enterprise resource management using ms project server 2007 using... · develop detailed project...

22
OFFICIAL INDUSTRY ASSOCIATION FOR MICROSOFT OFFICE PROJECT Presented By: Enterprise Resource Management using MS Project Server 2007 Gerald Leonard Gerald Leonard PMP, MCTS, CQIA, ITIL PMP, MCTS, CQIA, ITIL Project Assistants Project Assistants Project Management Consultant Project Management Consultant 1 © 2006 MPA. All rights reserved.

Upload: others

Post on 03-Jul-2020

9 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Enterprise Resource Management using MS Project Server 2007 using... · Develop Detailed Project Plans •Build the detailed project plan (e.g. detailed tasks, milestones etc.) •Assign

OFFICIAL INDUSTRY ASSOCIATION FOR MICROSOFT OFFICE PROJECT

Presented By:

Enterprise Resource Management using MS Project Server 2007

Gerald Leonard Gerald Leonard PMP, MCTS, CQIA, ITILPMP, MCTS, CQIA, ITILProject Assistants Project Assistants Project Management ConsultantProject Management Consultant

1© 2006 MPA. All rights reserved.

Page 2: Enterprise Resource Management using MS Project Server 2007 using... · Develop Detailed Project Plans •Build the detailed project plan (e.g. detailed tasks, milestones etc.) •Assign

Objectives

Why should an organization Implement a Enterprise Resource Management solution?How to define Enterprise Resource ManagementHow to use Microsoft Enterprise Resource Management features How to apply Microsoft ERM Tools to effectively manage resources

To ensure you understand:

Slide 2

Page 3: Enterprise Resource Management using MS Project Server 2007 using... · Develop Detailed Project Plans •Build the detailed project plan (e.g. detailed tasks, milestones etc.) •Assign

Why should an organization Implement a Enterprise Resource Management solution?

Lack of visibility on current resource’s demand and capacity.Not sure if you have the right resources work on the right initiativesNot sure if you have enough of the right skill sets and experience level.Lack of insight into resource utilization.

Slide 3

Page 4: Enterprise Resource Management using MS Project Server 2007 using... · Develop Detailed Project Plans •Build the detailed project plan (e.g. detailed tasks, milestones etc.) •Assign

What is Enterprise Resource Management?

The management of a pool of resources belonging to the whole organizationAnalyzing and/or selecting resources based on availability and type from a central sourceMaking decisions on how to upgrade an enterprise resource pool based on its current makeup

Slide 4

Page 5: Enterprise Resource Management using MS Project Server 2007 using... · Develop Detailed Project Plans •Build the detailed project plan (e.g. detailed tasks, milestones etc.) •Assign

Microsoft EPM Features

Defining Human Generic ResourcesDefining Material ResourcesSetting cost rates and resource calendarsGeneric Skill MatchingResource Availability Reporting

How can a Microsoft Solution help with Enterprise Resource Management?

Slide 5

Page 6: Enterprise Resource Management using MS Project Server 2007 using... · Develop Detailed Project Plans •Build the detailed project plan (e.g. detailed tasks, milestones etc.) •Assign

Defining Human Generic Resources

A generic resource defines the type of resource we need on A generic resource defines the type of resource we need on our project. Skill sets, experience, etc...our project. Skill sets, experience, etc...

Slide 6

Page 7: Enterprise Resource Management using MS Project Server 2007 using... · Develop Detailed Project Plans •Build the detailed project plan (e.g. detailed tasks, milestones etc.) •Assign

Defining Material Resources

A material resource such as a test environment, a room, A material resource such as a test environment, a room, cables, cables, PCPC’’ss etcetc

Slide 7

Page 8: Enterprise Resource Management using MS Project Server 2007 using... · Develop Detailed Project Plans •Build the detailed project plan (e.g. detailed tasks, milestones etc.) •Assign

Costs Rates

Slide 8

Page 9: Enterprise Resource Management using MS Project Server 2007 using... · Develop Detailed Project Plans •Build the detailed project plan (e.g. detailed tasks, milestones etc.) •Assign

Resource Calendars

Slide 9

Page 10: Enterprise Resource Management using MS Project Server 2007 using... · Develop Detailed Project Plans •Build the detailed project plan (e.g. detailed tasks, milestones etc.) •Assign

Booking Types

Proposed: Resource Proposed: Resource can still be booked to can still be booked to another project during another project during a proposed time framea proposed time frame

Committed: Resource Committed: Resource cannot be booked to cannot be booked to another project during a another project during a committed time framecommitted time frame

Slide 10

Page 11: Enterprise Resource Management using MS Project Server 2007 using... · Develop Detailed Project Plans •Build the detailed project plan (e.g. detailed tasks, milestones etc.) •Assign

Resource Availability Reporting

© 2006 MPA. All rights reserved. 11

Page 12: Enterprise Resource Management using MS Project Server 2007 using... · Develop Detailed Project Plans •Build the detailed project plan (e.g. detailed tasks, milestones etc.) •Assign

