edward downer elementary school playfield renovation status update 06/10/14
TRANSCRIPT
WCCUSD Bond ProgramConstruction Update
Edward Downer Elementary School Playfield RenovationStatus Update
06/10/14
Construction Manager: Gabriel Fortich (SGI)
Project Engineer: Shawn Fitzgibbons (SGI)
Inspector of Record: Man Wah Cheng
Architect of Record: Rod Sepulvida (BCA Architects)
General Contractor: Maggiora & Ghilotti, Inc.
Edward Downer Elementary SchoolPlayfield Renovation
Project
Project Team
DEMOLITION OF EXISTING ASPHALT PAVING AND
MISCELLANEOUS ITEMS TO BUILD A NEW GRASS
FIELD INCLUDING ROUGH AND FINISH SITE GRADING,
IRRIGATION, PLANTING, AND FIELD DRAINAGE.
ELECTRICAL SCOPE CONSISTING OF POWER AND
DATA CONNECTION TO NEW IRRIGATION CONTROLLER
AND PROVISION OF CONDUIT AND FULL BOXES FOR
FUTURE LOW VOLTAGE SYSTEMS.
Edward Downer Elementary SchoolPlayfield Renovation
PROJECT SUMMARY
Edward Downer Elementary SchoolPlayfield Renovation
Project
Project Summary
Project Duration: 180 (Calendar
Days)
Notice To Proceed Date: May 19, 2014
Completion Date: Nov 15, 2014
Percent Complete: 18%
Base Contract Amount: $563,226.00
Edward Downer Elementary SchoolPlayfield Renovation
Project
General Information
Edward Downer Elementary SchoolPlayfield Renovation
Project
Site Demolition
Edward Downer Elementary SchoolPlayfield Renovation
Project
Clear and Grubbing
Edward Downer Elementary SchoolPlayfield Renovation
Project
Utility Trenching
Edward Downer Elementary SchoolPlayfield Renovation
Project
Electrical and Signal Conduit
Edward Downer Elementary SchoolPlayfield Renovation
Project
Sub-Grade Preparation