dynamic reservoir simulation of the alwyn field using eclipse

Upload: nwosu-ugonna-dixon

Post on 05-Nov-2015

139 views

Category:

Documents


10 download

DESCRIPTION

Eclipse software is a very powerful reservoir simulation tool that is highly indispensable in the development of any oil field.This project proposes an optimized development plan for production of the Alwyn North reservoir through the maximization of total oil production at minimum cost per barrel. A black oil model was simulated using Eclipse software for the determination of the field oil recovery, among other parameters such as field oil production rate and field water cut, of four development scenarios: natural depletion, water injection, gas injection and water-alternating-gas injection. Each development scenario was optimized for number, location, completion and geometry of production and injection wells as applicable.

TRANSCRIPT

  • INSTITUTE OF PETROLEUM STUDIES

    June 2015

    Dynamic Reservoir

    Simulation of the Alwyn

    Field using ECLIPSE TM

    NWOSU UGONNA DIXON IPS/MSC/PPD/2014/240

    IJEH GIFT ISIJOKELU IPS/MSC/PPD/2014/235

  • NWOSU, DIXON 1 IJEH, ISIJOKELU

    EXECUTIVE SUMMARY

    This project proposes an optimized development plan for production of the Alwyn North reservoir

    through the maximization of total oil production at minimum cost per barrel. A black oil model was

    simulated using Eclipse for the determination of the field oil recovery, among other parameters such as

    field oil production rate and field water cut, of four development scenarios: natural depletion, water

    injection, gas injection and water-alternating-gas injection. Each development scenario was optimized for

    number, location, completion and geometry of production and injection wells as applicable.

    Natural depletion was simulated by depleting the reservoir to a bottom-hole pressure limit 0f 100 bars

    using four already-drilled wells. The field oil recovery was 30 % and the duration of the production

    plateau at 4200m3 was 6 years.

    Water injection was simulated injecting water as a secondary recovery mechanism after depleting the

    reservoir to a bottom-hole flowing pressure of around 260 bars. Two additional production wells and four

    additional injection wells were drilled to give maximum results with this scheme. The oil recovery thus

    increased from 30% to about 53% with the production plateau sustained for 3.9 years albeit at a higher

    plateau rate of 7200m3

    Gas injection was proposed to reduce the high water cut levels associated with water injection by

    injecting gas into the reservoir using the same water injection wells. The field oil recovery reduced to

    42%.

    The Water-alternating gas scheme, using the same injectors and producers as in water injection, gave a

    field oil recovery of about 555 with a production plateau sustained for 4.2 years.

    Water Injection and Water-alternating Gas stood out clearly in terms of profitability, internal rate of return

    and pay-back time. . Water Injection was the best performer with a pay-back time, internal rate of return

    and profitability index of 1.2 years, 90% and 3.26. Recommendation on best production scheme was

    proposed based on technical criteria, environmental consideration and comparison of economic

    parameters.

  • NWOSU, DIXON 2 IJEH, ISIJOKELU

    ACKNOWLEDGEMENT

    This project is dedicated to Mrs Elizabeth Nneka Nwosu who departed this earth

    on 5th, June 2015. May her soul rest in perfect peace.

    Mr Soma Sakthikhumar also deserves a worthy mention for being patient enough

    to impart the desired knowledge to us.

    Picarq Corporation, Total Nigeria and Institute of Petroleum Studies are also

    appreciated for putting the necessary logistics, facilities and finance in place to

    make this project a success.

  • NWOSU, DIXON 3 IJEH, ISIJOKELU

    Table of Contents

    Executive Summary ...................................................................................................... ii

    Acknowledgements iv

    List of Tables vi

    List of Figures ix

    CHAPTER ONE ............................................................................................................... 9

    INTRODUCTION ........................................................................................................... 11

    1.1 Purpose of study ..................................................................................................... 11

    1.3 Geological Description And Field Characteristics .............................................. 11

    1.3.1 Location ............................................................................................................... 12

    1.3.2 Field Characteristics Tectonics .......................................................................... 13

    1.3.3 Geological Setting ............................................................................................... 13

    1.3.4 Brent East Reservoir of Alwyn North Field ....................................................... 15

    1.3.4.1 Geological Description ..................................................................................... 15

    1.3.4.2 Tectonics .......................................................................................................... 16

    1.3.4.3 Sedimentology ................................................................................................. 17

    1.3.4.4 Log correlations ............................................................................................... 19

    1.4 OBJECTIVES OF THE STUDY ............................................................................. 20

    1.5 Reservoir Model And Characteristics ................................................................... 21

    1.5.1 Rock Typing ........................................................................................................ 22

    1.5.2 Reservoir Fluid Properties ................................................................................. 24

    1.5.3 Fluids in Place .................................................................................................... 24

    CHAPTER TWO ............................................................................................................ 26

    FIELD DEVELOPMENT TECHNIQUES ...................................................................... 27

    2.1 Constraints ............................................................................................................ 27

  • NWOSU, DIXON 4 IJEH, ISIJOKELU

    2.1.1 Drilling Constraints ........................................................................................... 27

    2.1.2 Production Constraint ...................................................................................... 28

    2.1.3 Water Injection Constraint ............................................................................... 28

    2.1.4 Gas Injection Constraint ................................................................................... 29

    2.2 Analytical Calculations ........................................................................................ 29

    2.2.1 Case One: Natural Depletion ............................................................................ 30

    2.2.1.1 Minimum number of wells .............................................................................. 31

    2.2.1.2 Material Balance For Natural Depletion Alone ............................................ 32

    a. Rock And Fluid Expansion .................................................................................... 32

    i. Tarbert Region: ....................................................................................................... 33

    ii. Ness Region: .......................................................................................................... 33

    2.2.2 Case Two: Water Injection ............................................................................... 35

    2.2.2.1 Material Balance ............................................................................................. 35

    i. Tarbert Region: ....................................................................................................... 35

    Evaluation of Ea ......................................................................................................... 35

    Evaluation of Ed ........................................................................................................ 37

    ii. Ness Region ........................................................................................................... 38

    Evaluation of Ea ......................................................................................................... 38

    2.2.2.2 Estimation of Oil Recovery Using Hand Calculation .................................. 40

    Table 2.6: Oil Recovery from Natural Depletion and Water Injection ................... 41

    2.2.2.3 Minimum number of wells: ............................................................................ 41

    Implication: ................................................................................................................ 43

    2.2.3 Case Three: Gas Injection ................................................................................. 44

    2.2.3.1 Material Balance ............................................................................................. 44

  • NWOSU, DIXON 5 IJEH, ISIJOKELU

    i. Tarbert Region ........................................................................................................ 44

    Evaluation of EA: ....................................................................................................... 44

    Evaluation of ED: ....................................................................................................... 44

    CHAPTER THREE ......................................................................................................... 49

    DYNAMIC FIELD DEVELOPMENT STUDY USING ECLIPSE SOFTWARE ............. 49

    3.1 Case One: Natural Depletion ............................................................................. 49

    3.1.1 Natural Depletion with the Available Four Exploratory Wells ..................... 49

    3.1.2 Effect of Critical Gas Saturation ....................................................................... 52

    3.1.3 Natural Depletion with Increased Development Wells: ............................... 54

    3.1.3.1 Natural Depletion with Five Producer Wells .............................................. 54

    3.1.4 Inferences: Natural Depletion .......................................................................... 57

    3.2: Case 2: Water Injection Preceded by Natural Depletion ................................ 58

    3.3 Case 3: Gas Injection Preceded by Natural Depletion ....................................... 62

    3.4 Case 4: Water- Alternating Gas Injection .......................................................... 63

    CHAPTER FOUR ........................................................................................................... 68

    ECONOMIC ANALYSIS ................................................................................................ 68

    4.1 Economic Evaluation of Natural Depletion at Economic Limit ....................... 70

    4.2 Economic Evaluation of Gas Injection Scheme at Economic Limit ................. 72

    4.3 Economic Analysis of Water Injection Scenario ............................................... 76

    4.4 Economic Analysis of the Water-Alternating-Gas Scheme .............................. 78

    4.5 Investment Decision ............................................................................................ 81

    4.5.1 Lowest Capital Investment ............................................................................... 82

    4.5.2 Pay-back time ................................................................................................... 83

  • NWOSU, DIXON 6 IJEH, ISIJOKELU

    4.5.3 Profitability Index and Economic Life............................................................. 84

    4.5.4 Gross Profit Margin per barrel ......................................................................... 85

    4.5.5 Cumulative Net Present Value (CNPV): ......................................................... 86

    4.5.6 Internal Rate of Return (IRR): ......................................................................... 86

    CHAPTER FIVE ............................................................................................................. 88

    CONCLUSION AND RECOMMENDATIONS ............................................................ 88

    5.1 Conclusion ......................................................................................................... 88

    5.2 Recommendations ............................................................................................ 89

    REFERENCES ................................................................................................................. 90

    APPENDICES .............................................................. Error! Bookmark not defined.

