early delivery systems status
DESCRIPTION
Early Delivery Systems Status. Daryl Cote. Agenda. EDS Follow-ups from last meeting EDS 2 Release 3: Telemetry & State Estimator EDS 3 Release 5 & 6: SCED / LFC Registration Status. Frequency Plot 6/25/08. 7/15 ICCP Site fail-over results. - PowerPoint PPT PresentationTRANSCRIPT
August 11, 2008
TPTF
Early Delivery SystemsStatus
Daryl Cote
2TPTF8/11/2008 2
Agenda
• EDS Follow-ups from last meeting
• EDS 2 – Release 3: Telemetry & State Estimator
• EDS 3– Release 5 & 6: SCED / LFC
• Registration Status
3TPTF8/11/2008 3
Frequency Plot 6/25/08
59.92
59.94
59.96
59.98
60
60.02
60.04
60.06
60.08
0900 0930 1000 1030 1100 1130 1200 1230 1300 1330 1400 1430 1500
Hz
Time
Frequency During 6/25/08 EDS3 R6.3 Test
Frequency
First QSE switched to NodalAll QSEs on Nodal
First QSE switched back to ZonalAll QSEs back on Zonal
4TPTF8/11/2008 4
7/15 ICCP Site fail-over results
• Denton & College Station TSPs, and Exelon QSE, had not set up their Taylor links.
• LCRA TSP was only able to support one link at a time. • STEC TSP’s link had to be cycled. No issues thereafter. • STEC QSE was unable to read their base points from us. • AEP QSE link was up, but no data was available. • AEN TSP performed a site failover at the same time as the test.
They came back up after a few minutes.
• Since the test:– QSE & TSP ICCP Associations Completed
• Working through outstanding issues with three MPs
– ICCP High Availability Completed
5TPTF8/11/2008 5
Met Data from WGRs
• Individual detailed letters were distributed to WGRs on Aug 7th
– Letters provided Meteorological data status by resource– Requested response by August 14th on how they will correct the
issues– Deadline for issue correction is October 31st
• Current Status on next two slides
6TPTF8/11/2008 6
Wind Telemetry
• MMS UI Feedback– Concerned about the amount of work needed to view/update
COPs, etc. for multiple resources. Current UI allows user to view multiple days for one unit, not multiple units for one day
– Concerned about the way error and confirmation messages display (not implemented yet)
– Concerned about raw .xml displaying on the Awards tab (not implemented yet)
7TPTF8/11/2008 7
Wind Telemetry
8TPTF8/11/2008 8
Focused State Estimator Testing Dates
Start Date and Time End Date and Time Duration
August 6 12:00 am August 6 11:59 pm 24Hrs
August 12 12:00 am August 14 11:59 pm 72Hrs
August 19 12:00 am August 21 11:59 pm 72Hrs
August 26 12:00 am August 28 11:59 pm 72Hrs
September 2 12:00 am September 4 11:59 pm 72Hrs
September 8 12:00 am September 12 11:59 pm 120Hrs
Please reference the market notice on July 25 titled Focused State Estimator Support Date and Requirements and Continuing SCED Input Requirements
• Results from 8/6 – lower than non-focused days– EDS team will communicate through multiple channels prior to
the next testing date– ERCOT is reinforcing roles / responsibilities internally
9TPTF8/11/2008 9
QSE Telemetry
10TPTF8/11/2008 10
TSP Telemetry
11TPTF8/11/2008 11
Load Observability
AEP were very proactive in providing telemetry and still more to come.
