environmental issues in federal permitting for energy projects

26
Environmental Issues in Federal Permitting for Energy Projects Winston & Strawn LLP July 14, 2015

Upload: winston-strawn-llp

Post on 23-Jan-2018

219 views

Category:

Law


2 download

TRANSCRIPT

Page 1: Environmental Issues in Federal Permitting for Energy Projects

Environmental Issues in Federal Permitting for Energy Projects

Winston & Strawn LLP July 14, 2015

Page 2: Environmental Issues in Federal Permitting for Energy Projects

Today’s eLunch Presenters

Tyson Smith Energy

San Francisco

[email protected]

Stephanie Sebor Environmental

Chicago

[email protected]

Eleni Kouimelis Environmental

Chicago

[email protected]

2

Page 3: Environmental Issues in Federal Permitting for Energy Projects

Agenda

• Brief Introduction • Emerging Issues in Energy Project Development

• Rethinking Transmission under NEPA • Mitigating ESA Listing Decision Uncertainty

• Environmental Regulatory Developments • Recent Amendments to Incidental Take Statement Regulations • Migratory Bird Treaty Act Incidental Take Permitting Program • Waters of the United States Rule • Update on EPA’s Greenhouse Gas Rulemakings

• CEQ Issuance of NEPA Guidance Documents

3

Page 4: Environmental Issues in Federal Permitting for Energy Projects

Emerging Issues in Energy Project Development

Page 5: Environmental Issues in Federal Permitting for Energy Projects

Energy Project Development

5

Project Approvals

Clean Water

Act

Clean Air Act

NEPA

ESA

NHPA

State CPCN

Project Approvers

EPA/State EPA

Corps of Engin’rs

Fed. Land Agencies

Other Fed.

Agencies

ISOs

State Utility Commission

Page 6: Environmental Issues in Federal Permitting for Energy Projects

What Was Old Is New Again… • Transmission corridor development and NEPA was a “hot topic” in

the 1970s and 1980s • Coextensive with period of large power generation station construction • Along with highway construction, developed a large body of law

addressing “connected actions” and “segmentation” • Involved applicants for permits that were responsible for siting,

constructing, and operating the transmission lines and the generation facility

• Significant changes in electricity system since that time • De-regulation and the rise of merchant generation • Separation of generation and transmission systems • Major advances in renewable energy development

• Result: Caselaw does not necessarily match current reality

6

Page 7: Environmental Issues in Federal Permitting for Energy Projects

Fermi 3 Project • DTE’s proposed 1600 MW new nuclear project in Michigan at site

of existing Fermi 2 reactor • New offsite transmission lines would be owned and operated by

ITCTransmission • DTE has no control over the siting, design, or operation of offsite

transmission lines • Final transmission route determined in a Certificate of Public

Convenience and Necessity from the Michigan Public Service Commission

• Nuclear Regulatory Commission’s FEIS • Explains that ITCTransmission has not formally announced a route for

a new offsite transmission line serving Fermi 3 • Relied on publicly-available information and reasonable expectations

regarding configurations that ITCTransmission would use based on standard industry practice

7

Page 8: Environmental Issues in Federal Permitting for Energy Projects

• Under 40 CFR 1508.25, connected actions: • Automatically trigger other

actions requiring EIS • Cannot or will not proceed

unless other actions are taken previously or simultaneously

• Are interdependent parts of a larger action and depend on the larger action for their justification

8

Application to New Paradigm

Page 9: Environmental Issues in Federal Permitting for Energy Projects

9

Application to New Paradigm

• Improper segmentation factors: • Whether there is a proposed

action; • Whether the actions have

independent utility; and • Whether there is sufficient federal

control and responsibility.

