Transcript

Copyright

by

Chioke Bem Harris

2010

The Thesis committee for Chioke Bem Harriscertifies that this is the approved version of the following thesis:

A Mixed-Integer Model for Optimal Grid-Scale Energy

Storage Allocation

APPROVED BY

SUPERVISING COMMITTEE:

Michael E. Webber, Supervisor

Jeremy P. Meyers, Supervisor

A Mixed-Integer Model for Optimal Grid-Scale Energy

Storage Allocation

by

Chioke Bem Harris, B.S.

THESIS

Presented to the Faculty of the Graduate School of

The University of Texas at Austin

in Partial Fulfillment

of the Requirements

for the Degree of

MASTER OF SCIENCE IN ENGINEERING

The University of Texas at Austin

August 2010

To my girlfriend and parents for their indefatigable support throughout my

development as a scholar.

Acknowledgments

Many thanks to my advisors Dr. Michael Webber and Dr. Jeremy Meyers for

their unending support throughout the development of this work. Additionally, John

Baker, Pat Sweeney, Mark Kapner, Babu Chakka and Eddy Tan from Austin Energy

were all instrumental in providing guidance and the data necessary to make this work

possible.

v

A Mixed-Integer Model for Optimal Grid-Scale Energy

Storage Allocation

Chioke Bem Harris, M.S.E.

The University of Texas at Austin, 2010

Supervisors: Michael E. WebberJeremy P. Meyers

To meet ambitious upcoming state renewable portfolio standards (RPSs), re-

spond to customer demand for “green” electricity choices and to move towards more

renewable, domestic and clean sources of energy, many utilities and power producers

are accelerating deployment of wind, solar photovoltaic and solar thermal generating

facilities. These sources of electricity, particularly wind power, are highly variable

and difficult to forecast. To manage this variability, utilities can increase availability

of fossil fuel-dependent backup generation, but this approach will eliminate some of

the emissions benefits associated with renewable energy. Alternately, energy storage

could provide needed ancillary services for renewables. Energy storage could also

support other operational needs for utilities, providing greater system resiliency, zero

emission ancillary services for other generators, faster responses than current backup

generation and lower marginal costs than some fossil fueled alternatives. These ben-

efits might justify the high capital cost associated with energy storage. Quantitative

analysis of the role energy storage can have in improving economic dispatch, how-

ever, is limited. To examine the potential benefits of energy storage availability, a

generalized unit commitment model of thermal generating units and energy storage

facilities is developed. Initial study will focus on the city of Austin, Texas. While

vi

Austin Energy’s proximity to and collaborative partnerships with The University of

Texas at Austin facilitated collaboration, their ambitious goal to produce 30-35% of

their power from renewable sources by 2020, as well as their continued leadership in

smart grid technology implementation makes them an excellent initial test case. The

model developed here will be sufficiently flexible that it can be used to study other

utilities or coherent regions. Results from the energy storage deployment scenarios

studied here show that if all costs are ignored, large quantities of seasonal storage

are preferred, enabling storage of plentiful wind generation during winter months to

be dispatched during high cost peak periods in the summer. Such an arrangement

can yield as much as $94 million in yearly operational cost savings, but might cost

hundreds of billions to implement. Conversely, yearly cost reductions of $40 million

can be achieved with one CAES facility and a small fleet of electrochemical storage

devices. These results indicate that small quantities of storage could have signifi-

cant operational benefit, as they manage only the highest cost hours of the year,

avoiding the most expensive generators while improving utilization of renewable gen-

eration throughout the year. Further study using a modified unit commitment model

can help to narrow the performance requirements of storage, clarify optimal storage

portfolios and determine the optimal siting of this storage within the grid.

vii

Table of Contents

Acknowledgments v

Abstract vi

List of Tables x

List of Figures xii

Chapter 1. Introduction 1

Chapter 2. Motivation 4

2.1 Energy Storage and the Smart Grid . . . . . . . . . . . . . . . . . . . 5

2.2 Grid-connected Energy Storage . . . . . . . . . . . . . . . . . . . . . 11

2.3 Addressing Stochastic Renewable Generation in the Electric Grid . . . 14

Chapter 3. Unit Commitment Modeling Theory 19

3.1 Unit Commitment Modeling for Future Scenarios with Energy Storage 19

3.2 Previous Unit Commitment Modeling Efforts . . . . . . . . . . . . . . 24

3.3 Stochastic Programming and Unit Commitment . . . . . . . . . . . . 29

3.4 Grid-connected Energy Storage . . . . . . . . . . . . . . . . . . . . . 32

Chapter 4. Unit Commitment Modeling with Storage 38

4.1 Methodology . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 38

4.2 Supporting Data . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 44

4.3 Model Structure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 53

4.4 Governing Equations . . . . . . . . . . . . . . . . . . . . . . . . . . . 58

4.4.1 Objective Functions . . . . . . . . . . . . . . . . . . . . . . . . 58

4.4.2 Constraint Equations . . . . . . . . . . . . . . . . . . . . . . . 60

4.4.3 Storage-specific Constraints . . . . . . . . . . . . . . . . . . . . 64

Chapter 5. Results 68

5.1 Monthly Averaged Demand, Wind and Solar Generation . . . . . . . 69

5.2 Year-long Results with Storage . . . . . . . . . . . . . . . . . . . . . . 85

5.3 NOx and CO2 Emissions Pricing . . . . . . . . . . . . . . . . . . . . . 99

viii

Chapter 6. Conclusion 103

Appendix A. Options and Runtimes for Each Scenario 110

Bibliography 112

Vita 120

ix

List of Tables

2.1 Twenty-six states have set renewable portfolio standards (RPS) defin-ing the percentage of total electricity that must be generated fromrenewable sources by set deadlines. . . . . . . . . . . . . . . . . . . . 6

3.1 Parameters and options applied for each model run typically sug-gest model runtimes, where full year (FY) models require significantlylonger times than single day models, even with access to greater compu-tational resources. (Further information regarding the details of eachmodel run is given in Appendix A) . . . . . . . . . . . . . . . . . . . 22

4.1 Austin Energy’s projected generating fleet in 2020 is comprised of avariety of thermal generating units, as well as several types of renewables. 46

4.2 Emission rates for all thermal generators are passed to the model tostudy the effect of emissions pricing on storage allocation and unitcommitment decisions. . . . . . . . . . . . . . . . . . . . . . . . . . . 49

4.3 For the purposes of this study, a small subset of storage types has beenselected based on their cost and performance attributes. . . . . . . . . 52

4.4 GAMS models are structured around controlling indices called “sets.” 54

4.5 Model parameters define the operating constraints of all generators intable 4.1, as well as time-dependent functions. . . . . . . . . . . . . . 54

4.6 Model variables are combined with parameters to form the objectivefunction and constraint equations. . . . . . . . . . . . . . . . . . . . . 55

4.7 For the discrete storage scenarios, additional parameters are requiredto enable constraints on their assignment and operation. . . . . . . . 57

4.8 Additional variables must be defined to constrain the selection andoperation of energy storage in the discrete storage scenarios. . . . . . 57

5.1 Estimated Capital Costs for Selected Storage Devices . . . . . . . . . 69

5.2 Summary of All Scenarios/Cases Presented . . . . . . . . . . . . . . . 70

5.3 Comparing the effects of storage availability reveals that even limitedstorage can manage the highest cost hours of the year, though largequantities of seasonal storage has dramatic effects on dispatch through-out the year. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 93

5.4 If possible, large quantities of energy storage will be allocated by themodel, even when operating costs are included. . . . . . . . . . . . . 96

5.5 With low limits set for all available energy storage types, the optimaloutcome still appears to be the maximum allowable storage. . . . . . 97

x

5.6 Comparing capital costs to annual savings for each of the storage sce-narios suggests the limited storage portfolio provides the best economicbasis for implementation. . . . . . . . . . . . . . . . . . . . . . . . . . 98

A.1 Parameters and options applied for each model run can affect runtimesand system resource management, where full year (FY) models typi-cally required significantly longer runtimes, even when executed on theHPC cluster. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 111

xi

List of Figures

2.1 Storage for arbitrage will yield a flatter daily demand profile, storingcheaper electricity at night and dispatching it during more expensivepeak daytime hours. . . . . . . . . . . . . . . . . . . . . . . . . . . . 10

2.2 The estimated levelized costs of energy storage for 10 hour arbitrage(load shifting) are quite high. With computational studies, it maybe revealed, however, that these costs are outweighed by the benefitsoffered by energy storage. . . . . . . . . . . . . . . . . . . . . . . . . 13

2.3 Denmark increased available thermal generation from 1985 (L) to 2008(R) using mostly small, flexible and efficient combined heat and power(CHP) facilities. This development was a key component in their planto pursue aggressive wind generation growth. . . . . . . . . . . . . . . 15

3.1 In a scenario tree, the number of nodes, and hence, number of paths,increases exponentially as the depth of the tree increases. . . . . . . . 30

4.1 Nearly all of Austin Energy’s planned generation growth by 2020 willbe from renewable sources. . . . . . . . . . . . . . . . . . . . . . . . . 47

4.2 Decker Power Plant unit 1 CO2 emissions are modeled as proportionalto generator load (MW), a reasonable approximation that avoids in-troducing non-linearities to the model. . . . . . . . . . . . . . . . . . 48

5.1 Typical dispatch for a July 2020 day requires dialing back or shuttingdown inexpensive units at night and the use of older, dirtier generatorsto meet peak demand. . . . . . . . . . . . . . . . . . . . . . . . . . . 71

5.2 Dispatch with available storage in a July 2020 day meets peak demandusing wind energy available at night, avoiding the use of expensive anddirty generators and peaking units. . . . . . . . . . . . . . . . . . . . 74

5.3 In a November 2020 day, as with most winter and spring months inTexas, demand can be served almost entirely by baseload generationand renewables because variations during the day are limited. . . . . 76

5.4 As with the November 2020 scenario without storage, demand varieslittle throughout the day and is served by inexpensive generators, yield-ing minimal opportunity for benefit from energy storage availability. 77

5.5 Demand during winter months, as in February 2020, can be servedentirely by renewables and baseload generators in great part becauseof significant wind availability during these months. . . . . . . . . . 79

5.6 In the modeled February 2020 day, frequent ramping of some genera-tors appears, as in several other dispatch results with storage, likely aconsequence of the use of linear marginal costs for these results. . . . 80

xii

5.7 In most months, the availability of energy storage maximizes the dis-patch of inexpensive generators by shaping wind output. . . . . . . . 82

5.8 Benefits from the availability of energy storage scale roughly with max-imum allocation of storage. . . . . . . . . . . . . . . . . . . . . . . . 84

5.9 With a rolling planning solution method, the portion of the modelsolved as a full mixed-integer program is limited to a section of the fullstudy length to shorten solution times. . . . . . . . . . . . . . . . . . 86

5.10 As in earlier results, the availability of energy storage improves dispatchof inexpensive generators by shaping renewables availability. . . . . . 87

5.11 Energy storage flattens demand significantly throughout the year, andas shown in the histogram in the right panel, storage thus reducesthe number of hours of peak generation and the magnitude of peakrequirements while also increasing demand during the lowest few hoursof the year. Average load and standard deviation for each of these casesare summarized in table 5.3. . . . . . . . . . . . . . . . . . . . . . . 89

5.12 With the presence of CAES, the discrete scenario results show not onlya concentration of load levels to be served, as in figure 5.11, but also asmall overall reduction in load. . . . . . . . . . . . . . . . . . . . . . 90

5.13 With limited storage available, minimal reshaping of demand occurs,using storage to shift only the most expensive hours of the year, max-imizing the benefit of what storage is available. . . . . . . . . . . . . 91

5.14 While there is no clear bias towards storage in one period or anotherwhen quantities or model length are limiting factors, when energy stor-age quantities are unlimited, storage is concentrated primarily in thewinter and spring months, when stored energy is the cheapest. It islikely that the difference between generic and discrete storage behaviorin the final months of the year is a consequence of limiting constraintsin the discrete storage scenario. . . . . . . . . . . . . . . . . . . . . . 94

5.15 As CO2 prices increase, dispatch changes to use natural gas generatorsinstead of coal power plants. Since natural gas facilities are much moreflexible in their operation, less storage is required to achieve the samelevel of system flexibility. . . . . . . . . . . . . . . . . . . . . . . . . 100

5.16 Similar to CO2 prices, as NOx prices increase, dispatch shifts towardincreased use of natural gas generators, while storage changes to pro-vide needed system resilience. . . . . . . . . . . . . . . . . . . . . . . 101

xiii

Chapter 1

Introduction

Many utilities plan to significantly expand the portion of their total gener-

ation from wind, solar photovoltaics and concentrating solar power, alongside the

introduction of ‘smart grid’ technologies. Renewable power sources offer domestic

energy security and reduced carbon emissions, but their intermittency complicates

utility management and might limit the degree to which they can be deployed on the

grid. This intermittency, as well as unpredictability of customer demand, is currently

managed by operating primary fossil fuel generators at part-load, providing “spin-

ning reserve,” with fleets of fast-response gas turbines or diesel generators to relieve

spinning reserve providers. Revising this operational approach with the availability

of electrical energy storage could boost efficiency and provide more rapid responses

to interruptions. While the integration of renewable energy sources is typically one

of the key goals of the smart grid, other goals include greater system resiliency and

reliability, better utilization of existing non-renewable generating units and increased

customer participation, including demand-side management (DSM) through smart

metering and smart appliances. Energy storage might be able to improve outcomes

for all these objectives. Storage can also be used for arbitrage, which affects prices

and could have significant effects on customer energy conservation incentives.

To examine the potential benefits of energy storage, a novel unit commitment

model that captures storage attributes is developed. This modeling approach will

yield a structure that can be adapted to a variety of thermal generator and storage

1

constraints, as well as any meaningful set of generators and demand. The city of

Austin serves as the test region for the development of this model. Austin Energy

has generously provided data about historical dispatch and power plant operational

characteristics that fill critical roles in the structure of the model. Beyond these

data, Austin Energy serves as an appropriate initial case for model testing. They are

currently proceeding with the introduction of a wide range of smart grid technologies

to improve system awareness and operations. They also have aggressive demand-side

management programs to help reduce increases in peak demand into the future and

to increase market penetration of smart appliances to be able to attenuate demand

during peak periods. Further, the utility, in conjunction with the city, has committed

to an ambitious schedule for renewable energy introductions, with plans to obtain

30-35% of their electricity from renewable sources by 2020. More than 70% of the

renewable generation contracted to meet this target will be from wind energy, meaning

that by 2020, more than 20% of Austin Energy’s generation will be from wind.

Given the Austin Energy’s profile, energy storage could provide significant

operational value to them — firming and shaping renewable generation, providing

lower marginal cost generation during peak hours and reducing emissions compared

to fossil fueled backup generation, but the use of storage for these applications is not

well understood. The unit commitment model developed in this work is designed

to determine the optimal level of energy storage that will minimize operating costs.

Modeling capital costs through levelized cost of energy (LCOE) or another economic

metric would improve storage portfolio allocation as compared to examining only

operational costs by capturing the primary costs associated with storage. Unfortu-

nately, including storage capital costs would require knowledge about capital costs

and financing of existing plants owned by Austin Energy. Since these data are not

available, capital costs must be excluded from the model and are instead examined

2

with the model results instead of being captured in the objective function. Scenarios

using this basic framework reveal trends across months of dispatch and those results

are compared with a year-long model run. Due to the computational cost of such long

analysis periods, only a few year-long scenarios are run. In these year-long cases, the

unit commitment framework is extended to perform optimal storage selection from a

limited set of storage types. Finally, the effect of emissions pricing schemes on energy

storage selection is explored. From the results of these scenarios, storage portfolios

and implementation guidelines are developed.

3

Chapter 2

Motivation

In the interest of moving towards the use of more renewable, domestic and

secure resources for electricity generation, and often to meet ambitious renewable

portfolio standards (table 2.1), many states are rapidly deploying wind and solar

generation assets. [1] These generators, especially wind facilities, have highly variable

outputs and must be sited where the relevant resource is most available, creating

capacity constraints and additional reliability challenges. [2] Currently, intermittency

from these sources is managed with fast-response natural gas or diesel generators. [3]

These generators could be replaced with energy storage, which offers lower marginal

costs, protection from volatile fuel prices, greater system resiliency and zero emissions.

With the complexity and requirements of the electric grid, however, it is not obvious

if energy storage will be able to deliver these benefits at a reasonable price. This work

explores existing electricity generation and distribution system and changes planned

to implement the smart grid to determine what role energy storage might have in

the future smart grid. While some studies have examined the effect of energy storage

for specific applications or the particular benefits of one type of energy storage, this

work will develop a model that determines the optimal allocation of storage based on

the city of Austin that can be adapted to any region of study and for any type(s) of

energy storage.

4

2.1 Energy Storage and the Smart Grid

Energy storage has been identified as a potential component of the future smart

grid, one significant enough that it is specifically identified in Title XIII of EISA

2007. [4] As part of its mandate in EISA 2007, DOE has qualitatively determined

what roles energy storage could fulfill in smart grid development plans. [4] Since one

of the primary motivations of the smart grid is to increase the utilization of existing

generation, transmission and distribution (T&D) resources, energy storage can be

placed at the site of intermittent generators such as wind farms, at choke points

in the distribution network, or at a substation to improve local power quality and

reliability. [2] Placing storage at these locations could allow deferment of some T&D

improvements or enable optimization of an improved T&D system.

In addition to improvements in resiliency that can enable increased renew-

able energy generation, the smart grid will also enable greater system efficiency. The

Electric Power Research Institute (EPRI) has found that rollout of smart grid tech-

nologies could yield a 4% reduction in energy use in 2030 as compared to a reference

case. [4] As a point of comparison, that would be roughly equivalent to eliminating

the emissions of 50 million cars. [5] Beyond the emissions impact, that translates to

a $20.4 billion in annual savings for utility customers nationwide. [4] With a more

robust and efficient system, and better knowledge and control of demand, it will be

easier for utilities to manage the integration of renewable energy sources that pro-

duce intermittent power. That will help states meet targets for renewable power

growth and minimize fuel consumption by reducing their dependence on natural gas

or diesel reserve generators and use of fossil fuel-based power plants. Energy stor-

age can also support requirements for reserve generation in place of fossil fuel-based

facilities, yielding zero emissions and, without fuel needs, lower operating costs.

5

Table 2.1: Twenty-six states have set renewable portfolio standards (RPS) definingthe percentage of total electricity that must be generated from renewable sources byset deadlines. [5]

State Amount (%) Year

Arizona 15 2025California 20 2010Colorado 20 2020Connecticut 23 2020District of Columbia 11 2022Delaware 20 2019Hawaii 20 2020Iowa 105 MW -Illinois 25 2025Massachusetts 4 2009Maryland 9.5 2022Maine 10 2017Minnesota 25 2025Montana 15 2015New Hampshire 16 2025New Jersey 22.5 2021New Mexico 20 2020Nevada 20 2015New York 24 2013North Carolina 12.5 2021Oregon 25 2025Pennsylvania 18 2020Rhode Island 15 2020Texas 5880 MW 2015Washington 15 2020Wisconsin 10 2015

6

Energy storage could also be beneficial for utilities that have renewable gen-

eration that is not well matched to peak demand times. For example, Texas has

the largest installed base of wind power in the United States, nearly all of which is

located in western Texas, away from the state’s population centers. [6] West Texas

wind power is at its peak during the middle of the night, when demand is lowest. [7]

While sometimes that energy might be needed to supplement base load power plants

to meet minimum demand, often wind generation must be accommodated by dialing

back base load generators. On summer days with high peak demand, though baseload

generators might not be fully dispatched at night, inefficient peaking generation is

required during the day to meet demand. If energy storage were available, excess

nighttime generation could be deferred to peak hours when it is more useful. Energy

storage for arbitrage of renewables, however, is not limited to inland wind generation.

All solar photovoltaics, regardless of the quality of the solar resource, generate less

power as the sun goes down, just as demand approaches its peak.

Demand response control can assist utilities when unexpected supply losses

occur or during periods of unprecedented demand. Utilities, (regional transmission

organizations) RTOs and (independent system operators) ISOs contract with cus-

tomers who can support power losses in their operations in exchange for compensa-

tion. If a system operator encounters an unexpected need for reserve power, they

may temporarily disconnect these contracted customers to restore reserve availability

until demand falls or additional generation comes online. [8] As an example, in Texas

on February 26, 2008, the Electric Reliability Council of Texas (ERCOT) region ex-

perienced a significant unexpected loss of wind power at the same time demand was

increasing. To compensate for the sudden loss of reserve power availability, ERCOT

used its demand response capability to cut power to several customers. This ac-

tion was sufficient to restore balance to the system and minimized the impact of the

7

power loss, preventing much larger scale brownouts or blackouts. [9] While demand

response is helpful in providing system resiliency, energy storage could provide elec-

tricity as quickly as demand response when needed, reducing or eliminating the need

to interrupt customers.

