environmental impact assessment for the proposed 400 · pdf fileenvironmental impact...
TRANSCRIPT
Environmental Impact Assessment for the Proposed 400 kV Transmission Line from Omatando to Oshivelo (Portion 2) Draft Environmental Impact Assessment Report
2014
i
COPYRIGHT © NAMPOWER, 2014. ALL RIGHTS RESERVED
PROJECT NAME
Environmental Impact Assessment for the Proposed 400 kV
Transmission Line from Omatando Substation to Oshivelo
Substation (Portion 2)
STAGE OF REPORT Draft Environmental Impact Assessment Report for Public Review
CLIENT
NamPower
Enquiries: Horst Mutschler
Tel: (061) 205-2735
E-Mail:
LEAD CONSULTANT
Enviro Dynamics
Enquiries: Norman van Zyl
Tel: (061) 223-336
E-Mail: [email protected]
DATE OF RELEASE October 2014
CONTRIBUTORS TO THE REPORT
Sheldon Husselmann, Norman van Zyl, Ernst Simon, Iani de Kock,
Eddy Kuliwoye, Eloise Carstens
Internal Review: Norman van Zyl
ii
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
Declaration
I hereby declare that I:
have knowledge of and experience in conducting assessments, including
knowledge of the Environmental Management Act (7 of 2007), its
regulations and guidelines that have relevance to the proposed activity;
have performed the work relating to the application in an objective
manner, regardless of whether or not the views and findings were
favourable to the applicant;
have complied with the Act, and its regulations, guidelines and other
applicable laws.
I also declare that there is, to my knowledge, no information in my possession that
reasonably has or may have the potential of influencing –
any decision to be taken with respect to the application in terms of the Act
and its regulations; or
the objectivity of this report, plan or document prepared in terms of the Act
and its regulations.
Norman van Zyl
Environmental Assessment Practitioner (EAP)
iii
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
EXECUTIVE SUMMARY
INTRODUCTION
In order to address the growing power demand in Namibia as well as the need to
ensure security of supply for future growth, NamPower intends to construct a new
400 kV transmission line from Kunene Substation (near Ruacana) to Oshivelo
Substation via Omatando Substation (near Ongwediva).
NamPower has appointed Enviro Dynamics CC to conduct an EIA and compile a
Specific Environmental Management Plan (EMP) for the proposed transmission line
route.
The terms of reference for this Environmental Impact Assessment (EIA) process are as
follows:
Assessment of the proposed route; and
Compilation of an EIA Report (which includes the compilation of an
Environmental Management Plan);
PROJECT DESCRIPTION
As highlighted in the Transmission Master Plan the two main reasons why this
transmission line is needed are:
1. The growing demand for electricity in the north of Namibia; and
2. The need to strengthen the northern section of NamPower's transmission grid
to ensure security of supply.
NamPower initially planned the route to avoid as far as practicably possible densely
populated areas (see map below) and hence reduce the need to relocate local
residents. However due to the proximity of certain sections of the initial route
alternative to the Etaka River and Lake Oponono, a Ramsar site and home to a
small group of critically endangered Blue Cranes, the proposed route was realigned
northward to reduce the risk of Blue Crane fatalities.
iv
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
The proposed transmission line (TX) route for Portion 2 (174 km in total) is as follows:
Section 1: Single circuit TX line (mostly a monopole or compact lattice
structure, but where possible a guyed V-structure) approximately 68 km, from
the Omatando SS (near Ongwediva) eastward to the Okatope SS located
near Okatope;
Section 2: Single circuit TX line (guyed V-structure) approximately 106 km long,
from Okatope SS to Oshivelo SS located near Oshivelo;
The servitudes will be 50 m wide for Section 1, which runs through densely populated
areas and 80 m for Section 2, which runs through sparsely populated areas. For the
entire line an estimated 12 m width needs to be totally cleared of vegetation and
obstacles to create a service road and ensure the line has sufficient clearance to
vegetation. The entire footprint of each V-structure (70 m X 50 m) will also be
cleared of vegetation.
The total estimated cost for of the project is has yet to be determined.
v
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
LEGISLATION AND RECEIVING ENVIRONMENT
Given the nature of some of the foreseeable impacts (resettlement and
compensation, potential loss of important bird and plant species and impacts on
heritage resources), the most important provisions of the applicable legislation are
those highlighted from the Compensation Policy Guidelines for Communal Land; the
Ramsar Convention, the Convention on Biodiversity, the Nature Conservation
Ordinance, the Forestry Act and the National Heritage Act.
A concise description of the baseline conditions pertaining to specific environmental
features has been provided, as informed by specialists’ studies. These environmental
features were identified during the Scoping Stage as those which required further
investigation. Key potential impacts relating to birds, vegetation, archaeology and
socio-economic concerns are identified.
A summary of all the issues identified for both the biophysical and social
environment is presented in the table below.
PUBLIC PARTICIPATION
Public participation was carried out during the Scoping Stage of this EIA process in
accordance with the EIA Regulations. Various stakeholders at national, regional
and local level were identified and their input solicited. Particular effort was exerted
to involve stakeholders at a local level – those living in and around the project area.
Public meetings during the public consultation period were held as follows:
DATE LOCATION
10 March 2014 Ruacana: Eha Lodge
10 March 2014 Outapi: Outapi Town Lodge
11 March 2014 Okahao: Ongozi Lodge
11 March 2014 Ongwediva: Hotel Destiny
12 March 2014 Onyaanya: Uukule Senior Secondary School
12 March 2014 Omuthiya: Roadhouse Guesthouse
vi
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
The Draft Scoping Report was circulated to all Interested and Affected Parties
(I&APs) for them to review and a comments period from the 13th to the 27th of June
2014 was provided. No comments were received during this period.
The Draft Environmental Impact Assessment Report will be circulated to all I&APs for
review and a comments period of two weeks provided.
IMPACT ASSESSMENT
The impacts, identified during the Scoping Stage of this EIA process, which required
further investigation are assessed using a range of assessment criteria. The
application of these criteria uses a balanced consideration of duration, extent, and
intensity, modified by probability, cumulative effects, and confidence in order to
determine significance. Mitigation and monitoring measures are prescribed and
these are addressed in the General and Specific EMP.
RECOMMENDATIONS AND CONCLUSIONS
The following should be noted about the key impacts:
Impact on vegetation: Several high use value tree species and a few range
restricted plant species occur within the project area. The mitigation
measures prescribed in this report and the EMP are sufficient to address these
potential impacts.
Impact on birds: The wider project area supports a relatively high diversity of
bird species (approximately 200 species). The main impact on birds
associated with the proposed transmission line is related to potential collisions
once the line is operational. The mitigation measures prescribed in this report
and the EMP are sufficient to address these potential impacts.
THEME ISSUE
SAFETY
Houses should be located at least 20 m from the line.
Safety measures during construction should be in place (including clearing of
landmines).
EMPLOYMENT Local labour should be used to the extent possible.
BIODIVERSITY Loss of important bird and plant species owing to habitat disturbance and
destruction.
SOCIO-
ECONOMIC
Compensation for various housing structures as well as trees, e.g. fruit trees,
should be identified.
HIV/AIDS infection rates and marriage instability
Short term economic boom due to construction workers supporting local
shops.
HERITAGE Disturbance and destruction of heritage resources.
vii
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
Socio-economic impacts: The proposed route goes through densely
populated areas. A total of 43 households will be affected by the proposed
route and relocation will need to take place in several instances. A total of
165 fruit-bearing trees will need to be removed. The mitigation measures
prescribed in this report and the EMP are sufficient to address these potential
impacts.
Impact on archaeology: One potentially sensitive archaeological site in the
form of a floodplain covering an area of 4 ha, is located north of Ondangwa.
The mitigation measures prescribed in this report and the EMP are sufficient to
address these potential impacts.
It is the opinion of Enviro Dynamics that sufficient information is available to address
all impacts identified and assessed during this Environmental Impact Assessment
process through the recommended mitigation measures laid out in this report and
the General and Specific EMP.
It is therefore recommended that the proposed project receive Environmental
Clearance, provided that both the General and Specific EMPs are implemented.