ONCOR have provided majority of their telemetry
All remaining issues are being actively worked by MPs and ERCOT
* All buses included in this list have a load
12TPTF8/11/2008 12
State Estimator- Convergence Rate – June
SE Statistics June 08
0.00
0.10
0.20
0.30
0.40
0.50
0.60
0.70
0.80
0.90
1.00
CONVERGENCE
ERCOT Software Upgrade caused convergence issue
Monthly Convergence: 83.49%
13TPTF8/11/2008 13
State Estimator- Convergence Rate – July
Monthly Convergence: 85.33%
SE Statistics July 08
0.00
0.10
0.20
0.30
0.40
0.50
0.60
0.70
0.80
0.90
1.00
7/1/
08
7/3/
08
7/5/
08
7/7/
08
7/9/
08
7/11
/08
7/13
/08
7/15
/08
7/17
/08
7/19
/08
7/21
/08
7/23
/08
7/25
/08
7/27
/08
7/29
/08
CONVERGENCE
14TPTF8/11/2008 14
MP10 Status
• MP10 forms were due to ERCOT by April 15, 2008• Initiation of network model change process (Transmission Data
Forms as needed) target date of two weeks of ERCOT request
• Status of 179 sites• 70% are complete• 8% need to submit Transmission Data Forms or review corrected packages• 16% are waiting on feedback/corrections by ERCOT• 6% are non-responsive
• Submittals to include• MP10 Form w/ all boxes checked if approved• If not approved, briefly write issues on MP10 form• If ERCOT model change required:
• Complete ERCOT Transmission Data Form • Send correct updated operational (non-relaying) one-line for facility
MP10 STATUS as of August 1, 2008
RED (Missing)
RED (Non-Responsive)
AMBER (Feedback Required)
GREEN (Verification Complete orModifications Needed from ERCOT)
15TPTF8/11/2008 15
MP10 – Next Steps
Updated MP10 Metric Criteria
The Readiness Team will review documentation that verifies that all participating resources in the Texas Nodal Market have completed their mapping of Resources to Resource Nodes and Resources to EPS Meters.
Readiness will be achieved when each resource has either mapped their Resources or have accepted the existing default configuration.
It is the intent of this metric to ensure that the settlement of Resources involved in a net metering configuration can be executed as specified by the Nodal Protocols.
Target Completion: Receipt of Network Model One-Line (NMO) + 30 Days
16TPTF8/11/2008 16
MP11 Status
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
TOTAL GEN LOAD
RAG for RARF 8/01/08
GREEN (Tier 1 Validation Completed)
AMBER (Missing or Inaccurate data)
RED (Missing Critical Data)
RED (Non-Responsive)
MP11 Status as of August 1, 2008
RED (Non-Responsive)
RED (Missing Critical Data)
AMBER (Missing or Inaccurate data)
GREEN (Tier 1 Validation Completed)
• Review/Validation process and timing• Business review by WCS (may need immediate corrections by MP in order
to load into RARF database)• EDS critical data review continues with feedback to MP• Technical review by data consumers within ERCOT in progress
• Status of 221 sites• 77% Tier 1 Validation is complete• 18% Contain missing or inaccurate data• 2% Missing critical data• 3% Non-responsive
17TPTF8/11/2008 17
MP-11 - Ongoing Registration Data Screening
REGISTRATION DATA PROCESSD
ata
Con
sum
ers
(e.g
. MM
S,
EM
S, N
MM
S)
Reg
istr
atio
n /
AM
Tea
mE
DS
Tea
mM
arke
t P
artic
ipan
t
MP Sends Rarf
Tier 1 Screen Pass?
MP Corrects and resends
No
Loaded to RARF DB
Yes
Synchronize RARF DB with
NODAL TEST DB
Tier 2 Screen Pass?
Data Stubbed in NODAL TEST DB
Issue recorded in Data Issues Log
Notify Reg Team[this will be a
weekly review]
Tier 3 Screen Pass?
Consumer Test Teams Notified
No
Project Proceeds
Notify EDS TeamNo
Yes
Review with MP
Project Proceeds
Stop
Review Issues are with MP
Yes
NoSent back to EDS team for further
analysis
Terms:Tier 1 Screen – Screen basic data such as resource names, QSE General
information and form completenessTier 2 Screen – Screen data quality in isolation such as ramp rates, CC
configurations and transitionsTier 3 Screen – Test data quality and compatibility with consumer application.
Data Consumer – Application or system that will use the data (e.g. EMS, MMS, etc)
Separate Process
18TPTF8/11/2008 18
MP11 – Next Steps
Updated MP11 Metric Criteria
The intent of this metric is that ERCOT has all registration related data for all market participants intending to participate in the Nodal Market on record.
Updated MP 11 Metric Criteria: To work towards final acceptance of Resource Registration documents to include:• Acceptance of RARF• Acceptance of Resource Network Topology Registration• Non-Modeled Generation Declaration• Resource Decision Making Authority Attestation
Target Completion: December 31, 2008