environmental & social management system …
TRANSCRIPT
Ethiopian Electric Utility
i
The Federal Democratic Republic of Ethiopia
Ethiopian Electrification Program (ELEAP)
ENVIRONMENTAL & SOCIAL
MANAGEMENT SYSTEM
GUIDELINE (ESMSG)
FINAL
JUNE 2018
FOR
ADDIS ABABA, ETHIOPIA
Ethiopian Electric Utility
i
Environmental and Social Management System Guideline (ESMSG)
for ELEAP
TABLE OF CONTENTS
TABLE OF CONTENTS .................................................................................................................. I
LIST OF TABLES .......................................................................................................................... II
LIST OF FIGURES ........................................................................................................................ II
LIST OF BOXES ............................................................................................................................ III
LIST OF ANNEXES ...................................................................................................................... III
ACRONYMS .................................................................................................................................. IV
EXECUTIVE SUMMARY ............................................................................................................ VI
1. INTRODUCTION ................................................................................................................... 1
1.1 BACKGROUND .............................................................................................................................. 1
1.2 PURPOSE OF THE ESMS GUIDELINE ............................................................................................. 2
1.3 APPROACHES TO THE ESMSG STUDY .......................................................................................... 2
1.4 PROGRAM PROPONENT AND OPERATOR ....................................................................................... 2
1.5 PUBLIC DISCLOSURE AND CONSULTATION ................................................................................... 3
2. ETHIOPIA ELECTRIFICATION PROGRAM DESCRIPTION ......................................................................... 3
2.1 PFORR PROGRAM SCOPE .............................................................................................................. 5
2.2 EXCLUDED ACTIVITIES. ................................................................................................................ 8
2.3 DISBURSEMENT LINKED INDICATORS AND VERIFICATION PROTOCOLS ........................................ 8
3. ORGANIZATIONAL RESPONSIBILITIES FOR ELEAP IMPLEMENTATION ............. 8
3.1 FEDERAL LEVEL KEY INSTITUTIONS FOR ELEAP IMPLEMENTATION ........................................... 9
3.2 REGIONAL, ZONAL AND WOREDA LEVELS KEY ACTORS FOR ELEAP ......................................... 15
4. ESMS POLICY AND LEGAL FRAMEWORK ..................................................................... 18
4.1 BACKGROUND ............................................................................................................................ 18
4.2 ETHIOPIA’S RELEVANT LEGAL FRAMEWORK, POLICIES, STRATEGIES, AND REGULATIONS ....... 18
5. ESMS PROCESSES: PREPARATION& IMPLEMENTATION ......................................... 24
5.1 GENERAL.................................................................................................................................... 24
5.2 KEY ISSUES AND RESPONSIBILITIES FOR THE SCREENING AND APPRAISAL PROCESSES................ 25
5.3 PROCEDURES AND STEPS FOR ENVIRONMENTAL AND SOCIAL MANAGEMENT SCREENING .......... 25
6. GRIVANCE REDRESS MECHANISM .................................................................................. 32
6.1 ELEAP GRIEVANCE REDRESS PROCEDURE ................................................................................ 33
6.2 KEY CONSIDERATIONS FOR ELEAP GRM PROCEDURE ............................................................. 37
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
ii
7. ELEAP ENVIRONMENTAL AND SOCIAL BENEFITS AND IMPACT .......................... 38
7.1 POSITIVE ENVIRONMENTAL AND SOCIAL IMPACTS OF ELEAP .................................................. 39
7.2 ADVERSE ENVIRONMENTAL AND SOCIAL IMPACTS .................................................................... 41
8. SAFETY MANAGEMENT ....................................................................................................... 51
8.1 USE OF PPE AND SAFETY PROTECTION MATERIAL ...................................................................... 54
8.2 INDICATIVE SAFETY MONITORING AND REPORTING .................................................................. 56
8.3 NOTIFICATION ............................................................................................................................ 58
9. TRAINING AND CAPACITY BUILDING ............................................................................. 59
9.1 OVERVIEW ................................................................................................................................. 59
9.2 ESMSG TRAINING .................................................................................................................. 61
9.3 TECHNICAL AND FINANCIAL ASSISTANCE .................................................................................. 62
10. MONITORING, ANNUAL AUDIT AND REPORTING OF ESMSG IMPLEMENTATION
................................................................................................................................................ 64
10.1 MONITORING .............................................................................................................................. 64
10.2 ANNUAL AUDIT .......................................................................................................................... 65
10.3 REPORTING ................................................................................................................................. 66
11. ANNEXES ................................................................................................................................. 68
LIST OF TABLES
TABLE 1. PROGRAM RESULTS CHAIN............................................................................................................................. 3 TABLE 2: SOME OF THE LEGAL REQUIREMENTS & COMPLIANCE MEASURES APPLICABLE TO ELEAP ........................ 21 TABLE 3. OUTLINE OF ROLES AND RESPONSIBILITIES FOR THE ESMSG ...................................................................... 25 TABLE 4: ELEAP GRM’S ROLES, RESPONSIBILITIES, IMPLEMENTATION MECHANISM, AND TIMEFRAME ..................... 35 TABLE 5: ENVIRONMENTAL AND SOCIAL BENEFITS OF ELEAP .................................................................................. 39
LIST OF FIGURES
FIGURE 2: ENVIRONMENT AND CLIMATE CHANGE DIRECTORATE UNDER MOWIE ORGANOGRAM ............................. 11 FIGURE 3: ORGANIGRAM OF EEU’S EHSQ DIRECTORATE .......................................................................................... 12 FIGURE 4: ELEAP E&S SCREENING AND MANAGEMENT ACTIVITY AND RESPONSIBILITIES FLOWCHART............................................... 28 FIGURE 5: PROJECT SCREENING IMPLEMENTATION CYCLE UNDER THE ELEAP .......................................................... 31 FIGURE 6: ESMS GRIEVANCE AND COMPLAINT MANAGEMENT MECHANISM ............................................................. 38 FIGURE 7: TYPICAL PPE AND SAFETY PROTECTION MATERIALS .................................................................................. 55 FIGURE 8: INDICATIVE REPORTING FLOW CHART FOR DETAIL WRITTEN INCIDENT REPORT .......................................... 57 FIGURE 9: INDICATIVE FLOW CHART FOR THE NOTIFICATION OF INCIDENTS ................................................................ 58
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
iii
LIST OF BOXES
BOX 1. THE ELECTRIC ACCIDENTS HAZARDS .............................................................................................................. 52 BOX 2. GENERAL SAFETY PRACTICES .......................................................................................................................... 53 BOX 3. GENERAL SAFETY RESPONSIBILITY APPLICABLE FOR ELEAP WHICH IS ADHERED BY EEU ............................. 54 BOX 4. PERSONAL PROTECTIVE EQUIPMENT (PPE) ..................................................................................................... 55 BOX 5. POINTS ON ACCIDENT REPORTS, RECORDS, AND INVESTIGATION ..................................................................... 59 BOX 6. POSSIBLE AGENDA FOR A 2-DAY WORKSHOP INTRODUCING THE ESMSG ..................................................... 61 BOX 7. INDICATIVE TRAINING TOPICS AND SCHEDULE ................................................................................................ 62 BOX 8. INTEGRATION OF ENVIRONMENTAL MANAGEMENT INTO DEVELOPMENT PLANNING ...................................... 62
LIST OF ANNEXES
ANNEX 1: SCREENING FORM ....................................................................................................................................... 68 ANNEX 2: ENVIRONMENTAL AND SOCIAL EXCLUSION LIST ........................................................................................ 73 ANNEX 3: GUIDELINE FOR THE PREPARATION OF SITE SPECIFIC OF ESMP ................................................................... 74 ANNEX 4: SUGGESTED ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN (ESMP) TEMPLATE FOR A SUBPROJECT 76 ANNEX 5: EXAMPLE OF ENVIRONMENTAL CONTRACT CLAUSES ................................................................................. 77 ANNEX 6: BUILDING CODE OF STANDARDS ................................................................................................................ 81 ANNEX 7: FORMAT OF AN ANNUAL/QUARTERLY ENVIRONMENTAL REPORT ............................................................... 85 ANNEX 8: INDICATIVE ENVIRONMENTAL AND SOCIAL MANAGEMENT MEASURES ..................................................... 86 ANNEX 9: INDICATIVE ESMS IMPACT MITIGATION AND MONITORING CHECKLISTS .................................................. 88 ANNEX 10: PREDICTION AND EVALUATION OF POTENTIAL ENVIRONMENTAL IMPACTS .............................................. 98 ANNEX 11: DETAILS OF PERSONAL PROTECTION EQUIPMENT’S ................................................................................. 104 ANNEX 12: SAMPLE COMPLAINT FORM ..................................................................................................................... 108 ANNEX 13: SAFETY CHECKLIST ................................................................................................................................. 109
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
iv
ACRONYMS
APA Annual Performance Assessment IPS Industrial Projects Services
BOLSA Bureau of Labor and Social Affair km2 Square kilometer
CSA Central Statistical Agency KWp Kilo Watt Peak
CRMP Cultural Resources Management Plan LED Light-emitting diode
DBE Development Bank of Ethiopia Masl Meters above sea level
DLI Disbursement Linked Indicators MOFEC Ministry of Finance and Economic
Cooperation
DOE Directorate of Electrification MC Minimum Condition
EA Environmental Assessment MOLSA Ministry of Labor and Social Affair
ECCEP Ethiopia Clean Cooking Energy
Program
MoEFCC Ministry of Environment, Forest and
Climate Change
EEP Ethiopian Electric Power MoWIE Ministry of Water, Irrigation and
Electricity
EEU Ethiopian Electric Utility MSE Micro and Small Enterprises
EEPCo Ethiopian Electric Power Corporation NGO Nongovernmental organization
EHS Environment, Social, Health, and
Safety
PAPs Project affected Peoples
EMP Environmental Management Program PCRs
PCB
Physical Cultural Resources
Printed Circuit Board
ENREP Ethiopia- Electricity Network
Reinforcement and Expansion Project
PPE Personal Protective Equipment
EOREP Ethiopia Off Grid Renewable Energy
Program
PSE Private Sector Enterprises
EPA Environmental Protection Authority RSG Resettlement System Guideline
ESIA Environmental & Social Impact
Assessment
RAP Resettlement Action Plan
ESMP Environmental and Social
Management Plan
REFA Regional Environment and Forest
Authority
ESMS Environmental and Social
Management Systems
SHS Solar Home System
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
v
ESMSG Environmental and Social
Management System Guideline
SNNPRS Southern Nations, Nationalities and
Peoples ‘Regional State
FDRE The Federal Democratic Republic of
Ethiopia
SMP Safety Management Plan
GOE Government of Ethiopia SPMG Solar PV Multi-grid
GHC Grievance Hearing Committee TOR Terms of Reference
GRS Grievance Redress Service TOT Training of Trainer
GTP Growth and Transformation Plan TA Technical Assistance
HH Household ToR Terms of Reference
HoH Head of Household WB World Bank
IDA International Development Association WME Water, Mines and Energy
ILO International Labor Organization WMEB Water, Mines and Energy Bureau
IPF Investment Project Finance WMP Waste Management Plan
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
vi
EXECUTIVE SUMMARY
Introduction
The Ethiopian Government has completed its first phase of Growth and Transformation Plan (GTP-I)
(2010/11–2014/15), which set a long-term goal for Ethiopia to become a middle-income country by 2025.
The second phase of the Growth and Transformation Plan (GTP-II) was developed for the period of 2015-
2020 that includes a plan to reach eight (8) million customers mainly households for electricity connections
by 2020 and is currently under implementation. In November 2017, the Government launched the National
Electrification Program (NEP) for the achievement of universal access by 2025 (goal set in the GTP). The
NEP transforms the Government vision into action, with targets and timetables, as well as an investment
prospectus and syndication scenario.
The World Bank Ethiopia Electrification Program (ELEAP) Program for Results (PfoR) will directly
support the GoE’s National Electrification Program in scaling-up electricity connections through
densification activities, as well as increasing access to off-grid technologies. Strong emphasis is also placed
on strengthening the capacity of the sector institutions to achieve the targets linked with grid electrification
and off-grid, particularly on planning, technical implementation, financial management, procurement,
governance, social and environmental management, gender, skill development and financial viability.
One of the effectiveness conditions (dated covenant) for the Ethiopia Electrification Program (ELEAP)
Program for Results Financing, regards the adoption by the EEU Board of the Environmental and Social
Management System Guidelines (ESMSG). This ESMSG document was prepared on the basis of the
ELEAP-Environmental and Social System Assessment (ESSA), drafted by a joint team of environment and
social development specialists from the World Bank and EHS team of EEU during the preparatory work
for ELEAP. The ESSA was prepared through a comprehensive review of systems and procedures were
adopted by Ministry of Water Irrigation and Electricity (MoWIE), and the Ethiopian Electric Utility (EEU)
at the national regional, zonal and woreda levels; and other relevant sectoral institutions responsible for
addressing social, environmental and safety issues associated with ELEAP. The review process followed
an in-depth analysis and scrutiny on how environmental and social issues should assessed, integrated and
operationalized into ELEAP , which was then used as a significant input to the preparation of this ESMSG
by EEU.
This ESMSG document is planned to be used by all EEU’s regional and district/woreda offices, with the
support of the all Regional Water and Energy Bureaus, to ensure that all environmental, social and safety
issues during implementation of ELEAP are adequately addressed, and that relevant capacity and training
needs are established to effectively implement ESSA recommendations.
The objective of the ESMSG is to provide an overarching document which clarifies the organizational
arrangements and criteria to be applied during the preparation and implementation of project specific
instruments, including Environmental and Social Management Plans (ESMP), Environmental and Social
Impact Assessment (ESIA), Safety Management Plan (SMP), A/RAP, etc. to manage anticipated risks and
impacts associated with the Program.
The main purposes of the ESMSG are to:
• Establish clear procedures and methodologies for the environmental and social assessment, review,
approval, implementation, monitoring and reporting requirements;
• Identify impacts and recommend measures to prevent, minimize, mitigate or compensate
anticipated adverse impacts as well as to enhance potential benefits of ELEAP.
• Specify appropriate roles and responsibilities for managing and monitoring environmental and
social concerns related to ELEAP construction works;
• Provide practical information resources for implementing the ESMS Guidelines.
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
vii
For ELEAP, the Government of Ethiopia procedures require that the ESMSG is prepared and publicly
disclosed prior to commencement of each program activities. This allows the public and other stakeholders
to comment on the possible environmental and social impacts of the Program, particularly measures and
plans to prevent or mitigate any adverse environmental and social impacts. Thus, the final ESMSG
document will be disclosed through the EEU website, and in public locations at Regional and District
offices.
Ethiopian Electrification Program Description
The Government’s National Electrification Program (NEP) aims to achieve universal electrification by
2025. The NEP will be carried out in phases, with the immediate focus being on the early years of the
Program (2018–2023). The phased focus under the NEP also allows for enhanced technical planning and
coordinated fund mobilization. The NEP is organized into three pillars addressing the dominant challenges
of the sector:
Pillar 1 - On-grid electrification. The core focus of the NEP in the early years will be around on-grid
access provision, taking advantage of renewable energy based supply. The execution will be carried out
through Densification and Expansion:
Pillar 2 - Off-grid service provisioning. This Pillar targets communities where the grid would not reach
within the next 5–10 years (pre-electrification) as well as communities for which the grid is not the least-
cost solution (permanent off-grid). This include Stand-alone solar system and Mini-grids.
Pillar 3 - Sector capacity and institutional reform. This pillar focuses on providing the necessary
technical assistance and capacity-building support required by the sector institutions to achieve the
ambitious targets set under Pillars 1 and 2 by directly supporting the achievement of outcomes from the
first two pillars. This includes a comprehensive program with a focus on utility reform and skill
development in the following areas: (a) planning capabilities; (b) technical and commercial capacities; (c)
financial management (FM) functions; (d) streamlining procurement; (e) transparency, accountability, and
governance; (f) safeguarding the environment and society; (g) gender equity; and (h) long-term sector
financial viability.
The Program explicitly excludes possible high-risk activities and Category “A” types of activities.
Investments, which according to the WB Operational Policy for Environmental Assessment (OP 4.01) are
classified in Category A are explicitly excluded from the Program. These “…are projects which are likely
to have significant adverse environmental impacts that are sensitive, diverse, or unprecedented. These
impacts may affect an area broader than the sites or facilities subject to physical works”. Category A
projects are not supported by PforR operations and EEU cannot use ELEAP funding for these types of
investments.
While the scope and scale of works under the Program are not expected to cause significant adverse
environment and social impacts, the national EIA procedures require that all investments are screened for
negative impacts that are sensitive, diverse, or unprecedented on the environment and/or affected people.
Sitting, design, construction, and implementation of all physical works must consider safety risks and
develop a management plan to integrate measures to ensure that activities result in minimum or no safety
risks or impacts. In addition to screening for significant negative impacts, the following works will be
ineligible for financing under the ELEAP:
• Distribution and last mile connection stringing route outside of existing rights-of-way;
• Infrastructure works that require significant resettlement of people (more than 200 people, project-
specific);
• Activities that would significantly convert natural habitats or significantly alter potentially
important biodiversity and/or cultural resource areas;
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
viii
• Block access to and/or use of water points etc.;
• Significant impact on physical cultural resources (archaeological sites; religious monuments or
structures; natural sites with cultural values; cemeteries; graveyards; graves; and other sites of
significance);
• Have risk on and/or exclude some members of community, including vulnerable groups,
underserved peoples and ethnic minorities;
• Can instigate social tension or conflict and Likely to adversely create or exacerbate conflict within
communities;
• Contravene international and regional conventions on environmental and social issues.
Institutional and Implementation Arrangements and Responsibilities
MoWIE and EEU will be responsible for achieving the targets of ELEAP. Under MoWIE, the Directorate
of Electrification (DoE) which will be established is expected be responsible for Program oversight and
monitoring progress. The DoE will rely on other sector agencies to facilitate successful implementation of
the goals and objectives of the ELEAP. In addition, a Steering Committee will provide high-level strategic
direction and policy guidance to the DoE. The main implementing agency for majority of the ELEAP
activities will be the EEU.
With regards to environmental and social management, the federal, regional, and woreda levels relevant
government institutions are responsible to take key roles in supporting environmental, social and safety
management activities of the Program to ensure sound implementation. As stated above, MoWIE as an
umbrella institution for the proposed ELEAP is responsible to oversee and ensure sustainable management
during the implementation for both on grid and off grid components. EEU is the direct implementer for on-
grid and off-grid components. The Environment and Climate Change Directorate (ECCD) under the
MoWIE and the Environment and Social, Health and Safety and Quality and Process Excellence (EHS,
Q&PE) directorate under EEU will have major roles and responsibilities to guarantee sound implementation
of environmental, social and safety management during implementation of ELEAP.
Both EEU and MoWIE are required to comply with the wider environmental and sustainability objectives
of the Constitution and other sectoral policies. In addition, it is quite evident that the various stakeholders
will play also direct or indirect roles in the implementation environmental, social and safety management.
The different key actors expected to play a role during implementation of the proposed programs are the
following:
• Ministry of Water, Irrigation and Electricity (MoWIE)
• Ethiopian Electric Utility (EEU)
• Ethiopia Energy Authority (EEA)
• Ministry of Environment, Forest and Climate Change (MoEFCC)
• Ministry of Labor and Social Affairs (MoLSA)
• Relevant Regional Governments Bureaus (RWMEB, BoLSA, BLAU, REPFA)
• Zonal and woreda level Water, Mines and Energy Offices
The importance of integration and coordination of these key actors and timely follow-up coordination and
efficiency is significantly acknowledged for sound implementation of ELEAP.
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
ix
ESMS Policy and Legal Framework
The effects of development projects on the biophysical and social environment should be assessed to ensure
that all development program and project implementations, as much as possible, must be environmental
friendly and comply with the relevant environmental policies, guidelines and procedures. In this regards,
policies, legislative frameworks, guidelines and standards have been developed by governmental and non-
governmental organizations to contribute for the enhancement of sustainable development.
In order to assess the adequacy of Ethiopia’s legal and regulatory framework, relevant laws and institutions
for environmental and social impact assessment and management are described, along with the roles and
responsibilities of institutions involved in the environmental and social assessment and management
processes.
Ethiopia’s Relevant Legal Frameworks, Policies and Strategies
The effects of development projects on the environment should be assessed to ensure that projects, as much
as possible, are in harmony with the environment. In one way or another, this ultimately contributes to
ensure sustainable development. In this regard, policies, legislative frameworks, guidelines and standards
have been developed by governmental and non-governmental organizations to contribute for the
enhancement of sustainable development. Relevant legal and administrative frameworks, policies and
strategies of the Government of Ethiopia have been discussed; these include:
• The Constitution of the FDRE
• Ethiopia Growth and Transformation Plan (GTP) II
• Environment Policy of Ethiopia
• Energy Policy of Ethiopia
• Land Tenure Policy of Ethiopia
• National Policy of Women
• National Health Policy (1998)
• Social Protection Policy of Ethiopia
• Ethiopia Electric Utility’s Environmental and Social Policy and Procedures
• And various Program related strategies and guidelines
ESMS Processes: Preparation and Implementation
The ESMSG document sets out the steps and procedures for screening of program activities as to
environmental and social management requirements and identifies the responsibilities of implementing
parties in the program ESMS. It covers detail discussions and guidance on environmental and social issues
that will be addressed, steps to be taken for managing environmental, social and safety risks; various
elements of the ESMSG which include environmental screening and assessment processes, application for
environmental authorization, and guideline for ESMP; and anticipated program impacts and the respective
measure to ensure compliance of national and international policies and standards.
This ESMS will be applied during ELEAP construction and operation phases to warrant the required
Environmental, Social, Health, and Safety (ESHS) issues are considered and recommended measures are
applied over the program implementation period. These include:
• Assesses the program benefits and compare it with the environmental, social, health and safety
risks associated with the program in a manner consistent with the Program for Results Financing.
• All the projects under the program are screened for environmental and social safeguards as per the
preset criteria and checklist before commencement of construction activities and request approval
from the relevant environmental institutions at all level.
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
x
• Adequate staffing with environmental and social expertise at EEU’s national and regional levels
bureau with specific responsibilities for addressing ELEAP environmental, social and safety
matters.
• Sufficient and applicable technical capacity and facilities for EHS management that will be in place
within EEU-EHS unit over the program period.
• Sound implementation of ESMSG and RSG, as required.
• An annual environmental, social and safety (EHS) audit and quarterly EHS performance review.
Procedures and Steps for Environmental and Social Management Screening
The overriding guiding principle to the implementation of ELEAP is through participatory and community
demand driven approach. The environmental, social and safety management and screening process will be
attained through the following procedures and steps:
Given the scale and nature of anticipated construction activities of ELEAP, an Environmental, and Social
Impact Assessment (ESIA) might not be necessary. However, using the screening checklist (Annex 1),
program’s activities are required to pass through environmental screening to identify the level of impact
and respective measures aimed at avoiding, offsetting, and/or minimizing environmental, social and safety
impacts to levels that are acceptable.
The overall guiding principles of the proposed ELEAP implementations are the following, but not limited
to:
• Conforming to the national and regional environmental assessment requirements and standards;
• Ensuring no harm or minimum impact to the nearby social and biophysical environment that can
be mitigated easily by employing best practices methods;
• Proposed activities under ELEAP will undergo for environmental and social impacts screening;
• Ensuring sound implementation of the recommended mitigation measures;
• The planning and implementation process will integrate ESMP or other relevant environmental,
social and safety management instruments, as required;
• Promoting adequate and timely technical support to MoWIE, EEU at National, Regional and
Woreda levels; and
• Promoting supervision and monitoring of implementation of program activities by EEU, MoWIE,
and the respective regional and woreda level Bureaus and offices, with the support from
environment protection and Labor and Social services institutions.
• Ensuring on time quarterly performance review and annual audit.
Based on the Ethiopian Environmental legislation the program might not require full ESIA and all activities
under the program should avoid sensitive areas and take steps to ensure that projects stay within Schedule
II of national environmental assessment category or world bank environmental assessment category
“category B” (It must be noted that any projects or activities that will be categorized as Category ‘A’ will
not be financed by the ELEAP). Besides, every potential project that will be funded under this program is
subject for environmental and social management screening to confirm the anticipated adverse impacts and
classify the subprojects based on their level of impacts, and thereby propose preparation of the required
safeguards instruments.
The environmental and social management screening process will be done on potential activities under
ELEAP. The dedicated Environmental, Social, Health and Safety (ESHS) specialists at national and
regional EEU offices with regular support from regional energy and environment bureaus are responsible
to conduct environmental and social management screening before the commencement of the program
construction activities. The EHS specialists will use the environmental and social screening form developed
and enclosed in this ESMSG.
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
xi
The steps and procedures described below are the corner stones for ensuring environmental and social
impacts are adequately addressed over the program implementation period.
• Step One: Project preparation and Consultation
• Step Two: Desk appraisal
• Step Three: Environmental and Social Safeguards screening
• Step Four: Submission of screening report to MoWIE or REFCC
• Step Five: Review of screening report and appraisal by MoWIE or REFCC
• Step Six: Approval of projects by MoWIE, REFCC
• Steps Seven: Submission of approval decision report to EEU, including the need for preparation
and approval of other EHS instruments (ESMP, A/RAP, SMP, …), as applicable
• Steps Eight: Implementation of EHS management plans
• Steps Nine: Supervision and Monitoring
• Steps Ten: Annual EHS auditing and quarterly EHS performance review
Strengthen the Grievance Redress Mechanism
Over ELEAP implementation period, beneficiaries may have complaints related to the program
implementation activities. The GRM committee will be established at all levels to receive, review and
address complaints in line with loss of livelihood, income or assets, dissatisfaction of the services, etc. a
detailed GRM procedure in line with EEU’s customer service manual is developed for the off-grid
component and updated for the on-grid component followed by orientation for implementers.
The proposed ESMSG Grievance/ Grievance include:
Amicable solution, mediation using customary rules. Complaints. Appeal to court. As long as one of
ELEAP Program activities (construction works) entails resettlement and/or compensation, the Program will
establish a register of resettlement/compensation related grievances and disputes. The existence and
conditions of access to grievances/ complaints register (where, when, how) will be widely disseminated
within the interested area of the program activities sites as part of the consultation undertaken for the
investment (construction works).
First Instance – Amicable Settlement
People may prefer such matters to be handled by a “first instance” mechanism, on the model of traditional
dispute-resolution mechanisms. In such compensation and resettlement operations, it usually appears that
many grievances have roots in misunderstandings, or result from conflicts with neighbors, which can
usually be solved through adequate mediation using customary rules.
Appeal to Court
Whenever misunderstandings and disputes arise between the principle parties, the preferred means of
settling disputes is through arbitration (Proclamation No. 455/2005). The number and composition of the
arbitration tribunal may be determined by the concerned parties.
Courts of law shall be considered as a last resort option, which in principle should only be used where first
instance amicable mechanisms have failed to settle the grievance/dispute. However, the Constitution allows
any aggrieved person the right of access to a court of law.
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
xii
Monitoring, Evaluation and Learning
As experiences in Ethiopia entails, the view towards complaint handling as a means for improving overall
administrative and service delivery is not yet well developed i.e. complaint handling is largely being viewed
as an end by itself. Besides, record keeping and data management is not fully developed and that it is not
yet used as a monitoring and evaluation tool. Moreover, even though if record keeping stands to be better,
a fully disaggregated data into all-important indicators are not yet visible. The ELEAP GRM guideline will
attempt to help to avert this constrained experience and will utilize GRM as a learning and management
tool.
ELEAP Environmental and Social Benefits and Adverse Impact
The environmental and social benefits are derived from access to electricity services for household and
business energy sources. These benefits derived from the program is basically to the community members
who are residing within and nearby the project area and other beneficiaries of the proposed Program and to
the nation in general. An increased distribution of electricity to the project area will minimize the pressure
on the use of fuel wood that is rampant in the area and is ultimately would help to conserve the fragile and
diminishing forest cover of the country by providing an alternative source of energy.
The potential adverse environmental, social and safety risks and impacts of the Program are associated with
program activities, including construction and rehabilitation of medium and low-voltage distribution lines
and installation of MV-LV transformers, construction of hybrid mini grid, and disposal and replacement of
spent lead-acid batteries from solar home systems. Whereas, the potential adverse social impacts are likely
to be associated with land acquisition for mini grid and acquisition of way leaves (rights of way) for LV
distribution lines.
The ESMG identifies the key measures to be taken for improved environmental and social due diligence in
the Program and is intended to help the Government and implementing agencies in overcoming gaps related
to environment, social, and safety aspects of the program and improvements of the implementing agencies
system on safeguards managements.
The following table indicate the summary of potential environmental and social benefits and impacts drawn
from the implementation of the proposed ELEAP.
Environmental and Social
Benefits
Environmental and Social Adverse Impacts and Risks
• Provision of on-grid
electricity
• Power generation using
renewable energy sources
(mini-grids):
• Provision of electricity to
households and businesses
• Employment opportunities
• Improvement in social
facility services (schools,
health facilities, and
government offices):
• Reduce Women’s Burden:
• Loss and Destruction of Vegetation cover/crop and Habitat:
• Clearing and loss of existing vegetation cover which may contribute for
loss of plant cover and biodiversity;
• Disturbance of top soil that promotes of soil erosion;
• Plant material removed from site causes GHG emissions and air
pollution if burned;
• Air quality aesthetics and visual related impacts- visual intrusion on the
landscape;
• Water Resources;
• Storage and Management of solid waste;
• Risks from poor maintenance of solar home systems: battery
replacement;
• Fugitive Dust and Noise;
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
xiii
Environmental and Social
Benefits
Environmental and Social Adverse Impacts and Risks
• Chemical impact;
• Soil Erosion;
• Heat or Light Reflection;
• Biodiversity;
• Occupational health and safety (OHS);
• Cultural Heritage;
• Polychlorinated biphenyls (PCBs) Impacts;
• Health Effects of Electromagnetic Fields (EMF) Impacts;
• Fire risk;
• Risks from provision of electricity to households and businesses:
• Risks from land and RoW acquisition:
• Risk that vulnerable groups will not share equitably in project benefits
provision of electricity to communities:
• Risks related to Labor Influx.
Training and Capacity Building
During the Program implementation period, substantive capacity building and technical assistance program
shall be designed and implemented on environmental and social safeguards and safety assessment and
management practices through provisioning and improving of human and financial resources, provision of
trainings and other logistics facilities.