If storage is only used to provide ancillary services, it will not have the same

interaction with smart pricing and customer behavior because it will lack sufficient

capacity to affect prices. This use will, however, increase utilization of planned im-

provements to T&D infrastructure. While this application provides significant opera-

tional benefits, it is unlikely to provide significant diurnal storage for renewables that

are not well matched to demand. Utilities will not be able to realize the same fuel

savings as with storage for arbitrage, but they will be less reliant on demand response

contracts to ensure that they have sufficient flexibility in their system, which can yield

some long term cost reductions. Thus, there is likely still benefit in pursuing smaller

amounts of storage for ancillary services if large quantities of storage for arbitrage is

not an option.

Alternately, storage could be used for arbitrage, storing electricity when gener-

ation is cheaper and returning it to the grid when prices are higher (figure 2.1). This

implementation can benefit a utility by increasing the utilization of existing generat-

ing resources, storing excess generation at night and returning it to the grid during

higher value hours during the day, as discussed previously. Unfortunately, peak de-

mand reductions from customers through smart pricing programs implemented as

part of smart grid development could nullify the value of storage for arbitrage. Us-

ing storage for arbitrage could flatten the effective demand curve, illustrated by the

sine curves representing demand and storage-adjusted demand in figure 2.1. Reduc-

tions in effective peak demand will mean fewer expensive power plants will have to

8

be dispatched, reducing the cost of peak power and minimizing customer incentive

to change behavior. Alternately, if customers respond to price signals or use smart

appliances to curtail their use during peak hours, the potential benefit of storage for

arbitrage during the highest priced hours of the year might not be possible, since

those hours will not be nearly as expensive. Energy storage might be a far more

expensive way to reduce variations in demand, but if placed appropriately within

the T&D system, using storage for arbitrage also ensures that most or all renewable

energy generated will eventually be dispatched. Since renewable energy sources typ-

ically have extremely low operating costs, their increased availability will offset fuel

use associated with traditional generating plants, allowing utilities to realize signifi-

cant operating cost reductions. Ignoring capital costs, these savings will exceed those

associated with demand-side management like smart pricing and smart appliances.

Both potential savings and the need for energy storage will increase with increasing

installed renewable energy generation.

Various studies have made qualitative assessments of possible operational ben-

efits to energy storage availability on the electric grid, but few studies have attempted

to quantify the potential benefits or the amount of energy storage that is appropriate

to meet particular operational goals. As a result, there exists no generalized frame-

work in the literature that has been developed specifically for studying the effects

of energy storage on the grid. Analytical methods such as unit commitment that

might serve as suitable approaches for quantitative analysis of energy storage have

only seen recent study. This work thus seeks to develop these study methods toward

the development of a tool that will enable determination of an optimal allocation of

energy storage and what portfolio of storage technologies might be optimal to reduce

operating costs associated with thermal generator dispatch.

9

0 2 4 6 8 10 12 14 16 18 20 22 24

0

400

800

1200

1600

2000

2400

Time (h)

Load

(M

W)

Without StorageWith Storage

Figure 2.1: Storage for arbitrage will yield a flatter daily demand profile, storingcheaper electricity at night and dispatching it during more expensive peak daytimehours. [3]

10

The city of Austin, Texas has been selected to test and validate the develop-

ment of a model for energy storage allocation in the electric grid. The Electric Relia-

bility Council of Texas (ERCOT) provides significant data online to support analysis

like that undertaken in this work and Austin Energy has generously provided thermal

generator and historical dispatch data. Apart from the availability of data, Austin

Energy is well suited to a study of the benefits of energy storage, as they have already

committed to significant wind and solar power as part of their future generating fleet

and plan to have at least 30% of their electricity from renewable sources by 2020 (see

figure 4.1). [3] Austin Energy has also already begun implementing some smart grid

technology. They have begun installing smart meters across their service area and are

preparing to implement increased distributed renewable energy generation, software

allowing customer interaction with smart meter data, smart pricing, user management

of smart appliances and sufficient system resiliency to support the charging infras-

tructure for plug-in hybrid electric and battery electric vehicles. [10, 11] Further, the

state of Texas has commenced construction of competitive renewable energy zones

(CREZ) to facilitate access to wind power from load centers in the eastern part of

the state. [12] Even without this additional transmission infrastructure, already has

more installed wind capacity than any other state. [12,13]

2.2 Grid-connected Energy Storage

Many different types of energy storage could be employed by utilities and bal-

ancing authorities, depending on their goals for the system. Large-scale facilities are

typically most appropriate for seasonal storage or daily arbitrage, though they might

be capable of short-term storage or rapid system responses. [2] Pumped hydro already

provides storage capacity in the United States and many other countries. [2] While

pumped hydro can be highly responsive and provide storage for an unlimited period

11

with minimal decay, it is only feasible in areas with sufficient water and elevation

changes. [2] Compressed air energy storage (CAES) stores air in underground caverns

and can provide storage on a similar scale, but few full-scale facilities have been con-

structed. [14] Also, CAES still requires fossil fuels, as all existing plants depend on

natural gas to heat the air as it expands out of the storage cavern, though researchers

are exploring solar thermal systems as a replacement for the natural gas. [14]

For shorter storage periods, as with ancillary service provision or to enable

more efficient T&D utilization, batteries might be the most appropriate storage type.

[2] Lead-acid batteries are a mature technology and relatively inexpensive, but they

can tolerate relatively few deep discharge cycles. Many utilities have tested lead-acid

battery systems, but none have pursued large-scale adoption of the technology. [15]

Over the long term, lead-acid batteries would become expensive because they require

frequent replacement as they lose capacity. [16] Lithium-ion batteries have become

popular in recent years for their high energy density and ability to withstand many

charge cycles. Unfortunately, lithium-ion technology is extremely expensive and, at

its current level of technological maturity, is better suited to applications where energy

density is more important, such as laptops and mobile phones. [16] High-temperature

sodium sulfur batteries (NaS) and redox flow batteries (RFB) both show promise for

utility scale applications, as they have the cycle life needed to withstand heavy use

for many years. [17] Because of only recent interest in energy storage for electric grid

applications, however, they are largely confined to specialized applications and pilot

programs. [18] High costs plague all battery types, and are likely the largest barrier

to utility adoption of this storage type (figure 2.2).

A possible solution to the cost and implementation problems facing energy

storage in the smart grid is the use of batteries in plug-in hybrid electric vehicles

12

Vanadium RFB

NaS Battery

PolysulfideBromide RFB

CAES

Cost ($/MW)

0 500 1000 1500 2000 2500 3000 3500 4000

Capital Costs Operating Costs

Figure 2.2: The estimated levelized costs of energy storage for 10 hour arbitrage (loadshifting) are quite high. With computational studies, it may be revealed, however,that these costs are outweighed by the benefits offered by energy storage. [19]

13

(PHEVs). Utilities have envisioned that PHEV owners will plug their vehicles in at

night to charge and, with the installation of public charging stations, will also likely

be plugged in during the day while at work. [2] In this scenario, since PHEV batteries

will be available to the grid for most non-commute hours during the weekdays, PHEVs

can essentially be viewed as energy storage for the cost of public charging points. [2]

Encouraging or requiring PHEV owners to participate in a program that uses the

batteries in their car in this way will require a significant shift in the way they interact

with their utility. Information regarding the utility’s and owner’s plans for how the

car’s batteries are used must be coordinated if each is to get what they want out of

the car. Further, the utility will have to provide some incentive for PHEV owners

to participate in such a program, as the utility’s use of the battery will probably

shorten its life and occasionally make it unavailable to the owner. [2] Since there are

few battery electric vehicles (BEVs) and PHEVs on the road today, it is difficult to

predict their popularity and how owners will use them. The logistics associated with

utilities sharing battery use with vehicle owners will, however, present a significant

challenge for utility system planning. [2]

2.3 Addressing Stochastic Renewable Generation in the Elec-tric Grid

Regardless of the integration challenges associated with PHEVs, it remains

unclear how or even whether energy storage is needed in the United States electric

grid. Though this work seeks to determine the optimal implementation of energy

storage, clearer qualitative trends might be apparent when examining the strategies

adopted by other nations that have already introduced significant renewable genera-

tion. There are several such countries that have significantly higher levels of installed

wind energy than the United States, which is highly variable, and hence, a driver

14

Figure 2.3: Denmark increased available thermal generation from 1985 (L) to 2008(R) using mostly small, flexible and efficient combined heat and power (CHP) facili-ties. This development was a key component in their plan to pursue aggressive windgeneration growth. [5]

15

for energy storage deployment. For example, 20% of Denmark’s generation mix is

wind energy. [20] That is planned to rise to 50% for all renewables, mostly wind,

by 2050. [21] Despite these ambitious targets, as shown in figure 2.3, Denmark does

not have domestic energy storage. They are able to avoid the expense of domestic

energy storage because of several key features of their electric generation and T&D

systems. As can be seen in figure 2.3, much of the power generated in the coun-

try is derived from small combined heat and power (CHP) facilities. These small

generating plants provide district heating to neighborhoods and also generate local

electricity. [20] These plants are new facilities that are efficient and responsive, so they

can be cycled throughout the day with minimal equipment reliability and performance

impacts. [21] Figure 2.3 also shows the geographic diversity of wind generation facil-

ities in Denmark, which ensures unexpected weather patterns are unlikely to affect

many locations at once. The use of offshore and onshore wind also provides further

balance, as weather conditions often differ between those locations. [21] Denmark

exploits its extensive interconnects with neighboring countries Germany, Sweden and

Norway to balance power generation. [20] Through these interconnects, they can take

advantage of pumped hydro energy storage in Norway and Sweden. [21] Collectively,

these features of their generation system provide the stability needed to extensively

integrate wind power.

Ireland is less ambitious than Denmark in its wind integration plans, but

has set goals similar to many US states RPS’ standards, summarized in table 2.1.

[22] Ireland plans to generate 20% of its power from wind by 2020. [23] Because of

its expense, Irish researchers have sought to avoid the need for energy storage. [22]

Notably, Ireland has only one small 400 MW high voltage DC interconnect with

Scotland [23] and it cannot be used to provide real-time support for sudden losses of

wind power. [22] As a point of reference for the interconnection, the Irish system is

16

nominally 9600 MW. [22] Ireland has a diverse group of flexible generating facilities,

much like Denmark, which help it cope with increasing wind power installations. [22]

Ireland is also aided by a diversity of wind power generation locations, which will

not all be affected simultaneously by changes in weather. [23] To counteract the

lack of storage, researchers have already explored optimization methods that exploit

Ireland’s flexible generation fleet and improved T&D infrastructure to ensure that

the government’s 20% wind power goal can be reached without the use of energy

storage. [22] This approach, however, yields a measurable emissions penalty over the

use of energy storage for ancillary services. [22]

Because the United States electric grid lacks some of the features of those in

Denmark and Ireland, it appears that similar wind energy penetration levels can be

reached without energy storage or significant emissions and operational cost conse-

quences. Although smart grid improvements to T&D infrastructure will help support

the increased presence of renewable energy generation, the national generation fleet

has not benefited from recent construction of many efficient, flexible generating units

as in Denmark. [3] The Irish system uses inefficient gas turbines to provide ancil-

lary services and accepts the environmental consequences of such an approach, while

Denmark depends on the availability of pumped hydro storage from Scandinavia.

American utilities could expand installation of peaking generating units like in Ire-

land, but domestic utilities might wish to retain the emissions benefits associated

with renewable generation even when those resources are not available. The optimal

quantities, locations and types of storage to use cannot be known without further

analysis. Given qualitative evidence of operational benefit, independent system oper-

ators (ISOs) are nonetheless interested in proceeding with energy storage testing [1].

Unfortunately, with sub-optimal implementation strategies, system operators and

utilities might determine that their results do not justify the cost. [2]

17

Apart from energy storage, smart grid technologies promise many operational

advantages for all organizations responsible for ensuring reliable, consistent power

delivery in the United States. Planned improvements to T&D infrastructure and

smart devices that enable customer interaction and increase awareness of their power

consumption will enable more dependable, secure and efficient power generation and

delivery. They will also enable more effective utilization of existing generation re-

sources and increased integration of new renewable generation sources. While these

advantages are well established, the optimal utilization of energy storage requires

significant further study. In particular, researchers must determine what parameters

determine when energy storage becomes a requirement for a given region, how much

storage should be used and where that storage should be placed. Additionally, utili-

ties will be interested in the potential for cost reductions associated with storage for

arbitrage or alternately, at what capital cost threshold energy storage for arbitrage

becomes a good investment. A modeling approach that will explore the potential

benefits and characterize the optimal allocation of energy storage will be revealed in

subsequent chapters.

18

Chapter 3

Unit Commitment Modeling Theory

3.1 Unit Commitment Modeling for Future Scenarios withEnergy Storage

Unit commitment for an electricity generation system combines optimal eco-

nomic dispatch with forward-looking generator startup and shutdown to determine

which electricity generating units should be operating and at what level (in MW) for

every time step in a model. [24] Economic dispatch is the allocation of power from

each unit in a utility’s fleet of generators to minimize cost, maximize profit or achieve

some other operational objective(s) and occurs at each time step during the modeled

period. [24] Unit commitment is a common approach for electric power generator

scheduling [25], and basic models can serve as a foundation for exploring a variety of

specific system interactions and provide valuable future planning insight for system

operators, independent power producers, electric utilities and other market partici-

pants. [26] For example, unit commitment models can enable study of the effects of

deregulation or market restructuring, the introduction of new markets (e.g., a sepa-

rate market for ancillary services) or market rules, other market design changes, or

prediction of bidding strategies of participants in day-ahead and balancing markets

(as in ERCOT or other ISO systems). [27]

Other researchers have already applied unit commitment to study the effect of

energy storage on dispatch and the operation of generation systems, but their interests

have primarily focused on pairing an energy storage device with wind generation

19

to address intermittency or to explore the potential benefits of using PHEVs for

energy storage. [7, 28–30] This study applies unit commitment more broadly to the

allocation of energy storage, as opposed to specifically improving the performance of a

renewable generating facility or studying the effect of only one type of energy storage.

Austin Energy plans to introduce a sizable fleet of renewable generation, particularly

wind power, in the next decade. Significant emissions reductions, capacity factor

improvements and potential reductions in operating costs might be gained with the

availability of energy storage, but these benefits are unknown and existing studies do

not quantify overall improvements in system operation with energy storage. As unit

commitment methods are useful for studying future operational scenarios, they are

applied here to the exploration of the role energy storage could provide as part of

Austin Energy’s future generation plans.

While unit commitment is a well-established method for modeling electric

power generation systems and provides a suitable foundation for modeling future

scenarios, some limitations arise when examining energy storage. The ability of a

unit commitment model to predict the operation of some future generation assets or

the impact of a change in market rules is dependent on the selection of an appropriate

model and time step length. If careful consideration is not given at this stage, the

model’s results might give a solution implied by the selected time scales. For example,

if a model intended to examine some transient behavior has time steps that are too

long, it might fail to capture the feature of interest, giving results suggesting the

phenomenon does not occur or is insignificant. While this problem might appear

easily avoided by using appropriately short time steps, computational constraints

might limit the feasible number of time steps if the model length is many orders of

magnitude larger than the step. At the same time, some models might require long

time horizons to capture variations in demand or renewable resource availability over

20

seasonal time scales.

A unit commitment model could have a time horizon of only 24 hours or as

long as is desired for planning purposes, and the modeled period can be broken into

as many segments as is appropriate for the goals of the model. Typically, shorter

time steps are appropriate for examining impacts on system reliability, while longer

time steps are best for long-term planning. For a given model length, shorter time

steps increase computational cost significantly and yield minimal benefit in generator

commitment or dispatch if long-term planning is the primary goal. Table 3.1 makes

clear the computational challenges posed by models that are extremely large. With

a full year model period and 15 minute time steps, each of these model cases has

at least 10 million undetermined variables, “non-zeroes,” that must be selected for

optimality by the solver. Adding constraints to accurately model system constraints

introduces more variables and makes the problem harder to solve. The case of generic

storage selection that required only eight hours to run was aided by the generic storage

variable that could provide any necessary ramping to store power from or return power

to the grid, making the operational constraint equations for thermal generators easier

to satisfy. In all other model cases, relative inflexibility in the plants available to the

system makes finding a feasible and definitively optimal solution is a slow process.

Further, the significant computing power used to solve these models, discussed in

greater detail in section 4.1, is still not readily accessible by most researchers, despite

the reductions in cost and increases in speed and memory size over the development

period of unit commitment models. Given these challenges, appropriate decisions

about what time length time steps and total model period are needed to balance

computational time and resource requirements while including sufficient resolution to

capture features of interest and avoid misleading results.

21

Tab

le3.

1:P

aram

eter

san

dop

tion

sap

plied

for

each

model

run

typic

ally

sugg

est

model

runti

mes

,w

her

efu

llye

ar(F

Y)

model

sre

quir

esi

gnifi

cantl

ylo

nge

rti

mes

than

singl

eday

model

s,ev

enw

ith

acce

ssto

grea

ter

com

puta

tion

alre

sourc

es.

(Furt

her

info

rmat

ion

rega

rdin

gth

edet

ails

ofea

chm

odel

run

isgi

ven

inA

pp

endix

A)

Model

Cas

eSol

uti

onT

ime

Rol

ling

Pla

nnin

g?N

on-z

eroes

Iter

atio

ns

Opti

mal

ity

Cri

teri

on(%

)T

ime

Lim

it(s

)It

erat

ion

Lim

it

2020

Mon

ths

3m�

No

29,1

5315

00�

0.1

1000

2,00

0,00

0

2008

w/o

Sto

rage

,F

Y†

unk.

Yes

nz

iter

0.00

177

7,60

01,

000,

000,

000

2020

w/o

Sto

rage

,F

Y†

51h,

49m

Yes

10,7

16,3

3132

8,59

00.

001

777,

600

1,00

0,00

0,00

0

2020

w/

Sto

rage

,F

Y‡

8h,

12m

No

11,5

94,7

1990

0,85

00.

0001

777,

600

1,00

0,00

0,00

0

2020

w/

Dis

cret

e,F

Y†

98h,

16m

No

13,7

02,8

832,

207,

528

0.00

1*25

9,20

01,

000,

000,

000

2020

w/

Lim

ited

,F

Y†

4h21

mN

o13

,702

,883

1,76

3,05

10.

0135

0,00

01,

000,

000,

000

2020

w/

Em

issi

ons,

FY†

72h–2

17h

No

11,8

40,6

711,

100,

000–

3,50

0,00

0*0.

001

777,

600

1,00

0,00

0,00

0

†T

his

case

was

run

wit

hG

AM

S/C

PL

EX

op

tion

sn

odefi

lein

dat

3an

dw

ork

mem

of

8192

meg

abyte

s.S

eeA

pp

end

ixA

for

det

ail

s.‡

Th

isca

sew

asru

nw

ith

work

mem

of10

24

meg

abyte

s.S

eeA

pp

end

ixA

for

det

ail

s.*

Did

not

full

yco

nver

ged

ue

tore

sou

rce

lim

its.

�A

pp

roxim

ate

valu

es

22

Given the computational requirements associated with lengthy or large system

models, it might appear that applying a heuristic solution approach, one based on

typical historical generator dispatch, could serve as a simplified substitute for unit

commitment modeling. Such heuristic methods were popular when computational

resources were expensive and limited, but this approach dictates the solution space

and limits the ability of the user to capture any operational objective outside that

which defined the original heuristic. [31] With the availability of robust optimiza-

tion tools and solvers and ample computational capability, unit commitment enables

flexible modeling of a variety of scenarios without heuristics. [32] It also avoids the

presupposition that a modeled future scenario will operate in a manner consistent

with historical empirical data and reduces the risk that assumptions used to build a

heuristic will unintentionally promote particular outcomes.

While, in theory, heuristics could be used to solve unit commitment problems,

as discussed previously, applying heuristics to these systems might yield misleading

solutions. As a result, optimization techniques are well-suited to unit commitment.

Unit commitment could be considered part of a class of problems that involve system

scheduling and planning or resource allocation. While optimization has been used to

solve unit commitment problems with varying levels of success since at least a half

century ago [24], similar problems have been studied in conjunction with optimization

methods for at least as long, providing additional opportunities for the discovery of

improved solution methods. Many practical problems have similar formulations to

unit commitment problems for power generation, such as river flow management

systems or networks, traffic flow study, manufacturing plant operations and product

distribution systems. As a result, there exists a rich operations research literature on

these problems. [25] In some cases, this work might even be combined, where river

flow management and significant quantities of hydro generation (as in the northwest

23

United States or Brazil) might be studied with unit commitment of other generators

to model a complete power generation system. [32] These previous studies provide

meaningful guidance to future work studying novel systems with unit commitment.

