Page 1 BRAD-L22301-WP4-SQUIBB-DMS 01
RISK ASSESSMENT AND METHOD STATEMENT FOR THE DEMOLITION OF THE FOLLOWING PONDS BUILDINGS AT
BRADWELL BUILDINGS 39, 40, 62, X4, 101, 150, 150a, 73a, 73b, 74 & TANK
ROOM ABOVE BUILDING X5
DOCUMENT NO: BRAD/L22301/WP4/SQUIBB/DMS-01
Originating Organisation: Squibb Group Revision: 1 Status & Purpose: Demolition RAMS Lead Author: Tom Marron Date: 30/08/2016
Page 2 BRAD-L22301-WP4-SQUIBB-DMS 01
1.0 Revision and changes log
If comments require changes to the method statement the document will be reissued to Squibb Group for revision. Once the comments have been addressed the above procedure will be repeated, attaching the previous approval sheet for reference during approval, until the document is approved. Once approved, method statements will be reviewed for suitability every 3 months as a minimum or where circumstances alter the risks or methodology. The review will be recorded on the hardcopy on the table on page 2 of the document. Should for any reason the methodology or control measures require review then the method statement will be revised and reissued following the above procedure. In order to highlight changes within the method statement please indicate the section and summary of the changes made. Revision Date Comments/Summary of changes Page
No Amended
By 1 30/8/2016 Changes to document after meeting on
Tues 23rd August. Tank room added to demolition methodology. Comments from Natural England & TSA Ecology have been addressed in the RAMS
Tom Marron
1.1 Method Statement review log
Date Reviewed by
Comments Acceptable
Page 3 BRAD-L22301-WP4-SQUIBB-DMS 01
Page 4 BRAD-L22301-WP4-SQUIBB-DMS 01
2.0 Contents
Page 1.0 Revision and changes log 2
1.1 Method statement review log 2
2.0 Contents 3
3.0 Introduction and scope 4
4.0 Environmental Management 5
5.0 Identify general site hazards 9
6.0 Project Management 12
7.0 General operations 12
8.0 Equipment 12
9.0 Materials and waste management 13
10.0 PPE 14
11.0 Emergency Procedures 14
12.0 Prerequisites 15
13.0 Demolition methodology 17
Soft strip 17
Demolition group 1. 17
Demolition group 3. 28
Demolition group 2. 33
Completion and Handover 37
14.0 Risk Assessment 38
14.0 Record of briefing 50
Page 5 BRAD-L22301-WP4-SQUIBB-DMS 01
3.0 Introduction and scope This document has been prepared to describe the outline methods of operations and techniques proposed for the controlled dismantle and demolition of the following Ponds buildings at Bradwell. There are 11 buildings in total to be demolished. The buildings have been split into 3 Demolition groups and will be demolished in the sequence as shown below. Group 1. 62-Iso container loading bay X4-The flask loading bay 40-Active waste handling building 39-Final delay tank building Tank room on the roof of building X5 Group 3. 73b-Active waste vaults vent plant building south 74-Incinerator building 73a-Active waste vaults vent plant building north Group 2. 150a-Elevated walkway 150-Sub change room 101-Fed drum store The buildings have been left in a ‘cold and dark’ condition. All plant and equipment will have been removed from the buildings. All water and power supplies to the buildings will have been have been disconnected. The buildings will be dismantled/demolished using excavator and various attachments. The demolition waste arisings will be segregated at source removing all re-bar and steel which will be placed into the metal waste skip. The concrete and brick spoil from each individual building will be transferred to an area of site outside the Radiological controlled area (RCA) as directed by Magnox The concrete and brick spoil will be crushed to 6F2 and stored as agreed with Magnox. It is anticipated that some residual asbestos may be present in some of the buildings and may be encountered during the demolition phase. Squibb group personnel will be asbestos awareness trained Buildings X4 & X5 are built as one building and require separation, therefore a temporary designed scaffold will be erected to support building X5 prior to the demolition of building X4. The scaffold facing building X4 will be fitted with ranch boards to which 1000guage polythene sheeting will be fitted so to seal off building X5 prior to demolition. The scaffold will remain in situ until a permanent designed structure has been agreed and installed. The scaffold design and erection works will be carried out under a separate RAMS.
Page 6 BRAD-L22301-WP4-SQUIBB-DMS 01
Page 7 BRAD-L22301-WP4-SQUIBB-DMS 01
4.0 Environmental Management. The demolition of the pond buildings within this RAMS is scheduled to take place from September 2016 through to January/February 2017. Advice has been taken from Kayleigh Cheese (Natural England) and also from Tony Stones (TSA Ecology) regarding the potential impact demolition works would have on overwintering birds. The overwintering period for a number of bird species especially water birds, waders, wildfowl is from October to March.
Photo1. Location of demolition operations.
The area highlighted in the photograph above shows the majority of the buildings to be demolished on the east side of the ponds complex.
There are a few small buildings to the west side of the ponds which will be very quickly demolished due to their size.
Natural England have raised a number of issues which they would like addressed within the RAMS.
How are the buildings to be demolished and by what machinery?
The machinery is listed in section 8 and the method of demolition has been detailed for each individual building.
The demolition method has been written to exclude the use of pneumatic hammers in favour of the concrete crusher as recommended in the Magnox 2013/2014 Bradwell Site Environmental Management Plan.
Page 8 BRAD-L22301-WP4-SQUIBB-DMS 01
Page 9 BRAD-L22301-WP4-SQUIBB-DMS 01
Hours of operation?
The hours of operation will be approx. 7.30am to 5.30pm. No demolition works will commence until daylight and demolition operations will cease prior to loss of natural light.
How will the waste from demolition be disposed of?
What access routes are to be used?
What times will rubble be taken away?
What form of transportation will be used?
The demolition spoil will be transferred from the RCA to an agreed location within the Bradwell site perimeter using a tipper lorry. The waste will be transferred a short distance only carrying the demolition spoil from each individual building.The waste will be recycled and reused as required by Magnox. The waste will be transferred as required during normal working hours. At no time will waste be transferred at night.
Birds could be affected by movement and lighting.
The lorry used on site will be travelling short distances only (within site boundry) The excavator will always be moving in slow motion and covering very short distances. All plant and equipment will be turned off at all times when not in use. Plant operators to be ever mindful of the environmental issues when revving engines. No works are to be carried out outside of normal daylight hours so avoiding light spill in the direction of coastal areas.
What noise will be produced?
The noise of the excavator at source will vary between 85 decibels and 110 decibels at peak depending on the operation. As stated previously concrete crunching/crushing will be used instead of concrete breaking.
The noise levels at 100 mtrs from source will read at 70 dB(A)
The noise levels at 200mtrs from source will read at 63.98dB (A)
There are areas of interest close to the site. Pewet Island in the estuary to the north west of the site is a high tide roost site (TSA Ecology report-26/08/2016) See map on page 8.
The demolition works are being carried out to the west side of the two reactor buildings. See photos 1& 2.