ELEAP will further established and strengthen the capacity building architecture to ensure sound technical
capacity on environment, social and safety matters at all levels of EEU and MoWIE through adopting a
systematic, cascading and coordinated vision and approach. The continual and rapid expansion of
electrification in Ethiopia will require extensive capacity-building support not only for the electricity sector
institutions, the MoWIE and EEU, but also for the broader sector participants such as academic institutions
(universities and vocational training centers) and community and other local stakeholders
The training and capacity building activities proposed to support ESMSG implementation are:
• General training and awareness/sensitization provided for staffs from MoWIE, EEU and the Regional
level offices), REFAs and community members, and relevant line ministries and regional offices.
• In depth training for relevant Regional Energy and EEU bureaus responsible for the project and EHS
staffs on implementation of the ESMSG including all aspects of environmental, social and safety
management, ESMP, SMP, A/RAP, public consultation, and integration of environmental, social and
safety management plans into development planning;
• Technical and financial assistance to each EEU-EHS units at national and regional level that
participate in program’s EHS implementation to:
o Produce a Screening Report, an ESMP and other safeguard instruments TOR, an
Environmental and Social Management Plan (ESMP), Safety Management Plan (SMP) or
abbreviated Resettlement Action Plan (ARAP); and
o Establish and support operation of systems for monitoring and reporting on Environmental
and Social Management Plan (ESMP), Safety Management Plan (SMP) or
abbreviated/Resettlement Action Plan (A/RAP) implementation.
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
xiv
• Appointment of one Environmental and Social Specialist and one Occupational Health and Safety
specialist in each regional EEU offices who are responsible for overall ESMSG implementation.
The program is designed to further establish and strengthen the capacity building architecture to ensure
sound technical capacity on environment, social and safety matters at all levels of EEU and MoWIE through
adopting a systematic, cascading and coordinated vision and approach.
Monitoring and Annual Auditing and Quarterly Performance Review of ESMSG Implementation
An annual independent audit on ESMSG implementation will be carried out by an independent auditor,
based on the internal annual review prepared by EEU (and the EEU quarterly reviews). The audited report
will be submitted to MoWIE for verification of results through the Central Statistical Agency (CSA), and
disbursements under ELEAP based on results. The independent auditor will also assess how and to what
extent that the environmental and social considerations are being incorporated into EEU planning process.
The Quarterly performance review will be conducted by EEU regularly. The annual audit and quarterly
performance review will also include the achievement of ESMG, ESMP, SMP, A/RAP preparation, and
implementation, as required.
Ethiopian Electric Utility
1
1. INTRODUCTION
1.1 Background
The Ethiopian Government has completed its first phase of Growth and Transformation Plan (GTP-I)
(2010/11–2014/15), which set a long-term goal for Ethiopia to become a middle-income country by 2025.
The second phase of the Growth and Transformation Plan (GTP-II) was developed for the period of 2015-
2020 that includes a plan to reach eight (8) million customers mainly households for electricity connections
by 2020 and is currently under implementation. In November 2017, the Government launched the National
Electrification Program (NEP) for the achievement of universal access by 2025 (goal set in the GTP). The
NEP transforms the Government vision into action, with targets and timetables, as well as an investment
prospectus and syndication scenario.
The World Bank Ethiopia Electrification Program (ELEAP) Program for Results (PfoR) will directly support
the GoE’s National Electrification Program in scaling-up electricity connections through densification
activities, as well as increasing access to off-grid technologies. Strong emphasis is also placed on
strengthening the capacity of the sector institutions to achieve the targets linked with grid electrification and
off-grid, particularly on planning, technical implementation, financial management, procurement,
governance, social and environmental management, gender, skill development and financial viability.
The Program Development Objective (PDO) is to increase access to electricity in Ethiopia and to
enhance institutional capacity for planning and implementation of the Government’s electrification
program. The PforR instrument innovatively links the disbursement of funds directly to the delivery of
defined results and strengthens government program systems.
ELEAP will support the implementation of Ethiopian electrification program and its implementation plan in
the following three key results areas:
a) Results Area 1: Increase access to electricity connections to households in areas covered by the
grid. The key intermediate indicator would be the number of customers connected to the network. In
addition, increased number of kilometers of low-voltage distribution lines erected would also be
tracked.
b) Results Area 2 Increase access to off-grid electricity. The ongoing private sector led market
development activities off-grid service delivery will be continued. NEP also envisions scaling-up
public sector led off-grid programs. This includes mini-grids and stand-alone solar systems for
remote areas of the country where neither the grid, nor the private sector distribution channels will
reach in the near-term. While the comprehensive off-grid strategy is under development, the
proposed ELEAP will support pilot-scale off-grid service delivery activities, i.e., off-grid
electrification of up to 5 communities using renewable energy mini-grids (solar or hybrid) and stand-
alone solar systems for households in these communities.
c) Results Area 3: Sector capacity and Institutional reform. The key indicators for this result area will
be determined through the technical, fiduciary and Environmental and Social system assessments to
be prepared as part of the program preparation. This could include targets related to improving the
technical capacity and the financial sustainability of the sector utilities.
For the design of ELEAP, an Environmental and Social System Assessment (ESSA) was carried out by a
team of environment and social development specialists from the World Bank to assess country systems for
environmental and social management. During ESSA preparation, the team conducted a comprehensive
review of systems and procedures of the Ethiopian Electric Utility (EEU) at national level and regional, zonal
and woreda levels EEU and other relevant sectoral institutions who are responsible for environmental, social
and safety matters to address social, environmental and safety issues associated with ELEAP.
The ESSA preparation involved significant consultations at all levels, assessment of existing system and site
visits to environmentally and socially significant areas and activities throughout the Program implementation
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
2
regions. This process was pass-through an in-depth analysis and revisiting how environmental and social
issues were assessed, integrated and operationalized into the ELEAP and all the information has contributed
a significant input to the preparation of this ESMSG.
This ESMSG document is planned to be used by EEU’s regional and district/woreda bureaus and offices to
ensure that all environmental, social and safety issues are adequately addressed and that the relevant capacity
and training needs are established to effectively implement the recommended measures, and supported by
relevant sector institutions, including MoWIE and Regional Energy Bureaus.
1.2 Purpose of the ESMS Guideline
The objective of the ELEAP PforR ESMS Guideline is to provide an overarching document which clarifies
the organizational arrangements and criteria to be applied during the preparation and implementation of
project specific Environmental and Social Management Plans (ESMP).
The main purposes of the ESMSG are to:
• Establish clear procedures and methodologies for the environmental and social assessment, review,
approval and implementation of construction works to be financed by the program;
• Identify impacts and respective recommended measures to prevent, minimize, mitigate, or compensate
anticipated adverse impacts as well as to enhance potential benefits of the ELEAP;
• Specify appropriate roles and responsibilities, and outline the necessary reporting procedures, for
managing and monitoring environmental and social concerns related to the ELEAP construction
works;
• Provide practical information resources for implementing the ESMS Guideline.
Given the nature and type of program activities, it is identified that the majority of the ELEAP PforR program
activities are unlikely to result in any significant environmental, social or safety negative impacts. This is
because the projects comprise electricity connections to households in areas in proximity of the existing grid
(within 3km) where other low-voltage distribution lines erection are tracked, and new connections can be
accommodated within existing land take and will have no additional impacts on surrounding land use or
users.
1.3 Approaches to the ESMSG Study
This ESMSG will be based upon the ESSA study outcomes and incorporates information from the national,
MoWIE, EEU’s policy and legal reviews; environmental, social and socio-economic baseline; and impact
assessment and mitigation / monitoring recommendations from the related study. Guidance on producing
ESMSG has been based on in-country and World Bank guidance.
1.4 Program Proponent and Operator
EEU is the Project Proponent (implementing agency) for ELEAP and has worked with the World Bank for
the design of ELEAP. EEU will select subprojects for implementation and establish an implementation
program based on the recommendations made in ELEAP. EEU will operate and maintain the densification
program and supply power to consumers.
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
3
1.5 Public Disclosure and Consultation
Public consultation will be an integral part of the process throughout the planning and execution of a project.
The EHS department under EEU at national level and Regional EEU EHS focal points will interact closely
with the national and regional offices and bureaus over the program implementation period to ensure
participation of all parties. Although the major responsibility of ELEAP implementation lies with EEU, it
may be entrusted to a reputed institution at all levels enjoying the confidence of the people in the area.
For Programs such as the ELEAP, the Government of Ethiopia procedures require that the ESSA, ESMSG
and other instruments are prepared and publicly disclosed prior to appraisal and commencement of each
program activities. Further, the adoption by the EEU Board of this document constitutes a dated legal
covenant under ELEAP. Public disclosure allows the public and other stakeholders to comment on the
possible environmental and social impacts of the project, particularly measures and plans to prevent or
mitigate any adverse environmental and social impacts. In this regard, the draft ESSA has been disclosed
both in-country and on World Bank’s external website and comments received have been incorporated in the
final ELEAP ESSA version After adoption by the EEU Board, these ESMS guidelines will also be publicly
disclosed by the EEU and MoWIE through their website and in public locations, i.e., in Regional and District
offices. Likewise, subsequent EMPs and other instruments will be disclosed in the same manner prior to start
of the respective construction works.
2. ETHIOPIA ELECTRIFICATION PROGRAM DESCRIPTION
The Program development objective (PDO) is to increase access to electricity in Ethiopia and to enhance
institutional capacity for planning and implementation of the Government’s electrification program.
The following outcome indicators will be used to measure achievement of the PDO:
• PDO Indicator 1: Number of people provided with on-grid electricity services
• PDO Indicator 2: Number of people provided with off-grid electricity services
• PDO Indicator 3: Improved planning and implementation capacity of the electricity sector
The Program includes three Results Areas: (1) increase access to on-grid electricity in areas covered by the
national grid; (2) increase access to off-grid electricity; and (3) strengthen sector capacity and institutional
reform. The Results Chain (Table 1) includes a description of activities within each of the Results Areas
which are necessary for achieving the PDO. Indicators and outcomes within each of the Results Areas have
been defined to monitor the progress of the Program. A subset of these indicators will be used as
Disbursement Linked Indicators (DLIs,) bolded in Table 1 of the Program; the remaining will be monitored
through the Program Results Framework.
Table 1. Program Results Chain
Results
Area
Activities Intermediate
Indicators/Outputs
Outcomes
Results
Area 1:
Increase
access to
on-grid
electricity in
areas
covered by
• Service drops, including
meters, and ready-boards
• LV and MV lines
constructed or rehabilitated
• Cumulative number of
residential grid electricity
connections under the Program
[DLI1]
• Cumulative number of non-
residential grid connections
under the Program
• Increased number of
people provided with
on-grid electricity
services
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
4
Results
Area
Activities Intermediate
Indicators/Outputs
Outcomes
the power
grid • Households connected to the
grid under the Program that are
female-headed
Results
Area 2:
Increase
access to
off-grid
electricity
• Preparation of feasibility
studies and implementation
plans for mini-grids and SAS
• Installation of renewable
energy/hybrid mini-grids
• Installment of SAS
• Households provided with
electricity through mini-grids
and SAS
• Cumulative number of mini-
grids installed [DLI2a]
• Cumulative capacity of
renewable energy installed
through mini-grid projects
under the Program
• Cumulative number of stand-
alone solar PV systems installed
[DLI2b]
• Increased number of
people provided with
off-grid electricity
services
Results
Area 3:
Strengthen
sector
capacity and
institutional
reform
• Staff training and annual
capacity-building activities
• Preparation of studies on:
o Affordable customer
connection policy
o Low-cost
electrification/technical
standards
o Long-term financial
sustainability
o Power system
rehabilitation
• Establishment of minimum
entry conditions for
procurement
• Preparation of off-grid
strategy
• Establishment of a gender
and citizen engagement (CE)
framework
• DoE is established and has put
in place integrated M&E
system, that is maintained
throughout the Program [DLI3]
• Finalization and
implementation of affordable
connections study and long-
term financial sustainability
study
• Annual connection rollout plans
adopted by EEU [DLI4]
• Audited financial statements
(compliant with International
Financial Reporting Standards
[IFRS]) submitted [DLI5a]
• Acceptable performance of
procurement processes and
(internal and external) audit
system maintained [DLI5b]
• Reports on fraud and corruption
(F&C) verified by the Federal
Ethics and Anti-Corruption
Commission (FEACC [DLI5c]
• Gender and CE work program
approved in first year of
Program and Gender and CE
reports updated annually;
[DLI6a]
• Strengthen sector
institutional capacity
• Improved cost-
effectiveness of
Program
• Strengthen sector
planning capacity
• Improve gender and
CE systems
• Strengthen
safeguards system
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
5
Results
Area
Activities Intermediate
Indicators/Outputs
Outcomes
• Annual customer satisfaction in
key aspects of the Program was
equal or higher than last year’s,
as per annual surveys (between
July 8, 2019 through July 7,
2022) [DLI6b]
• Women in STEM: Increase
women’s employment at EEU
• ESMS established and
operational according to the
adopted guidelines [DLI7]
• Cumulative number of staff in
EEU and MoWIE receiving
training under the Program
2.1 PforR Program Scope
ELEAP is designed to directly support the implementation of the National Electrification Program, across its
three pillars. It will support significant scale-up in electricity connections under Pillar 1 (densification), pilot
programs for off-grid service delivery under Pillar 2, and support Pillar 3 (sector capacity and institutional
reform), an essential precondition for success of the activities under the first two pillars (Figure 1). ELEAP
will finance the activities of the NEP’s on a countrywide eligibility basis.
Figure 1. Program Boundaries for the Proposed ELEAP
Source: NEP-IRM.
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
6
Activities under Results Area 1: Increase access to on-grid electricity in areas covered by the power grid
through large scale and programmatic densification of electricity connections, including installation of LV
extensions, service drops, metering and limited installations or rehabilitation of MV lines. While Ethiopia’s
geospatial least-cost access expansion plan is under development,1 substantial progress can be made on an
immediate basis by implementing densification activities in areas where the network can support new
connections (a significant waiting list already exists). Densification of consumer connections in areas that
have been recently electrified through the UEAP will enable electrification at a rapid pace, subject to
improvements in sector capacity (as described in paragraph 38 below). Large-scale and programmatic
densification activities will result in improved cost-efficiency of the electrification program and significantly
increased economic benefits in the targeted areas. Activities for densification connections will mostly include
installation of short LV extensions, service drops, and metering, while a few connections might require
limited MV extensions. As part of the NEP, the proposed ELEAP will directly support 1,080,000 new
connections.
Activities under Results Area 2: Increase access to off-grid electricity through provision of support for
pilot-scale off-grid service delivery activities, including off -grid electrification of communities using
renewable energy mini-grids (such as solar and hybrid), as well as installation of SAS for beneficiaries in
these communities. The ongoing private sector-led market development activities and off-grid service
delivery will be continued through the DBE credit facilities under the ENREP. The NEP also envisions
scaling up public sector-led off-grid programs. This includes mini-grids and SAS for remote areas of the
country where neither the grid nor the private sector distribution channels will reach in the near term. While
the comprehensive off-grid strategy of the NEP is under development, the proposed ELEAP will support
pilot-scale off-grid service delivery activities, that is, off-grid electrification of up to five communities using
renewable energy mini-grids (solar or hybrid) and 50,000 SAS for households in these communities.
Activities under Results Area 3: Strengthen sector capacity and institutional reform. Support under
ELEAP will address the key elements of Pillar 3 of the NEP, which focuses on supporting sector capacity
and institutional reform in the Government's electrification program, specifically improving the capacity of
EEU and MoWIE to plan and implement the Program through, inter alia, (a) preparation of annual connection
and roll-out plans; (b) establishment of the DoE and an integrated M&E system; (c) production of
International Financial Reporting Standards Compliant Audited Financial Statements (without disclaimer
opinion); (d) performance improvements of procurement processes; (e) production of reports on F&C
allegations; (f) preparation of reports on CE and gender; (g) improvement of customer satisfaction; and (h)
establishment and maintenance of an ESMS.
Program beneficiaries. The beneficiaries of the Program will include the following:
(a) Households. Given that the majority of the unelectrified households in Ethiopia are in rural areas,
the Program activities are substantially geared toward being ‘pro-poor’. Access to electricity
contributes to an improvement in the quality of life by enabling newly connected consumers to
undertake productive and income-generating activities (less time spent on fetching traditional sources
of energy and clean water) and enhanced access to information/communication (through phone,
radio, television, and so on). Empirical evidence also points to health benefits owing to the reduction
of indoor air pollution due to reduced kerosene consumption.
1 The World Bank and other DPs are supporting the GoE with technical assistance activities to establish a data-driven
planning framework through the development of a nationwide geospatial least-cost plan, which will further detail cost
of connection and guide the optimal strategy for sequencing the rollout of on- and off-grid connections to achieve
universal access.
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
7
(b) Social institutions. Improvements in the quality of public service delivery are expected through
increased electricity connections, especially of public facilities such as schools; clinics; hospitals (for
example, for cold chain, vaccine and medicine refrigeration, lighting, sterilization); and water
pumping stations (for example, for safe drinking water) used by poor and vulnerable households.
(c) Productive enterprises. Improved access to electricity supply will contribute to increased
productivity and income of enterprises (particularly for micro/small/medium enterprises) and will
assist them in reducing their dependency on expensive diesel generation that has a substantially
higher per unit cost. In addition, increased access to electricity can boost productivity and reduce
sales and equipment losses.
(d) Electricity sector institutions. The sector institutions, especially the MoWIE and EEU, are expected
to benefit from the strengthening of planning and implementation capacity of the NEP, which could
translate into improved institutional performance as well as cost-effectiveness, efficiency,
transparency, and accountability of the sector.
(e) Gender-differentiated benefits. Providing rural households, social services, and enterprises with
improved electricity services has the potential to promote gender equality, create employment and
business opportunities for women, and improve development outcomes regarding, for example,
education. Under the Program, gender-differentiated considerations will be mainstreamed as part of
the utility operations.
Notes for ELEAP investments:
a) The Program explicitly excludes possible high-risk activities and Category “A” types of activities.
Investments, which according to the WB Operational Manual for Environmental Assessment (OP 4.01)
are classified in Category A are explicitly excluded from the Program. These “…are projects which are
likely to have significant adverse environmental impacts that are sensitive, diverse, or unprecedented.
These impacts may affect and area broader than the sites or facilities subject to physical works”.
Category A projects are not supported by PforR operations and EEU cannot use the ELEAP grants for
these types investments.
b) While the scope and scale of works under the Program are not expected to cause significant
adverse environment and social impacts, the national EIA procedures require that all investments
are screened for negative impacts that are sensitive, diverse, or unprecedented on the environment and/or
affected people.
c) Sitting, design, construction, and implementation of all physical works must consider safety risks
and develop a management plan to integrate measures to make them activities result minimum or
no safety risks or impacts.
d) In addition to screening for significant negative impacts, the following works will be ineligible for
financing under the ELEAP:
• Distribution line route outside of existing rights-of-way;
• Infrastructure works that require significant resettlement of people (more than 200 people,
project-specific);
• Activities that would significantly convert natural habitats or significantly alter potentially
important biodiversity and/or cultural resource areas;
• Block access to and/or use of water points etc.;
• Significant impact on physical cultural resources (archaeological sites; religious monuments or
structures; natural sites with cultural values; cemeteries; graveyards; graves; and other sites of
significance);
• Have risk on and/or exclude some members of community, including vulnerable groups,
underserved peoples and ethnic minorities;
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
8
• Can instigate social tension or conflict and Likely to adversely create or exacerbate conflict
within communities;
• Contravene international and regional conventions on environmental and social issues.
2.2 Excluded activities.
The program will not support activities that are likely to have significant adverse impacts that are sensitive,
diverse or unprecedented on the environment and/or affected people (see Annex 2).
2.3 Disbursement Linked Indicators and Verification Protocols
Disbursement under ELEAP will be governed by a set of seven DLIs. The selection of the DLIs was guided
by the following: (a) consideration of how the selected DLIs would directly provide the incentives for
meeting Program goals and (b) feasibility of measuring, monitoring, and verifying the Disbursement Linked
Results (DLRs). The choice of DLIs is based on the most relevant output indicators, which signal progress
toward achieving the planned outcomes under the Program. Regarding Environmental and Social
Management for the program, the following DLIs are dedicated
(a) DLI 3: Strengthen sector institutional capacity. This DLI relates to Results Area 3 and will be
triggered upon establishment of the DoE within the MoWIE to ensure coordination of activities under
the NEP and putting in place an integrated M&E system that is maintained throughout the Program.
The DoE will include staff with technical, procurement, FM, safeguards, and M&E capacity.
(b) DLI 6: Improve gender and CE systems. This DLI encompasses efforts to mainstream CE and
gender activities at the EEU. The EEU will publish an annual report summarizing CE and gender
activities each year for the duration of the proposed ELEAP. This DLI is related to Results Area 3 and
will be triggered upon (i) the design and adoption of CE and gender work program (as defined in the
POM) in the first year and publication of a report on CE engagement and gender activities for
subsequent years of the Program and (ii) the annual customer satisfaction survey showing equal or
increased customer satisfaction in key aspects (service, grievance, transparency, dialogue, or others,
and so on) in the later years of the Program.
(c) DLI 7: Strengthen safeguards systems. This DLI responds to the critical need to strengthen capacity
to supervise and monitor the social and environmental impacts of the Program. The existing ESMS in
the EEU needs to be improved and required to be implemented at the regional and national levels.
During the first year of implementation, the EEU will establish the ESMS, including
recruitment/assignment of safeguards personnel at the regional and national levels and the adoption of
safeguards guidelines. In subsequent years, the MoWIE and EEU will ensure adequate implementation
of the ESMS, focusing on the adequate screening of Program activities, the implementation of
recommended safeguards measures, and the functioning of the complaint-handling mechanism.
3. ORGANIZATIONAL RESPONSIBILITIES FOR ELEAP IMPLEMENTATION
Governmental institutions at federal, regional, and woreda levels are responsible to take key roles on
supporting, directing, and monitoring of the proposed program to ensure sound implementation of the
required environmental, social and safety management practices during the implementation of ELEAP.
MoWIE as an umbrella institution for the ELEAP is responsible to oversee and ensure sustainable
management during the implementation for both on grid and off grid components; whereas, EEU is direct
implementer mainly for on-grid and off-grid components Both EEU and MoWIE are required to comply with
the wider environmental and sustainability objectives of the Constitution and other sectoral policies. In
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
9
addition, it is quite evident that the various stakeholders will play also direct or indirect roles in the
implementation of national energy programs, as well as the required safeguards policies. The degree of
influence of the various actors to bring change and ensure the sustainable implementation of the proposed
energy programs do vary both in terms of temporal and spatial dimensions. The different key actors expected
during implementation of the proposed programs are the following:
• Ministry of Water, Irrigation and Electricity (MoWIE)
• Ethiopian Electric Utility (EEU)
• Ethiopia Energy Authority(EEA)
• Ministry of Environment, Forest and Climate Change (MoEFCC)
• Ministry of Labor and Social Affairs (MoLSA)
• Relevant Regional Governments Bureaus (RWMEB, BoLSA, BLAU, REPFA)
• Zonal and woreda level Water, Mines and Energy Offices
The importance of integration and coordination of these key actors and timely follow-up coordination and
efficiency is significantly acknowledged for sound implementation of the new Ethiopia Electrification
Program (ELEAP). The roles and responsibilities of the above institutions and their performance and capacity
related to implementation of activities under the program, particularly on the management of environmental,
social and safety matters are discussed below. This section summarizes the institutional roles and
responsibilities of relevant organizations on managing environmental, social and safety matters for effective
implementation of program’s environmental and social management system as defined in various rules,
procedures, and implementation guidelines.
The existing institutional mechanisms and frameworks that are being used for the implementation of other
ongoing energy sector programs are the basis for ESMSG. The following sections describe the relevant
organizational responsibilities and their capacity towards ensuring sound implementation of ELEAP. As
stated above, EEU will be the main driver of implementation of the Ethiopian Electrification Program
(ELEAP)-PforR and it is responsible for the overall program design and implementations at all levels.
Regarding the implementations of environmental and social safeguards, in addition to EEU and MoWIE,
various parties are engaged directly or indirectly for review and clearance of the environmental, social and
safety management, oversee and support the overall Program component activities to be in an
environmentally friendly and socially acceptable.
The Environment and Climate Change Directorate (ECCD) under the MoWIE and the Environment and
Social, Health and Safety (EHS) department under EEU will take the major role and responsibilities to
guarantee sound implementation of environmental, social and safety management during implementation of
the ELEAP. The key directorate and departments under different institutions and their roles, responsibilities
on the implementation of environmental, social and safety management are discussed as follows.
3.1 Federal level Key Institutions for ELEAP implementation
3.1.1 Ministry of Water, Irrigation and Electricity (MoWIE)
The Ministry of Water, Irrigation and Electricity (MoWIE) is a sectoral institution for Water, Irrigation and
Electricity development programs. Under the MoWIE, the DoE will be responsible for Program oversight
and monitoring progress. The DoE will rely on other sector agencies, including the EEU, to facilitate
successful implementation of the goals and objectives of the ELEAP. In addition, a Steering Committee will
provide high-level strategic direction and policy guidance to the DoE. The Ministry of Environment, Forest
and Climate Change (MoEFCC) delegated MoWIE, dated December 2010, for review and clearance of
environmental and social safeguards instruments, which are prepared for the energy and water sector
development Programs. This delegation provided power to enforce the national proclamations and
regulation related to environmental and social safeguards at all phases of Program implementation.
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
10
Delegated authority: The Federal Environment Protection Agency has delegated authority to sector
institutions to ensure implementation of EIAs in their sector and to undertake EIA reviews. For instance,
MoWIE is responsible for ensuring that an EIA is undertaken on water and energy Programs and to review
the EIA. This delegation has been communicated to sector ministries through an official letter sent by the
Federal EPA dated December 2010.
Vis-à-vis the existing capacity of the Ministry on environmental and social safeguards management during
Program implementation period, the Environment & Climate Change Directorate (ECCD) established under
MoWIE is responsible to ensure the enactment of environmental and social safeguards legal frameworks and
adequate care has been taken by the program implementers at all phases of the program execution.
The ECCD was established in the Ministry of Water, Irrigation, and Electricity in 2011 to bring
environmental protection and sustainable development, secure public welfare, benefit and participation and
facilitates development activities within the scope of the program. The ECCD has two sections (Climate
Change and EIA unit) and both units are staffed with fifteen (15) staffs having different disciplines like
environmentalist and sociologists, etc. (Figure 2). The Environment and Climate Change Directorate (ECCD)
to manage issues related to environment and climate change of the sector and these include:
• Prevent and control pollution of water resources;
• Enforcing and ensuring the compliance of Energy sector program activities to the EIA proclamation
which currently is being implemented;
• Reviewing EIAs and monitoring the implementation of EIA recommendations which is also in part
being implemented through Water, Irrigation and Electricity sectors;
• Regulating environmental compliance and developing legal instruments that ensure the protection of
the environment;
• Ensuring that environmental concerns are mainstreamed into sector activities.
The Roles and Responsibilities of Environment & Climate Change Directorate are:
• Plan the tasks in the Directorate, monitor the implementation, report timely to the concerned
stakeholders;
• Coordinate development plans/programs/projects/initiatives of the CRGE in the Water, Irrigation
& Electricity sectors of the Ministry;
• Evaluate and comment Policy, Proclamation, regulations, strategies, programs, plans, ranks & rules
of Water, Irrigation & Electricity sectors; monitor implementation;
• Coordinate efforts that secure the benefits from Clean Development Mechanisms, Renewable
Energy Sources & other facilities in the Water, Irrigation & Electricity sectors; monitor
implementation;
• Prepare awareness creation programs for the concerned stakeholders;
• Develop Database & publicize to stakeholders;
• Evaluate, approve & give clearance based on environmental Impact Assessment documents of the
planned developmental Programs of the Water, Irrigation & Electricity sub-sectors;
• Coordinate compensation, resettlement & public participation works of Water, Irrigation &
Electricity sub-sectors development plans jointly with other stakeholders;
• Monitor the implementation of management plan of ESIA documents of Water, Irrigation &
Electricity sub-sectors during the implementation of the development plans;
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
11
• Identify & create awareness about the influence of climate change on Water, Irrigation & Electricity
sub-sectors and encompass in the environmental study documents;
• Give support and Work jointly with regional and other stakeholders; and
• Participate in international climate change negotiations.
Figure 1: Environment and Climate change directorate under MOWIE Organogram
3.1.2 Ethiopian Electric Utility (EEU)
The Ethiopian Electric Utility (EEU) is responsible for the implementation of ELEAP. It was established as
a new utility in 2013 and the details of the utility roles and responsibilities are discussed under section four
(4) above.
The national regulation was endorsed for the establishment of the EEU on the date of December 27, 2013
“Council of Minsters Regulation No. 303/2013 to provide for the establishment of the Ethiopian Electric
Utility-Ministers Regulation: Page 7126”. The Regulation stated that the purposes for which the EEU is
established are as follows to:
• construct and maintain electric distribution networks;
• contract out the distribution networks construction to contractors as required;
• administer electric distribution networks, to purchase bulk electric power and sell electric energy to
customers;
• initiate electric tariff amendments and, upon approval, to implement same;
• in line with directives and policy guidelines issued by the Ministry of Finance and Economic
Development, to sell and pledge bonds and to negotiate and sign loan agreements with local and
international financial sources; and
• undertake any other related activities necessary for the attainment of its purposes.
EEU has established the Environment, Health, and Safety (EHS) department (EHS), comprises of two units,
i.e., environment and social; and health and safety (Figure 4). The EHS department main responsibility is
Minister (MoWIE)
Environment and cimate change Directorate (ECCD)
EIA team
EXPERTS
Scocioeconomist, Environmentalist, Economist, Lawer, Geographer
Climate Change Team
EXPERTS
Environmentalist, Forester, Economist, Ecologist, Sociologist
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
12
working on environmental, social, health and safety matters, which the major responsibilities of the unit are
the followings:
• Policy formulation on EHS
• Drafting and finalization of the EHS manual, procedures and guideline
• Coordinating within the organization for building the internal system capability and implementing
the required training of staff for the successful implementation of the EHS measures
• Establish and strengthen coordination among the relevant government organizations, like MoWIE,
MoEFCC, MoLSA
• Monitoring and Evaluation of the implementation of safeguards under the Program
• Data collection and reporting to the funding organizations in the agreed format at agreed intervals
• Ensure sufficient resources to provide the required services on EHS over the program period
• Ensure adequate occupational health & safety instruction are given to all parties engaging in the
implementation of ELEPA
• Coordination with the funding organizations and review of safeguards instruments of the
development programs under EEU
• Confirm to organize collection, analysis, and presentation of data on accident, sickness, and incidents
involving personal injury or injury to occupational health with a view to taking corrective, remedial,
and preventive action.