3.2 Previous Unit Commitment Modeling Efforts

Modeling of power generation systems using a unit commitment approach be-

gan more than 50 years ago, around the time mathematical computing resources

became available to a limited number of large research institutions. [33] Because of

the potential complexity inherent in meaningful modeling of any sizable fleet of gener-

ating units over a time horizon of more than a few hours, the availability of computers

was pivotal to the use of unit commitment methods. [33] Extremely expensive com-

puting resources with limited capabilities significantly limited the size and complexity

of viable models. [33] Typically, the method of Lagrange multipliers or Lagrangian

relaxation was used to reduce computational requirements. [33] Lagrangian relaxation

is a necessary condition of optimality that moves inequality constraints into the ob-

jective function, creating a new objective that acts as a lower bound on the solution

space of the original problem. [33] Despite extraordinary computational limitations,

development of unit commitment models were immediately undertaken to study op-

timal electricity generation systems because of the staggering cost savings that could

be derived from even small improvements in dispatch decisions. [24] These historical

developments form the foundation for the unit commitment modeling formulation

presented in section 4.3.

Muckstadt and Koenig [24] developed a relatively complete unit commitment

model that captures many of the constraints required to model thermal generators.

Their model includes production, startup and shutdown costs, reserve allocation,

24

as well as transmission constraints, included through quantification of transmission

limitations as incremental production costs so that a new cost type need not be

introduced. [24] While computational limitations constrained their ability to model

extended periods, the authors identified 24 hours as the required minimum period to

capture the changes in unit commitment between low demand early morning hours

and peak demand during the late afternoon. [24] They also chose to attempt modeling

in two hour increments, more than previous authors had succeeded in modeling. [24]

To model what was at the time a very large system, Muckstadt and Koenig

employed a novel approach to Lagrangian relaxation by applying the relaxation across

generators. Previous work from Muckstadt and other authors avoided decomposition

using Lagrangian relaxation, which sometimes resulted in algorithms that were un-

able to find feasible solutions, or applied decomposition across time steps, which made

finding a feasible solution challenging since the main motivation of unit commitment

is to reveal economic dispatch decisions made with respect to constraints across many

time steps. Applying optimal economic dispatch where discrete time steps are not

connected limits the model’s value by eliminating its ability to plan for future changes.

For example, as demand increases during daytime hours, additional generating units

might need to be brought online to meet future demand, but making these units

available at appropriate levels during rising demand might require bringing them on-

line before they are strictly needed. [24] To accommodate the initial activation of a

generating asset at its minimum load, other units might need to be dialed back from

optimal generating levels for a short period. Because performing economic dispatch at

discrete time steps does not capture planning that requires knowledge or forecasting

beyond the current time step, it cannot appropriately model commitment of thermal

generating units. [24] Though such an approach might provide computational cost

benefits, startup and shut down penalties, up and down ramp rates, and responsive

25

(spinning) reserve, which can only be included in full unit commitment models, are

important components of thermal generator operation and should not be ignored. [26]

Recognizing the importance of temporal constraints between time increments moti-

vated the authors’ approach of decomposition of generating units. The decomposed

subproblems were solved using dynamic programming, followed by a final branch-and-

bound method to yield the optimal feasible solution. While this simplifying solution

approach is not employed in models developed here, Muckstadt and Koenig’s recog-

nition of capturing constraints across time periods remains an important component

of unit commitment modeling. [34,35]

Even with these aggressive decomposition approaches, limited computational

power meant the use of mixed-integer programs (MIP) for unit commitment was still

out of reach for problems of a meaningful size — more than about 12 time steps

and 15 generating units. [24] Further, for problems with more than ten generators

and ten time steps, convergence to a value of less than 0.5% was not achievable with

reasonable computational expense. [24] Despite these limitations, for more than two

subsequent decades, while computational resources remained a binding constraint,

the approach applied here defined the mathematical decomposition methods applied

to unit commitment models. [24]

Subsequent work on unit commitment models applied the basic decomposition

approach developed by Muckstadt and Koenig but modified the approach to empha-

size a feature or capture a particular constraint of interest. Zhuang and Galiana [35]

developed a heuristic approach to fully capture all types of reserve power require-

ments for a typical system. To explore the effect of ramp rates, not discussed by

Muckstadt and Koenig as an operating constraint on thermal generators, Wang and

Shahidehpour departed from Muckstadt and Koenig’s solution approach, favoring a

26

novel artificial neural networks approach to find optimal but infeasible solutions and

then using heuristics to search locally for a feasible solution. [31] With an improved

decomposition approach and greater computing power, Bard [34] was able to examine

a much larger problem than Muckstadt and Koenig, up to 100 generators and 48 time

periods, without the need for a branch-and-bound approach to find a feasible result

from the dual problem. He also examined the effect of including generator ramping

constraints. [34]

Following the work of these and other authors, Baldick [26] developed a unit

commitment approach capturing in one model all of the constraints relevant to the

unit commitment problem. Like many of his predecessors, Baldick continued to use

the solution approach originally proposed by Muckstadt and Koenig while also lever-

aging lessons from the literature to structure the problem and decomposition to speed

solution times. [26] The emphasis of this paper, however, was on the development of

a generalized unit commitment approach, including thermal generator startup and

shutdown costs, minimum up and down times, ramp rate limits, reserve power avail-

ability, fuel and energy limits, power flow limits, line flow (transmission) constraints

and voltage requirements, along with the scheduling of hydroelectric generation. [26]

Since this formulation captures most significant operational constraints, it largely

parallels the model developed in section 4.3. The inclusion of hydroelectric genera-

tion in the unit commitment problem was an improvement specifically identified by

Muckstadt and Koenig for future workers. [24, 36] While the author still depends on

Lagrangian relaxation to find feasible solutions, sufficient computational resources

were available to solve a problem of reasonable size (10 generators and 24 periods)

with nearly all of these constraints included. [26] Further, the author indicates mod-

els that selectively exclude constraints will likely yield suboptimal solutions, though

the final model presented neglects power flow and voltage requirements. [26] Based

27

on this conclusion, the model presented here attempts to capture all major thermal

generator operational constraints.

Beyond these workers, despite the increasing availability of sufficient computa-

tional resources to solve full MIP models, capturing all operational limitations without

simplification or decomposition strategies, many authors continued to pursue alterna-

tive strategies, testing models with incomplete constraints. [25] While these research

pursuits often led to robust, efficient solution methods, the availability of greater

computing power has meant many of these approaches are no longer necessary and

their incomplete models are less than desirable. Baldick’s note to future researchers

regarding the problems with results from incomplete models did not halt their pro-

liferation and led to repetition of his admonition in later work. [26] Goransson and

Johansson identified several articles by other authors that ignored some constraints

in the interest of expediency. [20] Goransson and Johansson revealed that the inclu-

sion of minimum load level, startup time and startup costs yield a unit commitment

model that better predicts operating costs when compared to models excluding those

parameters. [20] In their study area, western Denmark, complete modeling of plant

operating constraints increases operating costs and emissions by as much as 5%, in

addition to increasing import and export quantities from neighboring countries. [20]

Following the contributions from and outcomes of these researchers’ work, here a MIP

model is developed that is as complete as is required to capture all costs relevant to an

electric utility, avoiding the explicit use of decomposition strategies and heuristics and

depending instead on the solver to select those strategies that will yield optimality

given the inclusion of all constraints.

28

3.3 Stochastic Programming and Unit Commitment

With the proliferation of powerful and inexpensive computing resources, unit

commitment models have continued to move toward greater accuracy, capturing all

readily modeled system capabilities and operational constraints. Now that large de-

terministic models, with hundreds of generators for thousands of time steps, can be

solved easily, interest has turned towards stochastic modeling of system components

formerly idealized as deterministic. The components of greatest interest are demand,

which was historically the sole major stochastic element in the electricity system mod-

els, and wind generation, which is subject to significant variability and is of recent

interest. As a result, a significant body of contemporary work on unit commitment

has applied stochastic programming methods to determine the effect that modeling

systems as stochastic instead of deterministic has on the response of that system. [37]

Stochastic programming could be important in creating a unit commitment model

of Austin Energy’s future generating mix since wind energy forms such a significant

component of the total generation mix, as shown in table 4.1. Further, using stochas-

tic programming to represent wind energy could increase the quantitative savings

from energy storage in the model results, as energy storage can serve to moderate

variability in the grid.

Many researchers have independently pursued the modeling of stochastic ele-

ments in unit commitment problems, leading to a variety of approaches to modeling

stochasticity, however, scenario-based methods appear to be preferred by most au-

thors. [22, 37, 38] Stochastic elements are typically modeled by generating scenario

trees, as in figure 3.1, based on historical data. Monte Carlo-based methods, such

as Markov chains, have been used by some authors to cope with large quantities of

historical data. [22] If scenario generation demands or historical data are more limited

29

Figure 3.1: In a scenario tree, the number of nodes, and hence, number of paths,increases exponentially as the depth of the tree increases. [39]

or the scenario tree is shallow, simpler methods may be employed. [38]

The method used to create scenarios in a structure such as figure 3.1 is con-

ceptually similar to that used by Watkins et al. [38] and Kracman et al. [40]; both

authors generate scenario trees based on historical inflow data for a watershed. The

number of branches from each node of the tree and the overall depth of the tree

were preselected by the researchers to manage tree size, and hence, computational

requirements. [38] These historical data were sorted by magnitude and then separated

into segments based on the number of branches from the first node. [40] Then, each

segment of data was again sorted by magnitude and split based on the predetermined

number of branches. This process continued until all the planned branches had been

filled. [40] With a completed tree, the authors assume the probability of every path

is equal. Approaches explored in [22, 41] may be applied to construction of these

30

scenario trees, where each terminal (leaf) node has a defined path to the root node

and each of those paths has a probability that can be estimated based on historical

data, rather than assuming all scenarios have equal probability.

Applying stochastic modeling of system elements requires restructuring of the

unit commitment model from a deterministic predecessor. If using a scenario tree,

model equations with the terms of interest (e.g. load, wind generation) must be

multiplied by a probability variable. The model is then solved as before, with the

probability and values of each path from the scenario tree inserted where appropri-

ate. Both Tuohy et al. [22] and Watkins et al. [38] show clear examples of where

these terms appear in unit commitment model equations. Unfortunately, while this

stochastic programming approach is easily implemented from a deterministic basis,

it presents a significant computational challenge. [22] If the formulation were solved

deterministically, it would be equivalent to solving the problem for one particular

scenario. [22] For every additional scenario, the model must be run again. [22] There

are some simplifications solvers can apply to reduce solution time once the problem

has been run once, but the additional computational time required for scenario tree-

based stochastic models is inevitably much greater than with equivalent deterministic

systems. [22]

Initial applications of stochastic programming to unit commitment focused

on demand, which has always been an only moderately predictable element utilities

accommodate in their generation planning. [42] Recent interest in reducing the envi-

ronmental impact of electricity generation has yielded extensions of these models to

capture stochastic sources of renewable power. [42] Tuohy et al. [22] built upon the

stochastic unit commitment model developed by Barth et al. [43] to model stochastic

load and wind generation. Both implemented rolling planning, where the probabil-

31

ity of a certain outcome increases as it approaches the present modeled time and

‘knowledge’ of that period improves. Pappala et al. [44] developed a similar model

using a particle swarm optimization-based scenario generation and artificial neural

network solution approach, similar to Shahidehpour and Wang [31], instead of the

more common scenario tree method. All three models were developed with an em-

phasis on determining the effects of significant wind penetration, greater than 20%

of total generation, on the operation of fossil fuel-based generating units in the sys-

tem. While it would appear that such an analysis would be of significant interest

here, compensating for the uncertainties associated with stochastic elements in a unit

commitment model increases the commitment of mid-merit and peaking generators.

This change in commitment requirements yields minimal benefit and required solu-

tion runtimes as long as eight days. [22] Pappala et al. found increases in predicted

operational costs and improvements in schedule quality based on increased system

resiliency of 2-4%. [44] In a similar study, Tuohy et al. found improvements of less

than 1%. [22] Despite contemporary availability of significant computational power

and the anticipated improvements in unit commitment and dispatch resiliency associ-

ated with stochastic modeling, the minimal improvement realized with these methods

does not appear to merit required computational resources.

3.4 Grid-connected Energy Storage

With the rapid growth of stochastic renewable energy generation in the past

decade, energy system modeling efforts have focused not only on applying stochastic

programming methods to capture those effects but also on modeling the potential

benefit of energy storage for compensation. Some analyses of energy storage forgo

the creation of a complete unit commitment model, using commercially available

software packages or readily available data provided by ISOs or other market opera-

32

tors. [7, 45–48] Because the utilization of energy storage in the electric grid has only

received recent attention and no public, widely available empirical data exist from

what limited energy storage tests have taken place in the United States, potential

applications, siting and of energy storage are only partially characterized. Further, a

wide range of analytical approaches from various authors have provided meaningful

results for a specific circumstance of interest. Thus, these studies have often intro-

duced approaches that are not easily replicated and might only be useful in examining

the particular storage function or capability of interest to the authors. As a result,

there remain many opportunities to characterize the potential applications and ben-

efits, if they exist, of energy storage in the electric grid. The study performed here

will apply established unit commitment approaches for thermal generation previously

explored in section 3.2 to reveal the optimal use of energy storage.

Early studies of energy storage were concerned primarily with role of storage in

the market, examining the functions it serves best — ancillary services and regulation

or arbitrage — while ignoring costs, and in some studies, determining when it is

cost effective to provide that service. Since cost is a primary barrier to storage

implementation, its best function is of significant interest, as the appropriate use of

storage will determine its future implementation. Without any prior study of which

storage technologies might provide the greatest benefit, analysis of many available

technologies revealed that storage for ancillary services was likely cost effective, given

the low cost of small quantities of storage and the sometimes high prices paid for

these services. [45] Primarily as a result of high storage capital costs across all major

technologies, early analysis of arbitrage did not appear cost effective with minimal

wind generation and low electricity prices. [45] At the same time, several authors

pointed to arbitrage as a much more beneficial function for storage, particularly with

high levels (greater than 20%) of wind generation or high energy prices, if capital

33

costs could be managed. [45,46,49] Studies that ignored storage capital costs favored

arbitrage. [46] A few have noted that optimal application of storage for arbitrage

would be impossible for an operator to achieve in a real electricity market because

it is impossible to predict future prices, however, Lund et al. [46] propose a few

strategies to achieve near-optimal results. It should be noted that these methods

could be implemented by a utility operating energy storage for aribtrage, but further

exploration of computational approaches to accurately predict future electricity prices

are beyond the scope of this work.

Beyond this early work, the primary storage application of interest to most

authors was price arbitrage, as larger storage facilities can likely also provide ancil-

lary services. Small-device arbitrage, where energy storage acts as a price-taker and

takes advantage of the large price differences between nighttime and peak periods,

as mentioned previously, could be profitable if future market conditions change. [47]

Increasing quantities of storage will diminish the difference between peak and off-peak

prices, reducing the marginal benefit to the operator of further increases in storage

availability. Large quantities of storage might be able to provide other benefits, such

as improved utilization of existing T&D resources, congestion management and de-

ferral of capital investments in generation and T&D. [48] Regardless of the size of

available storage, round-trip efficiency has a significant impact on the value of stor-

age. Compromising efficiency to reduce costs is of significant detriment to the value

of the stored energy and thus, of the arbitrage effectiveness. [47, 48]

In large quantities, energy storage could provide sufficient capacity to make

wind or other renewable generation into a dispatchable or “firm” resource, much like

a thermal generator. With current energy and storage prices, such large quantities of

storage are cost-prohibitive. In the future, however, market changes might promote

34

such a use of energy storage. Without carbon pricing, comparing the generation of

baseload power from natural gas, wind with natural gas support or wind with CAES

support, the combination of wind and CAES has the highest levelized cost. At carbon

prices in excess of $35/ton of carbon (not CO2), Greenblatt et al. [50] find that wind

and CAES combined generation is price competitive with coal generation. If other

energy prices increase or the cost of wind turbines and CAES facilities decrease, lower

carbon prices might yield a similar result. [50] Further, the presence of energy storage

transforms wind into a dispatchable resource and enables wind capacity factors of

greater than 80% by storing wind when it cannot be used and dispatching it when

needed. [50] For baseload generation, this approach promotes the construction of

wind generation and energy storage far beyond the capacity of available transmission

to ensure continuous use of all transmission capacity. [50] A baseload generation

application of wind power requires the collocation of wind and storage, but the optimal

siting of storage for non-baseload power was not addressed by Greenblatt et al. [50]

The optimal location of storage is of significant interest, as storage might be

better able to make renewable generation dispatchable when it is collocated with the

generation instead of being located at the load, as some authors (and this work) as-

sume will occur. [50] While early studies identified binding transmission constraints as

a potential problem with energy storage collocated with wind generation, few studies

have determined what effect transmission constraints and other system limitations

would have on the sizing and effectiveness of storage. [45] In contrast to Greenblatt

et al. [50], where the author’s objective was to provide firm wind for baseload power,

Denholm and Sioshansi [7] find that when collocating storage with wind, less than

25% of the wind farm’s capacity should be provided as storage. Broadly, improved

utilization of transmission capacity at high transmission costs might warrant energy

storage, but sizing and revenue might vary depending on the particular transmission

35

corridor. [7] In examining the arbitrage value of storage specifically, the locational

value of storage at various nodes in the Pennsylvania-New Jersey-Maryland intercon-

nection (PJM) were found to vary by as much as 25%, dependent on transmission

constraints, storage efficiency and energy prices. Storage participation in the ancil-

lary services market, while currently restricted in PJM, could increase the variation

and magnitude of revenue from energy storage significantly. [48]

Beyond conventional stationary energy storage, PHEVs have recently been

of significant interest because, if popular, they are a possible source of free or low-

cost energy storage for regulation and arbitrage. Depending on the primary focus of

the study — consumers or operators and minimizing emissions, profits or costs —

conclusions about the value of vehicle-to-grid (V2G) services from PHEVs vary widely.

[28–30] Sioshansi and Denholm [28] created a unit commitment model of ERCOT to

focus on the emissions benefits associated with V2G services. For simplification,

they assumed PHEVs would always be plugged in for hour increments starting on

the hour and that PHEVs would always be plugged in when not in use. These

assumptions enable PHEV participation in ancillary services markets, which might

be of significant value during peak hours. Other studies have revealed that the use

of LiFePO4 batteries, as in PHEVs, for V2G energy results in less than half the

capacity loss of driving and that there is minimal capacity loss associated with deep

discharge. [29] These results suggest the use of PHEV batteries for ancillary services

instead of arbitrage will not extend battery lifetimes but might limit profits. Further,

Peterson et al. [30] found that it is unlikely that PHEVs can be used for ancillary

services since their availability during peak hours, when ancillary service market prices

are highest, will be limited. The authors estimate that less than 5% of PHEVs will

likely be available for ancillary services.

36

If the use of PHEVs for arbitrage grows, as in Sioshansi et al., the difference

between peak and off-peak prices will be limited and PHEVs participation in the

ancillary service market might be limited, the value of V2G services to vehicle owners

will be limited. [48] Assuming battery replacement costs are paid by the utility, annual

vehicle owner profits from V2G services will likely be around $200. If vehicle owners

are forced to provide V2G services by their utility at the owner’s expense, annual

profit will likely fall to less than $100 due to battery replacement costs. [29,30] These

results suggest that V2G incentives are too limited to promote widespread adoption.

The potential role of PHEVs on the grid, however, is examined here on a limited

basis.

37

Chapter 4

Unit Commitment Modeling with Storage

4.1 Methodology

As discussed in chapter 3, unit commitment methods have been applied by

many authors to explore the effects of modifications to the electric grid. [25] I will

examine the role energy storage can play in the electric grid to minimize total op-

erating costs and costs with respect to NOx and CO2 emissions, similar to models

developed by Sioshansi and Denholm [28] to study possible cost, reliability and emis-

sions benefits from PHEV V2G technology. This analysis uses a MIP approach, which

facilitates representation of complex thermal generator operational constraints, such

as minimum load level, startup costs and shutdown costs. It does not capture non-

linear heat rates or emissions characteristic of thermal generators. Modeling these

non-linearities is avoided because of the complexity they introduce.

