dsm-1510002-sp-20_v1.0[1]
TRANSCRIPT
7/22/2019 DSM-1510002-SP-20_V1.0[1]
http://slidepdf.com/reader/full/dsm-1510002-sp-20v101 1/28
Downstream Manufacturing Restricted
DBAM Code and Name:
MAN.15.10 Provide Asset Availability – Ensure
Assessment and Mitigation Planning for
Corrosion Under Insulation andExternal Chloride Stress Corrosion Cracking
Document Number
DSM-1510002-SP-20 Equipment Integrity
Shell Downstream Manufacturing
Assessment and Mitigation Planning forCorrosion Under Insulation and
External Chloride Stress Corrosion Cracking
Table of Contents
1. General ......................................2 1.1 Scope ........................................... 2 1.2 Purpose ........................................ 2 1.3 Overview....................................... 2 1.4 Deviations..................................... 2 1.5 Tools............................................. 3 1.6 Definitions..................................... 3
2. Assessment ..............................4 2.1
General......................................... 4
2.2 Prioritising Units ........................... 5 2.3 Developing the Equipment and
Piping List ..................................... 5 2.4 Challenging the Need for
Insulation...................................... 5 2.5 Performing an Initial External
Visual Inspection .......................... 5
2.6 Determining the Probability ofOccurrence of CUI and ECSCC... 6
2.7 Estimating the PotentialConsequence of a Failure............ 6
2.8 Determining the InspectionStrategy ........................................ 7
3. Mitigation Planning.................. 8 3.1 Development ................................ 8 3.2 Additional Considerations ............ 8
Appendix 1 – Example InsulationSystem Checklist ................... 18
Appendix 2 – Technical Basis ...... 19
Appendix 3 – Risk Assessment
Example .................................. 27
Version: 1.0 Date: January 2007 Custodian: DME/4 ECCN: EAR99 Page: 1 of 28
Printed _______________ Printed copies are uncontrolled
Printed copy should not be used more than 1 month after printed date
Mar 12, 2007
7/22/2019 DSM-1510002-SP-20_V1.0[1]
http://slidepdf.com/reader/full/dsm-1510002-sp-20v101 2/28
Downstream Manufacturing Restricted
DBAM Code and Name:
MAN.15.10 Provide Asset Availability – EnsureEquipment Integrity
Assessment and Mitigation Planning for
Corrosion Under Insulation andExternal Chloride Stress Corrosion Cracking
Document Number
DSM-1510002-SP-20
1. General
1.1 Scope
1. This Downstream Manufacturing (DSM) Specification (SP) provides requirements and
supporting elements for the assessment and mitigation planning for corrosion under
insulation (CUI) of carbon and low alloy steels and external chloride stress corrosion
cracking (ECSCC) of austenitic stainless steel.
2. Duplex stainless steels and high alloys are excluded from this Specification. A
knowledgeable materials and corrosion engineer should be consulted for requirements
for these materials.
1.2 Purpose
1. This SP provides sites with a risk-based assessment and mitigation planning
methodology for CUI and ECSCC based on operating conditions, installation design and
current condition.
2. Implementation of this SP provides sites with an understanding of the equipment and
piping susceptible to CUI and ECSCC and an equipment and piping list prioritised by
both the likelihood of deterioration occurring and the estimated potential consequences
should a pressure boundary breach occur.
3. This SP describes the risks consistent with the March 2006 edition of the Group Risk
Assessment Matrix.
4. This SP summarizes the technical issues to consider in the management of these
mechanisms.
1.3 Overview
The approach employed by this document assesses the risk of CUI and ECSCC by a
combination of the current condition of the equipment or piping, the original equipment
specifications and accurate operating conditions. A graphical representation of the
management program for CUI or ECSCC is shown in the first row “Prioritisation and
Inspection Strategy Determination” of Figure 1, Overview: Management of Corrosion Under
Insulation for Carbon/Low Alloy Steel, and Figure 2, Overview: Management of External
Chloride Stress Corrosion Cracking for Austenitic Stainless Steel.
1.4 Deviations
1. The requirements in this SP are based on expert knowledge and field experience.
Individual sites should rarely need to adopt more or less stringent requirements.
2. Deviations from the requirements in this SP shall use Deviation Request Form
DSM-0515001-TO-12, which shall be kept in a log for technical assurance auditing.
Version: 1.0 Date: January 2007 Custodian: DME/4 ECCN: EAR99 Page: 2 of 28
Printed _______________ Printed copies are uncontrolled
Printed copy should not be used more than 1 month after printed date
Mar 12, 2007
7/22/2019 DSM-1510002-SP-20_V1.0[1]
http://slidepdf.com/reader/full/dsm-1510002-sp-20v101 3/28
Downstream Manufacturing Restricted
DBAM Code and Name:
MAN.15.10 Provide Asset Availability – EnsureEquipment Integrity
Assessment and Mitigation Planning for
Corrosion Under Insulation andExternal Chloride Stress Corrosion Cracking
Document Number
DSM-1510002-SP-20
Version: 1.0 Date: January 2007 Custodian: DME/4 ECCN: EAR99 Page: 3 of 28
Printed _______________ Printed copies are uncontrolled
Printed copy should not be used more than 1 month after printed date
3. Deviations from the recommendations in this SP may occasionally be necessary due to
specific local requirements.
4. Deviations from the recommendations in this SP should also be logged and provided tothe technical community and the Equipment Integrity (EI) Global Process Owner (GPO)
for review and use in the continuous improvement of this specification.
1.5 Tools
1. This SP uses a semi-quantitative method to assess CUI and ECSCC risks. More
quantitative, computerized risk assessment tools may be employed provided the results
using those methods are consistent with this Specification. Computerized tools shall be
endorsed for use for CUI and ECSCC by the EI GPO.
2. With computerized risk based inspection (RBI), the CUI/ECSCC assessment can be
performed at the individual equipment or piping level or it may be more efficient to
group piping and equipment and analyse them together. Groups of equipment and pipingwith the same service that cannot be isolated individually and are in similar condition
may be good candidates for grouping. Groups of equipment can include a corrosion loop
or a long line of piping in a piperack.
1.6 Definitions
1. Corrosion under insulation (CUI) – Aqueous corrosion of carbon and low alloy steels.
The resulting corrosion pattern is of generally uniform morphology. CUI does not
include external chloride stress corrosion cracking.
2. Cladding – Insulation covering; usually aluminium sheet, but can be stainless steel,
galvanised carbon steel, or UV-cured fibreglass.
3. Criticality – A combination of the probability of failure and the consequence of the
failure (another term for long-term average risk)
4. Deadleg – Components of a piping system that normally have no significant flow.
Examples include blanked branches, lines with normally closed block valves, lines with
one end blanked, pressurized dummy support legs, stagnant control valve bypass piping,
spare pump piping, level bridles, relief valve inlet and outlet header piping, pump trim
bypass lines, vents, drains, bleeders, sample points and instrument connections.
Note: Deadlegs and attachments that protrude from insulated piping can operate at a
much different temperature than the operating temperature of the active line. This
temperature difference is important in determining items in a CUI program.
5. External chloride stress corrosion cracking (ECSCC) – stress corrosion cracking of
austenitic alloys containing less than 32% nickel initiating on the external (non-processcontacting) surface. Refers to austenitic stainless steel in this SP unless duplex stainless
steel or high nickel alloy specifically detailed. In addition to chloride, can also include
other halides (fluoride and bromides) in the environment.
Mar 12, 2007
7/22/2019 DSM-1510002-SP-20_V1.0[1]
http://slidepdf.com/reader/full/dsm-1510002-sp-20v101 4/28
Downstream Manufacturing Restricted
DBAM Code and Name:
MAN.15.10 Provide Asset Availability – Ensure
Assessment and Mitigation Planning for
Corrosion Under Insulation andExternal Chloride Stress Corrosion Cracking
Document Number
DSM-1510002-SP-20 Equipment Integrity
6. Inspection Strategy (IS) – Plan for inspection and maintenance of equipment items
susceptible to CUI. An IS:
a. Is developed from probability and consequence assessment.
b. Includes visual and NDE inspections, potential repair/replacement plans for metal
loss; repair/replacement plans for coating and insulation systems.
c. Includes re-assessment needs for future inspection.
