Coleman Mach Factory Air Conditioner Diagram May Be Designed

In Four Different Ways

• The dotted outlined box on the left shows a PTCR and start capacitor.

• The right dotted outlined box shows a start relay design.

• The dotted parts inside each block show that those pieces may or may not be installed in either design.

• There could be 2 or 3 capacitors within the electric box.

Page 3: SOFTSTARTRV Installation · 2020. 4. 3. · SoftStartRV Integrates into Coleman Mach 1, 3, 3+, 10, 15 Wiring Diagram •5 Color-Coded SoftStartRV Wires •Look at the right dotted

SoftStartRV Integrates into Coleman Mach 1, 3, 3+, 10, 15 Wiring Diagram

• 5 Color-Coded SoftStartRV Wires

• Look at the right dotted block which shows a start relay design.

• SoftStartRV installs the same way irrespective of the configuration used in your air conditioner.

• Follow the steps in this guide to correctly install SoftStartRV

Page 4: SOFTSTARTRV Installation · 2020. 4. 3. · SoftStartRV Integrates into Coleman Mach 1, 3, 3+, 10, 15 Wiring Diagram •5 Color-Coded SoftStartRV Wires •Look at the right dotted

Open The Air Conditioner Cover

All installation is done inside the cover of the air conditioner on top of the RV.

• NOTE 1 The first step is to turn off power to the RV.

• NOTE 2 The cover is held in place with four screws, two on each end.

• Remove the four screws and remove the cover. Place the cover and screws out of the way so you can safely work on the air conditioner.

Page 5: SOFTSTARTRV Installation · 2020. 4. 3. · SoftStartRV Integrates into Coleman Mach 1, 3, 3+, 10, 15 Wiring Diagram •5 Color-Coded SoftStartRV Wires •Look at the right dotted

1. Install SOFTSTARTRV -Here the RED arrow points to 3 different locations.

2. 5 wires must be pointing down or mounted parallel to the air condition cabinet bottom.

4. YELLOW arrow points to the cover of the electric box. Unscrew cover for access.

Installing the SoftStartRV unit: Clean the surface of the mounting location and the bottom of the enclosure.

Peel tape seal on the back of the unit on the unit and mount the box.

Screws are provided to better secure unit.

Never mount the SoftStartRV in the hot air exhaust from the condenser fan.

Mounting Locations & Electric Panel

Page 6: SOFTSTARTRV Installation · 2020. 4. 3. · SoftStartRV Integrates into Coleman Mach 1, 3, 3+, 10, 15 Wiring Diagram •5 Color-Coded SoftStartRV Wires •Look at the right dotted

Always install SoftStartRV with the wire exit pointing down or parallel to the ground.

Never install SoftStartRV with the wire exit pointing up, as it may collect moisture.

Never mount the SoftStartRV in the hot air exhaust from the condenser fan.

Example Mounting Location For SoftStartRV

Page 7: SOFTSTARTRV Installation · 2020. 4. 3. · SoftStartRV Integrates into Coleman Mach 1, 3, 3+, 10, 15 Wiring Diagram •5 Color-Coded SoftStartRV Wires •Look at the right dotted

• The compressor is shown with red arrow in photo.

• The RED arrow points to the cap over the compressor wiring.

• Do not remove this cap for installation.

• Follow the 3 red, black, and white wires from the Compressor cap to the electric box.

• The wires go through to the electrical box. See YELLOW arrow

Locating The Compressor & 3 Compressor Wires To Electrical Box

Page 8: SOFTSTARTRV Installation · 2020. 4. 3. · SoftStartRV Integrates into Coleman Mach 1, 3, 3+, 10, 15 Wiring Diagram •5 Color-Coded SoftStartRV Wires •Look at the right dotted

SoftStartRV- Routing 5 Wires• Remove the putty from

hole access to the electrical box wire see RED arrow

• Push the 5 SoftStartRV wires through the hole. See YELLOW arrow

Page 9: SOFTSTARTRV Installation · 2020. 4. 3. · SoftStartRV Integrates into Coleman Mach 1, 3, 3+, 10, 15 Wiring Diagram •5 Color-Coded SoftStartRV Wires •Look at the right dotted

• Replace the putty. by molding it around the wires. See RED arrow

• Use the wire zip ties provided to make sure the wires are neat. See YELLOW arrow.