viii
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
TABLE OF CONTENTS
EXECUTIVE SUMMARY .............................................................................................................. iii
TABLES AND FIGURES ............................................................................................................... x
ABBREVIATIONS ....................................................................................................................... xi
APPENDICES ............................................................................................................................ xii
1 INTRODUCTION ................................................................................................................. 1
1.1 BACKGROUND .......................................................................................................... 1
1.2 TERMS OF REFERENCE ............................................................................................... 2
1.3 WORK PLAN FOR STUDY............................................................................................ 3
2 PROJECT DESCRIPTION .................................................................................................... 4
2.1 NEED FOR THE DEVELOPMENT ................................................................................. 4
2.2 ROUTE ALTERNATIVES AND SELECTION ................................................................... 4
2.3 THE PROPOSED NEW TRANSMISSION LINES ............................................................ 6
2.4 STRUCTURAL AND PHYSICAL REQUIREMENTS OF THE LINE .................................... 8
2.5 CONSTRUCTION ACTIVITIES ...................................................................................... 9
2.6 PROJECT COST AND TIMELINE ............................................................................... 10
2.7 CONSTRUCTION MATERIALS AND PROCESS ........................................................ 10
2.8 WASTE MATERIALS ................................................................................................... 10
2.9 EMPLOYMENT CREATION ....................................................................................... 11
2.10 DECOMMISSIONING ............................................................................................... 11
3 LEGISLATION AND POLICIES .......................................................................................... 12
4 RECEIVING ENVIRONMENT ............................................................................................ 15
4.1 BIOPHYSICAL ENVIRONMENT ................................................................................. 15
4.1.1 GENERAL DESCRIPTION OF THE ENVIRONMENT OF PORTION 1 ................. 15
4.1.2 VEGETATION ..................................................................................................... 16
4.1.3 BIRDS .................................................................................................................. 19
ix
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
4.2 SOCIAL ENVIRONMENT ........................................................................................... 21
4.2.1 INTRODUCTION ................................................................................................. 21
4.2.2 GENERAL DESCRIPTION OF THE SOCIAL ENVIRONMENT OF PORTION 2 ... 21
4.2.3 ARCHAEOLOGY ............................................................................................... 22
5 PUBLIC CONSULTATION .................................................................................................. 24
5.1 INTRODUCTION ........................................................................................................ 24
5.2 THE MEETINGS TO DATE ........................................................................................... 24
5.3 PUBLIC CONCERN ................................................................................................... 26
5.4 PUBLIC FEEDBACK ................................................................................................... 27
6 IMPACT ASSESSMENT ...................................................................................................... 28
6.1 THE ‘NO-GO’ ALTERNATIVE .................................................................................... 28
6.2 IDENTIFICATION OF KEY ISSUES ............................................................................... 28
6.3 METHODOLOGY EMPLOYED FOR THE IMPACT ASSESSMENT ............................. 31
6.4 ASSESSMENT OF IMPACTS ....................................................................................... 32
6.4.1 IMPACT ON VEGETATION ................................................................................ 32
6.4.2 IMPACT ON BIRDS ............................................................................................ 35
6.4.3 IMPACT ON THE SOCIO-ECONOMIC ENVIRONMENT .................................. 40
6.4.4 DESTRUCTION OR DAMAGE TO ARCHAEOLOGICAL SITES ......................... 44
6.4.5 ASSESSMENT OF CUMULATIVE IMPACTS ........................................................ 46
7 CONCLUSIONS AND RECOMMENDATIONS ................................................................ 47
7.1 CONCLUSIONS......................................................................................................... 47
7.2 RECOMMENDATIONS.............................................................................................. 48
8 REFERENCES ..................................................................................................................... 49
x
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
TABLES AND FIGURES
Table 1: Vegetation related sensitivities ......................................................................... 16
Table 2: Bird related sensitivities ....................................................................................... 20
Table 3: Socio-economic related sensitivities ................................................................ 23
Table 4: Summary of the meetings conducted ............................................................. 25
Table 5: Summary of issues ............................................................................................... 26
Table 6: Identification of key impacts during the various phases of the project. ..... 30
Table 7: Definitions of each of the criteria used to determine the significance of
impacts ............................................................................................................. 31
Table 8: Definitions of the various significance ratings ................................................. 32
Table 9: Summary of vegetation impact assessment ................................................... 34
Table 10: Summary of bird impact assessment ............................................................ 38
Table 11: Summary of the potential impacts of the proposed power line project
on the surrounding socio-economic environment ..................................... 43
Table 12: Summary of archaeology impact assessment ............................................ 45
Figure 1: Diagrammatic summary of work plan ............................................................ 3
Figure 2: Route alternative considered. ......................................................................... 5
Figure 3: Proposed transmission line route from Omatando SS to Oshivelo SS. ........ 7
Figure 4: Example of tower design for single circuit line in densely populated
areas .................................................................................................................... 8
Figure 5: Example of structure for single circuit line in sparsely populated areas .... 8
Figure 6: Servitude details for the proposed transmission line ..................................... 9
Figure 7: Vegetation sensitivities and bird movement and distribution ................... 18
Figure 8: Screening process to determine key issues ................................................. 29
Figure 9: Location of areas of concern for vegetation and birds ............................ 33
Figure 10: Sections along Portion 2 sensitive to bird collisions ..................................... 37
Figure 11: Archaeological site of concern .................................................................... 44
xi
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
ABBREVIATIONS
kV Kilo Volt
EIA Environmental Impact Assessment
GIS Geographic Information System
EMP Environmental Management Plan
ToR Terms of Reference
I&AP Interested and Affected Party
SS Substation
TX Transmission
GN Government Notice
ECB Electricity Control Board
GG GG
NHC National Heritage Council
MSL Mean Sea Level
AD Anno Domini/ In the year of our Lord
NORED Northern Regional Electricity Distributor
BID Background Information Document
HIV Human Immunodeficiency Virus
AIDS Acquired Immunodeficiency Syndrome
km kilometre
m metre
m3 Cubic metre
xii
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
APPENDICES
Appendix A Curriculum Vitae
Appendix B1 General EMP
Appendix B2 Specific EMP
Appendix C Vegetation Impact Assessment Report
Appendix D Bird Impact Assessment Report
Appendix E Social Impact Assessment Report
Appendix F Archaeology Impact Assessment Report
1
1 INTRODUCTION
1.1 BACKGROUND
Namibia at present is a net importer of electricity, relying on neighbouring nations to
supply current shortfall. The demand for electricity nationally has been increasing
especially in the northern regions of Namibia. The recently approved NamPower
Transmission Master Plan has recognised this increase in demand and hence the
urgency to find a solution. In order to address this demand as well as that of
ensuring security of supply for future growth, NamPower intends to construct a new
400 kV transmission line from Kunene Substation (near Ruacana) to Oshivelo via
Ongwediva (see Figure 3).
NamPower has appointed Enviro Dynamics CC, assisted by Urban Dynamics, to
conduct an Environmental Impact Assessment (EIA) for the proposed transmission
line route in accordance with the Environmental Management Act of 2007 and its
Regulations (2012).
The Scoping Stage of this EIA process was concluded in May 2014. The Scoping
Report was circulated to all registered Interested and Affected Parties (I&APs) for
review before being submitted to the Directorate of Environmental Affairs (DEA) for
review and comment. During the Scoping Stage impacts were identified and public
consultation carried out for a 380 km proposed transmission line route.
In order to streamline the applications for Environmental Clearance the proposed
380 km transmission line route has been divided into two portions, namely Portion 1
and Portion 2. NamPower intends to construct Portion 1 first as a matter of urgency.
Separate Environmental Impact Assessment Reports (EIARs) have hence been
produced for each portion. This report is the culmination of the detailed
investigation and assessment stage of an EIA for Portion 2. This report provides a
detailed assessment of impacts identified during the Scoping Stage, as informed by
the detailed specialist studies conducted for this EIA.
Norman van Zyl, who is a qualified and recognised Environmental Assessment
Practitioner (see Appendix A for CV) led the assessment.
2
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
1.2 TERMS OF REFERENCE
The Terms of Reference (ToR) for the assessment of the proposed project is based on
the requirements set out by the Environmental Management Act (2007) and its
Regulations (February 2012). The process covered the following steps, which are
reported on in this document as follows:
Provide a detailed description of the proposed activity, including a
description of the need and desirability of the proposed project and a
presentation of alternatives considered (Chapter 2);
Identify all legislation, policies and guidelines that are applicable to the
proposed project (Chapter 3);
Identify existing environmental (both ecological and socio-economic)
features and/or conditions of the receiving environment in order to determine
how these may be affected by the proposed project (Chapter 4); and
Inform I&APs and relevant authorities of the details of the proposed
development and provide them with a reasonable opportunity to participate
during the process (Chapter 5);
Assess the agreed upon route’s socio-economic and bio-physical impacts
expected during construction and operation of the route (Chapter 6).
3
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
1.3 WORK PLAN FOR STUDY
In order to meet the requirements of the Terms of Reference for this EIA, the study
consists of four phases as indicated in Figure 1 below. The purpose of this document
is to assess the impacts identified in the previous stage of this EIA process.
Figure 1: Diagrammatic summary of work plan
Stage 3: EMP Revision
Review NamPower’s EMP to include site specific issues
Stage 4: Reporting
Submit Draft Reports to the Client and I&AP’s
Receive and incorporate comments from Client.
Submit final EIA Report and EMP
Comment on
draft document
and feedback
Stage 2: Detailed Investigation
Specialist Investigations
Final route selection
IMPACT ASSESSMENT
Wide Public
Consultation
Stage I: Route and substation site evaluation
Introductions with Client
Meetings with technical staff of NamPower about
possible alternatives
Site Visit
Map proposed route and consider any obvious
conflict areas, using GIS.
Public consultation (including meetings)
Issue identification and risk assessment
Final scope and tor of study
This Report
4
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
2 PROJECT DESCRIPTION
The need for the proposed new transmission line and an evaluation of route
alternatives are provided in this chapter as well as the technical specifications of the
infrastructure to be constructed. This chapter highlights aspects of this project,
which are likely to interact significantly with the socio-ecological environment.
2.1 NEED FOR THE DEVELOPMENT
The recently approved NamPower Transmission Master Plan outlines Namibia’s future
transmission needs up to 2050.
As highlighted in the Master Plan the two main reasons why this transmission line is
needed are:
1. The growing demand for electricity in the north of Namibia; and
2. The need to strengthen the northern section of NamPower's transmission grid
to ensure security of supply.
2.2 ROUTE ALTERNATIVES AND SELECTION
NamPower planned the original route via less densely populated areas (Figure 2).
During the route alternatives selection process and physical route evaluation, the
following opportunities and constraints were raised:
1. The route was very close to the northern boundary of the Etosha Pan and
Lake Oponono, which are sensitive areas to water bird life, especially the
critically endangered Blue Crane. Therefore the entire section from the
Makalani Substation to a point just short of the Oshivelo Substation were
located in or very near the breeding grounds of the Blue Crane. This element
of the route could lead to unacceptable Blue Crane fatalities, as this species
is prone to power line collisions.
2. Moving the section from the proposed site for the Makalani Substation to the
Oshivelo Substation merely further north (away from the water courses and
pans mentioned) on a new alignment would cause severe socio-economic
disruption with excessive compensation costs, making the project not viable.
3. The route of the existing 132 kV line from Omatando to Okatope could be
successfully widened to accommodate the new 400 kV line with limited
compensation costs and socio-economic impacts.
5
Figure 2: Route alternative considered.
6
4. The route of the existing 132 kV line from Okatope to Oshivelo Substation is
subject to the following limitations: limited space owing to existing rail, road
and power line servitudes and densely populated with major villages and
large homesteads. Using the existing route in this section will cause excessive
social disruption and compensation costs will be excessive.
5. A new route was set out north of the railway line from near Okatope to
Oshivelo substation via a more direct but less populous area. The result is that
the socio-economic effect and compensation requirement are lowered
significantly.
The revised route is shown in Figure 3.
2.3 THE PROPOSED NEW TRANSMISSION LINES
As discussed in the scoping report of this EIA, the project comprises two portions. This
report’s focus is on Portion 2, which includes the following components:
Section 1: Single circuit TX line (possibly the structure displayed in Figure 4)
approximately 68 km, from Omatando SS eastward, running along the existing
132 kV TX line to the vicinity of Okatope SS; and
Section 2: Single circuit TX line (structure in Figure 5) approximately 106 km, on
a new alignment (deviating from 132 kV line), from the vicinity of Okatope SS
to Oshivelo SS.