Figure 2: Organigram of EEU’s EHSQ Directorate
REGIONAL ENVIRONMENT, SOCIAL, HEATH
AND SAFETY MANAGER AND SOCIAL (EHS)
UNITS
CEO
ENVIRONMENT, SOCIAL,
HEATH, AND SAFETY
(EHS) HEAD
ENVIRONM
ENT
OFFICER
SOCIAL
OFFICER HEALTH
OFFICER SAFETY
OFFICER
HEALTH AND
SAFETY MANAGER
ENVIRONMENT AND
SOCIAL MANAGER
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
13
3.1.3 Ministry of Environment, Forest and Climate Change (MoEFCC)
At a federal level, the lead environmental protection organization is the MoEFCC. The former Environmental
Protection Authority (EPA), which is transferred to MoEFCC was established in 1995 under Proclamation
9/1995, as an independent agency reporting to the Council of Ministers. The mandates, which previously
indicated for the former Federal EPA, have been transferred over to the MoEFCC. MoEFCC is required to
implement measures to ensure that the environmental objectives of the Constitution are realized and that
social, economic and environmental justice is promoted. They also have responsibilities for building a
climate resilient green economy and for ensuring the implementation of international environmental
agreements.
The key objective of the MoEFCC is to formulate policies, strategies, laws and standards, which foster social
and economic development in a manner that enhance the welfare of humans and the safety of the
environment, and to spearhead in ensuring the effectiveness of the process of their implementation. As per
proclamation 916/2015, The Ministry of Environment, Forest and Climate Change have bestowed among
others with the following powers and duties:
• Coordinate activities to ensure that the environmental objectives provided under the Constitution and
the basic principles set out in the Environmental Policy of the Country are realized;
• Establish a system for evaluating and decision making, in accordance with the Environmental Impact
Assessment Proclamation, the impacts of implementation of investment programs and projects on
environment prior to approvals of their implementation by the concerned sectoral licensing organ or
the concerned regional organ;
• Coordinate actions on soliciting the resources required for building a climate resilient green economy
in all sectors and at all Regional levels; as well as provide capacity building support and advisory
services;
• Establish an environmental information system that promotes efficiency in environmental data
collection, management and use;
• In accordance with the provisions of the relevant laws, enter any land, premise or any other place
that falls under the federal jurisdiction, inspect anything and take samples as deemed necessary
with a view to discharging its duty and ascertaining compliance with environmental protection
requirements.
• Enforcing and ensuring compliance to the EIA proclamation which currently is being implemented
through delegated authority provided to sector ministries;
• Reviewing EIAs and monitoring the implementation of EIA recommendations which is also in part
being implemented through delegated authority provided to sector ministries;
• Regulating environmental compliance and developing legal instruments that ensure the protection of
the environment;
• Where projects are subject to federal licensing execution or supervision or where they are likely to
entail inter-regional impacts, review environmental impact study reports of such projects and notify
its decision to the concerned licensing agency and, as may be appropriate, audit and regulate their
implementation in accordance with the conditions set out during authorization.
• Ensuring that environmental concerns are mainstreamed into sector activities; and
• Coordinating, advising, assessing, monitoring and reporting on environment-related aspects and
activities
• Promote or assist in the formulation of environmental protection action plans and Programs and
solicit support for such action plans and Programs.
• Prepare directives to implement environmental protection laws and, upon approval, ensure their
implementation.
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
14
• Provide advice and support to regions regarding the management and protection of the
environment.
• Delegate some of its powers and duties, as it may be deemed appropriate, to other agencies.
The MoEFCC, the Former EPA, delegated the respective development Ministries, including the MoWIE to
review and provide clearance on the environmental and social assessment report prepared for Energy sector
programs. Therefore, the MoWIE is responsible to ensure the compliance of the proposed program to the
required environmental and social management policies and legal framework and other relevant international
policies and standards, including WB policies applicable for the ELEAP. The MoEFCC is also responsible
to check and evaluate the MoWIE’s decision on environmental assessment process and clearance through
the regular consultation with MoWIE and clearance reports of the MoWIE on safeguards instruments.
The MoEFCC is responsible to provide guidance, technical support, and capacity building on safeguards
management for regional environmental authorities; preparation of guidelines and procedures appropriate to
the programs/projects, and create awareness towards sound management of environmental and social
safeguards. The MoEFCC has no direct involvement of the MoEFCC in reviewing and clearance of the
safeguards instruments prepared by ELEAP. As the department of EIA under the MoEFCC has an extensive
experience in reviewing, decisions for safeguards instruments approval and clearance, and project site
auditing, the EEU and MoWIE would obtain support and guidance over the program implementation period,
as required.
Sector environment units: The other environmental organs stipulated in the Environmental Protection
Organs Establishment Proclamation (295/2002) are ‘Sector Environmental Units’ which have been
established in some of the line Ministries, including MoWIE. These Sector Environment Units have the
responsibility of coordinating and implementing activities in line with environmental protection laws and
requirements (Article 14, Proclamation 295/2002).
Article 13 of the EIA Proclamation 299/2002 requires that public instruments undertake EIA. To this end,
Sector Environmental Units play an important role in ensuring that EIA is carried out on Program activities
initiated by their respective sector institution. However, capacity of these units is limited
3.1.4 Ministry of Labor and Social Affairs
The Ministry of Labor and Social Affair (MoLSA), the main agency responsible for Occupational Health
and safety was established in 1995 under Proclamation 4/1995, as an independent agency reporting to the
Council of Ministers.
The MolSA is required to provide regional authorities with guidance, technical support, and capacity
building; support the development of various guidelines, including procedures appropriate to local projects;
undertake awareness creation in other federal agencies; and provide technical support to those agencies. The
Ministry of Labor and Social Affairs shall have the powers and duties to:
• With a view to ensuring the maintenance of industrial peace: a) encourage and support workers and
employers to exercise their right to organize and collective bargaining; b) encourage the practice of
participating in bilateral forums between workers and employers and tri-partite forums including the
government; c) establish efficient labor dispute settlement mechanisms;
• Issue and follow up the implementation of occupational health and safety standards
• Create conducive conditions for the provision of efficient and equitable employment services;
determine conditions for the issuance of work permit to foreigners and issue such permits; regulate
the provision of foreign employment services to Ethiopians;
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
15
• Undertake studies on manpower employed in the formal and informal sectors, unemployed
manpower and the classification of jobs in the country; collect, compile and disseminate information
on labor market;
• Register workers’ and employers’ unions established at national level;
• Register workers’ unions and collective agreements relating to federal public enterprises situated in
cities accountable to the Federal Government, and carry out labor inspection services in such
enterprises;
• Undertake and facilitate the implementation of studies on ensuring and improving the social well-
being of citizens, on a) the protection of family and marriage; b) the creation of equal opportunity
for persons with disabilities; c) the provision of care to the elderly and the encouragement of their
participation. 33. Other Federal Executive Organs.
3.2 Regional, Zonal and Woreda levels key actors for ELEAP
3.2.1 Regional, Zonal and Woreda level Water, Mines and Energy Bureaus (WMEB)
The regional Water, Mines and Energy Bureaus are the major stakeholders to support EEU during
implementation of the ELEAP at the regional and local level (Zone and Woreda) and are an autonomous
body under MoWIE. The respective main roles under these regional bureaus are to promote and facilitate
improved access to modern energy services, particularly for off grid energy sources in rural areas of the
nation, by working in partnership and collaboration with other relevant sectors, microfinance institutions,
private sector actors, NGOs, and community based organizations (CBOs). Overall, the main functions of
RWMEB are the following:
• Promote the alternative energy systems by using different means including media;
• Coordinate and support the design, implementation and supervision of distribution power line
rehabilitation and upgrading construction activities;
• Awareness creation on the on grid and off-grid energy components of programs for the pertinent
government energy sectors in zones and woredas and the relevant private sector (micro finance
institutions, distributors of solar energy systems, technicians for the installation of solar energy
systems) in their respective regions;
• Provide training on technical aspects of off grid system like installation and maintenance of solar
lanterns, solar home systems at zone and Woreda levels including for technicians graduated from
TVET;
• Control the distribution and installation of illegal solar energy equipment in collaboration with
other government sectors;
• Support, follow-up, monitor and evaluate the overall implementation of the alternative sources
of energy at hand in their respective regions;
• Avail accessories on time in consultation with the relevant bodies;
• Sensitize the beneficiaries to return loans in collaboration with zonal and Woreda administrative
bodies;
• Ensure that all lenders finish their construction on fixed time of construction and install the solar
systems within a specified period;
• Ensure that all the necessary appliances are provided on time;
• Make sure that the solar systems are functional;
• Organize quarterly field visit with the micro finance institutions and respective Woreda
officials/experts for joint supervision and support;
• Report to the MoWIE on a monthly, quarterly, biannually and annually basis.
• Promote, stimulate, facilitate, and improve modern energy access for productive uses in rural
areas to stimulate rural economic and social development; and
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
16
• Promote rational and efficient production and use of energy, and facilitate identification
and development of improved energy Program s and activities in rural areas.
3.2.2 Regional and Local Environmental Protection Authorities
Proclamation No.295/2002 (The Environmental Protection Organs Establishment Proclamation) empowers
each regional state to establish its own independent environmental agency. The Tigray, SNNPR, and
Benishangul Gumuz regional States have established the Environmental Protection Core Process Unit under
the Environmental Protection, Land Administration, and Use Bureau (EPLAUB). Whereas, the Oromia and
Amhara Regional states have a standalone regional environmental authority align with the MoEFCC.
Depending on the existing roles and responsibilities arrangements of the local environmental organs who are
delegated by the regional respective bureaus for, safeguards document review and clearance and monitoring
of environmental management, the local offices are mandated only for category B project, like ELEAP
program with limited impacts that can be managed with best practice.
The Environmental protection departments and units at all regions are responsible to monitor, review and
provide clearance of safeguards instruments prepared for projects implemented at regional level, particularly
for category A/Schedule I projects. For Category B/ Schedule II and Category C/ Schedule III projects, which
applies for ELEAP, in some regions, the regional authorities and respective core processes delegated for
zonal and woreda level environmental authorities and offices and authorities to monitor and follow-up the
implementation of safeguards instruments. No clearance is provided at zonal and woreda level, except for
simple ESMP that is prepared for projects with minimum impacts.
The major activities of these organs are responsible for: formulating regional policies, strategies and
guidelines; regulating development projects in order to minimize environmental damage; initiating
environmental laws; environmental auditing and collecting environmental data. The Amhara and Tigray
regions have endorsed the EIA proclamation and guidelines that all environmental and social safeguards
management under project activities aligned with. Among other the responsibilities of Zonal and Woreda
level Environmental organs are:
• Coordinate activities to ensure that the basic principles set out in the Environmental Policy of
the Country are realized;
• Establish a system for evaluating and decision making, in accordance with the Environmental
Impact Assessment Proclamation, the impacts of implementation of investment programs and
projects on environment prior to approvals of their implementation by the concerned sectoral
licensing organ or the concerned regional organ;
• Enforcing and ensuring compliance to the EIA proclamation which currently is being
implemented
• Reviewing ESMPs and monitoring the implementation of ESMPs recommendations;
• Regulating environmental compliance that ensure the protection of the environment;
• Ensuring that environmental concerns are mainstreamed into sector activities; and
• Coordinating, advising, assessing, monitoring and reporting on environment-related aspects and
activities
3.2.3 Regional and District Land Administration and Use (LAU) Institutions
Regional states have the responsibility to enact rural land administration and land use laws with detailed
provisions on implementation and to establish institutions to support implementation of these laws.
Following establishment of the Federal Environmental Protection Authority (EPA), regional governments
established the Environmental Protection, Land administration, and Use Authority (EPLAU) then vested with
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
17
responsibility of the administering rural land. Currently, there are certain variations among regions in the
arrangement of Environment and Land Administration and Use offices, for instance, Amhara Land
Administration and Uses (LAU) is independent bureau accountable to Regional Councils; while others are
embedded in the Bureau of Agriculture and are responsible for providing technical and administrative support
as well as carrying out a review and monitoring function for the implementation of regulations related to land
acquisition.
The land Administration and Use department of EPLAU or the LAU bureau is responsible for providing
technical and administrative support as well as carrying out a review and monitoring function for
implementation of regulations related to land acquisition .During the assessment, regional consultations made
with representatives from Amhara Land Administration and Use Bureau (BoALAU), South (SNNP) region
land Administration and Use department under Bureau of Agriculture and Natural Resources (SBOANR),
Benishangul Gumuz Bureau of Environment, Forestry and Land Administration (BoEFLA) and Tigray
Environmental Protection, Land Administration And Use Agency (TEPLAUA). The land Administration
and Use departments of these offices are responsible for providing technical and administrative support as
well as carrying out a review and monitoring function for implementation of regulations related to land
acquisition.
3.2.4 Regional Bureaus of Labor and Social Affairs (BoLSA)
Bureaus (agency in some regions) of labor and social affairs have been established in the nine regional states
and two city administrations. The Bureau of Labor and Social Affairs (BoLSA) is mandated to manage social,
labor and health and safety issues. These regional offices coordinate the implementation of the (2014) Social
Protection Policy. BoLSA/Agency of Labor and Social Affairs are also responsible for supervising the
implementation of occupational health and safety standards during construction. In cooperation with
concerned stakeholders, they undertake and facilitate the implementation of studies on ensuring and
improving the social well-being of citizens, particularly related to creating enabling conditions for persons
with disabilities to benefit from equal opportunities and full participation, as well as providing care to the
elderly and encouraging their participation
The labor, health and safety activities are managed by the harmonious industrial relations and employment
services promotion departments of the labor and social affairs offices. Regionally the similar unit /structure
manages labor and worker safety activities with staffing structure at zone and woreda/district level as well.
For the ESSA, consultations were made with SNNPR, Agency of Labor and Social Affairs (ALSA), Tigray
(BoLSA), Benishangul Gumuz (BOLSA) and Amhara (BoLSA).
The labor relation and employment service department of SNNPR has Organizational Safety and Health
(OSH), labor relation and industrial relations board as well child labor and trafficking sections. The structure
is similar for other regions, there is also staffing at zone and woredas, however woreda level staffing is very
limited, based on field observations only one expert per woreda in the case of visited woredas in Benishangul
and Tigray. Generally, when staffing capacity is seen though it varies from region to region, there is staffing
gap for regular inspection, follow up and training provisions. The consulted regional offices in Tigray and
Amhara informed that they provide trainings on labor proclamations, as well as other health and safety issues,
as they are trained by the ministry and other non-governmental agencies. They also conduct inspections.
These offices are willing to provide trainings on Health and Safety to other stakeholders like EEU upon
request.
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
18
4. ESMS POLICY AND LEGAL FRAMEWORK
4.1 Background
The effects of development projects on the biophysical and social environment should be assessed in order
to ensure that all development program and project implementations, as much as possible, must be
environmental friendly and comply with the relevant environmental policies, guidelines and procedures. In
this regards, policies, legislative frameworks, guidelines and standards have been developed by governmental
and non-governmental organizations to contribute for the enhancement of sustainable development.
This section describes the existing environmental and social management system of the various institutions
applicable to the Program. It provides an overview of the policy and legal framework and a profile of the
various key institutions and their role with respect to the management of environmental and social aspects.
As a PforR, ELEAP requires that all operations will function within an adequate national legal and regulatory
framework. In this context, management of the environmental and social effects of program activities under
ELEAP has been assessed to manage the adverse impacts based on the existing environmental and social
management systems of Ethiopia.
Based on the previous assessment conducted by WB, the applicable Ethiopia’s environmental and social
policies and legal framework have been identified. Therefore, national policies, legislations and guidelines
which govern the way in which environmental and social assessments are conducted in Ethiopia, and the
framework in which the environmental and social management of development projects should be
undertaken, have been identified and reviewed during this ESMSG process.
4.2 Ethiopia’s Relevant Legal Framework, Policies, Strategies, and Regulations
4.2.1 The Constitution of the Federal Democratic Republic of Ethiopia
The constitution of the Federal Democratic Republic of Ethiopia had issued in August 1995 with several
provisions, which provides basic and comprehensive principles and guidelines for environmental protection
and management in the country. The concept of sustainable development and environmental and social rights
among others are pinpointed below:
Article 44- Environmental Rights
• All persons have the right to a clean and healthy environment.
• All persons who have been displaced or whose livelihoods have been adversely affected as a result
of State programs have the right to commensurate monetary or alternative means of compensation,
including relocation with adequate State assistance.
Article 90- Social Objectives
• To the extent the country’s resources permit, policies shall aim to provide all Ethiopians access to
• Public health and education, clean water, housing, food and social security.
• Education shall be provided in a manner that is free from any religious influence, political
partisanship or cultural prejudices.
Article 92- Environmental Objectives
• Government shall endeavor to ensure that all Ethiopians live in a clean and healthy environment.
• The design and implementation of programs and projects of development shall not damage or destroy
the environment.
• People have the right to full consultation and to the expression of views in the planning and
implementations of environmental policies and projects that affect them directly.
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
19
• Government and citizens shall have the duty to protect the environment.
4.2.2 Relevant Environmental and Sectoral policies
As stated above, Ethiopia has adopted the Constitution in 1995, which provides the basic and comprehensive
principles and guidelines for environmental protection and management. Among other things the
Constitution states that everyone has the right to live in a clean and healthy environment and the government
will make every effort to provide such an environment. The policy document contains elements that state the
importance of mainstreaming socio-ecological dimensions in development programs and projects. In lien
with the constitution, the Government of Ethiopia has issued several sectoral and cross-sectoral policies and
guidelines that consider environmental issues for sustainable development. Among these, the ones which are
most relevant are described below
4.2.2.1 Environment Policy of Ethiopia (EPE)
The Environmental Policy (EPE) of the Federal Democratic Republic of Ethiopia was approved by the
Council of Ministers in April 1997 (EPA/MEDAC 1997) that was based on the policy and strategic findings
and recommendations of the Conservation Strategy of Ethiopia. The policy is aimed at guiding sustainable
social and economic development of the country through the conservation and sustainable utilization of the
natural, man-made and cultural resources and the environment at large. The overall policy goal is to improve
and enhance the health and quality of life of all Ethiopians and to promote sustainable social and economic
development through the sound management and use of natural, human-made and cultural resources and the
environment as a whole so as to meet the needs of the present generation without compromising the ability
of future generations to meet their own needs.
The Specific Policy Objectives among others seeks to:
• ensure that the benefits from the exploitation of non-renewable resources are extended as far into the
future as can be managed, and minimize the negative impacts of their exploitation on the use and
management of other natural resources and the environment;
• incorporate the full economic, social and environmental costs and benefits of natural resource
development into the planning, implementation and accounting processes by a comprehensive
valuation of the environment and the services it provides, and by considering the social and
environmental costs and benefits which cannot currently be measured in monetary terms;
• prevent the pollution of land, air and water in the most cost-effective way so that the cost of effective
preventive intervention would not exceed the benefits;
• conserve, develop, sustainably manage and support Ethiopia’s rich and diverse cultural heritage; and,
• raise public awareness and promote understanding of the essential linkages between environment and
development.
Specifically, with regard to Energy Resource, the three major relevant policies issued in the Environment
Policy of Ethiopia are the following:
• To adopt an inter-sectoral process of planning and development this integrates energy development
with energy conservation, environmental protection and sustainable utilization of renewable
resources.
• To promote the development of renewable energy sources and reduces the use of fossil energy
resources for ensuring sustainability and for protecting the environment, as well as for their
continuation into the future.
• To locate, develop, adopt or adapt energy sources and technologies to replace biomass fuels.
The Government of Ethiopia has recently initiated to update the Environmental policy of Ethiopia. The
Technical committee under the Ministry of Environment, Forest, and Climate Change was formalized to be
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
20
in charge of updating the National environmental policy to fulfill and gaps identified in addressing climate
change and other environmental issues.
4.2.2.2 Ethiopia Electric Utility’s (EEU’s) Environmental and Social Policy and Procedures
The draft Policy statement on ‘Environment & Social”; along with stated ‘Objectives’ was developed and
framed by the EEU. Environmental and Social Office of EEU has developed its corporate Environmental
and Social Policy and Procedures (ESPP) to address the environment and socio-economic issues arising from
its activities based on the basic principles of Avoidance, Minimization and Mitigation.
EEU is committed to the goal of sustainable development and conservation of nature and natural resources,
while continually improving its management systems by accessing specialised knowledge and technology.
EEU shall strictly follow the basic principles: of Avoidance, Minimization and Mitigation in dealing with
environmental and social issues. Where imperative, Restoration and Enhancement shall be undertaken and
strive to become Africa’s hub of green and clean energy by following excellent standards and benchmarks.
The objectives of the Policy are as follows: -
• To avoid operation in environmental eco-sensitive areas, forests, sanctuaries, national park etc.
• To minimize adverse impacts on natural environment;
• To mitigate the damage; and
• To facilitate harmonious relationship between EEU and the community through mutual cooperation.
The ESPP outlines EEU's approach and commitment to deal with environmental and social issues relating to
its generation plants, transmission system and distribution network. This document is a dynamic and living
document, which shall be further upgraded in the light of the experiences gained from field implementation
and other relevant factors. The main aim of ESPP is to give a human face to corporate functioning and move
away from the classical cost-benefit approach to the larger realm of corporate social responsibility, while
mainstreaming the environmental and social concerns.
This first ESPP document has been developed, based on desk research, consultations with the Environmental
Monitoring Office of the former EEPCo, on the regulatory framework and analysis of the domestic laws of
the land, consistent international regulations, guidelines, etc.
EEU has established EHS department, which comprises two units i.e. Environment and Social; Health
and Safety offices (Figure 4). The EHS team main responsibility is working on environmental, social
and safety matters, which the major responsibilities of the unit are the followings: -
• policy formulation on EHS;
• drafting and finalization of the EHS manual, procedures and guideline;
• coordinating within the organization for building the internal system capability and implementing
the required training of staff for the successful implementation of the EHS measures;
• coordination within the relevant government organizations, like MoWIE, MoEFCC;
• monitoring and Evaluation of the implementation of safeguards under the Program;
data collection and reporting to the funding organizations in the agreed format at agreed intervals;
and
• coordination with the funding organizations and review of safeguards instruments of the
development programs under EEU.
4.2.3 Proclamations, Regulations, and Procedural Guidelines
The summary of GoE proclamations and legal frameworks on environmental and social management
applicable to the ELAEP are depicted in the below Table 2. Please refer ESSA for details on Environmental
and social management proclamation, directive and legal framework.
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
21
Table 2: Some of the Legal Requirements & Compliance Measures applicable to ELEAP
NO. LEGAL
REQUIREMENTS
ACT/RULES/GUIDEL
INES
APPLICABLE ATTRIBUTES • EEU’S COMPLIANCE MEASURES
1 A Proclamation on
Energy, No. 810/2013 • Section 5 Art. (17) Suggests that compensation to be paid for all
damages while performing the activities provided under Art. (16)
• EEU follows these provisions together with
EPA guidelines.
• Section 5 Art. (18) Provides basis for expropriation of land in
accordance with the relevant law.
• Section 5 Art. 16(3) Provides the right to cut or lop trees or remove
crops, plants or other things that obstruct the construction or
operation of electrical works or may cause danger to electrical
lines.
2
Environmental
Protection Authority
(EPA) Proclamation No
295/2002
• Its objective is to ensure the country’s sustainable social and
economic development. Environment Impact Assessment (EIA) is
also required as per existing provisions of law.
• EEU commits itself to follow the mandatory and
prescriptive requirements.
3 Environment Pollution
Control (EPC)
Proclamation, 300/2002
• Deals with Management and Handling of Hazardous Waste,
Chemical and Radioactive Substance.
• EEU express the determination and commitment
to follow the substantial rule of Management
and Handling of Hazardous Waste, Chemical
and Radioactive Substance.
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
22
NO. LEGAL
REQUIREMENTS
ACT/RULES/GUIDEL
INES
APPLICABLE ATTRIBUTES • EEU’S COMPLIANCE MEASURES
Batteries Management
and Handling) • Bulk consumers like EEU to dispose all used batteries to dealers,
manufacturer, registered recycler, re-conditioners or at the
designated collection centres only.
• Used batteries are sold to registered recyclers/
dealers/ manufacturers are submitted to the
concerned Authority or the relevant regional
environmental agency.
Hazardous Wastes
(Management and
Handling)
• All used mineral oil is categorized as hazardous waste and require
proper handling and disposal.
• Mineral oil is sold as used oil to registered
recyclers, is submitted to the concerned
Authority or the relevant regional
environmental agency.
Ozone Depleting
Substances (Regulation
and Control)
• Controls and regulations specified on manufacturing, import,
export, and use of CFC compound.
• EEU follows all provisions of notification, and
is phasing out all equipment’s that use ODS
4 Labour Proclamation,
2003 • The act specifies the employer's liability for compensation to the
employee in several situations.
• EEU maintains safety as a top priority, and has
a dedicated unit to oversee all health and safety
aspects of its project. EEU has framed detailed
guidelines/checklists for workers’ safety.
5 Resettlement Policy
Framework • Applicable to projects where 400 families in plain and 200 families
in hills are displaced amass.
• Entitlement benefits listed for PAFs are adopted
by EEU in its “Social Entitlement Framework”
and the same is implemented wherever land
acquisition is undertaken.
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
23
NO. LEGAL
REQUIREMENTS
ACT/RULES/GUIDEL
INES
APPLICABLE ATTRIBUTES • EEU’S COMPLIANCE MEASURES
6 Land Expropriation
and Payment of
Compensation Act, 2005
• This Act prescribes a well-defined procedure for acquisition of
private properties for public purpose.
• EEU follows the procedures as prescribed in the
Act for acquisition of land for its projects
wherever applicable. EEU exercises flexibility
during site selection to avoid environmental and
social impacts.
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
24
• Directive on Clearance of Overhead Electric Lines No. EEA/1/2005
The previous Ethiopia Electricity Agency (EEA), established in 2014 as an autonomous organ with
naming Ethiopian Energy Authority (EEA), is responsible for setting standards and specifications for
electricity projects related activities. The Council of Minsters Regulation No 308/2014 gave way to the
establishment of the Ethiopian Energy Authority as an autonomous federal government organ.
The Energy Authority is accountable to the Ministry of Water, Irrigation and Energy. The Directive on
Clearance of overhead electric lines was issued by the then Ethiopian Electricity Agency pursuant to the
authority vested in it by Articles 55, 67 and 69 of Electricity Operations Council of Ministers
Regulations No. 49/1999. The objective of the Directive is to set standards for the clearance spaces
associated with transmission and distribution lines for the purpose of the protection of persons from risk
and property from damage, as well as to specify the quality of supply voltage.
Article 6, 7 and 8 of the directive include the minimum standard distance corresponding to electric lines
from ground for a road accessible to vehicular traffic, a building or structure, track of a small gauge
railway/tramway system and clearance from vegetation as well as other lines. For ELEAP activities
mainly involve works on low and medium voltage up to 33kv. According to the Agency directives of
overhead electric line clearance 5 m wide ROW is required for overhead electric lines, not exceeding
33 kV and growing of trees under electric lines shall not be allowed. The land beneath these overhead
lines can continue to be used normally by the owner for grazing and plowing. The ROW is required to
ensure the safe construction, maintenance, and operation of the power line.
4.2.4 Occupational and Community Health and Safety
Ethiopian Federal Democratic Republic constitution ensures the right of workers to work in a healthy
and safe working environment as stipulated in Article 42(2). The Constitution contains a full chapter on
fundamental rights and freedoms, which includes the right to equality without discrimination, the rights
of women and children, the right to access to justice, and economic, social and cultural rights. It also
covers the “Rights of labor”, including the rights of workers to form associations to improve their
conditions of employment and economic well-being, the reasonable limitation of working hours, to
remuneration for public holidays and to a healthy and safe working environment. The structure and
division of powers between Federal and State governments are also covered by the Constitution.
• Directive of 2008 Occupational Safety and Health,
The other significant piece of recent legislation in this area is the Occupational Safety and Health
Directive, which was adopted in July 2008. This is also very wide-ranging in its application, covering
all employment sectors but with specific provisions for the manufacturing and construction sectors.
Without prejudice to the Labor Proclamation, this Directive lays down general duties of employers and
the duties and rights of workers, and the need for certain organizational measures such as a safety and
health policy and arrangements, and for personal protective equipment. It also specifies measures for
controlling a wide range of risks, such as those from chemicals, noise, radiation, machinery, working at
heights, boilers and lifting equipment. There are also specific provisions for the recording and notifying
of occupational accidents and diseases (Box 6).
5. ESMS PROCESSES: PREPARATION& IMPLEMENTATION
5.1 General
This chapter sets out the ESMS processes, particularly screening of program activities for environmental
and social management and identifies the responsibilities of implementing parting in the program
ESMS. In detail, the section discusses about environmental and social issues that will be addressed,
steps to be taken for managing environmental, social and safety risks; various elements of the ESMSG
which include environmental screening and assessment processes, application for environmental
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
25
authorization, and guideline for ESMP; and anticipated program impacts and the respective measure to
ensure compliance of national and international policies and standards.
5.2 Key issues and responsibilities for the screening and appraisal processes
In order to ensure the ESMS is in place, EEU is required to demonstrate the implementation of the
program activities are environmental friendly and socially acceptable. The ESMSG has been prepared
and be available for relevant implementing institutions at all levels. As required, other safeguards
instruments like ESMP, A/RAP and Safety Management Plan (SMP) will also be prepared during
implementation period before the commencement of the specific project construction activities.
The program will take EHS risks/impacts seriously for better management of activities under the
program with full consideration of the importance of the environmental, social and safety matters and
to ensure improvements in people’s well-being. The GoE has established institutions and legal
framework for environmental, social and safety management. The activities set out in this ESMSG
therefore build on the GOE’s policies, laws, and procedures in environmental, social and safety
management (see section 4). The following table 3 outlines the proposed roles and responsibilities for
the different steps in screening and appraisal.
Table 3. Outline of Roles and Responsibilities for the ESMSG
Activity Lead Role for preparation and/or
implementation
Lead role for
review,
approval
&monitoring
Completion of screening using the form in
Annex 1: Screening Form.