Typical Completed Wiring & Mounting

SoftStartRV

Page 10: SOFTSTARTRV Installation · 2020. 4. 3. · SoftStartRV Integrates into Coleman Mach 1, 3, 3+, 10, 15 Wiring Diagram •5 Color-Coded SoftStartRV Wires •Look at the right dotted

Another Typical Example Of Parallel Installation

Page 11: SOFTSTARTRV Installation · 2020. 4. 3. · SoftStartRV Integrates into Coleman Mach 1, 3, 3+, 10, 15 Wiring Diagram •5 Color-Coded SoftStartRV Wires •Look at the right dotted

Making The Connections

Recommend you use only end splice connectors for connecting one wire to another

Due to vibration, wire nuts can come off

Use connectors in the install kit provided. Don’t use automotive connectors because they’re are not rated for line voltage.

Page 12: SOFTSTARTRV Installation · 2020. 4. 3. · SoftStartRV Integrates into Coleman Mach 1, 3, 3+, 10, 15 Wiring Diagram •5 Color-Coded SoftStartRV Wires •Look at the right dotted

RED X’s indicate components THAT MUST BE DISCONNECTED & OR REMOVED

NOTE 1 The RED X’s indicate components THAT MUST BE DISCONNECTED & OR REMOVED during installation of SoftStartRV.

NOTE 2 The RED X connection wire must be disconnected and or removed from the C terminal of the Run Capacitor (RUN CAP) See RED arrow points to Run Capacitor

Page 13: SOFTSTARTRV Installation · 2020. 4. 3. · SoftStartRV Integrates into Coleman Mach 1, 3, 3+, 10, 15 Wiring Diagram •5 Color-Coded SoftStartRV Wires •Look at the right dotted

• All air conditioners use a split style run capacitor as shown in the picture.

• Terminal identifiers are usually stamped into the top of the capacitor.

• The “C” terminal or common terminal has several white wires plugged into it. BLUE arrow

• The HERM terminal has one or more red wires connected. RED arrow

• Although not visible, the FAN terminal is also labeled and has a single wire connected

Identifying Run Capacitor Terminals

Page 14: SOFTSTARTRV Installation · 2020. 4. 3. · SoftStartRV Integrates into Coleman Mach 1, 3, 3+, 10, 15 Wiring Diagram •5 Color-Coded SoftStartRV Wires •Look at the right dotted

STEP 1 Locate the WHITE compressor wire on the compressor terminal labeled R see RED arrow

This white wire connects to the C terminal on the Run Capacitor see YELLOW arrow

Note: Some air conditioners have several white wires on the Run Capacitor terminals.

Be sure to follow the white wire from the compressor completely back to the run capacitor

Locate The WHITE Compressor Wire & Follow it to the Run Capacitor Inside Electrical Box

Page 15: SOFTSTARTRV Installation · 2020. 4. 3. · SoftStartRV Integrates into Coleman Mach 1, 3, 3+, 10, 15 Wiring Diagram •5 Color-Coded SoftStartRV Wires •Look at the right dotted

Follow White Compressor Wire To Run Capacitor Terminal C

STEP 1, contd. Follow the white wire from the compressor into the electric box to the top of the run capacitor as indicated by the RED arrow.

STEP 2 Disconnect the white wire from Run Capacitor and Cut off the connector on the end.

Page 16: SOFTSTARTRV Installation · 2020. 4. 3. · SoftStartRV Integrates into Coleman Mach 1, 3, 3+, 10, 15 Wiring Diagram •5 Color-Coded SoftStartRV Wires •Look at the right dotted

End Splice White Compressor Wire To SoftStartRV Blue Wire

STEP 3

Take white compressor & blue SoftStartRV wire see RED arrow

Strip about ½ inch of insulation from the white wire and strip ½” of insulation from the BLUE wire from SoftStartRV.

STEP 3 Twist both wires together and crimp them with an end splice connector see YELLOW arrow

.

Page 17: SOFTSTARTRV Installation · 2020. 4. 3. · SoftStartRV Integrates into Coleman Mach 1, 3, 3+, 10, 15 Wiring Diagram •5 Color-Coded SoftStartRV Wires •Look at the right dotted

End Splice White Compressor Wire To SoftStartRV Blue Wire

STEP 3 contd.