7. Linework – Piping or piping system
8. Plant – All the units at an entire location (e.g. Berre, Geismar, Stanlow, etc.). Also
referred to as a "site".
9. Process unit – Section of a site that manufactures a product. For example, the "IPA"
process unit uses propylene as a feedstock and produces isopropyl alcohol. Also referred
to simply as a "unit" or “factory”.
10. RBI – Risk Based Inspection
11. Site – All the units at an entire location (e.g. Berre, Geismar, Stanlow, etc.). Also
referred to as a "plant".
12. Stainless steel – Austenitic stainless steel, unless specified otherwise in this SP. This
term does not apply to duplex stainless steels or nickel alloys.
13. Susceptible areas – Areas on equipment or piping that are more vulnerable than other
areas because they retain moisture or because they are points of water ingress. See
Appendix 2, Technical Basis, for a description of some common locations on equipment
that are more susceptible to CUI.
14. Tag number – Equipment number or piping system number.
15. Unit –Section of a site that manufactures a product, also referred to as a "process unit" or“factory”. For example, the "IPA" unit uses propylene as a feedstock and produces
isopropyl alcohol.
16. UV – Ultraviolet light
17. VCE - Vapour cloud explosion
18. VIR – Value Investment Ratio
2. Assessment
2.1 General
1. This section describes how to perform a site assessment for CUI and/or ECSCC and
includes how to prioritise the units to be assessed, how to prioritise the equipment and
piping within each unit and how to determine which inspection strategy to apply to the
equipment and piping. These steps are outlined in the first row “Prioritisation and
Inspection Strategy Determination” of Figure 1, Overview: Management of Corrosion
Version: 1.0 Date: January 2007 Custodian: DME/4 ECCN: EAR99 Page: 4 of 28
Printed _______________ Printed copies are uncontrolled
Printed copy should not be used more than 1 month after printed date
Mar 12, 2007
7/22/2019 DSM-1510002-SP-20_V1.0[1]
http://slidepdf.com/reader/full/dsm-1510002-sp-20v101 5/28
Downstream Manufacturing Restricted
DBAM Code and Name:
MAN.15.10 Provide Asset Availability – Ensure
Assessment and Mitigation Planning for
Corrosion Under Insulation andExternal Chloride Stress Corrosion Cracking
Document Number
DSM-1510002-SP-20 Equipment Integrity
Under Insulation for Carbon/Low Alloy Steel, and Figure 2, Overview: Management of
External Chloride Stress Corrosion Cracking for Austenitic Stainless Steel.
2.2 Prioritising Units
Sites may elect to assess CUI and ECSCC risks across the entire site as a whole or unit-by-
unit with the priority of unit assessment based on the type of hydrocarbon each unit processes
(e.g. a unit processing ethylene would have a higher priority than a unit processing residue).
The decision on how to assess should be based on the effectiveness and efficiency of
application of each method.
2.3 Developing the Equipment and Piping List
1. A complete list of equipment and piping systems with their corresponding historical,
installation, and process condition data shall be developed for the equipment and pipingin each unit being assessed.
2. This equipment and piping is analysed and a risk-based inspection strategy determined
through the process described in the remainder of Section 2. This process may be
performed at the individual equipment or piping level or it may be more efficient to
group piping and equipment and analyse them together. Groups of equipment and piping
with the same service, in similar condition and that cannot be isolated individually may
be good candidates for grouping. Groups of equipment can include a corrosion loop or a
long line of piping in a piperack.
2.4 Challenging the Need for Insulation
After the equipment and piping list has been developed but prior to starting the determinationof the inspection strategy, the need for insulation should be verified. Sites should use the flow
scheme of Figure 3, Challenging the Need for Insulation (and part two in Figure 4) to
determine whether or not insulation is actually required and if a detailed Risk-Based
Inspection (RBI) analysis is necessary.
2.5 Performing an Initial External Visual Inspection
1. After the equipment and piping list has been generated, an initial external visual
inspection shall be conducted to assess the condition of the insulation system and
exposed areas of the coating.
2. Personnel experienced with inspection of CUI and ECSCC should participate in this
inspection.
3. The condition of the insulation and data necessary to determine the probability of CUI
and/or ECSCC shall be collected and documented.
1. Refer to Appendix 1, Example Insulation System Checklist.
Version: 1.0 Date: January 2007 Custodian: DME/4 ECCN: EAR99 Page: 5 of 28
Printed _______________ Printed copies are uncontrolled
Printed copy should not be used more than 1 month after printed date
Mar 12, 2007
7/22/2019 DSM-1510002-SP-20_V1.0[1]
http://slidepdf.com/reader/full/dsm-1510002-sp-20v101 6/28
Downstream Manufacturing Restricted
DBAM Code and Name:
MAN.15.10 Provide Asset Availability – Ensure
Assessment and Mitigation Planning for
Corrosion Under Insulation andExternal Chloride Stress Corrosion Cracking
Document Number
DSM-1510002-SP-20 Equipment Integrity
4. Sites may use the results of the latest documented external visual inspection to serve this
purpose if the quality, relevancy, time the inspection data was performed provides
adequate information to determine the probability as outlined Section 2.7.
5. For additional insight into CUI and ECSCC, refer to Appendix 2, Technical Basis.
2.6 Determining the Probability of Occurrence of CUI and ECSCC
1. After the initial external visual inspection is completed, the probability of CUI/ECSCC
shall be determined.
2. Several factors affect this probability, including operating temperature, insulation type
and condition, coating type and condition, and age of the coating system.
3. Personnel experienced with CUI and/or ECSCC and personnel experienced with the
equipment history should be involved in determining the probability of occurrence. The
same experienced individual who participated in the external visual inspection should participate in the probability determination.
4. Probability of occurrence shall be quantified using Table 1, Probability Assessment for
CUI of Carbon/Low Alloy Steel or Table 3, Probability Assessment for ECSCC of
Austenitic Stainless Steel.
a. Each probability factor heads a column in the tables.
b. Move down the column to the description that matches that of the condition of the
equipment or piping being evaluated.
c. Move across to the Points column on the right to determine the number of points for
that probability factor.
d. Repeat this procedure for each factor in the table.
e. Add all the points to determine the Probability Point Total.
Note: Wall thickness considerations are not included in the probability assessment table
for carbon/low alloy steel, but appreciate that the less wall loss can be tolerated, the
more probable a CUI failure will be at a specified corrosion rate.
2.7 Estimating the Potential Consequence of a Failure
1. After the equipment and piping list has been generated, the consequence of a potential
failure shall be determined. The first step is to determine the failure mode:
a. For CUI, the potential failure mode is a ½ inch (12.5 mm) hole throughout the
evaluation. Although smaller and larger hole sizes are possible, using a consistent
hole size that encompasses the vast majority of expected failures, ensures that theconsequences of failure are based on the process conditions and not arbitrary
variations in the hole size.
b. For ECSCC, the potential failure mode is a “weeping” leak through a fine network
of cracks. Global industry experience has shown that a hole as a potential failure
mode is not practical and, since stainless steel exhibits a high level of fracture
toughness, a collapse failure mode is extremely rare.
Version: 1.0 Date: January 2007 Custodian: DME/4 ECCN: EAR99 Page: 6 of 28
Printed _______________ Printed copies are uncontrolled
Printed copy should not be used more than 1 month after printed date
Mar 12, 2007
7/22/2019 DSM-1510002-SP-20_V1.0[1]
http://slidepdf.com/reader/full/dsm-1510002-sp-20v101 7/28
Downstream Manufacturing Restricted
DBAM Code and Name:
MAN.15.10 Provide Asset Availability – Ensure
Assessment and Mitigation Planning for
Corrosion Under Insulation andExternal Chloride Stress Corrosion Cracking
Document Number
DSM-1510002-SP-20 Equipment Integrity
2. With the equipment and piping list and the potential failure mode identified, an estimate
of the duration of a leak and the quantity that would be released shall be developed and
the consequence of such a potential failure estimated.
a. Health, Safety & Environmental and Financial consequences shall be determined
individually with the highest consequence level governing.
b. Personnel experienced in hazard evaluations should be consulted to validate the
assigned Health & Safety and Environmental consequences.
c. Where they exist, a similar unit in another Manufacturing location shall be
benchmarked to validate the consequences established with discrepancies resolved.
d. Personnel experienced in the assessment of operational and financial impacts should
provide input in to the Financial consequence determination.
i. Both equipment damage and lost production should be analysed.
ii. The cost of repairs should not be included in the analysis unless total equipment
replacement is determined to be the only feasible repair.