In the early stages of model development, MATLAB was used with its opti-

mization toolbox. but due to toolbox limitations, MATLAB was ultimately replaced

with a more robust optimization program. MATLAB is fast and convenient when

solving linear programs (LPs) but, because of the way MATLAB functions handle

constraint data, the optimization functions were limited in their ability to model

semi-continuous, binary and integer variables. Since modern unit commitment mod-

els are almost exclusively MIPs, without additional third-party packages, MATLAB

could not handle realistic constraints on thermal generator operation. To overcome

these limits, the model was rewritten using the General Algebraic Modeling System

38

(GAMS), a program designed specifically for solving optimization problems. As will

be explored further in section 4.3, GAMS offers significant convenience by provid-

ing simple methods for the introduction of major model components — parameters,

vectors of operating constraints; and variables — and the declaration of equations

with straightforward, intuitive notation. GAMS transforms user inputs in this form

into the objective and constraint equations that an appropriate solver will accept as

inputs. This framework does not constrain the type of model to be solved, number

of constraints, length of time steps or total number of time steps.

Because GAMS is a well-established tool for optimization studies, for every

problem type, there exist several solvers that can be used. While many solvers are

available, it is outside of the scope of this work to explore the performance of each

one. Instead, I have chosen to employ CPLEX, a linear and mixed-integer program

solver developed by IBM ILOG that provided robust solutions for the MIP problems

solved here.

Initial work in MATLAB was performed using an Apple PowerBook G4 1.33

GHz with 2GB RAM running Mac OS X 10.5.7 and MATLAB R2009a. For prelimi-

nary implementation in GAMS, the only available license was for Microsoft Windows.

This initial work was performed on an Apple MacBook Pro 2.53 GHz Intel Core 2 Duo

with 4GB RAM running Mac OS X 10.6.3 and Windows 7 Professional running na-

tively in Apple Boot Camp or virtualized using VMware Fusion 3.0.2. Initial models

examined a 24-hour dispatch window in 15-minute time increments. Because GAMS

stores a significant portion of data for the solver in the computer’s physical memory

(RAM) to speed repeated computations, when the dispatch window was extended and

model functionality expanded, physical memory limits became a binding constraint

on model size. As a result, the model was slightly modified to run on The University

39

of Texas at Austin Mechanical Engineering department’s high performance comput-

ing (HPC) cluster. The HPC is a system of eleven rack-mounted Dell Poweredge 2950

workstations running Ubuntu Linux, each with two dual-core, hyper-threading 3.73

GHz Intel Xeon processors and 24 GB of shared RAM. The vast hard drive storage,

physical memory and processor power available on the HPC enabled problem sizes as

large as one year in 15-minute increments, or 35136 time steps. Even larger problems

could be solved if they were of interest, particularly with the use of more advanced

decomposition techniques, such as rolling planning. [22] Visualization of all results

were completed entirely on the Apple MacBook Pro in the Mac OS using R version

2.19 and the R GUI version 1.31. [51]

Initial models used to test the operation of new constraints studied only a 24-

hour dispatch window in 15-minute time increments. These preliminary results from

building the model in GAMS are presented in section 5.1. Once constraint equations

and output were tested in this arrangement, the model was changed to study dispatch

for a full year and, since GAMS is highly flexible, minimal modifications to GDX (a

proprietary input/output file format used by GAMS) files were the only changes

required. Major results presented in sections 5.2 and 5.3 examine a full year of

demand, as in Tuohy et al. [22] Modeling such a long time period ensures that seasonal

variations in the optimal allocation of energy storage will be fully characterized.

Because of the length of a full year unit commitment model, 15-minute time steps

are used for optimal economic dispatch to manage computational requirements. The

choice of time step size is extremely important. Time steps that are larger than a

few minutes might predispose the model to optimal outcomes that suggest storage

for arbitrage only, since temporal resolution is insufficient to capture ancillary service

provision. In its current form, the model can indicate whether and how much storage

can provide arbitrage benefit. Unfortunately, 15-minute time steps provide insufficient

40

resolution to model the use of storage to improve system reliability or provide ancillary

services, which are areas where storage has been predicted to be useful. [7, 28, 47]

Minute-by-minute demand and wind generation data would be required to study

the effect of energy storage on system reliability, but such a model for a full year

would be so large that it would be beyond the practical capabilities of even the best

commercial MIP solvers. As a result, longer time steps to enable modeling of a full

year period have been chosen in the interest of finding an optimal level of energy

storage for general system operation. It is likely that some limited regulation for

system reliability could nonetheless be provided by an arbitrage-optimized storage

system.

Early models, both those with 24-hour and full-year dispatch, used exclusively

marginal cost objective functions. These results are presented in sections 5.1 through

5.3. The last set, in section 5.3, includes emissions cost minimization objectives with

linear emissions rates and varying emissions prices. These approaches proceed toward

improving representation of real system constraints and limitations, where the final

set in section 5.3 represent some future scenario where emissions pricing might affect

dispatch decisions and economic value of storage. In unit commitment models like

these, profit maximization is a reasonable alternate approach for treating operating

costs. Such an approach, however, is avoided here. While the marginal cost for the

last (most expensive) unit dispatched could be used as a proxy for the market price

of electricity, enabling a profit maximization model, it would not necessarily provide

the most accurate representation of market prices in all time periods. Because the

ERCOT market, where prices are set for most of Texas, has a variety of generators,

the generators that are marginal (price-setting) from Austin Energy’s fleet for every

modeled time step might not closely represent the costs for ERCOT’s marginal gener-

ator(s). Further, during periods of scarcity, when limited excess capacity is available,

41

particularly during the early evening hours of the summer months, prices based on

marginal costs might fail to capture the effects of limited available capacity in the

system and might thus significantly underestimate market prices.

The selection of appropriate objective functions is critical to the value of results

generated by the model. Constraints governing the operation of thermal generators

are, however, also important to ensure that results that satisfy the objective are also

consistent with real system limitations. In the interest of modeling realistic thermal

generator limitations, the model developed here includes most of the critical elements

identified by Baldick [26] and often omitted by other authors. [25] Thermal genera-

tor constraints include up and down ramp rates (MW/min), minimum startup and

shutdown levels (MW), generator nameplate capacity (MW), startup costs, and pro-

vision of spinning reserves. I have neglected minimum generator up- and down-times,

commonly included in unit commitment models, since the inclusion of startup costs

in the objective function should prevent repeated on/off cycling of all generators ex-

cept simple-cycle gas turbines, which are designed for frequent startup and shutdown.

Without further data regarding generator minimum up- and down-times, results in

chapter 5 suggest that generator startups are well controlled. These constraints pro-

vide for complete modeling of typical physical operation of thermal generators. Elec-

trical system constraints — reactive power and voltage regulation and support —

are ignored. Most authors neglect these constraints with no apparent detriment to

commitment and dispatch decisions. [26] Forced and scheduled generator outages are

also ignored, which will yield overprediction of dispatch of some generators during

some periods, but these should balance out through the year as all units compensate

for other generator outages.

Apart from these system constraints, transmission constraints are also ignored,

42

because the focus of the analysis is on Austin Energy’s own generation. While some

authors have included transmission constraints, they have been left as future work

here. [52–54] The transition from a zonal to a nodal market structure in ERCOT

will discretize links between major generators and load centers in the operation of

the market. This change will facilitate increased representation of transmission con-

straints in the market, which will likely lead to increased prices where demand for

access to transmission and hence, transmission congestion, is highest. It is unclear

whether these additional costs will impose significant effects on commitment decisions

by Austin Energy in the future. When the market transition is completed, further

analysis will be warranted. Also, a study of Austin Energy within ERCOT will en-

able the inclusion of these transmission effects, as well as an examination of profit

maximization objective functions.

There exist several other model components explored in chapter 3 that are

ignored here, either because they are not applicable to Austin Energy’s generating

units or because they are not anticipated to provide significant benefit or improvement

in commitment and dispatch decisions. As emphasized by Baldick [26], hydroelectric

generator scheduling is an important model component in those systems where hydro-

electric units are a significant percentage of the generator fleet. Since Austin Energy

does not have any hydroelectric generation in its fleet, scheduling of that generator

type is ignored. [3] Operational effects addressed by other authors include the appli-

cation of stochastic programming to wind and demand variability in an attempt to

improve the accuracy of their unit commitment and economic dispatch decisions. [22]

As discussed in section 3.3, various authors found no more than a 4% improvement

in dispatch and schedule decisions. [22,37,44,55] The authors of the study that most

closely parallels the work presented here found an improvement in costs of less than

1%. [22] While including stochastic modeling of wind and demand yields limited

43

improvement in results, it significantly increases the computational expense of the

model, so it is neglected here.

The development of a complete unit commitment model of Austin Energy’s

thermal generating fleet was done in the interest of studying the role that energy

storage can play in that system. Thus, energy storage was initially included in the

model by simply adding another unit to the list of thermal generators in Austin En-

ergy’s fleet, where that generator had zero marginal costs and virtually unconstrained

ramp rates and ‘nameplate capacity.’ This approach does not capture storage effi-

ciency, but it also does not require predetermination of available storage types. This

zero-cost, 100% efficiency case provides an upper bound on the application of energy

storage for arbitrage in Austin Energy’s system. Some models presented in section

5.2 include a more robust representation of storage that uses a selection approach to

determine the best type(s) from some set of possible storage devices. These devices

are constrained by maximum storage and withdrawal (MW), up and down ramp rates

(MW/min), and total capacity (MWh), and include round-trip efficiency, fixed and

variable marginal costs. These data, for each available storage type, are provided in

table 4.3.

4.2 Supporting Data

For the constraints detailed in section 4.1 to be effective in a unit commitment

model, data about the capabilities of thermal generating units must be provided. To

generate meaningful results, a real system must be described by these constraints,

hence the use of Austin Energy’s fleet for the model. Thanks to the generosity and

cooperation of Austin Energy, I was able to obtain the data required to capture these

constraints. Table 4.1 includes all the supporting data required to describe Austin

44

Energy’s thermal generating fleet. It should be noted that there are four peaking

gas turbine units each at Decker and Sand Hill. Since individual gas turbines at

each of these facilities are the same design, size, age and performance, these peaking

units capabilities are aggregated into two single peaking sources to reduce the number

of generators in the model. Dispatch of these units as a group is equivalent to all

four units at each plant being dispatched independently. Information about each

generating unit’s fuel, prime mover type and nameplate capacity is published in the

Austin Energy Resource Guide. [3] Minimum load, up and down ramp rates were

provided by Austin Energy. Marginal costs were estimated based on average 2008

heat rates provided by Austin Energy, fuel energy content [56] and fuel prices [57,

58]. Additional O&M costs were added to these marginal cost estimates based on

information compiled by Lott et al. [59] Since nuclear power fuel costs are not as

readily available, estimated marginal costs closely parallel data in [59]. All renewables

are indicated as having zero marginal costs. This simplification of costs was done in

an attempt to ensure that all available renewable generation will be dispatched, since

Austin Energy currently contracts all its renewables to third-parties with agreements

to buy all generated electricity. It is known that many of these generators have

extremely high marginal costs. but contractual purchasing agreements make the cost

irrelevant to economic dispatch. The last line in table 4.1 describes storage as it is

included in initial modeling results in sections 5.1 and 5.2, where storage is treated

as having zero marginal costs and had minimal constraints on its operation.

As mentioned previously, later models presented here include emissions rates.

Emissions for Austin Energy’s generators were captured from publicly available Con-

tinuous Emissions Monitoring System (CEMS) data. [61] To ensure compliance with

federal air quality standards, the Environmental Protection Agency requires continu-

ous monitoring and electronic reporting of emissions levels at all major thermal power

45

Tab

le4.

1:A

ust

inE

ner

gy’s

pro

ject

edge

ner

atin

gflee

tin

2020

isco

mpri

sed

ofa

vari

ety

ofth

erm

alge

ner

atin

gunit

s,as

wel

las

seve

ral

typ

esof

renew

able

s.

Fac

ilit

y[3

]F

uel

[3]

Typ

e[3

]M

axim

um

Load

(MW

)[3

]

Min

imu

mL

oad

(MW

)‡

Sta

rtu

pC

ost

($)†

Marg

inal

Cost

($/M

Wh

)†

Max.

Ram

pU

p(M

W/m

in)‡

Max.

Ram

pD

own

(MW

/m

in)‡

Fay

ette

Un

it1

Coa

lS

team

305

90

12,0

00

15.1

53

Fay

ette

Un

it2

Coa

lS

team

302

90

12,0

00

15.2

53

ST

PU

nit

1N

ucl

ear

PW

R211

37

15,0

00

21.8

2.3

7S

TP

Un

it2

Nu

clea

rP

WR

211

37

15,0

00

21.8

2.3

7S

and

Hil

l5

Nat

ura

lG

asC

omb

ined

-cycl

e512

120

7,5

00

54.2

15

15

Dec

ker

Un

it1

Nat

ura

lG

asS

team

327

45

10,0

00

95.6

44

Dec

ker

Un

it2

Nat

ura

lG

asS

team

414

55

10,0

00

97.7

44

San

dH

ill

Pea

kN

atu

ral

Gas

Sim

ple

-cycl

e289

12

250

113.9

40

40

Dec

ker

Pea

kN

atu

ral

Gas

Sim

ple

-cycl

e193

48

500

151.7

20

20

Win

d846

00

01,0

00

1,0

00

Lan

dfi

llG

asM

eth

ane

Com

bin

ed-c

ycl

e7.8

30

01

1B

iom

ass

Wood

Was

teS

team

200

30

00

44

Sol

arP

hot

ovol

taic

100

00

01,0

00

1,0

00

Sto

rage

1,2

00

-1,2

00

00

1,0

00

1,0

00

†T

hes

eco

sts

are

esti

mat

edb

ased

on[5

6–60

]an

dd

on

ot

reflec

tact

ual

marg

inal

or

start

up

cost

s.‡

Th

ese

dat

aw

ere

pro

vid

edby

Au

stin

Ener

gyor

esti

mate

db

ase

don

info

rmati

on

from

Au

stin

En

ergy.

46

2020

2008

Nameplate Capacity (MW)

0 1000 2000 3000 4000

Coal Nuclear Natural Gas Gas Turbines Wind Solar PV Biomass

Figure 4.1: Nearly all of Austin Energy’s planned generation growth by 2020 will befrom renewable sources. [3]

plants in the United States. NOx and CO2 emissions (lbs and tons, respectively) and

load levels (MW) for all of Austin Energy’s generators were, with MATLAB’s regres-

sion function polyfit, transformed into linear regressions. A quadratic example of the

data available and a regression from polyfit are shown in figure 4.2. Because CEMS

data for Decker’s gas turbines is not consistent with the physical limits of those fa-

cilities, all gas turbines in the fleet will be approximated to the emissions rates of

Sand Hill unit 1. This approximation might distort emissions price scenario dispatch

since the gas turbines at Decker are 21 years older than those at Sand Hill, but it will

likely have a minimal effect on unit commitment since the gas turbines at Decker are

almost never used. The gas turbines at Sand Hill are assumed to have homogeneous

emissions rates.

As shown in figure 4.1, Austin Energy’s renewable generating fleet will grow

significantly by 2020. Energy storage is likely to have the greatest benefit after this

growth in installed wind capacity, so this future scenario has been modeled. Austin

47

0 50 100 150 200 250 300

050

100

150

200

Plant Load (MW)

CO

2 Em

issi

ons

(ton

s)

CEMS DataLinear Regression (MATLAB)

Figure 4.2: Decker Power Plant unit 1 CO2 emissions are modeled as proportionalto generator load (MW), a reasonable approximation that avoids introducing non-linearities to the model. [61]

48

Table 4.2: Emission rates for all thermal generators are passed to the model to studythe effect of emissions pricing on storage allocation and unit commitment decisions.

Emission Plant Rate (tons/MW) Base Level (tons)

CO2 Decker 1 5.5e-01 9.44CO2 Decker 2 5.5e-01 10.1CO2 Decker GT‡ - -CO2 Fayette 1 9.7e-01 20.5CO2 Fayette 2 9.9e-01 16.4CO2 Sand Hill GT 6.6e-01 -2.51CO2 Sand Hill 5 3.6e-01 13.5

NOx Decker 1† 7.6e-04 -2.9e-02NOx Decker 2† 5.5e-04 -2.5e-02NOx Decker GT‡ - -NOx Fayette 1 4.4e-04 4.7e-02NOx Fayette 2 5.6e-04 -1.9e-02NOx Sand Hill GT 7.4e-05 2.3e-03NOx Sand Hill 5 2.6e-05 9.6e-03

† Most cases were an acceptable linear fit but these emission rates were not.‡ Since Decker gas turbine data were not properly reported in CEMS, these are taken in the modelto be equal to Sand Hill gas turbine reported data

49

Energy has estimated that their peak requirements will increase by 238 MW from

2008 to 2020, assuming their DSM efforts in the intervening years are successful. [3]

Load data provided by Austin Energy for 2008 in 15-minute increments was scaled

by finding the peak of that year and increasing it by 238 MW. Time periods where

demand was less than peak were increased by a fraction of 238 MW based on the

fraction of demand in that period compared to peak 2008 demand. As an example, if

the peak in 2008 was 2000 MW and the time period of interest had, in 2008, a load

of 1500 MW, the adjusted value for 2020 in that period would be 1500/2000 · 238 +

1500 MW.

Using a similar approach to demand scaling, wind and solar availability were

scaled based on anticipated increases in installed capacity between 2008 and 2020.

Existing wind generation data provided by Austin Energy from their Sweetwater,

Hackberry, Whirlwind and King Mountain facilities was aggregated and scaled up to

the anticipated 846 MW of peak generation available in 2020. Since wind generation

rarely reaches its peak capacity, 2008 wind availability was scaled according to its 2008

percentage of peak — if in some time period in 2008 wind availability was 137 MW,

or 50% of peak, then in 2020, that value was scaled to 50% of 846 MW, or 423 MW.

It is currently unknown whether, as more wind generation is installed at existing and

new sites based on CREZ locations, variability will scale directly as assumed here,

or be reduced due to geographic wind turbine diversification or other factors. Unlike

wind, where existing generation was scaled to fit future capacity, insufficient solar

generation is currently in Austin Energy’s fleet for similar assumptions to be made.

Instead, data from the National Solar Radiation Database (NSRDB) were used to

estimate future solar photovoltaic generation. [62] New Braunfels, TX (site 722416)

was the closest NSRDB site to Austin Energy’s planned solar photovoltaic facility

in Webberville, TX. Hourly total solar insolation data from 2004 were converted to

50

power output using planned peak capacity of 100 MW and an assumed panel efficiency

of 19%. Since data with a higher sampling rate were not available, it was assumed

that solar radiation remained constant throughout each hour period in the model. It

should be noted that since stochastic programming is avoided in these models, it is

assumed that all wind and solar generation provided as inputs to the model for all

time steps will be dispatched at those levels.

In later model variations, storage can be selected from a set of available storage

types. As discussed in section 4.1, because the size of the time steps in these models,

storage will either be used for arbitrage or not selected; hence, the storage types

provided to the model are those that are both available in Texas and suitable for

daily storage. Because of geographic restrictions, pumped hydroelectric storage is

not included. The parameters shown in table 4.3 detail the operating constraints

on a typical energy storage unit — charge and discharge rates (MW), charge and

discharge ramp rates (MW/min), fixed ($/MW-year) and variable marginal costs

($/MWh), round-trip efficiency, and total capacity (MWh). Each storage type shown

in table 4.3 provides details for a typical single unit. The model is able to select

a nearly unlimited number of units and a combination of different storage types to

reach optimality. It should be noted that the number of PHEVs are restricted to

12,000, which represents roughly 3% of the vehicles in the Austin Energy service area

and is an approximation of an upper limit for PHEV market penetration in the region

after slightly less than one decade of widespread commercial availability. PHEVs are

treated as zero cost storage for the utility, which assumes that customers will receive

no benefits from the utility for the use of their battery. While this arrangement is

unlikely, so many compensation or incentive structures are possible that it is outside

the scope of this study to explore which might be most appropriate or to assume that

one particular approach will achieve market acceptance. Also, PHEVs are assumed

51

Tab

le4.

3:F

orth

epurp

oses

ofth

isst

udy,

asm

all

subse

tof

stor

age

typ

eshas

bee

nse

lect

edbas

edon

thei

rco

stan

dp

erfo

rman

ceat

trib

ute

s.

