energy management audit
TRANSCRIPT
Energy Management &
Audit
Definition of Energy Audit
“The strategy of adjusting and optimizing energy, using systems and procedures so as to reduce energy requirements per unit of output while holding constant or reducing total costs of producing the output from these systems”
“The judicious and effective use of energy to maximize profits (minimize costs) and enhance competitive positions”
Types of Energy Audit
• Walk Through or Preliminary energy audit
• Detailed energy audit
• Type of energy audit chosen depends on– Function and type of industry– Depth to which final audit is
needed– Potential and magnitude of cost
reduction desired
Walk-through or preliminary audit Walk-through or preliminary audit comprises one day or half-day visit to a plant and the output is a simple report based on observation and historical data provided during the visit. The findings will be a general comment based on rule-of-thumbs, energy best practices or the manufacturer's data.
Preliminary Energy SurveyQuick overview of energy use patterns
• Provides guidance for energy accounting
system
• Provides personnel with perspectives of
processes and equipment
• Identify energy – intensive processes and
equipment
• Identify energy inefficiency ,if any
• Set the stage for detailed energy survey
Steps in conducting Preliminary Energy Audit
1. Plan how to obtain useful data– Plan how to win the involvement/ commitment of
others2. Collect data
Collect existing data e.g., a energy bills(volume/cost)
Collect Production output/records plant layouts using checklists
3. Analyse data Find unit cost of energy (Rs./ kWh for all types) Find fixed and variable energy element Derive ‘energy Index’: energy cost/unit output,
energy cost/floor area
Steps in Conducting Preliminary Energy Audit
4. Formulate plan Formulate Immediate energy-
saving actions: Where? How ? How much?
– Areas to investigate further– Resources required for more
detailed study
5. Action and Monitoring6. Next steps (e.g Need for detailed
Audit)
Detail audit Detail audit is carried out for the energy savings proposal recommended in walk-through or preliminary audit. It will provide technical solution options and economic analysis for the factory management to decide project implementation or priority. A feasibility study will be required to determine the viability of each option.
Detailed Energy Survey
Detailed evaluation of energy use pattern
• By processes and equipment
• Measurement of energy use parameters
• Review of equipment operating
characteristics
• Evaluation of efficiencies
• Identify DSM options and measures
• Recommendation for implementation
Detailed Energy Audit
• Evaluates all energy using system, equipment and include detailed energy savings and costs
• Carried out in 3 phases– Pre-audit Phase– Audit Phase – Post-Audit
Ten Steps Methodology for Detailed Audit
Step No
PLAN OF ACTION PURPOSE / RESULTS
Step 1 Step 2
Phase I –Pre Audit Phase Plan and organise Walk through Audit Informal Interview with
Energy Manager, Production / Plant Manager
Conduct of brief meeting /
awareness programme with all divisional heads and persons concerned (2-3 hrs.)
Resource planning, Establish/organize a
Energy audit team Organize Instruments & time frame Macro Data collection (suitable to type of
industry.) Familiarization of process/plant activities First hand observation & Assessment of
current level operation and practices
Building up cooperation Issue questionnaire for each department Orientation, awareness creation
Step 3 Step 4
Phase II –Audit Phase Primary data gathering,
Process Flow Diagram, & Energy Utility Diagram
Conduct survey and
monitoring
Historic data analysis, Baseline data
collection Prepare process flow charts All service utilities system diagram
(Example: Single line power distribution diagram, water, compressed air & steam distribution.
Design, operating data and schedule of operation
Annual Energy Bill and energy consumption pattern (Refer manual, log sheet, name plate, interview)
Measurements :
Motor survey, Insulation, and Lighting survey with portable instruments for collection of more and accurate data. Confirm and compare operating data with design data.
Step 5 Step6 Step 7
Step 8 Step9
Conduct of detailed trials
/experiments for selected energy guzzlers
Analysis of energy use Identification and
development of Energy Conservation (ENCON) opportunities
Cost benefit analysis Reporting & Presentation to
the Top Management
Trials/Experiments:
- 24 hours power monitoring (MD, PF, kWh etc.).