Regional safeguards specialists under
the EEU offices
MoWIE, CSA,
REFAs (if
required)
PESIA, ESMP, SMAP, A/RAP
preparation, if required
Regional safeguards specialists under
the EEU offices
Implementation of ESMP, SMP, A/RAP,
as required Safeguards specialists under the EEU
EHS unit and Regional EEU offices
Monitoring of ESMP, SMP, A/RAP
implementation.
Annual Audit and quarterly Performance
review
EEU-EHS unit for quarterly
performance review, REFA for the
annual environmental, social and safety
audit
MoWIE, CSA,
MoEFCC
(if required)
Inspection and Supervision of
occupational health and safety
EEU EHS unit and Regional EEU
offices,
BoLSA,
MoLSA
5.3 Procedures and Steps for environmental and social management screening
5.3.1 Guiding Principles
The overriding guiding principle to the implementation of the proposed programs is through
participatory and community demand driven approach. The environmental, social and safety
management and screening process will be attained through the procedures and steps described below
on project screening cycle (see Figure 4).
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
26
Given the scale and nature of anticipated construction activities of ELEAP, an Environmental, and
Social Impact Assessment (ESIA2) might not be necessary. However, using the screening checklist
annexed in this ESMSG, program’s activities are required to pass through environmental screening to
identify potential risks and categorize subprojects on the bases of level of impacts, and take respective
measures aimed at avoiding, offsetting, and/or minimizing environmental, social and safety impacts to
levels that are acceptable.
This section describes the steps and procedures of environmental and social management screening to
ensure that environmental, social and safety risks and impacts are adequately addressed over the
program implementation period. The ELEAP-ESSA highlighted the Program planning and focus on
ensuring environmental friendly and socially acceptable program implementation with no harm
principle through applying best practices and sound mitigation measures.
The implementation of environmental management and screening process will be attained through the
procedures and steps described below on program implementation and screening cycle as shown in
Figure 5. The overall guiding principles of the proposed ELEAP implementations are the following, but
not limited to:
• Conforming to the national and regional environmental assessment requirements and
standards;
• Ensuring no harm or minimum impact to the nearby social and biophysical environment that
can be mitigated easily by employing best practices methods;
• Proposed activities under ELEAP will undergo for environmental and social impacts
screening;
• Ensuring sound implementation of the recommended mitigation measures;
• The planning and implementation process will integrate ESMP or other relevant environmental,
social and safety management instruments, as required;
• Promoting adequate and timely technical support to MoWIE, EEU at National, Regional
and Woreda levels; and
• Promoting supervision and monitoring of implementation of program activities by EEU,
MoWIE, and the respective regional and woreda level Bureaus and offices, with the support
from environment protection and Labor and Social services institutions.
• Ensuring on time quarterly performance review and annual audit.
Based on the Ethiopian Environmental legislation the program might not require full ESIA and all
activities under the program should avoid sensitive areas and take steps to ensure that projects stay
within Schedule II of national environmental assessment category or world bank environmental
assessment category “category BI3” (It must be noted that any projects or activities that will be
categorized as Category ‘A’ will not be financed by the ELEAP). Besides, every potential project that
will be funded under this program is subject for environmental and social management screening to
confirm the anticipated adverse impacts are small in scale and possible to manage with best practice
methods
The environmental and social management screening process will be affected on potential activities
under the ELEAP. The dedicated Environmental and Social and Health and Safety (EHS) specialists at
2 Any subproject that would be considered as category ‘A’ with adverse significant impacts, and irreversible nature will not be
financed from the proceeds of ELEAP.
3 “Category B” meaning that their potential adverse environmental impacts on human populations or environmentally important
areas – including wetlands, forests, grasslands, and other natural habitats – are limited, site-specific, few if any of the impacts
are irreversible, and they can be mitigated easily
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
27
national and regional EEU offices with regular support from regional energy and environment bureaus
are responsible to conduct environmental and social management screening before the commencement
of the program construction activities. The EHS specialists will use the environmental and social
screening form annexed in this ESMSG (Annex 1).
Based on the consultations with relevant stakeholders and review of the Program ESSA and appraisal
document and other national and EEU policies and guidelines, the following key steps and procedures
were identified during the environmental and social screening process (Figure 5). The section below
describes the steps for environmental and social screening process (the screening process) leading
towards the environmental and social management review and approval of activities under the proposed
Program.
5.3.2 Procedures and Steps
To ensure that the anticipated adverse impacts are small in scale and managed with best practice
methods, every potential activity under the proposed program will require environmental screening.
The dedicated Environmental and Social and Health and Safety (EHS) specialists at national and
regional EEU offices with regular support from regional energy and environment bureaus are
responsible to conduct environmental and social management screening before the commencement of
the program construction activities. The EHS specialists will use the environmental and social screening
form (Annex 1).
Based on the consultations with relevant stakeholders and review of the Program ESSA and appraisal
document and other national and EEU policies and guidelines, the following key steps and procedures
were identified and will be employed during environmental and social screening process (Figure 5).
Step One: Project preparation and Consultation
During planning and preparation of all projects under the Program, the implementing institution is
required to ensure that environmental, social and safety risks and impacts of the program are small scale,
could be mitigated, and/or minimized through implementations of sound mitigation measures. Before
the commencement of any project activity under the program, EEU EHS specialists are responsible to:
a) Review ESMSG and RSG requirements and implement measures stated in the ESMSG.
b) Obtain copies of all relevant federal and regional laws, guidelines, and procedures relating to
environmental protection, safety risks, resettlement issues and social and labor issues.
c) Ensure there is good knowledge of ESMSG requirements at different levels.
d) Contact the Regional Environmental and Forest Authority (REFA):
• Provide them with a copy of this ESMSG and the RSG document; and
• Inform the REFA that projects under the program will be screened and categorized as
being Schedule 2 or 3 in terms of federal and regional environmental legislation.
e) Identify potential environmental, social, and safety impacts in general and the respective
mitigation measures.
f) Identify interested and affected communities4, NGOs, etc., and consult them of the proposed
activities and its potential impacts.
4 Individuals or groups concerned with or affected by an activity and its consequences. These include local
communities, work force, customers, or consumers, environmental interested groups and the general public.
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
28
The screening and assessment of environmental and social impacts, as required is carry out by EEU’s
EHS specialists (Figure 4).
Figure 3: ELEAP E&S screening and management activity and responsibilities flowchart
Step Two: Desk appraisal
Prior to going to the project sites, a desk appraisal of the Program activity will be carried out by EEU-
EHS staffs to collect information on the environmental, social safeguards and safety issues to plan
screening activities accordingly and identify the potential impacts and recommend the respective
mitigation measures and for identification of impacts. Information on anticipated impacts and the
respective mitigation measures will be used by implementing institutions to obtain an overview of
potential environmental and social impacts that could be generated due to the implementations of each
subproject.
Step Three: Safeguards screening
Screening is the processes of determining whether or not a project requires ESIA, PESIA, ESMP, SMP,
ARAP/RAP or other instruments and the level at which the assessment should occur. The EEU-EHS
staffs at all levels are responsible for screening and initiate the process by submitting the screening form
contained in ESMG-Annex 1. This ESMSG Screening Report will describe,
a) The proposed activities and their potential impacts
b) Characteristics of the location (sensitivity of the area)
c) Size (small, medium and large scale)
d) Degree of public interest
ETHIOPIA ELECTRIFICATION PROGRAM (ELEAP)
Environment and social management instrument Preparation: EEU
–EHS staffs at National and regional level offices
National Regional District/Woreda Implementation level
EEU-EHS staffs with the support from MoWIE, REFA Desk appraisal and
Screening for Safeguards
Beneficiary Community members
On grid or Off grid Project Components
Environment and social
management instruments
Preparation, as required
Review/clearance/approval:
REFA
Review/clearance/approval:
MoWIE Environment and social
management instruments
review and clearance/approval
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
29
e) Institutional requirement, environmental enhancement and monitoring considerations,
The outcome of screening will be that each project is categorized as being a Schedule 1, 2 or 3:
a) Schedule 1 projects are fed into the standard ESIA process determined by MoEFCC/REFA;
b) Schedule 2 projects will not require full ESIA, but will necessitate the inclusion of
environmental and social mitigation and enhancement measures that includes preparation of
either PESIA or ESMP in the design and implementation of projects using standard
construction contract clauses, and an environmental management plan; and
c) Schedule 3 projects are not subject to any further environmental assessment as no potential
impacts are anticipated; but will still apply the environmental clauses as part of the
construction contract agreement.
As stated above, the Regional EEU-EHS staffs undertake environmental and social screening for each
project activities under the program to ascertain that the likely social and environmental impacts are
identified. This screening will be carried out by using the Environmental and Social Screening Form
(see ESMSG Annex 1). Completion of the screening form will facilitate the identification of potential
environmental and social impacts, determination of their significance, assignment of the appropriate
environmental category, proposal of appropriate environmental mitigation measures, and conduct any
further environmental assessment work, if necessary.
The assignment of the appropriate environmental category for the project under the program will be
based on the information provided in the environmental and social screening form (see ESMSG annex
1) and reference to national environmental procedural guideline. Consistent with the ESMSG, the
activities of the proposed projects are likely to be categorized as “Schedule 2”, meaning that their
potential adverse environmental impacts on human populations or environmentally important areas –
including wetlands, forests, grasslands, and other natural habitats – are limited, site-specific, few if any
of the impacts are irreversible, and they can be mitigated easily.
Given the scale and nature of the project, some of the project activities may be categorized as “Schedule
3” if the environmental and social screening results indicate that such activities will have no or limited
environmental and social impacts. Therefore, apart from screening, those projects do not require
additional environmental safeguards instrument preparation. That means, if the screening form has only
“No” entries, the proposed activity will not require further environmental assessment work, and the
project will be approved for the implementation.
Step Four: Submission of screening report to MoWIE or REFA
After thorough screening of the program activities, EEU will require to submit the screening result
reports to the MoWIE or REFA for review with a recommendation of environmental assessment
category and request for approval.
Step Five: Review of screening report and appraisal by MoWIE or REFA
The MoWIE or REFA will review the screening reports comprises of screening results and
recommendations to provide feedbacks on the specific screening endeavors and broader issues of
screening and the environmental and social safeguard instruments. The review process will take into
account that the proposed subproject activities may not necessarily need a full scale ESIA since the
Proposed Program is under category B/Schedule II.
After Review the Screening Report MoWIE/REFA will:
(a) Accept the document - with conditions relating to implementation;
(b) Accept the documents with required and/or recommended amendments; or
(c) Reject the document with comments as to what is required to submit an acceptable Screening
Report.
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
30
As necessary, after review of the screening, a field appraisal mission may require by MoWIE/REFA to
the location of the program activity to obtain additional information before the program activity be
considered for approval. If the desk appraisal and screening indicate that the proposed program activity
may have environmental and/or social concerns that are not adequately addressed, or if the application
meets certain criteria, the MoWIE/REFA will require a field appraisal before the application can be
considered further. Therefore, if the screening process resulted in project to fall under schedule 2
projects it will be subject to a limited Environmental and Social Review carried out by the EEU- EHS
staffs. The review will require:
• A field visit to the project area to identify likely environmental and social impacts;
• Brief consultation with beneficiaries and affected communities;
• Preparation of partial ESIA or an Environmental and Social Management Plan (ESMP), as
required;
• Use of the ESMSG environmental contract clauses and impact mitigation checklists: Example
of Environmental Contract Clauses (see Annex 4) and Environmental and Social Impact
Mitigation and Monitoring Checklists (Annex 7); and
• Preparation of, if necessary, SMP, A/RAP and other safeguards instruments.
MoWIE/REFA will provide decision on the screening reports (with required and/or recommended
amendments), as stated above, without requiring field appraisal mission or reject the document with
comments as to what is required to submit an acceptable document.
Depending on the field appraisal mission, the appraisal might reconsider the need for of changing of the
environmental assessment category and development program activity specific ESMP, SMP, A/RAP,
or other safeguards instruments. EEU-EHS staffs at all levels are responsible to ensure the required
environmental, social and safety management instruments are prepared as per the national requirements.
The ESMP and other instruments like, SMP, A/RAP can be conducted by a team of experts from EEU-
EHS unit or by a consultant, as necessary. EEU at all levels will supervise environmental, social and
safety management implementation work. Once the required instruments are prepared, EEU will make
recommendations to MoWIE/REFA for final clearance and approval.
Step Six: Approval of projects by MoWIE, REFA
The first step in the approval process is to determine if all the relevant information has been provided,
and is adequate. The MoWIE at national level and REFA at regional local level will check if the
screening report have thoroughly considered all environmental, social and safety issues with regards to
the identification of potential adverse effects arising from the program as well as recommended
mitigation measures to adequately address negative impacts.
Program activities may not be eligible for funding, if they have a potential to generate negative impact
on physical cultural resources, natural habitats and forests and require land acquisition. A list of such
projects that may not be funded by the program are described in program exclusion list (Annex2).
The screening of the project might result in a request for development of specific Environmental and
Social Management Plan, SMP, A/RAP, associated with the program activities. MoWIE /REFA will
review the ESMP, SMP, A/RAP and make decision of the approval of the program activity (with or
without conditions relating to implementation); recommending to re-design (with required and/or
recommended amendments); or rejecting the project activity (with comments as to what is required to
submit as an acceptable report).
Steps Seven: Submission of approval decision report to EEU
All review of the screening report and additional instruments (ESMP, SMP, A/RAP, etc.), if applicable,
should be done in the given shortest time to avoid delays in program activity implementation. The result
of the review and final approval will be submitted to EEU from REFA/MoWIE as soon as completed.
The Review report to EEU should include but not limited to:-
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
31
• The decision on each program activity whether an ESMP and other instruments are required or
not;
• If an ESMP and other instruments are being required, the recommended scope of the ESMP and
other instruments are clearly indicating the aspects to be seriously addressed, the skills required
and duration of the ESMP and other documents to be finalized;
• If an ESMP and other instruments are not required, include guidance on special needs such as
technical guidelines on any of the program activities; and
• Approval without conditions for those program activities with no potential adverse impacts.
Steps Eight: Implementation
Once approval obtained from MoWIE/REFA, EEU will act on the decisions and requirements provided
by the MoWIE/REFA and commence the implementation of the program’s construction activities.
Steps Nine: Supervision and Monitoring
The EEU, MoWIE, REFA will carry out supervision and monitoring, in consultation and support from
the World Bank.
Steps Ten: Annual EHS auditing and quarterly EHS performance review
The annual EHS auditing and quarterly EHS performance review is the responsibility of EEU, to be
audited by an independent auditor and submitted to MoWIE
Figure 4: Project Screening Implementation cycle under the ELEAP
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
32
6. GRIVANCE REDRESS MECHANISM
A Grievance is furiousness or bad feelings coming from a feeling of having been neglected. In case of
Program activities/subprojects involving land acquisition and involuntary resettlement, the grievance
procedure and appeal mechanism are an important aspect related to resettlement/ rehabilitation of the
PAPs because there may be individuals who are not satisfied with their compensation package or the
resettlement process, or who may feel that they were eligible for compensation. It is essential to settle
these issues as early as possible in order that the resettlement process is on the right track and it is
therefore, necessary to set up systems to address such grievances.
Grievance mechanisms provide a formal avenue for affected groups or stakeholders to engage with the
Program implementers or owners on issues of concern or unaddressed impacts. Grievances are any
complaints or suggestions about the way ELEAP activities/ subprojects are being implemented. They
may take the form of specific complaints for damages/injury, concerns about routine project activities,
or perceived incidents or impacts. Identifying and responding to complaints supports the development
of positive relationships between ELEAP implementers and affected groups/communities, and other
stakeholders.
The Ethiopian Government outlined standard requirements for complaints handling mechanisms for
development initiatives5. Grievance mechanisms should receive and facilitate resolution of the affected
communities’ concerns and complaints. The concerns should be addressed promptly using an
understandable and transparent process that is culturally appropriate and readily acceptable to all
segments of affected communities, at no cost and without retribution. Mechanisms should be appropriate
to the scale of impacts and risks presented by Program activities.
While ELEAP subprojects may have limited potential adverse impacts to people and the environment
in general, identifying complaints and ensuring timely resolution is still very necessary. Over the ELEAP
implementation period, beneficiaries may have complaints related to the program implementation
activities.
ELEAP On-Grid: based on EEU’s complain handling procedure, customers submit their complaints on
the spot at district level for customer services focal person/ Environmental and Social Inspector (ESI),
using call centers and at the regional grievance offices. Public forum is also used as one mechanism to
share complaints. The GRM procedure is distributed to regional grievance unit; EEU district offices
have customer policies and procedures manual that includes complaint handling section. There is also a
general guide on compensations (for damages sustained due to power fluctuation), and Public Liability
Insurance Policy in cases of accident and damage of materials on customers due to electricity problem.
There is however, gap in application of written procedures and responsiveness, gaps in awareness among
customers on GRM procedures as well as requirements for compensations, limited number of staff and
the nature of some challenges faced which are beyond the district or regional offices. The third person
liability procedure/compensation procedure lacks updates and detail guidance. The existing GRM and
related guidelines are updated considering the current conditions and applicability. Staff trainings and
community awareness is also vital.
5 National Proclamations (No. 433/2005 and 434/2005) and institutional level operational guidelines clearly define
the procedures to follow under corruption offences as well as for administrative complaints.
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
33
ELEAP Off-Grid: EEU has limited experience with off-grid activities (only some with mini-grids) and
consequently there is the lack of written procedure or staff trainings to manage grievance in a systematic
way, which needs to be tackled to adequately respond to grievances that may come from the
implementation of off-grid activities
An attempt has been made during the ESSA, to identify all potential impacts of the ELEAP, to address
and mitigate potential impacts, and to carry out a mechanism to implement these mitigation measures
(including payment of compensation).
However, during the Program implementation, stakeholders (mostly the communities in the vicinity of
the Program activities sites/ distribution, transmission line routes) may still have some grievances with
respect to the Program activities, their impacts, compensation and other resettlement operations. The
main potential reasons of these grievances could be:
➢ PAPs not enlisted as per the defined eligibility criteria,
➢ Losses (such as damaged crops, trees or other assets) not identified correctly,
➢ Compensation inadequacy or inappropriateness,
➢ Dispute about ownership,
➢ Delay in disbursement of compensation,
➢ Improper distribution of compensation in case of joint ownership
➢ Any other issue arising during the subprojects implementation.
In order to address the above eventualities, the Grievance Redress Mechanism (GRM) is devised. The
main objective of the GRM is be to provide a mechanism to mediate conflict and cut down on lengthy
litigation, which could delay the infrastructure subprojects of ELEAP. It aims at reassuring people who
might have objections or concerns about their assistance, provide a public forum to raise objections and
conflict resolution, and all in all address these issues adequately. The main functions of the GRM are as
follows:
▪ Provide a mechanism to the PAPs on problems arising as a result of Program activities,
▪ Record the grievance of the PAPs, categorize and prioritize the grievances that need to be
resolved, and
▪ Report to the aggrieved parties about the developments regarding their grievances and the
decision of the authorities in charge of providing the decisions.
6.1 ElEAP Grievance Redress Procedure
I. First Instance (Program Implementation Section)
A. Under ELEAP GRM, the Environmental and Social Inspector (ESI) will maintain the Social
Complaint Register (SCR) at the sites to document all complaints received from the local
communities. The information recorded in the register will include date of the complaint, details
of the complainant, description of the grievance, actions to be taken, the person responsible to
take the action, follow up requirements and the target date for the implementation of the
mitigation measure. The register will also record the actual measures taken to mitigate these
concerns.
B. As soon as a complaint is received, the ESI will discuss it with the Environment Health and
Safety (EHS) team, and determine the remedial action. If required, consultations will also be
undertaken with the Contractor’s Site Managers (CSM). Once the remedial action is decided,
implementation responsibility as well as schedule will be determined.
C. The proposed remedial action will be documented in the SCR, with complete details (by whom
and when). The proposed remedial action will be shared with the complainant. Similarly, the
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
34
actual action taken will also be documented in the Register and shared with the complainant.
The complainant’s views on the remedial action taken will also be documented in the Register.
D. The SCR will be reviewed during the fortnightly meetings at the site during the Program; and
the action items discussed. The progress on the remedial actions will also be reviewed during
the meetings.
E. The Register will also be shared with the CSM and ESI at site, on regular basis, for information
and further action, if any.
II. Second Instance (Grievance Redress Committee)
A GRM committee will be established at all Program implementation Woredas to receive, review and
address complaints in line with loss of livelihood, income or assets, dissatisfaction of the services, etc.;
for cases that cannot be managed through first instance grievance redressing mechanism.
In order to address any unresolved grievances at a higher level of the Program, a Grievance Redress
Committee (GRC) will be constituted. The Committee will be headed by the Woreda Administrator,
with Woreda justice office; EEU representative, representative of PAPs, representatives from elders/
religious leaders and other members. A non-project person acceptable to all parties can also be member
of this Committee. Any un-resolved issue will be sent to the Committee for determining the remedial
action.
III. Appeal to Court
Whenever misunderstandings and disputes arise between the principal parties (e.g. EEU or other ELEAP
Implementing Bodies and PAPs) involved in the resettlement and compensation process, the preferred
means of settling disputes is through arbitration (Proclamation No. 455/2005). The number and
composition of the arbitration tribunal may be determined by the concerned parties.
Although Proclamation No. 455/2005 provides for appeals from the valuation decision, such action will
not delay the transfer of possession of land to the intended recipient.
Courts of law shall be considered as a last resort option, which in principle should only be used where
first and second Grievance Redressing Mechanisms have failed to settle the grievance/dispute. However,
the Constitution allows any aggrieved person the right of access to a court of law.
The ELEAP GRM’s roles, responsibilities, implementation mechanism, and timeframe is discussed in
the following table 4.
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
35
Table 4: ELEAP GRM’s roles, responsibilities, implementation mechanism, and timeframe
Stage/Description Action Action By When Monitoring
By
Notes
Mobilization at
site
Placement of Social Complaint Register (SCR) at the
site office
EHS Team At the time of
site
mobilization.
ESI The SCR will have separate columns for: i) date
of complaint; ii) description of complaint; iii)
particulars of complainant; iv) details of action
required/decided; v) person(s) responsible to take
action; vi) person(s) responsible to monitor the
action; vii) details of action taken (when, by
whom, where); viii) comments of the
complainant after the action taken.
A separate SCR will be placed at each grid station
included in the proposed project, and any other
project site offices.
Complaint raised
by
complainant
The complaint is recorded in the SCR.
EHS Team - ESI The relevant columns of the SCR are filled.
Identification of
remedial action
A meeting is held between EHS Team and ESI, and if
required with PM and Site In charge.
The remedial action is identified.
The CSM and EHS are informed regarding the
grievance and the remedial action identified.
ESI Within 2 days
of the new
complaint.
ESC The relevant columns of the SCR are filled.
Implementation
of
remedial action
The remedial action is implemented Contractors or
PIU, depending
upon the nature
of the remedial
measure
4 weeks
(max.)
ESI The relevant columns of the SCR are filled.
Feed back to the
complainant
Information is provided to the complainant regarding
the remedial action taken.
The comments/observations of the complainant are
obtained and documented.
EHS Team Within 1
week of the
action taken.
ESI The relevant columns of the SCR are filled.
Fortnightly site
meetings
The SCR will be discussed. ESI Fortnightly. PM The discussion will be documented in the minutes
of meeting.
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
36
Stage/Description Action Action By When Monitoring
By
Notes
On monthly basis The summary of SCR will be sent to CSM and ESC. ESI Monthly. PM -
Un-resolved
complaint sent to
Grievance
Redress
Committee
(GRC)
The GRC will identify the remedial action. CSM Within one
month.
Woreda
Administrator
ESI will send the complaint to the GRC after one
month of receiving the complaint, if remains
unresolved.
Appeal to Court Complainant will take the case to formal court
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
37
6.2 Key Considerations for ELEAP GRM Procedure
Disclosure of the GRM: The existence and conditions of access to this register (how, where, when) shall be
widely disseminated within the Program implementation areas as part of the consultation undertaken for the
investment subprojects projects.
Expectation When Grievances Arise: When PAPs present a grievance, they expect to be heard and taken
seriously. Therefore, EEU and other Program stakeholders such as the consulting and contracting engineers
involved in the Program must provide adequate information to people that they can voice grievances and
work to resolve without fear of retaliation or some sort of social retribution.
Grievance Submission Method: A complainant has the option to lodge his/her complaint to Environmental
and Social Inspector (ESI) at EEU-EHS Office or GRC, at their vicinity with their convenient method of
communication (verbal/ face to face, written, telephone, etc.)
Registration of Grievances: as long as one of the ELEAP subprojects entails resettlement and/or
compensation, complaints will be transcribed, recorded in a log, examined; investigated and remedial actions
will be taken to settle. Any grievance that may arise from the resettlement operation will be filed in the first
instance settlement procedure.
Management of Reported Grievances: The procedure for managing grievances should be as follows:
a. The affected person files his/ her grievance, relating to any issue associated with the resettlement
process or compensation, in writing or phone to the Program Grievance Redress mechanism (ESI)/
EEU Office (Phone numbers will be provided by the EEU officers). Where it is written, the grievance
note should be signed and dated by the aggrieved person. And where it is phone, the receiver should
document every detail.
b. ESI will act as the Program Liaison with PAPs to ensure objectivity in the grievance process.
c. Where the affected person is unable to write, the local Liaison Officer will write the note on the
aggrieved person’s behalf.
d. Any informal grievances will also be documented
Grievance Log and Response Time: The process of grievance redress will start with registration of the
grievance/s to be addressed, for reference purposes and to enable progress updates of the cases. Thus, a
Grievance Form/ Register will be filed with ESI of the Program. The Form/Register should contain a record
of the person responsible for an individual complaint, and records of date for the complaint reported; date
the Grievance Logged; date information on proposed corrective action sent to complainant (if appropriate),
the date the complaint was closed out and the date response was sent to complainant.
The Program Liaison officer/ ESI working with the Kebele/Woreda Administrator will record all grievances
and ensure that each complaint has an individual reference number, and is appropriately tracked and recorded
actions are completed.
The response time will depend on the issue to be addressed but it should be addressed with efficiency.
Grievances Reporting Mechanism: The EEU EHS/ ESI will be responsible for compiling submitted and
processed complaints/ grievances on regular basis and report to PIU and other relevant stakeholders as per
agreed plan.
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
38
Figure 5: ESMS Grievance and Complaint Management Mechanism
7. ELEAP ENVIRONMENTAL AND SOCIAL BENEFITS AND IMPACT
Given the nature and scale of the proposed program activities, the negative impacts that could be emanated
that affect the nearby biophysical and social environment are expected to be minimal. Unlike the negative
impacts, the program would also generate a tremendous benefit to the community residing nearby. However,
poor planning and implementation of the proposed energy program could also affect the biophysical and
social environment.
The potential adverse environmental, social and safety risks and impacts of the Program are associated with
program activities, including construction and rehabilitation of medium and low-voltage distribution lines
Registration of the grievance or dispute by ELEAP Activities
Internal assessment of the nature of the grievance or dispute
Decision as to method of addressing the grievance or dispute
Complaint resolved amicably
[First Instance]
Yes
Final closure
No
Resort to GRC
Result of GRC
Grievance processed by GRC
Complaint resolved No
Yes
Final closure
Final closure One or both parties resort to
Courts of Law
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
39
and installation of MV-LV transformers, construction of hybrid mini grids, and disposal and replacement of
spent lead-acid batteries from solar home systems. Whereas, the potential adverse social impacts are likely
to be associated with land acquisition for mini grid and acquisition of way leaves (rights of way) for LV
distribution lines.
Overall, the anticipated impacts are expected to be minimum and most of them may stem from ground
disturbance due to vegetation clearance and excavation/digging for pole erection; masonry activities to
reinforce the electric pole; onsite concrete mixing; transportation and distribution of solar panels; installation
of equipment; and waste management within and around the core activities area. These are also not
anticipated to be of large scale but could affect individual project-affected persons (PAPs) that lose assets
including structures, crops and trees, and the use of portions of their land. It is anticipated that most of the
adverse effects, associated with the construction and operation will be reversible in nature and there are no
impacts that will lead to irreversible negative permanent change.
The ESMSG identifies the key measures to be taken for improved environmental and social due diligence
in the Program and is intended to help the Government and implementing agencies in overcoming gaps with
regards to environment, social, and safety aspects of the program and improvements of the implementing
agencies system on safeguards managements. This section describes the potential environmental, social and
safety benefits and impacts that could be generated from the implementation of the ELEAP and outlines the
measures that may be implemented to address potential impacts.
7.1 Positive Environmental and Social Impacts of ELEAP
The proposed Program activity is expected to be implemented in an environmental friendly and socially
acceptable manner that attributed by provision of benefits to the community members who are residing
within and nearby the project area and other beneficiaries of the proposed Program and to the nation in
general. An increased distribution of electricity to the project area will minimize the pressure on the use of
fuel wood that is rampant in the area and is ultimately would help to conserve the fragile and diminishing
forest cover of the country by providing an alternative source of energy. This section is a detailed outline of
the potential environmental and social benefits that generated from the implementation of the proposed
ELEAP. The Program’s environmental and social Benefits are substantial and long-term and are summarized
in the below table 5.
Table 5: Environmental and Social Benefits of ELEAP
Benefits Description
Benefits from Provision
of on-grid electricity
• Reduction in use of diesel or gasoline-powered generators and other
equipment such as grain mills, pumps, leading to reduced emissions
of air pollutants, greenhouse gases (GHG), and noise
• Reduction in consumption of kerosene for lighting and other uses,
resulting in improved indoor air quality
• Reduction in use of animal dung and/or crop residue for cooking and
space heating, which usually serve as fertilizer in rural area.
Benefits from power
generation using • Reduce deforestation and forest degradation in areas where non-
renewable biomass is used as a source of fuel, which implies that the
demand for firewood and charcoal is reduced.
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
40
Benefits Description
renewable energy
sources:
• Reduction in use of diesel or gasoline-powered generators and other
equipment such as grain mills, pumps, leading to reduced emissions
of air pollutants, greenhouse gases (GHG), and noise
• Increase in generation capacity with avoided GHG emissions
• Public goods benefits, such as increased security and lower
environmental contamination.