    APPENDIX A ............................................................................................................. 92

    A1 Natural Depletion: Evaluation Of Revenue, Opex, Cash Flow, Internal Rate

    Of Return , Pay-Back Time And Npv Using 10% As The Discount Factor ............ 92

    A2 Gas Injection: Evaluation Of Revenue, Opex, Cash Flow, Internal Rate Of

    Return , Pay-Back Time And Npv Using 10% As The Discount Factor ................. 93

    A3 Water Injection: Evaluation Of Revenue, Opex, Cash Flow, Internal Rate Of

    Return , Pay-Back Time And Npv Using 10% As The Discount Factor ................. 94

    A4 Natural Depletion: Evaluation Of Revenue, Opex, Cash Flow, Internal Rate

    Of Return , Pay-Back Time And Npv Using 10% As The Discount Factor ............ 95

    APPENDIX B .............................................................................................................. 96

    Evaluation Of Npv For The Various Development Schemes Using The Calculated

    Internal Rate Of Return ............................................................................................ 96

    B1 Gas Injection: Evaluation Of Npv Using The Calculated Internal Rate Of

    Return......................................................................................................................... 96

  • NWOSU, DIXON 7 IJEH, ISIJOKELU

    B2 Water Injection: Evaluation Of Npv Using The Calculated Internal Rate Of

    Return......................................................................................................................... 97

    B3 Wag Injection: Evaluation Of Npv Using The Calculated Internal Rate Of

    Return......................................................................................................................... 98

    APPENDIX C .............................................................................................................. 99

    Full PVT Report ......................................................................................................... 99

  • NWOSU, DIXON 8 IJEH, ISIJOKELU

    LIST OF TABLES- Table 1.1: Rock Typing and Layers representing the Tarbert and Ness

    22

    Table 1.2: Initial Values of Fluid Properties ............................................................. 24

    Table 1.3: Table Showing the Fluids in Place Volume ............................................. 25

    Table 2.1: PVT File ..................................................................................................... 30

    Table 2.2: Analytical solution for Recovery by Natural Depletion Drive............... 34

    Table 2.3: Reciprocal Mobility Ratio computation for obtaining error. Ea ........... 37

    Table 2.4: Relative Permeability (Imbibition) data table ....................................... 37

    Table 2.5: Relative Permeability (Imbibition) data table ........................................ 39

    Table 2.6: Oil Recovery from Natural Depletion and Water Injection ................... 41

    Table 2.7: Gas-Oil Relative Permeability Data for Rock-Type 1 ............................. 45

    Table 2.8: Recoveries from combined Natural Depletion and Gas Injection ........ 48

    Table 3.1: Comparison of WI and WAG ................................................................... 67

    Table 4.1 Revenues and Expenditures for Natural Depletion ............................... 70

    Table 4.2 Economic Evaluation Indices for Natural Depletion ............................. 71

    Table 4.3 Revenues and Expenditures for Gas Injection 73

    Table 4.4 Economic Evaluation Indices for Gas Injection .................................... 74

    Table 4.5 Revenues and Expenditures for Water Injection .................................... 76

    Table 4.6 Summary of Economic Evaluation for Water Injection

    77

    Table 4.7 Revenues and Expenditures for WAG Injection ................................... 79

    Table 4.8 Summary of Economic Evaluation Parameters for WAG Injection .... 80

    Table 4.9: Economic Evaluation for the various development schemes

    87

  • NWOSU, DIXON 9 IJEH, ISIJOKELU

    LIST OF FIGURES Figure1.1: Alwyn North Field Localization Map 7

    Figure 1.2: Alwyn Area Location Map 8

    Figure1.3: Stratigraphy of the Alwyn North Field 9

    Figure 1.6: Cross Section Through Alywn Showing The Faults 11

    Figure 1.7: Depositional Setting of the Brent Group

    Figure 1.8: Showing Log Correlations 13

    Figure 1.8: Reservoir Model Showing the Grids 17

    Figure 1.9: Data File Initialized to Obtain Volumes In-Place 19

    Fig2.1: Reciprocal Mobility Ratio Chart 29

    Fig2.2: Fractional Flow curve for the Tarbert Region 31

    Fig2.3: Fractional Flow curve for the Ness Region

    32

    Figure 2.4: Relative permeability versus gas saturation curves 39

    Figure 2.5: Plot of Gas Fractional flow against saturation for Tarbert 40

    Fig 3.1: Well Architecture: Natural Depletion 42

    Fig 3.2: FOPR, FOPT and FOE for the 4-well Natural Depletion case 42

    Fig 3.3: Oil Production Rate from Wells PA2, PA1, PN2 and PN1 44

    Fig 3.4: Field Recovery Efficiency and Field Plateau Rate for both cases 46

    Fig 3.6: Field Water Cut and Field Gas-Oil Ratio for both cases 47

    Fig 3.7: Well Architecture: Natural Depletion with Wells 48

    Fig 3.9: FPR, FOE, FWCT, FGOR as a function of time 49

    Fig 3.10: Well by Well Analysis 50

    Fig 3.11: Well Architecture: 7 producers and 5 injectors 52

  • NWOSU, DIXON 10 IJEH, ISIJOKELU

    Fig 3.12: Water Injection: FOPR, FOE and FOPT 53

    Fig 3.13: Water Injection: FPR, FWCT and FWIR 54

    Fig 3.14: Gas Injection: FOPR, FOE and FOPT 55

    Fig 3.15: Water Injection: FPR, FWCT and FWIR 56

    Fig 3.16: Sub-case 1: FOPT, FOE, FOPR, FWIR and FOPR 59

    Fig 3.17: Sub case 2: FOPR, FOPT, FOE, FWIR and FPR 59

    Fig 3.18: Sub case 3: FOPR, FOPT, FOE, FWIR and FPR 60

    Fig 3.19: Sub case 4: FOPR, FOPT, FOE, FWIR and FPR 61

    Fig4.1 Cash flow curve for Natural Depletion Scheme 67

    Fig4.2 Cash flow for Gas Injection 69

    Fig4.3 Cash flow for Water Injection 73

    Fig 4.4: Cash flow for WAG Injection 75

    Fig 4.5: Investment Costs for the various development schemes 76

    Fig 4.6 : Pay-back time for the various development schemes 77

    Fig 4.7: Economic Life and PI for the various development schemes 79

    Fig 4.8 GPM per barrel for the various development schemes 80

    Fig 4.9 NPV for the various development schemes 81

    Fig 4.10 IRR for the various development schemes 82

  • NWOSU, DIXON 11 IJEH, ISIJOKELU

    CHAPTER ONE

    INTRODUCTION

    1.1 Purpose of study

    To determine the optimum field development plan for the Alwyn North Field

    (Brent East Reservoir) in terms of recovery and economics, using Eclipse reservoir

    simulator.1.2 Scope of Study

    This study was limited to the Brent East panel of the Alwyn North Field. The

    reservoir model focused on the Ness 2 and Tarbert 1, 2 and 3 units because of the

    small oil content in Ness 1.

    Black Oil PVT representation was used in this study. The drive mechanisms were

    determined using material balance. Annual production was set at 15% of ultimate

    reserves.

    The following cases were examined:

    1. Natural depletion with Flowing well pressure limit of 100bars

    2. Natural depletion up to a reservoir pressure 290bars then introduction of

    Water injection as secondary recovery process

    3. Natural depletion to a reservoir pressure 350bars then introduction of Gas

    injection as secondary recovery process

    4. Natural depletion to a reservoir pressure 350bars then introduction of

    Water injection as secondary recovery process for 4years followed by an alternate

    gas injection.

    1.3 Geological Description And Field Characteristics

    In a bid to explore the Alwyn North field a thorough geological description of the

    field is necessary to ensure complete understanding of the geology of the area. The

    geological settings, sedimentology and other related aspects of the field are

    described in this section.

  • NWOSU, DIXON 12 IJEH, ISIJOKELU

    1.3.1 Location

    The Alwyn North Field was discovered in 1974 in the South Eastern part of the East

    Shetland Basin in the UK North sea, about 140 km East of the near most Shetland

    Island and about 400 km North East of Aberdeen. The Alwyn field lies respectively

    4 and 10 km south of Strathspey and Brent field, 7 km east of Ninian field, and 10

    km north of Dunbar field (see field localisation map below). The water depth is

    around 130 m. The field is in the UKCS Block 3/9 and extends northward into the

    Block 3/4. The location map and 3D view of the area is shown in Fig. 1.1 and 1.2

    respectively.

    Figure1.1: Alwyn North Field Localization Map

  • NWOSU, DIXON 13 IJEH, ISIJOKELU

    Figure 1.2: Alwyn Area Location Map

    1.3.2 Field Characteristics Tectonics

    Tectonics played a significant role on the structure of ALWYN North field.

    Tensional movements leading to the development of the Viking Graben from

    the lower Permian times to Upper Jurassic generated a complex fault pattern.

    Several seismic data acquisition programs were carried out: 2D seismic in 1974

    and 1977, and 3D in 1980/81. Seismic data analysis indicates that the oil bearing

    sands are controlled on one hand by normal sealing faults with a general North-

    South direction, on the other hand by a major unconformity at the base of

    Cretaceous. This unconformity is related to erosion of the Brent formation in the

    eastern part of ALWYN North field.