- Load variations trends in pumps, fan compressors etc. - Boiler/Efficiency trials for (4 – 8
hours) - Furnace Efficiency trials
Equipments Performance experiments etc
Energy and Material balance & energy
loss/waste analysis Identification & Consolidation ENCON
measures Conceive, develop, and refine ideas Review the previous ideas suggested by unit
personal Review the previous ideas suggested by
energy audit if any Use brainstorming and value analysis
techniques Contact vendors for new/efficient
technology Assess technical feasibility, economic
viability and prioritization of ENCON options for implementation
Select the most promising projects Prioritise by low, medium, long term
measures
Documentation, Report Presentation to the top Management.
Step10
Phase III –Post Audit phase Implementation and Follow-
up
Assist and Implement ENCON recommendation measures and Monitor the performance
Action plan, Schedule for implementation
Follow-up and periodic review
Inputs and Outputs of Energy audit
ELECTRICAL ENERGY AUDIT Areas covered under Electrical audit are1. Electrical System :• Electrical Distribution system (substation & feeders study)• PF Improvement study • Capacitor performance • Transformer optimization • Cable sizing & loss reduction • Motor loading survey • Lighting system • Electrical heating & melting furnaces• Electric ovens
2. Mechanical System : • Fans & Blowers • Exhaust & ventilation System • Pumps and pumping System • Compressed air System • Air Conditioning & Refrigeration System • Cooling Tower System
THERMAL ENERGY AUDIT
Areas covered under Electrical audit are• Steam Generation Boilers• Steam Audit and Conversation • Steam Trap Survey • Condensate Recovery System • Insulation Survey • Energy and Material Balance for Unit operation• Heat Exchanger• Waste Heat Recovery System
WATER AUDIT & CONSERVATIONIndustry has recognized 'Water Audit' as a important tool for water resource management Water Audit study is a qualitative and quantitative analysis of water consumption to identify means of reuse and recycling of water. This study includes segregation of effluent streams and schemes for effectively treating them to enable byproduct recovery. Water Audits encourage social responsibility by identifying wasteful use, enables estimation of the saving potential they not only promote water conservation but also deliver cost savings, but also companies to safeguard public health and property, improve external relations and reduce legal liability.
Benefits of energy audit
There is a lot of potential for energy savings from energy audits.. Technical solutions proposed in the energy audits show massive potential for energy savings in every sub-sector with an average of almost ten percent of the energy usage. However, this can only materialize through replication at other factories within the respective sub-sector.
Benefits of an industrial energy audit include: •Energy savings •Avoiding power factor penalties and environmental compliance costs •Quality improvements •Productivity improvements •Reduced maintenance •Fewer breakdowns •Better safety and protection •A process for repeatable improvements
Process VS. Equipment
Equipment efficiency improvement : Max. 5%
Process efficiency improvement : 15% to 30%
Conclusion
Focus on Processes
Examples of processes
• Electrical furnace
• Rolling mills
• Gas furnace
• Steam generation
• Feed water system
• Condensate return system
• Steam distribution system
• Electrlyzer
Energy intensive processes and equipment
Examples of equipment
• Electrical motor
• Pump
• Fan
• Heater (gas,..,electric)
• Dryer (steam/electric)
• Motor / generator
• Compressor
• Light bulb
Conducting Energy Audits
• Lay out – Process FD-
• Operating Conditions
General
Systems• Boiler & Steam System
•HVAC
•Elec. Supply System
•Water systems
•Compressed Air System
•Lighting
•Motors and Drives
•Processing Lines
•Building Envelope
Energy Data
•Electricity Bills
•Fuel Bills
•Water Bills
Step 1 : Data CollectionStep 2 :Pre. Audit Report
Energy Accounting
• Normalization
•Time Plotting of data
Identifying ECO
Step 3 :Facility Inspection
• Detailed Measurements
•Categorizing Consumption
•Systems Detailed Specs. And operating conditions
Step 4 :Detailed Audit Report
• Detailed Inventory
•Specific Energy Consumption
•Conceptual Design for ECO
•Economic Evaluation and Analysis
Goals of the energy audit are to :• Clearly identify types and costs of energy use
• Understand how that energy is being used and possibly wasted
• Identify and analyze more cost-effective ways of using energy
- Improved operational techniques
- New equipment
• Perform an economic analysis on those alternatives and determine which are cost-effective for your business or industry
AEE/ Certified Energy Manager CEM AEE/ Certified Energy Manager CEM ®® B - 2B - 2
Analysis of BillsThe audit must begin with a detailed analysis of the energy bills for the previous twelve months. This is important because :
• The bills show the proportionate use of each different energy source when compared to the total energy bill.