Page 10 BRAD-L22301-WP4-SQUIBB-DMS 01
Page 11 BRAD-L22301-WP4-SQUIBB-DMS 01
Photo 2. This photo shows the considerable green belt to the east and west sides of the site.
Jetty Demolition area
Reactor buildings N
The reactor buildings will act as a natural noise barrier between the demolition site and Pewet island. The Island is also a good distance from the demolition area. There is a considerable green belt to the west and east of the station. See photo 2.
Photo 1 shows the north shore to be approx. 200 mtrs from the demolition site. The (TSA Ecology report-26/08/2016) states that the most of the effects of demolition activities (If Any) will be to the north and north east of the site.
The Bradwell Site Environmental Management Plan 2013/2014 gives a brief description of the area to the north and northeast.
“In contrast the section of dyke that lies immediately to the north of the power station supports dense common reed with little surface water at all. The section to the east of the power station also holds little or no water and supports a mosaic of dense reed habitat and grassland dominated by sea couch”.
Looking closely at photo 1 I do not believe that the area north of the site would be the prime site that would attract overwintering birds with so much prime marsh ground on which to feed and rest to choose from. However, it would be very interesting to carry out surveys of the area before, during and after the works.
Page 12 BRAD-L22301-WP4-SQUIBB-DMS 01
Information needs to be included regarding dust and how it is to be controlled.
Information on dust has been addressed during every phase of demolition and also in the risk assessment. Damp down as required is a statement used for each and every building. As required is taken to mean just that. We do not want to be using too much water which is a waste.
Natural England assumes that there will be no discharges associated with these works, If there is then detailed information will be required.
The only discharge envisaged will be surface water which will be generated during the damping down process during demolition. In order to contain any particulate, Squibb Group will position square spill pads across the surface water drains. The drain cover will be lifted, the pad will be positioned and the drain cover replaced. This will form a seal allowing only water to filter through the pad.
Map of coastal area.
Page 13 BRAD-L22301-WP4-SQUIBB-DMS 01
5.0 IDENTIFY GENERAL SITE HAZARDS
Vehicle Movements
Beware of vehicle movements on site and keep to designated pedestrian routes All plant must be fitted with reversing alarms and accompanied by banksman
Trip Hazards
Maintain good housekeeping at all times and ensure work areas are cleaned up at regular intervals
Keep pedestrian walkways clear at all times
Noise
Noise levels will be monitored throughout the project At exposure levels of 85dB (A) Squibb group will ensure that ear protection is worn at all times
Dust
During demolition works dust will be minimised using dust suppression methods
Light eye protection is mandatory on site for Squibb operatives.
Harmful
Substances
COSHH and Material Safety Data Sheets will be available for all residual hazardous materials
Asbestos
Areas containing ACM’s will have been cleared and removed by licensed asbestos removal operatives.
The finding of any further suspect materials or asbestos containing materials will be reported to Magnox. Demolition works will stop until the asbestos issue has been addressed by a licensed contractor.
Page 14 BRAD-L22301-WP4-SQUIBB-DMS 01
Electricity
Prior to commencing demolition works all electrical supplies should be isolated. If you have any doubts about electrical supplies, stop work and consult with the Site Manager.
Certificates of electrical isolation to be passed to Squibb site manager prior to commencement of demolition works
Manual Handling
Always consider what you are going to lift and how you are going to lift, there may be another way
Always consider mechanical methods such as forklifts or other types of plant.
Working at Height
If you believe your work will create an unprotected edge then stop and raise this concern with your supervisor or the Site Manager so that a suitable system can be put into place.
Never walk away and leave an open edge or hole unprotected.
Electrical tools
All electrical tools will be inspected prior to use to ensure that they are in good working order and fit for purpose.
Always use the correct tools for the task being carried out
All tools, cables will be 110v and carry in date inspection tags (PAT)
Radiaton Contamination
This work is being carried out on a Nuclear site
All works are to be carried out in accordance with the relevant safety documentation, Work Order Card (WOC) Radiological Control Document (RCD) Permit to work(PTW)
All waste movements will be in accordance with Magnox Project Waste Management Plan, Ref number: BRAD/22408/PWMP/008
All waste will be surveyed by Health Physics prior to transfer
The containment of the Ponds building is to be maintained at all times
Page 15 BRAD-L22301-WP4-SQUIBB-DMS 01
Figure 1. Layout of ponds buildings. N S The buildings highlighted in yellow are the buildings to be demolished. Pipeline Position plywood sheets to protect this protruding pipe section Plywood sheets Excavator. Exclusion zone
Erect scaffold to support and seal off X5 Tank room on X5 roof Exclusion zone barriers Excavator to separate building X4 from building X5 at this point See photo no 2.
Road
Page 16 BRAD-L22301-WP4-SQUIBB-DMS 01
6.0 Project Management. Name Position Contact no: Office Westley Squibb Operations Director 07770238317 Barking
Robert Syms Director Nuclear 07912733085 Barking-Visiting
Philip Ashfield Estimating Director 07973741719 Barking-Visiting
Richard Parcell H&S Director 07736018456 Barking-Visiting
Richard Roberts Asbestos division 07736018521 Barking-Visiting
Tony Challis Site manager 07736018450 Site Based
7.0 General Operations Site establishment Set up area exclusion zones Protect any drains using plywood sheets and spill pads Protect the protruding pipe system to the east of building 40 using plywood sheets Soft stripping Erect temporary designed scaffold to support building X5 prior to demolition of X4. Scaffold to include ranch boards so that1000 gauge polythene can be fitted to seal building X5 prior to the demolition of building X4. Demolition of the buildings as listed in section 3 (Scope of works) Processing of waste Transfer of demolition concrete and bricks to an area outside of the RCA as instructed by Magnox Crushing of concrete and bricks to 6F2 Transfer of waste materials Backfilling of basement/open tank structure at buildings 39 and 74 Site clean up Demobilise Handover of clean area 8.0 Equipment 2 x 20t - 360 Degree excavator steel tracked with pulverisor/grab, breaker and buckets. Tipper lorry-8 wheeled with carrying capacity of 18t or RORO lorries Rubber tracked concrete crusher Skips for metal, glass, asphalt and wood
Page 17 BRAD-L22301-WP4-SQUIBB-DMS 01
Equipment continued Diesel generator Spill kit Mobile Elevated Working Platform (MEWP) Oxy-Propane burning equipment 110v Electrical tools: Reciprocating saw, 9” Grinder Various hand tools Various 110v lights and cables Fire extinguishers Heras fence panels for compound and skip laydown area Debris containment netting Fuel bowser (Bunded) Water supply and hoses for damping down during demolition 1000 gauge polythene sheet x 3 Spraytak glue x tins Staple gun and staples 1 x box of 3” cloth tape Two way radios and chargers Diamond cutting chain saw Hilti breaker TE 3000-AVR Wheelbarrow Podium steps Various hand tools, shovels, brushes. 9.0 Materials and waste management All materials arising from demolition activities will be segregated and placed into the relevant waste skips. Skips will be required for Glass, metal, wood and asphalt. The waste skips will be numbered and labelled as instructed by Magnox. The waste skips will be positioned at an agreed location within the demolition compound and will be covered with tarpaulins at all times when not in use. The waste skips will be transferred from site only when they have been approved for transport by the waste team. The concrete and brick spoil will be transferred as instructed by Magnox to an area outside of the radiological controlled area. The concrete and brick spoil from each individual building will be kept separate as instructed by Magnox. The concrete and brick spoil will be crushed to 6F2. Squibb Group will adhere to all aspects of the SWMP Ref no: BRAD/22408/PWMP/008 in accordance with Magnox site procedures and all applicable UK waste regulations. Should any suspect materials be found during operations then work will stop and a report will be forwarded to Magnox.