    In a bid to explore the Alwyn North field a thorough geological description of

    the field is necessary to ensure complete understanding of the geology of the

    area. The geological setting, sedimentology and other related aspects of the field

    are described in this section.

    1.3.3 Geological Setting

    The Brent formation was deposited in a deltaic and shallow marine environment

  • NWOSU, DIXON 14 IJEH, ISIJOKELU

    during the Middle Jurassic period. The Statfjord formation was deposited in a

    fluvial and shallow marine environment during the Lower Jurassic period. Each

    panel has several pre-cretaceous tilted blocks (see Figure 1.3 below). The cap

    rock is made of three on lapping shaly formations:

    Heather formation: marine transgressive shales with thin limestone

    stringers, which is deposited after the tectonic activity.

    Kimmeridge clay thick in the West, thin in the East, which is the main

    hydrocarbon source rock.

    Thick cretaceous sequence.

    Figure1.3: Stratigraphy of the Alwyn North Field

    ALWYN North reservoirs were relatively unaffected by diagenesis due probably

    to an early hydrocarbon impregnation.

    RFT shows that each panel had its own pressure regime. Water-oil contacts were

    identified at different depth. All the panels were independent from the other.

  • NWOSU, DIXON 15 IJEH, ISIJOKELU

    1.3.4 Brent East Reservoir of Alwyn North Field

    This study was considering only the East Panel of the Alwyn North field.

    1.3.4.1 Geological Description

    The structure of Alwyn Brent East Block was generally an eroded monoclinal,

    with Base Cretaceous Unconformity (BCU) setting east and south limit, Spinal

    Fault setting west limit (separating Brent east from north and central west

    blocks), and a fault with sometimes very small throw setting north limit. East

    structure under BCU is quite complicated, and described under the generic term

    of slumps (linked to gravitational collapse of head blocks during Cretaceous

    erosion similar as ones encountered in Brent field).

    In the Brent East panel, the oil zone is in a stratigraphic trap as shown below

    created by the erosion unconformity to the east, by a northsouth fault to the

    west (between A-1 and A-2 wells) and by a transverse fault to the north. The

    Brent Geological Cross section is shown below.

    Figure 1.4: Brent Geological Cross section

    The Brent geological well section is shown in Fig. 1.5.

  • NWOSU, DIXON 16 IJEH, ISIJOKELU

    Fig: Brent Geological well Section

    1.3.4.2 Tectonics

    Several seismic data acquisition programs were carried out: 2D seismic in 1974

    and 1977, and 3D in 1980/81. Seismic data analysis indicates that the oil bearing

    sands are controlled on one hand by normal sealing faults with a general North-

    South direction, on the other hand by a major unconformity at the base of

    Cretaceous. This unconformity is related to erosion of the Brent formation in the

    eastern part of ALWYN North field.

    Following the seismic interpretation, ALWYN North field was divided into the

    following panels:

    Brent North.

    Brent Northwest.

    Brent Southwest.

    Brent East.

    Statfjord

    Triassic .

  • NWOSU, DIXON 17 IJEH, ISIJOKELU

    The first four panels are oil bearing within the Brent. The Statfjord formation is

    a condensate gas reservoir with the Brent completely eroded. The underlying

    Triassic is gas bearing.

    Figure 1.6: Cross Section Through Alywn Showing The Faults

    1.3.4.3 Sedimentology

    The Brent group is divided into three main units: the Lower Brent (Broom,

    Rannoch and Etive formations), the Middle Brent (Ness formations), and the

    Upper Brent (Tarbert formations). The last two are the only oil-bearing

    formations in the Brent East panel.

    The Lower Brent formation was deposited in a shoreface (Rannoch) to

    coastal barrier (Etive) environment. The clastic reservoir is made of

    transgressive sandstone (Broom) and prograding sandstones (Rannoch

    and Etive). Thus, the petrophysical properties range from low to medium

    permeability. This unit does not contain any oil in the Brent East reservoir.

    The Middle Brent formation was deposited in a deltaic to alluvial plain

    (Ness 1) and lagoon to lower delta plain (Ness 2) environment. Thus,

    sandstones are inter bedded with clay and coal. In general, Ness 1 unit has

  • NWOSU, DIXON 18 IJEH, ISIJOKELU

    poorer petrophysical characteristics than Ness 2 unit and its oil-bearing

    leg is much lower especially to the East of the reservoir.

    The Upper Brent was deposited in a prograding lower shoreface

    environment. Three different types of sandstone are identified. At the top

    (Tarbert 3), are massive sands with very good reservoir characteristics.

    This is the main oil bearing unit in the Brent East reservoir. Below

    (Tarbert 2), there are mica-rich sandstone with lower permeability. These

    mica-rich sandstones exhibit a high natural radioactivity. The base of the

    Tarbert formation (Tarbert 1) is very similar to the top sandstone. Despite

    its lower average permeability, Tarbert 2 unit is not considered as a

    permeability barrier.

    Figure 1.7: Depositional Setting of the Brent Group

    To summarize, Tarbet can be described as massive shore face sands with

    excellent petro-physical properties, well connected throughout the field and

    may be even regionally, communicating partially with Upper Ness fluviatile

    system which is isolated from Lower Ness.

    Base Brent Etive and Rannoch are better quality reservoirs, but mainly water

    bearing in Brent East Block.

  • NWOSU, DIXON 19 IJEH, ISIJOKELU

    Considering the small oil content in Ness 1, this unit is neglected in the reservoir

    model. Thus, the reservoir model focuses on the Ness 2 and Tarbert 1, 2 and 3

    units.

    The Brent East reservoir of Alwyn North was characterized using data from two

    of the original vertical appraisal wells (3/9A-2, 3/9A-4) and two new deviated

    delineation wells (N1 and N3). N3 characterized the northern part of the field

    where an important oil leg was confirmed mainly in the Tarbert units. N1

    located to the West did not produce any oil and only encountered the aquifer,

    which does seem to be active. The water salinity in the reservoir is about 17,000

    ppm.

    1.3.4.4 Log correlations

    The last two appraisal wells, namely N1 and N3, were extensively cored.

    Numerous core samples were analyzed through routine conventional core

    analysis. Several permeability-porosity relationships were derived (see annex 2):

    one for each of the reservoir units considered (Tarbert 3, Tarbert 1&2 and Ness 2).

    Special core analyses were carried out on a few samples from each of the

    reservoir units. Unsteady state measurements under reservoir conditions (fluids

    and pore pressure) were conducted to obtain a set of relative permeability and

    of capillary pressure curves.

  • NWOSU, DIXON 20 IJEH, ISIJOKELU

    Figure 1.8: Showing Log Correlations

    1.4 OBJECTIVES OF THE STUDY

    The goal of this study is to propose an initial development plan for the Brent

    East reservoir, this plan should maximize the total hydrocarbon production and

    minimize the development cost in $/bbl.

    Several aspects were investigated:

    a. Using available data, a reservoir performance analysis was performed to

    identify the main reservoir driving force. Using material balance, the different

    drive mechanisms were investigated in order to estimate the oil recovery.

    Primary production as well as secondary production must be investigated

    (material balance calculation above Psat). In order to calculate the Material

    Balance, use average values of Swi and Sor.

    b. Based on the results of the first step, different production schemes should

    were defined: Natural depletion, water injection, gas injection. Each scenario

    was reported in detail with all relevant information, assumptions and selected

  • NWOSU, DIXON 21 IJEH, ISIJOKELU

    options. The annual production plateau was estimated to be around 15% of

    EUR. The production profiles were evaluated over 15 years.

    c. 60% of EUR must be produced at plateau rate.

    d. Each scenario was implemented in the numerical reservoir model. In natural

    depletion, the model was run until 100 bar (BHP). Are the calculated

    numbers of producers relevant? Investigate was done to give the best number

    of wells. For secondary production: We optimize the injectors to meet the

    target production. Attention was paid to the critical gas saturation (Sgc).

    e. A proposed scenario was selected based on technical criteria and economic

    parameters were compared.

    f. Using the selected development scheme, the major uncertainties were

    investigated to assess the impact of the model assumptions including for

    instance:

    permeability anisotropy: Ky = 10*Kx,

    fault transmissibility: sealing / non sealing,

    Tarbert 2 Tarbert 3 connection: transmissivity of layer 4,

    aquifer strength: decrease of pore volume in the water zone (see the impact

    on natural depletion scheme),

    1.5 Reservoir Model And Characteristics

    Based on the Brent East characteristics described previously, a reservoir

    simulation model was designed to investigate the production capacity of this

    reservoir. The reservoir model was built using the four appraisal wells: A2, A4,

    N2 and N3. These wells can be abandoned according to the production scheme.