• An examination of where energy is used can point out previously unknown energy wastes, and
• The total amount spent on energy puts an obvious upper limit on the amount that can be saved.
AEE/ Certified Energy Manager CEM AEE/ Certified Energy Manager CEM ®® B - 3B - 3
AEE/ Certified Energy Manager CEM AEE/ Certified Energy Manager CEM ®® B - 4B - 4
AEE/ Certified Energy Manager CEM AEE/ Certified Energy Manager CEM ®® B - 5B - 5
Av. Load Duration Curve
0
200
400
600
800
1000
1200
744 1464 2208 2928 3672 4416 5136 5880 6552 7296 8016
Hrs / Year
kW
A complete analysis of the energy bills for a facility requires a detailed knowledge of the rate structures in effect for the facility.
To accurately determine the costs of operating individual pieces of equipment, break down energy bills into their components (e.g. demand charge and energy charges for the electric bill).
This breakdown also allows more accurate savings calculations for Energy Management Opportunities (EMOs) such as high-efficiency equipment, rescheduling of some on-peak electrical uses, etc.
AEE/ Certified Energy Manager CEM AEE/ Certified Energy Manager CEM ®® B - 6B - 6
Steps in the On-site Energy Audit
1. Identify layout and operating schedule for facility.
Make a plan or sketch of the building(s) which shows building sizes, window areas, and wall and roof composition and insulation
2. Compile an equipment inventory.
List all energy consuming equipment, with hours of
use each year and energy ratings or efficiencies
AEE/ Certified Energy Manager CEM AEE/ Certified Energy Manager CEM ®® B - 7B - 7
3. Determine the pattern of building use to show annual needs for heating, cooling and lighting
4. Conduct a room-by-room lighting inventory
– Light fixtures– Lamp types, size and numbers– Levels of illumination– Uses of task lighting
AEE/ Certified Energy Manager CEM AEE/ Certified Energy Manager CEM ®® B - 8B - 8
AEE/ Certified Energy Manager CEM AEE/ Certified Energy Manager CEM ®® B -9B -9
Energy Balance for Facility
Facility
Electricity 2,597,700 kWh
Natural Gas 329,863 GJ
Lighting 130,560 kWh
Boiler 329,863 GJ
Motors 1,516,619 kWh
Compressors 116,379 kWh
HVAC 34,286 kWh
Chillers 274,560 kWh
Electric Heaters
100,100 kWh
Miscellaneous 260,000 kWh
Total: 2,432,501 kWh/yr
AEE/ Certified Energy Manager CEM AEE/ Certified Energy Manager CEM ®® B -10B -10
Demand Balance for a Facility Electricity 345-378 kW
Lighting 18 kW
Chillers 34.3 kW
Electric Heaters 13 kW
Facility
Motors 197.1 kW
Compressors 14.9 kW
HVAC 17.1 kW
Miscellaneous 35 kW
Total: 329.4 kW
Geographic Location / Degree Days / Weather Data
• Geographic location of facility and weather data for that location are important.
