7/30/2019 Progress Report for DC System Project_as of January 132013
1/3
RAISSY TRADING & CONSTRUCTION CO. LTD.
DAILYPROGRESSREPORTProjectName:ReplacementOfDCSystemForSubstaionInAsir ProjectStarted: October6,2012Location :AsirRegion ReportNo.:10PeriodCovered : Date: January13,2013S/N DESCRIPTION
Date
Start
Date
Finish
ToDate TotalRemarks
Accomp AccompI Mobilization
1 Manpower 10/06/12 11/05/12 100% completed
2 EquipmentandTools 10/06/12 10/10/12 100% completed3 Materials 10/10/12 28/12/12 100% completed
SUBSTATIONDCSYSTEMINSTALLATION
IReplacementOfDCSysteminKamisNorth
S/S
1 DeliveryOfMaterialsToSubstation 10/07/12 10/08/12 100% completed2 InstallationofNewBatteryCharger 10/14/12 10/15/12 100% completed3 InstallationofNewBatteryCells 10/16/12 10/17/12 100% completed4 Fillingofelectrolytestobatterycells 10/18/12 10/20/12 100% completed5 CablingandWiringofNewDCSystem 11/20/12 11/21/12 100% completed6 TestingandCommissioning
DCDistributionPanelis
alreadyavailablefrom
SCECO
7 Dismantlin of the existin s stem8 Housekeeping&HandovertoClient(SEC)II ReplacementOfDCSysteminMilitary1S/S
1 DeliveryOfMaterialsToSubstation 10/09/12 10/10/12 100% completed2 Installation
of
New
Battery
Charger 10/21/12 10/22/12 100% completed
3 InstallationofNewBatteryCells 10/23/12 10/24/12 100% completed4 Fillingofelectrolytestobatterycells 11/04/12 11/05/12 100% completed5 CablingandWiringofNewDCSystem 11/22/12 11/24/12 100% completed6 TestingandCommissioning AwaitingforSCECOto
providesecondary
transformerfor380VAC
powersupply.
7 Dismantlingoftheexistingsystem8 Housekeeping&HandovertoClient(SEC)
III ReplacementOfDCSysteminMilitary2S/S
1 DeliveryOfMaterialsToSubstation 10/11/12 10/13/12 100% completed2 InstallationofNewBatteryCharger 11/06/12 11/07/12 100% completed3 InstallationofNewBatteryCells 11/08/12 11/10/12 100% completed4 Fillingofelectrolytestobatterycells 11/11/12 11/12/12 100% completed5 CablingandWiringofNewDCSystem 11/25/12 11/26/12 100% completed6 TestingandCommissioning AwaitingforSCECOto
providesecondary
transformerfor380VAC
powersupply.
7 Dismantlingoftheexistingsystem8 Housekeeping&HandovertoClient(SEC)
IVReplacementOfDCSysteminSaratObeida
S/S
1 DeliveryOf
Materials
To
Substation 10/14/12 10/14/12 100% completed
-
7/30/2019 Progress Report for DC System Project_as of January 132013
2/3
2 InstallationofNewBatteryCharger 11/13/12 11/14/12 100% completed3 InstallationofNewBatteryCells 11/15/12 11/17/12 100% completed4 Fillingofelectrolytestobatterycells 11/18/12 11/19/12 100% completed5 CablingandWiringofNewDCSystem 11/27/12 12/02/12 100% completed6 TestingandCommissioning
Scheduledfortestingan
commissioning7 Dismantlingoftheexistingsystem8 Housekeeping&HandovertoClient(SEC)V
ReplacementOfDCSysteminMuhayil
SouthS/S
1 DeliveryOfMaterialsToSubstationtransferofmaterialisto
bescheduledin
coordinationwithSCECO
Twobatterysystem
replacementwillbe
installed.
2 InstallationofNewBatteryCharger3 InstallationofNewBatteryCells4 Fillingofelectrolytestobatterycells5 CablingandWiringofNewDCSystem6 TestingandCommissioning7 Dismantlingoftheexistingsystem8 Housekeeping&HandovertoClient(SEC)
PORTABLEDCSYSTEMINSTALLATION
I AssemblyOf
1st
Portable
DC
System
1 DeliveryOfMaterialsToSubstation 100% completed2 AssemblyOfMobileCabinet 100% completed3 InstallationofNewBatteryCharger 12/01/12 12/10/12 100% completed4 InstallationofNewBatteryCells 12/11/12 12/13/12 100% completed5 Fillingofelectrolytestobatterycells 12/15/12 12/16/12 100% completed6 CablingandWiringofPortableDCSystem 12/17/12 12/19/12 90%7 TestingandCommissioning8 Housekeeping&HandovertoClient(SEC)
II Assembly
Of
2nd
Portable
DC
System1 DeliveryOfMaterialsToSubstation 100% completed2 AssemblyOfMobileCabinet 100% completed3 InstallationofNewBatteryCharger 12/20/12 12/22/12 100% completed4 InstallationofNewBatteryCells 12/23/12 12/24/12 100% completed5 Fillingofelectrolytestobatterycells 12/25/12 12/28/12 100% completed6 CablingandWiringofPortableDCSystem 12/29/12 12/30/12 90%7 TestingandCommissioning8 Housekeeping&HandovertoClient(SEC)
III AssemblyOf3rdPortableDCSystem
1 DeliveryOfMaterialsToSubstation 100% completed2 AssemblyOfMobileCabinet 100% completed3 InstallationofNewBatteryCharger 01/02/13 01/04/13 100% completed4 InstallationofNewBatteryCells 01/02/13 01/06/13 100% completed5 Fillingofelectrolytestobatterycells 01/07/13 01/07/13 100% completed6 CablingandWiringofPortableDCSystem 12/28/12 12/29/12 90%7 TestingandCommissioning8 Housekeeping&HandovertoClient(SEC)
IV AssemblyOf4rthPortableDCSystem
1 DeliveryOf
Materials
To
Substation 100% completed
-
7/30/2019 Progress Report for DC System Project_as of January 132013
3/3
2 AssemblyOfMobileCabinet 100% completed3 InstallationofNewBatteryCharger 01/07/13 01/08/13 100% completed4 InstallationofNewBatteryCells 01/09/13 01/11/13 100% completed5 Fillingofelectrolytestobatterycells 01/12/13 01/13/13 25%6 CablingandWiringofPortableDCSystem 01/11/13 01/12/13 90%7 TestingandCommissioning8 Housekeeping&HandovertoClient(SEC)V AssemblyOf5thPortableDCSystem
1 DeliveryOfMaterialsToSubstation 100% completed2 AssemblyOfMobileCabinet 100% completed3 InstallationofNewBatteryCharger 01/08/13 01/08/13 100% completed4 InstallationofNewBatteryCells 01/10/13 01/11/13 100% completed5 Fillingofelectrolytestobatterycells 01/12/13 01/13/13 25%6 CablingandWiringofPortableDCSystem 01/11/13 01/12/13 90%7 TestingandCommissioning8 Housekeeping&HandovertoClient(SEC)
PreparedBy:
Eng'r.FrederickGuisando SiteEngineer