Typ

eR

oun

d-t

rip

Effi

cien

cy

Typ

ical

Siz

e(M

Wh

)

Maxim

um

Inp

ut

(MW

)

Maxim

um

Ou

tpu

t(M

W)

Ch

arg

eR

am

pR

ate

(MW

/m

in)

Dis

charg

eR

am

pR

ate

(MW

/m

in)

Fix

edM

arg

inal

Cost

s($

/M

W-y

ear)

Vari

ab

leM

arg

inal

Cost

s($

/M

Wh

)

NaS

Bat

tery

[18]

0.88

0.43

0.0

50.0

50.0

50.0

542,2

00

0V

anad

ium

FB

[18]

0.85

100

10

10

0.5

0.5

56,1

00

0P

HE

Vs

[63]

0.9

0.01

160.0

10.0

10.0

05

0.0

05

00

CA

ES

[14]

1.25†

10,0

00270

200

20

270

108,0

00

1.5

†H

eat

isad

ded

,ty

pic

ally

by

bu

rnin

gn

atu

ral

gas,

tora

ise

the

tem

per

atu

reof

the

ou

tflow

stre

am

bef

ore

exp

an

din

git

ina

turb

ine

train

,m

akin

gth

eto

tal

ener

gyex

trac

ted

grea

ter

than

that

store

d.

[14]

52

to be available whenever the utility wants to use their stored electricity and that

their charge level does not vary apart from when the utility dispatches them. This

assumption is not realistic since owners are likely to use their cars throughout the

day and reconnect them to the grid at varying levels of charge. The details of V2G

interactions of PHEVs are, however, outside the scope of this study and neglecting

them minimizes computational requirements for modeling PHEVs as a possible energy

storage option.

4.3 Model Structure

GAMS, used to implement the unit commitment models presented here, im-

poses a specific structure on those models. In GAMS, governing sets, or variable and

parameter indices, are declared first. Parameters — variables with fixed values that

typically describe components in the modeled system — are declared and assigned

values directly in the code or, as in this model, read from a GDX file, which enables

the use of Excel for data entry and promotes code brevity. Finally, scalars and vari-

ables are declared and described. All of these components are then combined into

equations that follow a form nearly identical to that presented in section 4.4. This

approach creates a structure that can be conveniently represented, as has been done

in tables 4.4 through 4.8.

These models were originally structured such that results for cases with and

without storage were captured with one GAMS file. Since each variable must have a

single index associated with it, structuring the model in this way led to many different

variable names, making the code excessively long and difficult to follow. With added

equations to capture more constraints, the model was transitioned to a structure

where each version had only two indices, one for those parameters and variables that

53

Table 4.4: GAMS models are structured around controlling indices called “sets.”

Index (Set) Description

g All generating units (Table 4.1)t Model time periods in 15-minute increments

Table 4.5: Model parameters define the operating constraints of all generators in table4.1, as well as time-dependent functions.

Parameter Description

mcg Marginal costs for all generators g ($/MW)maxpowerg Generator nameplate (maximum) capacity (MW)minpowerg Minimum generator operating level (MW)rampupg Ramp rate increase limit (MW/min)rampdowng Ramp rate decrease limit (MW/min)startcostg Startup costs for all generators g ($)demandt Demand in each period (MW)windt Aggregated wind availability (deterministic) in each period (MW)†

solart Solar availability (deterministic) in each period (MW)emissionsg Emissions rate based on plant output (tons/MW or lbs/MW)interceptg Base level emissions rate from each generator (tons or pounds)

† Wind availability is aggregated over all Austin Energy’s contracted wind farms

change for every generator g and one for those that vary throughout the modeled time

t. As indicated in table 4.4, in all models presented here, regardless of the length of

the model, only 15-minute time steps are used.

The parameters in table 4.5 are almost entirely identical to the column head-

ings in tables 4.1 and 4.2. Those parameters that vary with t : deterministic demand,

wind and solar availability, are added here. These parameters are known for the full

model period, regardless of its length, and all ‘available’ wind and solar generation

must be dispatched. Thermal generators must respond to compensate for changes

from these and other renewable generators, as they do in Austin Energy’s current

54

Table 4.6: Model variables are combined with parameters to form the objective func-tion and constraint equations.

Variable Description

ong, t Binary indicating plant g turned on in period toffg, t Binary indicating plant g shut off in period t-1sprg, t Spinning reserve quantity provided by plant g in period txg, t Power generated by unit g in period t (MW)yg, t Binary indicating if a unit g is on in period tz Objective function

system. Recall, however, that applying stochastic methods to model these parame-

ters would not significantly improve commitment or dispatch decisions. [22,37]

In addition to the parameters in table 4.5, three scalars are used in the model.

The quantity of spinning reserve that must be held in the model, following the 90 MW

guideline used by Austin Energy, is controlled by resamt. The marginal cost of the

two nuclear generators, South Texas Project units 1 and 2, is adjusted by $7/MWh

using scalar nukecdt so that their marginal prices are below that of the cheapest

generator indicated in 4.1. The modification of the nuclear generators’ marginal

costs is to ensure that they are always fully dispatched and that, if needed, Fayette

Power Project’s generators are dialed back first. Finally, the scalar price captures

the market price of the relevant emissions factor for scenarios that include emissions

pricing.

Binary variables ong, t and offg, t indicate when a plant has started up or shut

down. These variables will be explained further with the equations that govern their

assignment. Variable sprg, t ensures that sufficient spinning reserve, governed by re-

samt, is always allocated. In the model, only Fayette units 1 and 2, South Texas

Project units 1 and 2, Sand Hill unit 5 (combined-cycle) and Decker units 1 and 2

55

are permitted to provide spinning reserve only when they are on, or when their yg, t is

equal to 1. When storage is available, it is also permitted to provide spinning reserve,

though market protocols dictated by ERCOT do not explicitly allow the use of energy

storage for spinning reserves. The dispatch of every plant g for all times t is assigned

to the variable xg, t, where in all periods that x is non-zero, yg, t must be equal to one,

indicating that the plant is on. The variable z captures the value of the objective

function and is passed to the solver for minimization.

For those model cases that include energy storage declared as a thermal gener-

ator, the variable xg, t, where g refers to storage, can only be constrained in ways that

make sense for thermal generators. As a result, this model structure cannot, without

additional equations, fully describe a unit of energy storage. Since the goal of this

work is to reveal what storage types are best suited to energy storage in the grid and

at what price points those storage facilities might be practical, improved modeling

of energy storage is needed. A third model index (set), type, is declared to facilitate

selection of discrete storage types. All the storage units that can be selected, based on

table 4.3, are indexed over this set. As with thermal generators, constraints must be

declared to govern the operation of each of these storage units of type by converting

most of the columns in table 4.3 into parameters in table 4.7.

To capture round trip efficiency, withdrawals (outtype, t) from energy storage are

measured separately from inflows (intype, t). These values are constrained by maximum

withdrawals and inflows in every time period, as well as ramp rate changes in those

values. Additionally, the quantity stored, storedtype, t, at every time step t must be

measured to ensure that total storage capacity for each unit is not exceeded. The

information about storage unit performance characteristics given in table 4.3 describes

one characteristic unit of that storage type and ntype, an integer number of those units,

56

Table 4.7: For the discrete storage scenarios, additional parameters are required toenable constraints on their assignment and operation.

Parameter Description

efftype Round-trip efficiency for all storage units of type typesizetype Maximum capacity of one storage unit (MWh)inlimittype Maximum charge rate (MW)outlimittype Maximum discharge rate (MW)chgtype Maximum rate of change of charge rate (MW/min)dischgtype Maximum rate of change of discharge rate (MW/min)fixcosttype Fixed marginal costs ($/MW-year)varcosttype Variable marginal costs ($/MWh)

Table 4.8: Additional variables must be defined to constrain the selection and oper-ation of energy storage in the discrete storage scenarios.

Variable Description

storedtype, t Energy stored in storage unit type at the end of period tintype, t Input to storage type during period touttype, t Output from storage type during period tstrtype, t Spinning reserve provided by storage type during period tntype Number of units of energy storage type available on the grid

57

might be used in the model. Generally, this value is left to be assigned freely by the

model to select the optimal combination of storage types.

4.4 Governing Equations

The model components — sets, parameters and variables — presented in the

previous section come together to form the governing equations for all of the model

setups tested. Below are the specific objective functions and constraint equations that

provide realistic limits on the operation of thermal power plants and energy storage,

in those models that include discrete energy storage selection.

4.4.1 Objective Functions

All models in this work share a common marginal cost minimization objective

function equation. Equation 4.1 includes marginal costs as well as several other

parameters that are included for control or minimization:

z =∑g,t

mcg · xg,t +∑g,t

startcostg · ong,t +∑g,t

(ong,t + off g,t) (4.1)

Equation 4.1 captures major ongoing costs associated with thermal power

generators — operating, fuel and maintenance costs (first term) and startup costs

(second term). Marginal costs are given by table 4.1 except that nukecdt (not shown)

is subtracted from nuclear generator marginal costs to ensure they are the first thermal

generators dispatched. Because renewable generation assets are assigned artificial

marginal costs to ensure their dispatch, this objective does not strictly dispatch based

on marginal costs. Since generation from these units are provided through forward

contracts with IPPs, the terms of those contracts are not disclosed to the public and

thus marginal costs are unknown and not necessarily linked to the price Austin Energy

pays per MWh of generation. Each summation is over all terms in both sets g and

58

t, or generators and time steps, respectively. The way the objective is structured, it

appears that plant turn-ons are penalized twice, but the third term is strictly a control

for the variables ong,t and offg,t so that the model does not arbitrarily assign values

of 1 to those variables at times when a generator did not turn on or off, respectively.

The importance of this term is explained further with the introduction of equations

4.13 and 4.14. The addition of terms that do not directly affect operating costs would

appear to taint the objective, but including additional variables in the objective is

an effective method for controlling variable assignment and the actual operating cost

can be recalculated once the optimization run is complete.

For models that include discrete storage selection, two additional terms are

appended to the objective given by equation 4.1, shown in equation 4.2:

· · ·∑type,t

(0.25·outtype,t ·varcosttype)+∑type

(ntype ·inlimittype ·fixcosttype ·

cardt35040

)(4.2)

These terms calculate the variable and fixed marginal costs for those storage

types employed in the model. The value 35040 on the second term divides the length

of the model (cardt) by the length of a year to calculate the total fixed marginal costs

for the modeled period.

To capture the effect of potential future emissions pricing or markets, equation

section 4.3 is added to the objective:

· · ·∑g,t

price(emissionsg · xg,t + minimumg · yg,t) (4.3)

These terms calculate the emissions rate for any thermal generator g based

on historical CEMS data, detailed in section 4.2. The price is provided to the model

in $20/ton increments from $10/ton to $90/ton for CO2 and $10/lb increments from

$5/lb to $45/lb. The first term inside the parentheses describes the emissions rate

59

(tons/MW or lbs/MW) and the second term is the base level emissions quantity (tons

or lbs). These quantities are in table 4.2.

4.4.2 Constraint Equations

Each of the following equations serves to constrain operation of the model,

reflecting realistic physical constraints on generator operation. Some previous unit

commitment models neglect certain constraints, such as startup costs and minimum

load levels, but such omissions can significantly affect results. [20] In all unit commit-

ment systems, as in all real electricity generation and distribution systems, demand

must be met at all times. Equation 4.4 strictly requires the model to turn on sufficient

generating units to meet or exceed demand:

∑g

xg,t −∑type

intype,t +∑type

(outtype,t · eff type) ≥ demandt ∀ t (4.4)

The relation between dispatch (xg,t) and demand (demandt) implies that unit

commitment could exceed demand, but because the objective to be minimized in-

cludes the dispatch term, demand will likely never be exceeded. Equation 4.4 is

dependent on the set t, thus, it is applied for all times t in the model formulation,

as indicated by ∀ t. Here, equation 4.4 includes terms with the variables intype,t and

outtype,t, which are only included for those models that have discrete storage selection.

An alternate formulation could include a slack variable q on the left-hand side of the

equation, allowing the model to not meet demand by assigning a positive value to

q. The slack variable would appear in the objective function, multiplied by a large

scalar value, penalizing the failure to meet demand. This approach could realisti-

cally represent the costs or penalties, if known, associated with blackouts or the use

of resource entities. This approach was tested during model development and the

value of penalty is crucial — if it is too small, the model will pay the penalty instead

60

of dispatching any generators and, if it is too large, it will never be used— so this

approach is avoided in the interest of determining unit commitment apart from the

availability of demand as a resource.

For all generating units modeled, there exist minimum and maximum operat-

ing levels, applied to unit commitment variable xg,t with equations 4.5 and 4.6:

xg,t ≥ yg,t ·minpowerg ∀ g, t (4.5)

xg,t + sprg,t

∣∣∣g < 7≤ yg,t ·maxpowerg ∀ g, t (4.6)

These reflect real constraints on the rotating equipment of power plants, which

can only generate electricity at a range of operating levels. Additionally, for those

plants that are permitted to provide spinning reserve, indicated by the restriction on

sprg,t, they must not provide more spinning reserve than is possible while remaining

under nameplate capacity. Both equations apply for all units g during all periods t. To

permit initial commitment at any allowable level between minpowerg and maxpowerg

(or 0), these equations are not applied in the first time step to. Notably, units are

not required to remain off for a specified amount of time through these or other

constraint equations, as the penalty applied to generator startup, included in the

objective function, ensures that repeated unit startup and shutdown will be avoided.

Equations 4.5 and 4.6 also control the assignment of binary yg,t, which indicates

whether a unit g is operating in period t. This variable will be important in the

assignment of binaries ong,t and offg,t in equations 4.13 and 4.14.

Typically, thermal power plants are constrained in their ability to change their

power output level quickly. Additionally, when they turn on, they are not able to

immediately provide generation up to their nameplate capacity. [31] For all time steps

beyond initial commitment period to, equations 4.7 and 4.8 control unit commitment

61

consistent with these limitations:

xg,t−xg,t−1 +sprg,t

∣∣∣g < 7≤ 15 ·minpowerg ·off g,t−rampupg (yg,t−ong,t) ∀g, t (4.7)

xg,t − xg,t−1 ≥ −minpowerg · off g,t − 15 · rampdowng (yg,t−1 − off g.t) ∀ g, t (4.8)

As with equations 4.5 and 4.6, equations 4.7 and 4.8 are not applied until

after to to allow initial commitment and dispatch, after which time any generator g

can be committed to no more than its previous generation level plus its maximum

ramp rate up, rampupg, or less than its previous generation minus its ramp rate

down, rampdowng. Ramp rates are specified in MW per minute, as in table 4.3, so

those values are multiplied by 15 in equations 4.7 and 4.8 to yield ramp rate for the

time step. Each of these equations applies to all generators g during all periods t.

Additionally, spinning reserve from those plants that are permitted to provide it must

not exceed the ramp up capability of that generator, thus it is included in equation

4.7.

For all generators that are permitted to provide spinning reserve, total reserve

available for all times t must be greater than resamt of 90 MW, the amount of reserve

held by Austin Energy:∑g

sprg,t

∣∣∣g < 7

+∑type

(strtype,t · eff type)∣∣∣type 6=3

≥ 90 ∀ t (4.9)

For scenarios with discrete storage selection, equation 4.9 follows the form

shown, including spinning reserve from thermal generators and from available storage

types except PHEVs. Where energy storage is treated similarly to other thermal

generators, the strtype term is eliminated and the first term is expanded to include

generic storage.

Because renewable power sources are modeled without marginal costs (table

4.1), it is likely that regardless of the selected objective, all renewables will be fully

62

dispatched by the model. Because of the contractual arrangements with IPPs to

furnish power from these sources, however, a deterministic approach is applied with

equations 4.10, 4.11 and 4.12, forcing the model to use all available renewable gener-

ation in all periods t :

xg,t

∣∣∣g=10

= windt ∀ t (4.10)

xg,t

∣∣∣g=13

= solart ∀ t (4.11)

xg,t = maxpowerg ∀ g∣∣∣g=11,12

, t (4.12)

Recall that wind and solar resources are calculated based on averages of their

generation profiles for every month in 2008, scaled up to correspond with Austin

Energy’s 2020 generation plans. Seasonally adjusted values are provided for both

generation types.

Equations 4.13 and 4.14 do not strictly describe constraints, but they are used

frequently in constraint equations. Equation 4.13 governs the assignment of variable

ong,t during all time steps beyond to (to avoid penalizing initial commitment), where

ong,t is a binary equal to 1 when a unit g is turned on in time t. Similarly, Equation

4.14 controls binary offg,t, which is equal to 1 when a unit g is turned off in time t-1 :

ong,t ≥ yg,t − yg,t−1 ∀ g, t (4.13)

off g,t ≥ yg,t−1 − yg,t ∀ g, t (4.14)

These equations are important in deactivating constraints that should not be

applied to a generator in a period t when it turns on or off. It might seem immediately

apparent that these relationships should be equalities, but if that were the case, during

time periods when a unit turns on, equation 4.14 would try to assign a value of -1

to the binary, with similar results from equation 4.13 when a unit turns off. The

63

inequalities allow the binaries to be assigned values of 1 during periods when a unit

is not turning on or off, so the variables ong,t and offg,t are penalized in the objective

function.

4.4.3 Storage-specific Constraints

When storage is treated as simply an added on unit in the model with Austin

Energy’s existing thermal generation, only one additional equation is included in the

model to control the assignment of xg, t for storage:∑t

xstorage, t = 0 (4.15)

In the interest of constraining energy stored or used as little as possible in

any period t, only this constraint is applied. Equation 4.15 requires that whatever is

discharged from storage must be returned by the end of the modeled period, where

round-trip efficiency of the transmission and energy storage system are assumed to

be unity. As it is, this idealization precludes replication of model results with a real

storage portfolio, which motivates later expansion of the modeling of energy storage.

In the case of models where the time period is limited to a single day, equation 4.15

ensures that energy storage is not modeled as a limitless supply of free energy. If the

model were expanded to weeks or months, this constraint would only dictate that

the final and initial state of charge must be the same, allowing variations in state of

charge across multiple-day boundaries if such an operational approach is optimal.

To more realistically model energy storage in the unit commitment framework,

additional equations for the model are developed using the parameters and variables

from tables 4.7 and 4.8. These control the operation of storage to remain within the

constraints presented in table 4.3. It should be noted that these additional equations

do not determine optimal storage location, only portfolio selection. It is possible that

64

the optimal storage portfolio might vary somewhat depending on facility siting, but

answering that question would require significant further model development and is

thus outside the scope of this thesis.

The major constraint equation controlling the use of energy storage defines the

change in the quantity stored in each time step as the difference between the inputs

and outputs in that period:

storedtype, t = storedtype, t−1 + intype, t − outtype, t ∀ type, t (4.16)

Equation 4.16 calculates the energy stored at the end of period t, storedtype, t,

for all periods t and all storage units type. The variable outtype, t measures the amount

discharged from the storage device, where the amount delivered to the grid is outtype, t

multiplied by efftype. This calculation is performed in the thermal generator equation

4.4. Each of the variables represented in this equation capture totals for all n units of

each type of storage selected in the results, which is distinctly different from storage

unit parameters, which must be multiplied by n to determine actual operational

constraints. Upper operational limits are controlled by:

storedtype, t ≤ sizetype · ntype ∀ type, t (4.17)

intype, t ≤ inlimittype · ntype ∀ type, t (4.18)

outtype, t + strtype, t

∣∣∣type 6=3

≤ outlimittype · ntype ∀ type, t (4.19)

Equation 4.17 ensures that total energy stored (MWh) does not exceed the

capacity of the storage unit at any point during the modeled time period. Equations

4.18 and 4.19 control the maximum inflow and discharge for all storage devices selected

by the model at all times t. In these, as in all subsequent equations here, where a

parameter appears in the equation it must be multiplied by n, the number of that

65

storage unit type that have been selected. In equation 4.19, as in all equations where

strtype, t appears, spinning reserve from storage cannot be provided by PHEVs. In

the model, this restriction is applied directly to the variable strtype, t in the equation

declaration.

In addition to limiting inflow and discharge or outflow for all storage types,

the rate of change in these values must also be controlled:

storedtype, t − storedtype, t−1 ≤ 15 · chgtype · ntype ∀ type, t (4.20)

storedtype, t − storedtype, t−1 − strtype, t ≥ −15 · dischgtype · ntype ∀ type, t (4.21)

In a manner nearly identical to equations 4.7 and 4.8 for thermal power plants,

equations 4.20 and 4.21 control ramp rates for energy storage. Equation 4.21 also

limits spinning reserve quantities that can be provided by a given energy storage type

to no more than what it can ramp to in that period, not including ramping capacity

dispatched.