• Reduction in capital, operation and maintenance cost of diesel powered
generation plant
• Contribute to the Climate Resilient Green Economy (CREG) initiative
Benefits from provision
of electricity to
households:
• Improve to access to grid electricity whose tariff is relatively cheaper than
other sources
• Business activity at home like: food catering, tailoring, game zone, etc.
would be established and therefore these activities will augment
household income
• Creates extra time for household to discuss about family chorus
• Reduction in indoor air pollution from kerosene and other sources of
energy that are accountable to lung and respiratory diseases especially for
women and their children who cling upon their shoulder
• Provide better illumination than other sources
• Since household electricity penetration rate is one of the Human
Development Indices (HDI), it will support the Ethiopian government
strategy of poverty reduction,
• Connect the household with the outside world
• Used for refrigeration, cooking stoves, entertainment, mobile charging
and communication, lighting for students to study and have family quality
time.
• Vulnerable groups and underserved people in pastoral and remote
communities will also benefit from access to off-grid electricity services
such as stand-alone solar systems and mini grids.
Benefits to business: • Business opportunities will be created for women and men in the local
community with higher productivity and longer working hours
• transform their products and services of existing businesses
Benefits employment
opportunities: • Temporary employment opportunity will be created for skilled and
unskilled labor during construction and operation.
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
41
Benefits Description
• Hold a workforce that can be employed in the construction works of the
distribution line and mini grid related activities.
• Community in the project area and its immediate surroundings will drive
income and employment opportunities for themselves and their families
Improvement in social
facility services (schools,
health facilities, and
government offices):
• Ensuring efficient provision of education services at day and night
classes.
• Night school will be opened, so that drop outs will continue their
education
• Encourage students to continue their education in the nearby schools.
• Efficient and quality health services through sustainable sterilization of
medical appliances, refrigeration of vaccines and other medicines, cold
storages/ preservation of medicines and medical laboratory tests.
• Better health care translated into safer deliveries, better care for children,
and other community members.
Reduce Women’s
Burden:
• Easing the burden of women.
• Facilitate the setting up of grain mills in the vicinities, promoting the use
of improved technology for the preparation of food using electric stoves,
the initiation and development of motorized water pumps, etc.
• Reduce the time for collection of fire wood and animal dung for cooking
and space heating
• Enable communication and interaction of women in the project area using
mobile phone service.
7.2 Adverse Environmental and Social Impacts
7.2.1 Negative Environmental Impacts
Due to the construction and operational activities of the proposed programs, limited negative environmental
and social impacts are anticipated to affect the nearby biophysical and social environment. However,
considering the nature and limited scale of the Program activities, potential negative impacts will be
mitigated and/or avoided through implementation of appropriate best management practices. The following
adverse impacts are foreseen to occur during construction, and operational phase of the program.
Impacts from MV and LV Power line construction, and rehabilitation activities
Construction of Access Roads: The construction of access roads can affect the environment through
vegetation clearance, compaction of land, dust pollution and impact on natural habitats. To avoid/minimize
the anticipated impacts, temporary access roads shall be rehabilitated and existing roads/trails are used for
access, the impact is not expected to be significant.
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
42
Construction of Right of Way (ROW): Possible interference with or fragmenting of land uses along the
ROW will be the causes for opening of remote lands to human activities such as settlement, agriculture and
vegetation. These effects can be significant if natural habitats such as wetlands and national parks are
affected. To offset the impacts from ROW construction, the Employer/Contractor shall identify well-
established routes corridors with minimum impacts that help for transport of goods and ensure the
cumulative effects from the program are not to be significant.
Construction of LV Distribution Line Pole: Clearing of vegetation, site compaction has the potential to
change land use patterns. However, the area required for each pole erection for the distribution line is not
expected to have a major adverse impact on land use patterns. As the construction activities limited in the
existing site, no or minimum impacts are expected. Efforts will be made during the construction activities
of the distribution line to ensure that the paths are routed in areas with no/minimal vegetation area and
natural habitats as possible to avoid land acquisition.
Loss and Destruction of Vegetation cover/crop and Habitat: Although the line is focused on the exiting
path, the anticipated distribution lines, particularly in rural areas are mostly covered by agricultural land.
Activities like excavation and digging works may affect the vegetation and will involve clearing and loss of
existing vegetation cover and disturbance of top soil that promotes of soil erosion. The anticipated impacts
could be managed by avoiding and/or minimizing cutting of big trees, particularly care should be given for
indigenous trees, plan for replanting of trees; careful attention shall be given to threatened tree species, avoid
open burning of plant material and string conductors under tension to minimize potential damage to
remaining ground vegetation.
In addition, Activities like excavation and digging works particularly for reinforcing of distribution line,
clearing of way leave for distribution lines that cannot be located in the road reserve, pole erection,
installation of MV-LV transformers, hybrid mini-grid and Solar Home System equipment establishment, will
involve the followings impacts
• clearing and loss of existing vegetation cover which may contribute for loss of plant cover and
biodiversity;
• disturbance of top soil that promotes of soil erosion;
• plant material removed from site causes GHG emissions and air pollution if burned; and
In order to minimize and/or avoid the negative impacts, the Employers, Contractors, implementing bodies
and beneficiaries shall implement the followings measures:
• Avoid and/or minimize cutting of big trees, particularly care should be given for indigenous trees,
plan for replanting of trees, etc.
• Careful attention shall be given to threatened tree species, avoid open burning of plant material.
• Any impact on clearing of ground and tree crops is expected to unavoidable and the crops destroyed
will be compensated in accordance with the national law before any construction works commence.
The compensation and resettlement process will be prepared and clearly discuss in a RAP/ARAP
that will be used as an instrument to address such impacts.
• As per the national standards, limit the ROW at the recommended width for both 33 kV and 15 kV.
However, the undergrowth in the ROW should be allowed while only leaving a narrow strip to be
completely cleared to allow stringing of the line conductors.
• Strictly define ROW clearing activities in the contract specifications and in the Environmental and
Social Management Plan (ESMP) (guideline for the preparation of ESMP is stated in Annex 3).
• String conductors under tension to minimize potential damage to remaining ground vegetation.
Air quality: Open burring of vegetation and other wastes would contribute a potential impact on the Air
Quality, which ultimately pollute the air resulting in increases in bronchial and eye disorders. Dust and
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
43
exhaust emissions from construction activity with multiple crews operating off and on road equipment. The
impacts can be reduced if all program activities are implemented in an environmental friendly with best
management practices, considering watering of the road regularly, regular vehicle maintenance, etc.
Community members and contractor’s staff shall be advised and enforced to avoid such open burning that
result smoking and pollution of air.
Aesthetics and visual related impacts- visual intrusion on the landscape
The construction of distribution lines could impose a visual impact on the immediate surrounding area and
affect the aesthetic quality of the community residing nearby although the impact is expected to be minimal.
In addition, hybrid mini-grid and Panel installation and excavation of soil for pole erection could result in
minor change of the land aesthetics of the project areas. This may also affect the visual amenity of nearby
houses and surrounding communities. To minimize interruption of visual quality, solar panels should be
placed at the right direction (north –south) and with no reflection of light that affect the neighbors’ visual
quality. In all activities within the core area, indiscriminate disposal of excavated soils, unused concrete,
wooden timber, cables, electric equipment, empty oilcans, nails, and liquid wastes should be managed and
disposed of in appropriate way to ensure safe and acceptable aesthetic beauty to the workers and residents.
Water Resources
The contractor should follow the design to keep the construction activities to areas of lower elevation as
much as possible, in order to minimize the potential erosion impacts associated with the proposed
distribution lines. The contractor and Employer shall also develop a program of afforestation/tree planting
and water and soil conservation activities, as required, in areas where erosion is aggravated due to activities
associated with the program.
Storage and Management of solid waste
Waste management at the core project area shall be efficient and required to be implemented in an
environmentally friendly manner. Indiscriminate disposal and/or storage of solid and liquid wastes including
recycled batteries, used/burned transformers, other used and/or damaged solar panels, packages, and left-
over construction materials and cements, have the potential to generate an adverse impact on the nearby
environment and health and safety of the workers, local community and the beneficiaries. Solid waste
materials during the construction could include paper wrapping, scrap metal, excavated soils, polythene,
plastic and metal will cause pollution and littering of the immediate and localized environment.
This should be addressed promptly and wisely, through best practice methods for waste management and
disposal in and around the program site and these are:
• Conduct regular awareness creation and sensitization program for the proponent and community
reside in the area about the potential negative impacts, health and safety risks, and proper waste
management practices.
• Segregate and store properly with no impacts to be generated from the storage area.
• Final domestic and/or other nonhazardous wastes, after proper segregation, should be disposed of
safely at the designated waste disposal site.
• Contractors (when applicable) should engage a refuse handling company to remove the wastes from
the site to the recommended dumping site.
• Contractors (when applicable) should erect warning signs against littering and dumping sites within
the construction site.
• Excavated top soil should be used as backfill by the contractor.
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
44
• Contractors (when applicable) develop a waste management plan in line with the national policies,
standards and guidelines as well as international standards, including World Bank/IFC
Environmental, Health, and Safety (EHS) Guidelines GENERAL EHS GUIDELINES:
ENVIRONMENTAL WASTE MANAGEMENT6.
Risks from poor maintenance of solar home systems: battery replacement
The lack of technical staff to maintain solar home systems is one the existing problem highlighted during
the field visit that ultimately resulted significant impacts on the surrounding community health and natural
resources. Improper disposal of leftover materials leads to potential water pollution and health risk. Informal
battery recycling, by burning battery cases to extract lead causes air pollution and serious health risk for
those involved in the practice or living in the vicinity. Therefore, the program shall provide:
• Appropriate training for local technical persons, beneficiaries and other parties engaged in the solar
home system.
• Develop a waste management plan to ensure safe disposal of battery and other hazardous wastes.
• Develop the safeguards instruments as per the national standards and international policies and
standards, including WB/IFC procedure and guidelines Environmental, Health, and Safety (EHS)
Guidelines General EHS Guidelines: Environmental Hazardous Materials Management7 and enforce
the implementation of the standards and guidelines for sound management and disposal of used solar
batteries
• The program shall expedite and provide the required support for the preparation of the
national Policy framework on used battery disposal and/or recycling that will be prepared by WB
financed-ENREP AF project under DBE and adopt and implement the implementation of this
framework to ensure best disposal and recycling management practices over the project period.
Fugitive Dust and Noise
Noise resulting from access road and distribution line construction may disturb neighboring communities
and local fauna. This impact will be of a temporary nature and can be minimized by adopting appropriate
mitigation measures including maintaining equipment and vehicles to manufacturers’ standards and limiting
operating times to daylight hours.
Dust will be an issue during the construction of access roads and clearing of vegetation along the ROW,
especially since it is recommended that construction take place during the dry season. However, as most
construction activities will be undertaken remote from residential areas, the impact is not expected to be
major.
Fugitive dust will be localized and experienced only in the specific areas where the construction of access
roads, excavation for installation of substation, earth working for solar mini grid and may be emitted from
activities e.g., excavations and stockpiles of materials, machinery and truck traffic during the construction
phase. This could cause health related impacts to the communities around and workers in the program site.
Dust impacts from vehicular movement on gravel roads could lead to dust pollution in some areas during
6http://www.ifc.org/wps/wcm/connect/topics_ext_content/ifc_external_corporate_site/sustainability-at-ifc/policies-
standards/ehs-guidelines 7http://www.ifc.org/wps/wcm/connect/47d9ca8048865834b4a6f66a6515bb18/1-5%2Bhazardous%2B materials
%2B Management.pdf?MOD=AJPERES
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
45
dry conditions. This impact would be of a short duration during the construction phase. Dust pollution could
also take place during maintenance and inspection of the power lines. This impact will be localized and of
a short duration, and is anticipated to be low significance. Therefore, to minimize and/avoid the anticipated
impacts the contractor shall consider and implement the followings:
• The dirt roads and exposed construction areas should be moisturized during the dry season to prevent
or minimize the fugitive dust emissions.
• Proper location of material stockpiles, especially sand and soil downwind from the commercial,
residential, and other establishments will be required.
• Frequent wetting of the stockpile and working area.
• Screening of or providing wind breaks for stockpiles.
• Workers in the program site must be equipped with the necessary and required Personal Protective
Equipment (PPE) prescribed by the construction industry to mitigate dust impacts.
• Routing of the lines should preferably not be in close proximity to residential dwellings.
• The construction schedule should be communicated with potentially affected parties.
• Construction timeframes should be discussed with property owners.
• Dust-suppression techniques should be used along gravel roads, when required.
Chemical impact
The potential emissions associated with solar energy could be GHG emissions, mercury and cadmium
emissions. These elements are used in making solar components. However, there is no evidence that these
elements are released from solar panels, except during disposal. Therefore, care should be taken during
disposal of solar panel and other related accessories. The proponent shall design best practice method to
implement the disposal practice in consultation with the relevant institutions and ensure no impacts are
resulted to the surrounding social and biophysical environments. Moreover, as a good practice, it is essential
to identify suppliers that have products, particularly solar panels and inverters that comply with ISO or other
industry best practice standards.
Soil Erosion
During the construction phase, activities involving preparation, stripping, grading, soil removal, backfilling,
compacting, disposal of surplus and excavation of the earth surface to pave way for the installation of the
“substations” will lead to localized soil erosion and run off during torrential rains.
The building of foundations for distribution line poles and hybrid mini grids, can potentially exacerbate soil
erosion. Soils can also be impacted because of disposal of waste materials, and compaction with heavy
machinery used for the establishment of poles and the distribution line. This impact is only expected to occur
in the areas where excavation works will be carried out either to construct a substation. These impacts can
be managed by restricting the use of heavy machinery and vehicles to designated work areas and installing
soil protection works in areas sensitive to erosion prior to construction. The followings mitigation measures
are expected to be implemented by the Contractors/Employers
• During site preparation, disturbed soils should be compacted immediately.
• Prevented windblown erosion by soil compaction and wetting the ground to prevent rising of soil
particles.
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
46
• Include an adequate drainage channel that should facilitate drainage and avoid flooding in final site
leveling within the substations.
• A site drainage plan should be developed to protect against erosion.
• Protecting stockpiles with silt fencing and reduced slope angles should be used to minimize soil
erosion during construction.
• Use existing access roads and tracks wherever available.
• Decommission and rehabilitate excess temporary access tracks as soon as they are no longer required.
• Where access is required across agricultural lands use temporary access paths during the dry season
involving placement of geo-textile over aggregates where necessary.
• Minimize the need for access tracks whenever possible.
• Construction to proceed in the dry season if possible to minimize soil erosion and mass wasting and
to limit loss of crops (which are not grown in the dry season); where construction is required in the
rainy season, potentially unstable slopes to be avoided.
Heat or Light Reflection
In case of improper sitting of the solar panels, it may affect the neighboring community members due to
sunlight reflection from the panels, particularly if the panels are angled towards windows, doors or active
service area of the neighbors. If this is not corrected immediately, the reflection affects the neighbors and
other communities living nearby for a prolonged period of the year and become a source of grievance and
social conflict. Therefore, the implementing bodies of the program should follow the standard of placing the
roof top solar panel in north-south direction and conduct regular monitoring of the impacts, if any non-
conformity exists.
Biodiversity
Activities during upgrading of distribution line, opening of Right of Way (ROW), installation of mini-grid
would require clearance of vegetation within the area of interest. Although it is not significant, installation
and Roof Top solar system will have a case to remove where big trees that obstruct the use and efficiency
of solar panels. Such clearance of vegetation will result an impact on the existing fauna and flora species
and ultimately affect the biodiversity of the area. Generally, the anticipated impacts will not have potential
adverse impacts on terrestrial and/or aquatic biodiversity. However, it is essential to consider and ensure the
flowing measures:
• Assess the status and presence of sensitive species in the area.
• Check no sensitive fauna and flora species are found within and around the construction area that are
affected by the program activities
• Plan accordingly to minimize or avoid the sources of impacts during preconstruction phase.
• Make sure that pruning should only practice to remove branches that are associated with efficiency
of the solar energy system
Occupational health and safety (OHS)
Occupational health and safety issues are among the main concern of the program, which the ESSA
identified during site visit and consultations that were conducted at regional and local levels. The significant
concern of OHS will arise during the program implementation periods, predominantly during stringing,
operation of equipment and machinery during construction, operation and installation of mini-grid, which
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
47
causes a likelihood of accidents occurring especially to the workers. The potential for accidents and hazards
occurring in the “substation” during the operation of the equipment is a likely adverse impact that could lead
to loss of life or injury to the workers. These work places and health and safety risks include:
• Electrocution hazard during operation of generating plants and installation and maintenance of
power distribution lines.
• Injury from falls when working at heights or from falling objects.
• Injury or fatality from heavy construction equipment.
• Improper use and lack of availability of the required Personal Protective Equipment (PPE).
• Injury during excavation for mini grid structure, poles erection, etc.
All Environmental and social management procedures and processes recommended to be implemented
during program implementation period are designed to protect public and worker safety against the potential
risks associated with:
• construction and/or operations of facilities or other operational practices developed or promoted
under the program;
• exposure to toxic chemicals, hazardous wastes, and otherwise dangerous materials; and
• reconstruction or rehabilitation of infrastructure located in areas prone to natural hazards. This will
be implemented in line with core principles 3 and national and WB/IFC-Environmental, Health, and
Safety (EHS) Guidelines GENERAL EHS GUIDELINES: OCCUPATIONAL HEALTH AND
SAFETY8.
Specifically, to avoid these safety hazards and risks, the following general safety measures and those stated
below in the box 2 and 3 need to be considered during program implementation period.
• Ensure safe handling and use of PPE.
• Ensure the availability and proper use of PPE by the program beneficiaries, contractors, laborer who
are engaged in the construction, installation and operation and maintenance of the proposed program
• Monitor regularly the use and availability of PPE and other protective tools and materials by the
program coordination unit at all phases of the programs.
• All workers entering the construction site must be equipped with PPE including goggles, safety
shoes, overalls, gloves, dust masks, among others. The PPE should be those that follow the
international standards of PPE.
• ONLY competent workers and staff should be allowed to operate any machinery and equipment to
reduce the incidents of accidents.
• During the construction, the program site should be completely sealed off and warning signs erected
informing the public to keep off the construction site when construction is in progress.
8 http://www.ifc.org/wps/wcm/connect/9aef2880488559a983acd36a6515bb18/2%2BOccupational%2
BHealth%2Band%2BSafety.pdf?MOD=AJPERES
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
48
• Personal protection gear applicable to the activities must be provided and its use made compulsory
to all.
• Fire risks are possible due to improper storage facilities and lack of fire drill and this requires
provision of regular training and awareness creation to the workers and the community around.
• For any incidents of leakage or spill during installation, temporary containment structure is required
to clean-up accidental spills.
• Provide regular OHS induction training for staffs before mobilization to work
• Create awareness to the community reside nearby and ensure their understanding of the potential
safety and health impacts and respective measure
• Personal protection gear will be provided and its use made compulsory to all. The entire workforce
should be trained in the use of protective gear, handling of chemical products and acid storage cells,
electric safety equipment, procedures for entering enclosed areas, fire protection and prevention,
emergency response and care procedures.
• Training given to the employees should be backed by regular on- site training in safety measures.
• Machines and Equipment must be operated only by qualified staff and a site supervisor should be on
site at all times to ensure adherence.
• The contactor must develop workers’ Health and Safety Manual for which all the workers should be
conversant with for response in case of accidents.
During construction period, the contractor and other parties may use child labor due to lack of awareness on
the proclamation and the negative impact of child labor. Therefore, contractors and other participating
companies are not allowed to use child labor at any stage of the sub-projects implementation. Contractor
will be aware to enforce and respect the national Proclamation No. 377/2003 which states that children under
the age of 14 will not be employed and young workers (14 to 18 years) shall not perform work that is likely
to jeopardize their health or safety.
Cultural Heritage
Cultural resources include archeological sites, historic buildings, and sacred places. Potential impacts to
cultural resources could occur in two ways: 1) ground disturbing activities could result in the loss of or
damage to archeological artifacts or unmarked burial sites; or 2) the views and site lines to or from an
important historical site could be adversely affected by the physical presence of a substation upgrading and
TML activities. Both potential impacts must be considered when final selection of program sites and
distribution or upgrading power lines is conducted.
ELEAP should not affect any cultural heritage. During program implementation, it is important to ensure
that Program activities do not influence a place or building having aesthetic, anthropological, archaeological,
architectural, cultural, religion, historical or social significance or special value for present and future
generations. In order to minimize or avoid such impacts, all-necessary measures should be considered at the
subproject design phase and due attention should be paid during screening of the Program activities in
consultation with relevant institutions and activities shall be implemented in a manner consistent with
national and international policies and standards.
Polychlorinated biphenyls (PCBs) Impacts
PCBs used to be widely used as insulators in electrical equipment, including transformers, capacitors,
switches, voltage regulators etc. They are of concern because they are powerful toxins, even at low
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
49
concentrations, and they persist and bio-accumulate in the environment creating adverse health impacts and
adverse ecological changes. Refurbishment of any substations and upgrading/rehabilitation work of the
power line will need to check whether any such old transformers/equipment will be replaced and appropriate
safeguards taken. This is not an issue with new transformers, as they will not contain PCBs.
Health Effects of Electromagnetic Fields (EMF) Impacts
Electric and magnetic fields (EMF) are invisible lines of force that surround any electrical device. Power
distribution lines, electrical wiring, and electrical equipment all produce EMF. There are many other sources
of EMF as well. Electric fields are produced by voltage and increase in strength as the voltage increases.
Magnetic fields result from the flow of current through wires or electrical devices and increase in strength as
the current increases. Most electrical equipment should be turned on, i.e., current must be flowing, for a
magnetic field to be produced. Electric fields are often present even when the equipment is switched off, if
it remains connected to the source of electric power. In summary, voltage produces an electric field and
current produces a magnetic field. Electric fields are shielded or weakened by materials that conduct
electricity, even materials that conduct poorly, including trees, buildings, and human skin. Magnetic fields,
however, pass through most materials and are therefore more difficult to shield. However, both electric fields
and magnetic fields decrease rapidly as the distance from the source increases. As a precautionary measure,
ELEAP will adopt nationally accepted standards for ROW develop by the EEA and the respective
institutions, and if required, in some area international standard for ROW will be effective along the high
voltage distribution lines. All habitation and structures are excluded from the ROW to ensure safety of people
and animals from EMFs as well as from direct electric shocks and “flashover.” EEU and staffs working on
safety risk area will take the required safety responsibility to ensure no or minimum impacts to workers and
community nearby.
Fire risk
The risk of fire outbreaks during bad weather e.g. storms, winds etc. cannot be overruled especially when the
pole crash or if electrical faults occur. Also, failure to maintain the ROW could cause the overgrowth of
nearby trees that could end up crashing on the lines during poor weather and hence cause fire outbreaks of
black outs. Given the stringing activities in LV and MV is expected to be insulated, there will be no or
minimum impacts are expected. However, the followings are the mitigation measures to be considered by
Employer and the Contractors:
• A robust fire prevention program and fire suppression system should be developed by the contactor
for use in each work areas.
• All the site must contain firefighting equipment of recommended standards and in key strategic
points. This should include at least, Carbon dioxide systems, Detection/alarm systems, and portable
fire extinguishers among others.
• A fire risk management and evacuation plan must be prepared and posted in various points of the
cabins including procedures to take when a fire is reported.
• The Program should continuously ensure that the ROW is kept clear by regular trimming of trees
and maintenance.
Bird Strikes/Collusions
Distribution networks could be a limited source of bird strikes that get entangled to the lines causing their
injury or even instant death. This is especially more significant when large flock of birds migrates from one
point to another and usually gets struck by these distribution lines. However, the Program will entail insulated
power line, hence the risk of electrocution expected to be none or minimal, and no power line is pass through
any known migratory bird routes. The Program closely works with the MoEFCC and other organization like
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
50
Ethiopian Wildlife and Natural History Society (EWNHS), Ethiopian Institute of Biodiversity (EIB) and
MoANR to identify the potential birds’ migration route within the program area, if available and ensure
implementation of sound precaution and mitigation measure, like installation of habitat disturbance flapper
or balloon on the power line to avoid and/or minimize the anticipated impacts.
7.2.2 Negative Social impacts
The anticipated negative social impacts of the Program are not expected to be significant provided that land
and ROW acquisition are conducted in a manner consistent with the national standards and policies. The
main social risks include the following:
• Risks from provision of electricity to households and businesses:
There is possibility of safety risks with project activities that will have negative impact in the community if
not properly addressed. Risk of electrocution from substandard internal wiring, meter tampering, illegal
connections, or lack of knowledge of electrical systems is among the concern for future action. Safety threats
also include the collapse of distribution poles, especially wooden ones during storms.
• Risks from land and RoW acquisition:
Project Affected People (PAPs) might lose part of their livelihoods in the process of clearing vegetation for
the ROW, such as their cash crops including coffee plants, false banana (inset), mango, eucalyptus, and
other trees. Moreover, during construction foundation, erection as well as stringing of distribution lines can
involve movement of machinery, which may cause damage to crop that impact agricultural activities, and
the livelihoods of PAPs.
PAPS may also lose part of their land under various use or other properties. The proposed route options may
have impacts on the existing land use, both temporarily and permanently Land might be acquired for access
roads, workers camp, workers’ residence, solar panel installation. If the village benefiting from off-grid
solutions is to be connected to the main grid, ancillary features, including access roads and power
transmission/distribution lines to connect a project to an existing electrical grid, can result in significant land
use disturbances.
The PAPs may not be able to replace land or assets required, if there are cases of inadequate amount of
compensation or pressure to contribute land voluntarily that results in diminished quality of life for the
people affected.
• Risk that vulnerable groups will not share equitably in project benefits provision of electricity to
communities:
Women embrace disproportionately large number of poor in most countries due to gender discrimination.
The situation limits the women to have access to resources, opportunities, and public services necessary to
improve the standard of living for themselves and their families. In majority of rural areas of Ethiopia,
women’s economic activities are limited to household management and some major farm practices like
weeding and so on. Female-headed households may be disadvantaged in obtaining access to electricity
Persons with low income – the poor, elderly, or with disability – may not be able to afford the cost of
connections or of proper internal wiring. Underserved people and vulnerable groups may not be able to
benefit fully from the provision of electricity due to their life style (for instance pastoralists). Projects may
also be located in an area with the potential for containing tangible cultural resources
• Risks related to Labor Influx
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
51
The in-migrant people for job opportunities will bring both positive and negative impacts to the local people.
Some of them will have different cultural backgrounds that might be important for the culture of the local
communities and will bring more social interactions, skill transfer, and other socio-cultural developments.
Labor influx in line with ELEAP might be minimal ,though workers’ accommodations may need to be
constructed on-site. Workers’ accommodations require provision of potable water and availability of
wastewater, and solid waste disposal services. This may result in impacts on community infrastructure,
health, and safety. The influx of labor to the construction areas and their interactions with the local
communities may create access for the spread of communicable diseases and price increases in the area.
Food prices on local markets might increase, security and smuggling issues might arise and women from
local communities might be at risk of Sexually Transmitted Diseases (STDs) and unwanted pregnancies.
Preparation and implementation based on Labor Influx Management Plan is vital. The mitigation plan should
take an approach to control the spread of STIs. Health education programs, control of illegal/illicit drugs
and prostitution, and other socially condemned activities near the project site need to be included. Moreover,
mechanisms need to be put in place to prevent and minimize Gender Based Violence(GBV) and Violence
Against Children (VAC).Such mechanism should include working with the contractors to prevent sexual
harassment in the workplace and GBV and VAC in the project affected communities (for example through
code of conducts), strengthening grievance redress and other monitoring mechanisms to ensure safe and
ethical reporting systems to alert cases of GBV and VAC and assure them to access adequate response.
Risk that community benefits are not Sustainable-Power available for the extension to the grid may be
insufficient, resulting in black-outs. Demand may exceed supply, especially in some of the villages and small
towns that will eventually grow into big urban centers due to large scale infrastructure development such as
roads.
To conclude, most of these risks can be mitigated,
• Through awareness on hazards of electricity to the community, customers.
• Working based on Ethiopia Energy Authority standards and house wiring inspections, and programs
to assist the vulnerable groups.
• Ensuring participation of project affected people that incorporate vulnerable groups and underserved
communities in ongoing consultation throughout the design and implementation of the project.
• Establishing effective Grievance Response Mechanism and equitable and fair benefit sharing
• Carrying out acquisition of land and ROW processes in accord with, the national system and Core
Principle 4, using a resettlement guideline that includes the required procedures.
• Using local workers as much as possible to minimize influx. Furthermore, it is vital to prepare and
use labor influx management plan to manage related risks.
Further details of environmental, social and safety impacts and management are provided in the Annex 6
and 8.
8. SAFETY MANAGEMENT
Occupational Health and Safety (OHS) risk is one of the concerns that need to be considered and managed
properly to minimize risks and ensure efficient implementation of safety management practices measures
over the ELAEP implementation period. The potential occupational health and safety impacts that could be
generated from the construction activities of the program include, but not limited to:
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
52
• Exposure to physical hazards
• Exposure to dust and noise
• Falling objects
• Falling from height
• Electrocution
• Skin rush due to chemicals like PCBs
• Work in confined spaces
• Exposure to hazardous materials
• Exposure to electrical and other sources of hazards (Box 2)
Box 1. The Electric Accidents Hazards
To avoid and/or minimize the anticipated occupational health and safety (OHS) risks and impacts associated
with the program activities, the Contractor and Employer (EEU) are required to prepare a detailed safety
management plan, defining potential OHS issues and respective mitigation measures. More specifically,
the Contractor (when applicable) shall commit to prevent and manage these impacts and risks in an
acceptable way and comply with the required OHS national and international standards during
construction period. Among others measures expected to be taken by the Contractor:
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
53
• Effective implementation of safety prevention and control measures
• Develop safety training plan and conducting safety trainings
• Raise awareness and sensitization to workers and nearby community members;
• Maximize safety knowledge of supervisors, workers and any other relevant stakeholder so that they
can take their own responsibilities for preventing and avoiding safety risks, and avoid the occurrence
of any incidents
• Support Program staff and other relevant institutions in managing the safety risks associated with
the Program
• Develop notification and monitoring plan
• Conduct regular monitoring
• Adopt the general safety practices (Box 3)
• Be responsible on managing safety risks (Box 4)
Box 2. General safety practices
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
54
Box 3. General safety Responsibility applicable for ELEAP which is adhered by EEU
8.1 Use of PPE and safety protection material
Inadequate availability and use of personal protective equipment (PPE) and safety protection material and
tools were highlighted during the ESSA assessment and recommendations provided on the interventions
needed to fulfil all the necessary provision to ensure no/minimum safety risks. The EEU and Contractors are
required to include detail Health and Safety considerations/articles in their contract agreements and make
sure that any incidents and serious health and safety risks emanating from the Program’s activities to the
workers and community members residing within and around the program implementation area (within 3km
from the existing distribution network) are taken into account. The Program should also assign high priority
to the availability of safety materials and tools and Personal Protective Equipment (PPE) for all staffs and
laborers at all levels, before the beginning of construction activities (Box 5 and Figure 7).