Page 10: Environmental Issues in Federal Permitting for Energy Projects

Effects of ESA Listing Decisions

• Federal permitting agency is not the same as the responsible agency under the ESA

• Scope and timing of ESA listing decisions may be uncertain • Geographic scope of affected species • Timing of final decisions

• Creates substantial licensing/permitting uncertainty • Agencies hesitant to give appearance of rushing permit decision

prior to listing decision • Permitting agency must coordinate with USFWS after listing decision • Delay adversely affects project developer

• Regulatory uncertainty (timing of project start)

• Economic impacts (financing, cost of construction)

10

Page 11: Environmental Issues in Federal Permitting for Energy Projects

Geographic Range

11

Page 12: Environmental Issues in Federal Permitting for Energy Projects

Timing of ESA Decisions

• Practical • Informal coordination with USFWS

to inform them of schedule issues

• Pre-staged internal assessments if species is listed

• Legal • If species not yet listed, then

consultation not required

• If “no effect,” then consultation not required • Timing of listing v. effective date

• Focus only on actions “authorized” by Federal agency

• Consider license/permit conditions

12

Red Knot

Proposed Listing as “Threatened” Sept. 13, 2013

Reopening Comment Period April 4, 2014

Reopening Comment Period May 14, 2014

Final Listing Decision (Target) Sept. 13, 2014

Final Listing Decision (Actual) Dec. 11, 2014

Northern Long-Eared Bat

Proposed Listing Oct. 2, 2013

Extension of Listing Decision June 30, 2014

Reopening Comment Period Nov. 18, 2014

Final Listing Decision (Actual) April 2, 2015

End of Comment Period on 4(d) Rule July 1, 2015

Greater Sage Grouse

Listing Warranted, but Precluded Mar. 5, 2010

Status Review Sept. 1, 2015

Page 13: Environmental Issues in Federal Permitting for Energy Projects

Environmental Regulatory Developments

Page 14: Environmental Issues in Federal Permitting for Energy Projects

• On May 1, 2015, FWS and National Marine Fisheries Services issued a final rule amending their incidental take statement regulations

• Two components: • The wildlife agencies codified the use of surrogates to express the

amount or extent of a “take” • The wildlife agencies also codified their authority not to provide an

ITS with a biological opinion for federal planning decisions that anticipate future harm • Rather, an ITS will be provided at the point when future activities that

could result in takings are authorized

Revisions to Incidental Take Statement Regulations

14

Page 15: Environmental Issues in Federal Permitting for Energy Projects

• On May, 26, 2015, the U.S. Fish and Wildlife Service (“FWS”) initiated NEPA review of a proposed program for authorizing the incidental take of migratory birds protected by the MBTA

• Possible approaches include: • General incidental take authorizations for some types of hazards

associated with particular industry sectors • Individual permits authorizing incidental take from particular projects

or activities • Memoranda of Understanding (“MOU”) with federal agencies • Voluntary guidance for industry sectors

• FWS is requesting public comment on whether it should develop a general incidental take permit for the wind energy industry • Public comments are due July 27, 2015

Migratory Bird Treaty Act (“MBTA”) Incidental Take Permit Program

15

Page 16: Environmental Issues in Federal Permitting for Energy Projects

• On May 26, 2015, EPA and the U.S. Army Corps of Engineers finalized a rule defining “waters of the United States” subject to the Clean Water Act • The rule was published in the Federal Register on June 29, 2015

• Rule attempts to address uncertainty regarding the scope of the Clean Water Act’s jurisdiction, which is limited to navigable waters, defined as the waters of the United States, including the territorial seas • “Waters of the United States” is not defined in the Clean Water Act • The Supreme Court has interpreted the term in several cases, most

recently in Rapanos v. United States in 2006, which did not result in a majority opinion

• The rule affects both the NPDES and Section 404 permitting programs

Waters of the United States Rule

16

Page 17: Environmental Issues in Federal Permitting for Energy Projects

• Rule establishes eight categories of jurisdictional waters: • Six of which are per se covered by the Clean Water Act:

• Traditional navigable waters • Interstate waters • Territorial seas • Impoundments of jurisdictional waters • Tributaries • Adjacent waters

• Two of which may be subject to the Clean Water Act after a case-specific significant nexus analysis: • Isolated waters (such as Prairie potholes) • “Other” waters

• Waters within the 100-year floodplain of a traditional navigable water, interstate water, or the territorial seas

• Waters that are within 4,000 feet of the ordinary high water mark of a water of the United States

Waters of the United States Rule

17

Page 18: Environmental Issues in Federal Permitting for Energy Projects

• Rule establishes exclusions for converted cropland, waste treatment systems, certain ditches, groundwater, erosional features, and certain stormwater control features.