Note: For ECSCC, asset availability (economic consequences) most likely is the
governing scenario for most services due to the potential size of the leak (“weeping”
through a fine network of cracks). However, in some services, a weeping leak may result
in HSE consequences. Due to the latter situation, the potential HSE consequence of
leaks should also be determined.
2.8 Determining the Inspection Strategy
1. With the Probability Point Total and the consequence of a potential failure determined,
the inspection strategy shall be determined using Table 2, Strategy Matrix for CUI of
Carbon/Low Alloy Steel for CUI and Table 4, Strategy Matrix for ECSCC of AusteniticStainless Steel for ECSCC.
2. To determine the Inspection Strategy,
a. Determine the Probability (A, B, C, or D) from the Probability Point Total
determined in section 2.7.
b. Move across this row until it intersects with the column corresponding to the
consequence level determined in Section 2.7.
c. The box at the intersection indicates the Inspection Strategy.
3. See Appendix 3, Risk Assessment Example, for an example of how the consequence, the
probability and the inspection strategy were determined for a natural gas line.
Version: 1.0 Date: January 2007 Custodian: DME/4 ECCN: EAR99 Page: 7 of 28
Printed _______________ Printed copies are uncontrolled
Printed copy should not be used more than 1 month after printed date
Mar 12, 2007
7/22/2019 DSM-1510002-SP-20_V1.0[1]
http://slidepdf.com/reader/full/dsm-1510002-sp-20v101 8/28
Downstream Manufacturing Restricted
DBAM Code and Name:
MAN.15.10 Provide Asset Availability – Ensure
Assessment and Mitigation Planning for
Corrosion Under Insulation andExternal Chloride Stress Corrosion Cracking
Document Number
DSM-1510002-SP-20 Equipment Integrity
3. Mitigation Planning
3.1 Development
1. The mitigation plan should include a detailed, quarter-by-quarter schedule to mitigate the
risks identified during the assessment to As Low As Reasonably Practicable (ALARP)
and a cost estimate of sufficient quality to submit for T&R funding.
2. For CUI estimating, the following initial inspection coverages should be used:
a. IS-1 Delag 100% of susceptible areas followed by visual inspection & restoration
b. IS-2 Delag 50% of susceptible areas followed by a visual inspection & restoration
c. IS-3 Delag 50% of susceptible areas followed by a visual inspection & restoration
d. IS-4 No initial inspection. Reassessment interval to be assigned.
3. In the planning stages for CUI IS-1 inspection strategies, due to the number of
susceptible areas on a typical piece of equipment, the scaffolding necessary to access allthese areas, the potential consequences of a leak, the overall condition of the installation,
the insidious nature of CUI and the probability of finding deterioration that will cause the
inspection to be expanded, plan to entirely strip the equipment or piping for this strategy.
4. For ECSCC estimating, the initial inspection coverage for IS-1 thru IS-4 should be
assumed to be delagging of all susceptible areas and other accessible areas, visual and
eddy current inspection, followed by recoating and reinsulating. For IS-5, no initial
inspection is required as a reassessment interval will be assigned.
5. Inspection strategies are based on the risk of CUI or ECSCC resulting in the items that
have been ranked as IS-1 having a higher risk than items ranked IS-2, IS-2 higher than
IS-3, etc. Therefore, IS-1 ranked items should generally be planned to be completed
before IS-2 ranked items, IS-2 before IS-3.
6. The justification for mitigating financially driven impacts shall include a VIR analysis.
3.2 Additional Considerations
1. If removing lagging during unit operation could compromise process stability,
consideration should be given to delagging in smaller sections to allow progress to be
made without waiting until the next turnaround or outage.
2. As explained in Appendix 2, Technical Basis, areas particularly susceptible to water
ingress and/or water accumulation such as external stiffener rings or insulation support
rings have the highest inspection priority.
3. Consider equipment components and pipework inside of vessel skirts (not stacked vessel
skirts) and not operating below dew point as being inside buildings and not susceptible toCUI unless other problem conditions (steam tracing, etc.) exist.
4. Equipment with insulating paint should not be considered susceptible to CUI or ECSCC
unless excessive rust bloom or other conditions exist that indicate deterioration is
occurring.
Version: 1.0 Date: January 2007 Custodian: DME/4 ECCN: EAR99 Page: 8 of 28
Printed _______________ Printed copies are uncontrolled
Printed copy should not be used more than 1 month after printed date
Mar 12, 2007
7/22/2019 DSM-1510002-SP-20_V1.0[1]
http://slidepdf.com/reader/full/dsm-1510002-sp-20v101 9/28
Downstream Manufacturing Restricted
DBAM Code and Name:
MAN.15.10 Provide Asset Availability – Ensure
Assessment and Mitigation Planning for
Corrosion Under Insulation andExternal Chloride Stress Corrosion Cracking
Document Number
DSM-1510002-SP-20 Equipment Integrity
5. Equipment that uses personnel protection cages (as a replacement for insulation) is not
susceptible to CUI or ECSCC and therefore does not fall under the CUI/ECSCC
program.
6. Equipment that uses permanent removable insulation blankets is susceptible to CUI or
ECSCC and shall be included in the assessment.
7. Sites should consider inspecting and mitigating lower and higher ranked items together
where practical to increase efficiency and lower costs (e.g. RAM 4 and RAM 3
consequence piping laying side-by-side in a piperack).
8. Sites may elect to mitigate CUI and ECSCC risks unit-by-unit with the priority of the
units based on the type of hydrocarbon each unit processes (e.g. a unit processing
ethylene would have a higher priority than a unit processing residue).
a. This type of mitigation program is acceptable provided the first phase of mitigation
targets the highest risk items (IS-1s) across the site.
b. Mitigation of lower risk items (IS-2s, etc.) would then follow in the subsequent phases.
c. Mitigation of a lower risk item (e.g. an IS-2) during a higher risk phase of mitigation
should be by exception and only when significant benefit can be demonstrated (e.g.
significant cost savings, etc.).