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
55
Box 4. Personal Protective Equipment (PPE)
Figure 6: Typical PPE and safety protection materials
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
56
8.2 Indicative Safety Monitoring and Reporting
8.2.1 Monitoring
The Contractor, before commencement of construction works, shall develop a detailed monitoring plan to
check the effectiveness of safety measures during implementation. The general practice in monitoring is to
ensure the management of potential negative impacts generated from construction activities through sound
implementation of prevention and control measures. Together with the development of a monitoring plan,
the Contractor shall conduct regular monitoring of all prevention and control measures to ensure the
effectiveness of safety measures.
The Engineer and/or Health, Safety and Environment (HSE) manager of the Contractor, shall be responsible
for keeping record of monitoring activities. The Contractor should carry out daily/weekly/monthly/ quarterly
inspections for any events/incidents related to Program implementation, risks and impacts, and the prevention
and control measures set in place (Box 6). The documentation of daily/weekly/monthly/quarterly inspections
and monitoring shall be carried out to ensure that safety management activities are being properly carried
out.
8.2.2 Reporting
The Field Team
The Field team (Sub-contractor, Constructor’s team assigned at each construction sites, and others directly
engaged in the construction activities at the site level) shall report monitoring and inspection results, any
incidents/events not anticipated, and non-conformity/non-compliance activities and events associated with
the construction activities causing significant safety and health impacts to the workers and nearby community
members. These results shall be submitted to the contractor as soon as possible, with the details of the events
and incidents (Figure 8).
The daily/weekly/monthly/quarterly report, as agreed, shall include at least:
• Summary of activities undertaken during the reporting period;
• Deviations or non-compliances to the Employer HSE policy, contractor SMP, Contractor’s ESMP, and
other relevant legal and safeguards documents;
• Frequency of monitoring/inspections conducted during the reporting period;
• Summary of findings and results of monitoring and inspections activities;
• Planned inspection and monitoring activities during the next reporting period; and
• Where evidence of unforeseen impacts is identified, or the prevention and control measures implemented
appear to be inadequate, reporting of a list of unforeseen impacts and their respective additional control
and prevention measures should be provided.
The Contractor
The Contractor shall report to the Employer (EEU) the results of the monitoring and inspections undertaken
in accordance with the relevant components of the SMP and Contractor’s ESMP regularly incidents (Figure 8).
The daily/weekly/monthly/quarterly report shall include:
• Summary of activities undertaken during the reporting period;
• Deviations or non-compliances to the Employer HSE policy, contractor SMP, Contractor’s ESMP, and
other relevant legal and safeguards documents;
• Frequency of monitoring/inspections conducted during the reporting period;
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
57
• Summary of findings and results of monitoring and inspections activities;
• Planned inspection and monitoring activities during the next reporting period; and
• Where evidence of unforeseen impacts is identified, or the prevention and control measures implemented
appear to be inadequate, reporting of a list of unforeseen impacts and their respective additional control
and prevention measures should be provided.
The contractor is also expected to further update and use the indicative safety inspection checklist annexed
herewith during site inspection/monitoring (Annex 13). The checklist shall be filled regularly for each
construction activities of the program in a daily/weekly/monthly basis, as applicable. The Contractor shall
submit the final signed checklist to the Employer as an attachment together with the inspection/monitoring
report.
The Employer
The Employer is responsible to collect and compile all inspection and monitoring reports on time and report
to the World Bank on time, based on the significance of the incidents (Figure 8 and Box 6). The summary
of the checklist report will be attached to the monthly incident report and/or quarterly environmental and
social safeguards report. In case of any major incident or in case of grievance, the report will be submitted
to the World Bank upon notification received from the Contractor or other parities, when the cases are under
process and/or completed. The Employer shall provide a written report (in English) to the World Bank and
including, as a minimum, the following information:
• Date, Type and Scale of incident/event occurred;
• Confirmation of incident monitoring/inspection result (including monitoring/inspection location, date
and time of monitoring/inspection, inspection/monitoring result, date and time of the Contractor’s
monitoring/inspection result; and applicable Program standard);
• Actions taken in response to incidents due to electric hazards, falling from working at height on poles,
contact with live power lines);
• Additional recommendation on prevention, control and treatment of the (actual or potential) incidents;
• Additional inspection/monitoring activities to address safety issues and return to compliance;
• Confirmation of closeout of non-compliance conditions, or timetable for closeout (timetable to include
further monitoring and reporting to World Bank); and
• Proposed plan for submission of next follow-up report on inspection and monitoring.
Figure 7: Indicative reporting flow chart for detail written incident report
:
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
58
8.3 Notification
The Field team
The Field team (Sub-contractor, Constructor team designated for each site, and others directly engaged in the
construction activities at the field level) shall immediately notify the contractor about incidents and events of
non-compliance associated with the construction of distribution power lines causing significant impacts to
the workers and nearby community members/passer-by. The detailed events and incidents written reports
shall be prepared and submitted to the contractor within 72 hours (Figure 9). If the issues are not resolved in
the follow-up, reports shall be prepared periodically, until the safety issues are resolved and closed.
The Contractor
The Contractor shall notify the Employer about the incidents/unforeseen events associated with construction
activities of distribution power lines within twenty-four (24) hours after receiving the notification from the
Field team (Figure 9). The contractor is required to establish a strong communication mechanism/system
among the Employer-Contractor-Field teams to facilitate smooth notification and reporting processes among
all three parties, so as to ensure in time dissemination of notifications and information on safety matters and
incidents. The contractor shall also prepare and submit the follow-up detail written incident or non-
compliance report to the Employer within one week, based on the reports from the Field team.
The Employer
After receiving a notification on incidents from the contractor, the Employer shall accordingly notify the
World Bank as soon as possible not later than twenty four hours (24 hours), Figure 9. The employer shall
also prepare a detail written report on the incidents based on the information from the Contractor and submit
it to the World Bank.
Figure 8: Indicative flow chart for the notification of incidents
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
59
Box 5. Points on Accident reports, records, and investigation
9. TRAINING AND CAPACITY BUILDING
9.1 Overview
The ELEAP is designed to establish and strengthen the capacity building architecture to ensure sound
technical capacity on environment, social and safety matters at all levels of EEU and MoWIE through
adopting a systematic, cascading, and coordinated vision and approach. Skill development within the sector
institutions is a core aspect of the sustainability of the NEP, and is therefore, a key focus of ELEAP. The
continual and rapid expansion of electrification in Ethiopia will require extensive capacity-building support
not only for the electricity sector institutions, the MoWIE and EEU, but also for the broader sector
participants such as academic institutions (universities and vocational training centers) and community and
other local stakeholders.
ELEAP capacity building activities would continue to focus on all three levels of governments and tailored
to each of their needs, as elaborated below. Selected NEP activities related to skill development, including
environmental, social and safety management will be supported by ELEAP and/or related World Bank
operations.
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
60
(a) Sector institutions (EEU and MoWIE). Comprehensive training, technical assistance, and capacity-
building support will be provided for sector institutions for technical and planning skills development,
program management, M&E, fiduciary systems and safeguards management, as well as for transition
to customer-oriented business processes. These activities not only aim to strengthen the technical
capacity of the utility and its staff but also target improving commercial operations and utility
performance.
(b) Academic institutions. EEU has an ongoing program to recruit and train recent university graduates,
as well as technical and vocational education and training (TVET) program graduates. Deeper
interlinks will be supported with relevant local universities and TVET institutions to prepare a pipeline
of skilled labor force for the electricity sector.
(c) Community and local stakeholders. Capacity development support will also be provided to broader
stakeholders in the electricity sector, such as community groups, local industry participants, women,
and civil society organizations.
The intended capacity-building and technical assistance activities are required during Program preparation
and implementation to ensure the implementing agencies’ compliance with environmental and social
safeguards and safety management practices:
During program design and implementation period, substantive capacity building and technical assistance
program shall be designed and implemented on environmental and social safeguards and safety assessment
and management practices through provisioning and improving of human and financial resources, provision
of trainings and other logistics facilities.
The training and capacity building activities proposed to support ESMSG implementation are:
a) General training and awareness/sensitization provided by MoWIE, EEU (or their Regional
equivalent) and REFAs.
b) In depth training for relevant Regional Energy and EEU bureaus responsible for the project and EHS
staffs on implementation of the ESMSG including all aspects of environmental, social and safety
management, ESMP, SMP, A/RAP, public consultation, and integration of environmental, social and
safety management plans into development planning;
c) Technical and financial assistance to each EEU-EHS units at national and regional level that
participate in program’s EHS implementation to:
➢ Produce a Screening Report, an ESMP and other safeguard instruments TOR, an
Environmental and Social Management Plan (ESMP), Safety Management Plan (SMP) or
abbreviated/Resettlement Action Plan (A/RAP); and
➢ Establish and support operation of systems for monitoring and reporting on Environmental
and Social Management Plan (ESMP), Safety Management Plan (SMP) or
abbreviated/Resettlement Action Plan (A/RAP) implementation.
d) Appointment of one Environmental and Social Specialist and one Occupational Health and Safety
specialist in each regional EEU offices who are responsible for overall ESMSG implementation.
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
61
9.2 ESMSG TRAINING
During the assessment period, the ESSA team found that the existing technical capacity on environment,
social and safety management practices as well as preparation and implementation of instruments at regional
and district levels is limited. Therefore, provision of an induction training before the commencement of each
activities and a consecutive on job training throughout the program implementation period are vital to ensure
the capacity of implementing parties at all levels are at acceptable level.
Training to EEU-EHS specialists, and line agency staffs including Energy Bureaus at the regional level on
environmental, social and safety impacts and risks management, is required in the form of a phased training.
This general training and awareness/sensitization program will be developed as a training module. The
training will specifically aim to build awareness and sensitize a broad audience, particularly Managers and
Bureau Heads of EEU, MoWIE, Regional energy bureau and MFI, PSE specialists to the requirements and
key aspects ESMSG. In addition to what is stated below, a detail training plan will be prepared by EEU that
comprises all areas of EHS.
An example of an agenda for a proposed one-day training workshop on ESMS implementation and indicative
training outlines are given in the Boxes 6,7,8 below.
Box 6. Possible Agenda for a 2-day Workshop Introducing the ESMSG
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
62
Box 7. Indicative Training Topics and Schedule
Box 8. Integration of Environmental Management into Development Planning
9.3 Technical and Financial Assistance
EEU will carry out a consultative assessment exercise to determine the existing capacity/capability and the
support requirements for each of the participating regions in terms of their ability to successfully:
➢ Produce a Screening Report
➢ Produce an Environmental and Social Management Plan, Safety Management Plan, or
Abbreviated/Resettlement Action Plan
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
63
➢ Establish and support operation of systems for monitoring and reporting on ESMP, SMP and
A/RAP implementation.
9.3.1 Appointing Environmental, Social, Health and safety officers to EEU Regional Offices
Environmental, social, safety, and health officers are required to be positioned at the EEU head office and
regional EEU offices, as a minimum condition before start of the Program. As the implementing agency of
main activities under the Program, EEU is required to have sufficient staff with expertise in environmental
and social safeguards and health and safety at the national and regional levels. The regional EEU offices will
have an environmental, social, and safety units with relevant specialists (including at least one environmental
and social development specialist and one health and safety specialist, who will be subordinated to regional
EHS coordinators). The EHS department/unit at national and regional levels will also work in close
collaboration with MoWIE’s Environment and Climate Change Directorate and the MoEFCC at the national
level and with regional environmental authorities and labor and social affairs bureaus and other Government
organizations, whenever appropriate. The EEU unit shall also be equipped with all facilities, including
logistics, budget, and safeguards monitoring tools and instruments.
In this regard, it is important that an EHS department under EEU national and regional offices shall be
established and strengthened to provide overall support in supervising the implementation of the ESMSG
and coordinating with the relevant stakeholders involved in the Project.
The Specialists will contribute to the objectives of the Program which include:
➢ The preparation, together with the implementing entities, of annual work programs and budgets;
➢ Monitoring project progress as it relates to compliance with the ESMS guidelines, resolving
implementation bottlenecks, and ensuring overall that project implementation proceeds smoothly;
➢ Collecting and managing information relevant to the project and accounts (i.e. environmental
monitoring and audit reports – of ESMPs, SMPs, and RAPs ARAPs); and
➢ Ensuring that the implementing bodies are supported adequately and that they adhere to the
principles of the project, specific to compliance with ESMS guidelines.
The Specialist should be hired on a fulltime basis and will report to the main bodies responsible for execution
of the Project.
9.3.2 Indicative Terms of Reference for ELEAP Environmental and Social Specialist
OBJECTIVE: To provide technical advice on environmental management and mitigation, and ensure that the
ELEAP ESMS is fully implemented.
➢ Tasks
• Establish the system of screening forms and set out in this ESMSG, and oversee their smooth
operation in the implementation of ESMSG;
• Liaise with the Ethiopia EPA on a regular basis;
• Commission an independent auditing firm/agency to carry out an environmental performance
independent annual audit based on EEU quarterly and annual internal reporting, for submission
to MoWIE and CSA (for verification):
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
64
• Provide specific technical advice on mitigation measures for labor intensive projects;
• Provide technical advice to EEU on all technical issues related to natural resources, environment,
social and safety management. These issues will relate to impacts on surface water, groundwater,
agricultural resources and vegetation, sourcing of materials used in construction, human health,
physical and chemical hazards, EMF impacts, ecology and protected areas, land and soil
degradation;
• Raise awareness and proactively create demand for EHS technical advice among EEU officers;
• Liaise with the Regional EEU and district offices to ensure the project’s compliance with the
ESMSG, RSG, other safeguards instruments and all EHS aspects of the program;
• Be responsible for collating information related to the ESMSG, RSG and resettlement, if required;
• Undertake review of ESMP, SMP and A/RAPs to ensure compliance with the ESMSG and RSG;
and
• Lead the delivery of capacity building programs for EEU officers and technicians.
10. MONITORING, ANNUAL AUDIT AND REPORTING OF ESMSG
IMPLEMENTATION
10.1 Monitoring
Monitoring will be a continuing process throughout the life of the ELEAP, from installation and construction
phase up to operation and decommissioning phase. The purpose of monitoring is to establish benchmarks so
that the nature and magnitude of anticipated environmental, social and safety impacts can be continually
assessed ensuring the achievement of ESMSG objectives. Monitoring of activities during implementation of
the program and ESMSG will be continuous throughout program implementations with quarterly and annual
reviews to determine and guarantee the effectiveness of ESMSG measures and procedures.
The objectives of monitoring are
i) To alert program implementers by providing timely information about the success or otherwise of
the environmental, social and safety management process outlined in this ESMSG in such a manner
that changes can be made as required to ensure continuous improvement to ELEAP’s environmental,
social and safety management process (even beyond the Program period).
ii) To make a final evaluation to determine whether the mitigation measures incorporated in the
technical designs and the EMP have been successful in such a way that the pre-project environmental,
social and safety management condition has been restored, improved upon or, if worse than before,
determine what further mitigation measures may be required.
The ESMSG implementation indicators to be monitored during project implementation period include the
following, but not limited to:
• Number of field supervisions undertaken;
• Number of inspection checklist filled and reported;
• Number of ESMPs developed, as applicable;
• Number of written warnings of violations of ESMSG issued to contractors, in case of non-
compliances;
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
65
• Number of recommendations from the supervisions, annual review and monitoring that have been
implemented by the beginning of the following year;
• Number of staff and daily laborers at all levels trained in the implementation of this ESMSG, SMP;
and,
• Number of staff at federal, regional and district/field levels attending training course in ESMSG,
SMP, A/RAP, ESMP, and other safeguards instruments.
The ESMSG training component is monitored through indicators of number of specialists at EEU, EEU staff
at Regional and Woreda levels, Regional and Woreda energy experts, focal points, elders, beneficiaries, and
community members etc. trained and the topics covered.
Follow up on previous recommendations is monitored through the number of recommendations from the
annual review that have been implemented. The indicators are deliberately very simple. Despite their
simplicity, the integration of these indicators into Program monitoring & evaluation systems provides a
guarantee that the ESMSG will be implemented in full over the program implementation period.
The Monitoring and Evaluation Team and/or the EHS Coordination Team within, and MoWIE, who will
lead and oversee the implementation of any corrective measures that are required. Monitoring and evaluation
is necessary to ensure that (i) the ESMSG process is being implemented appropriately, and (ii) the mitigation
measures are being identified and implemented. This will enable to identify various issues that necessitate
amendments in the ESMSG to improve its effectiveness.
10.2 Annual Audit
The annual independent audit on ESMSG implementation will be conducted by an independent
auditor/agency based on the quarterly and annual reviews produced by EEU. The independent auditor will
submit the audit to MoWIE, who will then in turn submit to CSA for verification of results for disrbursements
by the WB under ELEAP. The Annual Audit also provides a strong incentive for EEU and MoWIE to ensure
effective implementation of the ESMSG. An Annual Audit Report will include a summary of the
environmental performance of the Program, based on the recommended measures indicated in the ESMSG;
presentation of compliance and progress in the implementation of the ESMSG and other safeguards
instruments; and a synopsis of the environmental monitoring results from individual program monitoring
measures (as set out in the project ESMSG, ESMP, SMP, A/RAP), at local level.
The main tasks of the audit study will be to the review EEU annual reporting (base on quarterly reporting),to
include:
• Consideration of the description of the program activity and site description;
• Indicate the objective, scope and criteria of the audit;
• Study all relevant environmental law and regulatory frameworks on health and safety, sustainable
use of natural resources and on acceptable national and international standards;
• Verify the level of compliance by EEU with the conditions of the ESMSG, ESMP, SMP, etc.;
• Evaluate the implementing agencies’ knowledge and awareness of and responsibility for the
application of relevant legislation;
• Review the internal annual report provided by EEU based on existing project documentation related
to all infrastructure facilities and designs;
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
66
• Examine monitoring programs, parameters and procedures in place for control and corrective
actions in case of emergencies;
• Examine records of incidents and accidents and the likelihood of future occurrence of the incidents
and accidents;
• Inspect all buildings, premises and camps in which areas where goods are stored and disposed of
and give a record of all significant environmental and safety risks associated with such activities;
• Examine and seek views on health and safety issues from the project employees, the local and other
potentially affected communities;
• Evaluate the training plan and its implementation;
• Prepare a list of safety, health and environmental concerns; and
• Identify any outstanding environmental, social and safety issues and provide recommendations
along with the responsible body and appropriate timeframe
Based on the internal annual EEU report, the independent audit team will report to MoWIE who will send
the report for verification to CSA, for disbursement under ELEAP based on results achieved taking into
account the following points:
• To what extent environmental and social considerations are being incorporated into the planning
process;
o To check that Program activities are being correctly screened.
o Other safeguards instruments (ESMP, PESIA, ARAP, SMP, RAP) have been duly prepared and
approved by the relevant competent agencies
o That mitigation measures, as set out under the ESMPs, RAPs and SMPs, are being identified and
implemented by EEU.
o To identify any amendments in the ESMS approach that are required to improve its effectiveness.
• The annual audit also includes the overall performance of ESMSG, ESMP, SMP, A/RAP preparation,
and implementation, as required. Over all the audit report will include:
o A summary of the environmental and social performance of the ELAEP, based on a sample of
visit at program activity sites;
o A presentation of compliance and progress in the implementation of the project ESMPs, SMPs
and A/RAPs;
o A synopsis of the environmental monitoring results from individual project monitoring measures
(as set out in the project ESMPs, SMPs, and A/RAPs).
10.3 Reporting
To monitor the progress of the implementation of the measures that have been identified in this ESMSG,
EEU quarterly and annual reports, as well as independent audit, will be carried out as outlined in the above
section. The principal output of EEU quarterly and annual reports is to present the methodology used for
reporting, summarize the results, and provides practical recommendations, to be then audited. Distinct
sections should address: a) ESMSG, ESMP, SMP, A/RAP and other safeguards instruments implementation
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
67
performance, and b) cumulative impacts and the respective measures. Annexes should provide the detailed
results of the fieldwork, and summarize the number of program activities supervised by the respective
national and regional teams and their nature of status of implementation according to the ESMSG and other
instruments. Copies of the annual audit and quarterly performance review report should also be delivered to
the EEU EHS unit, to each relevant Regional and National Government office responsible for appraisal,
approval, and implementation of projects. To ensure early detection of critical environmental and social
conditions and to provide information on the mitigation progress and results, reporting deadlines shall be not
later than one month after supervision of the program activity period.
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
68
11. ANNEXES
Annex 1: Screening Form
ELEAP construction works project name:
Location (include map/sketch), if applicable: (E.g. region, district, kebele, etc.)
Type of activity: (e.g. excavation, pole
erection, stringing, new construction,
rehabilitation, etc.)
Estimated Cost: (Birr), if applicable
Proposed Date of Works Commencement
Technical Drawing and Specifications
Reviewed, if applicable:
(circle
answer):
Yes No
This report is to be kept short and concise.
1. Site Selection:
Physical data*:
Site area and total distance covered, if applicable
Extension of or changes to existing alignment
Any existing property to transfer to project
Any plans for new construction
* Yes/No answers and bullet lists preferred except where descriptive detail is essential. **Refer to project
application for this information.
2. Impact identification and classification:
When considering the location of a ELEAP’s construction and stringing works, rate the sensitivity of the
proposed site in the following table according to the given criteria. Higher ratings do not necessarily mean
that a site is unsuitable. They do indicate a real risk of causing undesirable adverse environmental and social
effects, and that more substantial environmental and/or social planning may be required to adequately avoid,
mitigate, or manage potential effects. The following table should be used as a reference.
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
69
Impact Identification and Classification
Issues
Site Sensitivity Rating
Low Medium High
Natural habitats No natural habitats
present of any kind
No critical natural
habitats; other
natural habitats occur
Critical natural habitats
present
Water quality
and water
resource
availability and
use
Water flows exceed any
existing demand; low
intensity of water use;
potential water use
conflicts expected to be
low; no potential water
quality issues
Medium intensity
of water use;
multiple water users;
water quality issues
are important
Intensive water use;
multiple water users;
potential for conflicts is
high; water quality
issues are important
Natural hazards
vulnerability,
floods, soil
stability/
erosion
Flat terrain; no potential
stability/erosion
problems; no known
volcanic/seismic/ flood
risks
Medium slopes;
some erosion
potential; medium
risks from volcanic/
seismic/ flood/
hurricanes
Mountainous terrain;
steep slopes; unstable
soils; high erosion
potential; volcanic,
seismic or flood risks
Cultural
property
No known or suspected
cultural heritage sites
Suspected cultural
heritage sites; known
heritage sites in
broader area
of influence
Known heritage sites in
project area
Involuntary
resettlement
Low population density;
dispersed population;
legal tenure is well-
defined; well-defined
water rights
Medium population
density; mixed
ownership and land
tenure; well-defined
water rights
High population
density; major towns
and villages; low-
income families and/or
illegal ownership
of land; communal
properties; unclear
water rights
Indigenous/
Underserved
peoples
No indigenous/
Underserved population
Dispersed and mixed
indigenous/
Underserved
populations; highly
assimilated
indigenous /
Underserved
populations
Indigenous territories,
reserves and/or lands;
vulnerable indigenous/
Underserved
populations
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
70
3. Checklist of impacts
ELEAP construction activities (excavation, pole erection,
transformer installation, stringing, solar panel
installation, water supply, access road construction, solid
and liquid waste, etc.)
Potential for Adverse Impacts
None Low Med High Unknown
Soil erosion or flooding concerns (e.g., due to highly erodible
soils or steep gradients)
Number of stream crossings or disturbances
Significant vegetation removal
Wildlife habitats or populations disturbed
Be located within or nearby environmentally
Sensitive areas (e.g. intact natural forests, Wetlands, etc.)?
Cultural or religious sites disturbed
Economic or physical resettlement required
New settlement pressures created
Create solid waste on the sites (including excess fill materials
from grading and excavation activities, scrap wood and
metals, and small concrete spills)
Cause air pollution? (Fugitive dust, etc.)
Cause contaminated land?
Create Noise and vibration
Aesthetic disruption to the surrounding areas?
Cause Potential Physical hazards (Like accident or injury or
illness due to repetitive exposure to mechanical action or
work activity, falling from height)
Cause and spread communicable disease (poor sanitation and,
sexual transmission and vector-borne infections)
Cause poor Water Quality and less water Availability
Cause traffic congestion (Traffic accidents, injuries and
fatalities among members of the Community)
Block access to and from individual houses, business centers,
different institutions and buildings, both during construction
and operational phase of road projects
Cause flood and gully formation at the outlet or end point of
drainage canals
An open dich or drainage to be a waste bin that could possibly
become sources of microbial breed, physical damage to
humans and animals
Any right of way issues, ex impact on water lines,
telecommunication, electric poles and other utility lines
Possible impact on individual’s property, including impact on
houses, fences and other structures
Cause any occupational health and safety issues
Can cause serious Electro Magnetic Field effect
Risk of causing the contamination of drinking water?
Natural hazards in flood
Result in the production of solid or liquid waste,
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
71
ELEAP construction activities (excavation, pole erection,
transformer installation, stringing, solar panel
installation, water supply, access road construction, solid
and liquid waste, etc.)
Potential for Adverse Impacts
None Low Med High Unknown
or result in an increase in waste production, during
construction or operation?
Environmentally sensitive areas disturbed
Bad odor and noise nuisance
Increased social tension/conflict over toilet allocation
Risk of effluent quality for downstream communities and
environment
Existing water sources supply/yield depletion
Existing water users disrupted
Downstream water users disrupted
Potential conflict between downstream and upstream or
beneficiary communities
Sensitive ecosystems downstream disrupted
Block of access and routes or disrupt normal operations in the
general area
Will the project generate solid or liquid wastes? (Including
human excreta/sewage, hospital waste
Historical, archaeological or cultural heritage site
Any health and safety related risks to the community nearby
Other (specify):
4. General questions that applies for all types of program activities:
Questions Answer (Yes/No) with
description
State the source of information available at this stage (ELEAP report,
site observation, stakeholders’ consultation, ESMP or other
environmental and social study).
Has there been litigation or complaints of any environmental nature
directed against the proponent or ELEAP construction works
What are the likely environmental impacts, opportunities, risks and
liabilities associated with the project
Does the ELEAP construction activities have the potential to pollute the
environment, or contravene any environmental laws and regulations?
Does the design adequately detail mitigating measures?
Will the ELEAP construction activities require waste or safety
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
72
Questions Answer (Yes/No) with
description
management plan?
If Screening identifies environmental issues that require further study,
does the proposal include the ESMP, PESIA, SMP, A/ RAP, WMP or
any other types of study?
Indicate the scope and time frame of any outstanding environmental
study.
Required Environmental and Social Monitoring Plan:
If the screening identifies environmental issues that require long term or
intermittent monitoring (effluent, EMF impact, live line, gaseous
discharges, water quality, soil quality, air quality, noise etc.), does the
proposal detail adequate monitoring requirements?
Has consultation been conducted? Please attach minutes of meeting
Categorization & Recommendations*
Category Description Mark*
Schedule 1 Project to be fed into the standard ESIA process determined by MoEFCC
Schedule 2 Project will not require an ESIA, but will necessitate the inclusion of
environmental and social mitigation and enhancement measures in the design
and implementation of the project using standard construction contract clauses
and an environmental management plan
Schedule 3 Project is not subject to environmental assessment as no potential impacts are
anticipated.
A/RAP Project will require preparation of A/RAP
SMP Project will require preparation of safety management plan
WMP Project will require preparation of waste management plan
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
73
*Place tick in applicable box
Prepared by; Name:
Position
Organization
Signature:
Date:
Reviewed by; Name:
Position
Organization
Signature:
Date:
Annex 2: Environmental and Social Exclusion List
No. ELEAP Activities with the following impacts are not eligible for financing
1 Cause significant physical and economic relocation (more than 200 people and greater than 10% or
their landholding)
2 Cause large-scale physical disturbance of the site or the surroundings
3 Block access to and/or use of water points etc.
4 Located in protected areas and other ecologically sensitive ecosystems
5 Create encroachment and/or cause significant adverse impacts to critical natural habitats (e.g.,
wildlife reserves; parks or sanctuaries; protected areas; forests and forest reserves, wetlands, national
parks or game reserve; any other ecologically/environmentally sensitive areas)
6 Significant impact on physical cultural resources (archaeological sites; religious monuments or
structures; natural sites with cultural values; cemeteries; graveyards; graves; and other sites of
significance)
7 Have risk on and/or exclude some members of community, including vulnerable groups,
underserved peoples and ethnic minorities,
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
74
8 Can instigate social tension or conflict
9 Contravene international and regional conventions on environmental and social issues
Annex 3: Guideline for the preparation of site specific of ESMP
ESMPs should demonstrate that proposed environmental and social management and monitoring
activities will encompass all major impacts and how they will be integrated into subproject
supervision. The ESMP should also describe proposed measures, methods, and actions to facilitate
public consultation. It is important that the ESMP identify linkages to other social and
environmental safeguards plans relating to the subproject, such as plans to deal with resettlement
issues. Given the scale and nature of the subproject and the significance of the potential anticipated
impacts, Regional Water, Mines and Energy Bureaus in collaboration with Woreda Water, Mines
and Energy Offices are responsible for preparing a project specific ESMP for identified subprojects
in a format suitable for inclusion as technical specifications in the contract of each subproject
beneficiaries, if applicable and required. ESMPs should be finalized and approved after considering
comments from the Ministry of Water, Irrigation and Electricity (MoWIE) at the national level and
Regional and Woreda Environmental offices at regional and Woreda level. The World Bank
safeguards team will review and provide comments on draft site-specific instruments (if required)
and monitor safeguards compliance, among others. Given below are the important elements that
constitute an ESMP:
i) Description of the project: Scale nature and type of subprojects implemented under the
proposed programs are summarized.
ii) Description of Subproject implementation area: The Biophysical and social environmental setting of
the specific subproject implementation area are summarized
iii) Impacts: Predicted adverse environmental and social impacts (and any uncertainties about their
effects) for which mitigation is necessary should be identified and summarized.
iv) Description of Mitigation Measures: Each measure should be briefly described in relation to
the impact(s) and conditions under which it is required. These should be accompanied by and/or
referenced to designs, development activities (including solar home system and biogas
equipment descriptions), operating procedures, and implementation responsibilities. Proposed
measures and actions to facilitate public consultations should be clearly described and justified.