Page 18 BRAD-L22301-WP4-SQUIBB-DMS 01
10.0 Personal Protective Equipment Hard hat – BS EN 397 Safety boots – BS EN ISO 20345 Hi vis coat or vest - BS EN 471 Safety glasses - BS EN 166 Full face visor – EN166 Ear protection – BS EN 352-2 SNR 28 & BS EN 352-3 SNR 30 High vis waterproofs (for inclement weather conditions) Protective gloves – Mechanical risks – BS EN 388: 2003 Leather welders gauntlets – BS EN 388 :2003 Flame retardant coveralls – BS EN ISO 15025: 2002
Page 19 BRAD-L22301-WP4-SQUIBB-DMS 01
11.0 Emergency procedures Specific site emergency procedures will be adhered to at all times. Instructions will be posted at the site base. All operatives will attend the specific Bradwell site induction including access and egress to the Radiological Controlled Area (RCA) prior to commencement of works. In the event of a minor accident the operative should report to his trained fist aider and then
• In the Make their way to the Occupational Health department or: • Contact the Duty First Aider-2222- for minor injuries: • Contact 2222- for major injures
In the event of a Major Accident / Emergency dial telephone number 2222 immediately.
• Once the casualty is dealt with, make the site safe and cordon off the area to ensure the scene does not get disturbed
• Inform the Construction Manager/Magnox Site Engineer immediately • All accidents are to be recorded in the Bradwell Accident Book which is located in the
Occupational Health Centre. • The Construction Manager/Magnox Site Engineer will inform the ISE and instigate an
initial fact find. • The initial fact find may include photographs of the area and short interviews with the
persons involved. • When the fact find is complete this will be used to complete the Event/Near Miss Report
form in accordance with MCP-18-001
Page 20 BRAD-L22301-WP4-SQUIBB-DMS 01
12.0 PREREQUISITES 12.1 All demolition works will be carried out in accordance with BS 6817:2011, the Health &
Safety at Work act 1974 and the specific Project Construction Phase Health and Safety plan. The works will be monitored through regular inspections ensuring it is being conducted safely and in accordance with this Method Statement/Risk Assessment All works will be undertaken in compliance with all relevant Magnox Construction Site Instructions (CON SI’s)
12.2 Ensure all operatives are SQEP to carry out their duties. SQEP file to be held in site office and available for inspection at all times
12.3 Ensure operatives have received the Bradwell site induction
12.4 Ensure that all operatives have read and fully understand the procedures within this RAMS All operatives involved with the works will sign the acknowledgement sheet
12.5 Working supervisor to pick up the Works Order Card (WOC) Permit to Work (PTW) prior to start of works Working supervisor to carry out and record daily team briefs prior to start of works Site operatives to carry out Point of work Risk assessment prior to commencement of works. This will be reviewed on a daily basis
12.6 Service isolation certificates to be obtained by site supervisor prior to start of works
12.7 Ensure all plant and equipment is located on site and that they carry in date inspection and test certification
12.8 Protect protruding pipework system to the east side of building 40 using 8’x4’x1” plywood sheets prior to start of demolition. See figure 1.
12.9 Ensure that the metal, glass. asphalt and wood skips are located in a suitable area within the site compound, Covered with tarpaulins, numbered and labelled accordingly as instructed by Magnox.
Page 21 BRAD-L22301-WP4-SQUIBB-DMS 01
12.10 Ensure that all electrical tools and equipment is 110v and carries in date PAT certification/tag
12.11 Ensure that existing man hole covers are covered with 8x4x1” plywood sheets. Ensure that square spill pads are fitted to all surface water drains. Traffic cones will be positioned to highlight the locations of the drain covers
12.12 Ensure that spill kit is positioned adjacent the diesel generator and fuel bower.
12.13 Ensure that water supply, hoses and nozzles are connected and in place prior to demolition works.
12.14 Ensure exclusion zones are in place and that all relevant safety signage has been displayed and secured.
12.15 Ensure that the HOT WORKS permit is in place prior to starting works
12.16 TEMPORY DESIGNED SUPPORT SCAFFOLD STRUCTURE DIVIDING X4 from X5
12.17 Ensure that a designed scaffold structure has be erected to support building X5 prior to the demolition of building X4. This scaffold will also act as a dividing wall between X4 and X5 .
12.18 The scaffold structure will be ranch boarded across the complete structure
12.19 The scaffold framework and ranch boards will be covered with 1000 gauge polythene sheeting using staple gun, 3” cloth tape and spraytak glue as required to seal building X5 from building X4. Operative will use a MEWP to access and carry out this task.
12.20 The polythene will be fixed at wall and ceiling surfaces using spraytak glue, 3” cloth tape and wooden latts. Wooden latts will also be pinned to the scaffold ranch boards to further secure the polythene sheeting.
Page 22 BRAD-L22301-WP4-SQUIBB-DMS 01
13.0 DEMOLITION METHODOLOGY 13.1 SOFT STRIP
Position temporary lighting as required
13.2
Soft stripping will be carried out using a reciprocating saw and basic hand tools as required. Podium steps will be used for some access. The podium steps will be tagged with an in date inspection label.
13.3 Remove all timber doors and door frames from buildings and transfer to the wood skip.
DEMOLITION GROUP ONE: 13.4 BUILDING 62 - ISO CONTAINER LOADING BAY - (21.3m x 7.6m x 4m high)
The road to the east of building 62 will be temporarily closed and managed whilst ensuring that previously agreed emergency access/egress measures are maintained.
13.5 Establish exclusion zone. Position banksmen with radios.
13.6 Starting at the south east corner of building 62 the 360 excavator fitted with a multi jaw veractor will steadily crunch its way through the building starting at the south end and working its way north. Damp down as required The jaws will demolish the south end wall first, then steadily crunch through the roof section by section trimming the west and east supporting walls as it progresses in a northerly direction until building 62 has been demolished. See figure 1. The ground floor slab and ground beams will be left in place
13.7 Periodically excavator works will stop whilst any burning works take place (re-bar) Process the waste separating any steel. Transfer all steel to the metal skip.