Finally, regardless of ramp rates, a given energy storage type cannot provide

more reserve than is currently stored:

strtype, t

∣∣∣type 6=3

≤ storedtype, t ∀ type, t (4.22)

Equation 4.22 is entirely restricted to energy storage not provided from PHEVs

because, as mentioned previously, they are not permitted to provide reserve since they

cannot necessarily be expected to be plugged in when the utility wants to dispatch

them. Many other constraints to further limit PHEVs ability to provide storage

require predictions or estimates of owner behavior or desires. Will nighttime stored

energy be available during the day or consumed by commuting, will drivers be able to

plug in their vehicles midday, how much will drivers expect to be paid to comply with

66

utility needs for energy storage from their cars, and will drivers be willing to change

their driving and charging habits to earn more from utilities, are all questions that will

require further study before PHEVs can be fully detailed in a unit commitment model.

Further, it is unlikely that PHEVs will fit neatly into a unit commitment framework

since their availability will likely be non-optimal and subject to only limited control

by the utility.

67

Chapter 5

Results

The results presented henceforth step through the evolution of the model as

functionality and accuracy are added. Section 5.1 presents the first set of results,

where the future generation scenario to be examined is separated into averages for

each month in the year. Demand, wind, and solar generation in these results are all

averages of every day in the month. Each month is modeled discretely, shortening

solution times and providing a clear quantitative look at the potential benefits of

energy storage and the trends that might appear in the full-year models. These

results suggest that meaningful outcomes might be revealed in a full-year model,

but these models require significant computational resources, so fewer scenarios are

studied.

For the full-year models, results from scenarios with and without storage are

compared, including scenarios with discrete storage selection from the portfolio in

table 4.3. Current estimated capital costs associated with storage types available to

the model are in table 5.1. These capital costs are included for reference and can

be used to compare with maximum acceptable capital costs backed out from model

results. These results are presented in section 5.2. Capital costs are not captured

in the model; without accurate financing information about existing facilities and

planned expansion, it is difficult to compare them with energy storage. Further, future

prices could decrease due to economies of scale associated with mass production or

improved manufacturing techniques, or increase due to active material or construction

68

Table 5.1: Estimated Capital Costs for Selected Storage Devices [18]

TypePrice($/MWh)

Price($/MW)

Lifetime(years)

NaS Battery 196,000 1,862,000 10Vanadium FB 236,000 2,691,000 20PHEVs 0 0 10CAES 21,830 750,000 25

material costs, thus capital costs are also excluded on the basis of unknown future

storage prices.

In addition to presenting models with and without storage, emissions prices

and how they affect the value proposition for energy storage are explored as well.

Though CO2 emissions are not regulated and NOx markets are not currently present

in Texas, studying the pricing of these emissions parameters is relevant because of the

possibility of future legislation. Since this work examines generation cases in 2020,

it is possible that in these future scenarios, regulations for large emitters of these

pollutants will be in place. A range of prices for each pollutant are tested to examine

how energy storage can manage cost increases associated with changes in dispatch

decisions. All the scenarios studied for this work are summarized in table 5.2.

5.1 Monthly Averaged Demand, Wind and Solar Generation

For these results, each month of demand, wind and solar data were scaled to

match our 2020 scenario of interest, and then all the days each month were averaged

to make a scenario day for study. As a result, these cases can only represent an

average of availability of renewable resources and demand requirements, excluding

cases with the worst renewables availability or highest demand peaks.

69

Table 5.2: Summary of All Scenarios/Cases Presented

Scenario/Case Description

Month-by-Month,24-Hour

Model runs for each month with separate runs for caseswithout storage and with generic, unconstrained storage,all using 2020 scenario conditions for load, wind and solargeneration, and generating fleet capabilities

2008 without Storage A single model execution for a full year using load, windand generating fleet information to validate model dis-patch accuracy against Austin Energy data

2020 without Storage A full-year model using estimated 2020 scenario condi-tions with only thermal generators available for dispatch

2020 with Storage A full year using the estimated 2020 scenario conditionswith generic energy storage available, unconstrained byround-trip efficiency or marginal costs

2020 with DiscreteStorage

A full-year model using 2020 scenario conditions plus en-ergy storage availability based on constraints in table 4.7and integer caps on storage availability in table 5.4

2020 with LimitedDiscrete Storage

A full-year model similar to ‘2020 with Discrete Storage,’but with lower caps on storage availability, shown in table5.5

2020 Storage plusCO2 Prices

Similar to ‘2020 with Storage,’ except with CO2 pricesincluded in the objective function

2020 Storage plusNOx Prices

Similar to ‘2020 with Storage,’ except with NOx pricesincluded in the objective function

70

Time Step [h]

Load

[MW

]

0 2 4 6 8 10 12 14 16 18 20 22

010

0020

0030

00

BiomassLandfill GasSolarWindSand Hill PeakDecker Unit 2

Decker Unit 1Sand HillFayette Unit 2Fayette Unit 1STP Unit 2STP Unit 1

Figure 5.1: Typical dispatch for a July 2020 day requires dialing back or shuttingdown inexpensive units at night and the use of older, dirtier generators to meet peakdemand.

71

Each of these models were run in GAMS, which includes a variety of options

that affect the way the program and solver run. In the case of these monthly average

results, these options were not needed because of the small number of variables in

each model. These were run with the optimality criterion, the value that determines

model termination, set at the default value of 0.1%. Each model took between a few

seconds and a few minutes to complete when running locally in 64-bit Windows 7 on

the MacBook Pro detailed in section 4.1. Figure 5.1 shows a typical 24-hour dispatch

case for July 2020 without storage. To be strictly rigorous, dispatch decisions should

be plotted as a series of bars, one for each 15 minute interval. The model does not

make continuous dispatch decisions, nor is the time interval small enough for the

results to approximate continuous dispatch, but the smoothing between 15 minute

intervals is a reasonable approximation of the dispatch that could be expected if the

time intervals were shortened considerably. Additionally, displaying the results in

this way is easier to follow. It should be noted that while it is assumed here that

dispatch decisions made for each 15 minute increment transition smoothly to the

next interval, in our calculations of costs and storage allocation, it is assumed that

dispatch is constant throughout the interval.

During the hottest months in Texas, May through September, load varies

dramatically between the lowest and highest demand intervals. The high peak is

a consequence of high cooling loads from the hottest afternoon hours coupled with

significant late afternoon activity as people arrive home. At the same time, wind

generation is reduced and solar generation is beginning to taper during these hours,

requiring that Decker generators 1 and 2 turn on. These generators have high NOx

emissions and high heat rates. In Austin Energy’s current operational structure, they

avoid the use of Decker even during peak hours through a 300MW summer power

purchasing agreement (PPA), likely with a cleaner facility. The costs associated with

72

this approach are unknown and it is unknown whether Austin Energy will continue

to engage in forward contracts for summer peak generation, so the model does not

include this or a similar contract.

Conversely, during the evening hours, many generators must be dialed back or

shut down to accommodate large quantities of available renewable energy. Further,

peaking gas turbines were activated to smooth the shutdown and startup of the

Sand Hill combined cycle generator. Further, the second generator at Fayette had to

be dialed back and the first generator briefly curtailed to accommodate renewables

and the shutdown of Sand Hill 5. In reality, it is likely that some wind would be

curtailed to avoid shutting down the combined cycle generator at Sand Hill because

that generator has minimum on and off times of over 24 hours. Because these data

on minimum operating times were not available when these models were run, these

requirements are violated for the combined cycle generator at Sand Hill but could be

included in future work.

With the availability of energy storage, as in figure 5.2, dispatch changes dra-

matically. Though as stated previously, the dispatch of Decker 1 and 2 is typically

avoided with a PPA, with energy storage, neither a PPA nor the dispatch of decker

is required because renewables available at night that would normally require dialing

back inexpensive generators can be shifted to the day, maintaining a relatively con-

stant level of generation throughout the day. The lightly shaded purple area between

the red and black lines shows where energy is stored at night and then returned to

the grid during peak hours. The cheapest generators, South Texas Project 1 and 2

(nuclear), Fayette 1 and 2 (coal) and Sand Hill 5 (natural gas combined cycle) are

operated at or near full capacity all day, while more expensive generators are entirely

avoided. Because of the availability of energy storage, dispatch requires only these

73

Time Step [h]

Load

[MW

]

0 2 4 6 8 10 12 14 16 18 20 22

010

0020

0030

00

StorageBiomassLandfill GasSolarWind

Sand HillFayette Unit 2Fayette Unit 1STP Unit 2STP Unit 1

Without StorageWith Storage

Figure 5.2: Dispatch with available storage in a July 2020 day meets peak demand us-ing wind energy available at night, avoiding the use of expensive and dirty generatorsand peaking units.

74

generators and renewable sources to meet demand throughout the day, even as de-

mand varies significantly. The drop in dispatch of Sand Hill 5 from maximum to

minimum load for a few hours in the evening is a consequence of needing to discharge

all stored energy, as required by equation 4.15. These models do not include non-linear

plant efficiencies that would likely discourage operating any generator at minimum

load except to avoid startup penalties. If these non-linearities were captured, Sand

Hill would probably be dialed back slightly throughout the dispatch period instead.

Cooler days in winter and spring months are characterized by demand that

is much flatter throughout the day, as in figure 5.3. The largest change between

the lowest and highest demand intervals during these months might only be a few

hundred megawatts. These months also have the highest wind availability, resulting in

significant curtailment of generation from baseload units throughout the day. Again,

it is likely that some wind generation would be curtailed to ensure the nuclear facility

could continue to operate at maximum output. Because demand is low and flat

throughout the day, most demand can be met with baseload generators Fayette and

South Texas Project, but for a few hours each day, peaking generators or a Decker

unit might be used to meet demand. This dispatch does not best utilize inexpensive

thermal generation, since baseload generators must be curtailed during nighttime

hours to accommodate renewable capacity.

Since winter and spring demand varies little between maximum and minimum

periods, figure 5.4 shows it can be served almost entirely by baseload generation

and available renewables. Even with the minimal variation in load, some peaking

generation is still required because renewables in Austin Energy’s portfolio are not

well-phased for peak demand. With energy storage, this generation can be avoided by

storing some wind generation during the nighttime hours and dispatching it during

75

Time Step [h]

Load

[MW

]

0 2 4 6 8 10 12 14 16 18 20 22

010

0020

0030

00

BiomassLandfill GasSolarWindSand Hill Peak

Decker Unit 1Fayette Unit 2Fayette Unit 1STP Unit 2STP Unit 1

Figure 5.3: In a November 2020 day, as with most winter and spring months in Texas,demand can be served almost entirely by baseload generation and renewables becausevariations during the day are limited.

76

Time Step [h]

Load

[MW

]

0 2 4 6 8 10 12 14 16 18 20 22

010

0020

0030

00

StorageBiomassLandfill GasSolarWind

Fayette Unit 2Fayette Unit 1STP Unit 2STP Unit 1

Without StorageWith Storage

Figure 5.4: As with the November 2020 scenario without storage, demand varieslittle throughout the day and is served by inexpensive generators, yielding minimalopportunity for benefit from energy storage availability.

77

the daytime peak. Further, the limited variation in demand means that little storage

is required to accommodate peak load. In some cooler months, allocation of energy

storage might be characterized by a series of charge and discharge intervals if there is

not a singular peak in demand. In all the cases shown in figures 5.1 through 5.4 and

all other observed cases, regardless of the number of charge and discharge periods or

the magnitude of the peak during the day, the optimal level of storage is whatever is

required to maintain flat or nearly flat total dispatch throughout the day, enabling

the use of inexpensive generators throughout the day and the avoidance of expensive

facilities like Decker and simple cycle gas turbines.

Similar to figure 5.3, figure 5.6 shows dispatch during a cool fall month when

load is nearly flat throughout the day. Again here, some generation from an expensive

and inefficient facility is required during the brief peak period. In each of these cases

where the coal facility is partially dispatched on at least one generator, the mismatch

in the dispatch of the two units is likely a consequence of not modeling the non-linear

efficiencies of these generators. If these non-linearities were included, both units would

likely be dispatched equally. Regardless, the predicted cost of dispatch, assuming the

average linear heat rates used as proxies for non-linear data are consistent with real

plant efficiency, should still be predicted correctly by this model.

As in a few other winter and spring months, in figure 5.6 Fayette 1 is dispatched

with significant seemingly random variations throughout the day. This behavior is

also likely a consequence of not including non-linear heat rates for thermal generating

facilities. If those were included, then it is likely the dispatch of Fayette 1 would

be smoothed somewhat, operating at a sustained lower level that is preferred to the

frequent ramping between maximum load and some lower level. Since storage is

available, smoother dispatch of this generator is definitely feasible, as in figure 5.4.

78

Time Step [h]

Load

[MW

]

0 2 4 6 8 10 12 14 16 18 20 22

010

0020

0030

00

BiomassLandfill GasSolarWindDecker Unit 1

Fayette Unit 2Fayette Unit 1STP Unit 2STP Unit 1

Figure 5.5: Demand during winter months, as in February 2020, can be served en-tirely by renewables and baseload generators in great part because of significant windavailability during these months.

79

Time Step [h]

Load

[MW

]

0 2 4 6 8 10 12 14 16 18 20 22

010

0020

0030

00

StorageBiomassLandfill GasSolarWind

Fayette Unit 2Fayette Unit 1STP Unit 2STP Unit 1

Without StorageWith Storage

Figure 5.6: In the modeled February 2020 day, frequent ramping of some generatorsappears, as in several other dispatch results with storage, likely a consequence of theuse of linear marginal costs for these results.

80

This dispatch being returned as optimal by the solver is possibly the consequence of

there existing several nearly identical minima in the problem’s solution space. As

mentioned before, it is also likely that with non-linear heat rates in the model, the

dispatch of the two coal generators would be the same instead of Fayette 2 operating

at minimum load throughout the day.

Looking broadly at the effect of energy storage on dispatch throughout the

year, as in figure 5.7, there are several important trends to note in the operation of

Austin Energy’s generating fleet. The optimal allocation of energy storage appears to

scale roughly with the cost of generation for the marginal (price setting) generator.

As the cost of generation increases, so does the presence of energy storage. In each

of these cases, total stored energy appears to capture only renewables. While this

observation is not strictly correct since, as seen in figure 5.2, in some nighttime

intervals, natural gas generation is also stored, during most intervals in most months

modeled, all stored energy is from renewable sources. Even without examining the

dispatch curves from every month to validate this conclusion, considering that most

renewables are from wind, which is most available at night in Texas, in months when

less than half of total renewable generation is stored and more than half of total

renewables are available at night, it is likely that all or nearly all stored energy is

from renewable sources. Further, overall utilization of the most inexpensive and

efficient plants in the fleet is enabled with the availability of energy storage. This

trend is most obvious in intermediate months like April, May and October, where

the cases with storage show a marked increase in coal dispatch and a corresponding

reduction in the use of natural gas facilities. In summer months where natural gas

dispatch appears unchanged, there is an increase in the use of the cheaper and cleaner

combined cycle unit at Sand Hill and a reduction or elimination of dispatch of Decker

1 and 2, as seen in figure 5.2. If non-linear heat rates and emissions rates were

81

December

November

October

September

August

July

June

May

April

March

February

(With Storage)

January

24 Hour Total Electricity Dispatched (MWh)

0 10000 20000 30000 40000 50000

Nuclear Coal Natural Gas Gas Turbines Renewables Storage

Figure 5.7: In most months, the availability of energy storage maximizes the dispatchof inexpensive generators by shaping wind output.

82

included in the model, improvements in dispatch with energy storage would likely

increase. Non-linear parameters would signal in the model what operating point is

preferred based on the objective function and it has already been shown that energy

storage enables superior dispatch of generating assets.

Comparing the costs of dispatch and allocation of storage, shown in figure 5.8,

between cases with and without storage for each month, it appears that allocation

of energy storage roughly scales with the benefit it provides to dispatch, just as it

scales with the availability of renewables, as seen in figure 5.7. WIth the increased

dispatch of cheaper units shown in figure 5.7, significant cost savings are realized in

most months. In particular, by dispatching the combined cycle unit at Sand Hill and

shaping renewables to correspond with demand, the use of Decker 1 and 2 can be

avoided, providing significant cost reduction. Looking closely at February and March

in figure 5.7, dispatch of less than 100 MW of natural gas generation is replaced by

stored energy between the cases with and without storage but more than 1000 MW

of energy is stored. This small change is likely a consequence of significant renewables

that are not timed appropriately to meet demand and inexpensive baseload generators

that are sufficient to meet almost all remaining demand. Redistributing renewable

generation to peak hours and avoiding the dispatch of peaking generators or one of the

units at Decker for a brief period cannot provide significant cost reductions but might

require a lot of storage. If seasonal storage were available, enabling the operation of

South Texas Project and Fayette generators at full capacity and capturing any excess

renewables could provide significant benefit if returned to the grid during the summer

months, when renewables are less readily available. In examining the results of energy

storage allocation in the full-year models, it turns out this approach is the optimal

allocation of energy storage if it is not quantity limited.

83

December

November

October

September

August

July

June

May

April

March

February

January

Peak Quantity Stored (MWh)

0 40 80 120 160

0 2,000 4,000 6,000 8,000

Total Cost Reduction ($000s/day)

Total Cost ReductionPeak Quantity Stored

Figure 5.8: Benefits from the availability of energy storage scale roughly with maxi-mum allocation of storage.

84

5.2 Year-long Results with Storage

Following on from the results in section 5.1 comparing average days in each

month using the 2020 scenario conditions detailed earlier, a series of year long models

with energy storage are examined to determine if the effects of storage — leveling

of load and increasing dispatch of cheap and efficient thermal generating units while

avoiding more expensive peaking generators — persist with a full year of dispatch.

These year-long models will facilitate study of the hypothesis based on the results in

figures 5.7 and 5.8 that seasonal storage might be able to provide additional dispatch

improvements and cost reductions over daily arbitrage. The impact of including

round-trip efficiencies, marginal costs and other storage constraints from table 4.3 on

energy storage allocation is examined. The types of storage selected by the model,

and the effect of varying integer limits on discrete energy storage allocation are also

studied with a set of discrete storage selection models.

Because of the size of these models, options available in GAMS and CPLEX

have been leveraged to decrease the solution time and preserve HPC resources for

other users. These options are detailed in appendix A, table A.1. Rolling planning is

also employed, using a technique similar to that suggested by [22] and [43] . As shown

in figure 5.9, each case uses a five-iteration rolling planning horizon. This approach

shortens solution time by solving only a small portion of the problem with the integer

constraints intact (green), relaxing the integer constraints in the portion of the model

not yet studied as a MIP (red), transforming that portion into an easier-to-solve LP.

The portion of the model already studied as a MIP has its integer variables fixed to

the values determined by the MIP solution (blue). This approach means in any given

solution case, the time spent solving the MIP is greatly reduced and the size of the

problem that is not at least partially characterized shrinks with each iteration.

85

5

4

3

2

Iteration 1

Time Step

0 5856 11712 17568 23424 29280 35136

Fixed MIP Relaxed (LP)

Figure 5.9: With a rolling planning solution method, the portion of the model solvedas a full mixed-integer program is limited to a section of the full study length toshorten solution times.

Figure 5.10 confirms the conclusions from figures 5.7 and 5.8 on the effect of

energy storage on economic dispatch decisions. The availability of energy storage in

year-long simulations enable dispatch of the cheapest and most efficient generators

in the fleet, coal and nuclear power facilities. Dispatch of these cheaper but less

flexible generators replaces the use of more expensive and dirty generators during

on-peak hours, particularly Decker 1 and 2 and simple-cycle gas turbines. In addi-

tion to superior utilization of thermal generation, energy storage enables the use of

renewable energy sources during peak hours instead of only the hours when they are

most available. These effects combine to reduce the cost of dispatch by $75 million,

$94 million and $40 million each year for the generic storage, discrete storage and

allocation limited discrete storage models, respectively.

In the comparison in figure 5.7 and in figures 5.12 and 5.13 below, the discrete

energy storage scenarios appears to serve less demand, which is because some of the

86

Limited Discrete

Discrete

Storage

No Storage

Energy Dispatched (MWh)

0.0e+00 3.0e+06 6.0e+06 9.0e+06 1.2e+07 1.5e+07

Nuclear Coal Natural Gas Gas Turbines Renewables

Figure 5.10: As in earlier results, the availability of energy storage improves dispatchof inexpensive generators by shaping renewables availability.

87

traditional thermal generation has been replaced by stored energy returned to the

grid from the CAES facility. The CAES facility modeled here uses natural gas as

a secondary input to the outlet turbines, where the combustion of that natural gas

to preheat the air expanding out of the storage cavern increases the output energy

such that efficiency of the plant appears, on an electricity in versus electricity out

comparison, to be greater than one. This additional electricity from the combustion

of natural gas is the energy displacing other, more expensive facilities.