Sections 1 and 2 will be referred to collectively as Portion 2.
7
Figure 3: Proposed transmission line route from Omatando SS to Oshivelo SS.
8
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
2.4 STRUCTURAL AND PHYSICAL REQUIREMENTS OF THE LINE
In terms of structural design alternatives for the proposed project, the guyed V-structure
is structurally the most efficient design for 400 kV single circuit transmission lines, and can
be up to four times cheaper than self-supporting monopole structures. Additionally,
conductors are arranged in a perfect delta configuration (conductors arranged in
triangular formation) which reduces surge-impedance loading. This has a positive
impact on its electrical efficiency. Its utilisation must therefore be maximised wherever
possible. Monopole structures are more compact in terms of their footprint and hence
better suited for areas where servitude widths are limited and are also better suited for
manoeuvrability (i.e. creation of bend points). These considerations guide structure
design selection.
The length of the proposed transmission lines for Portion 2 is estimated to be
approximately 174 km long. Section 1 will be supported mostly by a self-supporting
galvanised steel mono-pole structure (see Figure 4) or a compact lattice structure and
where possible a steel guyed V-structure. Section 2 will be supported by a galvanised
steel guyed V-structure (see Figure 5). The approximate height of these structures will
be 45 m.
The servitude will be 50 m wide for Section 1, which runs through densely populated
areas and 80 m for Section 2, which runs through sparsely populated areas. For the
entire line an estimated 12 m width needs to be totally cleared of vegetation and
obstacles to create a service road, to provide access (during construction and
Figure 4: Example of tower design for single
circuit line in densely populated areas
Figure 5: Example of structure for single circuit line in
sparsely populated areas
9
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
maintenance) to the line throughout its lifespan of 30 years. This clearing is also required
to ensure the conductors clear taller vegetation such as trees. Owing to its larger
footprint, the area about the centre of each V-structure to be cleared of vegetation
will cover an area of approximately 70 m X 50 m. The EIA team however, assessed a
corridor of 500 m wide (250 m on either side of the proposed line).
For safety and technical reasons, no other permanent structures are allowed within the
servitude. Grazing and subsistence cultivation of fields with associated subsistence
farming activities may be accommodated within this area, except for the 12 m strip,
which is needed during construction and operation.
2.5 CONSTRUCTION ACTIVITIES
All the components for power line construction (concrete, pylons, conductors, and
insulators etc.) will be transported to site by road on low-bed trailers. The main access
roads to the line are the C46 (closer to Omatando SS) and the B1 (between Ondangwa
and Oshivelo) which will most probably be used to transport materials to and from the
transmission line. From here materials will be transported along the line via the existing
single track gravel road servicing the existing transmission line. No significant impacts
associated with traffic interruption are expected along the main roads. Even though
the traffic will increase, this will be for a short period. The maintenance road and all
connecting access roads addressed in the General EMP (see Appendix B1). Basic
traffic management pertaining to main roads will be addressed within the Specific EMP
(see Appendix B2).
Steel structures will either be erected by using a crane to place the pre-assembled
tower onto the concrete foundation or by building up the tower from its concrete
foundation section by section. The conductors will be strung using heavy-duty
mechanical winches.
Concrete for the pylon foundations will be mixed and poured on site or at a batching
plant in close proximity. Hence, all the concrete constituents (crushed stone, cement,
water and sand) will be transported to the project area. No borrow pits (existing or
Total 80 m servitude
to be clear of
settlement in sparsely
populated areas and
50 m in densely
populated areas
40 m servitude on
either side of the line
in sparsely populated
areas and 25 m in
densely populated
areas
12 m to be
cleared of
vegetation
Figure 6: Servitude details for the proposed transmission line
10
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
new) will be utilised for the proposed project. All building supplies will be supplied by
existing commercial suppliers.
Most often, construction camps accommodating construction labour force are located
close to the work area.
2.6 PROJECT COST AND TIMELINE
The project will be internally financed by NamPower. Cost estimates and estimated
time for construction have yet to be determined.
2.7 CONSTRUCTION MATERIALS AND PROCESS
The proposed project will require the following approximate volumes of materials per
km of transmission line:
Approximately 12 m3 water from boreholes for concrete.
Approximately 50 m3 sand and stone for concrete, sourced locally.
Approximately 12 tons galvanised steel, sourced internationally.
Conductor, optical fibre, Insulators and associated hardware will be sourced
internationally.
The project will be sourced from a base camp as well as a satellite camp for every 40
km of line. The construction process will use three separate teams that will be
responsible for:
Clearing the line, digging and casting of foundations;
Constructing(assembly and erection) of towers (specially trained team); and
Stringing and clamping the cabling (specially trained team).
2.8 WASTE MATERIALS
Besides some left-over concrete and various other residual building material, normal
domestic waste such as plastic bags, tins, bottles, paper, and packaging waste will also
be generated. Waste generation is an obvious impact of any project and needs to be
managed in an appropriate manner in order to minimise the proposed project’s
ecological footprint. Waste management is addressed in the General EMP (see
Appendix B1) for this project.
11
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
2.9 EMPLOYMENT CREATION
Employment opportunities on this project are limited. The construction of transmission
lines is a specialised operation, which will be managed by a local or foreign contractor
who will bring specialist foreign and Namibian staff from areas outside the project area.
The only activities for which the contractors most likely use local unskilled labour is for
the debushing of the site (debushing will be done mostly with machines, but may be
supplemented with manual labour) and for the digging of the foundations.
About 200 people will be employed during construction of a section of line, of which
approximately 30 people will be of management and supervisory capacity. The
remainder will be artisan and skilled labour, with a smaller component of unskilled
labour.
The maintenance of the new transmission line is likely to be done by existing NamPower
staff, therefore, no employment creation is expected during operation. If an
agreement can be reached between NamPower and the local authorities, the
maintenance of the cleared portion of the servitude could serve as an employment
opportunity.
2.10 DECOMMISSIONING
It is envisaged that the proposed project will continue as long as the demand for
electricity exists, hence decommissioning is not expected. However, in the event that
the proposed project needs to be decommissioned, relevant provisions have been
outlined with the Specific EMP (Appendix B2) to guide such activity. The activity
associated with decommissioning is similar to that of construction and as such most of
the provisions outlined within the Specific EMP will make reference to the applicable
construction-related provisions within NamPower’s General EMP (Appendix B1).
12
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
3 LEGISLATION AND POLICIES
The pursuit of sustainability, with respect to any project, is guided by a sound legislative
and policy framework. This section provides a review of applicable and relevant
legislation and policies, both international and national. This review serves to inform the
developer of the requirements and expectations, as laid out in terms of these
instruments, to be fulfilled before the proposed project may commence. The findings of
the above mentioned review are summarised below.
LEGISLATION/ POLICY/
GUIDELINE
RELEVANT PROVISIONS IMPLICATIONS FOR THIS
PROJECT
INTERNATIONAL
Ramsar Convention on
Wetlands of International
Importance (1971)
Article 2(1) provides for the inclusion of
wetlands in a “List of Wetlands of
International Importance” “especially
where these have importance as
waterfowl habitat”.
Article 2(6) provides for the exercising of
international responsibilities with respect
to these wetlands.
Article 4 provides for the promotion of
conservation of wetlands and waterfowl.
Namibia is a signatory to this
convention.
Etosha Pan, Lake Oponono and
the Cuvelai Drainage are all
included in the “List of Wetlands
of International Importance”
and their conservation has the
support of national government.
NamPower therefore has a
responsibility to ensure that steps
are taken to conserve water
birds.
Convention on
Biological Diversity (1992)
Article 6 (b) provides for the explicit
consideration of “the conservation and
sustainable use of biological diversity into
relevant… plans, programmes and policies”
In keeping with national
strategies, NamPower needs to
ensure that biodiversity is not
compromised as a result of this
project.
World Bank OP and BP
4.11 guidelines in respect
of “Physical Cultural
Resources”
Provides guidelines pertaining to physical
cultural resources with respect to project
screening, baseline surveys and mitigation.
The archaeological Impact
Assessment should adhere to
these guidelines.
NATIONAL
Namibian Constitution
First Amendment Act 34
of 1998
Chapter 11 Article 95: Promotion of the
Welfare of the People
Ecological sustainability should
inform and guide these projects.
Compensation Policy
Guidelines for
Explains situations that may give rise to
compensation e.g. where land is taken This document should inform and
guide the resettlement plan to
13
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
LEGISLATION/ POLICY/
GUIDELINE
RELEVANT PROVISIONS IMPLICATIONS FOR THIS
PROJECT
Communal Land
(applied with effect from
April 2008)
for township expansion or other public
service sector developments;
Gives direction on how compensation
shall be determined;
Helps affected land owners to choose an
option they consider fair; and
Is applicable in cases where an
occupant of land within a proclaimed
local authority boundary has been
occupying the affected land in
accordance with customary laws of the
area.
be compiled for this project.
Environmental
Management Act EMA
(No 7 of 2007)
Requires that projects with significant
environmental impact are subject to an
environmental assessment process
(Section 27).
Details principles which are to guide all
EIAs.
The EMA and its regulations
should inform and guide this EIA
process.
EIA Regulations GN No
28-30 (GG No 4878)
Details requirements for public
consultation within a given
environmental assessment process (GN
No 30 S21).
Details the requirements for what should
be included in a Scoping Report (GN No
30 S8) and an EIA report (GN No 30 S15).
Electricity Act 4 of 2007 The Electricity Control Board (ECB) with
regards to achieving its objectives must
make recommendations to the Minister
regarding the issue and renewing of
licences (S 3(2)(a)).
A licence needs to be obtained from the
ECB for the transmission of electricity (S
17(1)(c)).
The Minister or ECB may request that an
EIA accompany applications for licences
(S 21(2)(a)(i)).
Restoration of land and rehabilitation
measures may be stipulated as a
condition of a licence (S 24(2)(b)).
NamPower should adhere to
the recommendations made
by the ECB.
NamPower requires a licence
for the transmission of
electricity.
NamPower should adhere to
any restoration or
rehabilitation measures
stipulated in the conditions of
approval laid out by the ECB.