Page 23 BRAD-L22301-WP4-SQUIBB-DMS 01
13.8 Transfer all concrete and brick spoil from building 62 to an area of site outside of the RCA as directed by Magnox. The concrete and brick spoil will be further processed by a second excavator The waste will be put through the crusher and crushed to 6F2 The crushed waste will be stored as directed by Magnox
13.9 When all arisings have been removed from the vicinity of building 62 slab, the area will be checked and any remaining column stumps or trip hazards at slab level will cut flush/levelled.
13.10 Carry out a general clean up prior to starting the demolition of the next area (Building X4)
Building X4 Building 40 Building 39 Building 150 Building 62
S E W N Photo 3. Buildings to the east side of the pond complex.
Page 24 BRAD-L22301-WP4-SQUIBB-DMS 01
13.11 BUILDING X4. FLASK LOADING BAY (6m wide x 14m long x 8m high) The road to the east of building X4 will be temporarily closed and managed whilst ensuring that previously agreed emergency access/egress measures are maintained. Demolition will start at the east end of building X4 and continue in a westerly direction Position excavator on the east road. Position banksmen with radios
13.12 The jaws will demolish the east end wall first, then steadily crunch through the roof section by section trimming the north and south supporting walls as it progresses in a westerly direction. Damp down as required. Continue in this manner until building X4 crosses the roadway towards the flask wash down bay. Ensure that banksman is policing the barrier to the north of building X4. See figure 1. Remove metal doors, size reduce into manageable sections and transfer to metal skip The excavator and veractor head will carefully trim the roof and wall sections back to the point shown in the photo below as advised by Magnox X5 Trim the building back to this point X4
N Metal doors W E Photo 4. Separation point between building X4 and building X5 S
Page 25 BRAD-L22301-WP4-SQUIBB-DMS 01
Check that the polythene seal remains intact. The Radiological containment of the ponds buildings must be maintained at all times The ground floor slab and supporting piles will be left in place
13.13 Periodically excavator works will stop whilst any burning works take place (re-bar) Process the waste separating any steel and transfer steel to the metal skip.
13.14
Transfer all concrete and brick spoil from building X4 to an area of site outside of the RCA as directed by Magnox. The concrete and brick spoil will be further processed by a second excavator The waste will be put through the crusher and crushed to 6F2 The crushed waste will be stored as directed by Magnox
13.15 At this point SQEP operatives will use a mobile elevated working platform (MEWP) to access and trim the wall and roof surfaces flush using diamond cutting chain saw and hand held Hilti breaker as required. See photo 4.
13.16 When all arisings have been removed from the vicinity of building X4, the area will be checked and any remaining column stumps or trip hazards at floor level will be cut flush/levelled.
13.17 Carry out a general clean up prior to starting the demolition of the next area (Building 40)
Page 26 BRAD-L22301-WP4-SQUIBB-DMS 01
13.18 BUILDING 40 THE ACTIVE WASTE HANDLING BUILDING (7.4m wide x 22.3m long x 8m max high) The road to the east of building 40 will be temporarily closed and managed whilst ensuring that previously agreed emergency access/egress measures are maintained. Demolition will start at the south end of building and continue in a northerly direction Position excavator on the X4 slab facing north. Position banksmen with radios.
13.19 Protect protruding pipework system to the east side of building 40 using 8’x4’x1” plywood sheets prior to start of demolition. See figure 1.
13.20 The jaws will demolish the south end wall first, then steadily crunch through the roof and first floor slab section by section trimming the east and west supporting walls as the excavator progresses in a northerly direction. Damp down as required Continue as above until the two story section has been demolished. Continue to demolish the lower section of building 40 in the same manner trimming the roof and wall sections in a northerly direction as far as the south wall of building 39, until building 40 has been completely demolished. See photo 3. The ground floor slab and supporting piles will be left in place
13.21 Periodically excavator works will stop whilst any burning works take place (re-bar) Process the waste separating any steel. Transfer all steel to the metal skip.
13.22 Building 40 is the largest of the buildings to be demolished. The concrete and brick spoil from this building will be temporarily stockpiled on the X4 slab area. The spoil will be graded and compacted by the excavator. The reason for this operation is that the excavator will use the ramp in order to gain extra height for the demolition of the Tank room which sits on the roof of building X5. See figure 2 below.
Page 27 BRAD-L22301-WP4-SQUIBB-DMS 01
Figure 2. Building 40 temporary spoil heap. Building 39 Concrete and brick spoil from building 40 placed here.
Tank building on the roof of building X5
13.23 When all arisings have been removed from the vicinity of building 40 slabs the area will be checked and any remaining column stumps or trip hazards at floor level will be cut flush/levelled.
13.24 Carry out a general clean up prior to starting the demolition of the next area (Tank room on building X5 roof)
East road
Page 28 BRAD-L22301-WP4-SQUIBB-DMS 01
13.25 THE TANK BUILDING ABOVE BUILDING X5 ROOF. EXERCISE CAUTION DURING THIS OPERATION.
13.26 The east road will be temporarily closed and managed whilst ensuring that previously agreed emergency access/egress measures are maintained.
Photo no 5.
Tank room on building X5 roof.
13.27 Erect Heras fence panels around 3 sides of the tank room structure on the roof of building X5. The Heras fence panels will be fastened to the existing hand rail. 8’ x 4’ x 1” plywood sheets will be fixed to the Heras fence panels This will prevent any concrete debris from falling on to the roof of building 38b or building X3.
13.28 Position the excavator on the spoil heap (X4) facing west. Position banksmen as required.
13.29 Using the excavator jaws steadily crunch the roof section of the tank house into
Page 29 BRAD-L22301-WP4-SQUIBB-DMS 01
rubble. The tank house is open fronted which will allow the jaws easy access. See photo numbers 5&6.
13.30 Rotate the jaws accordingly and trim the walls of the tank house. Damp down as required.
Photo no 6.
The tank room is open fronted and has 4 concrete plinths on the roof surface on which tanks were positioned.
13.31 Remove demolition materials as far as possible using the excavator jaws including the concrete plinths shown above in photo no 6. Place the demolition spoil on the road in front of building X3. ENSURE that the demolition spoil is kept separate from that of building 40 on which the excavator is positioned.
13.32 When the tank room has been demolished as far as possible the excavator bucket will be positioned as close to the rubble as possible. Operatives will transfer the inaccessible demolition spoil to the bucket using shovels and wheelbarrow.
Page 30 BRAD-L22301-WP4-SQUIBB-DMS 01
13.33 Some trimming and breaking may be required to ensure that the roof surface is level and without trip hazards. This work will be carried out by SQEP operatives using the diamond cutting chain saw and a Hilti breaker.