• Rule has been criticized as an expansion of regulatory authority • Broad definition of tributary • Expansive significant nexus test

• Rule has also been criticized for failing to provide clarity regarding the scope of the Clean Water Act’s jurisdiction • Vague and complicated definitions will be difficult for regulators to

implement

• Rule has been attacked from various angles • Litigation brought by both industry and states

• Legislation – riders to appropriations bills and bills in both House and Senate

Waters of the United States Rule

18

Page 19: Environmental Issues in Federal Permitting for Energy Projects

• In 2014, EPA proposed three rules regulating GHG emissions from new, existing, and modified or reconstructed power plants under Section 111 of the Clean Air Act

• EPA is planning to finalize these rules this summer • First, EPA will issue its Section 111(b) rule for new power plants

• EPA sent the rule to OMB for review on May 7th

• Then, EPA will issue the final Clean Power Plan for existing sources • EPA sent the rule to OMB for review on June 1st

• At the same time, EPA will propose a federal plan for meeting the Clean Power Plan goals

• Last, EPA will issue its final Carbon Pollution Standards for Modified and Reconstructed Power Plants • EPA sent the rule to OMB for review on June 23rd

EPA Greenhouse Gas Regulatory Update

19

Page 20: Environmental Issues in Federal Permitting for Energy Projects

• Last year, the Supreme Court invalidated the Tailoring Rule in Utility Air Regulatory Group v. EPA • EPA may require sources that are subject to PSD and Title V

permitting based on their emissions of conventional pollutants to comply with best available control technology requirements for GHGs if they emit more than a de minimis quantity of GHGs

• EPA issued a memo on July 24, 2014 interpreting the de minimis quantity of GHGs to be 75,000 tons per year of CO2e

• D.C. Circuit vacated the Tailoring Rule regulations on April 10, 2015 and ordered EPA to conduct rulemaking to implement the Court’s decision • Uncertainty regarding how PSD permits that were issued to sources

based solely on their GHG emissions under the Tailoring Rule will be handled in light of the Court’s decision.

Tailoring Rule Update

20

Page 21: Environmental Issues in Federal Permitting for Energy Projects

Tailoring Rule Update • On May 7, 2015, EPA issued a direct final rule that would allow

for recession of certain PSD permits issued under Step 2 of the Tailoring Rule • The rule became effective on July 6, 2015

• On June 15, 2015 EPA announced its intention to conduct rulemaking to establish a de minimis threshold of GHG emissions that will trigger PSD permitting and GHG BACT requirements for sources that are already subject to PSD based on their emissions of conventional pollutants • EPA did not announce a firm timeline for issuing a proposed rule, but

indicated that a proposed rule is still a year away

21

Page 22: Environmental Issues in Federal Permitting for Energy Projects

CEQ Issuance of NEPA Guidance Documents

Page 23: Environmental Issues in Federal Permitting for Energy Projects

CEQ Guidance on GHGs in NEPA Reviews

• On December 18, 2014, CEQ published revised draft guidance describing how federal agencies should consider the effects of GHG emissions and climate change in their NEPA reviews • Supersedes prior draft guidance issued in 2010 • Guidance aims to provide clarity to federal agencies and to improve

consistency in how GHG emissions and climate change are addressed in NEPA reviews

• Guidance provides a reference point of 25,000 tpy CO2e emissions below which a quantitative analysis of GHGs is not warranted unless it is easily accomplished

• Industry groups have urged CEQ to withdraw or narrow its guidance

23

Page 24: Environmental Issues in Federal Permitting for Energy Projects

• On December 18, 2014, White House Council on Environmental Quality (CEQ) published a final guidance document clarifying federal agencies’ use of programmatic NEPA reviews • Programmatic reviews are performed to assess the environmental

impacts of proposed policies, plans, or programs. • Agencies should conduct programmatic NEPA reviews when

adopting official policies, formal strategic plans, or approving multiple projects on a large scale

• Programmatic NEPA reviews will typically be followed by project-specific NEPA reviews • Industry has expressed concern that more frequent programmatic

NEPA reviews could cause permitting delays.

CEQ Guidance on Programmatic NEPA Reviews

24

Page 25: Environmental Issues in Federal Permitting for Energy Projects

Questions?

25

Page 26: Environmental Issues in Federal Permitting for Energy Projects

Thank You.

Tyson Smith Energy

San Francisco

[email protected]

Stephanie Sebor Environmental

Chicago

[email protected]

Eleni Kouimelis Environmental

Chicago

[email protected]

26