Version: 1.0 Date: January 2007 Custodian: DME/4 ECCN: EAR99 Page: 9 of 28
Printed _______________ Printed copies are uncontrolled
Printed copy should not be used more than 1 month after printed date
Mar 12, 2007
7/22/2019 DSM-1510002-SP-20_V1.0[1]
http://slidepdf.com/reader/full/dsm-1510002-sp-20v101 10/28
Downstream Manufacturing
DBAM Code and Name: Assessment and Mitigation Planning for
MAN.15.10 Provide Asset Availability – EnsureEquipment Integrity
Corrosion Under Insulation andExternal Chloride Stress Corrosion Cracking
Version: 1.0 Date: January 2007 Custodian: DME/4
Figure 1 – Overview: Management of Corrosion Under Insulation for Carbon
Printed _______________ Printed copies are uncontrolled
Printed copy should not be used more than 1 month after printed date
Mar 12, 2007
7/22/2019 DSM-1510002-SP-20_V1.0[1]
http://slidepdf.com/reader/full/dsm-1510002-sp-20v101 11/28
Downstream Manufacturing
DBAM Code and Name: Assessment and Mitigation Planning for
MAN.15.10 Provide Asset Availability – EnsureEquipment Integrity
Corrosion Under Insulation andExternal Chloride Stress Corrosion Cracking
Version: 1.0 Date: January 2007 Custodian: DME/4
Figure 2 – Overview: Management of External Chloride Stress Corrosion Cracking for
Printed _______________ Printed copies are uncontrolled
Printed copy should not be used more than 1 month after printed date
Mar 12, 2007
7/22/2019 DSM-1510002-SP-20_V1.0[1]
http://slidepdf.com/reader/full/dsm-1510002-sp-20v101 12/28
Downstream Manufacturing Restricted
DBAM Code and Name:
MAN.15.10 Provide Asset Availability – Ensure
Assessment and Mitigation Planning for
Corrosion Under Insulation andExternal Chloride Stress Corrosion Cracking
Document Number
DSM-1510002-SP-20 Equipment Integrity
Figure 3 –Challenging the Need For Insulation – Part 1
Version: 1.0 Date: January 2007 Custodian: DME/4 ECCN: EAR99 Page: 12 of 28
Printed _______________ Printed copies are uncontrolled
Printed copy should not be used more than 1 month after printed date
Mar 12, 2007
7/22/2019 DSM-1510002-SP-20_V1.0[1]
http://slidepdf.com/reader/full/dsm-1510002-sp-20v101 13/28
Downstream Manufacturing Restricted
DBAM Code and Name:
MAN.15.10 Provide Asset Availability – Ensure
Assessment and Mitigation Planning for
Corrosion Under Insulation andExternal Chloride Stress Corrosion Cracking
Document Number
DSM-1510002-SP-20 Equipment Integrity
Figure 4 – Challenging the Need For Insulation – Part 2
Version: 1.0 Date: January 2007 Custodian: DME/4 ECCN: EAR99 Page: 13 of 28
Printed _______________ Printed copies are uncontrolled
Printed copy should not be used more than 1 month after printed date
Mar 12, 2007
7/22/2019 DSM-1510002-SP-20_V1.0[1]
http://slidepdf.com/reader/full/dsm-1510002-sp-20v101 14/28
Downstream Manufacturing Restricted
DBAM Code and Name:
MAN.15.10 Provide Asset Availability – Ensure
Assessment and Mitigation Planning for
Corrosion Under Insulation andExternal Chloride Stress Corrosion Cracking
Document Number
DSM-1510002-SP-20 Equipment Integrity
Table 1 – Probability Assessment for CUI of Carbon/Low Alloy Steel
Operating
Temperature
Coating Status
when new orlast applied
Cladding/
InsulationCondition
Insulation type Heat
tracing
External environment Points
Constantly
<−5°C or >175°C
<25ºF or >350ºF
REMOVE FROMCUI PROGRAM
Full QA coating
≤ 8 years sinceapplication
or
TSA < 15 years
Good toEngineeringStandards ornew/renewed(<5 years in
age)
Regularinspection andmaintenance
(every 5 years)
Not present Inside building, notsteam traced and not
sweatingREMOVE FROM CUI
PROGRAM
0
150ºC - 175°C
300ºF - 350ºF
Full QA coating8-15 years in
age orconventional
coating ≤ 8years sinceapplication
orTSA 15-30 years
Averagecondition,
overall highintegrity design& construction,tight inspection
ports
ExpandedPerlite,
Foamglass,Closed-Cell
Foam
Highintegritydesign
(steam) orelectrical
Arid or in-land
<500mm/yr [<20”/yr]rain
Low wetting rate(<20% of the time)
1
−5ºC - 49°C26ºF - 119ºF
OR111ºC - 149°C
226ºF - 299ºF
Conventionalcoating 8-15years in age
Averagecondition,
conventionaldesign andconstruction
Fibreglass, Asbestos,
Regular Perlite,Mineral/Rock
Wool (<10ppmCl)
Mediumintegritydesign(steam)
Moderate climate
500-1000mm/yr rain
[20-40”/yr] rainMedium wetting rate
(20 - 50% of the time)
3
50°C - 110°C120ºF - 225ºF
orcycling/sweating
conditions
Full QA orconventional
coating:> 15 years in
ageor
TSA > 30 yearsor
unpainted orunknown
Poor condition,damaged/wet/broken
seals
Cal Sil,Rockwool (no
spec),unknown
Lowintegrity
design orleaking(steam)
Coastal & marine
>1000mm/yr [>40”/yr]rain
High wetting rate(>50% of the time)
(e.g. coolingtower/deluge systems)
5
Notes:
(a) This probability table applies to equipment operating outdoors and in the temperature range of -5°C to 175°C [25°F to
350°F].
(b) Dead legs on equipment or piping operating outside of the CUI range must also be considered, as they will likely
operate in the CUI range at some location. For example, a long dead leg on a 230 °C [450°F] line could easily be in
the
50 – 110 °C [120°F - 225°F] metal temperature range for high probability of CUI.
(c) In case of cyclic service (or regular temperature changes), the range corresponding to the most critical temperature
reached shall be taken.
Version: 1.0 Date: January 2007 Custodian: DME/4 ECCN: EAR99 Page: 14 of 28
Printed _______________ Printed copies are uncontrolled
Printed copy should not be used more than 1 month after printed date
Mar 12, 2007
7/22/2019 DSM-1510002-SP-20_V1.0[1]
http://slidepdf.com/reader/full/dsm-1510002-sp-20v101 15/28
Downstream Manufacturing Restricted
DBAM Code and Name:
MAN.15.10 Provide Asset Availability – Ensure
Assessment and Mitigation Planning for
Corrosion Under Insulation andExternal Chloride Stress Corrosion Cracking
Document Number
DSM-1510002-SP-20 Equipment Integrity
Table 2 –Strategy Matrix for CUI of Carbon/Low Alloy Steel
Probability
Point Total
Inspection Strategy (IS)
D (> 20) IS-4 IS-3 IS-2 IS-1 IS-1
C (17 – 20) IS-4 IS-4 IS-3 IS-2 IS-1
B (11 - 16) IS-4 IS-4 IS-4 IS-3 IS-2
P r o b a b i l i t y
A (1 - 10) IS-4 IS-4 IS-4 IS-4 IS-3
Priority 1 2 3 4 5
Asset Damage &ConsequentialBusiness Loss
No/Slightdamage
<10k USDNo Disruption to
Operation
Minor damage10k -100k USD
Brief Disruption toOperation
Moderatedamage
100k -1M USDPartial Shutdown
Major damage 1M -10M USD
Up to two weeksshutdown
Massive damage>10M USD
Substantial ortotal loss ofoperation
Harm to People No/Slight injuryor health effect
Not affecting workperformance or
daily life activities.(First Aid caseand medical
treatment case.Exposure to
health hazardsthat give rise to
noticeablediscomfort, minor
irritation ortransient effectsreversible after
exposure stops.)
Minor injury orhealth effect
Affecting workperformance,
such as restrictionto work activities
or need to take upto 5 days to fully
recover.(Restricted or lost
workday casesresulting in up to5 calendar daysaway from work.Illness such asskin irritation.)
Major injury orhealth effect
Affecting workperformance inthe longer term,such as absence
from work formore than 5 days,affecting daily lifeactivities for more
than 5 days orirreversible
damage to health.(Long-termdisabilities.
Illnesses such assensitisation.)
Permanent totaldisability or up
to three fatalities (Illnesses such ascorrosive burns or
cancer.)
More than 3fatalities
(Cancer to a largeexposed
population. Majorfire or explosionresulting in morethan 3 fatalities.)
C o n s e q u e n c e o f F a i l u r e f o r
I n d i v i d u a l E q
u i p m e n t a n d P i p i n g
Environmental
Effect
No/Slight Effect
Slightenvironmental
damagecontained with thepremises. (Smallspill in process
area or tank farmarea that readily
evaporates.)
Minor Effect
Minorenvironmentaldamage but nolasting effect.
(Small spill off-sitethat seeps in theground. On-site
groundwatercontamination.
Complaints fromup to 10
individuals. Singleexceedance of
statutory or otherprescribed limit.)
Moderate Effect
Limitedenvironmental
damage that willpersist or requirecleaning up. (Spill
from a pipelinerequiring removaland disposal of alarge quantity of
sand/soil.Observed off-site
effects ordamage. Off-site
groundwatercontamination.)
Major Effect
Severeenvironmental
damage that willrequire extensive
measures torestore beneficial
uses of theenvironment. (Oilspill at a jetty thatends up on local
beaches requiringclean-up. Off-site
groundwatercontamination
over an extensivearea. Extendedexceedances of
statutory or otherprescribed limits
with potentiallong-term effects.)
Massive Effect
Persistent severeenvironmental
damage that willlead to loss ofcommercial,
recreational useof loss of naturalresources over awide area. (Crude
oil spillageresulting in
pollution of a largepart of a riverestuary and
extensive clean-up and
remediationmeasures.)