13.34 Transfer all concrete and brick spoil from the tank room to an area of site outside of the RCA as directed by Magnox. The concrete and brick spoil will be further processed by a second excavator The waste will be put through the crusher and crushed to 6F2 The crushed waste will be stored as directed by Magnox
13.35 Carry out a thorough clean up on completion of operations. Remove all plywood sheets and transfer to the equipment storage area. Remove all heras fence panels and transfer to the equipment storage area
13.36 BUILDING 40 DEMOLITION SPOIL Using the excavator and bucket, load the demolition rubble from building 40 into the lorry and transfer to an area of site outside of the RCA as directed by Magnox. The concrete and brick spoil will be further processed by a second excavator The waste will be put through the crusher and crushed to 6F2 The crushed waste will be stored as directed by Magnox
13.25 BUILDING 39 THE FINAL DELAY TANK BUILDING (14.7m long x 7.4m wide x 6.5m above ground) The building also has a 2m deep below ground basement. The road to the east of building 39 will be temporarily closed and managed whilst ensuring that previously agreed emergency access/egress measures are maintained. Demolition will start at the south end of building 39 and continue in a northerly direction Position excavator on building 40 slab facing north. Position banksmen with radios.
13.26 The jaws will demolish the south end wall first, then steadily crunch through the roof section by section trimming the east and west supporting walls as the excavator progresses in a northerly direction towards building 150. Damp down as required
Page 31 BRAD-L22301-WP4-SQUIBB-DMS 01
Remove all steel beams from the concrete roof rubble and set to one side for size reduction. Continue as above until building 39 has been demolished.
13.27 Periodically excavator works will stop whilst any burning works take place (re-bar/steel beams) Using burning techniques, size reduce the steel beams into manageable sizes. Process the waste separating any steel re bar. Transfer all steel to the metal skip.
13.28 Transfer all concrete and brick spoil to an area of site outside of the RCA as directed by Magnox. The concrete and brick spoil will be further processed by a second excavator The waste will be put through the crusher and crushed to 6F2 The crushed waste will be stored as directed by Magnox
13.29 Excavator to remove all waste from the basement of building 39.
13.30 A hydraulic breaker fitted to the excavator will punch holes in the base of the basement floor to assist drainage.
13.31 When all arisings have been removed from the vicinity of building 39 the area will be checked and any remaining column stumps or trip hazards at floor level will be cut flush/levelled.
13.32 The basement void will be backfilled with approved inert compacted granular material or suitably crushed demolition material as agreed with Magnox The material will be assessed against the chemical and engineering specification detailed in the Bradwell Material Management Plan – BMMP-EN/REP/119. The Environmental Specialist must provide written permission prior to any back-fill operations taking place.
13.33 Carry out a general clean up prior to starting the demolition of the next area which will be Group 3 (Building 73b)
Page 32 BRAD-L22301-WP4-SQUIBB-DMS 01
Figure 3. Site after the removal of Group 1 buildings 62, X4, 40, 39 & Tank room Demolition group 2 Temporary scaffold
E N S Demolition group 3 W
East Road
West road
Page 33 BRAD-L22301-WP4-SQUIBB-DMS 01
13.34 DEMOLITION GROUP 3. BUILDING 73b ACTIVE WASTE VAULTS VENT PLANT BULDING SOUTH The road to the west of building 73b will be temporarily closed and managed whilst ensuring that previously agreed emergency access/egress measures are maintained. Set up exclusion zone for Group 3 demolition works. Position excavator to the south side of building 73b facing north. Position banksmen with radios.
Building 73b. Exercise caution here
Reposition the salt container Photo 7.
13.35 Excavator operator and banksman will inspect the perimeter of the building prior to demolition to see if there are any issues or pipe systems that need to be protected. The building is stand alone and will be carefully folded into its own footprint using the excavator and bucket pulling the building away from all other structures in a south westerly direction. See figure 3. See photo 7.
13.36 Process the waste separating the metal sheet roof. Transfer all steel to the metal skip.
Page 34 BRAD-L22301-WP4-SQUIBB-DMS 01
13.37 Transfer all concrete and brick spoil to an area of site outside of the RCA as directed by Magnox. The concrete and brick spoil will be further processed by a second excavator The waste will be put through the crusher and crushed to 6F2 The crushed waste will be stored as directed by Magnox
13.38 When all arisings have been removed from the vicinity of building 73b the area will be checked and any remaining column stumps or trip hazards at floor level will be cut flush/levelled. Ground floor slab to be left in situ.
13.39 Carry out a general clean up prior to starting the demolition of the next area which will be Group 3 (Building 74)
13.40 BUILDING 74 THE INCINERATOR BUILDING 15m long x 7.4m wide x 6.3m high. The building extends approx. 1.5 m below ground. The road to the west of building 74 will be temporarily closed and managed whilst ensuring that previously agreed emergency access/egress measures are maintained. Set up exclusion zone for building 74 demolition works. Position excavator to the west road facing east. Position banksmen with radios.
Building 74. S Protect this pipe system N
Photo 8. Heras fence panels & plywood sheets
Page 35 BRAD-L22301-WP4-SQUIBB-DMS 01
13.41 Excavator operator and banksman will inspect the perimeter of the building prior to demolition to see if there are any issues or pipe systems that need to be protected. Erect heras fence panels to both sides of the pipe system shown on photo 8 and secure further panels above the pipe system so creating a tunnel. Position 8’ x 4’ x 1” plywood sheets and fasten to the upper heras fence panels creating a protective roof. Position plywood sheets to the south facing heras fence panels creating a protective wall. See photo 8.
13.42 The building is a single story structure extending 1,5m below ground. The building is stand alone and will be carefully folded into its own footprint using the excavator and bucket pulling the building away from all other structures in a south westerly direction. Excavator to remove all demolition spoil from the shallow basement.
13.43 Process the waste separating any metal from demolition spoil. Transfer all steel to the metal skip.
13.44 Transfer all concrete and brick spoil to an area of site outside of the RCA as directed by Magnox. The concrete and brick spoil will be further processed by a second excavator The waste will be put through the crusher and crushed to 6F2 The crushed waste will be stored as directed by Magnox
13.45 A hydraulic breaker fitted to the excavator will punch holes in the base of the basement floor to assist drainage.
13.46 The basement void will be backfilled with approved inert compacted granular material or suitably crushed demolition material as agreed with Magnox The material will be assessed against the chemical and engineering specification detailed in the Bradwell Material Management Plan – BMMP-EN/REP/119. The Environmental Specialist must provide written permission prior to any back-fill operations taking place.
13.47 Carry out a general clean up prior to starting the demolition of the next area which will be Group 3 (Building 73a)
Page 36 BRAD-L22301-WP4-SQUIBB-DMS 01
13.48 BUILDING 73a ACTIVE WASTE VAULTS VENT PLANT BULDING NORTH The road to the west and north of building 73a will be temporarily closed and managed whilst ensuring that previously agreed emergency access/egress measures are maintained. Set up exclusion zone for Group 3 demolition works. Position excavator to the north side of building 73a facing south. Position banksmen with radios.
Building 73a Protect these cable runs
Photo 9.