    Due to a sketchy knowledge of the Brent East reservoir at the beginning of the

    study, a Black Oil model was designed with rectangular cells with 36 cells along

    the x-direction and 51 cells along the y-direction. The geometry definition is

  • NWOSU, DIXON 22 IJEH, ISIJOKELU

    given in a Petrel file: 'MODEL_PETREL.GRDECL'. The structural

    framework used for the Corner Point Geometry is based on the Spinal Fault

    Geometry and the North fault limit. Model size is geometrically 36x51x18 but is

    in reality 36x51x17 (since the 1st layer representing all layers between the Base

    Cretaceous Unconformity and Top Brent is killed by nil porosity), Fig. 1.8.

    1.5.1 Rock Typing

    The rock typing to represent the Tarbert and Ness formations as shown in Table

    1-1. Tarbert can be described as massive shore-face sands with excellent

    petrophysical properties, well connected throughout the field. Tarbert

    communicates partially with the Upper Ness fluviatile system which is isolated

    from Lower Ness.

    Ness 1 and Ness 2 bear small oil content while lower Brent is mainly water and

    are thereby neglected in the reservoir model. Thus, the reservoir model focuses

    on Tarbert 1, 2 and 3.

    Table 1.1: Rock Typing and Layers representing the Tarbert and Ness

    Rock Type Formation Layer Tags

    Rock Type Formation Layer Tags

    Impermeable zone

    1

    Type 1

    Tarbert 3

    2,3,4

    Tarbert 2

    5,6

    Tarbert 1

    7,8,9

    Type 2

    Type 2

    Ness 2

    10,11,12,13,14

    Ness 1

    15,16

    Lower Brent

    17,18

    This model will only include the oil bearing sands from the Tarbert (1, 2 &

    3) and Ness (1 & 2) formations. Thus, in this study, the reservoir model has 17

    layers:

    3 in Tarbert 3

    2 in Tarbert 2

  • NWOSU, DIXON 23 IJEH, ISIJOKELU

    3 in Tarbert 1

    5 in Ness 2

    4 in Ness 1

    There are three equilibration regions defined in the EQUNUM keyword in the

    Regions section. However, there is no evidence of compartmentalization, all the

    regions have the same water-oil contact (WOC) and pressure regime.

    Figure 1.8: Reservoir Model Showing the Grids

    Initial pressure of the reservoir is 446 bar and saturation pressure is 258 bar. The

    reservoir petro- physical properties (porosity, permeability) were also scaled up.

    The property modeling was done as follows:

    Tarbert and Ness shallow marine sheet flood sandstone: Determine

    modelling with trend surface control maps

    Ness: Object modelling floodplain & lagoonal back barrier lobes

    Porosity: Depth and facies trends incorporated

    Permeability: Calibrated with core and DST Data

  • NWOSU, DIXON 24 IJEH, ISIJOKELU

    The petrophysical properties (porosity, permeabilities and NTG) are included in

    the grid in the include file: 'MODEL_PETREL_PETRO.GRDECL'. The original

    oil in place (OOIP) estimation, according to the geological model, is about 35.68

    MMsm3; this value is dependent on capillary pressure.

    1.5.2 Reservoir Fluid Properties

    Black Oil PVT representation was used in this study. The PVT data file PVT.INC

    contains the relevant composite black oil PVT data which accounts for the field

    separation conditions. Below is a table showing the initial PVT values of the

    reservoir fluid.

    Table 1.2: Initial Values of Fluid Properties

    Properties Value

    Initial Reservoir Pressure (Pi) 446 Bar

    Temperature (T) 110 oC

    Saturation Pressure (Psat) 258 Bar

    GOR 206.8974 v/v

    Formation factor, Bo@ Pi 1.6038

    OOIIP 35.68MMm3

    1.5.3 Fluids in Place

    The original data file was initialized to obtain the fluid in place values shown

    below. This was illustrated by adding the ECHO and FIPNUM keywords in the

    dot DATA simulation.

  • NWOSU, DIXON 25 IJEH, ISIJOKELU

    Table 1.3: Table Showing the Fluids in Place Volume

    Currently in place Tarbert Ness Entire Field

    Oil (sm3) 31,104,045 4,577,946 35,681,991

    Water (sm3) 125,222,389 188,540,747 313,763,137

    Dissolved Gas

    (sm3)

    6,426,769,976 945,920,886 7,372,672,862

    Figure 1.9: Data File Initialized to Obtain Volumes In-Place

  • NWOSU, DIXON 26 IJEH, ISIJOKELU

    As shown above, the Tarbert (Region 1) had Oil Originally in place as 31104045

    Sm3, while Ness (region 2) had Oil Originally in place as 4577946 Sm3,with

    Tarbert contributing 87% of the total oil in place in the entire field. The Ness

    can be said to be non-prolific, since it is producing more water than oil. For this

    reason, region 2 will not contribute per say to our proposed production, as such

    drilling into it would lead to early breakthrough and a reduction in oil recovery.

    Hence, our study was focused mainly on the Tarbert rock.

  • NWOSU, DIXON 27 IJEH, ISIJOKELU

    CHAPTER TWO

    FIELD DEVELOPMENT TECHNIQUES

    In this chapter we proposed an initial development plan for the Brent East

    reservoir, this plan should maximize the total hydrocarbon production and

    minimize the development cost in $/bbl. This is done in two parts, the analytical

    calculation of the recovery from natural depletion, water injection and gas

    injection and the other part, the simulation using ECLIPSE for each of the above

    mentioned scenarios with the inclusion of water alternate gas injection. In the

    excel calculation involving material balance and the different drive mechanisms

    were used to estimate the oil recovery. The first case used to produce the oil in

    place was natural depletion and also different cases of secondary production

    were also investigated (material balance calculation above Psat).

    The different secondary production schemes used were: Natural depletion, water

    injection, gas injection as well as Simultaneous Water Gas Injection (WAG).

    Each case is described in this chapter using both excel calculation and eclipse to

    validate. The annual production plateau estimate is around 15% of EUR. The

    production profiles were evaluated over a period of 15 years.

    Each case was implemented in the numerical reservoir model. For primary

    method, production was optimized by investigating the best number of wells.

    For secondary method, production was optimized by investigating the best

    number of producers and injectors to meet the target production.

    2.1 Constraints

    2.1.1 Drilling Constraints

    To develop the Brent East reservoir, a 40-slot well platform will be used.

    The maximum well deviation should not exceed 46 with respect to

    vertical.

    Production program should start at the beginning of 2012.

  • NWOSU, DIXON 28 IJEH, ISIJOKELU

    The maximum horizontal drain (x or y direction) of a well will be less than

    1000 m.

    The kick off point (start of deviation) is set at 2,000 m ground level. It is

    also possible to drill vertical wells with subsea completion.

    The average drilling completion time is about 2 months for vertical wells

    and 2 months for the horizontal ones.

    Wells may be t

    Two drilling rigs are available.

    The wells are drilled in 7".

    2.1.2 Production Constraint

    The minimum bottom hole flowing pressure (BHFP) is 260 bar.

    The perforations of the wells are chosen to optimize recovery depending

    on the well location.

    Vertical well production test indicates a maximum fluid (oil + water) rate

    of 1,800 Sm3/d.

    Horizontal well could produce up to 2,400 Sm3/d of liquid. Only flowing

    production is considered at this stage.

    Drainage radius for vertical wells is about 400 m.

    The averaged maintenance down time is 10 % for all the wells.

    Due to surface facilities on platforms, the maximum allowable GOR is 1500

    m3/m3 and the maximum allowable water cut is 90 %.

    The minimum economical rate for the field is 1000 Sm3/d of oil.

    To estimate the productivity index, we considered a skin of 5

    The annual production plateau should be around 15% of EUR (~7200

    Sm3/d)

    The production plateau should be maintained for 60% of the total oil

    production

    The production profiles should be evaluated over 15 years

    2.1.3 Water Injection Constraint

    During secondary recovery, the following constraint will be considered for water

    injection.

  • NWOSU, DIXON 29 IJEH, ISIJOKELU

    Seawater may be injected into the reservoir without any water

    compatibility problem.

    To estimate the water injectivity index, we considered a skin of -4 induced

    by thermal fractures due to the low temperature of the sea water injected

    in the formation (surface temperature of water: 8C).

    The fracture pressure of the Brent reservoir is about 480 bars.

    The maximum water injection rate is 3,000 Sm3/d. The maximum total

    water injection available is 15,000 Sm3/d.

    Control in voidage replacement

    2.1.4 Gas Injection Constraint

    If gas injection is considered during secondary recovery, the following constraint

    will be considered:

    Lean Statfjord gas may be injected.

    This lean gas is assumed to have the same characteristics as the Brent dissolved

    gas.

    The maximum gas injection rate is 800,000 Sm3/d per well. The maximum total

    gas injection available is 3,200,000 Sm3/d.

    Control in voidage replacement.

    2.2 Analytical Calculations

    The main drive mechanism for production of the Alwyn North Brent East

    reservoir is Expansion of original reservoir fluids (Oil) because the reservoir

    initially is undersaturated and will be depleted above bubble point pressure with

    a minimum drawdown of 20 bars. However, secondary and enhanced oil

    recovery mechanisms will also be deployed to increase recovery via water and/or

    gas injection. These scenarios will be investigated using MBE (Analytical or

    Hand Calculations) vis--vis dynamic Numerical Simulation with Eclipse and

    the results will be presented and discussed.