Each of the figures 5.11, 5.12 and 5.13 show load duration curves adjacent

to histograms that show the total hours of operation for each plotted range of load

levels. Load duration plots show each time step of load, 15 minutes in the case of

these results, sorted from highest load to lowest. The histograms paired with each

figure simply show the number of hours load is served in 50 MW increments in the

total load range. Bars to the right of the histogram show the mean and standard

deviation of the two scenarios to further emphasize the effects of storage. Together,

these figures provide a sense of the way load is distributed throughout the year —

either concentrated tightly around a few hundred megawatts that could be served

by a relatively inflexible fleet of generators optimized for these load levels or ranging

many hundreds of megawatts, requiring a wide range of flexible generating units to

respond to varying levels of demand. Each figure compares a single case for storage

with the baseline without storage case.

Figure 5.11 illustrates the effect of energy storage availability. In this case,

the quantity of storage available was not restricted. If storage is assigned without

regard to cost or efficiency constraints, while it does not affect the average load

level, it reduces the standard deviation of load from 383 MW to 202 MW. If storage

efficiency were included and if it were not for energy additions from natural gas in

88

Hours in a Year

Load

(M

W)

0 1500 3000 4500 6000 7500 9000

010

0020

0030

00

No StorageStorage

0 2000 4000

Load Histogram (h)

plot

int

MeanStandard Deviation

Figure 5.11: Energy storage flattens demand significantly throughout the year, and asshown in the histogram in the right panel, storage thus reduces the number of hours ofpeak generation and the magnitude of peak requirements while also increasing demandduring the lowest few hours of the year. Average load and standard deviation for eachof these cases are summarized in table 5.3.

89

Hours in a Year

Load

(M

W)

0 1500 3000 4500 6000 7500 9000

010

0020

0030

00No StorageDiscrete Storage

0 2000 4000

Load Histogram (h)

plot

int

MeanStandard Deviation

Figure 5.12: With the presence of CAES, the discrete scenario results show not onlya concentration of load levels to be served, as in figure 5.11, but also a small overallreduction in load.

expansion turbines at CAES facilities, load average would increase. Concentrating

load requirements into a narrow operating range allows sustained operation of the

cheapest and most efficient plants while simultaneously maximizing the usefulness of

renewable power generation, as suggested by figure 5.10. This flattening of demand

throughout the year is especially notable at the extremes, where maximum load is

reduced by 291 MW and minimum load increased by 241 MW.

The discrete energy storage case includes the impacts of energy storage and

captured the primary constraints that describe the operation of the selected energy

storage types, yet it showed a similar result to the generic storage case. The presence

90

Hours in a Year

Load

(M

W)

0 1500 3000 4500 6000 7500 9000

010

0020

0030

00No StorageLimited Discrete Storage

0 2000 4000

Load Histogram (h)

plot

int

MeanStandard Deviation

Figure 5.13: With limited storage available, minimal reshaping of demand occurs,using storage to shift only the most expensive hours of the year, maximizing thebenefit of what storage is available.

of energy storage here yields the same narrowing of operating load requirements, but

load is characterized by a lower average, since, as mentioned before, some additional

generation is provided by natural gas combustion during the release of compressed

air from the CAES storage cavern. This comparison also shows increases in minimum

load and concomitant decreases in maximum load compared to the generic storage

scenario. As mentioned before, the use of CAES that returns more electricity to the

grid than is stored depresses both the minimum and maximum values, yielding a

minimum load increase of only 46 MW and a peak decrease of 708 MW.

Since both the generic and discrete storage scenarios allocated significant quan-

91

tities of storage, the integer limits built into the discrete storage model were used to

test the effect of a more limited portfolio of storage, given in table 5.5. This portfolio

was selected based on current high storage capital costs that might encourage utili-

ties to be initially conservative with energy storage deployment. Given the marginal

benefit of additional storage, this portfolio is not conclusively optimal. With minimal

storage available, the distribution of load throughout the year shown in figure 5.13

is not as concentrated as it is for the unlimited1 storage scenarios. While storage

availability is limited, it is still sufficient to address the highest cost hours of the year.

Storage redistributes generation from lower cost periods to reduce dispatch require-

ments during peak hours. The total cost of this shifted generation, when including

storage marginal costs, is significantly lower than that of peaking generators. With

current capital costs, this result indicates that energy storage should be sized to ad-

dress these highest cost hours first. If storage capital costs decrease in the future,

further storage could be justified.

Regardless of the nature of the storage available, the magnitude of peak de-

mand and the number of hours of high demand are reduced while simultaneously

increasing load during the hours of lowest demand, flattening overall demand through-

out the year. With less storage available, as in the limited discrete storage case, this

effect is less pronounced, though still present. This outcome is consistent with our

month-by-month average results, where load was more consistent throughout the day

with storage than without, regardless of the month of interest. Standard deviation

quantifies this flattening of demand and is summarized for all scenarios in table 5.3.

Month-by-month energy storage in the discrete and generic scenarios in figure

1The model case with discrete energy storage is not strictly ‘unlimited,’ as there are integer limitson the total storage permitted for each type, but these limits are quite high. The significance ofthese limits is discussed at the end of section 5.2.

92

Tab

le5.

3:C

ompar

ing

the

effec

tsof

stor

age

avai

labilit

yre

veal

sth

atev

enlim

ited

stor

age

can

man

age

the

hig

hes

tco

sthou

rsof

the

year

,th

ough

larg

equan

titi

esof

seas

onal

stor

age

has

dra

mat

iceff

ects

ondis

pat

chth

rough

out

the

year

.

Sce

nar

ioA

vera

geL

oad

(MW

)Sta

ndar

dD

evia

tion

(MW

)∆

Max

imum

Loa

d(M

W)

∆M

inim

um

Loa

d(M

W)

Alloca

ted

Sto

rage

(MW

h)

Wit

hou

tSto

rage

1,59

638

2Sto

rage

1,59

620

2–2

9124

12,

218,

745

Dis

cret

eSto

rage

1,53

018

1–7

0846

2,35

4,32

1L

imit

edD

iscr

ete

Sto

rage

1,57

830

8–1

082

13,1

50

93

−4000

0

4000

8000

seq(1, 12)

Net

Qua

ntity

Sto

red

per

Mon

th (

MW

h)

Month−by−Month CasesLimited Discrete Storage

J F M A M J J A S O N D

−270000

−135000

0

135000

270000

Net

Qua

ntity

Sto

red

per

Mon

th (

MW

h)

Month−by−Month CasesGeneric StorageDiscrete StorageLimited Discrete Storage

J F M A M J J A S O N D

Figure 5.14: While there is no clear bias towards storage in one period or anotherwhen quantities or model length are limiting factors, when energy storage quantitiesare unlimited, storage is concentrated primarily in the winter and spring months,when stored energy is the cheapest. It is likely that the difference between genericand discrete storage behavior in the final months of the year is a consequence oflimiting constraints in the discrete storage scenario.

94

5.14 show that allocations are similar in all but the final months of the year, which

is a function of constraints present in the discrete storage scenario that ensure only

energy stored is available for withdrawal, whereas the generic storage case is only

required to return to the original state of charge by the end of the year. This means

that in the generic storage scenario, the storage facility can offer “endless” stored

power, so long as that electricity is returned by the end of the year, which is why that

case has such a large spike at the end of the year.

Looking closely at storage allocations in figure 5.14, it is evident that the

dramatic load leveling that appears in the load duration curves of figures 5.11 and

5.12 is achieved through extensive seasonal energy storage. From January through

May, storage is filled and then throughout the summer, June through September,

storage is fully depleted. Peak storage allocations are not dictated by increasing

peak demand levels, as given by the results in section 5.1, but are, as predicted from

those results, seasonal in nature. Seasonal storage, as allocated by the unlimited

storage cases, stores the cheapest power available in the year — inexpensive baseload

generation and plentiful wind power during the cool fall, winter and spring months

when demand is relatively flat — and returns that power to the grid during the highest

price peak demand periods the hot summer months. This storage approach yields cost

savings of almost $100 million every year, at least four times more than the savings

predicted by the daily price arbitrage use of storage suggested by the results in figure

5.8. Totaling the energy storage allocated month after month in the unlimited storage

scenarios, figure 5.14 reveals that the storage required to achieve this dramatic load

leveling and dispatch improvement is quite sizable, as shown in table 5.3, and while

these operational benefits are significant, the cost of such quantities of energy storage

is likely prohibitive.

95

Table 5.4: If possible, large quantities of energy storage will be allocated by themodel, even when operating costs are included.

NaS Battery Vanadium FB PHEVs CAES

Integer Limit 1,000,000 1,000,000 12,000 1,000,000Optimal Portfolio 999,987 999,987 12,000 999,986MWh Available 429,994 9.9e+07 139.2 9.9e+09

Comparing the generation allocated by the discrete storage model, in table 5.4,

to the quantity actually stored, in table 5.3, it appears that the model has allocated

significantly more storage than needed — nearly 1.0e+10 MWh are available but only

2.2e+06 MWh are stored at the peak in May (from figure 5.14). This appears to be

a consequence of incomplete convergence of the discrete storage scenario, caused by

binding resource constraints, as indicated in table 3.1. Based on the solution path

from the solver, it is evident that the integer values for energy storage were initially

set to their limits and progressively reduced as the solution converged. Since the

marginal cost penalties in the objective did not quickly modulate the assignment of

energy storage, all quantities are higher than necessary. Due to the considerable size

of the solution space for the discrete storage scenario, it might be difficult to reach a

converged solution with existing computing resources. It is likely that the quantity

of storage used, given in table 5.3 represents a more realistic measure of the required

portfolio size.

Based on the results from the year long scenarios with storage, it appears that

seasonal storage is favored. Unfortunately, if left unconstrained, the optimal quan-

tity of seasonal storage is prohibitively expensive, as shown in table 5.6. If storage

allocation is limited, the potential savings associated with storage are comparable to

capital costs for those facilities, given that only the most expensive hours of dispatch

96

Table 5.5: With low limits set for all available energy storage types, the optimaloutcome still appears to be the maximum allowable storage.

NaS Battery Vanadium FB PHEVs CAES

Integer Limit 5,000 10 0 1Optimal Portfolio 5,000 10 0 1MWh Available 2,150 1,000 0 10,000

in the year are addressed. Notably, nearly 75% of the $876 million system cost in the

limited scenario comes from electrochemical energy storage. As already discussed,

the use of storage for arbitrage to address only the highest cost hours of the year

provides the greatest marginal cost benefit. The marginal benefit of additional stor-

age is extremely limited, as evidenced by the unlimited storage scenarios that have

many orders of magnitude more storage capacity, and hence, much higher capital and

marginal costs, but only two to three times greater yearly system operational cost

savings. Payback times for these scenarios do not compare favorably either. The

portfolio in the limited storage case requires around 25 years, on the order of the life-

time of a CAES facility, while the larger storage scenarios require hundreds of years

or more, well beyond the expected lifetimes of the equipment purchased.

Appropriate capital cost targets for energy storage are difficult to determine

directly from these results, as they were not included in the optimization. If inte-

ger limited storage cases were run with progressively increasing portfolio sizes, the

marginal benefit of energy storage could be determined. This could be achieved more

efficiently, however, by directly capturing capital costs. Without these data, cost

trends can still be drawn from existing results. In the limited storage allocation sce-

nario, batteries made up about 75% of the capital cost but provided less than 25% of

total capacity, suggesting that costs for batteries will need to decline significantly be-

97

Table 5.6: Comparing capital costs to annual savings for each of the storage scenariossuggests the limited storage portfolio provides the best economic basis for implemen-tation.

ScenarioAllocatedStorage (MWh)

Capital Cost($ million)†

Cost Reduction($ million/year)

Storage 2.2e+06 52,800‡ 75Discrete Storage 1.0e+10 240,000,000 94Limited Storage 13,150 876 40

† Costs estimated based on $/MWh in table 5.1, not combined cost with $/MW‡ Capital cost estimated from portfolio costs from discrete storage case

fore there is a cost basis for their implementation. Additionally, CAES has a definite

economic basis for implementation given its ability to meet a variety of operational

objectives, not the least of which is addressing the highest value added periods of

the year. Comparing the cost of a CAES facility with those of the electrochemical

storage options in table 5.1, it is evident that capital costs for electrochemical storage

must decrease by about an order of magnitude, with expected lifetimes of at least

two decades, before they will be competitive with CAES. Even at those prices, total

available energy storage for a system the size of Austin Energy’s would be limited

to on the order of 10,000 MWh. Further study of CAES-only scenarios would pro-

vide a clearer sense of what the capacity threshold is for CAES implementation in a

system like Austin Energy’s. Additionally, as mentioned previously, capital costs are

probably important to include in future models to develop greater confidence of what

storage should be purchased.

98

5.3 NOx and CO2 Emissions Pricing

In the future, emissions prices might be imposed on large emitters through

carbon taxes or an emissions credit trading program. To examine the effect of energy

storage, the full year generic energy storage model was modified to include emission

rates for all thermal generators in Austin Energy’s fleet, as described in section 4.4.

The generic storage model was selected as the base for these studies because it was

more likely to reach an optimal solution before reaching imposed computational limits.

Emissions penalties were added directly to the objective function. The baseline case

with energy storage is compared against scenarios with increasing emissions prices

to observe how energy storage allocation changes with increasing prices. Since the

emissions models were based on the generic storage selection structure, marginal costs

associated with storage are not included.

Where energy storage is made available, it helps to transform renewable gen-

eration into a dispatchable resource while providing flexibility in the system to enable

greater dispatch of cheaper but less flexible generating units. Initially, as emissions

prices are imposed, dispatch remains unchanged, as emissions penalties are insuf-

ficient to promote more expensive plants over cheaper but dirtier coal generation.

Eventually, once prices rise past some threshold, dispatch changes to favor more ex-

pensive but cleaner natural gas generation. In Austin Energy’s fleet, these natural

gas facilities are also more flexible than the coal units, meaning less energy storage is

needed to provide the same level of overall system flexibility.

Initially, it might seem obvious that as emissions prices increase, energy stor-

age allocations would increase to improve renewables availability and dispatch of low

emission plants, but we do not, in fact, observe such trends. This is likely a con-

sequence of ignoring storage capital costs for the scenarios in figures 5.15 and 5.16.

99

0 30 50 70 90

CO2 Price ($/ton)

0.0e+00

2.0e+06

4.0e+06

6.0e+06

8.0e+06

1.0e+07

1.2e+07

1.4e+07

Ene

rgy

Dis

patc

hed

(MW

h)

0

1

2

Nor

mal

ized

Sto

rage

Nuclear Coal Natural Gas Gas Turbines Renewables Storage

Figure 5.15: As CO2 prices increase, dispatch changes to use natural gas generatorsinstead of coal power plants. Since natural gas facilities are much more flexible intheir operation, less storage is required to achieve the same level of system flexibility.

100

0 10,000 30,000 50,000 70,000 90,000

NOx Price ($/ton)

0.0e+00

2.0e+06

4.0e+06

6.0e+06

8.0e+06

1.0e+07

1.2e+07

1.4e+07

Ene

rgy

Dis

patc

hed

(MW

h)

0

1

2

Nor

mal

ized

Sto

rage

Nuclear Coal Natural Gas Gas Turbines Renewables Storage

Figure 5.16: Similar to CO2 prices, as NOx prices increase, dispatch shifts towardincreased use of natural gas generators, while storage changes to provide neededsystem resilience.

101

In all scenarios, storage is allocated according to the objective of operational cost

minimization, which fails to capture the diminishing marginal benefit of storage. If

capital costs were included, the storage allocation without emissions prices would be

reduced dramatically, as discussed previously. When emissions prices are imposed,

and thus the cost of operation is increased, capital costs associated with additional

storage would be justified. The transition to more expensive natural gas generation

would likely occur at lower emissions prices as well. Since storage would be more

expensive and thus less available, the amount of high-emissions coal generation that

could be offset by renewable sources would be reduced, raising the price of dispatch

higher than in the no-cost storage scenarios in figures 5.15 and 5.16. Alternately,

comparing these results with those where emissions prices are imposed and storage is

not available could provide dispatch costs between cases, which might be a meaning-

ful point of comparison. As discussed in section 5.2, including non-linear emissions

rates might also reveal slightly different trends by creating larger penalties for op-

erating outside the plant’s most efficient range. This could change the allocation

of energy storage, particularly in conjunction with the inclusion of capital costs, as

energy storage can help ensure that plants operate at their most efficient throughout

the day. Unfortunately, the computational expense of including non-linear emissions

would likely be significant.

102

Chapter 6

Conclusion

In the United states, through the implementation of state renewable portfolio

standards, as well as federal production and investment tax credits, the installed base

of renewable sources of electric power is growing rapidly. While this growth provides

significant environmental benefits, the predictability and availability of these resources

is limited, particularly in wind energy, thus requiring many gas turbine generators to

provide support for when wind is unexpectedly unavailable. Since many states have

set aggressive RPS goals and in some regions, much of that renewable energy will

come from wind turbines, addressing wind variability and availability is of increasing

importance.

This study has examined the use of energy storage to address the challenge

posed by the availability and variability of wind and other renewable resources. Grid-

scale energy storage is one of several possible approaches to manage variability and

improve availability of renewables, but it is not often considered a suitable candidate.

This is a consequence of its capital cost, though alternatives, apart from the con-

struction of many single-cycle gas turbines to provide backup generation, are often

also expensive. Few studies have closely examined the role energy storage can have

in managing variable renewables or improving dispatch through price arbitrage and

thus, it is possible that in future operating scenarios, storage might be able to add

value beyond that anticipated or assumed by other authors.

To study the value of energy storage in such a future operating scenario, a unit

103

commitment model was developed and implemented based on the thermal generating

fleet and future renewable expansion plans for Austin Energy. The city of Austin

was selected as a study area because the local utility, Austin Energy, has announced

ambitious goals for expanding renewable energy generation in their portfolio. By

2020, 30% of total generation will be from renewables and two-thirds of the 900

MW of renewable generation needed to meet this target will be from wind power.

Additionally, the state of Texas has invested heavily in transmission infrastructure

improvements that will facilitate future wind power development.

Unit commitment methods are well-suited to the study of thermal generators

with realistic operating constraints and have been used for modeling these and similar

systems for decades. Because these systems can be described by a series of equations,

they can easily become inputs for a computer program that can quickly provide

optimal unit commitment and economic dispatch decisions for any study period and

time interval length. Further, such an arrangement can enable convenient modeling

of a variety of time intervals to explore various operational effects in the system, such

as ancillary service markets or price arbitrage.

The unit commitment model presented here was implemented in GAMS as a

mixed-integer program, which is characterized by linear equations where some of the

variables are limited to integer or binary values. This problem formulation is harder to

solve than an ordinary linear program, but without some binary variables, it is difficult

to capture all thermal generator operating constraints, particularly those related to

startup and shutdown. A MIP formulation also enables accurate representation of

constraints that limit the operation of energy storage devices. Using this approach,

a model is developed that yields results facilitating analysis of the potential role of

energy storage for any coherent fleet of generators of any size such that storage for

104

ancillary services or arbitrage can be studied, depending on the time interval length

selected.

A variety of cases that begin to characterize energy storage and it’s poten-

tial influence in economic dispatch are selected here. The model’s commitment and

dispatch decisions have been compared against Austin Energy’s dispatch and veri-

fied that the model structure provides decisions comparable to those made by Austin

Energy when participating in ERCOT’s electricity market. Given that models with

millions of non-zero variables require excessive computational resources, initial cases

are monthly average studies, intended to reveal trends in storage allocation that might

be meaningful or support specific further study in year-long models. Energy storage

was found to store almost entirely renewable energy, firming and shaping those re-

sources so they can be available when they are needed most and not just when the

resource is available. Energy storage also significantly improves the utilization of

existing thermal generators, reducing the need to run expensive units like Decker,

engage in PPAs to avoid Decker or run inefficient and dirty peaking gas turbines.

Examining storage trends across the months in the study suggest that seasonal en-

ergy storage might make sense, as there exists underutilized baseload capacity and

renewable generation during the winter months. This possible benefit is studied using

year-long scenarios.