• Obtain average degree days for heating and cooling for that location for the past twelve months from:
– Closest weather station, or– Local utility
• Degree-day data is very useful in analyzing energy needed to heat or cool facility.
AEE/ Certified Energy Manager CEM AEE/ Certified Energy Manager CEM ®® B - 11B - 11
Heating degree days (HDD) and cooling degree days
(CDD) are separate values to a particular geographic location.
The degree day concept assumes:
• The average building has a desired indoor temperature of 21.1°C,
• 2.8°C of this is supplied by internal heat sources such as lights, appliances, equipment, and people.
The base for computing degree-days is 18.33°C.
AEE/ Certified Energy Manager CEM AEE/ Certified Energy Manager CEM ®® B - 12B - 12
Example
Assume a period of three days when the outside temperature averaged 10°C each day
The number of HDD for this three day period would be:
HDD = (18.33°– 10°) * 3 days = 25 degree days.
AEE/ Certified Energy Manager CEM AEE/ Certified Energy Manager CEM ®® B - 13B - 13
Facility Layout
• Obtain the facility layout or plan; review it to determine:
– Facility size– Floor plan– Construction features
(wall and roof material, insulation levels, door and window sizes and construction)
AEE/ Certified Energy Manager CEM AEE/ Certified Energy Manager CEM ®® B - 14B - 14
Operating Hours
• Obtain operating hours for facility
– How many shifts does the facility run? – Is there only a single shift?– Two? Three?
Knowing the operating hours in advance gives some indication as to whether any loads could be shifted
to off-peak times.
AEE/ Certified Energy Manager CEM AEE/ Certified Energy Manager CEM ®® B - 15B - 15
Equipment List
• Get equipment list for facility and review it before conducting audit.
• Identify all large pieces of energy-consuming equipment such as:
– Heaters, air conditioners, water heaters, and specific process-related equipment
• Equipment list and data on operational uses of equipment provide understanding of major energy-consuming tasks or equipment at facility.
AEE/ Certified Energy Manager CEM AEE/ Certified Energy Manager CEM ®® B - 16B - 16
Nine Major Systems To Consider
1. Building Envelope2. HVAC System3. Electrical Supply System4. Lighting5. Boiler and Steam System6. Hot Water System7. Compressed Air System8. Motors and drives9. Special Purpose Process Equipment
AEE/ Certified Energy Manager CEM AEE/ Certified Energy Manager CEM ®® B - 17B - 17
As you examine each system, you should ask:
1. What function(s) does this system serve?
2. How does this system serve its function(s)?
3. What is the energy consumption of this system?
4. What are the indications that this system is probably working ?
AEE/ Certified Energy Manager CEM AEE/ Certified Energy Manager CEM ®® B - 18B - 18
5. If this system is not working, how can it be restored to good working condition?
6. How can the energy cost of this system be reduced?
7. How should this system be maintained?
8. Who has direct responsibility for maintaining and improving the operation and energy efficiency of this system?
AEE/ Certified Energy Manager CEM AEE/ Certified Energy Manager CEM ®® B - 19B - 19
Preliminary Identification of Energy Management Opportunities (EMOs)
• During the on-site audit, take notes on potential EMOs that are evident.
• In general, devote the greatest effort to analyzing and implementing the EMOs which show the greatest savings, and the least effort to those with the smallest savings potential.
• Identifying EMOs requires a good knowledge of energy efficiency technologies available to do the same job with less energy and cost.
AEE/ Certified Energy Manager CEM AEE/ Certified Energy Manager CEM ®® B - 20B - 20
The Energy Audit Report
• The energy audit report
– Explains the final results of the energy analyses
– Provides energy cost saving recommendations.