    However, before proceeding we ran Eclipse in NOSIM mode to generate the

    PRT file containing the STOIIP of Alwyns Tarbert and Ness formations. The

    following screenshot captures this information and other important data.

  • NWOSU, DIXON 30 IJEH, ISIJOKELU

    The PVT file used for various calculations is shown below. The full PVT file used

    for gas injection is shown in the appendix.

    Table 2.1: PVT File

    Assumptions

    1. The Petro-physical and PVT Properties of both rock types are assumed to be

    similar.

    2. Vertical Sweep Efficiency, Ev is assumed to be 0.7 for all regions.

    2.2.1 Case One: Natural Depletion

    This refers to production of hydrocarbons from a reservoir without the use of

    any process (such as fluid injection) to supplement the natural energy of the

    reservoir. In the case of natural depletion, we used the material balance equation

    (MBE) to calculate the production and ultimate oil recovery under a natural

  • NWOSU, DIXON 31 IJEH, ISIJOKELU

    depletion process. The reservoir was depleted from the initial pressure (Pinitial =

    258bar) to a bottom hole pressure limit of 100 bar.

    The data used for these calculations were obtained from the PVT report and the

    INPUT data file. The Original Oil in Place for the two regions (Tarbert and Ness)

    was obtained from an initialization run in ECLIPSE. The result is displayed in

    Figure 1.9.

    In this type of reservoir, the principal source of energy is a result of gas

    liberation from the crude oil and the subsequent expansion of the solution gas

    as the reservoir pressure is reduced.

    Assumptions:

    1. No Aquifer support or water influx into the reservoir

    2. Recovery is by rock and liquid expansion

    2.2.1.1 Minimum number of wells

    The following equations were used to determine the minimum number of wells:

    ------------------------------2.1

    To get the initial number of wells, we need:

    --------------------------------------2.2

    Considering that for the development field case we don't have any production

    data, to estimate productivity index (average value between Pi and Pmin):

    --------------------------------------------------2.3

    Where,

    = 0.0086.2 = 0.0536 ___metric units

    = 0.0086.2 = 0.0536 ___metric units

    At reservoir pressure, 446bars

  • NWOSU, DIXON 32 IJEH, ISIJOKELU

    At 280bars,

    Well Potential =

    ----------------------------------------------2.4

    Assuming EUR = 25%

    Hence,

    Minimum number of wells =

    2.2.1.2 Material Balance For Natural Depletion Alone

    a. Rock And Fluid Expansion

    The equations were used for calculating material balance;

    ---------------------------------------------------------------2.5

    Where,

    Np = Cumulative Oil Produced

    Boi = Initial Formation Volume Factor of Oil

    Bo = Final Formation Volume Factor of Oil

    N = Stock Tank Oil Initially in Place (STOIIP)

    Ce = Equivalent Compressibility of Oil

    P = Pressure Drop

    But,

    ----------------------------------------------------2.6

    Where,

    Co = Compressibility of Oil

    Cw = Compressibility of Water

  • NWOSU, DIXON 33 IJEH, ISIJOKELU

    So = Oil Saturation

    Swc = Connate Water Saturation

    Cf = Rock Compressibility

    Also

    -----------------------------------------------------------------------------2.7

    i. Tarbert Region:

    Boi = Bo @ 446 = 1.6038

    Bo @ 280 = 1.6737

    For water participating in expansion,

    -----------------------------------------------------------------------2.8

    ii. Ness Region:

    Boi = Bo @ 446 = 1.6038

    Bo @ 280 = 1.6737

  • NWOSU, DIXON 34 IJEH, ISIJOKELU

    For water participating in expansion,

    Estimation of the above parameters and final EUR for NATURAL DEPLETION

    case are presented below:

    Table 2.2: Analytical solution for Recovery by Natural Depletion Drive

  • NWOSU, DIXON 35 IJEH, ISIJOKELU

    2.2.2 Case Two: Water Injection

    The previous case assumed the reservoir produced only by natural depletion. In

    practice, reservoirs are rarely allowed to deplete almost to their bubble point

    pressures. Pressure maintenance schemes are implemented to sustain plateau

    production usually with Water Injection Scheme (Note: Pressure maintenance

    by Gas Injection is usually not feasible because of the enormous amounts of gas

    that is required; gas Injection supports oil recovery mainly via dissolution and

    miscibility phenomena).

    Here, we will calculate the amount of additional oil that can be recovered by

    water injection and also the number of wells that will effectively sweep oil in the

    reservoir while maintaining the reservoir pressure above bubble point.

    The total recovery during a water injection process can be given by;

    ----------------------------------------------------------------2.9

    -------------------------------------------2.10

    Where,

    Ed = f(primary depletion, krw & kro, o & w)

    Ea = f(mobility ratio, pattern, directional permeability, pressure

    distribution, cumulative injection & operations)

    Ev = f(rock property variation between different flow units,fluid density), Ev =

    0.7(assumption)

    2.2.2.1 Material Balance

    i. Tarbert Region:

    Evaluation of Ea

    Ea can be gotten from the graph as shown below:

  • NWOSU, DIXON 36 IJEH, ISIJOKELU

    Fig2.1: Reciprocal Mobility Ratio Chart

    The Mobility Ratio (MR) is first obtained using the relationship

    ---------------------------------------------------------2.11

    Next, the Reciprocal Mobility Ratio (inverse of MR) is calculated and the areal

    sweep efficiency (EA) corresponding to this value is read off the Reciprocal

    Mobility Ratio Chart.

  • NWOSU, DIXON 37 IJEH, ISIJOKELU

    Table 2.3: Reciprocal Mobility Ratio computation for obtaining error. Ea

    From the table and chart above, Ea = 0.98

    Evaluation of Ed

    Ed is calculated from a plot of fractional flow, fw versus water saturation, Sw.

    This plot shows the fractional flow of water when injected into the reservoir to

    displace oil. The plots are different for each rock type.

    -------------------------------------------------------------2.12

    Plot of fw vs Sw is generated using corresponding Relative Permeability

    (Imbibition) data

    Table 2.4: Relative Permeability (Imbibition) data table

  • NWOSU, DIXON 38 IJEH, ISIJOKELU

    Fig2.2: Fractional Flow curve for the Tarbert Region

    As shown above,

    Swc = 0.15, Swm = 0.71

    Therefore, the drainage efficiency at Break-through (BT) is obtained from

    equation 2.12;

    Recovery =

    = 0.6588 = 65%

    Ed = 0.66, Ev = 0.7, Ea = 0.98

    Therefore, R = 0.66*0.7*0.98 = 0.45

    ii. Ness Region

    Evaluation of Ea

    EA is the same as obtained for Tarbert since both rock types contain the same

    reservoir fluid.

    Evaluation of Ed:

    Plot of fw vs Sw is generated using corresponding Relative Permeability

    (Imbibition) data

    0

    0.1

    0.2

    0.3

    0.4

    0.5

    0.6

    0.7

    0.8

    0.9

    1

    1.1

    0 0.2 0.4 0.6 0.8 1 1.2

    fw

    Sw

    Tarbert

    Tarbert

    Swm

  • NWOSU, DIXON 39 IJEH, ISIJOKELU

    Table 2.5: Relative Permeability (Imbibition) data table

    Fig2.3 : Fractional Flow curve for the Ness Region

    As shown above,

    Swc = 0.30, Swm = 0.66

    Therefore, the drainage efficiency at Break-through (BT) is obtained from

    equation 2.12;

    Recovery = (0.66-0.30)/(1-0.30) = 0.51 = 51%

    Swm

  • NWOSU, DIXON 40 IJEH, ISIJOKELU

    Ed = 0.51, Ev = 0.7, Ea = 0.98,

    R = 0.51*0.7*0.98 = 0.35

    2.2.2.2 Estimation of Oil Recovery Using Hand Calculation

    From equation 2.9,

    Oil Recovery with water:

    Total oil produced:

    ------------------------2.13

    Therefore,

    Table 2.6 shows a section of an MS Excel file that contains calculations for the

    total oil that can be produced by water injection.

  • NWOSU, DIXON 41 IJEH, ISIJOKELU

    Table 2.6: Oil Recovery from Natural Depletion and Water Injection

    From the table above, the total oil recovery from Tarbert and Ness by natural

    depletion and water injection is 4.49E+06 Sm3 with a Global percent recovery of

    51%.

    Given that annual production plateau should be around 15% of Estimated

    Ultimate Reserves (EUR), Average Oil Withdrawal per day calculated from Table

    2.6 is 7478 Sm3/day.