Forestry Act 12 of 2001
Nature Conservation
Ordinance 4 of 1975
Tree species and any vegetation within
100 m from a watercourse may not be
removed without a permit (Forestry Act
S22(1)).
Prohibits the removal of and transport of
various protected plant species.
The clearing of vegetation is
prohibited 100 m either side of a
river. Certain tree species
occurring in the area are
protected under this Act and
14
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
LEGISLATION/ POLICY/
GUIDELINE
RELEVANT PROVISIONS IMPLICATIONS FOR THIS
PROJECT
require a permit from the
Directorate of Forestry for
removal.
Labour Act 11 of 2007 Details requirements regarding minimum
wage and working conditions (S39-47).
NamPower should ensure that all
contractors involved in the
construction of the services
infrastructure for this project
comply with the provisions of
these legal instruments.
Furthermore Contractors are to
keep dust and noise nuisances
to a minimum.
Health and Safety
Regulations GN 156/1997
(GG 1617)
Details various requirements regarding
health and safety of labourers.
Public Health Act 36 of
1919
Section 119 states that “no person shall
cause a nuisance or shall suffer to exist on
any land or premises owned or occupied
by him or of which he is in charge any
nuisance or other condition liable to be
injurious or dangerous to health.”
National Heritage Act 27
of 2004
Section 46 prohibits the disturbance in
any form of heritage resources declared
as protected.
Section 48 (1) states that “A person may
apply to the [National Heritage] Council
for a permit to carry out works or
activities in relation to a protected place
or protected object”
All protected heritage resources
(e.g. human remains etc.)
discovered, need to be reported
immediately to the National
Heritage Council (NHC) and
require a permit from the NHC
before they may be relocated.
The provisions most important, in terms of guiding this EIA process from those listed
above are those pertaining to the conservation of biodiversity, particularly bird and
plant species (Ramsar Convention, Convention on Biodiversity, Nature Conservation
Ordinance and Forestry Act) those pertaining to resettlement and compensation of
local residents (Compensation Policy Guidelines for Communal Land) and finally those
pertaining to heritage resources (National Heritage Act).
15
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
4 RECEIVING ENVIRONMENT
This chapter focuses primarily on the features for which the information was insufficient
or that needed further investigation at the end of the scoping phase. The findings of
the specialist investigations form part of the descriptions, specifying sensitive areas
along the proposed route where human disturbance should be avoided or managed.
Proposed mitigation measures emanating from the assessment of the impacts are
discussed in Chapter 6.
4.1 BIOPHYSICAL ENVIRONMENT
4.1.1 GENERAL DESCRIPTION OF THE ENVIRONMENT OF PORTION 1
From west to east the proposed route starts in the Cuvelai landscape (Omatando SS) at
approximately 1100 m above MSL and enters Kalahari sandveld before moving through
western Karstveld, a short transition zone, before terminating in the Kalahari woodland.
The Karstveld is represented by a few low dolomite koppies/ridges. Gentle slopes and
wide flat expanses are two of the main distinctive features of the Cuvelai landscape.
Within the Cuvelai landscape the proposed route is underlain by sediments of silt and
clay, particularly within/along drainage channels (Mendelsohn, et al., 2000). Average
annual rainfall varies from 350 (western section) to approximately 500 mm (eastern
section) (Mendelsohn, et al., 2009). The Cuvelai drainage (see Figure 3) can be
described as a large inland delta of winding and interconnected ephemeral drainage
channels. The gentle slopes of the north central regions results in slow flow velocities
and hence slow rate of drainage, however the porous nature of the soil (and in some
areas only sand) mitigates against these slow drainage rates. The headwaters of the
Cuvelai are located in southern Angola between those of the Okavango and the
Kunene. Seasonal flash floods are a characteristic feature of the Cuvelai and these
vary considerably providing water further southwards with increasing intensity.
16
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
4.1.2 VEGETATION
The baseline description below pertaining to vegetation affected by Portion 2 has been
summarised from the report (see Appendix C) drafted by Mannheimer (2014).
The transmission line (from west to east) in terms of major vegetation zones starts in the
Cuvelai Drainage, then crosses into eastern Kalahari Woodlands.
In terms of minor vegetation zones Section 1 and at least the western half of Section 2
(see Figure 7) traverses the Oshana-Kalahari mosaic and palms and pans mosaic,
which includes high use value tree species such as the Jackal-berry (Diospyros
mespiliformis), Baobab (Adansonia digitata), Bird plum (Berchemia discolor), Strangler
fig (Ficus petersii), Sycamore fig (Ficus sycomorus), Manketti (Schinziophyton rautanenii)
and Marula (Sclerocarya birrea). The Leadwood tree (Combretum imberbe) has
widespread occurrence throughout the project area and is also a high use value tree.
The eastern half of Sections 2 (see Figure 7) traverses the Mixed Acacia Kalahari
woodlands, which includes high use value tree species such as Terminalia prunioides
woodland on deep Kalahari sands and the following woody species Acacia erioloba
(protected), Philenoptera nelsii (protected) and Terminalia sericea.
Plant diversity in the north central regions varies to a large extent (between 50 and 400
species). Diversity is at its highest in the extreme eastern end of the line. The diversity
then drops significantly with increasing distance to the west reaching lowest species
diversity in the pan area of the Cuvelai (less than 50 species).
The sensitivity of vegetation in the defined vegetation types are described in Table 1
below. The sensitive sections along the proposed route are further discussed in Chapter
7.
Table 1: Vegetation related sensitivities
ENVIRONMENTAL
FEATURE
DESCRIPTION SENSITIVITY POTENTIAL
IMPACTS
Range-restricted
and endemic flora
The following tree species, which are likely to
occur along the proposed transmission line
route, are restricted in range:
Entandrophragma spicatum (Owambo
wooden-banana, Omataku);
These species only
occur within a limited
geographic area
Loss in plant
species
biodiversity.
Regrowth and
coppice control
Some tree species (Dichrostachys cinerea)
are known to coppice strongly. General
vegetation regrowth will take place.
Service roads and
access to these
roads might become
overgrown
Impaired
ability to
maintain line.
17
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
ENVIRONMENTAL
FEATURE
DESCRIPTION SENSITIVITY POTENTIAL
IMPACTS
Clearing of
vegetation
Herbicides might be used to clear the
proposed route of vegetation during
construction and operation.
Invasive species will
encroach extensively
in areas disturbed by
herbicides.
Loss in plant
species
biodiversity.
High use value
plant species
The following tree species, which are likely to
occur along the proposed transmission line
route, are a few of those that have high use
value to local people and animals:
Adansonia digitata (Baobab); Berchemia
discolor (Bird plum); Combretum imberbe
(Leadwood); Diospyros mespiliformis
(Jackal-berry); Ficus petersii (Strangler fig);
Ficus sycomorus (Sycamore fig);
Schinziophyton rautanenii (Manketti);
Acacia erioloba, A. mellifera, Philenoptera
nelsii, Terminalia sericea, Croton gratissimus,
Dichrostachys cinerea and Catophractes
alexandri.
Plant species are
useful to local
residents and may in
some cases form part
of their livelihoods.
Economic
losses to
local
residents
18
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
Figure 7: Vegetation sensitivities and bird movement and distribution
19
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
4.1.3 BIRDS
The baseline description below pertaining to birds species affected by Portion 2 has
been summarised from the report (see Appendix D) drafted by Pallett (2014).
The proposed transmission line route traverses areas adjacent to the Etosha Pan, Lake
Oponono and the Cuvelai Drainage, which are all included in the List of Wetlands of
International Importance (Ramsar Convention on Wetlands, 2012). Namibia is a
signatory to this convention and as such the conservation of these Ramsar sites and
their associated water birds are a national concern.
The broader area traversed by the proposed transmission line route include habitats,
which collectively are frequented, to various degrees, by approximately 200 bird
species. Of these 29 species are conservation priorities by virtue of declining
populations or endemicity.
One species of particular concern is the blue crane. The blue crane has the smallest
range of all crane species. The total global population of blue cranes is approximately
25 000, but the Namibian contingent comprises 20 individuals. These birds are
concentrated in the eastern parts of Etosha National Park and in the grasslands centred
on the Omadhiya lakes, which is located due north of the national park. The numbers
of these cranes are in decline owing to habitat loss due to expanding human
populations, trapping and snaring, poisoning, and their high vulnerability to collisions
with power lines. The blue cranes are expected to fly north-west and north-east from
the area where most individuals are concentrated – the Etosha Pan and Omadhiya
Lakes area.
Portion 2 can be divided into two habitats:
Section d: Medium-settled areas with scattered homesteads, fields and open
grazing land. Occasional oshanas (shallow channels and pans provide
conditions conducive for feeding, shelter and breeding) – the entire length of
Section 1 from Okatope SS to Oshivelo SS (see Figure 7); and
Section e: Medium-to-sparsely-settled areas with occasional oshanas, grading
into the eastern Kalahari woodlands in the south (Medium density woodland with
open grassy patches provide conditions conducive for feeding, shelter and
breeding)– the entire length of Section 2 from the the Omatando SS to the
Okatope SS (see Figure 7).
Section d traverses the habitats, which most notably support the following Red-listed
species; Cape Vulture (critically endangered), Tawny eagle, martial eagle, bateleur,
20
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
Ludwig’s bustard, violet woodhoopoe and yellow-billed oxpecker, all of which are
endangered.
Section e traverses the habitats, which most notably support the following Red-listed
bird species, Blue and Wattled Crane and Cape Vulture (all critically endangered),
Grey Crowned Crane, Saddlebilled Stork saddle-billed stork, Tawny eagle, martial
eagle, bateleur, Ludwig’s bustard, violet woodhoopoe and yellow-billed oxpecker (all
endangered).
Please see Pallett (2014) (Appendix D) for a comprehensive list of affected bird species.
Table 2: Bird related sensitivities
ENVIRONMENTAL
FEATURE
DESCRIPTION SENSITIVITY POTENTIAL
IMPACTS
Bird collisions Various species of
predominantly large
birds are prone to
colliding with power
lines.
Collision mortalities are a significant
threat to many Red Data bird
species, e.g. Blue and Wattled
Crane. A full description of the red
data species expected on this
portion is provided in Pallet (2014).
Often this cause of mortality
combines with other threats such as
dwindling habitat and food
resources, and human disturbance.
Bird mortalities (of
red data species in
some instances)
owing to collisions
with powerlines.