AEE/ Certified Energy Manager CEM AEE/ Certified Energy Manager CEM ®® B - 21B - 21
Energy Audit Report Format
• Executive SummaryBrief summary of recommendations and cost
savings
• IntroductionPurpose of the energy auditNeed for a continuing energy cost control program
• Facility DescriptionSize, construction, facility layout, and hours of Operation, equipment list, with specifications
AEE/ Certified Energy Manager CEM AEE/ Certified Energy Manager CEM ®® B - 22B - 22
• Energy Bill AnalysisUtility rate structuresTables/graphs of energy consumptions and
costsDiscussion of energy costs and energy bills
• Energy Management Opportunities (EMO’s)Listing of potential EMOsCost and savings analysisEconomic evaluation
• Energy Action PlanSchedule for implementing EMOsDesignation of an energy monitor
• ConclusionAdditional comments not otherwise covered
AEE/ Certified Energy Manager CEM AEE/ Certified Energy Manager CEM ®® B - 23B - 23
AEE/ Certified Energy Manager CEM AEE/ Certified Energy Manager CEM ®® B - 24B - 24
Emission Factors
Emissions by Fuel Type Ton CO2 Ton SO2 Ton NOx
1 ton Mazout 3.229600 0.080000 0.0040001 ton Solar 3.229600 0.040000 0.0040001 m3 of Natural Gas 0.001950 0.000000 0.0000001 kWh of Electricity (assumes emissions are from a central utility-owned power stration) 0.000775 0.000019 0.0000021 ton of LPG 3.027000 0.000000 0.000000
Drawing process flow diagram -Identification of waste streams and obvious energy wastage
Reporting Format for Energy Conservation Recommendations A: Title of Recommendation : Combine DG set cooling tower with main
cooling tower B: Description of Existing System and its operation
: Main cooling tower is operating with 30% of its capacity. The rated cooling water flow is 5000 m3/hr.Two cooling water pumps are in operation continuously with 50% of its rated capacity. A separate cooling tower is also operating for DG set operation continuously.
C: Description of Proposed system and its operation
: The DG Set cooling water flow is only 240 m3/h. By adding this flow into the main cooling tower, will eliminate the need for a separate cooling tower operation for DG set, besides improving the %loading of main cooling tower. It is suggested to stop the DG set cooling tower operation.
D: Energy Saving Calculations Capacity of main cooling tower = 5000 m3/ hr Temp across cooling tower (design) = 8 oC Present capacity = 3000 m3/hr Temperature across cooling tower(operating)
= 4 oC
% loading of main cooling tower = (3000 x 4)/(5000 x 8) = 30% Capacity of DG Set cooling tower = 240 m3/hr Temp across the tower = 5oC Heat Load (240x1000 x 1x 5)
= 1200,000 K.Cal/hr
Power drawn by the DG set cooling tower
No of pumps and its rating = 2 nos x 7.5 kW No of fans and its rating = 2 Nos x 22 kW Power consumption@ 80% load = (22 x2 +7.5 x2) x.80 = 47 kW Additional power required for main cooling tower for additional water flow of 240m3/h (66.67 l/s) with 6 kg/cm2
= (66.67 x 6) / (102 x 0.55) = 7 kW
Net Energy savings = 47 – 7 = 40 kW E: Cost Benefits Annual Energy Saving Potential = 40kWx 8400hr = 3,36,000 Units/Year Annual Cost Savings = 3,36,000 xRs.4.00 = Rs.13.4 Lakh per year Investment (Only cost of piping) = Rs 1.5Lakhs Simple Pay back Period = Less than 2 months
Energy Audit Reporting Format
Energy Audit
Reporting Format
Worksheet for energy audit and reporting
Understanding energy costs
Typical summary of energy bill by a company
Conversion to common unit of energy
Benchmarking for energy performance
• Internal Benchmarking Historical and trend analysis
• External Benchmarking Across similar industries
Scale of operation, vintage of technology, raw material specification and quality and product specification and quality
Bench Marking Energy Performance
• Quantification of fixed and variable energy consumption trends vis-à-vis production levels
• Comparison of the industry energy performance w.r.t. various production levels (capacity utilization)
• Identification of best practices (based on the external benchmarking data)
• Scope and margin available for energy consumption and cost reduction
• Basis for monitoring and target setting exercises
Benchmarking parameters•Gross production relatede.g. kWh/MT clinker or cement produced (cement plant)e.g. kWh/MT, kCal/kg, paper produced (Paper plant)e.g. kCal/kWh Power produced (Heat rate of a power plant)e.g. Million kilocals/MT Urea or Ammonia (Fertilizer plant)
•Equipment / utility relatede.g. kWh/ton of refrigeration (on Air conditioning plant)e.g. % thermal efficiency of a boiler plante.g. kWh/NM3 of compressed air generatede.g. kWh /litre in a diesel power generation plant.