    2.2.2.3 Minimum number of wells:

    Oil Flow rate, Qo, per well, is given by :

    ----------------------------------------------------------2.14

    Where,

    Kro = relative permeability of oil in the presence of water

    Bo = oil formation volume factor

    o = viscosity of oil

  • NWOSU, DIXON 42 IJEH, ISIJOKELU

    C =conversion factor

    K = permeability

    H = net pay thickness

    P = pressure drawdown

    Rd = reservoir drainage radius

    Rw = well radius

    S = skin

    Assumptions for Calculation:

    Wells drilled and completed in the TARBERT Region

    Reservoir producing at Pseudo-steady state

    Oil flowing at connate water saturation

    Reservoir drainage radius equals 400m

    Values of average permeability, K, Net-to-Gross ratio, NTG and average

    thickness, DZ were obtained from the geological model using FLOVIZ with

    Eclipse Simulator run on NOSIM mode. An examination of the 9 vertical

    layers of the Tarbert region showed an erosion of the top layer. Hence, only 8

    layers of reservoir sand thickness were used.

    Qo @ 446bars

    Bo = 1.6038

    o = 0.3916

    Kro = 0.8

    Z = 8.0907 per layer* 8 layers *NTG = 64.7256 * 0.96883 = 62.7081m

    Qo @ 280bars

    Bo = 1.6737

    o = 0.2829

    Kro = 0.8

  • NWOSU, DIXON 43 IJEH, ISIJOKELU

    Z = 8.0907 per layer* 8 layers *NTG = 64.7256 * 0.96883 = 62.7081m

    We have been informed of a possible production downtime of 10%. Hence, our

    rate is subject to a WEFAC (Well Efficiency Factor) of 90%.

    Therefore,

    =

    Implication:

    We need to drill at least 5 producer wells for optimal reservoir exploitation by

    Natural Depletion.

    Secondary oil recovery by water injection is usually incorporated in the field life

    of a reservoir. Hence, optimum number of wells for increased recovery by water

    injection was also calculated. Because of thermal cracks induced by injecting

    cold North Sea water into the hot reservoir, a skin of -4 is expected for a water

    injection case.

    The most efficient way to determine the amount of Water for injection is to

    calculate the amount of water required to achieve zero-net-voidage by applying

    the VOIDAGE REPLACEMENT PRINCIPLE.

    Field oil production rate was previously determined as 7478 Sm3/day. We shall

    find the equivalent reservoir oil volume. This volume is equal to reservoir water

    volume for zero-net-voidage.

    Subsequently, we determine the surface equivalent of this reservoir water which

    is calculated as:

  • NWOSU, DIXON 44 IJEH, ISIJOKELU

    Implication:

    We need to drill at least 4 injection wells for optimal reservoir exploitation by

    voidage replacement.

    2.2.3 Case Three: Gas Injection

    We would calculate the amount of recovery that can be achieved by gas

    injection while maintaining the reservoir pressure above bubble point. Because

    the NESS region is predominantly water zone, there will be no need injecting gas

    in this region. Hence, we focused on recoveries from the TARBERT region.

    2.2.3.1 Material Balance

    i. Tarbert Region

    The total recovery possible during a gas injection process can be obtained from

    equation 2.15

    ---------------------------------------------------------------2.15

    Recall that Equation 2.10 for Recovery Factor with all parameters defined as

    previously is:

    Evaluation of EA:

    The Mobility Ratio is first obtained, Reciprocal Mobility ratio estimated, and

    traced up to the corresponding gas cut curve to read off EA =0.74 (See Table

    2.8).

    Evaluation of ED:

    As with the water injection case, plot varies for the different rock types as

    presented below. Because the reservoir is predominantly water-wet, Gas

  • NWOSU, DIXON 45 IJEH, ISIJOKELU

    Injection constitutes a Drainage Process. Hence, the Drainage Data for Tarbert

    is made use of for computing fractional flow.

    Table 2.7: Gas-Oil Relative Permeability Data for Rock-Type 1

  • NWOSU, DIXON 46 IJEH, ISIJOKELU

    Figure 2.4: Relative permeability versus gas saturation curves

  • NWOSU, DIXON 47 IJEH, ISIJOKELU

    Figure 2.5: Plot of Gas Fractional flow against saturation for Tarbert

    From the graph, the Sgf and Sgm as shown on the chart are determined.

    Sgm = 0.25 , Sgc 0.0

    Therefore, the drainage efficiency at Break-through (BT) is obtained as follows;

    EV = 0.7 (assumption)

    Applying Equation 2.10,

    Recovery of oil from gas injection is shown in the Table 2.8 below:

  • NWOSU, DIXON 48 IJEH, ISIJOKELU

    Table 2.7: Recoveries from combined Natural Depletion and Gas Injection

    As shown in the table above, total oil produced from Tarbert due to gas injection

    is 5,219,682.323 Sm3 with a per cent recovery of 14.49 %.

    Total oil from Tarbert from both natural depletion and gas injection is therefore,

    6,978,338.529 Sm3 with a per cent recovery of 19 %.

  • NWOSU, DIXON 49 IJEH, ISIJOKELU

    CHAPTER THREE

    DYNAMIC FIELD DEVELOPMENT STUDY USING ECLIPSE

    SOFTWARE

    A field development study can be conveniently done using Eclipse as different

    reservoir production cases can be simulated to determine the best strategy for

    producing from the field.

    Four cases will be considered:

    Natural Depletion

    Natural Depletion followed by Water Injection

    Natural Depletion Followed by Gas Injection

    Natural Depletion followed by Water Alternating Gas Injection (WAG)

    3.1 Case One: Natural Depletion

    Natural depletion, also known as primary production, describes a scenario

    where the reservoir is produced via its natural energy. In natural depletion, the

    energy required to drive the fluids from the reservoir to the wellbore and

    consequently to the surface is the reservoirs energy. This energy might be due

    to a solution gas drive, aquifer and rock expansion, gravity drainage or water

    drive.

    3.1.1 Natural Depletion with the Available Four Exploratory Wells

    For this natural depletion case, the original four vertical wells in the model were

    run to limit BHP of 100 bars atmospheric and the evolution of field pressures

    and flow rates during the period were noted.

  • NWOSU, DIXON 50 IJEH, ISIJOKELU

    Fig 3.1: Well Architecture: Natural Depletion from Wells PA2, PN2, PA1 and

    PN1

    Fig 3.2: FOPR, FOPT and FOE as a function of time for th e 4-well Natural

    Depletion case

  • NWOSU, DIXON 51 IJEH, ISIJOKELU

    The figure above indicates a maximum oil recovery of 22% for this natural

    depletion case. Also, the plateau production period peaks for only five years and

    then declines to zero in seven years. Hence, natural depletion can neither

    sustain production for the 15 years proposed for the project nor can recoveries

    are maximized.

    Moreover, the principle of profitable business is directly challenged as oil

    production revenue will be insufficient to offset the huge investments required

    for a project of this magnitude.Thus, the need for secondary and tertiary

    recovery schemes arises as the field cannot be produced with a primary recovery

    technique alone.

    Further, a disparity was observed between the calculated and simulated value of

    the maximum recovery. The recovery from the analytical calculations was 6%

    while the recovery from the numerical simulation was 22%. This suggests that

    there is a nearby aquifer that provided pressure support to the reservoir

    Fig 3.3: Oil Production Rate as a Function of Time from Wells PA2, PA1, PN2

    and PN1

    From an analysis of the figure above, it was observed that well PA2 contributed

    poorly to the total field production. This could be due to any or a combination

    of the following reasons:

  • NWOSU, DIXON 52 IJEH, ISIJOKELU

    Improper well placement,

    Proximity to a fault,

    High positive skin

    Completing the well in a water zone.

    Well PA2 can either be shut off or converted into an injection well since it is a

    poor producer. The latter was deemed a better economic decision as it ensured

    the continuous use of the well to add value to the field. Hence, subsequent

    simulations for the natural depletion case were done with PA2 shut while new

    wells were drilled and brought on stream.

    3.1.2 Effect of Critical Gas Saturation

    To study the effect of critical gas saturation on field productivity, the critical gas

    saturation was increased from 0%, as was used in the previous cases, to 10%. The

    implication of setting the critical gas saturation to 0% is that gas begins to

    evolve from solution throughout the reservoir as soon as the reservoir pressure

    depletes to a level that is below the bubble point pressure of the oil. This leads

    to an increase in gas-oil ration and a subsequent decrease in oil productivity.

    Fig 3.4: Comparing the Field Recovery Efficiency and Field Plateau

    Production Rate for both cases

  • NWOSU, DIXON 53 IJEH, ISIJOKELU

    Higher recoveries and longer plateaus were recorded for the simulation case

    with a critical gas saturation of 10%. There was an increase in total recovery from

    22% to 26% and the time required for production to terminate increased by one

    year.

    Fig 3.5: Comparing the Field Pressure and Total Field Production Volume for

    both cases

    By increasing the critical gas saturation to 10%, the field total production

    increased from 8MMm3 to 9MMm3 and an additional year was required for the

    reservoir to deplete to the bottom hole flowing pressure limit of 100bars.

    As with the previous graphs, the new case gave better results. In contrast with

    the previous case, an extra year was required for the field water cut to attain its

    maximum value and an additional 18 months was required for the field gas-oil

    ratio to attain its peak. From the results above, it can be confidently inferred

    that recovery is improved when dissolved gases stay longer in solution as gas

    mobility is delayed to obtain better oil recoveries. Hence, subsequent simulation

    cases will be done with the critical gas saturation set to 10%.