Electrocution of
birds by power
lines
Large birds that perch,
such as eagles and
vultures, depending on
the tower design, can
get electrocuted on
powerlines when they
open their wings and
breach two conductors.
It is mainly large raptors such as
martial eagles and white-backed
vultures that are prone to
electrocution in Namibia.
Bird mortalities (of
red data species in
some instances)
owing to
electrocution
Disturbance of
breeding birds
Birds may be disturbed
at their nesting sites
either intentionally or by
accident.
Intentional disturbance, such as
collecting young parrots or trapping
birds for the muti trade, makes
certain species such as parrots and
vultures vulnerable.
Breeding birds may
lose that clutch of
young, resulting in
less recruitment into
the population.
21
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
4.2 SOCIAL ENVIRONMENT
4.2.1 INTRODUCTION
This section of the report attempts to broadly describe the social receiving environment
in which the project is set to occur based on the specialist report by Simon (2014). The
specialist report mainly draws on the 2001 and 2011 Namibia Population and Housing
Censuses. The aim of the section is to highlight trends that can be used as a basis for
anticipating any potential social impacts that could derive from the proposed project.
4.2.2 GENERAL DESCRIPTION OF THE SOCIAL ENVIRONMENT OF PORTION 2
Portion 2 passes through two regions, namely the Oshana and Oshikoto regions. The
Oshana Region, which is the smaller of the two regions (covers 1% of Namibia’s surface
area), is also the most densely populated. According to Simon (2014) population
density varies along the line from the Omatando to Oshivelo Substations. The
population density is highest near the Omatando Substation and decreases as one
moves east towards Ongwediva and Oshivelo, meaning that is generally more difficult
to route the transmission line through the western section of Portion 2.
The area that will be traversed by the line in both regions is inhabited by communal
farmers with homesteads located inside their crop fields. According to Simon (2014)
wages and salaries are becoming increasingly important on both a national and
regional level with income generated through farming activities becoming less
prevalent. This may be due to the increase in urbanisation occurring in the area
(Oshana Region has seen a rate of urbanisation of 14% from 2001 to 2011, compared
with a 4% increase in the Oshikoto Region) or simply due to a loss of interest in farming.
Nonetheless, farming remains an important source of income with their main activities
seasonal cropping, livestock rearing and the harvesting of naturally occurring fruits and
vegetables.
The construction of the transmission line is likely to cause relocations of at least some
households, especially in the more densely populated areas.
Linked with a high level of dependence on subsistence farming as a main source of
livelihood, and on natural resources, it is understandable that many people are
concerned about land take for other purposes which would cause relocation of
people into an already overcrowded commons area. It would however be possible for
all homesteads affected to remain within the confines of their current fields should they
need to relocate. Furthermore it is understandable that for some householders, their
fruit trees are regarded as a very important livelihood source from which they make
22
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
alcoholic drinks to sell for a cash income or use it for own consumption. During difficult
times it also becomes an important source of food.
Apart from the Oshana region, which saw a reduction of 1% in the proportion of
extremely poor residents, unemployment and consequently poverty remains high with
too few employment opportunities in both of the affected regions. Despite the
appearance of overall economic progress, the proportion of the population
considered to be extremely poor has increased nationally and in all the regions. It is
therefore understandable that people are eager to take up any opportunity to gain
employment in an area where educational levels are low and unemployment levels
high.
Access to services, such as potable water and adequate sanitation, has improved
nationally and in both the affected regions (Simon, 2014). There is a clear tendency of
having access to and using electricity for lighting. Many distribution lines were observed
during the fieldwork conducted by Simon (2014). However, it seems that many people
still use wood or charcoal for cooking, especially in the Oshikoto Region. The regional
councils are in the process of improving sanitation in the rural areas and pit latrines
have been deployed to many homesteads in both regions. While health indicators,
such as infant mortality rates and staff-patient ratios, are not yet available for 2011,
there appears to be fewer hospital beds available both nationally and regionally,
which indicate a possible decrease in the quality of health provision. HIV prevalence
rates, however, are very well documented at various sites throughout Namibia, many of
which fall within the affected regions for this project and there appears to be a trend
towards decreasing HIV prevalence rates overall.
4.2.3 ARCHAEOLOGY
The baseline description below pertaining to archaeology affected by Portion 2 has
been summarised from the report (see Appendix F) drafted by the archaeologist
Kinahan (2014).
The northern regions of Namibia to be traversed by the transmission line project are not
well known archaeologically. Traditional methods of millet and sorghum cultivation, has
been combined with small scale stock farming to form a secure subsistence lifestyle
that has persevered in the north-central regions of Namibia for approximately one
thousand years.
The proposed transmission line runs through a floodplain north of Ondangwa. An early
Oshindonga settlement is suspected to be located within this floodplain. The site is
marked by a grove of large Ficus sycomorus (Sycamore Fig) trees, and associated
23
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
surface scatter of pottery. The site covers an area of approximately 4 ha which
contains about eight Sycamore Fig trees, most of which have a trunk thickness of 2 – 3
m. Fragments of pottery were found beneath several of the trees. The site is located
less than 50 m from the existing 132 kV transmission line.
Table 3: Socio-economic related sensitivities
ENVIRONMENTAL
FEATURE
DESCRIPTION SENSITIVITY POTENTIAL
IMPACTS
Unemployment The unemployment rate
throughout the project area is
significant.
The local community are in
need of employment
opportunities
Positive impact:
Limited job
opportunities
(mostly unskilled)
Economic Construction workers will settle
temporarily adjacent to the
proposed route.
Informal traders operating in
areas adjacent to the
proposed line can trade.
Positive: informal
economic
benefits.
The construction of the
proposed transmission line will
ensure the security of power
supply to the northern areas of
Namibia.
Lack of power supply security
for the northern regions of
Namibia.
Positive: security
of power supply
Resettlement and
relocation
The proposed transmission line
route runs through the property
(including trees) of some local
residents.
Residents whose property lies
within the servitude of the
transmission line may be
affected and in some cases
may need to be relocated.
Economic and
livelihood losses
for local
residents
Health impacts The transmission lines, which
run past some homesteads,
generate electromagnetic
fields.
Potential health risks
associated with exposure to
electromagnetic fields
generated by the line
Health impacts
HIV/AIDS prevalence in the
region is high. The project
area will experience an influx
of migrant workers during the
construction phase.
Potential increase in HIV/AIDS
infection rate owing to risky
sexual behaviour during
construction phase in the
event of an influx of migrant
labour.
Increased
HIV/AIDS
transmission
during
construction.
Heritage
resources.
Remains of an early village
settlement may be found near
a grove of Sycamore Fig trees
located near the proposed
transmission route.
Unearthed archaeological
remains are prone to
damage if not dealt with
carefully.
Disturbance
and/or
destruction of
heritage
resources.
24
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
5 PUBLIC CONSULTATION
5.1 INTRODUCTION
Public participation forms an important component of an Environmental Impact
Assessment (EIA) as it provides potential interested and affected parties (I&APs) with a
platform whereby they can raise any issues or concerns relevant to the proposed
project. In addition, it also warrants them with an opportunity to comment on all the
documents produced.
The consultation process followed during this EIA process included consultation
meetings in Ruacana, Outapi, Okahao, Ongwediva, Onyaanya and Omuthiya with the
relevant authorities and the public. Thereafter a scoping report containing the issues
identified during the scoping process was circulated to registered I&APs. Hard copies
of the report were sent to the Omusati, Oshana and Oshikoto Regional Council offices
to ensure that those without internet access could access and review the report. The
availability of the report at these locations was then announced over the radio. Lastly
meetings arranged by Urban Dynamics in collaboration with relevant constituency
councillors were held to consult with the people settled along, or adjacent to the
proposed route.
More details on the public participation process and its findings can be viewed in the
Scoping Report for this project.
5.2 THE MEETINGS TO DATE
Meetings were held at Ruacana, Outapi, Okahao, Ongwediva, Onyaanya and
Omuthiya. An overview of these meetings is provided in Table 4 below.
25
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
Table 4: Summary of the meetings conducted
THE MEETING MAIN ISSUES RAISED
Ruacana: The meeting was held on Monday
morning, 10 March 2014 at the Eha Lodge.
No one attended the meeting.
No one attended the meeting, so no issues were discussed.
Outapi: The meeting was held at the Outapi
Town Lodge on the 10 March 2014 in the
afternoon. The representatives included a
teacher, a representative from the Omusati
Regional Council and a warden from the
Ministry of Environment and Tourism.
Soil disturbance was mentioned. The collapse of power
lines due to theft of the members were discussed, which will
require education, by parents, but also from the councillors
to the people. Top-down communications were
emphasised. Impacts on the sense of place were also
mentioned, as well as the potential risk of landmines in the
area. Reliable quantification to accurately measure the
impacts of the project were listed as a concern.
Okahao: the meeting took place at the
Ongozi Lodge on 11 March 2014 in the
morning. It was attended by a
representative from the Otamanzi
Constituency, as well members from the
Okahao Town Council.
The potential impact of the power line on power failures in
town was discussed, including potential power shortages
during construction. The Compensation Policy and fair
compensation was also spoken about, as well as the
potential dangers of living or working near or under the
power line. Comments were made regarding the early
submission date for comments on the 20th of March. The
conservation of trees was mentioned. Another comment
made was that neither the people being affected nor the
Councillors that represent them were present at the
meeting. Again, Top-down communications from the
councillors to traditional authorities were emphasised, as
well as the importance of presenting an apolitical front
when working in the field.
Ongwediva: the public consultation meeting
was held at Hotel Destiny on 11 March 2014
in the afternoon and was attended by
members of the public, students from UNAM
and members of the Oshana Regional
Council.
The length and starting date of the project was discussed,
followed by a discussion on fair compensation and the
correct channels of the dissemination of information. The
ownership of land at Omatando and the consequential
responsibility for compensation was raised as an issue by
members of the public and the Oshana Regional Council.
The use of local labour and local employment creation was
also mentioned. The location of the line, as well as its
impact on the power supply at the north was then
discussed. The impact of migrant workers on HIV/AIDS rates,
as well as marriage stability was furthermore listed as a
concern. Presenting an apolitical front when working in the
field was again emphasised by the NamPower consultant.