Maximizing system efficiency
• Eliminate steam leakages by trap improvements
• Maximise condensate recovery• Adopt combustion controls for
maximizing combustion efficiency• Replace pumps, fans, air
compressors, refrigeration compressors, boilers, furnaces, heaters and other energy conservation equipment, wherever significant energy efficiency margins exist
Optimising Input Energy Requirement
• Shuffling of compressors to match needs.
• Periodic review of insulation thickness
• Identify potential for heat exchanger networking and process integration.
• Optimisation of transformer operation with respect to load
Fuel and Energy Substitution
Fuel substitution• Natural gas is increasingly the fuel of choice
as fuel and feedstock in the fertilizer, petrochemicals, power and sponge iron industries.
• Replacement of coal by coconut shells, rice husk,etc
• Replacement of LDO by LSHS
Energy substitution• Replacement of electric heaters by steam
heaters• Replacement of steam based hot water by
solar systems
Energy Audit
Instruments
Electrical Measuring Instruments: These are instruments for measuring major electrical parameters such as kVA, kW, PF, Hertz, kvar, Amps and Volts. In addition some of these instruments also measure harmonics. These instruments are applied on-line i.e on running motors without any need to stop the motor. Instant measurements can be taken with hand-held meters, while more advanced ones facilitates cumulative readings with print outs at specified intervals.
Combustion analyzer: This instrument has in-built chemical cells which measure various gases such as CO2, CO, NOX, SOX etc
Fuel Efficiency Monitor: This measures Oxygen and temperature of the flue gas. Calorific values of common fuels are fed into the microprocessor which calculates the combustion efficiency.
Fyrite: A hand bellow pump draws the flue gas sample into the solution inside the fyrite. A chemical reaction changes the liquid volume revealing the amount of gas. Percentage Oxygen or CO2 can be read from the scale.
Contact thermometer:
Contact thermometer: These are thermocouples which measures for example flue gas, hot air, hot water temperatures by insertion of probe into the stream. For surface temperature a leaf type probe is used with the same instrument.
Infrared Pyrometer: This is a non-contact type measurement which when directed at a heat source directly gives the temperature read out. Can be useful for measuring hot jobs in furnaces, surface temperatures etc.
Pitot Tube and manometer: Air velocity in ducts can be measured using a pitot tube and inclined manometer for further calculation of flows.
Ultrasonic flow meter: This a non contact flow measuring device using Doppler effect principle. There is a transmitter and receiver which are positioned on opposite sides of the pipe. The meter directly gives the flow. Water and other fluid flows can be easily measured with this meter.
Energy Audit
Instruments
Energy Audit
Instruments
Tachometer
Stroboscope
Speed Measurements: In any audit exercise speed measurements are critical as thay may change with frequency, belt slip and loading. A simple tachometer is a contact type instrument which can be used where direct access is possible. More sophisticated and safer ones are non contact instruments such as stroboscopes.
Leak Detectors: Ultrasonic instruments are available which can be used to detect leaks of compressed air and other gases which are normally not possible with human abilities.
Lux meters: Illumination levels are measured with a lux meter. It consists of a photo cell which senses the light output, converts to electrical impulses which are calibrated as lux.