Twist both wires together and crimp them with an end splice connector

This white wire from the compressor was removed from the C terminal of the run capacitor

Connect the white wire to the BLUE wire from the SoftStartRV

SEE RED arrow

Page 18: SOFTSTARTRV Installation · 2020. 4. 3. · SoftStartRV Integrates into Coleman Mach 1, 3, 3+, 10, 15 Wiring Diagram •5 Color-Coded SoftStartRV Wires •Look at the right dotted

Step #3 & #4 Connections Are On The Run Capacitor

STEP 3 contd.Remove white wire from C terminal See YELLOW arrow

Connect the BLUE SOFTSTARTRV wire to the white compressor wire that was removed from the C terminal of the run cap.

STEP 4 Connect the BLACK wire from the SoftStartRV to the C terminal of the Run Capacitor.

See GREEN arrow

Page 19: SOFTSTARTRV Installation · 2020. 4. 3. · SoftStartRV Integrates into Coleman Mach 1, 3, 3+, 10, 15 Wiring Diagram •5 Color-Coded SoftStartRV Wires •Look at the right dotted

RECAP & OVERVIEW Of The SoftStartRV 5 Wire Connections

STEP 1-Connect the BLACK wire from the SoftStartRV to the RUN CAPACITOR See GREEN arrow

STEP 2-Disconnect the WHITE wire from the RUN CAPACITOR See RED arrow

STEP 3- Connect the BLUE wire from the SoftStartRV (using a splice) to the WHITE WIRE from the “R” Terminal of the COMPRESSOR. See YELLOW arrow

STEP 4 - Connect the YELLOW wire from the SoftStartRV to the HERM of the RUN CAPACITOR See PURPLE arrow

Page 20: SOFTSTARTRV Installation · 2020. 4. 3. · SoftStartRV Integrates into Coleman Mach 1, 3, 3+, 10, 15 Wiring Diagram •5 Color-Coded SoftStartRV Wires •Look at the right dotted

RECAP & OVERVIEW Of The SoftStartRV 5 Wire Connections

STEP 5 Connect the RED wire to L3See GREEN arrow

STEP 6 Connect the BROWN wire to the OL (overload) terminal of the Compressor “C”See YELLOW arrow

STEP 7 Disconnect ALL wires to the START CAPACITOR and PTCR.See RED arrows

Check all connections and turn on the power.

Start the Fan first, then the A/C.

Page 21: SOFTSTARTRV Installation · 2020. 4. 3. · SoftStartRV Integrates into Coleman Mach 1, 3, 3+, 10, 15 Wiring Diagram •5 Color-Coded SoftStartRV Wires •Look at the right dotted

.

SOFTSTARTRV BLACK WIRE

Place a female quick-connect terminal on the BLACK wire from SoftStartRV and crimp tightly.

Connect the BLACK wire from SoftStartRV to the run capacitor on the same terminal group as the other white wires on the “C” terminal.

SEE RED ARROW

Extra Close Up Images: Make the BLACK WIRE from SoftstartRV connection to the Run Capacitor C Terminal-2 images

Page 22: SOFTSTARTRV Installation · 2020. 4. 3. · SoftStartRV Integrates into Coleman Mach 1, 3, 3+, 10, 15 Wiring Diagram •5 Color-Coded SoftStartRV Wires •Look at the right dotted

Extra Close Up Images: Step #7 YELLOW wire Connection On HERM Terminal on The Run Capacitor

SOFTSTARTRV YELLOW WIRE

Connect the YELLOW wire from the SoftStartRV to the HERM terminal of the Run Capacitor.

See YELLOW arrow

Page 23: SOFTSTARTRV Installation · 2020. 4. 3. · SoftStartRV Integrates into Coleman Mach 1, 3, 3+, 10, 15 Wiring Diagram •5 Color-Coded SoftStartRV Wires •Look at the right dotted

Close The Air Conditioner Cover

• Replace the four screws, two on each end

• Turn ON the power to the RV

• Turn the breaker for the A/C back on

• Set the thermostat set point to below ambient temperature

• Turn on the fan to low setting

• Turn ON Cooling