Version: 1.0 Date: January 2007 Custodian: DME/4 ECCN: EAR99 Page: 15 of 28
Printed _______________ Printed copies are uncontrolled
Printed copy should not be used more than 1 month after printed date
Mar 12, 2007
7/22/2019 DSM-1510002-SP-20_V1.0[1]
http://slidepdf.com/reader/full/dsm-1510002-sp-20v101 16/28
Downstream Manufacturing Restricted
DBAM Code and Name:
MAN.15.10 Provide Asset Availability – Ensure
Assessment and Mitigation Planning for
Corrosion Under Insulation andExternal Chloride Stress Corrosion Cracking
Document Number
DSM-1510002-SP-20 Equipment Integrity
Table 3 – Probability Assessment for ECSCC of Austenitic Stainless Steel
Operating
Temperature
Shop coating
or Al-wrapStatus & Age
Cladding/
InsulationCondition
Insulation type Heat tracing External
environment
Points
Constantly>175°C or <50°C
>350°F or <120°F
REMOVE FROMECSCC
PROGRAM
Shop Coating(full QA) < 8
yrsOr
Al-wrap*< 15 years
Good toEngineeringStandards
(undamaged)
RegularInspection/
Maintenanceevery 5-years
Regularinspection andMaintenance
(every 5 years)
Not present Inside building,not steam tracedand not sweatingREMOVE FROM
ECSCCPROGRAM
0
Shop coating(full QA) 8 -
15 yrsOr
Maintenance
Coating <8yrsOr
Al-wrap* 15-20 yrs
Averagecondition, butwith specialprecautions
taken at
susceptibleareas (c)
ExpandedPerlite,
Foamglass,Closed-Cell
Foam
High integritydesign
(steam) orelectrical (Cl-
free
insulation)
Arid or in-land
<500mm/yr[<20”/yr] rain
Low wetting rate
(< 20 % of thetime)
1
Shop coating> 12 yrs
OrMaintenancecoating > 8
yrsOr
Al-wrap* > 20yrs
Averagecondition, no
specialprecautions
taken atsusceptibleareas (c)
Fibreglass, Asbestos,
Regular Perlite,Mineral/Rock
Wool(low Chlorides
<10ppm)
Mediumintegritydesign(steam)
Moderateclimate
500-1000mm/yrrain
[20-40”/yr] rainMedium wetting
rate(20 – 50 % of the
time)
3
50 - 175 °C
120 - 350°For cycling/sweating
conditions (b)
Shop coating> 15 yrs
OrMaintenancecoating > 12
yrsOr
unknown
Poor condition,severely
damaged, wetOr
unknown
Mineral/RockWool
(no Chloridesspec),Cal Sil
Lowintegrity
design orleaking
(steam) orelectrical
(PVCinsulation)
Coastal &marine
>1000mm/yr[>40”/yr] rain
High wetting rate(> 50 % of the
time) or exposedto cooling
tower/delugesystems
5
Notes:
(a) Dead legs should be treated same as main pipe, except that temperature should be estimated, since the dead leg will
be much cooler, especially if long. For example, a dead leg on a 230°C (450°F) line could easily be in the 50-175°C
(120-350°F) metal temperature range for high probability.
(b) In case of cyclic service (or temporarily temperature changes), the range corresponding to the most critical
temperature reached shall be taken.
Version: 1.0 Date: January 2007 Custodian: DME/4 ECCN: EAR99 Page: 16 of 28
Printed _______________ Printed copies are uncontrolled
Printed copy should not be used more than 1 month after printed date
Mar 12, 2007
7/22/2019 DSM-1510002-SP-20_V1.0[1]
http://slidepdf.com/reader/full/dsm-1510002-sp-20v101 17/28
Downstream Manufacturing Restricted
DBAM Code and Name:
MAN.15.10 Provide Asset Availability – Ensure
Assessment and Mitigation Planning for
Corrosion Under Insulation andExternal Chloride Stress Corrosion Cracking
Document Number
DSM-1510002-SP-20 Equipment Integrity
Table 4 –Strategy Matrix for ECSCC of Austenitic Stainless Steel
Probability
Point Total
Inspection Strategy (IS)
D > 20 IS-5 IS-4 IS-3 IS-2 IS-1
C (15 - 19) IS-5 IS-5 IS-4 IS-3 IS-2
B (10 - 14) IS-5 IS-5 IS-5 IS-4 IS-3
P r o b a b i l i t y
A (< 10) IS-5 IS-5 IS-5 IS-5 IS-4
Priority 1 2 3 4 5
Asset Damage &ConsequentialBusiness Loss
No/Slightdamage
<10k USDNo Disruption to
Operation
Minor damage10k -100k USD
Brief Disruption toOperation
Moderate
damage100k -1M USD
Partial Shutdown
Major damage 1M -10M USD
Up to two weeksshutdown
Massive damage>10M USD
Substantial ortotal loss ofoperation
Harm to People No/Slight injuryor health effect
Not affecting workperformance or
daily life activities.(First Aid caseand medical
treatment case.Exposure to
health hazardsthat give rise to
noticeablediscomfort, minor
irritation ortransient effectsreversible after
exposure stops.)
Minor injury orhealth effect
Affecting workperformance,
such as restrictionto work activities
or need to take upto 5 days to fully
recover.(Restricted or lost
workday casesresulting in up to 5
calendar daysaway from work.Illness such asskin irritation.)
Major injury orhealth effect
Affecting workperformance inthe longer term,such as absence
from work formore than 5 days,affecting daily lifeactivities for more
than 5 days orirreversible
damage to health.(Long-termdisabilities.
Illnesses such assensitisation.)
Permanent totaldisability or up
to three fatalities (Illnesses such ascorrosive burns or
cancer.)
More than 3fatalities
(Cancer to a largeexposed
population. Majorfire or explosionresulting in morethan 3 fatalities.)
C o n s e q u e n c e o f F a i l u r e f o r
I n d i v i d u a l E q
u i p m e n t a n d P i p i n g
Environmental
Effect
No/Slight Effect
Slightenvironmental
damagecontained with thepremises. (Smallspill in process
area or tank farmarea that readily
evaporates.)
Minor Effect
Minorenvironmentaldamage but nolasting effect.
(Small spill off-sitethat seeps in theground. On-site
groundwatercontamination.
Complaints fromup to 10
individuals. Singleexceedance of
statutory or otherprescribed limit.)
Moderate Effect
Limitedenvironmental
damage that willpersist or requirecleaning up. (Spill
from a pipelinerequiring removaland disposal of alarge quantity of
sand/soil.Observed off-site
effects ordamage. Off-site
groundwatercontamination.)
Major Effect
Severeenvironmental
damage that willrequire extensive
measures torestore beneficial
uses of theenvironment. (Oilspill at a jetty thatends up on local
beaches requiringclean-up. Off-site
groundwatercontamination
over an extensivearea. Extendedexceedances of
statutory or otherprescribed limits
with potentiallong-term effects.)
Massive Effect
Persistent severeenvironmental
damage that willlead to loss ofcommercial,
recreational useof loss of naturalresources over awide area. (Crude
oil spillageresulting in
pollution of a largepart of a riverestuary and
extensive clean-up and
remediationmeasures.)
