrication
• Completed 60% Design Review
• Started 60% 3-D Model Review
Engineering
44%
50%
10
11
ACHIEVEMENTS
• Placed all POs for Long Lead equipment
• Placed POs for all Static Equipments, Rotating Equipments, and Steel Structure
• Placed more than 35% of instrumentation PO’s
• Completed PO Placement of the 1st material takeoff for the bulk materials
Procurement
20%
19%
12
ACHIEVEMENTS • Completed Company main & satellite offices
• Completed pilling work (335 Piles Installed)
• Started fence and warehouse foundation of laydown area
• Started foundation work for the main piperack (Pouring ~ 1,115 m3 of concrete)
• Manpower Status:
Construction
2.0%
0.5%
287
13
PROGRESS PHOTOS
14
PACKAGE QUALITY INDEX
Project Quality Index (PQI) Behavior
90.70
15
SIX MONTHS LOOK AHEAD
Start 2nd Material Take-Off
Start Supplementary HAZOP Review (Heaters and other Packages)
Complete all POs for Field Instruments
Complete all POs for Substation Equipment
Start Grounding Installation
OctoberOctober
NovembeNovemberr
December December
16
SIX MONTHS LOOK AHEAD
Complete PDR for PAS
Issue P&IDs for Construction
Deliver 1st Heavy Wall Pipe to Site
Complete 90% 3D Model Review
Deliver Reciprocating Compressors to Site
Start Main Steel Structure Erection
Start Substation Building Foundation
Complete 90% Design ReviewJanuaryJanuary
FebruaryFebruary
MarchMarch
17
• Adopting 2007 ASME Code for designing the reactors
15% less material will be used in the shell and head of the reactors
Additional cost savings may be realized for transportation, foundation, and
erection
No impact on the mechanical integrity of the two reactors
ITEM OF INTEREST
18
• Modifying the ADS design to meet
2010-CLG Standard Requirements
Provides more reliable performance by
minimizing the potential of spurious trips.
Implemented to all newly design hydrocracker units such as Luberef and Jizan
Reduce input points to ADS from 572 to 152 points
ITEM OF INTEREST
TI
TI
TI
TI
TI
TI
TI
TI
TI
TI
TI
TI
TI
TI
TI
TI
TI
TI
TI
TI
TI
TI
TI60 Points (Skin TIs)
132 Points (Inlet/Outlet)
TI
TI
Hydrotreating Bed
Hydrotreating Bed
Hydrotreating Bed
Hydrocracking Bed
Hydrocracking Bed
Hydrocracking Bed
1 Point (Outlet Piping)
TI
1 Point (Outlet Nozzle Skin)
ADS36 Points (Inlet/Outlet)
0 Point (Skin TIs)
1 Point Recycle
Gas Flow
Total = 38 Points/reactor
Total = 194 Points
19