Onyaanya: the public consultation meeting
was held at Uukule Senior Secondary School
The impact of the line for power in the North, its location
and the impact on public safety of the line was discussed,
along with the Cabinet’s Compensation Policy and any
26
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
THE MEETING MAIN ISSUES RAISED
on 12 March 2014 in the morning. Only
members from the Ministry of Education
were in attendance.
resultant short term economic boom.
Omuthiya: The final public consultation
meeting was held the afternoon of the 12th
of March as was attended by a
representative of the Omuthiya Town
Council and a representative from the Kind
Nehale Community Conservancy.
Fair compensation for any loss of land, structures or other
assets was again discussed, as well as the inability of rural
households to directly connect to the line. Following the
correct channels of communication was emphasised, as
well as the need to remain apolitical when working in the
field.
5.3 PUBLIC CONCERN
From the comments received during the consultation meetings, a number of key issues.
The key issues identified are listed below in Table 5.
Table 5: Summary of issues
THEME ISSUE
POWER SUPPLY The ability of the line to provide for the future power needs of the northern
regions.
COMPENSATION Compensation for various housing structures as well as trees, e.g. fruit trees,
should be identified.
COMMUNICATION Communication should follow the proper channels from the Councillors to the
Traditional Authorities.
REPRESENTATION All the Interested and Affected Parties, as well as their Representatives need to
be in attendance during consultation.
SAFETY Houses should be located at least 20 m from the line.
Safety measures during construction should be in place.
EMPLOYMENT Local labour should be used to the extent possible.
VEGETATION Loss of vegetation and destruction of natural habitat.
FAMILY HIV/AIDS infection rates and marriage instability
ECONOMY Short term economic boom due to construction workers supporting local
shops.
POLITICS Especially in an election year, remaining apolitical in the field is important.
27
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
5.4 PUBLIC FEEDBACK
The Draft Scoping Report has been circulated to all I&APs for their comment. A two
week commentary period was provided from the 13th to the 27th of June 2014. Hard
copies of the report were sent to the Omusati, Oshana and Oshikoto Regional Council
offices to ensure that community members without internet access could access and
review the report. The availability of the report at these locations was then announced
over the radio by the respective constituency councillors. No comments on the report
were received.
The same process will be followed for the draft Environmental Impact Assessment
Report (EIAR) for Portion 2. The EIAR will be made available for public review for two
weeks. Any comments on the report will be addressed in an Issues and Responses Trail.
28
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
6 IMPACT ASSESSMENT
6.1 THE ‘NO-GO’ ALTERNATIVE
This alternative predicts the future scenario of the site, which would exist in the absence
of any project. This prediction is based on the status quo, as described in the baseline
description (Chapter 4). Should the proposed project not receive Environmental
Clearance from the DEA, the ‘no-go’ alternative will persist.
The current land use in the area consists primarily of communal farming. Communal
farmers are highly dependent on the land for their main livelihoods, which is
subsistence-type crop farming, livestock rearing and the harvesting of wild foods and
fruits. The ‘no-go’ alternative will result in the continuation of these land use activities.
Agriculture provides direct benefits to those who engage in it (farmers receive
payments for selling their livestock and harvest).
If the proposed project is denied Environmental Clearance, the demand for electricity
in the north of Namibia will continue to grow at the current rate. NamPower however,
will be without the means to meet this demand in a secure manner and further strain
would be placed on Nampower’s transmission grid.
In light of these consequences, the ‘no-go’ alternative is not considered desirable.
6.2 IDENTIFICATION OF KEY ISSUES
During the Scoping Stage of this project a screening process was applied whereby all
potentially significant impacts were identified based on an understanding of existing
environmental sensitivities, legal requirements as well as the concerns raised by I&APs.
The process explained in Figure 8 was then followed to screen the various potential
impacts. Two groups of issues were identified:
Issues that could be addressed in the Generic or Specific EMP (see Appendix B1
and B2) i.e. issues for which mitigation and management measures could
already be identified during the Scoping Stage of this EIA process and issues that
do not fall within the scope of this study; and
Issues that needed further specialist investigation i.e. issues for which sufficient
information was not available to propose mitigation measures or assess the
potential impact.
29
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
Based on the screening process outlined above, four areas were identified as those
which required further investigation in order to address the potential impacts.
Specialists were therefore tasked to further investigate these areas:
Impacts on vegetation (Coleen Mannheimer)
Collision of birds with the power lines (John Pallett)
Impacts archaeological sites (John Kinahan)
Socio-economic and visual impact (Ernst Simon)
The findings from these investigations are summarised in Table 6 and form the focus of
the rest of this chapter.
Figure 8: Screening process to determine key issues
Does the issue fall within the scope of the project and the
responsibility of NamPower?
30
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
Table 6: Identification of key impacts during the various phases of the project.
SPECIALIST
STUDY
POTENTIAL IMPACTS OF THE PROJECT
CONSTRUCTION OPERATION AND MAINTENANCE DECOMMISSIONING
Vegetation Damage to vegetation due to vehicle
activity, construction of pylons and
construction laydown.
Damage to vegetation due to vehicle
activity.
Management of vegetation regrowth
Disturbance or destruction of vegetation
Birds Disturbance from road construction and
traffic and habitat destruction
Collisions with power line and stay wires Disturbance from traffic and noise
Archaeology Disturbance or destruction of existing
archaeological sites
Destruction or damage to new
archaeological sites exposed during
construction work.
Disturbance or destruction of existing
archaeological sites
Disturbance or destruction of existing or
new archaeological sites
Socio-
Economic and
Visual impact
Conflict with existing land uses.
Visual impact.
Meeting increased electricity demand
(positive impact).
Conflict with existing land uses.
Visual impact.
Reduction in the availability of electricity
in the northern regions
31
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
6.3 METHODOLOGY EMPLOYED FOR THE IMPACT ASSESSMENT
Each of the identified impacts listed above were assessed with the aim of determining
their significance. The criteria used to describe the significance of a given potential
impact on a particular environmental feature (i.e. vegetation, biodiversity, birds,
archaeology and socio-economic environment) are contained in the Table 7 below:
Table 7: Definitions of each of the criteria used to determine the significance of impacts
DESCRIPTION
Nature Reviews the type of effect that the proposed activity will have on the relevant
component of the environment and includes “what will be affected and how?”
Extent Geographic area. Indicates whether the impact will be within a limited area
(on site where construction is to take place); local (limited to within 15km of the
area); regional (limited to ~100km radius); national (limited to the borders of
Namibia); or international (extending beyond Namibia’s borders).
Duration Whether the impact will be temporary (during construction only), short term (1-5
years), medium term (5-10 years), long term (longer than 10 years, but will cease
after operation) or permanent.
Intensity Establishes whether the magnitude of the impact is destructive or innocuous
and whether or not it exceeds set standards, and is described as none (no
impact); low (where natural/ social environmental functions and processes are
negligibly affected); medium (where the environment continues to function but
in a noticeably modified manner); or high (where environmental functions and
processes are altered such that they temporarily or permanently cease and/or
exceed legal standards/requirements).
Probability Considers the likelihood of the impact occurring and is described as uncertain,
improbable (low likelihood), probable (distinct possibility), highly probable (most
likely) or definite (impact will occur regardless of prevention measures).
Significance Significance is given before and after mitigation. Low if the impact will not have
an influence on the decision or require to be significantly accommodated in
the project design, Medium if the impact could have an influence on the
environment which will require modification of the project design or alternative
mitigation (the route can be used, but with deviations or mitigation) High where
it could have a “no-go” implication regardless of any possible mitigation (an
alternative route should be used).
Status of the impact A statement of whether the impact is positive (a benefit), negative (a cost), or
neutral. Indicate in each case who is likely to benefit and who is likely to bear
the costs of each impact.
Degree of Confidence in
Predictions
Is based on the availability of specialist knowledge and other information.
32
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
Table 8: Definitions of the various significance ratings
SIGNIFICANCE RATING CRITERIA
Low Where the impact will have a negligible influence on the environment and no
modifications or mitigations are necessary for the given development
description. This would be allocated to impacts of any intensity, if at a local
scale/ extent and of temporary duration/time.
Medium Where the impact could have an influence on the environment, which will
require modification of the development design and/or alternative mitigation.
This would be allocated to impacts of medium intensity, locally to regionally,
and in the short term.
High Where the impact could have a significant influence on the environment and,
in the event of a negative impact the activity(ies) causing it, should not be
permitted (i.e. there could be a ‘no-go’ implication for the development,
regardless of any possible mitigation). This would be allocated to impacts of
high intensity, locally for longer than a month, and/or of high magnitude
regionally and beyond.
6.4 ASSESSMENT OF IMPACTS
6.4.1 IMPACT ON VEGETATION
DESCRIPTION
According Mannheimer (2014) several endemic, protected and high use-value tree
species occur along the proposed route. The highest recorded concentrations of the
fruit and fodder trees are located along Section 1 (Figure 9) near the Omatando
Substation. Tree species, which are used for timber and fuel are common along most of
the proposed route and in recent years have been experiencing high levels of loss,
particularly in the densely populated areas, hence cumulative losses are of concern. It
is unlikely that the proposed project will pose a significant threat to endemic and range
restricted tree species.
However, despite the presence of these species the overall impact of the project on
vegetation could be low if sufficient care is taken to prevent unnecessary collateral
damage. This is due to the fact that affected species are sparsely distributed along
most of the proposed route, which has already been adjusted to avoid most significant
clusters of vegetation.
33
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
MITIGATION
The following mitigation measures are recommended:
The layout of substations should avoid trees of high concern and other large
trees where technically possible;
The movement of construction vehicles should be controlled;
Arboricides that may be spread by water to non-target areas should not be
used; and
Large fruit trees should be conserved as far possible regardless of whether
consent is obtained from local people.
MONITORING
The following monitoring measures are recommended:
Individual trees of high concern species close to the route that can be spared
should be mapped, clearly marked and pointed out to construction crews; and
Regular inspection of compliance should be undertaken during construction.
Figure 9: Location of areas of concern for vegetation and birds
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
Table 9: Summary of vegetation impact assessment
POTENTIAL IMPACT STATUS/ NATURE EXTENT DURATION INTENSITY PROBABILITY DEGREE OF
CONFIDENCE
SIGNIFICANCE
PRE-MITIGATION POST-MITIGATION
CONSTRUCTION PHASE
Destruction of
important fruit trees
due to construction
activities
Negative, local populace likely to
lose trees offering high value nutrition
and cash crops, also foods that can
be stored for the dry season.
