emdm3001081 monolithic suspension development activity plan piero rapagnani detector meeting...
TRANSCRIPT
EMDM300108 1
Monolithic suspension development
Activity planPiero Rapagnani
Detector meeting 30-01-2008
EMDM300108 2
Tests on new payload Development and implementation of New Ear Design Safety and Transport Studies
Three Parallel Tasks
1) Steel wire suspension
2) Fibre wire suspension(new C assembly procedure)
3) Complete monolithic suspension
1) Set-up preparation
2) Delivery of fused silica parts
3) Bonding tests
4) Loss tests
5) Complete monolithic suspension
1) Resistance to shocks
2) Resistance to dust pollution
3) Resistance to humidity
4) Silica Dust Containment
5) Storage
6) Transport
EMDM300108 3
1) Steel_proto_assembly 2008
28/01 - 28/02
• New RM prototype (Aluminum,ready)• New MAR prototype (PVC arms, ~ready)• Dummy MI (Al, black, existing, side flats to be machined,~ready)
• Wires 200 m (ready)• Spacers (Al, to be machined)• RM coils (~ready)• Mounting (non standard)
Assembly check and integration of new marionette and new reaction mass.
EMDM300108 4
2) Steel_proto_LC 2008
01/03 - 30/04
• LC setup (Control chain calibration, basic control tests).
Remarks: - control-DAQ crate ~ready (ADC config, CCD to be tested !!!)
- CD crate to be installed.
Test of new marionette and new reaction meas.
EMDM300108 5
3) Fiber_NewEarOld_preparation
(Old design revised, delivered in Feb-08)
2008 11/02 - 30/04
• Improved mounting tools (optimizing C-tool design).• Background activities: - fibre production - fibre tests and systematics
- training for EGO support
Remarks: - CO2 laser performance checked and realigned. - bending point measurement machine ready.
Assembly feasibility technique preparation.
EMDM300108 6
4) Fiber_NewEarOld_integration2008
01/05 - 31/05
• Unmount Proto_steel suspension.• Assembly Dummy Mirror, new_RM, new_MAR, fibres (using specific C-tool developed).
• Leave 1 week in the assembly frame.• Integration and transport in the LC facility.
Suspension prototype integration.
EMDM300108 7
5) Fiber_NewEarOld_LC2008
01/06 - 31/07
• TF measurements• Control tests• Roboustness tests.
Suspension prototype Local Control test.
1st Milestone
EMDM300108 8
6) Fiber_NewEarNew_preparation(New design, meant to separate
weldingfrom bonding, delivered in May-08)
200801/02 - 31/8
• Improvement of the mounting tools.• Pieces delivery.• Bonding (silicate/water-glass) & losses tests.• Suspension parts assembly.• Background activities: - fibre production - fibre tests and systematics
Assembly feasibility and technique preparation.
EMDM300108 9
7) Fiber_NewEarNew_assembly_integration
200801/09 - 31/10
• Suspension and roboustness using the assembly frame
• 1Week (min) stand.• assembling using the payload prototype RM, MAR
Suspension in the frame
2nd Milestone
EMDM300108 10
8) Safety and Transport studies Mar/08 - Feb/09
• Infrastructure design• Orders• Construction• Implementation…
Completion of the monolithic suspension facility, an open task:hard to delineate methods beyond “conservative and reasonable”.
Call for other EGO/Virgo collaborators ????
EMDM300108 11
9) Best_Fiber_XX_LC2008
01/11 - 31/12
Integration of the best solution found in the LC facility
3rd Milestone
• Decision about the destiny of prototype with OldEarNew suspension (if still there).
• Integration of the NewEarNew suspension (if 2nd Milestone OK) in the LC facility.
• TF measurements.• Control tests.• Roboustness tests.