Version: 1.0 Date: January 2007 Custodian: DME/4 ECCN: EAR99 Page: 17 of 28
Printed _______________ Printed copies are uncontrolled
Printed copy should not be used more than 1 month after printed date
Mar 12, 2007
7/22/2019 DSM-1510002-SP-20_V1.0[1]
http://slidepdf.com/reader/full/dsm-1510002-sp-20v101 18/28
Downstream Manufacturing Restricted
DBAM Code and Name:
MAN.15.10 Provide Asset Availability – Ensure
Assessment and Mitigation Planning for
Corrosion Under Insulation andExternal Chloride Stress Corrosion Cracking
Document Number
DSM-1510002-SP-20 Equipment Integrity
Appendix 1 – Example Insulation System Checklist
Insulation Condition Checklist
Tick box if applicable
⇒ Caulking/sealant that has hardened and separated
⇒ Circumferential cracks in jacketing
⇒ Corrosion of cladding
⇒ Damaged or loose cladding
⇒ Damaged vapour barrier/stop
⇒ Failure at bends (open joints)
⇒ Foot traffic damage
⇒ Gaps due to uncontrolled expansion contraction
⇒ Hot/Cold spots
⇒ Icing and/or condensation
⇒ Longitudinal cracks in jacketing
⇒ Missing insulation (not re-installed after shutdowns orinspections)
⇒ Missing insulation at flanges/valve boxes
⇒ Missing self tapers, rivets or SS bands
⇒ Rust stains and bulges in metal cladding
⇒ Sagged insulation and cladding
⇒ No termination at flanges/valves
⇒ No termination in a vertical pipe or piece of equipment
⇒ Water increase at penetrations (e.g. nozzles)
Version: 1.0 Date: January 2007 Custodian: DME/4 ECCN: EAR99 Page: 18 of 28
Printed _______________ Printed copies are uncontrolled
Printed copy should not be used more than 1 month after printed date
Mar 12, 2007
7/22/2019 DSM-1510002-SP-20_V1.0[1]
http://slidepdf.com/reader/full/dsm-1510002-sp-20v101 19/28
Downstream Manufacturing Restricted
DBAM Code and Name:
MAN.15.10 Provide Asset Availability – Ensure
Assessment and Mitigation Planning for
Corrosion Under Insulation andExternal Chloride Stress Corrosion Cracking
Document Number
DSM-1510002-SP-20 Equipment Integrity
Appendix 2 – Technical Basis
1. Overview
1. Degradation of equipment and associated CUI typically occurs at a rate that depends on various
factors, including temperature, time, insulation type, coating type, equipment configuration, and
the presence of water. These factors are described in the sections below.
2. To aid in an understanding of the life cycle of CUI, a typical CUI degradation progression is as
follows:
Age Equipment and/or Barrier Condition
0 years New equipment properly coated, insulated and installed.Equipment operates continuously at 80°C (175 °F).
2 to 5 years No maintenance has been performed on the insulation system.Caulking has failed, Insulation is wet and water hasaccumulated in water traps and low areas.
6 to 8 years Coating system begins to fail, especially in water traps and lowareas.
8 to 10 years Coating system has failed nearly completely and CUI hasstarted.
Approximately15 years
Significant CUI has occurred with CUI rates averaging 0.125 –0.250 mm/yr (5 – 10 mpy) and as high as 0.50 mm/yr (20 mpy)in severe cases. Leaks have begun to appear.
Approximately20 years
Through-wall failures not uncommon at this point andsusceptible equipment has experienced significant degradation.
3. Degradation of equipment caused by ECSCC is non-trendable degradation mechanism andtherefore very unpredictable. The occurrence of ECSCC is caused by the presence of water,
chlorides and a temperature above 50°C (120°F). The influence of Material stresses also play a
role. These factors are described in the sections below.
Version: 1.0 Date: January 2007 Custodian: DME/4 ECCN: EAR99 Page: 19 of 28
Printed _______________ Printed copies are uncontrolled
Printed copy should not be used more than 1 month after printed date
Mar 12, 2007
7/22/2019 DSM-1510002-SP-20_V1.0[1]
http://slidepdf.com/reader/full/dsm-1510002-sp-20v101 20/28
Downstream Manufacturing Restricted
DBAM Code and Name:
MAN.15.10 Provide Asset Availability – Ensure
Assessment and Mitigation Planning for
Corrosion Under Insulation andExternal Chloride Stress Corrosion Cracking
Document Number
DSM-1510002-SP-20 Equipment Integrity
4. To aid in an understanding of the life cycle of ECSCC, a typical ECSCC degradation progression
is as follows:
Age Equipment and/or Barrier Condition0 years New equipment properly coated, insulated, and installed. Equipment
operates continuously at 80 °C (175 °F).
2 to 5 years No maintenance has been performed on the insulation system.Caulking has failed, insulation is wet, water has accumulated in watertraps and low areas.
6 to 8 years Coating system has begun to fail. Chloride build-up due toevaporation/condensation cycling in water retaining parts.
8 to 10 years Probability of ECSCC increases with age.
More than 15years
Industry experience indicates that through-wall failures caused byECSCC (leaks) occurs on the average of between 15 to 35 years.
2. Material Susceptibility
1. CUI can occur in carbon steel, low nickel steel, and low alloys up to and including 9-chrome
alloys.
a. Chrome alloys are typically used for their strength at elevated temperatures and thus outside
the susceptible temperature range but in the case of retrofits, reuse, or idling of equipment,
these alloys can be found operating in the CUI temperature range.
b. The primary consideration for material susceptibility is the operating temperature.
c. Alloy materials should not be taken out of the CUI program without consulting a corrosion
engineer.
2. ECSCC can occur in austenitic stainless steels, typically 304(L), 316(L), 321, 347 and associated
weldments.
a. Duplex stainless steels are highly resistant, although not immune, to ECSCC. Duplex stainless
steels are of the type 22Cr-5Ni (or higher alloyed), such as UNS S31803 (tradename SAF
2205) or UNS S32550 (tradename Ferralium 255).
b. Alloys containing more than 32% Nickel are not susceptible to ECSCC (e.g., Alloy-825).
3. Water
1. CUI for carbon steel and low-alloy steel under insulation occurs when water or water vapour
penetrates under the insulation and remains in contact with steel that does not have a protective
coating or that has a failed protective coating, in the susceptible temperature range.
2. CUI for carbon steel and low-alloy steel under insulation also occurs when the equipment sweats,even when there is no degradation of the insulation. Equipment sweating is caused by
temperature cycling above and below the ambient temperature or by operation below the
atmospheric dew point
3. Preventing water from reaching the steel is the key to preventing CUI.
Version: 1.0 Date: January 2007 Custodian: DME/4 ECCN: EAR99 Page: 20 of 28
Printed _______________ Printed copies are uncontrolled
Printed copy should not be used more than 1 month after printed date
Mar 12, 2007
7/22/2019 DSM-1510002-SP-20_V1.0[1]
http://slidepdf.com/reader/full/dsm-1510002-sp-20v101 21/28
Downstream Manufacturing Restricted
DBAM Code and Name:
MAN.15.10 Provide Asset Availability – Ensure
Assessment and Mitigation Planning for
Corrosion Under Insulation andExternal Chloride Stress Corrosion Cracking
Document Number
DSM-1510002-SP-20 Equipment Integrity
4. Areas with a higher exposure to wet conditions have a higher likelihood of water intrusion and
subsequent CUI. High exposure conditions include the following:
a. Mist from cooling water towers, steam vents, and process vents. b. Unattended steam and/or condensate and/or cooling water leaks.
c. Periodically tested deluge systems.
d. Coastal/marine areas.
4. Water and Chlorides
1 External chloride stress corrosion cracking of stainless steel under insulation occurs when water
or water vapour and chlorides penetrates under the insulation and remains in contact with stainless
steel in the susceptible temperature range that does not have a protective barrier or that has a
failed protective barrier.
2. ECSCC also occurs when the equipment sweats due to temperature cycling within the susceptible
temperature range.
3. Preventing water from reaching the steel surface is the key to preventing ECSCC.
4. Areas with a higher exposure to wet conditions have a higher likelihood of water intrusion and
subsequent ECSCC. High exposure conditions include the following:
a. Mist from cooling water towers, steam vents and process vents.
b. Unattended steam and/or condensate and/or cooling water leaks.
c. Periodically tested deluge systems.
d. Coastal/Marine Areas.
5. Source of water is typically mist, rain, deluge systems, malfunctioning steam traps, and leakingtracing. Rain in coastal areas typically contains more chlorides than rain in non-coastal areas.
6. Source of chlorides is typically water. An additional source for chlorides is insulation material,
PVC insulation of heat tracing, and vapours from neighbouring plants.
5. Corrosion Rate
1. Rate of CUI of carbon steel is directly correlated to equipment surface temperature and the
amount of water present.
2 Rate of CUI tends to be higher in areas where there is a cyclic wet/dry interface
(detachment/spalling of corrosion scale).
3. Rate of ECSCC is a non-trendable degradation mechanism and therefore very unpredictable.
6. Insulation Type
1. Insulation that absorbs and retains water has a higher likelihood of creating an environment that
promotes CUI or ECSCC.