  • NWOSU, DIXON 54 IJEH, ISIJOKELU

    Fig 3.6: Comparing the Field Water Cut and Field Gas-Oil Ratio for both

    cases

    3.1.3 Natural Depletion with Increased Development Wells:

    The need to drill added development wells arises as a result of the fact that the

    three available wells are inadequate to optimally drain the field of its oil

    resources. Economics plays a major role here as drilling of new wells represents a

    major portion of capital expenditures. Thus, the number of new wells to be

    drilled should be optimized to obtain maximal recovery from the field.

    3.1.3.1 Natural Depletion with Five Producer Wells

    The minimum number of production wells, as computed through the hand

    calculations, was 5 wells. Well PA2 was shut in and two new wells, PB1 and PB2,

    were drilled to increase recovery from the field. PB2 was drilled very close to the

    shut-in PB1 and PB1 was drilled in an area with very high oil saturation.

  • NWOSU, DIXON 55 IJEH, ISIJOKELU

    Fig 3.7: Well Architecture: Natural Depletion with W ells PA1, PNI, PN2, PB2

    and PA4

    Fig 3.8: Natural Depletion with 5 Producers: FOE, FOPT and FOPR as a

    function of time

    For the 5-well case, FOPR peaked for 6 years in contrast with the 4-well case in

    which FOPR peaked for only 5 years. Field Oil Recovery also increased from 26%

    to 30%.

  • NWOSU, DIXON 56 IJEH, ISIJOKELU

    Fig 3.9: Natural Depletion with 5 Producers: FPR, FOE, F WCT, FGOR as a

    function of time

    Fig 3.10: Well by Well Analysis: Individual Oil Well Production Rate as a

    function of time

  • NWOSU, DIXON 57 IJEH, ISIJOKELU

    3.1.4 Inferences: Natural Depletion

    From the simulations and optimizations done thus, we came up with the

    following inferences:

    Ultimate Oil Recovery:

    The oil recovery obtained from the different simulation runs is shown on

    the bar chart displayed above. EUR from the natural depletion varied from 20%

    to about 30%. The highest recovery (30%) was obtained by depleting the

    reservoir naturally with 7 wells while shutting well A2. The low recovery from

    this type of reservoirs suggests that large quantities of oil remain in the reservoir

    and the reservoir pressure dropped very much for this low recovery. This

    naturally depleted reservoir will be considered a good candidate for secondary

    recovery applications such as water injection as well as gas.

    Reservoir pressure:

    The reservoir pressure declined rapidly and continuously. This reservoir

    pressure behaviour is attributed to the fact that no extraneous fluids or gas caps

    are available to provide a replacement of the gas and oil withdrawals. There is

    no voidage replacement no sweep provision for the hydrocarbon.

    Water production:

    There was considerable water production with the oil during the entire

    producing life of the reservoir. This is due to the presence of an active water

    drive.

    Gas-oil ratio:

    This natural depletion is characterized by a rapidly increasing gas-oil ratio from

    all the wells, regardless of their structural position. After the reservoir pressure

    has been reduced below the bubble-point pressure, gas evolves from solution

    throughout the reservoir. Once the gas saturation exceeds the critical gas

    saturation, free gas begins to flow toward the wellbore and gas-oil ratio

    increases.

  • NWOSU, DIXON 58 IJEH, ISIJOKELU

    3.2: Case 2: Water Injection Preceded by Natural Depletion

    In many cases, water injection has traditionally used in the oil industry for

    pressure maintenance. It is usually used to maintain pressure above the bubble

    point pressure and in some cases, to pressurize the reservoir to the bubble point

    pressure. By simulation for water injection, water is pumped or injected into the

    reservoir to maintain pressure and expel oil in the pore spaces. This water

    displaces this resident oil and pushes them towards the producing wells in that

    manner so as to maintain pressure and achieve improved recovery.

    In this water injection simulation case, the desire was to maintain the average

    reservoir pressure at 290 bars. Hence, the field was naturally depleted from 490

    bars to 290 bars and water injection was initiated at this instance. Well PA2, the

    poor producer well, was converted to an injector well. Four additional wells were

    then drilled to serve as injection wells.

    Due to the fact that oil could be recovered as a result of the water injection

    sweep, two extra producer wells were drilled. This gave a total of 7 producers

    and five injector wells.

  • NWOSU, DIXON 59 IJEH, ISIJOKELU

    Fig 3.11: Well Architecture: 7 producers and 5 injectors. We ll PA2 is an

    injection well

  • NWOSU, DIXON 60 IJEH, ISIJOKELU

    Fig 3.12: Water Injection: FOPR, FOE and FOPT as a function of time

    As predicted, the recovery efficiency increased with the water injection scheme.

    The recovery efficiency increased astronomically from 30%, as obtained with

    natural depletion to 52%. The maximum oil production of 7200m3/day could be

    sustained for four years and the production constraint of a keeping the plateau

    for a 60% of the Estimated Ultimate Recovery could be met.

    Also, the total oil production rose steadily and finally peaked at 18MMm3 in 14

    years.

  • NWOSU, DIXON 61 IJEH, ISIJOKELU

    Fig 3.13: Water Injection: FPR, FWCT and FWIR as a function of time

    Since the oil production was done at a pressure above oil bubble point pressure,

    the FGOR remained constant at a value of 0.2m3/m3. Reservoir pressure dropped

    steadily from initial reservoir pressure to 296 bars and started rising at the start

    of water injection. Field pressure rose very slowly from 296 bars to a final value

    of 312 bars in 14 years.

    The water injection wells were opened in the 16th month after the start of oil

    production. Water injection was done mostly in the Tarbert region. For this 7-

    well case, the water injection rate increased rapidly at the time of injection in

    order to compensate for voidage already created before injection. Injection rate

    then dropped gradually as the plateau rate (oil production) dropped too. The

    average reservoir pressure was maintained above 300 bars as it gently rose. The

    water cut also increased as the plateau rate was dropping which indicated that

    the injected water has broken through and then being produced.

  • NWOSU, DIXON 62 IJEH, ISIJOKELU

    3.3 Case 3: Gas Injection Preceded by Natural Depletion

    This was simulated by re-defining the water injection wells as gas injection wells.

    Gas was then injected into the reservoir when the reservoir pressure had

    dropped to 290bars because the injected gas is most soluble in the oil at that

    pressure.

    Fig 3.14: Gas Injection: FOPR, FOE and FOPT as a function of time

    The FOPR plateau at 7200m3 could only be sustained for 4 years and total oil

    recovery was 15 million cubic metres of oil. FOE dropped to 42% as against 52%

    that was obtained with water injection

  • NWOSU, DIXON 63 IJEH, ISIJOKELU

    Fig 3.15: Water Injection: FPR, FWCT and FWIR as a function of time

    From the production profile of the four wells case, proposed pressure

    maintenance at 340 bars wasnt as successful as desired. But however, the rate of

    pressure decline around 340 bars reduced for a while, it then reduced gradually

    from 340 bars at 300 days to 290 bars at 4 years where it was then maintained

    continuously.

    Since the field oil recovery dropped by using gas injection, there are still

    bypassed oil that were not recovered. This makes only the gas injection not very

    suitable on an absolute scale, hence the need for combination with water.

    3.4 Case 4: Water- Alternating Gas Injection

    In this secondary recovery scheme, the reservoir was allowed to deplete to a

    predetermined pressure after which water and gas were alternately injected.

    Water-alternating gas schemes have proven very effective for secondary recovery

    as gas injection schemes result in viscous fingering and reduced sweep

  • NWOSU, DIXON 64 IJEH, ISIJOKELU

    efficiency. In WAG schemes, the injected water displaces the oil in the high

    permeability layers while the gas displaces the oil in the low permeability zones.

    Water is injected into the reservoir for a period of say two years with the same

    conditions required for ordinary water injection. The water pumps are then shut

    off and the gas compressors are started for injection of gas into the reservoir

    through the same injection wells for a shorter duration. The duration of the

    water and gas injections are continuously altered until favourable results are

    obtained.

    Four WAG cycles were considered:

    Sub case 1: 2.5 years of water injection - 6 months of gas injection - 1.5

    years of water injection - 6 months of gas injection-water injection.

    Sub case 2: 32 months of water injection - 6 months of gas injection - 2

    years of water injection - 6 months of gas injection - 18 months of water

    injection-3 months of gas injection - 12 months of water injection - 3

    months of gas injection - 12 months of water injection - 3 months of gas

    injection - water injection

    Sub case 3: 2.5 years of water injection - 6 months of gas injection - 2 years

    of water injection - 6 months of gas injection - 2 years of water injection -

    6 months of gas injection - 2 years of water injection - 6 months of gas

    injection - 2 years of water injection - 6 months of gas injection -water

    injection.

    Sub case 4: 5 years of water injection-6 months of gas injection-2 years of

    water injection-6 months of gas injection-2 years of gas injection-6 months

    of gas injection-2 years of water injection-6 months of gas injection-water

    injection.