13.49 Excavator operator and banksman will inspect the perimeter of the building prior to demolition to see if there are any issues or pipe systems that need to be protected. Protect the cable systems behind building 73a. See photo 9
13.50 The building is stand alone and will be carefully folded into its own footprint using the excavator and bucket pulling the building away from all other structures in a north westerly direction. Ground floor slab to be left in situ.
13.51 Process the waste separating any metal from demolition spoil. Transfer all steel to the metal skip.
13.52 Transfer all concrete and brick spoil to an area of site outside of the RCA as directed
Page 37 BRAD-L22301-WP4-SQUIBB-DMS 01
by Magnox. The concrete and brick spoil will be further processed by a second excavator The waste will be put through the crusher and crushed to 6F2 The crushed waste will be stored as directed by Magnox
13.53 Carry out a general clean up prior to starting the demolition of the next area which will be Group 2 (Buildings 150 & 150a)
Site plan after the removal of demolition groups 1 & 3.
Figure 4. Demolition group 2: Buildings101,150 & 150a E N S W
East road
West road
Page 38 BRAD-L22301-WP4-SQUIBB-DMS 01
13.54 DEMOLITION GROUP 2. BUILDING 150 THE SUB CHANGE ROOM AND 150a THE ELEVATED WALKWAY The road to the east of building 150 will be temporarily closed and managed whilst ensuring that previously agreed emergency access/egress measures are maintained. Position the excavator to the north side of the elevated walkway facing south. See photo 10 below.
13.55 Excavator to reduce the elevated walkway and access stairwell to this height
Stairwell Building 150 S N Photo no 10. Elevated walkway with access stairway to the right and building 150 to the left.
13.56 150a The excavator will use the shears to reduce the height of the elevated walkway and access stairwell down to the levels shown in photo no 10.
13.57 Collect all broken glass and deposit in a skip for glass recycling. If the glass is reinforced with fine wire mesh it will be sent to the crusher with concrete and brick where it will be crushed to 6F2. Magnox to advise.
13.58 Segregate all steel angle, channels and cladding and transfer to the metal skip.
Page 39 BRAD-L22301-WP4-SQUIBB-DMS 01
13.59 Using excavator and shear demolish the framework and cladding of the lower stairwell
to the right of the elevated platform. Exercise caution in this vicinity ensuring that the Radiological containment of ponds building 38b is maintained at all times. Transfer all metals to the metal skip
13.60 The reduced elevated walkway consists of a metal deck and concrete floor. The excavator will shear the right hand side of the walkway and assist the walkway section to ground level. Working from left to right the excavator will crunch the walkway platform into manageable sections until it has been completely removed. Segregate all metals and transfer to metal skip. Transfer all concrete to the agreed waste processing area for crushing.
13.61 150 The building is of a porta-cabin style construction and is now a stand alone building The excavator with shear attachment will cut away and size reduce the building folding it in in its own footprint until it is reduced to ground level.
13.62 Remove all glass and transfer to the correct agreed waste route.
13.63 Segregate all steel and transfer to the metal skip.
13.64 Transfer any demolition waste to the agreed waste processing area for crushing.
13.65 When all arisings have been removed from the vicinity of building 150 and 150a the area will be checked and any remaining column stumps or trip hazards at floor level will be cut flush/levelled.
13.66 Carry out a general clean up prior to starting the demolition of the next area (Building 101)
Page 40 BRAD-L22301-WP4-SQUIBB-DMS 01
13.67 BUILDING 101. 16m long x 6.7m wide x 5.8m high.
The road to the east and west of building 101 will be temporarily closed and managed whilst ensuring that previously agreed emergency access/egress measures are maintained. Set up exclusion zone for the demolition of building 101. Position excavator to the north road facing south. Position banksmen with radios.
13.68 Excavator operator and banksman will inspect the perimeter of the building prior to demolition to see if there are any issues or pipe systems that need to be protected.
13.69 Building 101 is a steel framed construction with metal cladding finish. The excavator will size reduce the front elevation of the building (north side) using the shears. The metal will be transferred to the metal skip. Trim the roof section by section by section using the shears. The excavator with shear attachment will cut away and size reduce the upper east and west sides of the building. The excavator and shear attachment will size reduce the upper rear section of the building. The excavator and shear attachment will size reduce and transfer the lower east side and west side sections of the building. The excavator will fold in the rear framework pulling the building in a northerly direction away from the remaining pond structures size reducing the cladding and framework as it goes until the structure has been demolished to ground level.
13.70 Segregate all steel angle, channels and cladding and transfer to the metal skip.
13.71 When all arisings have been removed from the vicinity of building 101 the area will be checked and any remaining column stumps or trip hazards at floor level will be cut flush/levelled.
Page 41 BRAD-L22301-WP4-SQUIBB-DMS 01
13.72 The building floor slab will be left in situ.
13.73 Carry out a general clean up of the area
Ponds complex after the completion of demolition groups 1,2 & 3. Temporary scaffold
E N S W Figure 5.
East road
West road
Page 42 BRAD-L22301-WP4-SQUIBB-DMS 01
13.74
COMPLETION AND HANDOVER The site shall be cleared of all waste items. Remove all spill pads from surface water drains Transfer all skips as agreed with Magnox Waste Team. All plant and equipment will undergo a health Physics reassurance check prior to transfer from site All plant and attachments will be removed from site All tools and equipment will be removed from site The area will be thoroughly cleaned prior to handover Remove demarcation zone barriers and safety signs at demolition site. Remove demarcation zone barriers and safety signs at the crushing site. Magnox to inspect site prior to handover Works Order card (WOC) Form to be signed off.
Page 43 BRAD-L22301-WP4-SQUIBB-DMS 01
14.0 Demolition Risk Assessment for Bradwell Ponds Buildings
Task No
Task Effects of Hazard Rating Likelihood of Occurrence
Rating Initial Risk
Control Measures Residual Risk
1. General site activity uneven surfaces
Slips, trips and falls.
Med (2)
Daily movement of operative across site.
Med (2)
Med (4)
• Good housekeeping to be practiced at all times.
• Constant monitoring and regular supervision to be in place and used to spot potential incidents and hazards.
• Team to carry out POWRA daily • Correct use of barriers/exclusion zones • Exercise caution on site at all times
Low (2)
2. Vehicle/plant Movements.
Damage to vehicles and structures. Injury to site personnel. Crush and physical injury to all parts of body, possible death.
High (3)
Plant movements moving across site.
Med (2)
High (6)
• Vehicles to be supervised when entering the work area.
• Banks man to be in attendance at all times.
• Vehicles to be driven by licensed and authorised personnel only.
• Pedestrians to use footpaths where possible.
• Wear high visibility clothing at all times • Always be aware of moving plant and
vehicles and know their route. • Exclusion zones to be in place • No unauthorised persons present during
vehicle movements • Turn off excavator/vehicle engines when
not in use.
Low (2)
Page 44 BRAD-L22301-WP4-SQUIBB-DMS 01
3. Vehicle/plant Movements.
Collapse of manhole cover or underground voids resulting in vehicle overturning and crushing personnel.