Feasible and cost-effective measures to minimize adverse impacts to acceptable levels should
be specified with reference to each impact identified. Further, the ESMP should provide details
on the conditions under which the mitigation measure should be implemented. The ESMP
should also indicate the various practicable measures applicable to the proposed subprojects at
each project phases (design, construction and/or operation). Efforts should also be made to
mainstream environmental aspects wherever possible.
v) Description of monitoring program: The ESMP identifies monitoring objectives and
specifies the type of monitoring required; it also describes performance indicators which
provide linkages between impacts and mitigation measures identified in the ESA report,
parameters to be measured (for example: national standards, extent of impacted area to be
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
75
considered, etc.), methods to be used, sampling location and frequency of measurements, and
definition of thresholds to signal the need for corrective actions. Monitoring and supervision
arrangements should be agreed by the Bank and the borrower to: ensure timely detection of
conditions requiring remedial measures in keeping with best practice; provide information and
the progress and results of mitigation and institutional strengthening measures; and, assess
compliance with National and World Bank environmental safeguard policies
vi) Institutional arrangements: Institutions responsible for implementing mitigation measures
and for monitoring their performance should be clearly identified. Where necessary,
mechanisms for institutional coordination should be identified, as often, monitoring tends to
involve more than one institution. This is especially important for subprojects requiring cross-
sectoral integration. The ESMP specifies who is responsible for undertaking the mitigation and
monitoring measures, e.g., for enforcement of remedial actions, monitoring of implementation,
training, financing, and reporting. Institutional arrangements should also be crafted to maintain
support for agreed enforcement measures for environmental protection. Where necessary, the
ESMP should propose strengthening the relevant agencies through such actions as:
establishment of appropriate organizational arrangements; appointment of key staff and
consultants.
vii) Implementing schedules: The timing, frequency and duration of mitigation measures and
monitoring should be included in an implementation schedule, showing phasing and
coordination with procedures in the overall subproject implementation/operations manual.
Linkages should be specified where implementation of mitigation measures is tied to
institutional strengthening and to the subproject legal agreements, e.g. as conditions for loan
effectiveness or disbursement.
viii) Reporting procedures: Feedback mechanisms to inform the relevant parties on the progress
and effectiveness of the mitigation measures and monitoring itself should be specified.
Guidelines on the type of information required and the presentation of feedback information
should also be highlighted.
ix) Cost estimates and sources of funds: Implementation of mitigation measures mentioned in
the ESMP will involve an initial investment cost as well as recurrent costs. The ESMP should
include cost estimates into the sub-project design, bidding and contract documents to ensure
that the contractors will comply with the mitigation measures. The costs for implementing the
ESMP will be included in the sub-project design, as well as in the bidding and contract
documents. It is important to capture all costs – including administrative, design and
consultancy, and operational and maintenance costs – resulting from meeting required
standards or modifying subproject design.
To ensure unique identification and to cater for changes in administrative borders or names, the
ESMP further requires entering of GPS coordinates of the location, if applicable.
For each potential impacts of the project, corresponding mitigation measures, and who is responsible
for implementation is indicated. For each potential environmental and social impact, there can be
more than one mitigation measure. Responsibility for implementation of mitigation measures will
typically rest with the contractor or beneficiary during construction and operation of the biogas and
solar home systems.
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
76
The monitoring section of the ESMP prescribes indicators for monitoring the environmental and
social impact and the effects of mitigation measures. The responsibility for this will typically rest
with the EEU, MoWIE, and Regional and Woreda Water, Mines and Energy Bureaus/Offices, in
collaboration with the respective pertinent institutions. A template for ESMP is depicted in annex
4.
Annex 4: Suggested Environmental and Social Management Plan (ESMP) Template for a Subproject
Subproject identification
Subproject title/Name
Region Zone Woreda
Kebele/community Location GPS coordinates
Description of the subproject activity
Description of potential environmental and social impacts;
Description of planned mitigation measures and monitoring along with institutional
responsibilities and capacity/training requirements
Environmental and Social Management Plan-Mitigation
Project Phase Project
activity
Environm
ental
Impacts
Mitigation/
enhancement
measures
Institutional
responsibiliti
es
Time
frame
Cost
Pre-construction
Construction
Operation and
maintenance
Total mitigation costs
Environmental and Social Management Plan-Monitoring
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
77
Project Phase Impa
cts
Mitiga
tion
meas
ures
Paramet
ers to be
monitor
ed
location meas
urem
ents
frequ
ency
Insti
tutio
nal
resp
onsi
biliti
es
Cost
Pre-construction/
activities
Construction/
activities
Operation and
maintenance/
activities
Total monitoring costs
Annex 5: Example of Environmental Contract Clauses
Proper environmental management of construction projects can be achieved only with adequate site selection
and project design. Please note that this environmental clause shall be applicable for projects involving any
construction or rehabilitation activities, regardless of their category or schedules, and hence should be part
of the construction contract agreement. As such, for projects involving any new construction, or any
rehabilitation or reconstruction for existing projects, should provide information as to screening criteria for
site selection and design including the following:
Site selection
Sites should be chosen based on community needs for additional projects, with specific lots chosen based on
geographic and topographic characteristics. The site selection process involves site visits and studies to
analyze: (i) the site’s urban, suburban, or rural characteristics; (ii) national, state, or municipal regulations
affecting the proposed lot; (iii) accessibility and distance from inhabited areas; (iv) land ownership, including
verification of absence of squatters and/or other potential legal problems with land acquisition; (v)
determination of site vulnerability to natural hazards, (i.e. intensity and frequency of floods, earthquakes,
landslides, hurricanes, volcanic eruptions); (vi) suitability of soils and subsoils for construction; (vii) site
contamination by lead or other pollutants; (viii) flora and fauna characteristics; (ix) presence or absence of
natural habitats and/or ecologically important habitats on site or in vicinity (e.g. forests, wetlands, coral reefs,
rare or endangered species); and (ix) historic and community characteristics.
Project design
Project design criteria include, but are not limited to, the consideration of aspects such as heating, ventilation,
natural and artificial light energy efficiency, floor space (in square feet) per bed/ward, requirements for x-
ray rooms, adequacy of corridors for wheel chair/bed access, adequate water supply and sanitation systems,
historical and cultural considerations, security and handicapped access.
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
78
Construction activities and environmental rules for contractors
The following information is intended solely as broad guidance to be used in conjunction with local and
national regulations. Based on this information, environmental rules for contractors should be developed for
each project, taking into account the project size, site characteristics, and location (rural vs. urban).
After choosing an appropriate site and design, construction activities can proceed. As these construction
activities could cause significant impacts on and nuisances to surrounding areas, careful planning of
construction activities is critical. Therefore, the following rules (including specific prohibitions and
construction management measures) should be incorporated into all relevant bidding documents, contracts,
and work orders.
Prohibitions
The following activities are prohibited on or near the project site:
• Cutting of trees for any reason outside the approved construction area;
• Hunting, fishing, wildlife capture, or plant collection;
• Use of unapproved toxic materials, including lead based paints, asbestos, etc.
• Disturbance to anything with architectural or historical value;
• Building of fires;
• Use of firearms (except authorized security guards);
• Use of alcohol by workers.
Construction Management Measures
Waste Management and Erosion:
Solid, sanitation, and, hazardous wastes must be properly controlled, through the implementation of the
following measures:
Waste Management:
• Minimize the production of waste that must be treated or eliminated.
• Identify and classify the type of waste generated. If hazardous wastes (including health care wastes)
are generated, proper procedures must be taken regarding their storage, collection, transportation and
disposal.
• Identify and demarcate disposal areas clearly indicating the specific materials that can be deposited
in each.
• Control placement of all construction waste (including earth cuts) to approved disposal sites (>300
m from rivers, streams, lakes, or wetlands).
• Dispose in authorized areas all of garbage, metals, used oils, and excess material generated during
construction, incorporating recycling systems and the separation of materials.
• No trench shall be left open for more than 7 days, unless duly authorized by the supervisor upon
Contractor’s request. Trenches and other excavation works shall be established, demarcated/fenced
and/or signposted sufficient to prevent accident or injury to workers or the public, including during
hours of darkness.
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
79
Specific Protection Measures: Quarries and Borrow Areas and deposit sites
The Contractor shall obtain appropriate licenses/permits from relevant authorities to operate quarries or
borrow areas prior to their first use. The location of quarries and borrow areas shall be subject to review and
approval by relevant local and national authorities.
New sites:
a) Shall be located 1km or more from settlement areas, archaeological areas, and cultural sites - including
churches and cemeteries, wetlands or any other valued ecosystem component, or on high or steep ground.
b) Shall not be located in water bodies, or adjacent to them, as well as to springs, wells, well fields.
c) Shall not be located in or near forest reserves, natural habitats or national parks.
d) Shall be designed and operated in the perspective of an easy and effective rehabilitation. Areas with
minimal vegetation cover such as flat and bare ground, or areas covered with grass only or covered with
shrubs less than 1.5m in height, are preferred.
e) Shall have clearly demarcated and marked boundaries to minimize vegetation clearing and safety hazards
for third parties.
f) Shall be operated in accordance with the General Environmental Protection Requirements, the
Construction ESMP for the project and in accordance with any consent / permit conditions.
Maintenance:
• Identify and demarcate equipment maintenance areas (>15m from rivers, streams, lakes or wetlands).
• Ensure that all equipment maintenance activities, including oil changes, are conducted within
demarcated maintenance areas; never dispose spent oils on the ground, in water courses, drainage
canals or in sewer systems.
• Identify, demarcate and enforce the use of within site access routes to limit impact to site vegetation.
• Install and maintain an adequate drainage system to prevent erosion on the site during and after
construction.
Erosion Control
• Erect erosion control barriers around perimeter of cuts, disposal pits, and roadways.
• Spray water on dirt roads, cuts, fill material and stockpiled soil to reduce wind induced erosion, as
needed.
• Maintain vehicle speeds at or below 10mph within work area at all times.
Stockpiles and Borrow Pits
• Identify and demarcate locations for stockpiles and borrow pits, ensuring that they are 15 meters
away from critical areas such as steep slopes, erosion prone soils, and areas that drain directly into
sensitive water bodies.
• Limit extraction of material to approved and demarcated borrow pits.
Site Clean-up
• Establish and enforce daily site clean-up procedures, including maintenance of adequate disposal
facilities for construction debris.
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
80
Safety during Construction
The Contractor’s responsibilities include the protection of every person and nearby property from
construction accidents. The Contractor shall be responsible for complying with all national and local safety
requirements and any other measures necessary to avoid accidents, including the following:
• Carefully and clearly mark pedestrian-safe access routes.
• If school children are in the vicinity, include traffic safety personnel to direct traffic during school
hours.
• Maintain supply of supplies for traffic signs (including paint, easel, sign material, etc.), road marking,
and guard rails to maintain pedestrian safety during construction.
• Conduct safety training for construction workers prior to beginning work.
• Provide personal protective equipment and clothing (goggles, gloves, respirators, dust masks, hard
hats, steel-toed and –shanked boots, etc.,) for construction workers and enforce their use.
• Post Material Safety Data Sheets for each chemical present on the worksite.
• Require that all workers read, or are read, all Material Safety Data Sheets. Clearly explain the risks
to them and their partners, especially when pregnant or planning to start a family. Encourage workers
to share the information with their physicians, when relevant.
• Ensure that the removal of asbestos-containing materials or other toxic substances be performed and
disposed of by specially trained workers.
• During heavy rains or emergencies of any kind, suspend all work.
• Brace electrical and mechanical equipment to withstand seismic events during the construction.
Nuisance and dust control
To control nuisance and dust the Contractor should:
• Maintain all construction-related traffic at or below 15 mph on streets within 200 m of the site.
• Maintain all onsite vehicle speeds at or below 10 mph.
• To the extent possible, maintain noise levels associated with all machinery and equipment at or below
90 db.
• In sensitive areas (including residential neighborhoods, hospitals, etc.) more strict measures may
need to be implemented to prevent undesirable noise levels.
• Minimize production of dust and particulate materials at all times, to avoid impacts on surrounding
families and businesses, and especially to vulnerable people.
• Phase removal of vegetation to prevent large areas from becoming exposed to wind.
• Place dust screens around construction areas, paying particular attention to areas close to housing,
commercial areas, and recreational areas.
• Spray water as needed on dirt roads, cut areas and soil stockpiles or fill material.
• Apply proper measures to minimize disruptions from vibration or noise coming from construction
activities.
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
81
Community Relations
To enhance adequate community relations the Contractor should:
• Following the country and ESIA requirements, inform the population about construction and work
schedules, interruption of services, traffic detour routes and provisional bus routes, as appropriate.
• Limit construction activities at night. When necessary ensure that night work is carefully scheduled
and the community is properly informed so they can take necessary measures.
• At least five days in advance of any service interruption (including water, electricity, telephone, and
bus routes) the community must be advised through postings at the project site, at bus stops, and in
affected homes/businesses.
Chance Find Procedures for Culturally Significant Artefacts
The Contractor is responsible for familiarizing themselves with the following “Chance Finds Procedures”,
in case culturally valuable materials are uncovered during excavation, including:
• Stop work immediately following the discovery of any materials with possible archaeological,
historical, paleontological, or other cultural value, announce findings to project manager and notify
relevant authorities;
• Protect artefacts as well as possible using plastic covers, and implement measures to stabilize the
area, if necessary, to properly protect artefacts
• Prevent and penalize any unauthorized access to the artefacts
• Restart construction works only upon the authorization of the relevant authorities.
Environmental Supervision during Construction
The bidding documents should indicate how compliance with environmental rules and design specifications
would be supervised, along with the penalties for non-compliance by contractors or workers. Construction
supervision requires oversight of compliance with the manual and environmental specifications by the
contractor or his designated environmental supervisor. Contractors are also required to comply with national
and municipal regulations governing the environment, public health and safety.
Annex 6: Building Code of Standards
This Code applies, to Building Construction, Maintenance, Renovation, Demolishing and other associated
activities to all Classes of Buildings stated in Ethiopian Building Proclamation. This Code covers the Health
and Safety precautions for the most common construction activities. If a building construction involves
special methods of construction, the builder needs to come up with the associated Health and Safety
precautionary measures for such methods. The occupational health and safety requirements specified in this
document are only the minimum requirements. Other equivalent or better approaches are also acceptable if
proven.
1. Safety Plan, Site Planning and Layout
1.1 Safety Plan of A Work Place
A contractor prepares Safety Plan of Work places which shall incorporate the following.
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
82
• Assignment of a safety officer and/or the establishment of Safety and Health Committee whose members
include representatives of employers and workers. The Officer/Committee will be in charge of following
up the safety preparations and implementations.
• Provide on the job training by safety officer and/or safety committee members to the workers. The
training includes providing information to workers of any measures applied on the construction site for
ensuring safety in understandable ways.
• Displaying pieces of information of particular importance including the following.
• list of construction work to be performed on a construction site involving particular risks, the
approximate time of performance of the work, the contact details of a person responsible for the
work and measures for ensuring the safety of workers;
• instructions for action in the event of a risk, the names and contact details of persons responsible;
• the names and contact details of persons giving first aid, the contact address of nearest place of
providing emergency medical assistance and the means of access.
1.2. Site Layout of a Work Place: Before work begins, site layout plan that contains the following items
shall be prepared and approved.
• Safe means of access to and outlet from all workplaces.
• The sequence or order in which work will be done.
• Access for workers on and around the site.
• The locations of danger zones.
• Storage for flammable materials, if there are any.
• Routes for vehicular traffic. These should be “one way” as far as practicable.
• Storage areas for materials, construction waste and equipment. Materials need to be stored as close
as possible to the appropriate workstation.
• The location of construction machinery. This is usually dependent on operational requirements. The
objective should be to avoid the need to slew the load over workers and traffic of the surrounding
area.
• The location of office rooms and trade workshops.
• The location of medical and welfare facilities.
• Delineation and fencing external border of the site and clearly marking it in order to keep away
unauthorized persons and to protect the public from site hazards. The type of fencing will depend on
the location of the site, but in populated areas it should be at least two meters high and without gaps
or holes.
• Appropriate lighting posts, if night work or work when there is no adequate light is expected.
• Signs and signals that convey required cautionary messages.
2. Signs and Signals
• Warning, Cautionary, and Informative signs and signals shall be placed where required.
• Signs shall be visible at all times when work is being performed, and shall be removed or covered
when the hazards no longer exist.
• Danger Signs: Danger signs shall be used only where an immediate hazard exists. Danger signs shall
have red as the predominating color for the upper panel; black outline on the borders; and a white
lower panel for additional sign wording
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
83
• Caution signs: Caution signs shall be used only to warn against potential hazards or to caution against
unsafe practices.
3. Preventative and Protective Measures of Ladders and Scaffolding
• Ladders
The following general requirements apply to all portable ladders including job-made ladders.
• Ladder rungs, cleats and steps must be parallel, level and uniformly spaced when the ladder is in
position for use.
• Provide a metal spreader or locking device on each stepladder to hold the front and back sections in
an open position when the ladder is being used.
• Ladder components must be surfaced to prevent injury from punctures or lacerations, and prevent
snagging of clothing.
• The type of ladder to be used around electric lines should not be made of a conductor.
• The bottom of a ladder should be of such material that develops friction with the floor.
• Do not tie or fasten ladders together to create longer sections unless they are specifically designed
for such use.
• The minimum clear distance between the sides of individual rung/ step ladders and the minimum
clear distance between the side rails of other fixed ladders shall be 16 inches (41 cm).
• The following are recommended safe work practices when using portable ladders.
3.2. Scaffoldings: General requirements for all scaffolds
• All scaffoldings shall be designed in such a way that it is safe against falling, breaking and sway and
get approval.
• The employer shall provide safe means of access for each employee erecting or dismantling a
scaffold where the provision of safe access is feasible and does not create a greater hazard. The
employer shall have a competent person to determine whether it is feasible or would pose a greater
hazard to provide, and have employees use a safe means of access. This determination shall be based
on site conditions and the type of scaffold being erected or dismantled.
• The vertical supports of scaffolds shall rest on a firm foundation or sills.
• All scaffolds above 3 meters high above ground shall be equipped with a guardrail not less than 1
meter height and an intermediate rail.
• Scaffolding shall be erected plumb line, and level, and all connections shall be securely fastened.
• The width of work platforms on scaffolds shall be not less than 40 cm.
• Materials only for current use shall be kept on scaffolds.
• Safe means of access (ladder or equivalent) shall be provided to all working levels of the scaffolding.
• Overhead protection shall be provided for workers on a scaffold exposed to overhead hazards.
• Employees shall not work on scaffolds during storms or high winds.
• Tools, materials, and debris shall not be allowed to accumulate on scaffolds.
4. Excavation Work
➢ Before commencing excavation work the following pre-excavation requirements should be recognized:
• Excavation works with power tools or equipment in an area likely to have underground conduits,
cables or pipelines, the location of the service facilities shall be accurately determined;
Environmental and Social Management System Guideline (ESMSG)
Ethiopian Electric Utility
84
• Trees, boulders or other matters located within 2 meters of the area to be excavated shall be
removed before commencing excavation work;
➢ The following points should be properly studied before the work of excavation begins on site:
• The nature of the ground should be verified by a competent person or organization;
• Proper safety plan should be submitted and approved to make sure that the excavation will not
affect adjoining buildings, structures or roadways;
• The concerned body should check and verify the position of all the public utilities such as water
pipes, underground sewers and electrical conductors that may cause danger during work;
➢ A worker shall not be permitted or required to enter an excavation over 1.5 meters in depth unless:
• the sides of the excavation are firm or are sloped to safe angle;
• the sides have been secured by the use of sheet piling, shoring or bracing;
• The workers are protected by other effective means.
➢ If equipment or other heavy objects are located or operated close to the edge of excavation or if
excavations are adjacent to or abutting buildings or other structures or a hazard is created by vibration
from nearby equipment or from passing vehicles traffic, the added loads shall be considered in the design
of the support system;
➢ When workers are required to enter excavations over 1.5 meters in depth, a ladder shall be provided in
the immediate area where workers are employed and the ladder shall extend from the bottom of the
excavation to the least 90 cm above the top of the excavation;
➢ With the exceptions of borrow pits, excavations of depth higher than 3.0 meters shall be guarded by
substantial railings. Shallower excavations shall be marked along their perimeter by reflective ropes;
➢ Adequate measures should be taken to prevent the formation of dusts or to suppress as practicable as
possible, such as by sprinkling water at regular intervals in excavation works;
➢ A worker shall not allow excavated materials to remain within 1.2 meters of the edge of a trench typed
excavation, not within 1.5 meters of a pit-typed excavation.
Ministry of Water Resources, Irrigation and Electricity Ethiopian Electric Utility
85
Annex 7: Format of an Annual/quarterly Environmental Report
Relevant environmental authority:
Reporting dates:
District/Kebele:
Program activities approved:
Program activities
title
Activities Project phase9 Environmental.
Category
ESIA / EMP
completed?
Environmental
Permit granted? Effectiveness of
EMP
Issues10
(name, location,
title or reference)
(new construction,
rehabilitation,
maintenance)
See note below (1, 2 or 3) Yes, No or N/A Yes, No or N/A Good, poor, or
needs improvement
See note below
1
2
etc.
Program activities rejected:
Program activities title Activities Reasons for rejection Remarks11
1
2
Etc.
9 Program activities phase will be one of the following: (a) under project preparation or appraisal, (b) appraised, or (c) implementation 10 Issues: accidents, litigation, complaints or fines are to be listed 11 e.g. if an environmental permit was not granted, explain why
Ministry of Water Resources, Irrigation and Electricity Ethiopian Electric Utility
86
Annex 8: Indicative Environmental and Social Management Measures
NO
POTENTIAL ISSUES
Management MEASURES
A 1. Minimising adverse impact on natural forests
2. Lopping of trees
➢ EEU endeavours environmentally sensitive areas such as forest and other ecologically
fragile / sensitive areas while selecting its ROW
3. Habitat Loss
4. Vegetation damage
➢ To minimise damage to vegetation and habitat fragmentation, EEU utilises hand clearing
and transportation of material by head loads into forests
5. Habitat fragmentation
6. Edge effect on flora & fauna
➢ EEU maintains only a 3m wide strip for O&M and allows for regeneration of vegetation
in the other two strips and beneath the transmission lines (refer Appendix-III) to avoid
habitat fragmentation and edge effect.
7. Increased access to wild lands
8. Paths/Access roads
9. Run off and sedimentation from grading of access
roads
➢ EEU avoids creating new access roads or paths during construction activity and utilises
existing paths and field bunds for movement of material. It also strengthens existing village
road for transportation of material, which is also helpful to the local communities.
B 1. Chemical contamination from chemical
maintenance techniques
➢ EEU does not use chemicals for forest clearance/ROW maintenance
2. Poly-Chloro Biphenyls (PCBs) in electrical
equipment
➢ EEU does not use PCB's in its electrical equipment. MoEFCC has arranged for studies
with UNIDO for sampling of existing equipment and creation of a PCB management plan.
Ministry of Water Resources, Irrigation and Electricity Ethiopian Electric Utility
87
NO
POTENTIAL ISSUES
Management MEASURES
1. Change in land use and population relocation for
substations
➢ EEU avoids populated urban/rural areas, trees/ plantations for its substation. If unavoidable
EEU pays compensation on the principle of replacement. Issues of R&R are addressed
through detailed social assessment and planned measures for rehabilitation of affected
population through RAP/SAMP.
2. “Chance finds” or discovery of any archaeological
artefacts, treasure etc. during excavation
➢ Possibilities of such phenomenon are quite remote due to limited and shallow excavations.
However, in case of such findings, EEU will follow the laid down procedure.
D 1. Impaired cultural and aesthetic resources/ ➢ All possible precautions like use of safety equipment’s are ensured at construction site.
Site in-charge and Safety Officer carry out regular monitoring of these requirements for
strict compliance of these regulations.
2. Health and safety ➢ EEU lines do not cause any hazards to health and safety. EEU uses the best international
standards in technology.
3. Fire Hazards ➢ EEU uses state of art technology in its Distribution, Transmission lines and Sub-stations
which trips the line in fraction of seconds to prevent fire hazards
4. Pollution ➢ Although pollution is not an issue with transmission project still EEU is making all out
efforts to further minimise it. Sites are cleared of all the leftover material and debris to
avoid any chance of pollution.
Environmental and Social Management System Guidelines
Ministry of Water, Irrigation and Electricity Ethiopian Electric Utility
88
Annex 9: Indicative ESMS Impact Mitigation and Monitoring Checklists
Potential Impacts Generic Mitigation Measures Monitoring Indicators Responsibility
Negative social and economic effects on local people
and communities, such as:
• Unplanned commercial development
• Demand for local public infrastructure and
services increases beyond existing capacities
• Disruption of traditional lifestyles
• Induced population movements and natural
resource exploitation activities, due to improved
access (e.g. conversion of forest to pasture,
or of sustainable land use to unsustainable, short-
cycle cropping; illegal or unsustainable hunting)
• Work with affected communities to anticipate and
plan for enhanced access to and demand on local
public infrastructure and services
• Provide project funds to strengthen local public
infrastructure and services (e.g. health clinics,
markets, schools)
• Avoid creating congested and unsafe road conditions
at intersections, and in villages and towns
Participation of
communities in local
planning
EEU
Displacement of housing or farms or involuntary
resettlement
• Purchase of replacement land and resettlement
of affected people
• Monetary compensation
Number of project
affected people
adequately compensated
and resettled
EEU/ Land Use
Administration
Loss of natural areas, important habitats, biodiversity Avoid infringing on:
• Critical habitats or areas with significant biodiversity
(e.g. wetlands)
• Protected natural sites and wilderness areas
• Degree of biodiversity
(number of species) in
road vicinities
• Extent of critical
habitats
EEU / Bureau of
Agriculture and
Rural
Development
Damage valuable historic, religious, cultural, and
archaeological resources
Avoid areas of cultural, historical, or religious
significance Apply chance find procedures in
construction clauses
Participation of
communities in local
planning
EEU/ Land Use
Administration
Social disruption during construction (e.g. enhanced
transmission of STDs and TB) • Comprehensive community participation in
construction planning and management
• Education on avoiding communicable
diseases/hygiene
• Use regional labor where possible
Occurrence of illness
or disease
EEU / Bureau
of Health
Environmental and Social Management System Guidelines
Ministry of Water, Irrigation and Electricity Ethiopian Electric Utility
89
Potential Impacts Generic Mitigation Measures Monitoring Indicators Responsibility
Creation of stagnant water in construction borrow
pits and quarries, and on road sides, that breed
disease carriers
Assess ecology of disease carriers in road corridor, and
employ suitable mitigation measures (e.g.
proper drainage of construction areas and road sides,
effective road maintenance)
• Occurrence of illness
or disease
• Drive roads
after moderate rains to
identify areas that
collect or gully water
EEU
Impact of road noise on surrounding habitation • Plant 30-meter tree buffer strips between road and
surrounding habitation
• Planning activities in consultation with local
communities so that activities with the greatest
potential to generate noise are planned during periods
of the day that will result in least disturbance.
Number of community
complaints to local
authorities about noise
EEU
Dust • Stabilize the road surface with gravel and other rocky
surfacing materials
• Minimizing dust from material handling sources, such
as conveyors and bins, by using covers and/or control
equipment (water suppression, bag house, or cyclone)
• Minimizing dust from open area sources, including
storage piles, by using control measures such as
installing enclosures and covers, and increasing the
moisture content
• Dust suppression techniques should be implemented,
such as applying water or non-toxic chemicals to
minimize dust from vehicle movements
Number of community
complaints to local
authorities about dust
EEU
Contaminate surface water and generate trash due to
lack of solid waste management • Provide temporary sanitation (e.g. latrine), where this
is not possible, instruct crews to employ soil mining
(digging a pit for human waste and covering with soil
immediately after use)
• Collect all solid waste from all site areas and dispose
of either in local landfill or well-screened waste pits
Local complaints of
excessive waste and odors
EEU
Environmental and Social Management System Guidelines
Ministry of Water, Irrigation and Electricity Ethiopian Electric Utility
90
Potential Impacts Generic Mitigation Measures Monitoring Indicators Responsibility
Increased soil erosion leading to sediment in runoff
and, possibly, gully formation from:
• Construction activities such as grading,
excavations, and borrowing/quarrying
• Inadequate design of culverts and drainage
controls
Design:
• Use surface drainage controls and mulch on
vulnerable surfaces and slopes
• Line receiving surfaces with stones or concrete
• Locate and design borrow/quarry sites for erosion
control during road construction and future
maintenance operations
• Identify the most environmentally sound source of
materials within budget
Construction:
• Limit earth movement and soil exposure to the dry
season
• Balance cut and fill for minimum deposition of earth
• Provide sedimentation basins
• Resurface and re-vegetate exposed surfaces
• Quality
of soil/productivity
• Integrity of road
structures
• Accidents due to
erosion of road
EEU
Contamination of land in sites due to releases of
hazardous materials or oil.