    The results are presented below:

  • NWOSU, DIXON 65 IJEH, ISIJOKELU

    Fig 3.16: Sub-case 1: FOPT, FOE, FOPR, FWIR and FOPR as a function of time

    Fig 3.17: Sub case 2: FOPR, FOPT, FOE, FWIR and FPR as a function of time.

  • NWOSU, DIXON 66 IJEH, ISIJOKELU

    Fig 3.18: Sub case 3: FOPR, FOPT, FOE, FWIR and FPR as a function of time

    Fig 3.19: Sub case 4: FOPR, FOPT, FOE, FWIR and FPR as a function of time

  • NWOSU, DIXON 67 IJEH, ISIJOKELU

    Sub-case 3 was the most effective as it had the highest field oil recovery of 55%.

    Sub-cases 1, 2 and 4 had field oil recoveries of 54%, 54.5% and 52 % respectively.

    The pressure maintenance was effective around 350 bars and the decline in

    plateau rate was gradual over time. The field gas oil ration rose gently over the

    production period while the water cut rose steeply during the plateau

    production and then unnoticeable slowly during the decline period.

    There was fluctuation in the producing gas-oil ratio during the life of the

    reservoir due to the alternating injection of water and gas with FGOR highest

    during years of gas injection.

    In conclusion, compared to the water injection case, WAG showed an overall

    increase in FOE, FOPR, reduction in FWCT and better pressure maintenance.

    Table 3.1: Comparison of WI and WAG

    CASE

    FOE (%)

    FOPT (MM

    Sm3)

    FWCT (%) PLATEAU

    (Years)

    FPR

    (Bar)

    WI 50 18.30 85 3.8 310

    WAG 55 18.75 80 4.2 350

    WAG has a higher total oil production with reduced water production and

    better pressure maintenance than the water injection scheme. This is due to the

    fact that injecting gas; reduces the viscosity of oil which improves the sweep,

    reduces the amount of injected water/water cut. WI exhibited a longer plateau

  • NWOSU, DIXON 68 IJEH, ISIJOKELU

    CHAPTER FOUR

    ECONOMIC ANALYSIS

    The oil and gas business aims to maximize profitability of any prospect while

    minimizing expenditures and associated uncertainties/risks, within a shorter

    time frame. Hence, a key parameter for the justification of any petroleum

    business is its economic viability.

    The goal of this reservoir simulation project is to propose a development plan

    for the Brent East reservoir that maximizes hydrocarbon production and

    minimizes the development cost in $/bbl. In the previous chapter, the optimized

    development cases for the different development scenarios were determined

    after rigorous numerical simulations. This chapter will therefore, deal with the

    economic evaluation of those optimal development options for the ALWYN

    field.

    The capital costs, operating costs, gross revenues, pay-back time and other

    profitability indices will be determined for each of the development strategies

    that were optimised in the previous chapter. The final project decision will then

    be based on the economic evaluation results.

    The following assumptions were made in the evaluation:

    Oil price is pegged at $110/bbl.

    OPEX is limited to the lifting, transportation and distribution costs only.

    Other components of the operating expenditure that are based on

    specific activities anticipated in the lifetime of the field were not

    considered.

    The already existing wells come at zero cost. They will be neglected in

    the computation of the CAPEX

    The cost of water and gas volumes used for the injection cases, as well as

    their supportive surface handling equipment, was ignored.

    Taxation costs is 40% of gross revenue

    Maintenance costs, replacement costs, manpower costs,

    decommissioning and well work over expenditures were not considered

  • NWOSU, DIXON 69 IJEH, ISIJOKELU

    On-stream time was 7884 hours per year

    The economic analysis will be based on the field development capital

    and operating costs that were given in the November 2011 edition of the

    Journal of Petroleum Technology

    CAPEX

    Treatment and Production Facilities Platform 700MM$

    Drilling and Accommodation Platform 250MM$

    Secondary Platform 250MM$

    Drilling Cost per well for deviated wells from a platform 12MM$

    Gas compressors 44.2MM$

    OPEX

    Lifting, Production and Transportation costs 6.5$/bbl

    The following computed parameters were used to evaluate the profitability of

    the different scenarios:

    Revenue = Selling Price of oil x Volume of Produced Oil

    Total CAPEX = Cost of drilling and accommodation facilities + Cost of

    Production facilities

    Total OPEX= Lifting costs x Volume of Produced oil

    Depreciation = CAPEX/ Project life

    Taxable Income= Gross Revenue Depreciation - Operating Expenses

    Project tax bill = Taxation Rate x Taxable Income

    Cash Flow = Revenue Investment - OPEX- Tax bill Discounted Factor = (1 + i) n

    Discounted Cash Flow = Discount Factor x Cash Flow

    Net Present Value = Cumulative NPV each year.

    Gross Profit Margin = Gross Revenue Total Investment Costs

    GPM per barrel = GPM/ Total Production

    Profitability Index = Final CNPV/Total Investment

    Pay Back Period = Time at CNPV is 0

  • NWOSU, DIXON 70 IJEH, ISIJOKELU

    Internal Rate of Return, IRR = D.F at CNPV is 0

    4.1 Economic Evaluation of Natural Depletion at Economic Limit

    The natural depletion case represents the simplest and cheapest production

    strategy. Production commences as soon as the production and treatment

    facilities have been set up and no extra wells have to be drilled. Oil production

    from the four available injection wells totalled 67.33 million barrels with a

    recovery efficiency of 30%.

    Table 4.1 Revenues and Expenditures for Natural Depletion

    CAPITAL EXPENDITURE

    Units/Cost

    per barrel

    Unit

    Cost

    in

    MM$

    Total Cost in

    MM$

    Treatment and Production

    Facilities 1 700 700

    Drilling and Accomm0dation

    Platform with 40 Platform slots 1 250 250

    Drilling Cost for Horizontal Wells 0 16 0

    Drilling cost for Deviated/Vertical

    Wells 2 12 24

    Horizontal Subsea Well and Piping 0 40 0

    Vertical Subsea well and Piping 0 36 0

    Gas Injection Compressors 0 44.2 0

    Total Capital Investment 974 974

    OPERATING EXPENDITURE

    Production and Transportation

    Costs 67.33 6.5 437.6

    TOTAL EXPENDITURE 1411.6 1411.6

    Total Expenditure per barrel 20.96539433

    PROFIT

    Profit per barrel 89.03460567

    Gross Profit Margin in MM$ 5994.7 5994.7

  • NWOSU, DIXON 71 IJEH, ISIJOKELU

    Table 4.2 Economic Evaluation Indices for Natural Depletion

    NATURAL DEPLETION

    Total Oil Production in MMbbls 67.33

    Total Investment in MM$ 724

    Gross Revenue in MM$ 7406.3

    Gross Profit Margin in MM$ 5994.7

    Gross Profit Margin per barrel in MM$ 92.75

    Profitability Factor 1.975138122

    Cummulative Net Present value in MM$ 1430

    Internal rate of Return in % 40%

    Pay back Period 2.8 years

    Project's Economic Life 9 years

    With a gross profit of $5.99 billion dollars, over a fifteen year period, from a total

    expenditure of 974 million dollars, this seems to be a very sound investment

    strategy. For every barrel of oil produced, a gross profit of $89 is to be made.

    Investors should also drool at the fact that the initial capital investments would

    be recovered after only 2.7 years. Cumulative Net Present value stands at a

    staggering 1.43 billion dollars and the profitability factor is 1.97.

    The financial soundness of this production strategy is also backed by other

    profitability indices. The internal rate of return is 42% which is far greater than

    the projects rate of return.

  • NWOSU, DIXON 72 IJEH, ISIJOKELU

    Fig4.1 Cash flow curve for Natural Depletion Scheme

    However, the short economic life of the project might want to deter investors

    from backing this option. The project is only economic for 9 years out of the 15

    years that it is expected to run. The cash flow is fairly constant at 500 million

    dollars for the first six years and peaks at 580 million dollars in the seventh year.

    Economic decline sets in after the seventh year as cash flow is at the end of the

    8th and 9th is 419 MM$ and 41 MM$ respectively. The project is no longer

    economically viable after the 9th year.

    At face value, this is profitable for any investor but the short economic life

    represents a drawback.

    Other development strategies will have to be evaluated to determine the most

    profitable development option based on basic assumptions, available constraints

    and data.

    4.2 Economic Evaluation of Gas Injection Scheme at Economic Limit

    The gas injection scheme consists of seven producers (four new wells) and five

    injectors (four new wells) as well as the associated treatment and production

    systems. A very expensive gas compressor is also installed on-site to facilitate the

    injection of the gas at the required pressure. The gas injection strategy led to the

    -1200

    -1000

    -800

    -600

    -400

    -200

    0

    200

    400

    600

    800

    0 2 4 6 8 10

    Cash flow in MM$

    Time in years

    Cash Flow for Natural Depletion

    Cash Flow

  • NWOSU, DIXON 73 IJEH, ISIJOKELU

    production of 92.25 million barrels with a recover