High (3)
Plant movements moving across site.
Med (2)
High (6)
• All fragile surface structures are to be identified, marked and cordoned off.
• Visual inspection of manhole covers to be carried out by site manager and when required cover with plywood sheet.
• Traffic cones to identify drain covers and manhole covers
Low (2)
4. Third
party/others. Contact with hazardous demolition activities.
High (3)
Occasional visitors to site.
Low (1)
Med (3)
• Erect barriers and warning signs, • B a n k sm e n to restrict entry to all
but authorised persons. • Banksmen to keep at a safe
distance • Escort visitors at all times. • Vehicles to be escorted into site
with Banksman in attendance.
Low (2)
5. Work adjacent to access roads, buildings
Falling debris striking people, fence or passing vehicles.
Med (2)
Operatives and members of the public in vicinity.
Med (2)
Med (4)
• Work methods to be selected to protect fence line.
• Temporary barriers to be erected where necessary.
• Banksman to be used at all times • All work to be carried out to the
Approved Method Statement • Team to be vigilant at all times.
Low (2)
Page 45 BRAD-L22301-WP4-SQUIBB-DMS 01
6. Manual handling.
Muscular and skeletal injury to back, arm and body.
Med (2)
Operatives handling debris and small items of equipment.
Med (2)
Med (4)
• Always employ mechanical lifting equipment where possible, if not possible seek assistance or work in teams as required.
• Always use the correct lifting technique as trained.
• If manual handling is unavoidable assess and consider the following: The load - weight, unstable, sharp, hot or very cold, difficult to grasp etc. The individual - height or may have health problems. The task - does it involve poor posture, holding away from the body, handling while seated, and sudden movement. The environment - Uneven, slippery floors, poor lighting, different floor levels.
Low (2)
7. Use of general hand tools
Personal injuries, cuts & abrasions
Med (2)
Small team of operatives involved with soft stripping operations and wall trimming works
Med (2)
Med (4)
• Use only suitable tools for the task • Use tools as per manufacturer’s instructions • Wear suitable PPE as required • Check tools for damage before use • Operatives must be SQEP when using all
tools • POWRA to be carried out for daily tasks • Exercise caution at all times. • No lone working. • STAR principles.
Low (2)
Page 46 BRAD-L22301-WP4-SQUIBB-DMS 01
8. Working at
height. Use of MEWP
Physical injury to all parts of body, possible death resulting from fall.
High (3)
Small teams of operatives accessing work areas during soft strip or making good building surfaces working from MEWPs
Med (2)
High (6)
• A safe means of access to the work location must be provided using Podium steps or MEWP
• No lone working at any time • All workers must wear PPE provided • Fall prevention must be implemented
NOT fall arrest. • Exercise caution around uneven
surfaces • Exclusion zone around podium steps
and MEWP • MEWP operators to be SQEP • MEWP operators to be harness
trained. • MEWP to carry in date inspection and
test certification.
Med (3)
9. Tipper Truck/Plant Movements.
Damage to vehicles and structures. Injury to site personnel and truck operator. Crush and physical injury to all parts of body, possible death.
High (3)
Operative driving truck and site operatives.
Med (2)
High (6)
• Vehicles driven by competent persons • Banksman to be used when reversing in
tight spaces, erect cones, lights, signs, barriers around work area.
• Driver to leave wagon cab while being loaded.
• Truck/plant engines to be switched off when truck is not in use.
• Use appropriate attachments for the type of task to be completed.
• Set up demarcation zone around the work area
• No unauthorised persons allowed at work place
Low (2)
Page 47 BRAD-L22301-WP4-SQUIBB-DMS 01
10. Site General. Incident/Injury caused to personnel due to unknown hazards on site.
High (3)
Operatives working on site individually in small teams undergoing daily duties
Med (2)
High (6)
• SGL team to carry out initial site inspection of work area.
• Team to carry out POWRA prior to start of works and on a daily basis or as the site operations present new hazards
• Client to carry out reassurance monitoring/clearance of equipment prior to removal from site.
• Use good hygiene practices at all times
• Good housekeeping practices • Ensure road closure is put in place
during demolition activities • Display all relevant safety signs
Low (2)
11. Hazardous substances
Incident/Injury to personnel caused by coming into contact with various substances on site.
High (3)
Small teams of operatives involved in operation.
Med (2)
High (6)
• SGL to clearly define and instruct operatives in the control methods and advise on any additional PPE.
• Emergency procedures in place. • COSHH data and assessments to be
available in site file • Client to carry out reassurance
monitoring/clearance of equipment prior to removal from site.
• Operatives are allowed to use site welfare facilities.
Low (2)
Page 48 BRAD-L22301-WP4-SQUIBB-DMS 01
12. Environmental damage.
Contamination of land, air or water with chemicals or waste arising’s.
Med (2)
Operatives handling contaminated equipment.
Med (2)
Med (4)
• Clean up any spillages that may occur immediately.
• Report any major spillage try to prevent entry into drains.
• Refer to COSHH Assessments. • Spill kits placed adjacent to t h e
c o m p r e s s o r a n d f u e l b o w s e r • G e n e r a t o r t o b e p o s i t i o n e d o n
b u n d • Report the finding of any Asbestos
containing materials to the project engineer • Report any RA issues to the project
engineer
Low (2)
13. Falling objects/ panels
Injury to operative during demolition
Med (2)
Small teams of operatives involved in clean up
Med (2)
Med (4)
• SGL to ensure that all operatives are SQEP
• Demarcation zones to be in place. • Banksmen to operate at a safe distance • Banksmen to police exclusion zone at all
times • No unauthorised access • No lone working at any time
Low (2)
14. Working in elevated temperature
Dehydration/Heat stress
Med (2)
Small team carrying out daily duties
Med (2)
Med (4)
• SGL to ensure that all operatives are briefed on working in elevated temperatures
• Ensure that an adequate supply of drinking water is available local to the site
• No lone working at any time. • Weather conditions to form part of
POWRA discussions • Post dehydration urine color chart
Low (2)
Page 49 BRAD-L22301-WP4-SQUIBB-DMS 01
15. Electricity Electric shock Burns, Death
Med (3)
Operatives using electrical equipment
Med (3)
High (9)
• All tools to be 110V only • All cables to be 110v only • All operatives to be SQEP to use tools • All tools to be visually inspected prior to
use • All tools to hold in date PAT certification/
tag / cert • Use the correct tool only for the task • Ensure certificate of electrical isolation is
held prior to demolition works
Low (2)
16. Use of vibrating tools (HAVS)
White finger, numbness, loss of dexterity
Med (3)
Operatives working with vibrating tools periodically
Med (2)
High (6)
• Tools to be carefully selected with AV rating
• HAVs file to be present at the work place showing trigger times of all tools to be used on the project.