• Preparation of a management plan to manage
obsolete, abandoned, hazardous materials or oil
consistent with the approach to hazardous waste
management
Observation and
laboratory test
Contractor and
EPA
Illness or disease related to poor source water quality
or from contaminants entering water supply system • Ensure that water is fit for drinking (make
regular testing a part of the project if possible)
• Ensure planning, design, and maintenance of supply,
sanitation, and wastewater works is appropriate to
local needs, and to soil and water table conditions
• Occurrence of illness
or disease
• Regular testing (if
possible)
• Involve community in
local planning process
Local
government/
Community
Contaminated soils from disposal of inadequately
decomposed wastewaters
Ensure planning, design, and maintenance of supply,
sanitation, and wastewater works is appropriate to local
needs, and to soil and water table conditions
Involve community in
local planning process
Local
government/
Community
Environmental and Social Management System Guidelines
Ministry of Water, Irrigation and Electricity Ethiopian Electric Utility
91
Potential Impacts Generic Mitigation Measures Monitoring Indicators Responsibility
Contamination of water source supply • Protect groundwater sources from surface runoff (e.g.
rainwater, spillage around wells, wastewater from
latrines or homes) that may enter as drainage from
above or as seepage from below
• Locate source well away from latrines, septic
systems, traditional defecating areas, and animal pens
• Protect surface water sources from contamination
from:
• Runoff from nearby agricultural areas (e.g. silt, agro-
chemicals, animal waste)
• Other uses such as bathing, laundering, and animal
watering
• Garbage and vegetative debris
• Occurrence of illness
or disease
• Decrease in production
due to
water contamination
(e.g. stunted growth,
no growth)
• Complaints/problems
documented form local
community
Local
government/
Community
Ground and Surface water contamination • Ensure adequate design, installation, and
maintenance of latrines, holding tanks, septic systems
and wastewater soak ways
• Ensure adequate spacing between latrines and soak
ways
• Occurrence of illness
or disease
• Decrease in production
due to
water contamination
(e.g. stunted growth,
no growth)
Local
government/
Community
Displaced land uses Involve community in locating project sites and access
routes as well as developing practices & responsibilities
for managing project activities and sites
Survey of local
population regarding land
uses
Local
government/
Community
Environmental and Social Management System Guidelines
Ministry of Water, Irrigation and Electricity Ethiopian Electric Utility
92
Potential Impacts Generic Mitigation Measures Monitoring Indicators Responsibility
Disruption or destruction of sites of cultural, religious
or historical importance
Involve community in locating appropriate project sites
and access routes that avoid such resources
Survey of local
population regarding
problems with culturally
sensitive areas
Local
government/
Community
Human settlements and land uses near landfill and
composting sites
Involve community in locating project sites and access
routes
Survey of local
population regarding
siting of facility
Local
government
Windblown garbage, dust and smoke Spread and compact incoming refuse, and cover with
soil, daily
Complaints from
community
Local
government
Increased traffic to/from the sites Pave access roads, or use water spraying to reduce dust Complaints from
community
Local
government
Odors • Provide for safe ventilation of decomposition gases
• Spread and compact refuse, and cover with soil daily
Complaints from
community
Local
government
Containment of water sources • Ensure site layout and management practices,
including working training, are adequate
• Install adequate surface drainage control measures
• Maintain erosion and surface drainage control
measures during operations
• Incidences of illness
or disease
• Decrease in
agricultural production
Local
government
Creation of stagnant water sources • Ensure site layout is adequate for drainage
• Install adequate surface drainage control measures
• Maintain erosion and surface drainage control
measures during operations
Periodic check
for pooling water due to
inadequate drainage
Local
government
Environmental and Social Management System Guidelines
Ministry of Water, Irrigation and Electricity Ethiopian Electric Utility
93
Potential Impacts Generic Mitigation Measures Monitoring Indicators Responsibility
Creation of stagnant water in project sites that breed
disease carriers
Assess ecology of disease carriers in project area and
employ suitable mitigation measures (e.g.
proper drainage)
• Increase in disease
carriers
• Occurrence of illness
or disease
Local
government /
Community
Loss of natural area, important habitats, biodiversity Avoid infringing on:
• Protected natural areas and wilderness areas
• Critical habitats or areas with significant biodiversity
(e.g. wetlands)
Survey land area and
community
for environmentally
sensitive areas/habitats
Local
government /
Community
Soil erosion • Minimize time of exposure of areas cleared, graded
or excavated
• Stabilize and revegetate disturbed areas
• Install adequate surface drainage control measures
• Maintain erosion and surface drainage control
measures during operations
• Degree of erosion Local
government /
Community
Contamination of surface and groundwater with
landfill runoff and leachate • Protect water resources by locating landfills:
• Where the underlying soils are relatively
impermeable, and have a high capability
for containing chemical contaminants (e.g. clays)
• So that the bottom of the landfill is above the
water table
• Away and down gradient from surface waters, and
groundwater recharge areas sources, whose use could
be affected by contamination unless the distance to
• Complaints from
community
• Lower agricultural
productivity
• Increased instances of
illness or disease
Local
government /
Community
Environmental and Social Management System Guidelines
Ministry of Water, Irrigation and Electricity Ethiopian Electric Utility
94
Potential Impacts Generic Mitigation Measures Monitoring Indicators Responsibility
the receiving water is adequate to dilute and disperse
potential contamination
• Use a landfill liner (e.g. clay, synthetic)
• Collect surface runoff and discharge to safe area
• Install test wells at landfill perimeter, and
monitor water quality during operations, for early
identification and mitigation of emerging adverse
effects
• Disease transmission through infectious waste,
sharps, and contaminated water
• Chemical and toxic threats through chemical and
pharmaceutical exposure
• Community waste management plan
• Clearly assigned staff responsibilities
• Community guidelines for generation, handling,
storage, treatment and disposal
• Staff trained in handling, storage, treatment, and
disposal
• Protective clothing available (provide thick gloves
and aprons for staff handling healthcare waste)
• Good hygiene practices (soap and water readily
available)
• Vaccinated workers
• Temporary storage containers in designated locations
• Minimization, reuse, and recycling procedures •
Segregate waste
• Treatment methods for hazardous or highly
hazardous waste (open-air burning or incineration of
healthcare waste on site)
Schedule for periodic
review of compliance to
and effectiveness of plan
Ministry
of Health/ NGO/
Community
Environmental and Social Management System Guidelines
Ministry of Water, Irrigation and Electricity Ethiopian Electric Utility
95
Potential Impacts Generic Mitigation Measures Monitoring Indicators Responsibility
• Designate a final disposal site (bury waste on site in
clay-lined pit
• Spread of disease
• Environmental impact
• Select a location with easy access to safe drinking
water (source should be dedicated exclusively to the
facility, if possible, to reduce spreading disease)
• Install adequate sanitation facilities to prevent the
spread of disease from infected patients
• Avoid locations adjacent to schools to minimize
children’s risk of exposure
• Pick a location where waste can be safety buried (e.g.
above the water table and protected from
scavenging) or easily shipped off site for safe
disposal in a sanitary landfill
Involve community in
siting facility and
other planning measures
Ministry
of Health/ NGO/
Community
Post construction
Landslides, slumps and slips • Avoid areas of soil, slope or geological instability
and unstable river crossing sites
• Stabilize slopes by planting vegetation
• Minimize vertical road cuts
• Install drainage ditches to divert water away from
road
• Quality of road
• Degree of erosion
EEU
Accidents and safety risks Construct basic speed bumps and employ traffic
signs where possible • Number of accidents
reported per month to
local government
EEU
Increased soil erosion leading to sediment in runoff
and, possibly, gully formation from inadequate
maintenance of road surface, ditches, borrow/quarry
sites, and drainage and erosion control measures
• Ensure proper and timely maintenance of erosion
control and drainage measures along the road and
at borrow/quarry sites
• Clean out culverts and side channels/runout when
they begin to fill with sediment
• Quality
of soil/productivity
• Integrity of road
structures
EEU
Environmental and Social Management System Guidelines
Ministry of Water, Irrigation and Electricity Ethiopian Electric Utility
96
Potential Impacts Generic Mitigation Measures Monitoring Indicators Responsibility
• Fill mud holes and pot holes with quality gravel
• Use water from settling basins and retention
ponds for road maintenance
Design:
• Use surface drainage controls and mulch on
vulnerable surfaces and slopes
• Line receiving surfaces with stones or concrete
• Locate and design borrow/quarry sites for erosion
control during road construction and future
maintenance operations
• Identify the most environmentally sound source
of materials within budget
Construction:
• Limit earth movement and soil exposure to the
dry season
• Balance cut and fill for minimum deposition of
earth
• Provide sedimentation basins
• Resurface and re-vegetate exposed surfaces
• Accidents due to erosion
of road
• Collection of water in
drainage system
Quarry used for construction may become a health
hazard • Discuss with local community the usefulness
of using pits as water collection pits for cattle,
irrigation
• High light issues of disease transmission and the
need to prohibit its use for drinking, bathing, and
clothes washing
Occurrence of disease
or illness
EEU
Impact of road noise on village • Plant 30-meter tree buffer strips between road
and village
Number of community
complaints to local
authorities about noise
EEU
Dust due to traffic • Implement agreed dust control measures such as
wetting dirt roads, truck washing for trucks
exiting site, and monitoring dust emissions
Number of community
complaints to local
authorities about dust
EEU
Environmental and Social Management System Guidelines
Ministry of Water, Irrigation and Electricity Ethiopian Electric Utility
97
Potential Impacts Generic Mitigation Measures Monitoring Indicators Responsibility
Chemical hazards exhaust emissions from heavy
equipment and motor vehicles during construction and
maintenance activities
• Replacement of the hazardous substance with a
less hazardous substitute
• Implementation of engineering and
administrative control measures to avoid or
minimize the release of hazardous substances into
the work environment keeping the level of
exposure below national established or
recognized limits
• Number of workers
complaints to
management office about
chemical emission
Management
Office
Physical hazards represent potential for accident or
injury or illness due to Slips and falls on the same
elevation associated with poor housekeeping and
struck by Objects related to the potential fall of
materials or tools,
• Minimizing the hazard through design of safe
work systems and administrative or institutional
control measures
• Providing appropriate Personal protective
equipment (PPE) refers to protective clothing,
helmets, goggles, or other garment or equipment
• Health and Safety Warning Signs: Safety Signs
and Signals are one of the main means of
communicating health and safety information.
• Number of workers
complaints to
management
• Number of workers
injured
Management
office
Spread of Communicable diseases typically associated
with large development projects are those relating to
poor sanitation, sexual transmission and vector-borne
infections.
• Undertaking health awareness and education
initiatives,
• Training health workers in disease treatment
• Providing treatment through standard case
management in on-site or community health care
facilities. Ensuring ready access to medical
treatment, confidentiality and appropriate care,
particularly with respect to migrant workers.
• Number of community
complaints to local
authorities’
communicable disease
EEU and local
authorities
Environmental and Social Management System Guidelines
Ministry of Water, Irrigation and Electricity Ethiopian Electric Utility
98
Annex 10: Prediction and Evaluation of Potential Environmental Impacts
Environmental Components
Characterization Evaluation
Type of Impacts Effect Duration Change Periodicity Areal extent
Significance level
without mitigation
Construction Phases No
Im
pa
ct
Ben
efi
cia
l
Ad
verse
Un
kn
ow
n
Dir
ect
Ind
irec
t
Sh
ort
term
Med
ium
term
Lo
ng
ter
m
Rev
ersi
ble
Irrev
ersi
ble
Co
nti
nu
ou
s
Peri
od
ic
Irreg
ula
r
Locali
zed
Wid
esp
rea
d
Ex
ten
siv
e
No
n-
sig
nif
ica
nt
Sm
all
Mo
dera
te
Ma
jor
Physical Environment
Destruction of National Parks and
protected areas
Increased access to previously
inaccessible areas
Disturbance of landscape aesthetics
Exposure of soil to erosion
Interference with watercourses
Generation of blasting vibration and
safety hazards
Enhancement of slope/landscape
instability
Spillage of pollutants (fuel, lubricants
and chemicals)
Biological Environment
Environmental and Social Management System Guidelines
Ministry of Water, Irrigation and Electricity Ethiopian Electric Utility
99
Environmental Components
Characterization Evaluation
Type of Impacts Effect Duration Change Periodicity Areal extent
Significance level
without mitigation
Construction Phases No
Im
pa
ct
Ben
efi
cia
l
Ad
verse
Un
kn
ow
n
Dir
ect
Ind
irec
t
Sh
ort
term
Med
ium
term
Lo
ng
ter
m
Rev
ersi
ble
Irrev
ersi
ble
Co
nti
nu
ou
s
Peri
od
ic
Irreg
ula
r
Locali
zed
Wid
esp
rea
d
Ex
ten
siv
e
No
n-
sig
nif
ica
nt
Sm
all
Mo
dera
te
Ma
jor
Loss of Priority Forest Area
River side habitat degradation
Encroachment on ecologically sensitive
areas
Wetland Ecosystem
Migratory species
Loss of wild lands and wildlife habitats
Restriction on wildlife corridor
Wildlife hunting for bush meat and other
wildlife products
Loss of livestock feed resources
Socioeconomic Environment
Loss of property, residence and business
Loss of and displacement from
agricultural land
Environmental and Social Management System Guidelines
Ministry of Water, Irrigation and Electricity Ethiopian Electric Utility
100
Environmental Components
Characterization Evaluation
Type of Impacts Effect Duration Change Periodicity Areal extent
Significance level
without mitigation
Construction Phases No
Im
pa
ct
Ben
efi
cia
l
Ad
verse
Un
kn
ow
n
Dir
ect
Ind
irec
t
Sh
ort
term
Med
ium
term
Lo
ng
ter
m
Rev
ersi
ble
Irrev
ersi
ble
Co
nti
nu
ou
s
Peri
od
ic
Irreg
ula
r
Locali
zed
Wid
esp
rea
d
Ex
ten
siv
e
No
n-
sig
nif
ica
nt
Sm
all
Mo
dera
te
Ma
jor
Impact on social services and
infrastructures
Displacement of people
Loss of archaeological heritage and
monuments
Loss of cultural heritage and historic
sites
Disturbance of religious sites
Interference with services
Employment opportunities for local
population
Friction between workers and local
population
Spread of HIV/ADIS and other sexually
transmitted diseases
Increased health risks to workers and
residents
Environmental and Social Management System Guidelines
Ministry of Water, Irrigation and Electricity Ethiopian Electric Utility
101
Environmental Components
Characterization Evaluation
Type of Impacts Effect Duration Change Periodicity Areal extent
Significance level
without mitigation
Construction Phases No
Im
pa
ct
Ben
efi
cia
l
Ad
verse
Un
kn
ow
n
Dir
ect
Ind
irec
t
Sh
ort
term
Med
ium
term
Lo
ng
ter
m
Rev
ersi
ble
Irrev
ersi
ble
Co
nti
nu
ou
s
Peri
od
ic
Irreg
ula
r
Locali
zed
Wid
esp
rea
d
Ex
ten
siv
e
No
n-
sig
nif
ica
nt
Sm
all
Mo
dera
te
Ma
jor
Impairment of air quality from nuisance
dust
Odour resulting from inadequate
sanitary conditions
Nuisance noise at adjacent sensitive
receptors
Increased pressure on local services
Environmental problems arising from
development made possible by the
project
Uncontrolled migration of people into
the area
Operation and Maintenance
Phase
Physical Environment
Environmental and Social Management System Guidelines
Ministry of Water, Irrigation and Electricity Ethiopian Electric Utility
102
Environmental Components
Characterization Evaluation
Type of Impacts Effect Duration Change Periodicity Areal extent
Significance level
without mitigation
Construction Phases No
Im
pa
ct
Ben
efi
cia
l
Ad
verse
Un
kn
ow
n
Dir
ect
Ind
irec
t
Sh
ort
term
Med
ium
term
Lo
ng
ter
m
Rev
ersi
ble
Irrev
ersi
ble
Co
nti
nu
ou
s
Peri
od
ic
Irreg
ula
r
Locali
zed
Wid
esp
rea
d
Ex
ten
siv
e
No
n-
sig
nif
ica
nt
Sm
all
Mo
dera
te
Ma
jor
Decrease in downstream flow during
reservoir filling
Regulated flow and reduction in
flooding
Conflicting demand for water use
Deterioration of water quality in
reservoir
Sedimentation of reservoir and loss of
storage capacity
Reduced sediment flow
Scouring of riverbed and river bank
erosion
Local siltation
Nutrient trapping of the reservoir
Biological Environment
Loss/ reduction of Flora and/or Fauna
Environmental and Social Management System Guidelines
Ministry of Water, Irrigation and Electricity Ethiopian Electric Utility
103
Environmental Components
Characterization Evaluation
Type of Impacts Effect Duration Change Periodicity Areal extent
Significance level
without mitigation
Construction Phases No
Im
pa
ct
Ben
efi
cia
l
Ad
verse
Un
kn
ow
n
Dir
ect
Ind
irec
t
Sh
ort
term
Med
ium
term
Lo
ng
ter
m
Rev
ersi
ble
Irrev
ersi
ble
Co
nti
nu
ou
s
Peri
od
ic
Irreg
ula
r
Locali
zed
Wid
esp
rea
d
Ex
ten
siv
e
No
n-
sig
nif
ica
nt
Sm
all
Mo
dera
te
Ma
jor
Migratory species
Restriction on wildlife corridor
Loss of livestock feed resources
Change in disease ecology
Socioeconomic Environment
Risks to the public
Decrease in floodplain (recession)
agriculture
Employment opportunities
Increase in land values
Increased access threats to traditional
communities
Environmental and Social Management System Guidelines
Ministry of Water, Irrigation and Electricity Ethiopian Electric Utility
104
Annex 11: Details of personal protection equipment’s
S. No Name of Personal Protective
Equipment against protection from
Entitlement/ Eligibility Periodicity of distribution and frequency of issue
1 Industrial Safety Helmet (IS:2925-
1975)
For protection against falling objects.
All employees working in O&M of
Plant, TL & Substation (including
RHQ employees working directly or
visiting plants, Substation & TLM
during O&M) or construction work
under O&M.
Initially to all entitled employees and afterwards against return of
damaged or broken helmet.
On transfer employee shall return their helmet to store. In case of
loss of helmet of any individual, new helmet may be given to the
employee at a token price of 30% of the cost of helmet. Life is
considered as four years.
2 Face shield with replaceable acrylic
visor (IS:8521-1977)
For protection from frontal hazards
against splash of chemicals
Water treatment plant operators,
chemical changing/maintenance staff
and other persons handling hazardous
chemicals
Three nos. are to be kept on pool basis at plant/substation battery
room. One no. to be kept extra for replacement. Life is considered
as three years.
3 -i) Zero power blue color goggles with cup
type filters on both ends (IS:
2553:1977)
For protection from radiation due to
sparks/ flames
Working with grass cutter etc. Three nos. to be kept on pool basis at each plant/substation. One
no. to be kept for TL maintenance jobs. On specific requirement &
request of employee. HOD concerned may consider goggle with
toughened power goggles on receipt of eye test certificate from
authorized medical representative. Life is considered is three years.
3 -ii)
Zero power Plane goggles with cup type
filters on both ends (IS:2553:1977)
For protection of eyes injuries due to
flying objects sparks/ flames.
Working with grinders or similar type
of machines
Three nos. to be kept on pool basis at each plant/substation. One
no. to be kept for TL maintenance jobs. On specific requirement &
request of employee. HOD concerned may consider goggle with
toughened power goggles on receipt of eye test certificate from
authorized medical representative. Life is considered is three years.
Environmental and Social Management System Guidelines
Ministry of Water, Irrigation and Electricity Ethiopian Electric Utility
105
S. No Name of Personal Protective
Equipment against protection from
Entitlement/ Eligibility Periodicity of distribution and frequency of issue
3-iii) Welders Equipment’s for both eyes and
face protection (IS:1179)
For protection from radiation
Electrical welders. Two nos. to be kept at each plant/substation. On pool basis. One
no. to be kept for TL maintenance jobs. On specific requirement &
request of employee. HOD concerned may consider goggle with
toughened power goggles on receipt of eye test certificate from
authorized medical representative. Life is considered is three years.
4 i) Rubberized Apron (acid & Alkali Proof)
(IS:4501-1961)
For protection from contact with acid/
corrosive chemicals.
Working in battery room, water
treatment plant
Four nos. are to be kept at each plant/substation. On pool basis.
Persons using apron will keep apron at proper place after use. Life
considered is four years.
4 ii) Safety Belt (with thigh straps) (IS-
EN361 & EN 358) from indigenous or
imported manufacturer
For protection from fall from height
Employees required to work at a
height of 3 meters or more. It is to be
ensured that each employee working
at height (more than 3 meters) must
use safety belt.
Quantity equal to number of entitled employees but not less than 5
numbers. in each plants/substation or 10 numbers in TL office in
pool basis. Life is considered as eight years.
5 i) Artificial Respirator (Balloon Type)
For protection of person suffered from
shock or suffocation from smoke in case
of fire.
For offensive / harmful environment,
substation, control room etc.
Two nos. for each plant/substation to be kept at control room on
pool basis. One no each must be kept extra for each plant/substation
Life is considered as five years.
5 ii) Artificial Respirator (Dusk Type)
For protection from harmful dust from
silica/ coal/ dust
For offensive / harmful environment
(Plant/TL O&M staff)
Ten nos. to be kept in pool at plant/trans line office prone to dust
hazards area. Ten nos. to be kept extra at each TL office prone to
dust hazard area. Considering 50% of total TL offices are dust
prone area and dust masks are purchased after two years. However,
air filters may be changed as and when needed.
Environmental and Social Management System Guidelines
Ministry of Water, Irrigation and Electricity Ethiopian Electric Utility
106
S. No Name of Personal Protective
Equipment against protection from
Entitlement/ Eligibility Periodicity of distribution and frequency of issue
6 i) Electrical Safety shoes (without steel
toe)
For protection from electrical shock
All technical employees (Workmen,
supervisors, executives) including
RHQ directly working or visiting
plant/substation and TL during
construction and O&M
One pair to each entitled employee every 02 years.
6 ii) Rubber Gum Boot (Duck back / Bata
make)
For protection from rain, mud and
corrosive chemicals
Working in muddy/ slushy area of
Plant/TL and Substation.
One pair to entitled employee every three years. 5% to be kept extra
as reserve.
7 Ear Muffs
For protection from noise pollution.
Area where average noise level is
more than 80 db. Like A/c ventilator
room near ABCB, DG Set,
compressor area.
Initially six sets for each substation on pool basis. Considering they
are purchased every eight years.
8 i) Leather Hand Gloves (IS:6994 Part-I-
1973)
For protection from contact with
moderately hot substances & sharp
uneven surfaces.
Employees engaged in welding,
cutting, grinding
As per requirement and replacement against damage. Life is
considered as two years.
8 ii) Leather Hand Gloves (IS:6994)
For protection from contact with hot/
oily/ greasy objects, uneven surfaces.
Handling metallic objects,
reinforcement steel and other
plant/transmission/distribution lines
maintenance jobs as per requirement
(electrical apparatus)
As per requirement and replacement against damage. Life is
considered as two years.
Environmental and Social Management System Guidelines
Ministry of Water, Irrigation and Electricity Ethiopian Electric Utility
107
S. No Name of Personal Protective
Equipment against protection from
Entitlement/ Eligibility Periodicity of distribution and frequency of issue
8 iii) Cotton Hand Gloves
For protection from contact with hot
objects, uneven surfaces.
Handling metallic objects,
reinforcement steel and other
plant/TL maintenance jobs as per
requirement (electrical apparatus)
As per requirement and replacement against damage. Life is
considered as two years.
8 iv) Electrical Resistance Hand Gloves (IS:
4770-1968) - (to be purchased with test
certificates).
For protection from electrical shock.
Working in O&M of plant/TL and
Sub Station/ colony area. Electrical
Hand gloves should be purchased
after testing at the laboratory of
factory owner in presence of regional
safety officer or safety representative.
The gloves should be inspected by
nominated executive/ supervisor
periodically and before each use and
if found even minor damage must be
rejected.
Up to 2KV rating- six pairs to be maintained at plant/substation on
pool basis.
2KV to 15KV rating- Two pairs to be maintained in
plant/substation & six pair for TL maintenance on pool basis.
8 v) Acid/ Alkali Proof Hand Gloves
(Rubberized/ PVC)
For protection from contact with
corrosive chemicals.
Working in battery room/ other
entitled employees on individual
basis.
Four pairs to be kept in substation in battery room and six pairs for
other miscellaneous works in the plant/substation.
Environmental and Social Management System Guidelines (ESMSG)
Ministry of Water, Irrigation and Electricity Ethiopian Electric Utility
108
Annex 12: Sample Complaint Form
Complaint Form
Complaint Number Copies to forward to:
Name of the Recorder (Original)Receiver Party
Region/District/Kebele (Copy)Responsible Party
Date
INFORMATION ABOUT THE COMPLAINANT
Name Surname
Telephone Number
Address
Kebele/ Community
Region/District/woreda
Signature of Complainant
DESCRIPTION OF THE COMPLAINT
Environmental and Social Management System Guidelines (ESMSG)
Ministry of Water, Irrigation and Electricity Ethiopian Electric Utility
109
Annex 13: Safety Checklist
Region: ..................... Woreda………………Village or work site name: - …………………….
Date of Safety Audit/inspection: - .......................
Name of Project: ........................................................................ ……………
Voltage Level: -.................... ....................
Name of Contractor: -...................... ......................
Name of Sub Contractor: -.................................................................................................………
A. DURING FOUNDATION WORK:
S.N. Description of Activity Feed back Remarks
Yes No
EXCAVATION AND CASTING OF FOUNDATION/CONCRETING
1
Ensure Delineation of the foundation area by appropriate fencing to
avoid interference related accident
2 Ensure proper use of appropriate type of equipment for excavation
3
Proper management of dumping of Excavated soil. Check
construction materials are stacked at safe place and does not cause
any danger. (Minimum1.5 Mts. or half the depth of the pit
whichever is more)
4 Working area has been protected properly to avoid against fall of
passer-by or animal in the excavated pit.
5
Passer-by are at safe places and arrangement is made to inform
Public by caution markings (Red Flag)/ Public/Warning Notices.
6
Check that PPEs i.e. Safety helmets, safety boots, Safety Shoes,
Gloves, protective clothing, dust masks, ear-mufflers is used by
workers and Foreman/supervisor
7
The positions of underground installations such as sewers, water
pipes and electrical cables have been verified and in case of their
existence, they must be isolated.
8
Arrangement shall be made to prevent external vibrations due to
rail/road traffic (If required).
9
After excavation the work has been completed speedily erection of
concrete pole and back filling done at the earliest.
10
During backfilling ensure that it is done using appropriate tools and
equipment along with protective clothing
11
Check that the concrete Mixer machine is placed at a safe place.
(Not very, near to pit.)
Environmental and Social Management System Guidelines (ESMSG)
Ministry of Water, Irrigation and Electricity Ethiopian Electric Utility
110
S.N. Description of Activity Feed back Remarks
Yes No
12
A Competent Person shall make every day inspection of
excavations. In case, possible cave in or slide is apparent, all
working in the excavation shall be seized until the necessary pre-
cautions have been taken to safe guard the possible cave in or slide.
13
Where bare wire is used, wire mesh rolls shall be secured to prevent
dangerous recoiling action.
B. CONCRETE POLE ERECTION:
SN Description of Activity Feedback Remarks
Yes No
1 Check proper communication facility is available at site during
Concrete pole erection. (If required)
2
Ensure the derrick used before pole erection has been checked for
adequate strength/size. Ensure for copy of test certificate for all the
lifting machines and tackles.
3
Ensure that the ropes used before pole erection has been checked
for adequate strength/physical condition (Free from break of
strands and knots etc.
4 Check that the safety measures have been taken before undertaking
for the Road/Rail/involving likewise stretches.
5
For rail or road crossing check whether written working plan is
available at site with specific to safety e.g. local earthing, skilled &
experience manpower, strength and height of framework to
maintain the required clearance etc.
6
Check that only erection team members are allowed to stand near
the pole while erection is in process and should wear the safety
helmet/Safety Shoes.
7 Working area of the pole erection has been demarcated during
erection.
8
Check that proper arrangement is made while lifting the poles and
fixing them i.e. proper size and strength of the hook used for lifting
the pole.
9 Check sufficient numbers of workers are made available while
lifting the pole and erecting
10 Where the pole is erected near existing power line, ensure the power
line is interrupted and locally earthed of electricity flow.
Environmental and Social Management System Guidelines (ESMSG)
Ministry of Water, Irrigation and Electricity Ethiopian Electric Utility
111
C. CONDUCTOR STRINGING:
SN Description of Activity Feedback Remarks
Yes No
1. All drivers and plant operators are holding the valid driving
license.
2 Where conductor stringing is near to the existing power line, ensure
the power line is interrupted and locally earthed of electricity flow.
3
Check that the permit has been obtained from the Competent
Authority for stringing of conductor while crossing through
Road/venerable areas etc. (Where necessary)
4 Check that all safety measures have been taken during stringing
of conductor crossing the LV lines (Earthing of existing lines etc.)
5 Ensure that proper size of bolts and nuts are rigidly tightened.
6 Check that the backfilling of the foundation has been done as per
specification.
7 Check that proper communication facility is available at site
during stringing of conductor
8 Check whether the pole has been permanently earthed.
9 Ensure sending signal to puller to stop when last layer of conductor
/EW being pulled.
10 Only nylon or poly propylene ropes should be used during
conductor stringing in the vicinity of live overhead lines.
11
Ensure whether the network of distribution lines has been
thoroughly checked and precautions taken Against in advertent
charging.
12
Check that proper arrangement is made /available for
development and use of a Portable Earthing and Short–Circuiting
Devices which can be engaged and disengaged to and from the
distribution lines, keeping away from the lines, until all
operations on the same are completed and all men and materials
are removed from the lines.
13
Where bare wire is used, ensure that all the insulator strings are
thoroughly checked for availability and proper fixing of cotter
/split pins before hoisting the same.
Environmental and Social Management System Guidelines (ESMSG)
Ministry of Water, Irrigation and Electricity Ethiopian Electric Utility
112
General common points for all activities during Excavation, Casting of Foundation, substation
works, Concrete Poles Erection and Stringing of Conductors
SN Description of Activity Feedback Remarks
Yes No
1 Check whether the contractor had procured required quantity of PPEs
considering maximum numbers of erection workers deployed at one
time.
2
Supervisors/ Workmen have been provided with required healthy
PPEs, like Safety helmet/Safety Belts/ Safety Shoes/Gum Boot etc. as
applicable.
3 Availability of First Aid Box with required medicines at site.
4 Instruction register is available at site.
5 Ensure that Supervisor/Forman/workers Leader always issues
instruction to the Workmen before start of work.
6 Ensure that supervisory staff from supervision consultant, EEU is
available at site during construction.
7 All driver and plant operators are holding valid driving license.
8 Check the vehicle for rescue is available at site.
9 Ensure engaged labor are aware of the job and safety matters.
10 Check that the unskilled laborers are not engaged in skilled job.
11
Ensure that supervisor/workmen engaged in the field are aware of First
Aid Techniques (Such as in case of Electric Shock, Fall from the
height, and the person rescued from buried under the debris etc.
12 Check for nearby Hospital/ Doctor in case of emergencies arises.
13
While transporting heavy consignment of conductor/EW drums from
central store to site by the use of Cranes, Truck, and Tractor. The safety
aspect for construction and failure of brake system of moving
machinery is to be checked.
14 Check the competence (Qualification/Experience) of supervisor
/Foreman, worker leader of contractor.
REMARKS IF ANY: _____________________________________________________________
____________________________________________________________________________
Signature Signature Signature
Name: Name: Name:
Designation:
Designation: Designation:
Representative of Contractor Representatives of Supervision Consultant Representatives of EEU/EHS