Local Permanent Medium Probable High Medium Low
Destruction of
important and
protected wood,
timber , fuel and
fodder trees due to
construction activities
Negative, Local populace likely to
lose some of these resources.
However, electrification will also
reduce the pressure on wood for fuel.
Local Long-term Low Definite High Low Low
Destruction of
endemic and range-
restricted plant species
Negative Local/
National
Long-term Low Improbable High Low Low
OPERATION PHASE
Destruction of
important fruit trees
due to operation and
maintenance activities
Negative. Local populace likely to
lose trees offering high value nutrition
and cash crops, also foods that can
be stored for the dry season.
Local Permanent Medium Improbable High Low Low
Destruction of wood,
timber and fuel trees
due to operation and
maintenance activities
Negative. Local populace likely to
lose some of these resources.
However, electrification will also
reduce the pressure on wood for fuel.
Local Long-term Low Improbable High Low Low
6.4.2 IMPACT ON BIRDS
The proposed study area has a relatively high conservation status and biodiversity
value, which is reflected in the approximately 200 bird species that have been
recorded in the overall study area (Pallett, 2014).
The impact on birds relates to bird-powerline interactions (collisions, electrocutions
and nesting) and the disturbance of birds during construction. Electrocutions are
unlikely owing to the design of the V-structure pylons, which are not conducive for
perching and the fact that the monopole structures are located in densely
populated areas rarely frequented by vulnerable bird species. During construction
bird breeding and nesting sites are likely to be disturbed resulting in potential
breeding failure. The impact of greatest concern however, is that of bird collisions
with powerlines.
The intensity of the threat differs from species to species, depending on their present
population and range, and their vulnerability to collisions. Factors influencing the
vulnerability of bird species is the proximity of the powerline to their habitat and
intersections with migratory paths. The blue and wattled cranes are expected to
move north-west and north-east centred on their areas of highest concentration –
the Etosha Pan and Omadhiya Lakes area (Figure 9). Red Data species most likely
to be affected are:
Tawny eagle, bateleur eagle;
Cape vulture, White-backed vulture, lappet-faced vulture, white-headed
vulture;
Secretary bird, marabou stork, saddle-billed stork;
Greater flamingo, lesser flamingo, great white pelican;
Blue crane, wattled crane; and
Kori bustard, Ludwig’s bustard.
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
MITIGATION
The yellow section ‘d–65km’ in Figure 10 carries a moderate risk of collisions
with Red Data birds such as saddle-billed stork, marabou stork and raptors,
with a low possibility of cranes due to the area being moderately settled by
people, and the fact that the power line corridor along part of its length is
close to the B1 road which carries much traffic. However, parts of section ‘d–
65km’ might warrant marking with Double Loop Bird Flight Diverters commonly
referred to as ‘spirals’, for a short distance, such as where the line traverses
oshanas or a clump of relatively tall trees. These segments will be identified
by Mr John Pallett during the construction phase, and BFDs will be installed on
those sections;
The green section in Figure 10 (‘e-120 km’) should be marked with spirals
owing to potential intersection of blue or wattled crane flight paths;
A 10 m interval between devices on any one wire is recommended, with the
devices being staggered so that an oncoming bird is faced with a spiral every
5 m;
Spirals should be coloured either black or white, and the two colours should
alternate along the earth wires; and
A member from the NamPower SHE Section should be actively involved, as
often as practically possible, at the work sites which will help to keep levels of
intentional and accidental disturbance to nesting birds and to other terrestrial
wildlife low.
MONITORING
During standard maintenance operations, any bird mortalities should be
reported to the relevant NamPower staff member and to the coordinators of
the Environmental Information Service (www.the-eis.com) so that the
information is captured and available for future reference;
The condition of the devices should be recorded over time so that any
deterioration is noted;
The environmental officer(s) and any security staff should be briefed to be
alert and take note and record any suspicious activities;
Records should be kept by the relevant staff on how many nests are removed
from which towers, and of what kind of birds (if they can be identified). This
data should be forwarded to the relevant Environmental Officer in
NamPower, as well as to the coordinators of the Environmental Information
Service so the information becomes accessible to the public
Figure 10: Sections along Portion 2 sensitive to bird collisions
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
Table 10: Summary of bird impact assessment
POTENTIAL
IMPACT
STATUS/ NATURE EXTENT DURATION INTENSITY PROBABILITY DEGREE OF
CONFIDENCE
SIGNIFICANCE
PRE-MITIGATION POST-MITIGATION
CONSTRUCTION PHASE
Disturbance to
birds, habitat
modification/
destruction and
poaching.
Red-listed species are disturbed in their
feeding/ roosting/ breeding areas – even
though the habitat has been man-
modified. Poaching of birds. This may
result in a loss in biodiversity.
Local/
National
Temporary Low Probable Medium Low Low
OPERATION PHASE
Mortality of birds
due to collisions
with power line.
Loss of Birds (some of which are Red Data
Species) due to collisions with power line.
This may result in a loss in biodiversity.
Local/
National
Long-term/
Permanent
High Certain High High Medium
Mortality of birds
due to
electrocutions
Loss of Birds (some of which are Red Data
Species) due to electrocutions when
perched on towers. This may result in a loss
in biodiversity.
Local/
National
Permanent Low Improbable Medium Low Low
Removal of bird
nests on towers
Negative Local Long-term Low Definite High Low Low
IMPACT SIGNIFICANCE
Trade-offs pertaining to environmental opportunities and constraints are an
inevitable consequence of many development activities. The impact pertaining to
the mortality of birds due to collisions with power lines is unavoidable. Significant
time and effort has been exerted in terms of devising and choosing the best
practicable route alternatives. Mitigation measures have been devised and put in
place to further reduce the impact significance. However, despite these efforts the
post-mitigation impact significance will only be reduced (from high) to medium (not
low). This is owing to the fact that the proposed route intersects the flight paths of
critically endangered bird species and a high risk that collisions will occur (even if the
rate of collisions is unknown). The implementation of the proposed project, given
the significance of this impact, is only justified in light of the significant need to
increase the capacity of NamPower to supply electricity to the northern regions of
Namibia. The rate of increase in the demand for electricity has been faster in recent
years in keeping with the rate of urbanisation in the northern regions of Namibia.
Failure to implement the proposed project would have significant consequences for
future development in the north of Namibia and increased electricity demands
would destabilise sections of the national grid.
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
6.4.3 IMPACT ON THE SOCIO-ECONOMIC ENVIRONMENT
DESCRIPTION
According to Simon (2014) the proposed 400 kV transmission line from Omatando
Substation to Oshivelo Substation will partly be routed through a densely populated
communal farming area, resulting in the need to relocate some homesteads to the
outside of the servitude. A total of 43 households will be affected (Simon, 2014). The
main impacts of this line will therefore be on the communal farmers who are highly
dependent on the land for their main livelihoods, which are crop farming, livestock
rearing and the harvesting of wild foods and fruits.
The proposed route runs through 254 seasonally cultivated fields over a distance of
174 km. It is likely that a total of 165 fruit-bearing trees will need to be cut down in
preparation for constructing the transmission line. These trees are used as food, and
the making of traditional juice and alcoholic drinks. The fruit from these trees
become particularly important during harsh conditions when it supplements the
meagre food sources of some local households. Fields are generally rudimentarily
fenced and sometimes fenced with stock fences. Construction equipment will need
to pass through a total of 50 fences (Simon, 2014) and through crop fields. Provision
for access needs to be made for the maintenance of the line. Construction
equipment in the fields could result in soil compaction in the fields. During operation,
farming activities like ploughing and harvesting can be affected by the towers and
guy ropes.
Haul vehicles, earthmoving equipment, cranes, stringing equipment and chain saws
used during construction and operations produce noise and dust that may impact
adjacent land owners. Although the construction of a transmission line is a fairly
specialised operation, there are some tasks that require largely unskilled manual
labour such as the digging of foundation pits. This could bring some much needed
employment to the local community.
During the construction phase of the project, large construction machinery will move
and operate close to homesteads. This presents a safety risk for residents, especially
children who may venture too close in an attempt to observe these large machines
operate. During operation, risks are related to the collapse of towers or lines which
may cause electrocution or damage to farm infrastructure.
With construction workers moving into the area from elsewhere, it is likely that risky
sexual behaviour along the proposed route will increase during the construction
period. This could increase the spread of the HIV/AIDS.
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
MITIGATION/ENHANCEMENT
The social impact will be mitigated through compensation as per the
Compensation Policy Guidelines for Communal Land (2008) of the Namibian
Government. According to this policy, farmers must be compensated fairly
for the huts/buildings to be moved as well as for fences, kraals and other farm
infrastructure. This is to enable farmers to re-create their homestead outside
the servitude, but still in the same field. The Policy also makes provision for the
compensation for the loss of trees which are mainly used for making juice and
traditional alcoholic drinks but also for food in times of adversity or as pleasant
tasting fruits. Although compensation cannot replace the loss of these trees,
it does compensate people for the loss they would suffer as a result of the loss
of such trees. The impact will be mitigated through compensation, which will
be calculated and assessed in accordance with the Compensation Policy
Guidelines for Communal land (see Relocation and Compensation Plan as
Appendix to the Specific EMP (Appendix B2).
The placement of pylons should be planned in such a way that they fall
outside or along the edge of existing crop fields. This would lessen the impact
on farming operations during the operation phase of the line as well as limit
the impact of excavations on farming operations during the construction
phase. Excess soil from excavations should not be placed on crop fields, but
should rather be dispersed within and adjacent to the pylon footprint after
backfilling is completed.
A total of 50 fences, most built of poles and branches and some of poles and
strained wire must be crossed for the construction road. To mitigate this
impact, it is important that the survey team establish contact with each of
these farmers to determine the most suitable method of dealing with this
issue. In the cases where proper pole and strained wire fences exist, proper
gates must be installed as is normally done in the commercial farming areas.
In the case of pole and branch fences, it may be possible to open these
fences and leave it open for the duration of the construction period and then
to close it again after construction. But this will only be practical if
construction takes place outside the farming season. This needs to be
negotiated with the affected households. It is therefore very important that
construction is completed before the ploughing season is to commence.
