MVD NEW MADRID EARTHQUAKE RESPONSE PLAN
Patrick G. Tucker
MVD Civil Disaster Planner
Sarah Jones
MVR Emergency Management
May 8, 2014
BUILDING STRONG®
Concept of Operations
2
• MSC’s and District’s responsibilities aligned by state.
• Support FEMA/DHS through traditional ESF # 3 mission assignments as well as nontraditional missions.
• Worst Case Scenario assumes Memphis and St. Louis will be impacted districts (their PRT’s will not be available)
• Support to USACE Civil Works Projects Will Be Within Current Civil-Works Boundaries
BUILDING STRONG®3
Support to USACE Civil Works Projects Will
Be Within Current Civil-Works Boundaries
MVP, MVR, MVK, & MVN will still be
responsible for their CW AORMVM and MVS will be in reconstitutionImpacted MVM & MVM areas will be divided
into 4 sectors by MS River and E-W line
along MVM flood fight areas.CW Task force assigned to each sector
MVD CW Concept of Operations
BUILDING STRONG®4
NEW MADRID EARTHQUAKECIVIL WORKS TASK FORCES
(NWTF)(MVP)
(NETF)(MVR)
(SWTF)(MVN) (SETF)
(MVK)
BUILDING STRONG®
GIS/PLANNING
BUILDING STRONG®
STATE EOC, JFO, FSA/ISB
BUILDING STRONG®
MVR Task Force
BUILDING STRONG®
Team Structure Capabilities Employment Gaps
Team Structure
BUILDING STRONG®
MVR CWTF – NE Purpose CWTF-F Management Cell
► Direct damage assessments► Upward reporting► Resource support
CWTF Assessment Team► Mobile team – DTOS► Perform CW damage assessments
CWTF Support Team► Co-located with CWTF-F► Technical expertise to assessment and flood teams
CWTF Flood Fight Support► Mobile team► Coordinate/perform flood fight operations