Version: 1.0 Date: January 2007 Custodian: DME/4 ECCN: EAR99 Page: 21 of 28
Printed _______________ Printed copies are uncontrolled
Printed copy should not be used more than 1 month after printed date
Mar 12, 2007
7/22/2019 DSM-1510002-SP-20_V1.0[1]
http://slidepdf.com/reader/full/dsm-1510002-sp-20v101 22/28
Downstream Manufacturing Restricted
DBAM Code and Name:
MAN.15.10 Provide Asset Availability – Ensure
Assessment and Mitigation Planning for
Corrosion Under Insulation andExternal Chloride Stress Corrosion Cracking
Document Number
DSM-1510002-SP-20 Equipment Integrity
a. Mineral wool, fibreglass, and calcium silicate have the highest tendency to absorb water (and
chlorides).
b. Insulation with a closed cell structure, such as perlite and foam glass, has the lowest tendencyto absorb water (and chlorides)
2. Contact free insulation systems prevent accumulation of water and chlorides on the steel surface
and thereby reducing and significantly reduce the probability of developing both CUI and
ECSCC.
3. Insulating paint is sometimes used in lieu of conventional insulation. Equipment protected by
insulating paint is not considered to be susceptible to CUI or ECSCC.
7. Temperature
1. CUI susceptibility temperature range depends on the actual temperature of the process within the
piping or equipment. Experience shows that CUI can occur at a process temperature range from
-5 to175°C (+20 to350°F), and ECSCC at a process temperature range from 50 to 175°C (120 to
350°F).
2. With a well-maintained insulation system, external surface temperatures could typically be 10 to
15°C (20 to 30°F) closer to ambient air temperature than the process temperature. This
temperature difference can be much greater with significant insulation damage.
3. Surface temperature impacts the CUI corrosion rates. The highest CUI rates occur at a 50 to
110°C (120 to 230°F) temperature range.
a. In severe cases, CUI rates up to 1 mm/yr (40 mpy) have occurred at this temperature range,
although rates are typically on the order of 0.25 to 0.50 mm/yr (10 to 20 mpy).
b. Outside of this temperature range, rates typically decrease to 0.05 to 0.25 mm/yr (2 to 10
mpy/yr).
4. Rate of ECSCC is a non-trendable degradation mechanism and therefore crack initiation and
propagation rates are unpredictable. In practice, leakage has occurred within hours up to years.
5. Temperature cycles that include all or a portion of the CUI/ECSCC range tend to increase the
likelihood of CUI/ECSCC.
6. Breaches and damage points in the insulation can result in surface temperatures much lower than
the process temperature. These points can be at higher risk than the remainder of the system.
7. Although it can be argued that there is a correlation between temperature and probability of
ECSCC, in practice this is seldom the case.
8. All equipment spends some time at ambient temperature. Frequency and length of shutdowns
increases the probability of CUI.
9. Items such as deadlegs and vessel skirts, can operate at a much lower temperature and act as
cooling fins. These items are susceptible to CUI, even when the primary equipment temperature
is above 175°C (350°F).
Version: 1.0 Date: January 2007 Custodian: DME/4 ECCN: EAR99 Page: 22 of 28
Printed _______________ Printed copies are uncontrolled
Printed copy should not be used more than 1 month after printed date
Mar 12, 2007
7/22/2019 DSM-1510002-SP-20_V1.0[1]
http://slidepdf.com/reader/full/dsm-1510002-sp-20v101 23/28
Downstream Manufacturing Restricted
DBAM Code and Name:
MAN.15.10 Provide Asset Availability – Ensure
Assessment and Mitigation Planning for
Corrosion Under Insulation andExternal Chloride Stress Corrosion Cracking
Document Number
DSM-1510002-SP-20 Equipment Integrity
8. Coatings
8.1 General
Neither CUI nor ECSCC will occur if the protective coating has not failed or been damaged
unless a porous coating has been applied, which has occurred with silicone-based coatings on
stainless steel.
8.2 Carbon Steel
1. Coatings have a finite life and should be renewed if piping and equipment is to be
adequately protected from CUI.
2 Inorganic zinc coatings without a top coating are prone to rapid failure in the presence of
water.
3. Provided the coating was applied per the manufacturer recommendations (surface preparation, anchor profile, cure, etc.), the normal life expectancy of various common
coatings before breakdown commences is typically as follows:
ClimateCoating System
Coastal/Marine Temperate
Red Lead + Topcoat 8 yr 10 yr
Inorganic Zinc + Topcoat 8 yr 10 yr
Inorganic Zinc Only Less than 5 yr 8 yr
Immersion Service Coating 10 yr 15 yr
4. For carbon/low alloy steel, a TSA coating offers superior protection from CUI, if well
applied.
8.3 Stainless Steel
1. Aluminium foil wrapping is very effective for protection of stainless steel from ECSCC
when properly installed (applied with overlaps, in a manner that sheds water, etc.).
Aluminium wrapping is a cost effective and the preferred alternative for coating of
stainless steel.
a. Aluminium wrapping has been used in the process industry for over 20 years.
b. Aluminium wrapping can be applied online or offline.
c. Aluminium wrapping can be easily moulded around fittings and flanges.
d. Aluminium wrapping protects the stainless steel as a water/dirt barrier and protectsthe stainless steel by cathodic protection.
e. Although lifetime of aluminium wrapping is well over 20 years, its effectiveness will
also be affected by mechanical damage. It is therefore good practice to replace the
aluminium wrapping when equipment modification or maintenance occurs.
2. Organic coatings are appropriate for stainless steels provided good quality assurance and
control systems are in place.
Version: 1.0 Date: January 2007 Custodian: DME/4 ECCN: EAR99 Page: 23 of 28
Printed _______________ Printed copies are uncontrolled
Printed copy should not be used more than 1 month after printed date
Mar 12, 2007
7/22/2019 DSM-1510002-SP-20_V1.0[1]
http://slidepdf.com/reader/full/dsm-1510002-sp-20v101 24/28
Downstream Manufacturing Restricted
DBAM Code and Name:
MAN.15.10 Provide Asset Availability – Ensure
Assessment and Mitigation Planning for
Corrosion Under Insulation andExternal Chloride Stress Corrosion Cracking
Document Number
DSM-1510002-SP-20 Equipment Integrity
a. Life cycle costs of organic coatings should be evaluated because the use of
aluminium wrapping is almost always more cost effective and provides better
protection against ECSCC.
b. Organic coatings should be used only in areas in which aluminium wrapping is not
practical.
9. Heat Tracing
1. From the viewpoint of ECSCC, it is preferable to use electric heat tracing (in combination with
chloride free electrical insulation) in lieu of steam tracing, but in reality the majority of systems in
use will remain steam traced.
2. PVC electrical insulation of electrical heat tracing can be a source of chlorides.
3. Steam tracing failure inside the insulation defeats all CUI barriers because it introduces moisture,
strips away coatings and provides a temperature range where CUI and ECSCC are very
aggressive.
4. Steam tracing tubing is typically made of carbon steel, copper, stainless steel, or nickel alloy
(Incoloy) tubing.
a. Incoloy is expensive, but has a lower probability of in-service failure and may be justified on
the highest criticality systems.
b. Incoloy 825 has been justified and is now the standard for instrument systems on many sites.
c Stainless steel tubing is vulnerable to chloride stress corrosion cracking at similar conditions to
CUI and is unlikely to offer superior life in comparison to carbon steel tubing.
d. Copper ions make stainless steel more susceptible to pitting corrosion and an alternate material
is to be selected when steam tracing stainless steels.
5. The main leak point for steam tracing is around coupling joints. Locate these joints outside of the
insulation system.
6. The probability assessment used in this SP accounts for the fact that steam tracing increases the
probability of CUI/ECSCC.
7. As this can only be a general guide, local knowledge should be applied based on the condition of
the tracing network in general.
8. The probability score depends on the level of integrity of the steam tracing system, which depends
on the following features:
a. Tubing made of the proper material
b. Tubing installed using the highest level of quality control (adequate spacers, couplings outside
insulations)
c. Careful quality assurance verification has been performed after installation
9. High Integrity Design means that all the three features are satisfied. Medium Integrity Design
means that only two out of the three features are satisfied. Low Integrity Design means that no
features are satisfied.