EMDM300108 12
Draft of the planning
2008
1 Steel_Proto_Assembly
2 Steel_Proto_LC
3 Fiber_NewEarOld_preparation
4 Fiber_NewEarOld_integration
5 Fiber_NewEarOld_LC
6 Fiber_NewEarNew_preparation
7 Fiber_NewEarNew_assembly_integ
8 Safety and Transport studies
9 Best_Fiber_XX_LC
Sept Oct Nov DecMay June July AugJan Feb Mar Apr
EMDM300108 13
ITEM MOTIVATION PERIOD
1) Steel_proto_assembly Assembly/check/integration of new marionette and new reaction mass.
2008: 28/01-28/02
2) Steel_proto_LC Test of new MAR and new RM.
2008: 01/03-30/04
3) Fiber_NewEarOld_preparation(Old design revised, delivered 02-07)
Assembly feasibility and technique preparation.
2008: 11/02-30/04
4) Fiber_NewEarOld_integration
Suspension prototype integration (1 week preliminary suspension on the frame, transportation in LC facilty)
2008: 01/05-31/05
5) Fiber_NewEarOld_LC Suspension prototype dynamical and roboustness tests
2008: 01/06-31/07
6) Fiber_NewEarNew_preparation(New design, meant to separate welding from bonding, deliv. 04/07)
Assembly feasibility and technique preparation. Specific bonding tests.
2008: 01/02-31/08
7) Fiber_NewEarNew_assembly/ integration
Suspension prototype test in the assembly frame (1 week)
2008: 01/09-31/10
8) Safety and Transport (TBD)
Completion of the MS facility
Mar/08 - Feb/09
9) Best_Fiber_XX_LC Assembly and test (in vacuum?) of the best solution found
2008: 01/11-31/12
EMDM300108 14
Name Institution R=item responsible, E=direct engagement, C=collaborator
Geppo Cagnoli INFN-FI Res/C Roberto Cavalieri EGO Eng/C Ludovico Carbone INFN-PG Res/ R Shourov Chatterji INFN-RM1 Res/E Mauro Ciaccafava INFN-RM Tech/C Massimo Fabiani INFN-RM Tech/E Lucio Farnesini INFN-PG Tech/E Alberto Gennai INFN-PI Eng/C Dominique Huet EGO Res/ R Matteo Lorenzini INFN-FI Res/E Giovanni Losurdo INFN-FI Res/C Ettore Majorana INFN-RM Res/E Filippo Martelli INFN-FI Res/ R Alain Masserot CNRS-LAPP Eng/E Maurizio Perciballi INFN-RM Tech/R Francesco Piergiovanni INFN-FI Res/E Antonfranco Piluso INFN-PG Tech/C Paola Puppo INFN-RM Res/ R Piero Rapagnani INFN-RM Res/ R Alessandro Rizzo INFN-RM Tech/E Daniel Sentenac EGO Eng/E Helios Vocca INFN-PG Res/ R
peopleFurther support ? (from EGO)
- more technical support from local workshop and trained for skilled works (e.g. welding) +- infrastructure and safety(already involved, but could be officially appointed) +-operator for routinary production works once (fibres/quality/systematics)
EMDM300108 15
Present suspension critical parts
• Fiber handling may induce damages on their surfaces
• Silicate bonding is strongly stressed by the weldling
• Welding the fiber on the lower clamp may induce cleaning problems
EMDM300108 16
New monolithic design
FS bar
Upper clamp
Lower clamp
EMDM300108 17
New monolithic design - 2
CO2
EMDM300108 18
New monolithic design - 3
EMDM300108 19
Stress distribution
EMDM300108 20
Reaction mass
EMDM300108 21
MACHINEMeasurement of FS fibres bending length
EMDM300108 22
MACHINE
MEASUREMENT OF THE BEDING POINT:• Referred to the tip of the fibre at both the ends
• Problems during the welding operationOTHER MEASUREMENTS POSSIBLE WITH THE MACHINE• First violin mode• Vertical bouncing mode
Measurement of FS fibres bending length
Full characterization on a set of fibres pulled with the CO2 laserNEXT:
value accuracy
Bending length 36.64 mm 0.04 mm
Violin mode 445 Hz 1 Hz
Bouncing mode 6.1 Hz 0.1 Hz
with respect to the tip
EMDM300108 23
MACHINEMeasurement of FS fibres bending length