Construction vehicles will need to move across the fields during the erection
of the towers and the stringing of the lines. To mitigate the compaction of soil
it is suggested that these movements be limited and that alternative existing
roads be used to reach the pylons. The area is traversed by a number of
tracks and it is possible to utilise these tracks to reach the tower sites rather
than to drive through the fields.
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
Although little can be done to force the contractor to make use of local
labour, it is suggested that the contractor be sensitised about this issue and
requested to utilise local labour where possible and as and when required.
This should be made clear at the first site meeting after appointment. Local
leaders could help with recruitment and the senior headman should be
approached from the outset of the project to work out a methodology
according to which the contractor can carry out recruitment. If local people
are recruited, a key principle must be to make this as inclusive as possible and
recruit people living along the line equally as they are available.
To curb the potential impact of increased HIV infections, the matter should be
addressed at two levels. Firstly, all construction workers should be
encouraged to participate in an HIV/AIDS prevention programme and be
made aware of the dangers of unprotected sexual relations with the local
population. All staff should be subjected to the training prior to the
commencement of construction and once a month thereafter. The risks of
multiple and concurrent sexual partnerships should be included in the
prevention programme. Lastly, the traditional leaders of the area should also
be sensitised about these risks and also encouraged to take part in the
prevention programme. They would then be required to share this with the
local community.
Summary
The information from the social impact assessment is summarised in the Table 11
below.
Table 11: Summary of the potential impacts of the proposed power line project on the surrounding socio-economic environment
POTENTIAL IMPACT STATUS/ NATURE EXTENT DURATION INTENSITY PROBABILITY DEGREE OF
CONFIDENCE
SIGNIFICANCE
PRE-MITIGATION POST-MITIGATION
CONSTRUCTION PHASE
Impact on farming
operations
Negative Local Medium
term
Low Highly
probable
High Low Low
Dust and noise
impacts
Negative Local Long-term Low Highly
probable
High Low Low
Relocation of
homesteads
Negative Local Permanent Medium Definite High Medium Low
Loss of fruit-bearing
trees and associated
livelihood impact
Negative Local Permanent Medium Definite High Medium Low
Employment creation Positive Local Short term Low Probable High Low Low
Safety during
construction
Negative Local Short term Medium Probable High Medium Low
Spread of HIV/AIDS Negative Local Medium
term
Medium Highly
probable
High High Medium
OPERATION PHASE
Impact on farming
operations
Negative Local Long-term Low Highly
probable
High Medium Low
6.4.4 DESTRUCTION OR DAMAGE TO ARCHAEOLOGICAL SITES
According to Kinahan (2014) there is a possibility that part of the proposed route
traverses an area suspected to be the site of an early Oshindonga village settlement
(see Figure 11). Based on the presence of a large clump of potentially very old
Sycamore fig trees as well as some pottery in the topsoil this settlement, it is
suspected that a royal homestead was located within this site. Early historical
accounts mention these homesteads but none have been found so far. The site is
represented by a floodplain north of Ondangwa, which covers an area of
approximately 4 ha, which contains about eight Sycamore Fig trees, most of which
have a trunk width of 2 – 3 m. Hence there is a possibility that archaeological
remains might be disturbed or destroyed during the construction of the transmission
line near this site.
MITIGATION
The abovementioned site should be avoided as far as practicably possible in
terms of laydown areas and vehicular traffic. In addition, the archaeological
heritage data presented in the Archaeology Impact Study (see Appendix F)
should be integrated with the Specific EMP (Appendix B2) and follow-up
regarding this data should be carried out during the construction phase.
Figure 11: Archaeological site of concern
Table 12: Summary of archaeology impact assessment
POTENTIAL
IMPACT
STATUS/ NATURE EXTENT DURATION INTENSITY PROBABILITY DEGREE OF
CONFIDENCE
SIGNIFICANCE
PRE-MITIGATION POST-MITIGATION
CONSTRUCTION PHASE
Disturbance and/or
destruction of
heritage resources.
Remains of an early
Oshindonga settlement are
located along the proposed
route.
Local and
landscape
level
Permanent Low-High (Based
on proximity to
sites)
Possible Medium Medium Low
OPERATION PHASE
Disturbance and/or
destruction of
heritage resources.
Remains of an early
Oshindonga settlement are
located along the proposed
route.
Local and
landscape
level
Permanent Low-High (Based
on proximity to
sites)
Possible Medium Medium Low
DECOMMISSIONING PHASE
Disturbance and/or
destruction of
heritage resources.
Remains of an early
Oshindonga settlement are
located along the proposed
route.
Local and
landscape
level
Permanent Low-High (Based
on proximity to
sites)
Possible Medium Medium Low
6.4.5 ASSESSMENT OF CUMULATIVE IMPACTS
Cumulative impacts are impacts that result from the incremental impact of a
proposed activity on a common resource when added to the impacts of other past,
present or reasonably foreseeable future activities. Cumulative impacts can occur
from the collective impacts of individual minor actions over a period of time and
can include both direct and indirect impacts.
Power lines existing in the area include many lengths of 33kV and 132kV lines running
between Oshivelo and Ruacana, and northwards from Oshakati to Oshikango, and
a 66kV line running between Oshivelo and Oshakati. The addition of another power
line in an area that is frequented by a number of sensitive bird species may
cumulatively add to the existing impact that power lines have, particularly in terms
of collisions. It must also be remembered that all of the Red Data species affected
by the proposed line are also threatened by other factors such as human
disturbance, declining food and habitat availability. The cumulative effect of the
power line is thus significant for all of the Red Data birds.
Another area of potential concern is the cumulative effect associated with the
removal of tree species. Overharvesting due to population pressure for building
materials and other resources, such as palm wine, has already caused large scale
losses of palm trees and trees used for wooden tools and utensils, fuel and timber.
Large fruit trees, in the northern regions of Namibia, are of such high value that they
have often been retained, even within cultivated fields, but they are species that
are by nature sparsely distributed. The fact that wood for houses, fences, utensils,
tools and fuel often comes from species that are common, but not formally
protected (such as Colophospermeum mopane, Combretum collinum, Terminalia
sericea, T. prunioides, among others) means that their destruction should also be
minimised as far as possible, particularly the larger varieties.
MITIGATION
Bird mortalities due to collisions with powerlines are a major concern globally
and nationally. To reduce the additional threat posed by this power line on
Red Data species, such as the blue and wattled crane, the mitigation
measures prescribed in this report should strictly be adhered to. Furthermore,
it is important that members of the construction and maintenance teams are
made aware of the risks posed to birds by powerlines and that an overall
conscientiousness for the protection of wildlife is encouraged.
It will not be possible to avoid damage to tree species, some of which will be
common along the route. However, because there is already a high level of
loss, particularly in the densely populated areas, cumulative losses are of
concern so unnecessary collateral damage should be avoided and large
specimens of all tree species should be conserved as far as possible.
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
7 CONCLUSIONS AND RECOMMENDATIONS
7.1 CONCLUSIONS
The four key biophysical and socio-economic impacts related to the proposed
construction and operation of a new transmission line from the Omatando
Substation to the Oshivelo Substation can be summarised as follows:
Impact on vegetation: Several high use value (fruit, fodder, fuel and timber)
tree species as well as a few endemic and range restricted plant species
occur within the project area. Overall, vegetation losses are expected to be
low and hence the significance of the impact as well, owing to adjustments
to the transmission line route, which avoid significant clusters of vegetation.
Impact on birds: The project area supports a relatively high diversity of
species. The main impact pertaining to birds associated with the construction
and operation of the power line in this area is related to potential collisions
once the line is operational. The transmission line route has been adjusted to
move as far away from the areas supporting a relatively high diversity of bird
species, as possible. Mitigation measures (including fitting the proposed
transmission line with Bird Flight Diverters among others) have been included
in the Specific EMP to address bird-powerline interactions. Despite these
measures the significance of these impacts, overall, has only been reduced
to a medium level. However, the significance of the direct and indirect
economic benefits of the proposed project justifies the medium risk posed to
critically endangered species (specifically the blue and wattled crane).
Socio-economic impacts: The proposed route goes through densely
populated areas. In order to avoid impacts on people and their property the
transmission line route was adjusted to avoid as many properties as possible.
A total of 43 households will however still be affected by the proposed route.
Relocation will need to take place and property (homesteads and trees) will
be affected. A total of 165 fruit-baring trees will need to be removed.
However, compensation for the loss of trees, and other immovable property
will be carried out in accordance with a Relocation and Compensation Plan
drafted in line with the Compensation Policy Guidelines for Communal Land.
As a result the significance of these socio-economic impacts has been
reduced to a low level.
Impact on archaeology: One potentially sensitive archaeological site, a
floodplain covering an area of 4 ha, is located north of Ondangwa. This site is
to be avoided as far as practicably possible. A “chance find” procedure is
set out in EMP for use during the construction phase, to cater for the discovery
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
of new sites and hence the significance of this impact has been reduced to a
low level.
7.2 RECOMMENDATIONS
In light of what can be concluded regarding the potential impacts associated with
the proposed transmission line, NamPower will be able to reduce the significance of
most of these to acceptable levels if they implement the mitigation measures
outlined in both the General and Specific EMP (which includes the Relocation and
Compensation Plan). It is therefore important the EMP is audited to ensure
compliance and that monitoring takes place as outlined therein otherwise the
impacts identified will remain unacceptable.
It is therefore recommended that the proposed project receive Environmental
Clearance, provided that the generic EMP and the specific EMP are
implemented.
EIA for the Proposed 400 kV Transmission Line From Omatando to Oshivelo (Portion 2)
Draft EIA Report for Client Review
September 2014
8 REFERENCES
Mendelsohn, J., el Obeid, S. & Roberts, C., 2000. A Profile of North-Central Namibia.
Windhoek: Gamsberg Macmillan Publishers.
Mendelsohn, J., Jarvis, A., Roberts, C. & Robertson, T., 2009. Atlas of Namibia. 3rd ed.
Cape Town: Sunbird Publishers.
Ramsar Convention on Wetlands, 2012. The Annotated Ramsar List: Namibia.
[Online]
Available at: http://www.ramsar.org/cda/en/ramsar-pubs-notes-anno-list-
16497/main/ramsar/1-30-168%5E16497_4000_0__
[Accessed 25 March 2014].