Version: 1.0 Date: January 2007 Custodian: DME/4 ECCN: EAR99 Page: 24 of 28
Printed _______________ Printed copies are uncontrolled
Printed copy should not be used more than 1 month after printed date
Mar 12, 2007
7/22/2019 DSM-1510002-SP-20_V1.0[1]
http://slidepdf.com/reader/full/dsm-1510002-sp-20v101 25/28
Downstream Manufacturing Restricted
DBAM Code and Name:
MAN.15.10 Provide Asset Availability – Ensure
Assessment and Mitigation Planning for
Corrosion Under Insulation andExternal Chloride Stress Corrosion Cracking
Document Number
DSM-1510002-SP-20 Equipment Integrity
10. If extensive delagging is planned for a system incurring significant costs for insulation and
scaffolding, consideration should be given to renewing the associated tracing with couplings and
joints relocated outside of the insulation or replacement with an electrical heat tracing.
10. External Environment
In the probability assessment tables, reference is made to external environment with respect to rain and
wet industrial conditions. However, local conditions may vary and dictate a more or less severe
approach. For example:
1. A site in a temperate region [800 mm/yr (31.5 in/yr) rainfall], but at 60 km (37 mi) from the coast
with main wind direction from sea may classify as a coastal marine area.
2. A site in coastal area in an arid region with wind direction from the land side may classify as an
arid area.
11. Susceptible Areas
1. Protrusions extending through the insulation sheathing, even those properly caulked, will
eventually provide a means of water intrusion as caulking may start to dry out in a couple of years
and is seldom, if ever, renewed.
2. Examples of protrusions where water intrusion can occur include the following:
a. Stiffener rings
b. Insulation support rings
c. Skirt fireproofing “rain hat”
d. Brackets (platform, ladder, pipe, etc.)
e. Lifting lugs
f. Deadlegs (vents, drains, by-pass lines, level-leg-assemblies, etc.)
g. Small bore piping
h. Pipe hangers, supports and shoes
i. Valves, fittings, etc. with irregular insulation surfaces
j. Steam tracer-tubing penetrations
3. Other areas where water intrusion can occur include the following:
a. Terminations of personnel protection and other insulation systems, especially on vertical
surfaces
b. Steam tracing tubing junctions
c. Holes for inspection (i.e., condition monitoring locations)
d. Insulation junctions (cast to blanket, etc.)
e. Insulated flanges
f. Damaged or missing jacketing
Version: 1.0 Date: January 2007 Custodian: DME/4 ECCN: EAR99 Page: 25 of 28
Printed _______________ Printed copies are uncontrolled
Printed copy should not be used more than 1 month after printed date
Mar 12, 2007
7/22/2019 DSM-1510002-SP-20_V1.0[1]
http://slidepdf.com/reader/full/dsm-1510002-sp-20v101 26/28
Downstream Manufacturing Restricted
DBAM Code and Name:
MAN.15.10 Provide Asset Availability – Ensure
Assessment and Mitigation Planning for
Corrosion Under Insulation andExternal Chloride Stress Corrosion Cracking
Document Number
DSM-1510002-SP-20 Equipment Integrity
g. Improperly installed jacketing (improperly lapped, seams on top, etc.)
h. Sheathing seams (improper lap, hard/missing caulk, etc)
i. Cracked fireproofing on skirts (corrosion occurs primarily at both the base ring and near theskirt-to-vessel juncture weld)
j. Coat and wrap piping protection systems.
4. After intrusion, water saturates the insulation and accumulates at low points and other natural
collection areas. Examples include:
a. Insulation support rings
b. Stiffener rings
c. Lifting lugs
d. Sagging areas of piping and other low points
5. Accumulation of water can occur at a long distance from the point of intrusion, especially inservices where the surface temperature does not cause the water to evaporate. For example, on a
horizontal line in the middle of a span between pipe supports, where the insulation is missing at
the supports. Evaporated water can also travel through the insulated system and condense in
areas with a lower surface temperature.
6. For ECSCC, consider crevice corrosion sites (lap joints, crevices, etc.) in the evaluation.
7. Despite a thorough understanding of potentially susceptible areas, CUI remains difficult to
predict. Therefore the inspection approach shall include removal of an ample area (proportional
to the item being inspected) of insulation around the susceptible area to enable a thorough
assessment to be performed.
Version: 1.0 Date: January 2007 Custodian: DME/4 ECCN: EAR99 Page: 26 of 28
Printed _______________ Printed copies are uncontrolled
Printed copy should not be used more than 1 month after printed date
Mar 12, 2007
7/22/2019 DSM-1510002-SP-20_V1.0[1]
http://slidepdf.com/reader/full/dsm-1510002-sp-20v101 27/28
Downstream Manufacturing Restricted
DBAM Code and Name:
MAN.15.10 Provide Asset Availability – Ensure
Assessment and Mitigation Planning for
Corrosion Under Insulation andExternal Chloride Stress Corrosion Cracking
Document Number
DSM-1510002-SP-20 Equipment Integrity
Appendix 3 – Risk Assessment Example
1. Determining Consequence of a CUI failure
1. Assume the following piping system is being evaluated:
a. Natural Gas (API-570 Class 2) at 3.1 bar (45 psig) in a remote on-site location.
b. The Environmental Department estimates a leak would potentially result in several (<10)
odour complaints with no impact outside the fence.
c. Potential personal safety consequence is a first-aid incident.
d. The financial impact is less than 10,000 USD in equipment damage and repair cost and 2-day
outage of a single process unit worth 30,000 USD per day.
2. Using the Strategy Matrix (Table 2) to determine the consequence:a. Asset Damage & Consequential Business Loss – Move across to the box that reads “10 to
100k USD, brief disruption to operation”, corresponding to a consequence rating of 2.
b. Harm to People – Move across to the box that reads “No/Slight Injury”, corresponding to a
consequence rating of 1.
c. Environmental Effect – Move across to the box that reads “Minor Effect”, corresponding to a
consequence rating of 2.
3. Since the highest consequence rating was two (for both Asset Damage and Environmental Effect),
the overall consequence for this piping system is 2.
2. Determining Probability of a CUI Failure
1. Following is additional data on the fuel gas line:
a. Operating temperature: 135°C (275°F)
b. Coating information: Unpainted
c. Insulation type: Calcium silicate
d. Cladding/Insulation Condition: Average (Conventional Design)
e. Heat tracing: None
f. Environment: Located near the coast
2. Similar to the finding the consequence, follow the columns down on the probability assessment
table corresponding to the data above. For example, consider the operating temperature (the firstcolumn in Table 1, Probability Assessment for CUI of Carbon/Low Alloy Steel). With an
operating temperature of 135°C (275°F), move down the first column to the row that matches the
actual operating temperature (the fourth box from the top). Moving all the way across the fourth
row to the right-most column (Points), we find that this temperature corresponds to three points.
Version: 1.0 Date: January 2007 Custodian: DME/4 ECCN: EAR99 Page: 27 of 28
Printed _______________ Printed copies are uncontrolled
Printed copy should not be used more than 1 month after printed date
Mar 12, 2007
7/22/2019 DSM-1510002-SP-20_V1.0[1]
http://slidepdf.com/reader/full/dsm-1510002-sp-20v101 28/28
Downstream Manufacturing Restricted
DBAM Code and Name:
MAN.15.10 Provide Asset Availability – EnsureEquipment Integrity
Assessment and Mitigation Planning for
Corrosion Under Insulation andExternal Chloride Stress Corrosion Cracking
Document Number
DSM-1510002-SP-20
Version: 1.0 Date: January 2007 Custodian: DME/4 ECCN: EAR99 Page: 28 of 28
Printed Printed copies are ncontrolled
3. Repeating this for each column, the following results are generated:
Column Heading Points
Operating Temperature 3
Coating Status 5
Cladding/Insulation Condition 3
Insulation Type 5
Heat Tracing 0
External Environment 5
Total 21
3. Determining Inspection Strategy
1. Recall that the Consequence and Probability for this example are:
a. RAM Consequence – 2.
b. Probability – 21.
2. To determine the Inspection Strategy, enter the Table 2, Inspection and Maintenance Strategy
Matrix for CUI for Carbon/Low Alloy Steel, in the top row for a Probability Score more than 20.
Move across to the column corresponding to a RAM Consequence of 2. This results in Inspection
Strategy 3 (IS-3).
Mar 12 2007