edward downer elementary school playfield renovation status update 06/10/14

10
WCCUSD Bond Program Construction Update Edward Downer Elementary School Playfield Renovation Status Update 06/10/14

Upload: tavion-marter

Post on 15-Dec-2015

217 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Edward Downer Elementary School Playfield Renovation Status Update 06/10/14

WCCUSD Bond ProgramConstruction Update

Edward Downer Elementary School Playfield RenovationStatus Update

06/10/14

Page 2: Edward Downer Elementary School Playfield Renovation Status Update 06/10/14

Construction Manager: Gabriel Fortich (SGI)

Project Engineer: Shawn Fitzgibbons (SGI)

Inspector of Record: Man Wah Cheng

Architect of Record: Rod Sepulvida (BCA Architects)

General Contractor: Maggiora & Ghilotti, Inc.

Edward Downer Elementary SchoolPlayfield Renovation

Project

Project Team

Page 3: Edward Downer Elementary School Playfield Renovation Status Update 06/10/14

DEMOLITION OF EXISTING ASPHALT PAVING AND

MISCELLANEOUS ITEMS TO BUILD A NEW GRASS

FIELD INCLUDING ROUGH AND FINISH SITE GRADING,

IRRIGATION, PLANTING, AND FIELD DRAINAGE.

ELECTRICAL SCOPE CONSISTING OF POWER AND

DATA CONNECTION TO NEW IRRIGATION CONTROLLER

AND PROVISION OF CONDUIT AND FULL BOXES FOR

FUTURE LOW VOLTAGE SYSTEMS.

Edward Downer Elementary SchoolPlayfield Renovation

PROJECT SUMMARY

Page 4: Edward Downer Elementary School Playfield Renovation Status Update 06/10/14

Edward Downer Elementary SchoolPlayfield Renovation

Project

Project Summary

Page 5: Edward Downer Elementary School Playfield Renovation Status Update 06/10/14

Project Duration: 180 (Calendar

Days)

Notice To Proceed Date: May 19, 2014

Completion Date: Nov 15, 2014

Percent Complete: 18%

Base Contract Amount: $563,226.00

Edward Downer Elementary SchoolPlayfield Renovation

Project

General Information

Page 6: Edward Downer Elementary School Playfield Renovation Status Update 06/10/14

Edward Downer Elementary SchoolPlayfield Renovation

Project

Site Demolition

Page 7: Edward Downer Elementary School Playfield Renovation Status Update 06/10/14

Edward Downer Elementary SchoolPlayfield Renovation

Project

Clear and Grubbing

Page 8: Edward Downer Elementary School Playfield Renovation Status Update 06/10/14

Edward Downer Elementary SchoolPlayfield Renovation

Project

Utility Trenching

Page 9: Edward Downer Elementary School Playfield Renovation Status Update 06/10/14

Edward Downer Elementary SchoolPlayfield Renovation

Project

Electrical and Signal Conduit

Page 10: Edward Downer Elementary School Playfield Renovation Status Update 06/10/14

Edward Downer Elementary SchoolPlayfield Renovation

Project

Sub-Grade Preparation