Subsequently, generic energy storage and discrete storage selection were run

to examine how dispatch could change with a similar model over a year-long study

period. It was revealed that energy storage provides similar benefits to those sug-

gested by the 24-hour models, improving the use of renewables by converting them

into dispatchable resources available on-peak, increasing the utilization of inexpen-

sive, efficient baseload generators and reducing the use of single-cycle gas turbines and

105

older, more inefficient generators. These changes yield, over the study period, a sig-

nificant flattening of load requirements, dramatically reducing the standard deviation

of load, reducing the magnitude of peak demand and the number of extremely high

demand hours. This flattening of load is achieved, as postulated from the results of

the monthly average 24-hour models, through extensive seasonal storage, where inex-

pensive renewable and baseload generation is stored during the winter months when

demand is low and relatively flat and then returned to the grid during the highest

price peak hours during the summer months. Unfortunately, achieving these results

requires large quantities of seasonal storage, yielding capital costs many orders of

magnitude larger than the dispatch improvement provided. Further, possible losses

from seasonal storage were not addressed here and could be a significant problem,

particularly with compressed gas storage in geologic formations. Using the cost basis

presented in the 24-hour model, daily arbitrage during summer months can provide

sufficient dispatch improvement to justify the cost of a single CAES facility, which

would be sufficiently large to serve that storage requirement. That facility could po-

tentially also provide ancillary services, if permitted in ERCOT market rules, improv-

ing profitability. This result suggests that the marginal benefit of increased storage

for price arbitrage diminishes rapidly once the highest cost hours during the sum-

mer months are managed with storage. The quantity of storage required to perform

this limited function, however, would likely provide significant firming and shaping

of renewable resources and improve system reliability.

This conclusion is consistent with results from the limited storage scenario,

where 75% of total storage capacity but only 25% of the cost is from the single

CAES facility permitted in the model. With the understanding that the marginal

value of additional storage decreases rapidly, if costs can be reduced by 75% while

retaining most of the storage capacity, this result would be superior to the model’s

106

“optimal” result. Additionally, given that the marginal benefit of increased storage

declines rapidly, there exist few, if any periods that are sufficiently expensive to

justify the cost associated with electrochemical storage options. This conclusion is

contingent on storage capital costs remaining constant in the future. Capital costs for

electrochemical storage could, however, drop dramatically in the coming years. Since

capital costs are not captured in the model, these conclusions are not revealed directly.

In the future, developing models that capture both the capital and operational cost

impacts of energy storage might provide a clearer picture of the cost benefits, optimal

quantities and preferred types of storage.

In scenarios that included emissions prices, energy storage did not appear to

provide significant operational benefit. As prices increased, storage allocations largely

decreased, corresponding to increases in natural gas generator dispatch. Increased

dispatch of natural gas generation and correlated decreases in coal generation dispatch

yielded an increase in system flexibility, since natural gas generators are more capable

of ramping throughout the day without the help of energy storage. As a result,

storage added less value and became useful only in reallocating renewables to high

priced periods when peaking generation might otherwise be required. Further study

of emissions price scenarios would help determine if changes in dispatch would still

occur if storage were not available and enable comparison of operational costs between

scenarios with and without storage. These studies would also help to characterize the

cost savings realized at various emissions price points that could help further justify

the availability of energy storage.

Examining the trends from the results of all the scenarios presented here, it

appears that if attractive financing is available, between 10,000 and 20,000 MWh of

compressed air energy storage or other similarly priced and equally capable storage

107

technologies can improve renewable energy capacity factors and reduce peak gen-

eration requirements. Such a CAES facility would reduce yearly operational costs

dramatically for a system like Austin Energy’s, even without emissions prices. If

market rules do not prohibit the use of energy storage for ancillary service provision

and some small quantity of electrochemical energy storage is included as part of the

CAES facility development, energy storage can provide low marginal cost ancillary

services and participate in high value market arbitrage. If storage prices are reduced

by several orders of magnitude, energy storage could be expanded to provide seasonal

storage, favored by models that did not restrict energy storage allocation or capture

facility costs. Seasonal storage would enable the capture of large quantities of re-

newables during the winter months when they are most available and further flatten

apparent demand, improving the utilization of the lowest cost thermal generating

facilities.

From these results, analysis that captures capital costs of energy storage would

improve portfolio selection decisions in the discrete storage scenarios. Quantification

of the potential benefit of stochastic modeling of wind generation and demand to verify

results from the literature could prove useful. To accommodate stochastic modeling

and other changes to create more complete characterization of storage costs, simplifi-

cation of the MIP model structure should be explored. Finally, more complete study

of emissions pricing scenarios and how energy storage allocations change with vary-

ing emissions prices would yield a clearer indication of what emission price thresholds

motivate energy storage purchases. With existing results, it is evident that at current

capital costs, CAES is the only energy storage type studied here that can transform

renewable generation into a dispatchable resource and provide cost-competitive an-

cillary services with an acceptable payback period. With the methodology developed

here, future analysis might clarify optimal energy storage portfolios and help further

108

define performance requirements for storage.

109

Appendix A

Options and Runtimes for Each Scenario

All the results presented in chapter 5 were solutions to models run using the

optimization software GAMS with the solver CPLEX. GAMS facilitates the definition

of a variety of options that define how the program and solver will work toward a

solution. Several of these options were leveraged for the larger models that required

significant computing resources and time in an effort to minimize or manage those

requirements. The table also shows the solution time required for each model, where

the larger models required significantly longer and highly variable times.

In addition to the parameters shown in table A.1, options nodefileind and

workmem were set to 3 and 8192 megabytes, respectively, to ensure that never more

than one-fourth of total memory on an HPC was used by the model and that when

the working memory limit was reached, saved data would be compressed and written

to the hard drive. This approach increases solution time but ensures HPC resources

are available for other users. The 2020 monthly average cases presented in section 5.1

were run locally and did not require the use of these or any other non-default options.

Additionally, the full-year model with storage was run with a 1024 megabyte memory

limit and default solution data memory management, which retains all data in a

compressed format in the computer’s physical memory.

110

Tab

leA

.1:

Par

amet

ers

and

opti

ons

applied

for

each

model

run

can

affec

tru

nti

mes

and

syst

emre

sourc

em

anag

emen

t,w

her

efu

llye

ar(F

Y)

model

sty

pic

ally

requir

edsi

gnifi

cantl

ylo

nge

rru

nti

mes

,ev

enw

hen

exec

ute

don

the

HP

Ccl

ust

er.

Model

Cas

eSol

uti

onT

ime

Rol

ling

Pla

nnin

g?N

on-z

eroes

Iter

atio

ns

Opti

mal

ity

Cri

teri

on(%

)T

ime

Lim

it(s

)It

erat

ion

Lim

it

2020

Mon

ths

3m�

No

29,1

5315

00�

0.1

1000

2,00

0,00

0

2008

w/o

Sto

rage

,F

Y†

unk.

Yes

nz

iter

0.00

177

7,60

01,

000,

000,

000

2020

w/o

Sto

rage

,F

Y†

51h,

49m

Yes

10,7

16,3

3132

8,59

00.

001

777,

600

1,00

0,00

0,00

0

2020

w/

Sto

rage

,F

Y‡

8h,

12m

No

11,5

94,7

1990

0,85

00.

0001

777,

600

1,00

0,00

0,00

0

2020

w/

Dis

cret

e,F

Y†

98h,

16m

No

13,7

02,8

832,

207,

528

0.00

1*25

9,20

01,

000,

000,

000

2020

w/

Lim

ited

,F

Y†

4h21

mN

o13

,702

,883

1,76

3,05

10.

0135

0,00

01,

000,

000,

000

2020

w/

Em

issi

ons,

FY†

72h–2

17h

No

11,8

40,6

711,

100,

000–

3,50

0,00

0*0.

001

777,

600

1,00

0,00

0,00

0

†T

his

case

was

run

wit

hG

AM

S/C

PL

EX

op

tion

sn

odefi

lein

dat

3an

dw

ork

mem

of

8192

meg

abyte

s.‡

Th

isca

sew

asru

nw

ith

work

mem

of10

24

meg

abyte

s.*

Did

not

full

yco

nver

ged

ue

tore

sou

rce

lim

its.

�A

pp

roxim

ate

valu

es

111

Bibliography

[1] K. Forsten, R. Lordan, and N. Jones, “Green Transmission Efficiency Initiative:

Series of Regional Workshops,” 2009.

[2] DOE, “Bottling Electricity: Storage as a Strategic Tool for Managing Variability

and Capacity Concerns in the Modern Grid,” 2008.

[3] “Resource Guide: Planning for Austin’s Future Energy Resources.” http://

www.austinsmartenergy.com/downloads/AustinEnergyResourceGuide.pdf, Apr.

2008.

[4] Department of Energy, “President Obama Announces $3.4 Billion Investment to

Spur Transition to Smart Grid.” http://www.energy.gov/news2009/8216.htm,

2009.

[5] DOE, “The Smart Grid: An Introduction.” http://www.oe.energy.gov/

DocumentsandMedia/DOE\ SG\ Book\ Single\ Pages(1).pdf, 2008.

[6] Alternative Energy Institute, “windenergy.org - Maps.” http://www.

windenergy.org/maps/images/sites.jpg, 2009.

[7] P. Denholm and R. Sioshansi, “The value of compressed air energy storage with

wind in transmission-constrained electric power systems,” Energy Policy, vol. 37,

no. 8, pp. 3149–3158, 2009.

[8] Electric Reliability Council of Texas, “EECP and Pre-EECP Communica-

tions.” http://www.ercot.com/content/news/presentations/2007/EECP and

Pre-EECP Communications.pdf, 2007.

112

[9] Electric Reliability Council of Texas, “ERCOT Operations Report on the EECP

Event of Feburary 26, 2008.” http://www.ercot.com/meetings/ros/keydocs/

2008/0313/07. ERCOT OPERATIONS REPORT EECP022608 public.doc,

2008.

[10] Austin Energy, “Austin Energy Smart Grid Program.” http://www.

austinenergy.com/About\%20Us/Company\%20Profile/smartGrid/index.htm,

2009.

[11] Reuters, “Austin Energy Launches One of the First Smart Grid Deployments

in the Nation.” http://www.reuters.com/article/pressRelease/idUS140319+23-

Sep-2008+BW20080923, 2008.

[12] Lower Colorado River Authority, “LCRA and CREZ.” http://www.lcra.org/

energy/trans/crez/index.html, 2010.

[13] K. Belyeu, “Annual Wind Industry Report Reveals Strong Growth,” 2008.

[14] N. Desai, S. Gonzales, et al., “The Economic Impact of CAES on Wind in TX,

OK, and NM,” 2005.

[15] C. Parker, “Leadacid battery energy-storage systems for electricity supply net-

works,” Journal of Power Sources, vol. 100, pp. 18–28, Nov. 2001.

[16] C. Rydh and B. Sanden, “Energy analysis of batteries in photovoltaic systems.

Part I: Performance and energy requirements,” Energy Conversion and Manage-

ment, vol. 46, no. 11-12, pp. 1957–1979, 2005.

[17] EPRI, “Handbook of Energy Storage for Transmission or Distribution Applica-

tions,” 2002.

113

[18] EPRI, “Energy Storage for Grid Connected Wind Generation Applications,”

2007.

[19] EPRI, “EPRI-DOE Handbook of Energy Storage for Transmission and Distri-

bution Applications,” 2003.

[20] L. Goransson and F. Johnsson, “Dispatch modeling of a regional power genera-

tion system Integrating wind power,” Renewable Energy, vol. 34, pp. 1040–1049,

Apr. 2009.

[21] H. Sharman and H. Meyer, “Wind Energy: The Case of Den-

mark.” http://www.cepos.dk/fileadmin/user\ upload/Arkiv/PDF/Wind\

energy\ -\ the\ case\ of\ Denmark.pdf, 2009.

[22] A. Tuohy, P. Meibom, et al., “Unit Commitment for Systems With Significant

Wind Penetration,” IEEE Transactions on Power Systems, vol. 24, pp. 592–601,

May 2009.

[23] E. Denny and M. O’Malley, “Quantifying the Total Net Benefits of Grid Inte-

grated Wind,” IEEE Transactions on Power Systems, vol. 22, pp. 605–615, May

2007.

[24] J. Muckstadt and S. Koenig, “An Application of Lagrangian Relaxation to

Scheduling in Power-Generation Systems,” Operations Research, vol. 25, no. 3,

pp. 387–403, 1977.

[25] N. P. Padhy, “Unit commitment-a bibliographical survey,” IEEE Transactions

on Power Systems, vol. 19, no. 2, pp. 1196–1205, 2004.

[26] R. Baldick, “The generalized unit commitment problem,” IEEE Transactions on

Power Systems, vol. 10, no. 1, pp. 465–475, 1995.

114

[27] B. F. Hobbs, M. H. Rothkopf, et al., The Next Generation of Electric Power

Unit Commitment Models. Norwell, Massachusetts: Springer, 1st ed., 2001.

[28] R. Sioshansi and P. Denholm, “Emissions impacts and benefits of plug-in hybrid

electric vehicles and vehicle-to-grid services.,” Environmental Science & Tech-

nology, vol. 43, pp. 1199–204, Feb. 2009.

[29] S. Peterson, J. Apt, and J. Whitacre, “Lithium-Ion Battery Cell Degradation

Resulting from Realistic Vehicle and Vehicle-to-Grid Utilization.” 2009.

[30] S. B. Peterson, J. Whitacre, and J. Apt, “The economics of using plug-in hy-

brid electric vehicle battery packs for grid storage,” Journal of Power Sources,

vol. 195, no. 8, pp. 2377–2384, 2010.

[31] S. Shahidehpour and C. Wang, “Effects of Ramp-Rate Limits on Unit Commit-

ment and Economic Dispatch,” IEEE Transactions on Power Systems, vol. 8,

no. 3, pp. 1341–1350, 1993.

[32] E. Finardi and E. DaSilva, “Solving the Hydro Unit Commitment Problem via

Dual Decomposition and Sequential Quadratic Programming,” IEEE Transac-

tions on Power Systems, vol. 21, pp. 835–844, May 2006.

[33] D. P. Bertsekas, Constrained Optimization and Lagrange Multiplier Methods.

Belmont, MA: Athena Scientific, 1 ed., 1996.

[34] J. F. Bard, “Short-term Scheduling of Thermal-electric Generators Using La-

grangian Relaxation,” Operations Research, vol. 36, no. 5, pp. 756–766, 1988.

[35] F. Zhuang and F. D. Galiana, “Towards a more rigorous and practical unit

commitment by Lagrangian relaxation,” IEEE Transactions on Power Systems,

vol. 3, no. 2, pp. 763–773, 1988.

115

[36] J. J. Shaw, R. F. Gendron, and D. P. Bertsekas, “Optimal Scheduling of Large

Hydrothermal Power Systems,” IEEE Transactions on Power Apparatus and

Systems, vol. 104, no. 2, pp. 286–294, 1985.

[37] S. Cerisola, A. Baillo, et al., “Stochastic Power Generation Unit Commitment in

Electricity Markets: A Novel Formulation and a Comparison of Solution Meth-

ods,” Operations Research, vol. 57, no. 1, pp. 32–46, 2009.

[38] D. Watkins, D. McKinney, et al., “A scenario-based stochastic programming

model for water supplies from the highland lakes,” International Transactions in

Operational Research, vol. 7, pp. 211–230, May 2000.

[39] J. Linderoth, “Multistage Stochastic Programming,” 2003.

[40] D. R. Kracman, D. C. McKinney, et al., “Stochastic Optimization of the High-

land Lakes System in Texas,” Journal of Water Resources Planning and Man-

agement, vol. 132, no. 2, p. 62, 2006.

[41] G. Pflug, “Scenario tree generation for multiperiod financial optimization by

optimal discretization,” Mathematical Programming, vol. 89, pp. 251–271, Jan.

2001.

[42] S. Takriti, J. Birge, and E. Long, “A stochastic model for the unit commitment

problem,” IEEE Transactions on Power Systems, vol. 11, no. 3, pp. 1497–1508,

1996.

[43] R. Barth, H. Brand, et al., “A Stochastic Unit-commitment Model for the Eval-

uation of the Impacts of Integration of Large Amounts of Intermittent Wind

Power,” in 2006 International Conference on Probabilistic Methods Applied to

Power Systems, pp. 1–8, IEEE, June 2006.

116

[44] V. S. Pappala, I. Erlich, et al., “A Stochastic Model for the Optimal Operation of

a Wind-Thermal Power System,” IEEE Transactions on Power Systems, vol. 24,

pp. 940–950, May 2009.

[45] J. Barton and D. Infield, “Energy Storage and Its Use With Intermittent Renew-

able Energy,” IEEE Transactions on Energy Conversion, vol. 19, pp. 441–448,

June 2004.

[46] H. Lund, G. Salgi, et al., “Optimal operation strategies of compressed air energy

storage (CAES) on electricity spot markets with fluctuating prices,” Applied

Thermal Engineering, vol. 29, no. 5-6, pp. 799–806, 2009.

[47] R. Walawalkar, J. Apt, and R. Mancini, “Economics of electric energy storage for

energy arbitrage and regulation in New York,” Energy Policy, vol. 35, pp. 2558–

2568, Apr. 2007.

[48] R. Sioshansi, P. Denholm, et al., “Estimating the value of electricity storage in

PJM: Arbitrage and some welfare effects,” Energy Economics, vol. 31, no. 2,

pp. 269–277, 2009.

[49] R. Dufo-Lopez, J. Bernal-Agustin, and J. Dominguez-Navarro, “Generation man-

agement using batteries in wind farms: Economical and technical analysis for

Spain,” Energy Policy, vol. 37, no. 1, pp. 126–139, 2009.

[50] J. B. Greenblatt, S. Succar, et al., “Baseload wind energy: modeling the compe-

tition between gas turbines and compressed air energy storage for supplemental

generation,” Energy Policy, vol. 35, no. 3, pp. 1474–1492, 2007.

[51] R Development Core Team, R: A Language and Environment for Statistical Com-

puting. R Foundation for Statistical Computing, Vienna, Austria, 2009. ISBN

117

3-900051-07-0.

[52] J. Batut and A. Renaud, “Daily Generation Scheduling Optimization with Trans-

mission Constraints: A New Class of Algorithms,” IEEE Transactions on Power

Systems, vol. 7, no. 3, pp. 982–989, 1992.

[53] S. Ruzic and N. Rajakovic, “A New Approach for Solving Extended Unit Com-

mitment Problem,” IEEE Transactions on Power Systems, vol. 6, no. 1, 1991.

[54] J. J. Shaw, “A Direct Method for Security-Constrained Unit Commitment,”

IEEE Transactions on Power Systems, vol. 10, no. 3, 1995.

[55] S. Takriti, B. Krasenbrink, and L. S.-Y. Wu, “Incorporating fuel constraints and

electricity spot prices into the stochastic unit commitment problem,” Operations

Research, vol. 48, no. 2, pp. 268–280, 2000.

[56] I. Borg and C. Briggs, “U.S. Energy Flow–1988.” https://publicaffairs.llnl.

gov/news/energy/content/energy/energy\ archive/US\ energy\ flow\ archive/

UCID-19227-88.pdf, 1989.

[57] Energy Information Administration, “U.S. Natural Gas Prices.” http://tonto.

eia.doe.gov/dnav/ng/ng pri sum dcu nus m.htm, 2010.

[58] Energy Information Administration, “EIA - Average Price of Coal by State and

Mine Type.” http://www.eia.doe.gov/cneaf/coal/page/acr/table28.html, 2010.

[59] M. C. Lott, C. W. King, and M. E. Webber, “Analyzing Tradeoffs in Electric-

ity Choices Using the Texas Interactive Power Simulator (TIPS),” in 3rd In-

ternational Conference on Energy Sustainability, (Phoenix), pp. 1–9, American

Society of Mechanical Engineers, 2009.

118

[60] Environmental Protection Agency, “eGRID: Clean Energy: US EPA.” http://

www.epa.gov/cleanenergy/energy-resources/egrid/index.html, 2007.

[61] Environmental Protection Agency, “Clean Air Markets — Data and Maps.”

http://camddataandmaps.epa.gov/gdm/index.cfm?fuseaction=emissions.

wizard, 2008.

[62] National Renewable Energy Laboratory, “NSRDB: 1991-2005 Update.” http:

//rredc.nrel.gov/solar/old data/nsrdb/1991-2005/, 2005.

[63] T. Markel, K. Smith, and A. Pesaran, “PHEV Energy Storage Perfor-

mance/Life/Cost Trade-off Analysis,” 2008.

119

Vita

Chioke Harris was born in Seattle, Washington. He graduated from Lakeside

School, Seattle, Washington in 2004 and matriculated at Brown University in Prov-

idence, Rhode Island. During his years as an undergraduate student, he worked as

an engineering intern on a satellite launch program, airplane landing gear systems

and power and propulsion subsystems for the Space Shuttle at The Boeing Company

in Seattle, Washington and Houston, Texas. He received the degree of Bachelor of

Science with a concentration in Mechanical Engineering from Brown University in

May 2008. In fall 2008, he entered the Graduate School at The University of Texas

at Austin.

Permanent address: P.O. Box 49651Austin, Texas 78765

This thesis was typeset with LATEX† by the author.

†LATEX is a document preparation system developed by Leslie Lamport as a special version ofDonald Knuth’s TEX Program.

120


Top Related