Resource Visual Reports

© 2006 MPA. All rights reserved. 12

Page 13: Enterprise Resource Management using MS Project Server 2007 using... · Develop Detailed Project Plans •Build the detailed project plan (e.g. detailed tasks, milestones etc.) •Assign

Resource Work Summary Report

© 2006 MPA. All rights reserved. 13

Page 14: Enterprise Resource Management using MS Project Server 2007 using... · Develop Detailed Project Plans •Build the detailed project plan (e.g. detailed tasks, milestones etc.) •Assign

Additional Microsoft EPM Features

Establishing resource control via Resource Breakdown Structure (RBS)Setting resource attributes with custom resource outline codes Resource re-deployment via portfolio modelsWork ContoursHistorical resource usage on projects

Slide 14

Page 15: Enterprise Resource Management using MS Project Server 2007 using... · Develop Detailed Project Plans •Build the detailed project plan (e.g. detailed tasks, milestones etc.) •Assign

New Microsoft Resource Management Features

Team Builder Improved skills and resource searching Create filtered views that are specific to Team Builder Use filtering and searching when using Team Builder in Project Web Access

Resource plans Enables resource demand to be specified independent of project assignmentsSupports start date, finish date, and units of resource allocated to a projectAllows project summary resource assignment to pull from the resource plan or project assignmentsResource plans are available in Project Server reports

© 2006 MPA. All rights reserved. 15

Page 16: Enterprise Resource Management using MS Project Server 2007 using... · Develop Detailed Project Plans •Build the detailed project plan (e.g. detailed tasks, milestones etc.) •Assign

New Microsoft Resource Management Features (Cont)

Team resources Allows assignments to be published to a team Team members can see and take ownership of assignments published to a team Team capacity and demand can be viewed in Project Server 2007 reports

Resource editing Enterprise resources can be defined through Project Web Access or PSI Supports availability, rate tables, custom fields, and standard fields

© 2006 MPA. All rights reserved. 16

Page 17: Enterprise Resource Management using MS Project Server 2007 using... · Develop Detailed Project Plans •Build the detailed project plan (e.g. detailed tasks, milestones etc.) •Assign

How to use Microsoft Enterprise Resource Management features

11

Capture the project and resource request and build detailed business case. (Resources Plans)

22

33

44

55

11 Capacity analysis and detailed project and resource planning

44

5522 Track and manage resources and the project to a successful conclusion

Select the optimal project portfolio

33 Export selected projects to Project Server 2007

Page 18: Enterprise Resource Management using MS Project Server 2007 using... · Develop Detailed Project Plans •Build the detailed project plan (e.g. detailed tasks, milestones etc.) •Assign

Plan: Capacity Planning Analysis

Maximize Resource Utilization

•Identify skill surpluses and deficits across the planning horizon

• Finalize project portfolio release schedule

•Analyze and communicate training and headcount requirements to HR

Page 19: Enterprise Resource Management using MS Project Server 2007 using... · Develop Detailed Project Plans •Build the detailed project plan (e.g. detailed tasks, milestones etc.) •Assign

Plan: Detailed Planning

Develop Detailed Project Plans

•Build the detailed project plan (e.g. detailed tasks, milestones etc.)

•Assign name d / individual resources to the plan

•Capture inter project dependencies

•Finalize and baseline project plan

•Synchronize project level data with Office Project Portfolio Server 2007 via the Project Server Gateway

Page 20: Enterprise Resource Management using MS Project Server 2007 using... · Develop Detailed Project Plans •Build the detailed project plan (e.g. detailed tasks, milestones etc.) •Assign

Manage: Track Project and Resource Performance

Timesheets

Status Reports

Project Workspaces

Task Assignments

Issues & Risks Mgmt

Project ManagerProject ManagerTeam Team MembersMembers

Collaborate to deliver projects on time and within budget

• Share essential information through team project workspaces

• Keep teams aligned through task assignments and timesheet reporting.

• Proactively predict cost , resource and schedule overruns through KPIs

• Use built-in integration to communicate project-related information through Microsoft Office system applications.

Timesheets

Track Progress

Page 21: Enterprise Resource Management using MS Project Server 2007 using... · Develop Detailed Project Plans •Build the detailed project plan (e.g. detailed tasks, milestones etc.) •Assign

DEMO

© 2006 MPA. All rights reserved. 21

Page 22: Enterprise Resource Management using MS Project Server 2007 using... · Develop Detailed Project Plans •Build the detailed project plan (e.g. detailed tasks, milestones etc.) •Assign

Q & A

Gerald Leonard Gerald Leonard PMP, MCTS, CQIA, ITILPMP, MCTS, CQIA, ITIL

[email protected]@projectassistants.com

© 2006 MPA. All rights reserved. 22