• Trigger time/exposure time will be recorded on a daily basis within the HAVs file
• Recip saw (22m/s2)-25mts. This tool will be used sparingly
• Diamond chain saw(8.5m/s2)-2hrs 46mts
• Hilti breaker TE3000 AVR-7m/s2 • Operatives will be rotated as far as
possible to reduce exposure to HAV’s • TBT to be given to operatives prior to
start of works
Low (2)
Page 50 BRAD-L22301-WP4-SQUIBB-DMS 01
17. Demolition Dust
Dust-inhalation, atmospheric pollution
Low (2)
Operatives within the vicinity of demo works may be subjected to raised levels
Low (2)
Med (4)
• TBT to be given prior to start of works covering the hazards of dust
• Exclusion zone to be in place during demolition
• Method of damping down as required for dust suppression.
• Ensure that a water source is available close to the demolition site.
Low (2)
18. Demolition noise
Damage to hearing during use of power tools – demolition activities - tinnitus
Med (2)
Workforce on a daily basis
Med (2)
Med (4)
• Operatives to wear appropriate hearing protection when noise levels become elevated.
• A noise assessment will be carried out during demolition activities
• The noise levels of all tools will be recorded on file. The reciprocating saw has a noise rating of 90dB (A)
• The diamond cutting chain saw has a noise rating of 101dB(A)
• Hilti breaker TE3000 AVR -94dB(A) • Demarcation zones to be in place. • No unauthorised persons to be
allowed in the area • BS EN 352 – 02 Ear plugs with an
SNR value of 28 • BS EN 352 – 03 Ear muffs with an
SNR value of 30
Low (2)
Page 37 BRAD/L22301/WP4/SQUIBB/DMS 01
19. Overhead activities.
Contact with falling objects. Contact with overhead cables
High (3)
Operatives working next to demolition operations.
Med (2)
High (6)
• Site supervisor to visually inspect the site compound prior to start of works identifying any overhead cables or services
• Authorised persons only to be allowed on site
• Operatives to carry out daily point of work risk assessment prior to start of works
• Provision of exclusion zone and signage during demolition works
• Banksman to police exclusion zone. • Banksmen to operate at a safe distance
at all times • Operatives using MEWPs to ensure that
there are no obstructions within the work area prior to start of works.
Low (2)
20.
Working within the RCA
Radiation Contamination
High (3)
Operatives carrying out daily duties within the RCA
(Med) 2
High (6)
• All operatives to read and understand the local rules
• All operatives to undergo site induction including access and egress to RCA
• All operatives to wear EPD at all times when working within the RCA.
• Strict adherence to all Health physics procedures (Full body monitors) when exiting site
• Good hygiene practices at all times • No eating, drinking, chewing gum etc
within the RCA at any time.
Low (2)
Page 52 BRAD-L22301-WP4-SQUIBB-DMS 01
21. Hot Works Burns-Fire-Inhalation of fumes
High (3)
Operatives burning steel sections
(Med) 2
High (6)
• Remove all flammable items from the workplace prior to start of Hot Works
• Ensure Hot Works Permit is in place prior to start of task.
• Ensure that a second operative is in attendance as Fire-watcher during burning operations at all times
• Operatives to be SQEP • Operatives to wear the correct RPE during
hot works (Abek-1 filters and half face respirator)
• Operatives to wear the corect PPE during Hot works. Flame retardant coveralls, burning gauntlets and full face visor
• Ensure that suitable fire extinguishers are available at the workplace prior to start of Hot works
• Ensure operatives carry out POWRA prior to start of task.
• Ensure work area is. dampened down on completion of Hot works
• Ensure that a ONE hour inspection of the work area is carried out before the end of the shift
• Ensure that all operatives are aware of the Bradwell site Emergency procedures
Low (2)
Page 53 BRAD-L22301-WP4-SQUIBB-DMS 01
22. Storage of Oxy-Propane bottles
Fire-explosion-toxic by inhalation
High (3
Site operatives/Visitors
Med (2)
High (6)
• Ensure bottles are stored in a secure locked cage with appropriate signage.
• Carry out daily inspection of storage area and check bottles for leakage.
• Ensure flash backs are used at all times • Ensure pipes and gauges are fit for
purpose and in good condition • Bottles must be changed by a competent
person • Ensure storage cafes are stored at a
distance from occupied buildings • Individual bottles must be transported to
the point of work using bottle trolly and safety chain
• Remove all combustible materials from the vicinity of the bottle compound.
Low (2)
23. Asbestos Some residual asbestos containing materials may be present within the building
Asbestos related diseases-Mesothelioma
High (3)
Site operatives during soft strip and demolition works
Med (2)
High (6)
• SQUIBB operatives will be asbestos awareness trained
• Any suspect materials or ACMs encountered will be reported to Magnox
• Demolition works will stop until the asbestos issue has been addressed by a licensed contractor
Low (2)
Page 54 BRAD-L22301-WP4-SQUIBB-DMS 01
24 Environmental Issues
Risk of disturbance to conservation features (Birds) of International importance
Med (2)
General demolition works
Med (2)
Med (4)
• Minimise noise where possible at all times • Turn of machines when not in use. • Demolition to take place in daylight hours
only. • Minimise dust spread • Use water spray to suppress dust. • Control use of water • Avoid light spill in the direction of coast. • Use crunching head instead of breaker. • Use spill pads in surface water drains to
control and filter water discharge. • Carry out surveys of the area to the north
of site prior to start of works and during works in order to gain information.
Low (2)
Residual Risk Rating = Likelihood of Occurrence x Severity of Hazard High = 9, 6 Medium = 4, 3 Low =2, 1 Likelihood of Occurrence Low (1) May occur in time. However, hazard exists infrequently or hazardous event occurs very infrequently. Low expectation of occurrence. Medium (2) Likely to occur in time. Hazard exists intermittently or hazardous event occurs occasionally. It may be useful to define by exclusion, {i.e. clearly not' High' or 'Low' may be the most practical approach}. High (3) Likely to occur imminently or in the very short term. Hazard exists permanently or hazardous event occurs frequently, or much evidence of previous harm.
Severity of Hazard Low (1) Hazard resulting in minor injury requiring first aid treatment only. Minor consequential loss potential to both individual and organisation. Medium (2) Hazard capable of resulting in personal injury/illness requiring brief absence from work. Medical attention required. But ... Again, defining by exclusion, i.e. it simply isn't obviously 'High' or 'Low'. High (3) Hazard capable of resulting in death, severe injury or illness. Major consequential loss potential to the individual and organisation.
GENERAL
HAZARDS ARE NUMEROUS AND CAN BE EVERYWHERE THE KEY IS TO REMEMBER YOUR TRAINING. TAKE NOTE DURING SITE INDUCTIONS BE EVER VIGILANT AND WATCHFUL, DON’T TAKE CHANCES, IF YOU ARE NOT SURE ASK. REPORT ALL NEAR MISSES. NEXT TIME IT COULD BE AN ACCIDENT.
Page 41
15.0 Record of Risk Assessment & Method Statement Briefing
Name Signature Date